Environmental Permit No. EP-517/2017
環境許可證編號EP-517/2017
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND OPERATE
A
DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部
(許可證主要部分)
Pursuant
to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the
Director of Environmental Protection (the Director) grants this environmental
permit to the Drainage Services Department (hereinafter
referred to as the “Permit Holder”) to construct and operate the designated
project described in Part B subject to the
conditions specified in Part C. The issue of this
environmental permit is based on the documents, approvals or permissions
described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予渠務署(下稱“許可證持有人”)
以建造及營辦B部
所說明的指定工程項目,但須遵守C部
所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕
Application No. 申請書編號 |
AEP-517/2016 |
Document in the Register: 登記冊上的文件: |
Expansion of Sha Tau Kok Sewage Treatment Works (Register No. AEIAR-207/2017) : -
Environmental Impact
Assessment (EIA) Report (August 2016) [Hereafter referred
to as “the EIA Report”] -
Environmental
Monitoring and Audit (EM&A) Manual (August 2016) [Hereafter referred to as “the EM&A Manual”] -
Executive
Summary (August
2016) 沙頭角污水處理廠擴建工程 (登記冊檔號:AEIAR-207/2017): -
環境影響評估報告 (2016年8月)
[下稱“環評報告”] -
環境監察及審核手冊 (2016年8月)
[下稱“環監手冊”] -
行政摘要(2016年8月) Application for Environmental Permit submitted on 29 June 2016 (Application No. AEP-517/2016) [Hereinafter referred to as the “Application”] 於2016年6月29日 提交的環境許可證申請文件 (申請書編號: AEP-517/2016) [下 稱 「 申 請 書 」] The Director’s letter of approval of the EIA Report dated 14 February 2017, (Ref. ( ) in EP 2/N7/F/77) 署長於2017年2月14日發出環評報告的批准信,(檔案編號: ( ) in EP 2/N7/F/77) |
15 February 2017
2017年2月 15 日
Date 日期 |
|
(WONG Chuen-fai) Principal Environmental Protection
Officer (Strategic Assessment) for Director of
Environmental Protection 環境保護署署長 (首席環境保護主任(策略評估) 黃傳輝代行) |
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is
the description of the designated project mentioned in Part
A of this environmental permit (hereinafter referred to as
the “Permit”):
下列為本環境許可證 (下稱“許可證”) A部 所提述的指定工程項目的說明﹕
Title of Designated Project 指定工程項目的名稱 |
Expansion of Sha Tau Kok Sewage Treatment Works [This
designated project is hereafter referred to as “the Project”] 沙頭角污水處理廠擴建工程 [本指定工程項目下稱 “工程項目”] |
Nature
of Designated Project |
(i) Sewage treatment works
with an installed capacity of more than 5,000 m3 per day; and a boundary
of which is less than 200m from the nearest boundary of an existing or
planned residential area; place of worship; educational institution; or
health care institution (ii) An activity for the reuse of treated sewage effluent
from a treatment plant (iii) A submarine sewage outfall (i)
污水處理廠,而其裝置的污水處理能力超過每天5,000立方米;及其一條界線距離一個現有的或計劃中的住宅區;禮拜場所;教育機構; 健康護理機構的最近界線少於200米 (ii) 對從處理廠流出並經處理的污水進行再使用的活動 (iii) 海底污水渠口 |
Location of Designated Project 指定工程項目的地點 |
The location of the Project is
shown in Figure 1 of this
Permit 工程項目的位置載於本許可證圖1 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
Major
components of the Project include - -
A temporary sewage treatment
plant (TSTP) with treatment capacity of not more than 2,500 m3 /
day at Average
Dry Weather Flow (ADWF) to maintain the sewage treatment service during the construction
and before the commencement of operation of the expanded Sha Tau Kok Sewage Treatment Works (STKSTW); -
Expansion of STKSTW to a treatment capacity of not more
than 10,000 m3/day at ADWF; -
A 1.7km long new submarine outfall; -
Demolition of the
Sha Tau Kok Sewage Pumping Station (STKSPS) and decommissioning of the associated rising main;
-
A 520m long new gravity sewer to replace the rising main between the existing STKSPS and
STKSTW; and -
Production of reclaimed water
(maximum 50 m3/day) from treated effluent for non-potable use
within the STKSTW. 工程項目的主要組成部分包括 -
一個不多於每日2,500立方米處理量(以平均旱季流量計算)的臨時污水處理廠,以便在沙頭角污水處理廠擴建工程期間及投入運作之前,維持污水處理服務; -
擴建沙頭角污水處理廠至提供不多於每日10,000立方米的處理量(以平均旱季流量計算); -
興建長1.7千米的新海底排放管; -
拆卸沙頭角污水泵房並解除運作該加壓污水管; -
興建長520米的新引力污水渠,以取代連接現有沙頭角污水泵房至沙頭角污水處理廠的加壓污水管;以及 -
在沙頭角污水處理廠範圍內以經處理的污水生產再造水(最大設計流量為每日50立方米),供作非飲用用途。 |
1. General Conditions
1.1 The Permit Holder and any person
working on the Project shall comply with all conditions set out in this Permit.
