Environmental Permit No. EP-571/2019
環境許可證編號EP-571/2019
ENVIRONMENTAL IMPACT ASSESSMENT
ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部
(許可證主要部分)
Pursuant
to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the
Director of Environmental Protection (the Director) grants this environmental
permit to the Sha Lo Tung Development Company Limited (hereinafter
referred to as the “Permit Holder”) to construct and operate the designated
project described in Part B subject to the
conditions specified in Part C. The issue of this environmental permit
is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)
第10條的規定,環境保護署署長(署長)將本環境許可證批予沙螺洞發展有限公司(下稱“許可證持有人”)
以建造及營辦B部
所說明的指定工程項目,但須遵守C部
所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕
Application No. 申請書編號 |
AEP-571/2019 |
Document in the Register: 登記冊上的文件: |
(1) Shuen Wan Golf Course (Register No. AEIAR-221/2019): -
Environmental Impact Assessment Report [Hereafter
referred to as “the EIA Report”] -
Environmental Monitoring and Audit Manual [Hereafter
referred to as “the EM&A Manual”] -
EIA Executive Summary [Hereafter referred to as “EIA Executive Summary”] 船灣高爾夫球場 (登記冊檔號:AEIAR-221/2019): -
環境影響評估報告 [下稱「環評報告」] -
環境監察及審核手冊 [下稱「環監手冊」] -
環境影響評估報告行政摘要 [下稱「環評行政摘要」] (2)
The Director’s letter of
approval of the EIA Report dated 5 July 2019 (Reference: (47) in
EP 2/N5/O/69 Pt.2) 署長於2019年7月5日發出批准環評報告的信件 (檔案編號: (47) in EP 2/N5/O/69 Pt.2) (3)
Application for Environmental Permit submitted by the
Permit Holder on 11 September 2019 (Application No.
AEP-571/2019) 許可證持有人於2019年9月11日提交的環境許可證申請文件(申請書編號: AEP-571/2019) |
20
September 2019
2019年9月 20 日
Date 日期 |
|
(
K. H. TO ) Principal
Environmental Protection Officer for
Director of Environmental Protection 環境保護署署長 (首席環境保護主任 杜景浩 代行) |
PART B (DESCRIPTION OF DESIGNATED
PROJECT)
B部
(指定工程項目的說明)
Hereunder is the description of the designated project
mentioned in Part A of this environmental permit (hereinafter
referred to as the “Permit”):
下列為本環境許可證 (下稱“許可證”) A部
所提述的指定工程項目的說明﹕
Title of Designated Project 指定工程項目的名稱 |
Shuen Wan Golf Course [This
designated project is hereafter referred to as “the Project”] 船灣高爾夫球場 [本指定工程項目下稱 “工程項目”] |
Nature
of Designated Project |
An
outdoor golf course and all managed turf areas 戶外高爾夫球場及全部受管理的草地範圍 |
Location of Designated Project 指定工程項目的地點 |
The Project is located at Shuen Wan
Restored Landfill in Tai Po. The
location of the Project is shown in Figure
1 of this Permit. 工程項目位於大埔船灣已修復堆填區。工程項目的位置載於本許可證圖1。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
The Project scope comprises
construction and operation of the following key elements : 工程項目的範圍包括建造及營辦以下主要部份: -
An 18-hole golf course and its ancillary facilities
(under development scenario 2); and 一個18 洞高爾夫球場及其附屬設施(按發展方案2);及 -
Associated infrastructure such as drainage system,
sewerage system, irrigation system, etc. to support the daily operations of
the golf course. 支持高爾夫球場日常運作的基建配備,包括排水系統、污水系統、灌溉系統等。 |
1.
General Conditions
1.1
The Permit Holder and any person
working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may
constitute a contravention of the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) and may become the subject of appropriate action being taken
under the EIAO.
1.2
The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Air
Pollution Control Ordinance (Cap. 311), Waste Disposal Ordinance (Cap. 354), Water Pollution Control Ordinance
(Cap. 358) and Noise
Control Ordinance (Cap. 400). This
Permit does not of itself constitute any ground of defence against any
proceedings instituted under any legislation or imply any approval under any
legislation.
1.3
The Permit Holder shall make copies
of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of the Permit readily available at all times for
inspection by the Director or his authorised officers at all sites/offices
covered by this Permit. Any
reference to the Permit shall include all documents referred to in the Permit
and also the relevant documents in the Register.
1.4
The Permit Holder shall give a copy
of this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated in the Permit. The site(s) refers to site(s) of
construction and operation of the Project and shall mean the same hereafter.
1.5
The Permit Holder shall display
conspicuously a copy of this Permit on the Project Site(s) at all vehicular
site entrances/exits or at a convenient location for public’s information at
all times. The Permit Holder shall
ensure that the most updated information about the Permit, including any
amended Permit, is displayed at such locations. If the Permit Holder surrenders a part
or the whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project Site(s).
1.6
The Permit Holder shall construct
and operate the Project in accordance with the project description in Part B of this Permit.
