Environmental Permit No. EP-515/2017

環境許可證編號  EP-515/2017

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Section 10

 

環境影響評估條例

(第499章)

10

 

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE

A DESIGNATED PROJECT

 

建造及營辦指定工程項目的環境許可證

 

PART A (MAIN PERMIT)

A許可證主要部分

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to Glory Queen Limited (hereinafter referred to as the "Permit Holder") to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:

根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予 鈞 有 限 公 司(下稱 許可證持有人以建造及營辦B所說明的指定工程項目,但須遵守C所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:

 

Application No.

申請書編號

AEP-515/2016

Document in the Register :

登記冊上的文件:

 

1.           Proposed Low-rise and Low-density Residential Development at Various Lots and their Adjoining Government Land in D.D. 104, East of Kam Pok Road, Mai Po, Yuen Long, N.T.

 

-          Environmental Impact Assessment Report

-          Environmental Impact Assessment Study Executive Summary

-          Environmental Monitoring and Audit Manual

 

Hereinafter referred to as the “EIA Report”

(Register No.: AEIAR-205/2017)

 

新界元朗米路以東丈量約份第104約多個地段和鄰近政府土地的低層數和低密度住宅發展項目

 

-          環境影響評估報告

-          環境影響評估行政摘要

-          環境監察及審核手冊

 

下稱 環評報告

登記編號 : AEIAR-205/2017

Document in the Register :

登記冊上的文件:

 

2.           The Director’s letter of approval of the EIA Report dated 10 January  2017

(Ref.: (28) in Ax (2) to EP2/N6/P/127 Pt.4)

 

環境保護署長於2017110發出批准環評報告的信件

檔案編號 : (28) in Ax(2) to EP2/N6/P/127 Pt.4

 

3.           Application for Environmental Permit submitted by the Permit Holder on 24 June 2016

(Application No.: AEP-515/2016)

 

許可證持有人於2016624提交的環境許可證申請

申請書編號:AEP-515/2016

 

 

 

 

 

 

 

 

11 January 2017

 

 

Date

日期

 

( C.F. WONG )

Principal Environmental Protection Officer

(Strategic Assessment)

for Director of Environmental Protection

環境保護署長

首席環境保護主任策略評估黃傳輝代行


PART B (DESCRIPTION OF DESIGNATED PROJECT)

B 指定工程項目的說明

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as “the Permit”):

下列為本環境許可證下稱許可證”)A所提述的指定工程項目的說明:

 

Title of Designated Project

 

指定工程項目的名稱

 

Proposed Low-rise and Low-density Residential Development at Various Lots and their Adjoining Government Land in D.D. 104, East of Kam Pok Road, Mai Po, Yuen Long, N.T.

(This designated project is hereinafter referred to as “the Project”)

 

新界元朗米路以東丈量約份第104約多個地段和鄰近政府土地的低層數和低密度住宅發展項目

(本指定工程項目下稱“工程項目”)

 

Nature of Designated Project

 

指定工程項目的性質

 

A residential development within Deep Bay Buffer Zone 2

 

海灣2號緩衝區內的住宅發展

 

Location of Designated Project

 

指定工程項目的地點

 

 

Mai Po, Yuen Long, N.T.

新界元朗米

 

The location of the Project is shown in Figure 1 of this Permit

工程項目的地點展示於本許可證圖1

 

Scale and Scope of Designated Project

 

指定工程項目的規模和範圍

The Project is to construct and operate a residential development at DD104 Yuen Long, N.T.

 

工程項目為在新界元朗丈量約份第104約內營辦住宅

 

 


PART C (PERMIT CONDITIONS)

 

1.    General Conditions

 

1.1               The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap.499) and may become the subject of appropriate action being taken under the Ordinance.

 

1.2               The Permit Holder shall ensure full compliance with all legislation from time to time in force including, without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Waste Disposal Ordinance (Cap. 354) and Dumping at Sea Ordinance (Cap. 466). This Permit does not of itself constitute any ground of defense against any proceedings instituted under any legislation or imply any approval under any legislation.

 

1.3               The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

 

1.4               The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.

 

1.5               The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public’s information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended Permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6               The Permit Holder shall construct and operate the Project in accordance with the project description in Part B of this Permit.

 

1.7               The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and recommendations described in the approved EIA Report (Register No. AEIAR-205/2017), the application for Environmental Permit (Application No. AEP-515/2016) and other relevant documents in the Register, the information and mitigation measures described in this Permit, mitigation measures to be recommended in the submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on-going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

 

1.8               All deposited submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise specified by the Director.

 

1.9               All submissions approved by the Director, all submissions deposited without comments by the Director, and all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap.499). All submissions or any variation of the submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below before submitting to the Director under this Permit.

 

1.10            The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11            All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

 

1.12            The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than one month prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of construction.