Any non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the
subject of appropriate action being taken under the EIAO.
1.2 The
Permit Holder shall ensure full compliance with all legislation from time to
time in force including, without limitation to, the Air Pollution Control Ordinance (Cap. 311), Waste
Disposal Ordinance (Cap. 354), Water
Pollution Control Ordinance (Cap. 358) and Noise Control Ordinance (Cap. 400). This Permit does
not of itself constitute any ground of defence against any proceedings
instituted under any legislation or imply any approval under any legislation.
1.3 The
Permit Holder shall make copies of this Permit together with all documents
referred to in this Permit and
the documents referred to in Part A of the Permit
readily available at all times for inspection by the Director or his authorised
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
1.4 The
Permit Holder shall give a copy of this Permit to the person(s) in charge of
the site(s) and ensure that such person(s) fully understands all conditions and
all requirements incorporated in
the Permit. The site(s) refers to site(s) of construction and operation of the
Project and shall mean the same hereafter.
1.5 The
Permit Holder shall display conspicuously a copy of this Permit on the Project
site(s) at all vehicular site entrances/exits or at a convenient location for
public’s information at all times. The Permit Holder shall ensure that the most
updated information about the Permit, including any amended Permit, is
displayed at such locations. If the Permit Holder surrenders a part or
the whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended,
varied or cancelled Permit shall be removed from display at the Project site(s).
1.6 The
Permit Holder shall construct and operate the Project in accordance with the
project description in Part B of this Permit.
1.7 The Permit Holder shall ensure that the
Project is designed, constructed and operated in
accordance with the information and recommendations described in the approved
EIA Report (Register No: AEIAR-207/2017); the application document for environmental permit; the information or mitigation measures described in
this Permit; mitigation measures to be recommended in submissions that shall be
deposited with or approved by the Director as a result of permit conditions
contained in this Permit, and mitigation measures to be recommended under
on-going surveillance and monitoring activities during all stages of the
Project; and other relevant documents in the Register. Where recommendations referred
to in the documents of the Register are not expressly referred to in this
Permit, such recommendations are nevertheless to be implemented unless
expressly excluded or impliedly amended in this Permit.
1.8 All submissions, as required under this Permit, shall be
rectified and resubmitted in accordance with the comments, if any, made by the
Director within one month of the receipt of the Director’s comments or
otherwise as specified by the Director.
1.9 All submissions to the Director, all submissions deposited
without comments by the Director, and all submissions rectified in accordance
with comments by the Director under this Permit shall be construed as part of
the permit conditions described in Part C of this Permit.
Any variation of the submissions shall be approved by the Director in writing
or as prescribed in the relevant permit conditions. Any non-compliance with the
submissions may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap. 499). All
submissions or any variation of submissions shall be certified by the
Environmental Team (ET) Leader and verified by the Independent Environmental
Checker (IEC) referred to in Conditions 2.1 and 2.4 below before submitting to
the Director under this Permit.
1.10 The Permit Holder shall release all finalised submissions as
required under this Permit to the public by depositing copies in the
Environmental Impact Assessment Ordinance Register Office, or in any other
places, or any internet websites as specified by the Director, or by any means
as specified by the Director, for public inspection. For this purpose, the
Permit Holder shall provide sufficient copies of the submissions.