1.7
The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and
recommendations described in the approved EIA Report (Register
No: AEIAR-221/2019); the application
document for environmental permit; the information
or mitigation measures described in this Permit; mitigation measures to be
recommended in submissions that shall be deposited with or approved by the
Director as a result of permit conditions contained in this Permit, and mitigation
measures to be recommended under on-going surveillance and monitoring
activities during all stages of the Project; and other
relevant documents in the Register. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8
All submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within one month of the receipt of the
Director’s comments or otherwise as specified by the Director.
1.9
All submissions to the
Director, all submissions deposited without comments by the Director, and all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall
be approved by the Director in writing or as prescribed in the relevant permit
conditions. Any non-compliance with
the submissions may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap. 499). All submissions or any variation of
submissions shall be certified by the Environmental Team (ET) Leader and
verified by the Independent Environmental Checker (IEC) referred to in Conditions
2.1 and 2.6 below before submitting to the Director under this Permit.
1.10
The Permit Holder shall
release all finalised submissions as required under this Permit to the public
by depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any means as specified by the Director, for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
1.11
All submissions to the
Director required under this Permit shall be delivered either in person or by
registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong
Kong). Electronic copies of all
finalised submissions required under this Permit shall be prepared in Hyper
Text Markup Language (HTML) (version 4.0 or later) and in Portable Document
Format (PDF version 1.3 or later), unless otherwise agreed by the Director and
shall be submitted at the same time as the hard copies.
1.12
The Permit Holder shall notify the
Director in writing the commencement dates of construction and operation of the
Project no later than three months prior to the commencement of construction
and operation of the Project respectively.
The Permit Holder shall notify the Director in writing immediately if
there is any change of the commencement dates of construction and operation.
1.13
For the purpose of this Permit,
“commencement of construction” does not include works related to site
investigation, clearance and preparation, or other works as agreed by the
Director.
2.
Special Conditions
Employments and Submissions
before Construction of the Project
Employment
of Environmental Team (ET)
2.1
An ET, unless otherwise
approved by the Director, shall be established by the Permit Holder no later
than four months before the commencement of construction of the Project. The ET shall be directly supervised by
the Engineer’s Representative (ER) of the Permit Holder and
shall not be in any way an associated body of the Contractor, the Specialist
Contractor, the IEC, or the Independent Landfill Consultant for the Project or the
Shuen Wan Landfill Restoration Contractor.
The Permit Holder shall provide a site office to the ET for use. The ET shall be headed by an ET Leader
and supported by relevant specialists including Ecologist and Registered Landscape
Architect. The ET Leader shall be a
person who has at least 7 years of experience in environmental monitoring and
auditing (EM&A) or environmental management. The minimum on-site time for the ET
leader and ET shall be proposed with justifications, having regard to the
potential environmental impacts arising from activities on site at various
stages of the Project, for the approval of the Director. The qualifications of the ET Leader and specialists
in the ET shall be proposed with justifications for the approval of the Director.
2.2
The ET and the ET Leader shall be responsible for:
(i)
implementing the EM&A programme in accordance with the
EM&A requirements as contained in the EM&A Manual of the Project as
mentioned in Condition 3.1 below;
(ii)
certifying the environmental acceptability of
permanent and temporary works, relevant plans and submissions required in the
EM&A Manual and under this Permit;
(iii)
carrying out site inspections to audit the
Contractor’s site practice and work methodologies with respect to environmental
mitigation measures contained in the EM&A Manual of the Project and to take
pro-active actions to pre-empt environmental problems;
(iv)
notifying the IEC within one working day
of the occurrence of each and every instance or circumstance or change of
circumstances, which may affect the compliance with the recommendations of the approved
EIA Report (Register No. AEIAR-221/2019) and this Permit; and
(v)
keeping a contemporaneous log-book of any such instance or circumstance or
change of circumstances.
The log-book
shall be kept readily available for inspection by all persons assisting in
supervision of the implementation of the recommendations of the approved
EIA Report (Register No. AEIAR-221/2019) and this Permit or by the
Director or his authorised officers.
2.3
Failure to maintain records in the log-book, failure to discharge the
duties of the ET Leader as defined in the EM&A Manual would entitle the
Director to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit
Holder to make replacement, or further failure to keep
contemporaneous records in the log-book despite the employment of a new ET
Leader may render the Permit liable to suspension, cancellation or variation.
Employment of Ecologist
2.4
The Permit Holder shall,
no later than four months before the commencement of the construction of the
Project, appoint an Ecologist to form part of the ET to carry out work relating
to ecological aspects including but not limited to preparing submission of Tree
Preservation, Transplantation and Compensation Plan (TPTCP), Construction
Phasing Plan (CPP), and Powered Mechanical Equipment Restriction Zones Review
Report (PMERZRR) for the Project as required under Conditions 2.14, 2.15, and
2.18 of this Permit respectively, and to audit the implementation of ecological
mitigation measures to ensure compliance with the recommendations of the
approved TPTCP, CPP, PMERZRR and the approved EIA Report (Register No.
