Environmental Permit No. EP-522/2017
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the Director of
Environmental Protection (the Director) grants this environmental permit
to the Food and Health Bureau (hereinafter referred to as the “Permit Holder”) to construct and operate
the designated project described in Part B subject to the conditions specified
in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予食物及衛生局(下稱“許可證持有人”)以建造及營辦B部所說明的指定工程項目,但須遵守C 部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕
Application No. 申請書編號: |
AEP-522/2016
|
|
Document in the Register: 登記冊上的文件: |
(1) (2) (3) |
A Rooftop Helipad at the Proposed New Block of
Queen Mary Hospital (Register No. AEIAR-208/2017) -Environmental Impact
Assessment Report [Hereinafter
referred to as the “EIA Report”] -EIA Executive Summary [Hereinafter
referred to as the “EIA Executive Summary”] -Environmental Monitoring and
Audit Manual [Hereinafter
referred to as the “EM&A Manual”] 瑪麗醫院新醫院大樓天台直升機坪 (登記冊檔號: AEIAR-208/2017) -環境影響評估報告 [下稱「環評報告」] -環境影響評估報告行政摘要 [下稱「環評行政摘要」] -環境監察及審核手冊 [下稱「環監手冊」] The Director’s letter of approval of the EIA Report dated 22 March 2017 (Reference:
(20)
in EP2/H10/B/10 Pt.2) 署長於2017年3月22日發出批准環評報告的信件 (檔案編號:(20) in EP2/H10/B/10 Pt.2) Application for environmental permit submitted
by the Permit Holder on 21 November
2016 (Application No. AEP-522/2016) 許可證持有人於2016年11月21日提交的環境許可證申請 (申請書編號:AEP-
522/2016) |
22
March 2017
2017年3月22日
Date 日期 |
|
(Tony
W.H.CHEUNG) Acting Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (署理首席環境保護主任 張偉雄 代行) |
PART B (DESCRIPTION OF DESIGNATED PROJECT)
Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter
referred to as the “Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明﹕
Title
of Designated Project 指定工程項目的名稱 |
A Rooftop Helipad at the Proposed New Block of Queen Mary Hospital [This designated project is
hereinafter referred to as “the Project”] 瑪麗醫院新醫院大樓天台直升機坪 [本指定工程項目下稱「工程項目」] |
Nature of Designated Project |
A helipad within 300 m of existing
residential development 在現有的住宅發展300米內的直升機升降場 |
Location
of Designated Project 指定工程項目的地點 |
The location
of the Project is shown in Figure 1 of
this Permit. 工程項目的地點見本許可證圖1。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
The
Project is to construct and operate a helipad solely for
medical emergency purposes,
which mainly comprises:- (i) A helipad
structure
(approx. 40 metres in diameter) (ii) Other associated structures and utilities, etc. 工程項目包括建造及營辦一個只供緊急醫療服務的直升機坪,主要組成部分為: (i)
一個直升機坪結構(直徑約40米) (ii)
其他有關結構及設施等 |
1. GENERAL
CONDITIONS
1.1 The Permit Holder and any
person working on the Project shall comply with all conditions set out in this
Permit. Any non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the
subject of appropriate action being taken under the EIAO.
1.2 The Permit Holder shall
ensure full compliance with all legislations from time to time in force
including, without limitation to, the Air Pollution Control Ordinance (Cap.
311), Waste Disposal Ordinance (Cap. 354), Water Pollution Control Ordinance
(Cap. 358) and Noise Control Ordinance (Cap. 400). This Permit does not of
itself constitute any ground of defence against any proceedings instituted
under any legislation or imply any approval under any legislation.
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit
and the documents referred to in Part A of the
Permit readily available at all times for inspection by the Director or his
authorised officers at all sites/offices covered by this Permit. Any reference
to the Permit shall include all documents referred to in the Permit and also
the relevant documents in the Register.
1.4 The Permit Holder shall
give a copy of this Permit to the person(s) in charge of the site(s) and ensure
that such person(s) fully understands all conditions and all requirements
incorporated in the Permit. The site(s) refers to site(s) of construction and
operation of the Project and shall mean the same hereafter.