1.11 All submissions to the Director required under this Permit shall
be delivered either in person or by registered mail to the Environmental Impact
Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130
Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalised
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies.
1.12 The Permit Holder shall notify the Director in writing the
commencement dates of construction and operation of the Project no later than one month prior to
the commencement of construction and operation of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement dates of the construction and operation.
1.13 For the
purpose of this Permit, “commencement of construction” does not include works
related to site clearance and preparation, or other works as agreed by the
Director.
2. Special Conditions
Submissions
and Measures Before or During Construction of the Project
Employment of ET
2.1 A single ET shall be employed
by the Permit Holder no later than one month before the commencement of construction of the
Project. The ET shall be directly supervised by the
Engineer’s Representative of the Permit Holder (ER) and shall not be in any way an
associated body of the Contractor or the IEC for the Project. The
Permit Holder shall provide a site office to the ET for use. The ET shall be headed by an ET Leader and supported by relevant specialists including
Ecologist and Registered Landscape Architect. The ET Leader shall be a person who has at least 7 years of
experience in environmental monitoring and auditing (EM&A) or environmental
management. The minimum on-site
time for the ET Leader and ET, and the qualifications of the specialists in the
ET shall be proposed with justifications for the approval of the Director.
2.2 The ET and the ET Leader shall be
responsible for:
(i) implementing the EM&A programme in accordance with the
EM&A requirements as contained in the EM&A Manual of the Project as
mentioned in Condition 3.1 below;
(ii) certifying the environmental
acceptability of permanent and temporary works, relevant plans and submissions
required in the EM&A Manual and under this Permit;
(iii) carrying out site inspections to audit
the Contractor’s site practice and work methodologies with respect to
environmental mitigation measures contained in the EM&A Manual of the
Project and to take pro-active actions to pre-empt environmental problems;
(iv) notifying the IEC within one working day of the occurrence of
each and every instance or circumstance or change of circumstances, which may
affect the compliance with the recommendations of the approved EIA Report (Register No. AEIAR-207/2017) and this Permit; and
(v) keeping a contemporaneous log-book of any such instance or circumstance or
change of circumstances. The log-book shall be kept
readily available for inspection by all persons assisting in supervision of the
implementation of the recommendations of the approved EIA Report (Register No. AEIAR-207/2017) and this Permit or by the Director
or his authorized officers.
2.3 Failure to maintain records in
the log-book, failure to discharge the duties of the ET Leader as defined in
the EM&A Manual or failure to comply with this Condition would entitle the
Director to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit Holder to make replacement, or further
failure to keep contemporaneous records in the log-book despite the employment
of a new ET Leader may render the Permit liable to suspension,
cancellation or variation.
Employment of IEC
2.4 A single IEC with a supporting team shall be employed by the Permit
Holder no later than one
month before the
commencement of construction of the Project. The IEC and
his / her team shall not be in any way an
associated body of the ER, the Contractor or the ET for the Project. The
IEC shall be approved by the Director before appointment by the Permit Holder.
The Permit Holder shall provide a site office to the IEC and the supporting
team for use. The IEC shall be a person who has at least 7 years
of experience in EM&A or environmental management. The
minimum on-site time for the IEC and his / her team shall be proposed with justifications
for the approval of
the Director.
2.5 The IEC shall report directly
to the Director on matters relating to the EM&A programme and environmental
impacts from the Project and shall submit to the Director for approval, no
later than one month before
the commencement of the construction of the Project, a proposal on the reporting
mechanism covering the approaches for the IEC and the team to report to the
Director on:
(i)
how to discharge all the duties specified
under the EM&A programme and this Permit, taking into account the
construction activities and programme of the Project;
(ii)
how to
handle each and every
change of circumstances, emergency events relating to violation of
environmental legislation (such as illegal dumping relating to the Project) or non-compliance
(including suspects of non-compliance) with the recommendations (such as construction
methods, mitigation measures, and environmental standards) of the approved EIA Report (Register No. AEIAR-207/2017), the EM&A
Manual and this
Permit, which might affect the monitoring or control of adverse environmental
impacts from the Project; and
(iii)
how to keep
proper records in order to respond to questions and enquiries from the Director on the EM&A programme
and duties discharged by the IEC.