AEIAR-221/2019). The Ecologist shall
be a person who has at least 5 years of relevant experience in avifauna
survey. The qualification and
experience of the Ecologist shall be certified by the ET Leader, and verified
by the IEC for the approval of
the Director.
Employment of
Registered Landscape Architect
2.5
The Permit Holder shall,
no later than four months before the commencement of the construction of the
Project, appoint a Registered Landscape Architect to form part of the ET to
carry out work relating to landscape aspects including but not limited to preparing
submissions of Tree Survey Report and Landscape and Visual Mitigation Plan (LVMP)
for the Project as required under Conditions 2.13 and 2.23 of this Permit
respectively, and to audit the implementation of landscape mitigation measures
to ensure compliance with the recommendations of the approved LVMP and the
approved EIA Report (Register No. AEIAR-221/2019). The qualification and experience of the
Registered Landscape Architect shall be certified by the ET Leader and verified
by the IEC for the approval of the Director.
Employment of Independent Environmental Checker (IEC)
2.6
An IEC with a supporting team,
unless otherwise approved by the Director, shall be employed
by the Permit Holder no later
than four months before the commencement of
construction of the Project. The
IEC and the supporting team
including the Independent Landfill Consultant as required in Condition 2.10 of
this Permit, shall not be in
any way an associated body of the ER, the Contractor or the ET for the
Project. The IEC and the
Independent Landfill Consultant shall be approved by the Director before
appointment by the Permit Holder. The
Permit Holder shall provide a site office to the IEC and the supporting team
for use. The IEC shall be a person who has at least 7 years
of experience in EM&A or environmental management. The minimum on-site time for the IEC and the
supporting team shall be proposed with justifications for the approval
of the Director. The qualification and experience of the IEC and the
Independent Landfill Consultant shall be proposed with justifications for the approval of the
Director.
2.7
The IEC shall report directly to the Director on matters relating to the
EM&A programme and environmental impacts from the Project and shall submit
to the Director for approval, no later than one month before the commencement of
the construction of the Project, a proposal on the reporting mechanism covering
the approaches for the IEC and the team to report to the Director on:
(i)
how to discharge all the duties specified
under the EM&A programme and this Permit, taking into account the
construction activities and programme of the Project;
(ii)
how to handle each and every change of circumstances, emergency events
relating to violation of environmental legislation (such as illegal dumping
relating to the Project) or non-compliance (including suspected non-compliance) with the recommendations (such
as construction methods, mitigation measures, and environmental standards) of the approved EIA Report (Register No. AEIAR-221/2019), the
EM&A Manual and this
Permit, which might affect the monitoring and/or control of adverse
environmental impacts from the Project; and
(iii)
how to
keep proper records in order to respond to questions and enquiries from the Director on the EM&A
programme and duties discharged by the IEC.
2.8
The IEC shall be responsible for duties defined in the
EM&A Manual and this Permit, including but not limited to the following:
(i)
to audit the overall EM&A performance, including the
implementation of all environmental mitigation measures and monitoring
activities on site;
(ii)
to verify the environmental acceptability of permanent and
temporary works, relevant plans and submissions required in the
EM&A Manual and under this
Permit;
(iii)
to verify the log-book(s) mentioned
in Condition 2.2(v);
(iv)
to notify the Director by fax or email, within one working day of
receipt of notification from the ET Leader, or identification by
the IEC and his / her team, of each and every change of
circumstances and emergency events mentioned in Condition 2.7(ii);
(v)
to liaise closely with the Director;
(vi)
to accompany the Director in carrying out
site inspections and attending meetings when requested;
(vii)
to offer objective and professional advice on
environmental issues, when requested, and to respond to questions and enquiries from the Director on the EM&A programme
and duties discharged by the IEC, with the support of relevant information,
documents and records as appropriate; and
(viii) to
allocate adequate resources, including any necessary specialist support, for
discharging the duties required in this Permit and the EM&A Manual.
2.9
If the Director considers the IEC fails to discharge the
duties of the IEC as defined in the EM&A Manual or in this Permit, the Director may require the
Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed or
further failure to discharge the duties of the IEC despite employment of a new
IEC may render the Permit liable to suspension, cancellation or variation.
Employment of
Independent Landfill Consultant
2.10
The Permit Holder shall,
no later than four months before the commencement of the construction of the
Project, appoint an Independent Landfill Consultant to form part of the IEC
supporting team to verify the submissions of Design Plan and Works Plan for the
Project as required under Conditions 2.20 and 2.21 of this Permit respectively and
to audit the modification works of existing landfill restoration facilities to
ensure compliance with the recommendations of the approved Design Plan, the approved
Works Plan and the approved EIA Report (Register No. AEIAR-221/2019). The Independent Landfill Consultant shall
not be in any way an associated body of the ER, the ET, the Contractor, or the
Specialist Contractor for the Project or the Shuen Wan Landfill Restoration
Contractor. The Independent Landfill Consultant shall be approved by the
Director before appointment by the Permit Holder. The Independent Landfill Consultant
shall be a company experienced in the geotechnical, landfill gas and leachate
design aspects of landfill restoration and aftercare and employing at least two
professional engineers who are members of the Hong Kong Institution of
Engineers or of equivalent professional qualification as approved by the
Director. Among those two
professional engineers, one shall be a geotechnical engineer with the
qualification of Registered Geotechnical Engineer and one shall be a landfill
designer. Each of the professional
engineers shall have not less than 8 years post-qualification experience
specialising in the geotechnical, landfill gas and leachate design aspects of
landfill restoration and aftercare. If
the Director considers the Independent Landfill Consultant fails to discharge
the duties of the Independent Landfill Consultant as defined in this Permit,
the Director may require the Permit Holder by notice in writing to replace the
Independent Landfill Consultant.