1.5 The Permit Holder shall
display conspicuously a copy of this Permit on the Project site(s) at all
vehicular site entrances/exits or at a convenient location for public’s
information at all times. The Permit Holder shall ensure that the most updated
information about the Permit, including any amended Permit, is displayed at
such locations. If the Permit Holder surrenders a part or the whole of
the Permit, the notice he sends to the Director shall also be displayed at the
same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site(s).
1.6 The Permit Holder shall
construct and operate the Project in accordance with the project description in
Part B of this Permit.
1.7 The Permit Holder shall
ensure that the Project is designed, constructed and operated in accordance
with the information and recommendations described in the approved EIA Report (Register
No. AEIAR-208/2017), the application document for Environmental Permit
(Application No. AEP-522/2016), other relevant documents in the Register, the
information and mitigation measures described in this Permit, mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, and mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or amended in this Permit.
1.8 All deposited submissions,
as required under this Permit, shall be rectified and resubmitted in accordance
with the comments, if any, made by the Director within one month of the receipt
of the Director’s comments or otherwise as specified by the Director.
1.9 All submissions approved
by the Director, all submissions deposited without comments by the Director, or
all submissions rectified in accordance with comments by the Director under
this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the
submissions shall be approved by the Director in writing or as prescribed in
the relevant permit conditions. Any non-compliance with the submissions may
constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap. 499). All submissions or any variation of the submissions shall be
certified by the Environmental Team (ET) Leader and verified by the Independent
Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below, before submitting to the Director under this
Permit.
1.10 The Permit Holder shall release all
finalized submissions as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of the submissions.
1.11 All submissions to the Director
required under this Permit shall be delivered either in person or by registered
mail to the Environmental Impact Assessment Ordinance Register Office
(currently at 27/F, Southorn Centre, 130 Hennessy
Road, Wanchai, Hong Kong). Electronic copies of all
finalized submissions required under this Permit shall be prepared in Hyper
Text Markup Language (HTML) (version 4.0 or later)
and in Portable Document Format (PDF version 1.3 or later), unless otherwise
agreed by the Director and shall be submitted at the same time as the hard
copies.
1.12 The
Permit Holder shall notify the Director in writing the commencement dates of
construction and operation of the Project no later than 1 month prior to the
commencement of construction and operation of the Project. The Permit Holder
shall notify the Director in writing immediately if there is any change of the
commencement dates of the construction and operation.
1.13 For
the purpose of this Permit, “commencement of construction” does not include
works related to site clearance and preparation, or other works as agreed by
the Director.
2. SPECIFIC CONDITIONS
Submissions and Measures
before Commencement of Construction of the Project
Employment of Environmental Monitoring and Audit
(EM&A) Personnel
2.1 An Environmental Team (ET) shall be
established by the Permit Holder no later than one month before the
commencement of construction of the Project. The ET shall not be in any
way an associated body of the Contractor or the Independent Environmental
Checker (IEC) for the Project. The ET shall be headed by an ET Leader. The
ET Leader shall be a person who has at least 7 years of experience in
environmental monitoring and auditing (EM&A) or environmental
management. The ET and the ET Leader shall be responsible for the
implementation of the EM&A programme in accordance with the EM&A
requirements as contained in the EM&A Manual of the Project. The ET
Leader shall keep a contemporaneous log-book of each and every instance or
circumstance or change of circumstances, which may affect the compliance with the
recommendations of the EIA Report (Register No.: AEIAR-208/2017) and this Permit. The ET Leader shall notify the IEC within one
working day of the occurrence of any such instance or circumstance or change of
circumstances. The ET Leader’s log-book shall be kept readily available
for inspection by all persons assisting in supervision of the implementation of
the recommendations of the EIA Report (Register No.: AEIAR-208/2017) and this Permit or by the Director or his authorized
officers. Failure to maintain records in the log-book, failure to
discharge the duties of the ET Leader as defined in the EM&A Manual or
failure to comply with this Condition would entitle the Director to require the
Permit Holder by notice in writing to replace the ET Leader. Failure by
the Permit Holder to make replacement, or further
failure to keep contemporaneous records in the log-book despite the employment
of a new ET Leader may render the Permit liable to
suspension, cancellation or variation.