2.6 The
IEC shall be
responsible for duties defined in the EM&A Manual and this
Permit, including but not limited to the following:
(i)
to audit the overall EM&A performance, including the
implementation of all environmental mitigation measures and monitoring
activities on site;
(ii)
to verify the environmental acceptability of permanent and temporary
works, relevant plans and submissions required in the EM&A
Manual and under this
Permit;
(iii)
to verify the log-book(s) mentioned in Condition 2.2(v);
(iv)
to notify the Director by fax or email, within one working day of
receipt of notification from the ET Leader, or identification by
the IEC and his / her team, of each and every change of
circumstances and emergency events mentioned in Condition 2.5(ii);
(v)
to liaise
closely with the Director;
(vi)
to accompany the Director in carrying out
site inspections and attending meetings when requested;
(vii)
to offer objective and professional advice on
environmental issues, when requested, and to respond to questions and enquiries from the Director on the EM&A
programme and duties discharged by the IEC, with the support of relevant
information, documents and records as appropriate; and
(viii) to allocate adequate
resources, including any necessary specialist support, for discharging the
duties required in this Permit and the EM&A Manual.
2.7 If the Director
considers the IEC fails
to discharge the duties of the IEC as defined in the EM&A Manual or in
this Permit, the Director
may require the Permit Holder by notice in writing to replace the IEC.
Failure to replace the IEC as directed or further failure to so notify the
Director despite employment of a new IEC may render the Permit liable to
suspension, cancellation or variation. Notification by the Permit Holder
is the same as notification by the IEC for the purpose of this Condition.
Submission
of Management Organizations
2.8 The Permit Holder shall, no later than one month before the commencement
of construction of the Project, inform the Director in writing with the following information which shall
include at least an organization chart, names of responsible persons and their contact details:
(i)
the management organization of the main construction companies and / or any form of joint ventures associated with the construction of the
Project;
(ii)
the
management organization of the ET; and
(iii)
the
management organization of the IEC and the supporting team.
Submission of Demolition Noise Mitigation
Measures Plan (DNMMP)
2.9 The Permit Holder shall submit a
Demolition Noise Mitigation Measures Plan (DNMMP) no later than one month
before the commencement of the demolition of the existing structures in the Sha
Tau Kok Sewage Treatment Works (STKSTW) and Sha Tau Kok Sewage Pumping Station
(STKSPS). The DNMMP shall include the use of low-noise technology and equipment
to minimize demolition noise impact on the nearby noise sensitive receivers.
Measures in the DNMMP shall be fully implemented.
Measures To Minimize Construction Impacts
2.10 To minimize construction dust and noise
impacts, the section of gravity sewer
near Tin Hau Temple as shown in Figure
1 of this Permit shall be constructed by trenchless method to
minimize impact to the Tin Hau Temple.
2.11 To minimize water quality impact from the
marine construction works, the following mitigation measures shall be
implemented:
(i)
The submarine outfall
in Starling Inlet shall be constructed by
trenchless method such as Horizontal Directional Drilling or equivalent such
that the seabed (except at the diffuser location) will not be disturbed; and
(ii)
Cofferdam shall be installed
at the receiving pit of the diffuser of submarine outfall. Excavation of
sediment and construction of the diffuser shall be conducted in dry condition within
the fully-drained cofferdam.
2.12 To minimise potential
construction impact on the Night Roosting
Site for Great Egret (hereinafter referred to as “Night Roosting Site”) as
shown in Figure 2 of this Permit, the
Permit Holder shall undertake a pre-construction survey to reconfirm the usage
of the Night Roosting Site by Great Egrets or other ardeids species; and shall
deposit to the Director the pre-construction survey report no later than one
month before the commencement of any construction / demolition
works within 100m of the Night Roosting Site. If
the pre-construction survey report shows the Night Roosting Site is used by
Great Egrets or other ardeids species, then no work shall be undertaken within
100m from the Night Roosting Site from 16:00 to 07:00 of the following day. The pre-construction survey report shall be
certified by the ET Leader and the Ecologist referred to in Condition 2.1 and
verified by the IEC.