Failure to replace the Independent Landfill Consultant as directed or
further failure to discharge the duties of the Independent Landfill Consultant
despite employment of a new Independent Landfill Consultant may render the
Permit liable to suspension, cancellation or variation.
Employment of
Specialist Contractor
2.11
The Permit Holder shall,
no later than four months before the commencement of the construction of the
Project, appoint a Specialist Contractor with landfill restoration experience for
the approval by the Director. The
Specialist Contractor shall prepare the Works Plan under Condition 2.21 of this
Permit, supervise and construct modification, demolition and/or reprovision works
of existing landfill restoration facilities, conduct landfill gas hazard
monitoring and implement mitigation measures in compliance with the
recommendations of the approved Design Plan and Works Plan and the approved EIA
Report (Register No. AEIAR-221/2019).
The Specialist Contractor shall be a company which has completed within
the 5 years prior to the date of this Permit, or on the date of this Permit
have in hand, at least one landfill restoration and/or aftercare contract with
a total contract sum of not less than HK$100 million, solely under the name of
the Specialist Contractor company.
In the case where the Special Contractor company is a shareholder of a
Joint Venture company, its share of the Joint Venture in terms of landfill
restoration and/or aftercare contract sum shall be not less than HK$100 million,
or otherwise approved by the Director.
Any experience of the Specialist Contractor gained in the capacity as a
sub-contractor shall not be counted.
Any change or replacement of the Specialist Contractor approved by the
Director shall be subject to the prior written approval of the Director.
Submission of Management Organisations
2.12
The Permit Holder shall, no
later than four months before the commencement of construction of the Project, inform the
Director in writing with the following
information which shall include at least an
organisation chart, names of responsible persons and their
contact details:
(i)
the management organisation
of the main construction companies and / or any form of joint ventures associated with the construction of the
Project;
(ii)
the management organisation of the ET;
(iii)
the management organisation of the IEC and the
supporting team;
(iv)
the management organisation of the Specialist
Contractor; and
(v)
the
management organisation of the Independent Landfill Consultant.
Submission of Tree Survey Report
2.13
The Permit Holder shall conduct a comprehensive tree
survey on the existing trees of the Project Site to assess the condition of the
trees proposed to be retained. The Permit holder shall, no
later than four months before the commencement of construction of the Project,
submit 4 hard copies and 1 electronic copy of a Tree Survey Report to the
Director for approval. The Tree
Survey Report shall be prepared by the Registered Landscape Architect,
certified by the ET Leader and verified by the IEC for approval by the Director.
Submission of Tree Preservation, Transplantation
and Compensation Plan
2.14
The Permit Holder shall, no later than two months
before the commencement of construction of the Project, submit 5 hard copies
and 1 electronic copy of a Tree Preservation, Transplantation and Compensation
Plan (TPTCP) to the Director for approval.
The TPTCP shall be prepared making reference to the conceptual layout
plan in Figure 1 of this
Permit and based on the findings of the approved Tree Survey Report under
Condition 2.13 of this Permit and shall provide details of measures for
mitigation of the impact of the Project on night roosting of Collared Crow and
Black Kite, including:
(i)
Preservation of no less than 6.1 ha of existing tree
groups within the Project Site, including the 1.2 ha core roosting area as shown
in Figure 1 of this Permit; and
(ii)
Compensatory planting of no less than 10 ha of new
trees within the Project Site.
The TPTCP shall include the location and species of any
individual trees that would be directly affected by the proposed works,
recommending protective measures for identified individuals of each species
where in situ preservation is feasible, in particular the two individuals of Aquilaria sinensis as shown in Figure 1 of this Permit, assessing
the suitability and/or practicability of the transplantation of those
individuals that would be directly affected, and the location and species of
individual trees to be compensated for the loss of roosting sites.
The TPTCP shall be prepared by the Ecologist, certified
by the ET Leader and verified by the IEC as conforming to the findings and
recommendations of the approved EIA Report (Register No. AEIAR-221/2019)
for approval of the Director.
Recommendations on tree preservation, transplantation and compensation
in the approved TPTCP shall be fully implemented and maintained during
construction and operation phases of the Project. No felling or pruning of trees in core
roosting area at any time during construction and operation phases, except for
those recommended in the approved TPTCP.