 

1.13           For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation or other works as agreed by the Director. 

 

 

2.               Submissions or Measures to be Implemented before Construction of the Project

 

Employment of Environmental Monitoring and Audit (EM&A) Personnel

 

2.1        An Environmental Team (ET) shall be established by the Permit Holder no later than one month before commencement of construction of the Project. The ET shall not be in any way an associated body of the Contractor or the Independent Environmental Checker (IEC) for the Project. The ET shall be headed by an ET Leader. The ET Leader shall be a person who has at least 7 years of experience in environmental monitoring and auditing (EM&A) or environmental management. The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual of the Project. The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances, which may affect the compliance with the recommendations of the EIA Report (Register No. AEIAR-205/2017) and this Permit.  The ET Leader shall notify the IEC within one working day of the occurrence of any such instance or circumstance or change of circumstances. The ET Leader’s log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the recommendations of the EIA Report (Register No. AEIAR-205/2017) and this Permit or by the Director or his authorized officers. Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader. Failure by the Permit Holder to make replacement or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.

 

2.2        An IEC shall be employed by the Permit Holder no later than one month before commencement of construction of the Project. The IEC shall not be in any way an associated body of the Contractor or the ET for the Project. The IEC shall be a person who has at least 7 years of experience in EM&A or environmental management. The IEC shall be responsible for duties defined in the EM&A Manual, and shall audit the overall EM&A performance, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit. The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by fax or email, within one working day of receipt of notification from the ET Leader of each and every occurrence, change of circumstances or non-compliance with the EIA Report (Register No. AEIAR-205/2017) and this Permit, which may affect the monitoring or control of adverse environmental impacts from the Project. In the case where the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined in the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation. Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition.

 

Management Organization of Main Construction Companies

 

2.3        The Permit Holder shall, no later than one month before the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project. The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

 

            Submission of Detailed Drainage Plan

 

2.4       The Permit Holder shall devise a detailed drainage plan to ensure no uncontrolled surface discharge into the Ngau Tam Mei Drainage Channel (NTMDC) particularly during the construction stage of the Project, and to submit the plan to the Director for approval at least one month before commencement of construction.

           

Submission of Noise Mitigation Plan

 

2.5       The Permit Holder shall prepare a Noise Mitigation Plan for submission to the Director for approval at least one month before commencement of construction of the Project.

 

Submission of Landscape and Visual Implementation Plan

 

2.6       The Permit Holder shall prepare a Landscape and Visual Implementation Plan for submission to the Director for approval at least one month before commencement of construction of the Project.

 

 

3.         Measures to Mitigate Environmental Impacts during Construction of the Project

           

    Control of Water Pollution due to Site Runoff

 

3.1        To control water pollution due to site runoff, the Permit Holder shall implement and maintain the construction stage measures recommended in the detailed drainage plan approved under Condition 2.4.


Measures to Mitigate Noise Impacts

 

3.2        The Permit Holder shall implement and maintain the construction stage measures recommended in the Noise Mitigation Plan approved under Condition 2.5

 

Measures to Mitigate Ecological Impacts

 

3.3       The Permit Holder shall implement the following measures,

 

(a)    the installation of site hoarding shall not be carried out during peak winter bird season between October and March

 

(b)    with reference to Condition 2.5 and Condition 3.2, if noise barriers are  installed, they shall be opaque, non-reflective and with colour scheme to blend in with the environment.

 

Measures to Mitigate Visual and Landscape Impacts

 

3.4        The Permit Holder shall implement and maintain the construction stage measures recommended in the Landscape and Visual Implementation Plan approved under Condition 2.6.

 

 

4.    Submissions or Measures to Mitigate Environmental Impacts during Operation of the Project

 

            Submission of Detailed Operation and Emergency Response Plan for the Interim Sewage Treatment Plant (STP)

 

4.1        The Permit Holder shall devise a detailed operation and emergency response plan for the interim STP to ensure no net increase in pollution load to the Deep Bay, including ensuring sufficient annual quantity of water extraction from NTMDC for treatment to offset the pollution loads of the effluent arising from the development, and the emergency arrangements during possible breakdown of the operation of the interim STP, and to submit the plan to the Director for approval at least one month before commencement of operation of the interim STP.

 

Sewage Disposal

 

4.2      Before public sewer is available for connection, sewage from the Project shall be treated by the interim sewage treatment plant as stated in the EIA report.

 

4.3        The Permit Holder shall implement and maintain the operation stage measures recommended in the detailed operation and emergency response plan approved under Condition 4.1.

           
   
Control of Water Pollution due to Site Runoff

 

4.4       To control water pollution due to site runoff, the Permit Holder shall implement and maintain the operation stage measures recommended in the detailed drainage plan approved under Condition 2.4.