Submissions and Measures Before or During Operation
of the Project
Measures
to Minimize Operation Noise Impact
2.13 To minimize operation noise of the Project,
the following mitigation measures shall be implemented for the Temporary Sewage
Treatment Plant (TSTP) and the expanded STKSTW:
Measures for the TSTP
(i)
Pumps and air blowers
shall be enclosed within tank and acoustic enclosure respectively;
(ii)
Mechanical raked
screen shall be within steel casing; and
(iii)
Deodourization fan
shall be enclosed inside deodourization unit with the exhaust facing away from
the noise sensitive receivers .
Measures for the expanded
STKSTW
(i)
All the equipment
shall be enclosed inside building structure; and
(ii)
Exhaust fans shall be
fitted with acoustic louvre / siliencer.
Submission
and Measures to Minimize Operation Odour Impact
2.14 To minimize odour impact during operation
of the Project, the following mitigation measures shall be implemented:
(i)
No concurrent
operation of the TSTP and the expanded STKSTW;
(ii)
All process equipment
of the TSTP shall be enclosed; and all process equipment of the expanded STKSTW
shall be confined inside building substructure / superstructure;
(iii)
The TSTP and the
expanded STKSTW shall be equipped with deodourizing facility using activated carbon
filters and / or biotrickling filters to attain odour removal efficiency of no
less than 99.5% at exhaust;
(iv)
Sewage sludge shall
be removed off-site regularly to avoid accumulation of odourous materials on
site. Trucks transporting sludge shall be fully enclosed; and
(v)
The holding area of
the dewatered sludge and the loading operation of the sludge onto trucks shall
be within enclosed area of the
STKSTW with deodourization unit.
2.15 The Permit Holder shall, no less than one month
before the commencement of operation of the TSTP and of the expanded STKSTW respectively,
deposit 5 hard copies and 1 electronic copy of Commissioning Test Report to the
Director to demonstrate compliance with the odour removal efficiency as
described in Condition 2.14(iii) above.
Any measure(s) as recommended in the Commissioning Test
Report shall be fully implemented.
Submission and Measures to Minimize
Operation Water Quality Impact
2.16 The following precautionary measures shall
be implemented during the operation of the TSTP and of the expanded STKSTW to
minimize risk of discharge of untreated or incompletely-treated sewage into
marine water under emergency situation:
(i)
Routine / regular
checking of the equipment, provision of dual power supply and backup generator,
provision of standby equipment for all treatment units, 24-hour monitoring of
the operation of the TSTP and the expanded STKSTW, remote control and
monitoring system; and
(ii)
Provision of on-site
storage of raw sewage for the TSTP and the expanded STKSTW, with storage volume
of at least 625 m3 and 2,500 m3 respectively.
2.17 The Permit Holder shall submit an Emergency
Response Plan (ERP) no later than one month before the commencement of operation
of the TSTP and of the expanded STKSTW respectively (2 ERPs shall be submitted
i.e. 1 ERP for TSTP, 1 ERP for expanded STKSTW), for approval by the Director. Each
of the ERPs shall include, but not limited to, the following:
(i)
Locations of sensitive
receivers in the vicinity of the emergency discharge outlet;
(ii)
List of bodies to be
informed or involved;
(iii)
List of
mariculturists to be informed;
(iv)
Reporting procedures;
(v)
Responsibilities and
procedures for clean-up of the affected water body / sensitive receivers; and
(vi)
Investigation
arrangement of incidents that affect nearby fish culture zone, including water
sampling, assessing of the impact, investigating the cause of any fish kill /
loss of fishery, and the relevant departments to be consulted .
All measure(s) as recommended in ERPs shall be fully implemented in case of emergency
discharge.