Submission of Construction Phasing Plan
2.15
The Permit Holder shall review the phasing of the
construction activities and, no later than four months before the commencement
of construction of the Project, submit 4 hard copies
and 1 electronic copy of a Construction Phasing Plan (CPP) to the Director for
approval. The CPP shall be based on
the recommendations of the approved Tree Preservation, Transplantation and
Compensation Plan under Condition 2.14 of this Permit, and shall be designed with
a view to minimising the potential adverse impacts on the Collared Crow
including fragmentation on the roosting habitats, and to achieve the objectives
of tree preservation and compensation as stated in Condition 2.14 (i) and (ii) of
this Permit. The CPP shall take
into account the trees to be retained and the species and density of the new
trees to be planted for roosting habitats upon completion of site formation at
each phase. The CPP shall be prepared
by the Ecologist, certified by the ET Leader and verified by the IEC as
conforming to the findings and recommendations of the approved EIA Report
(Register No. AEIAR-221/2019) for approval of the Director. The phasing of construction activities
recommended in the approved CPP shall be fully implemented during construction
phase of the Project.
Submission of Construction Phase Water Quality Mitigation
Measures and Monitoring Plan
2.16
The Permit Holder shall, no later than two months
before the commencement of construction of the Project, submit 4 hard copies
and 1 electronic copy of a Water Quality Mitigation Measures and Monitoring Plan
(WQMMMP) to the Director for approval.
The WQMMMP shall be based on the approved Construction Phasing Plan under
Condition 2.15 of this Permit, and shall address potential water quality impact
on Tolo Harbour during construction phase of the Project, and shall include
comprehensive information on measures to reduce soil erosion, deployment of
temporary sedimentation tanks as well as other measures to intercept any
surface runoff and water quality monitoring requirements during the
construction phase. The WQMMMP
shall be certified by the ET Leader and verified by the IEC as conforming to
the findings and recommendations of the approved EIA Report (Register No.
AEIAR-221/2019) for approval of the Director. All measures recommended in the approved
WQMMMP shall be fully implemented during construction phase of the Project.
Submission of Construction Dust Management Plan
2.17
The Permit Holder shall, no later than two months
before the commencement of construction of the Project or otherwise approved by
the Director, submit 4 hard copies and 1 electronic copy of a Construction Dust
Management Plan (CDMP) to the Director for approval. The CDMP shall be based on the approved Construction
Phasing Plan under Condition 2.15 of this Permit, and shall include an updated
dust impact assessment and details of implementation programme of the required construction
dust mitigation measures for the Project.
The CDMP shall be certified by the ET Leader and verified by the IEC as
conforming to the findings and recommendations of the approved EIA Report
(Register No. AEIAR-221/2019) for approval of the Director. All measures recommended in the approved
CDMP shall be fully implemented during construction phase of the Project.
Submission
of Powered Mechanical Equipment Restriction Zones
Review Report
2.18
To minimise potential disturbance to Collared Crow
and Black Kite night roosts, the Permit Holder shall, based on the approved Construction
Phasing Plan under Condition 2.15 of this Permit, review the geographical
location of Restriction Zones as indicated in Figure 2 of this Permit, within which
powered mechanical equipment (PME) shall not be used during the restriction
hours in different months of the year as per Annex 1 of this Permit. If there is any change to geographical
location of the Restriction Zones, the Permit Holder shall, no later than two
months before the commencement of construction of the Project, submit 4 hard
copies and 1 electronic copy of a Powered Mechanical Equipment Restriction Zones
Review (PMERZRR), detailing the updated geographical location of the Restriction
Zones, to the Director for approval.
The PMERZRR shall be prepared by the Ecologist, certified by the ET
Leader and verified by the IEC as conforming to the findings and
recommendations of the approved EIA Report (Register No. AEIAR-221/2019) for
approval of the Director. The
restriction on operation hours of PME detailed in Annex 1 of this Permit
in the Restriction Zones detailed in Figure
2 of this Permit or as stated in the approved PMERZR shall be fully
implemented during construction phase of the Project.
Submission for Land Contamination Assessment
2.19
The Permit Holder shall carry out site re-appraisal
and detailed assessment of land contamination before the commencement of
construction works at the existing storage/ workshop area of the Project Site
as shown in Figure 3 of this
Permit. After site re-appraisal is
completed, the Permit Holder shall submit 4 hard copies and 1 electronic copy
of Land Contamination Review (LCR), including Contamination Assessment Plan
(CAP) where site investigation (SI) is required, to the Director for approval. If required under the approved LCR, the
Permit Holder shall conduct the site investigation (SI) in accordance with the
approved CAP and submit 4 hard copies and 1 electronic copy of a Contamination
Assessment Report (CAR) to document the findings of the SI to the Director for
approval. If contamination is
confirmed and remediation is deemed necessary, the CAR shall include a
Remediation Action Plan (RAP). If
remediation is required, the Permit Holder shall conduct the remediation in
accordance with the approved RAP and submit 4 hard copies and 1 electronic copy
of a Remediation Report (RR) to document the remediation work done to the
Director for approval. No
construction work at the existing storage/ workshop area shall be commenced
before the approval of LCR if no SI is required, before approval of CAR if SI
is required but no remediation is required, or before approval of RR if
remediation is required. The LCR/CAP,
and where required, the CAR, RAP and RR shall be certified by the ET Leader and
verified by the IEC for approval by the Director.