2.2 An Independent Environmental Checker (IEC) shall be employed by the Permit Holder no
later than one month before the commencement of construction of the
Project. The IEC shall not be in any way an associated body of the
Contractor or the ET for the Project. The IEC shall be a person who has at
least 7 years of experience in EM&A or environmental management. The
IEC shall be responsible for duties defined in the EM&A Manual and shall
audit the overall EM&A performance, including the implementation of all
environmental mitigation measures, submissions required in the EM&A Manual,
and any other submissions required under this Permit. In addition, the IEC
shall be responsible for verifying the environmental acceptability of permanent
and temporary works, relevant design plans and submissions under this
Permit. The IEC shall verify the log-book(s) mentioned in Condition 2.1 of
this Permit. The IEC shall notify the Director by fax, within one working
day of receipt of notification from the ET Leader of each and every change of
circumstances or non-compliance with the recommendations of the EIA Report (Register No.: AEIAR-208/2017) and this Permit, which might affect the monitoring
or control of adverse environmental impacts from the Project. In case the
IEC fails to so notify the Director of the same, fails
to discharge the duties of the IEC as defined in the EM&A Manual or fails
to comply with this Condition, the Director may require the Permit Holder by
notice in writing to replace the IEC. Failure to replace the IEC as
directed or further failure to so notify the Director despite employment of a
new IEC may render the Permit liable to suspension, cancellation or variation.
Notification by the Permit Holder is the same as notification by the IEC for
the purpose of this Condition.
Management
Organization of Main Construction Companies
2.3 The Permit Holder shall, no later than two weeks before
the commencement of construction of the Project, inform the Director in writing the management organization of
the main construction companies and/ or any form of joint ventures associated with the
Project. The submitted information shall include at least an organization
chart, names of responsible persons and their contact details.
Submission of Operational Helicopter Noise
Mitigation Measures Plan
2.4 The Permit
Holder shall, no later than one month prior to the installation of noise barriers of the Project, submit the Director four hard copies and one electronic
copy of an Operational Helicopter Noise Mitigation Measures Plan for approval. The Plan shall include an updated
prediction of noise levels in accordance with the updated information and
mitigation proposals in place. Before submission to the Director, the Operational Helicopter Noise Mitigation
Measures Plan shall be certified by
the ET Leader and verified by the IEC as conforming to the information and
recommendations contained in the EIA Report (Register No. AEIAR-208/2017) and
all relevant documents in the Register, or otherwise approved by the
Director in compliance with the requirements in “Technical Memorandum on
Environmental Impact Assessment Process”.
Submissions and Measures
Before and
During operation of the Project
Measures to Mitigate Noise
Impacts during Operation of Helipad (including trial flight)
2.5 Unless
otherwise approved by the Director, the Permit Holder shall comply with the
following conditions for the purpose of mitigating the helicopter noise impact:-
(i) No
helicopter flights shall be operated for the purpose of commercial operations,
training flights, transportation of guests, or other non-emergency uses (except
for trial flights).
(ii) The
Permit Holder shall notify the Director in writing the schedule of any trial
flights for evening time and night time (i.e. from 1900 hours to 0700 hours the
next day) of the Project at least two weeks prior to the flights; and
(iii) Helicopter
type of "Airbus H175" as recommended in the EIA Report (Register No. AEIAR-208/2017),
or other quieter helicopter(s) supported with justifications by the ET Leader
and verified by the IEC, shall be used in the Project.
Submission
of Helicopter Flight Plan
2.6 The
Permit Holder shall no later than 1 month before the commencement of operation of the Helipad submit to the Director for approval 4 hard copies and 1
electronic copy of a flight plan showing the flight paths and approach &
take-off angles for the helicopter. The plan shall include at least the
following information:
(i) A
detailed flight profile;
(ii) Figures
showing the restricted ranges of approach/ taking-off flight paths and angles;
and
(iii) A
detailed implementation programme for the proposed
flight profile.