Submission
and Measures to Minimize Operation Landscape and Visual Impact
2.18 The
Permit Holder shall submit a detailed Landscape and Planting Plan (LPP), no
later than one month before the commencement of the implementation of planting
and landscape works, for approval by the Director. The LPP shall include tree
planting, rooftop and vertical greening to facilitate the STKSTW structures of
the Project to harmonize with the surrounding natural environment; and the use of native
tree and plant species compatible with the STKSTW structures of the Project to
provide better screening effect and to mitigate the landscape and visual
impacts especially when viewing from the Starling Inlet. The LPP shall be certified by the ET Leader
and the Registered Landscape Architect referred to in Condition 2.1 and
verified by the IEC.
Measures to Mitigate Impact from the Reuse
of Treated Effluent
2.19 The following measures for reusing treated
effluent from the Project as reclaimed water shall be implemented:
(i)
Quality of the reclaimed water, which shall be for
non-potable uses only, shall meet the following requirements;
Water Quality Parameter |
Unit |
Reclaimed
Water Quality of this Project |
pH |
n/a |
6 – 9 |
Turbidity |
NTU |
≤ 2 |
Total Suspended Solids |
mg / L |
≤ 10 |
Biochemical Oxygen Demand (BOD5) |
mg / L |
≤ 10 |
Colour |
Hazen Unit |
≤ 20 |
Ammonia Nitrogen |
mg / L |
≤ 1 |
Threshold Odour Number |
T.O.N |
≤ 100 |
Synthetic Detergents |
mg / L |
≤ 5 |
Escherichia coli |
cfu / 100ml |
Not Detectable |
Dissolved Oxygen |
mg / L |
≥ 2 |
Residual Chlorine |
mg / L |
≥ 1 (For cleansing and toilet flushing) ≤ 1 (For landscape irrigation) |
(ii)
The reclaimed water
pipeline shall be a separate system and shall not be connected with the potable
water pipeline system. To avoid cross-connection of the reclaimed water supply
to the potable water supply, the Permit Holder shall specially arrange the pipes
for the reclaimed water to differentiate them from that of the potable water
pipe, by
clear labels, warning signs and notices, colour-coding, and / or using different pipe sizes; and
(iii)
To minimize the formation of aerosol from reclaimed water, high
pressure jetting / cleansing equipment shall not be allowed during ground and
facility washing and landscape irrigation using the reclaimed water.
3 ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS
3.1 The Permit Holder
shall implement the EM&A programme in accordance with the
procedures and requirements as set out in the EM&A Manual. Any changes to
the programme shall be justified by the ET Leader and verified by the IEC as
conforming to the information and requirements contained in the EM&A Manual
before submission to the Director for approval.
3.2 The
Permit Holder shall take samples, measurements and necessary remedial actions in accordance with the
requirements of the EM&A Manual by:
(i)
conducting baseline environmental monitoring;
(ii)
conducting impact monitoring;
(iii)
carrying out remedial actions described in the Event/Action Plans of the
EM&A Manual in accordance with the time frame set out in the Event/Action
Plans, or as agreed by the Director, in case where specified criteria in the
EM&A Manual are exceeded; and
(iv)
logging and keeping records of the details of (i) to (iii) above for all
parameters within 3 working days of the collection of data or completion of
remedial action(s), for the purpose of preparing and submitting the monthly
EM&A Reports and to make available the information for inspection on site.
3.3 The
Permit Holder shall submit 4 hard copies and 1
electronic copy of relevant Baseline Monitoring Reports to the Director at least 2 weeks before the commencement of
construction of the Project. The submissions shall be certified by the ET
Leader and verified by the IEC as having complied with the requirements as set
out in the EM&A Manual before submission to the Director. Additional
copies of the Baseline Monitoring Reports shall be provided upon
request by the Director.
3.4 The
Permit Holder shall submit 4 hard copies and 1
electronic copy of Monthly EM&A Reports for the construction stage of the
Project to the Director, within 2 weeks after the end of the reporting
month. The monthly EM&A Reports shall include an executive
summary of all environmental
audit results, together with actions taken in the event of non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit Levels),
complaints received and emergency events relating to violation of environmental
legislation (such as illegal dumping). The submissions
shall be certified by the ET Leader and verified by the IEC as having complied
with the requirements as set out in the EM&A Manual before submission to
the Director. Additional copies of the Monthly EM&A Reports shall be
provided upon request by the Director.