Submission for Design Plan and Works Plan
2.20
The Permit Holder shall, no later than three months
before the commencement of construction of the Project or otherwise approved by
the Director, submit 5 hard copies and 1 electronic copy of a Design Plan with
details on the interfacing works including all demolition, relocation,
reprovision and modification works of the existing landfill restoration
facilities to the Director for approval.
The Design Plan shall be based on the approved Construction Phasing Plan
under Condition 2.15 of this Permit, and shall include but not limited to the
following:
(i)
the objectives of the design and works;
(ii)
landfill facilities affected by the design and the
works;
(iii)
the location of affected facilities;
(iv)
drawings to show the design of new facilities
proposed;
(v)
a summary table detailing the affected facilities
and the proposed modification works involved, and the mitigation measures to be
employed;
(vi)
potential environmental impacts of the design and
works;
(vii)
any safety precaution and monitoring required, and
(viii)
impact assessment on waste excavated, if any, as
well as its disposal.
The Design Plan shall be prepared in consultation
with the Shuen Wan Landfill Restoration Contractor. The Design Plan shall be certified by the
ET Leader, verified by Independent Landfill Consultant, and then verified by
the IEC for approval by the Director.
2.21
The Permit Holder shall, no later than one month
before the commencement of construction of the Project or otherwise approved by
the Director, submit 4 hard copies and 1 electronic copy of a Works Plan prepared
based on the approved Design Plan under Condition 2.20 of this Permit. The Works Plan shall provide details for
implementing the interfacing works including all demolition, relocation,
reprovision and modification works of the existing landfill restoration
facilities and shall include but not limited to the following information:
(i)
Works areas;
(ii)
Construction phasing;
(iii)
Number of operatives;
(iv)
Experience and special skills of operatives;
(v)
Supervisors responsibilities;
(vi)
Plant and equipment;
(vii)
Method statement, procedures and sequencing of the
works;
(viii)
Measures to address the interfacing issues and to
avoid any impacts to the existing operations of the landfill;
(ix)
Emergency procedures, including fire fighting;
(x)
Storage and use of safety equipment;
(xi)
Proposed landfill gas monitoring requirements;
(xii)
Safety precaution; and
(xiii)
Signs, barriers and guarding.
The Works Plan shall be prepared in consultation
with the Shuen Wan Landfill Restoration Contractor. The Works Plan shall be prepared by the
Specialist Contractor, certified by the ET Leader, verified by the Independent
Landfill Consultant, and then verified by the IEC for approval by the
Director. All works and measures described in the
approved Works Plan shall be fully implemented during construction phase of the Project.
Submission of Updated Construction Phase Landfill
Gas Hazard Assessment
2.22
The Permit Holder shall, at least three months before the commencement
of construction of the Project, submit to the Director for approval four hard
copies and one electronic copy of an Updated Construction Phase Landfill Gas
Hazard Assessment (Updated CPLFGHA), which shall include a review of the
qualitative landfill gas hazard assessment in the approved EIA report (Register
No. AEIAR-221/2019), preparation of a detailed and updated qualitative landfill
gas hazard assessment and associated mitigation measures related to the
interfacing and modification works of the existing landfill restoration
facilities, preparation of detailed design of gas protection measures and the
establishment of maintenance and monitoring programmes to ensure the continued
performance of the proposed control measures for construction phase of the
Project. The Updated CPLFGHA shall
take into account the recommendations of the approved Design Plan and the
approved Works Plan in Conditions 2.20 and 2.21 of this Permit respectively. The Updated CPLFGHA shall
be certified by ET Leader and verified by the IEC as conforming to the findings
and recommendations of the approved EIA Report (Register No. AEIAR-221/2019) for
approval of the Director. All recommendations in the
approved Updated CPLFGHA shall be fully implemented during construction phase of the Project.
Submission of Landscape and Visual Mitigation
Plan
2.23
The Permit Holder shall, no later than one month before the
commencement of construction of the Project or otherwise approved by the
Director, submit 5 hard copies and 1 electronic copy of a Landscape and Visual
Mitigation Plan (LVMP) to the Director for approval. The LVMP shall be prepared making reference to the
conceptual layout plan in Figure 1
of this Permit, and based
on the approved Tree Preservation, Transplantation and Compensation Plan under Condition
2.14 of this Permit and shall include details of tree treatment proposal, implementation
programme, maintenance and management schedules, and drawings in an appropriate
scale of the required landscape and visual mitigation measures, including
lighting design to avoid glare impact, for the Project. Before submission to the Director, the
LVMP shall be prepared by the Registered Landscape Architect, certified by the
ET Leader, and verified by the IEC as conforming to the relevant information
and recommendations on landscape and visual mitigation measures contained in
the approved EIA report (Register No. AEIAR-221/2019) or otherwise approved by
the Director. All recommendations
in the approved LVMP shall be fully implemented and maintained during construction and
operation phases of the Project.