The
plan shall be certified by the ET Leader and verified by the IEC as conforming
to the information and recommendations contained in the EIA Report (Register
No. AEIAR-208/2017) and shall be fully and properly implemented.
3.
ENVIRONMENTAL MONITORING
AND AUDIT REQUIREMENTS
3.1 The Permit Holder shall implement the EM&A programme in
accordance with the procedures and requirements as set out in the EM&A Manual. Any changes to the programme shall be justified by the ET
Leader and verified by the IEC as conforming to the information and
requirements contained in the EM&A Manual before
submission to the Director for approval.
3.2
The Permit Holder shall carry
out the following items in accordance with the requirements of
the EM&A
Manual:
(i)
conduct environmental site
audits in accordance with the time frame set out in the EM&A Manual;
(ii)
carry out remedial actions described
in the Event/Action Plans of the EM&A Manual in accordance with the time
frame set out in the Event/Action Plans, or as agreed by the Director, in case
where specified criteria in the EM&A Manual are exceeded; and
(iii)
log and keep records of the details of
(ii) above for all parameters within 3 working days of the
collection of data or completion of remedial action(s), for the purpose of
preparing and submitting the monthly EM&A Reports and to make available the
information for inspection on site.
3.3
The Permit Holder shall submit
4 hard
copies and 1 electronic copy of Monthly EM&A Reports for the construction
stage of the Project to the Director, within 2 weeks after the end of the
reporting month. The monthly EM&A Reports shall include an executive summary of all environmental audit results, together with
actions taken in the event of non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit Levels),
complaints received and emergency events relating to violation of environmental
legislation (such as illegal dumping and landfilling). The submissions shall be
certified by the ET Leader and verified by the IEC as having complied with the
requirements as set out in the EM&A Manual before
submission to the Director. Additional copies of the Monthly EM&A
Reports shall be provided upon request by the Director.
3.4
All environmental
monitoring and audit data submitted under this Permit shall be true, valid and
correct.
4. ELECTRONIC REPORTING OF EM&A INFORMATION
4.1 To
facilitate public inspection of the Monthly EM&A Reports via the EIAO
Internet Website and at the EIAO Register Office, electronic copies of these
Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies as described in Conditions 3.3
and 3.4 above. For the HTML version, a content page capable of providing
hyperlink to each section and sub-section of these Reports shall be included in
the beginning of the document. Hyperlinks to all figures, drawings and tables
in these Reports shall be provided in the main text from where the respective
references are made. All graphics in these Reports shall be in interlaced
GIF, JPEG or PDF
format unless otherwise agreed by the Director. The content of the
electronic copies of these Reports must be the same as the hard copies.
Notes:
1. This
Permit consists of three parts, namely, Part A
(Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions). Any person relying on this permit shall obtain independent legal advice on
the legal implications under the EIAO, and the following notes are for general
information only.
2. If
there is a breach of any condition of this Permit, the Director or his
authorized officer may, with the consent of the Secretary for the Environment,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit Holder
shall not carry out any associated works without the permission of the Director
or his authorized officer.
3. The
Permit Holder may apply under Section 13 of the EIAO to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the Project site by the amended permit.
4. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under Section 12 of
the EIAO to the Director for a further environmental permit.
5. Under
Section 14 of the EIAO, the Director may with the consent of the Secretary for
the Environment suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the Project site.
6. If
this Permit is cancelled or surrendered during the construction or operation of
the Project, another environmental permit must be obtained under the EIAO
before the Project could be continued. It is an offence under Section 26(1) of
the EIAO to construct or operate a designated project listed in Part 1 and 2 of
Schedule 2 of the EIAO without a valid environmental permit.
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment
to a fine of $2 million and to imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2
years;
(iii)
on a first summary conviction to a
fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in
any case where the offence is of a continuing nature, the court or magistrate
may impose a fine of $10,000 for each day on which he is satisfied the offence
continued.
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the EIAO within 30 days of receipt of this Permit.
9. The
Notes are for general reference only and that the Permit Holder should refer to
the EIAO for details and seek independent legal advice.
Environmental Permit No. EP-522/2017