3.5 All environmental monitoring and audit data
submitted under this Permit shall be true, valid and correct.
3.6 To ensure a high degree of transparency
regarding the monitoring data and results in view of the public concern about
the Project, all environmental monitoring and audit data and results and all
submissions and all performance test data and results required by this Permit
shall be made available by the Permit Holder to the public through a dedicated
website to be set up by the Permit Holder under Condition 4.2 below, in the
shortest practicable time and in no event later than 2 weeks after such
information is available.
4. ELECTRONIC
REPORTING OF EM&A INFORMATION
4.1 To facilitate public
inspection of the Baseline Monitoring Report and Monthly EM&A Reports via
the EIAO Internet Website and at the EIAO Register Office, electronic copies of
these Reports shall be prepared in Hyper Text Markup Language (HTML) (version
4.0 or later) and in Portable Document Format (PDF version 1.3 or later),
unless otherwise agreed by the Director and shall be submitted at the same time
as the hard copies as described in Conditions 3.3 and 3.4 above. For the HTML
version, a content page capable of providing hyperlink to each section and
sub-section of these Reports shall be included in the beginning of the
document. Hyperlinks to all figures, drawings and tables in these Reports shall
be provided in the main text from where the respective references are
made. All graphics in these Reports shall be in interlaced GIF, JPEG or PDF
format unless otherwise agreed by the Director. The content of the
electronic copies of these Reports must be the same as the hard copies.
4.2 The Permit Holder shall,
within 6 weeks after the commencement of construction of the Project, set up a
dedicated Internet website and notify the Director in writing the Internet
address where the environmental monitoring data and project information is to
be placed. All environmental monitoring data described in Condition 4.1
above shall be made available to the public via the abovementioned dedicated
Internet website in the shortest possible time and in any event no later than 2
weeks after the relevant environmental monitoring data are collected or become
available, unless otherwise agreed with the Director. All finalized submissions and plans shall be
made available to the public via the dedicated Internet website in the shortest
possible time and in any event no later than 2 weeks after the submissions and
plans are approved by or deposited with the Director, unless otherwise agreed
with the Director. The Permit Holder shall maintain the dedicated
website for public access of the environmental monitoring data and reports
throughout the entire construction period and during the first 3-year period of
operation of the Project, or otherwise as agreed by the Director.
4.3 The Internet website as
described in Condition 4.2 above shall enable user-friendly public access to
the environmental monitoring data and project information including the Project
Profile and this Permit. The Internet website shall have features capable
of:
(i)
providing
access to all environmental monitoring data of this Project collected since the commencement of construction;
(ii)
searching by date;
(iii)
searching by types of monitoring data; and
(iv)
hyperlinking to relevant monitoring data after
searching
or otherwise as agreed by
the Director.
Notes:
1. This
Permit consists of three parts, namely, Part A
(Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions). Any person relying on this permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
2. If
there is a breach of any condition of this Permit, the Director or his
authorized officer may, with the consent of the Secretary
for the Environment, order the cessation of associated work until the
remedial action is taken in respect of the resultant environmental damage, and
in that case the Permit Holder shall not carry out any associated works without
the permission of the Director or his authorized officer.
3. The
Permit Holder may apply under Section 13 of the EIAO to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the Project site by the amended permit.
4. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under Section 12 of
the EIAO to the Director for a further environmental permit.
5. Under
Section 14 of the EIAO, the Director may with the consent of the Secretary for the Environment, suspend, vary or
cancel this Permit. The suspended, varied or cancelled Permit shall be removed
from display at the Project site.
6. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the EIAO before
the Project could be continued. It is an
offence under Section 26(1) of the EIAO to construct or operate a designated
project listed in Part I of Schedule 2 of the EIAO without a valid
environmental permit.
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment
to a fine of $2 million and to
imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a
fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of
a continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the EIAO within 30 days of receipt of this Permit.
9. The Notes are for general reference
only and that the Permit Holder should refer to the EIAO for details and seek
independent legal advice.
Environmental
Permit No. EP-517/2017
環境許可證編號 EP-517/2017
[ Back to First Page ] / [ Back to
Main Index ]