Submissions
or Measures to be Implemented during Construction of
the Project
Submission
of As-built Drawings of Modification Works of Existing Landfill Restoration Facilities
2.24
The Permit Holder shall deposit 4 hard copies and 1
electronic copy of the as-built drawings of the modification works of existing
landfill restoration facilities carried out under the approved Works Plan under
Condition 2.21 of this Permit to the Director no later than two months before
commencement of operation of the Project.
The drawings shall be prepared by the Specialist Contractor, certified
by the ET Leader and verified by Independent Landfill Consultant and then
verified by the IEC before submission to the Director.
Submission of Updated Operation Phase Landfill
Gas Hazard Assessment
2.25
The Permit Holder shall, at least one month before the commencement of
operation of the Project, submit to the Director for approval four hard copies
and one electronic copy of an Updated Operation Phase Landfill Gas Hazard
Assessment (Updated OPLFGHA), which shall include a review of the qualitative landfill
gas hazard assessment in the approved EIA report (Register No. AEIAR-221/2019),
preparation of a detailed and updated qualitative landfill gas hazard assessment
and the establishment of maintenance and monitoring programmes
to ensure the continued performance of the proposed control measures for
operation phase of the Project. The
Updated OPLFGHA shall take into account the recommendations of the approved
Design Plan, the approved Works Plan and as-built drawings of modification
works of existing landfill restoration facilities under in Conditions 2.20, 2.21
and 2.24 of this Permit respectively.
The
Updated OPLFGHA shall be certified by ET Leader and verified by the IEC as
conforming to the findings and recommendations of the approved EIA Report
(Register No. AEIAR-221/2019) for approval by the Director. All recommendations in the approved Updated
OPLFGHA shall be fully implemented and maintained during operation phase of the Project.
Submission of Turfgrass Management Plan
2.26
The Permit Holder shall, at least three months
before commencement of laying of turfgrass of the
Project, submit 6 hard copies and 1 electronic copy of a Turfgrass Management
Plan (TMP) to the Director for approval.
The TMP shall make reference to the agrochemicals application rates and
application area as assumed in the approved EIA Report (Register No.
AEIAR-221/2019) and shown in Annex 2 of this Permit, and include
information on the turfgrass species, usage of agrochemicals, management
methodology, as well as worst-case assessments on the water quality impacts
resulting from landfill leachate and the possible discharge from the Project
into Tolo Harbour. The TMP shall be
certified by the ET Leader and verified by the IEC as conforming to the
findings and recommendations of the approved EIA Report (Register No.
AEIAR-221/2019) for approval by the Director. All details and measures recommended in
the approved TMP shall be fully implemented and maintained during construction
and operation phases of the Project.
Submission
of Noise Mitigation Plan
2.27
The
Permit Holder shall, no later than two months before the commencement of
operation of the Project, submit 4 hard copies and 1 electronic copy of a Noise
Mitigation Plan (NMP) to the Director for approval. The NMP shall include Commissioning Test Report
to confirm the compliance with the maximum sound power levels for all plants
and equipment considered in the approved EIA Report (Register No.
AEIAR-221/2019), including golf course machinery such as tractors, mowers and aerators. The NMP shall be
certified by the ET Leader and verified by the IEC as conforming to the findings
and recommendations of the approved EIA Report (Register No. AEIAR-221/2019) for
approval by the Director. All recommendations in the approved NMP shall be
fully implemented and maintained during operation phase of the Project.
Implementation
of Construction Phasing Plan
2.28
The phasing of construction activities recommended
in the approved Construction Phasing Plan under Condition 2.15 of this Permit
shall be fully implemented during construction phase of the Project.
Measures for Mitigation of Construction Dust Impact
2.29
All measures recommended in the approved
Construction Dust Management Plan under Condition 2.17 of this Permit shall be
fully implemented during construction phase of the Project.
Measures for Mitigation of the Impact on Night Roosting of Collared Crow
and Black Kite during Construction
2.30
The restriction on operation hours of PME detailed
in Annex 1 of this Permit in the Restriction Zones detailed in Figure 2 of this Permit or as stated
in the approved Powered Mechanical Equipment Restriction Zones Review under
Condition 2.18 of this Permit shall be fully implemented during construction
phase of the Project.
2.31
No felling of trees shall be carried out in the Project Site during
construction phase prior to the approval of Tree Preservation, Transplantation
and Compensation Plan under Condition 2.14 of this Permit.
2.32
No felling or pruning of trees in core roosting area
as shown in Figure 1 at any
time during construction phase of the Project, except for those recommended in
the approved Tree
Preservation, Transplantation and Compensation Plan under Condition 2.14 of
this Permit.
2.33
All recommendations in the approved Tree Preservation, Transplantation
and Compensation Plan under Condition 2.14 of this Permit shall be fully
implemented and maintained during construction phase of the Project.
Measures to Minimise Impact on Restored Landfill during Construction
2.34
No
excavation on the existing landfill and no modification,
relocation, reprovision or demolition of landfill restoration facilities shall
be allowed during
construction phase of the Project other
than those stated in the approved Design Plan and Works Plan under Conditions 2.20
and 2.21 of this Permit.