 

Measures to Mitigate Noise Impacts

 

4.5        The Permit Holder shall implement and maintain the operation stage measures recommended in the Noise Mitigation Plan approved under Condition 2.5

 

Measures to Mitigate Ecological Impacts

 

4.6       With reference to Condition 2.5 and Condition 4.5, if noise barriers are installed, they shall be opaque, non-reflective and with colour scheme to blend in with the environment.

 

Measures to Mitigate Visual and Landscape Impacts

 

4.7       The Permit Holder shall implement and maintain the operation stage measures recommended in the Landscape and Visual Implementation Plan approved under Condition 2.6.

 

 

5.         Environmental Monitoring and Audit (EM&A) Requirements

 

5.1       The EM&A programme shall be implemented in accordance with the procedures and requirements in the EM&A Manual. Any changes to the monitoring and audit requirements shall be justified by the ET leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual, and shall seek the prior approval from the Director before implementation.

 

5.2       Samples, measurements and necessary remedial actions shall be taken in accordance with the requirements of the EM&A Manual by:

 

a)    conducting baseline environmental monitoring;

 

b)    conducting constructional and operational phase impact monitoring;

 

c)    carrying out remedial actions described in the Event/Action Plans of the EM&A   Manual in accordance with the time frame set out in the Event/Action Plans, or as agreed by the Director, in case where specified criteria in the EM&A Manual are exceeded;

d)    logging and keeping records of the details of (a) to (c) above for all parameters within 3 working days of the collection of data or completion of remedial action(s), for the purpose of preparing and submitting the monthly EM&A Reports and to make available the information for inspection on site.

 

5.3       Four (4) hard copies and 1 electronic copy of the Baseline Monitoring Report shall be submitted to the Director at least 2 weeks before commencement of construction of the Project.  The submission shall be certified by the ET Leader and verified by the IEC.  Additional copies of the submission shall be made available to the Director upon his request.

 

5.4       Four (4) hard copies and 1 electronic copy of monthly EM&A Report shall be submitted to the Director within 2 weeks after the end of the reporting month.  The EM&A Reports shall include a summary of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels).  The submissions shall be certified by the ET Leader and verified by the IEC.  Additional copies of the submission shall be provided to the Director upon request by the Director.

 

5.5       All EM&A data submitted under this Permit shall be true, valid and correct.

 

 

6.        Electronic Reporting of EM&A Information

 

6.1       To facilitate public inspection of the Baseline Monitoring Report and monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Conditions 5.3 and 5.4 above of this Permit.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made.  All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director.  The content of the electronic copies of these Reports must be the same as the hard copies.

 

6.2       The Permit Holder shall, within 6 weeks after commencement of construction of the Project, set up a dedicated Internet web site and notify the Director in writing the Internet address where the environmental monitoring data and project information is to be placed.  All environmental monitoring data described in Condition 6.1 above shall be made available to the public via the dedicated Internet web site in the shortest possible time and in any event no later than 2 weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director.  All finalized submissions and plans shall be made available to the public via the dedicated Internet web site in the shortest possible time and in any event no later than 2 weeks after the submissions and plans are approved by or deposited with the Director, unless otherwise agreed with the Director.

 

6.3       The Internet web site as described in Condition 6.2 above shall enable user-friendly public access to the environmental monitoring data and project information including the Project Profile, EIA report, Environmental Permit(s) and finalized submissions and plans required under this Permit. The Internet web site shall have features capable of:

 

a)   providing access to all environmental monitoring data of this Project collected since the commencement of construction;

b)   providing access to all finalized submissions as required under this Permit;

c)   searching by date;

d)   searching by types of monitoring data; and

e)   hyperlinking to relevant monitoring data after searching

 

or otherwise as agreed by the Director

 

Notes :

 

1.       This Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project) and PART C (Permit Conditions).  Any person relying on this Permit shall obtain independent legal advice on the legal implications under the EIAO, and the following notes are for general information only.

 

2.       If there is a breach of any condition of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

 

3.       The Permit Holder may apply under Section 13 of the EIAO to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

 

4.       A person who assumes responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the EIAO to the Director for a further environmental permit.

 

5.       Under Section 14 of the EIAO, the Director may with the consent of the Secretary for the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the site.

 

6.       If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the EIAO before the Project could be continued. It is an offence under Section 26(1) of the EIAO to construct or operate a designated project listed in Part I of Schedule 2 of the EIAO without a valid environmental permit.

 

7.       Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the EIAO, is liable: -

 

(i)                  on a first conviction on indictment to a fine of $2 million and to imprisonment for 6 months;

 

(ii)                on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;

 

(iii)               on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

 

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

 

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.

 

8.       The Permit Holder may appeal against any condition of this Permit under Section 17 of the EIAO within 30 days of receipt of this Permit.

 

9.       The Notes are for general reference only and that the Permit Holder shall refer to the EIAO for details and seek independent legal advice.

 

 