Measures to Minimise Landfill Gas Hazards during
Construction
2.35
All measures, maintenance and monitoring programmes
detailed in the approved Updated Construction Phase Landfill Gas Hazard Assessment under Condition 2.22 of
this Permit shall be fully implemented and maintained during construction phase
of the Project.
2.36
No smoking and no naked flame shall be allowed
within the Project Site during construction phase of the Project.
Measures to Minimise Marine Water Quality Impact
during Construction
2.37
All measures recommended in the approved
Construction Phase Water Quality Mitigation Measures and Monitoring Plan under
Condition 2.16 of this Permit shall be fully implemented during construction
phase of the Project.
2.38
No marine works, including modification of the
existing seawall, marine dredging works on existing seabed, and use of
construction barges, shall be allowed during construction phase of the Project.
2.39
Underground storage tank(s) with a total capacity of
not less than 30,000 m3 shall be constructed before commencement of
operation of the Project for collection of surface runoff at the Project Site
during operation phase of the Project.
2.40
Underground storage tank(s) shall be constructed
prior to the construction of access road in each of the construction phases to
collect surface runoff for sedimentation.
Measures to Minimise Hazard to Life due to
Dangerous Goods during Construction
2.41
No more
than 50 construction workers shall be allowed within the Project Site area that
falls within the consultation zone of Tai Po Gas Production Plant as shown in Figure 4 of this Permit during construction phase of the Project.
Measures against Potential Land Contamination Impact
2.42
No construction work at the existing storage/
workshop area as shown in Figure 3
of this Permit shall be commenced before the approval of Land Contamination Review
under Condition 2.19 of this Permit if no site investigation (SI) is required, before
approval of Contamination Assessment Report if SI is required but no
remediation is required, or before the approval of the Remediation Report under
Condition 2.19 of this Permit if remediation is required.
Measures to be
Implemented during Operation of the Project
Operation
Hours
2.43
The operation hours of the outdoor golf playing area
shall be restricted to 07:00 to 18:00 between the months of March and August
inclusive.
2.44
The operation hours of the outdoor golf playing area
shall be restricted to 07:00 to 17:00 between the months of September and
February inclusive.
2.45
The operation hours of the outdoor driving range
shall be restricted to 07:00 to 22:00 throughout
the year.
Measures to
Minimise Water Quality Impact during Operation
2.46
Underground storage tanks with a total capacity of
not less than 30,000 m3 shall be properly maintained during
operation phase of the Project for collection of surface runoff at the Project
Site. All surface runoff and water
collected in the drainage system shall be stored in the underground storage
tanks for re-use on-site, unless when the storage tank(s) are full, upon which
time the surface runoff and water collected in the drainage system may bypass
the underground storage tanks and, after passing through the requisite grease
traps and silt traps, and flow into Tolo Harbour. Such bypass into Tolo Harbour shall
cease once the water storage tanks system has recovered its storage capacity.
2.47
All sewage from toilets shall be discharged to the
public sewerage system.
Measures to Minimise Hazard to Life due to
Dangerous Goods during Operation
2.48
No
permanent working or residential population shall be allowed within the Project
Site area that falls within the consultation zone of Tai Po Gas Production
Plant as shown in Figure 4 of this Permit during
operation phase of the Project.
2.49
No more
than 20 transient workers and 20 transient visitors shall be allowed at any
time within the Project Site area that falls within the consultation zone of
Tai Po Gas Production Plant as shown in Figure
4 of this Permit during
operation phase of the Project.
Measures for Mitigation of the Impact on Night Roosting of Collared Crow
and Black Kite during
Operation
2.50
No felling or pruning of trees in core roosting area
as shown in Figure 1 at any
time during operation phase of the Project, except for those recommended in the
approved Tree
Preservation, Transplantation and Compensation Plan under Condition 2.14 of
this Permit.
2.51
All recommendations in the approved Tree Preservation, Transplantation
and Compensation Plan under Condition 2.14 of this Permit shall be fully
maintained during operation phase of the Project.
2.52
All lightings installed at the Project Site, in particular those at the
driving range, shall be directed away from the core roosting area as shown in Figure 1 of this Permit to minimise glare
impact on the night roosting of Collared Crow and Black Kite during operation
phase of the Project.
Measures to Minimise Impact on Restored Landfill during Operation
2.53
No
excavation on the existing landfill and no modification,
relocation, reprovision or demolition of landfill restoration facilities shall
be allowed during operation phase of the Project, unless otherwise approved by
the Director.
Measures for Mitigation of Landfill Gas Hazard during Operation
2.54
All measures, maintenance and monitoring programmes detailed in the
approved Updated OPLFGHA under Condition 2.25 of this Permit shall be fully
implemented and maintained during operation phase of the Project.
2.55
No smoking and no naked flame shall be allowed
within the Project Site during operation phase of the Project.
Measures
for Landscape and Visual
Impacts during Operation
2.56
All recommendations in the approved Landscape and Visual Mitigation
Plan under Condition 2.23 of this Permit shall be fully implemented and maintained
during operation
phase of the Project.
Implementation of Turfgrass Management Plan during
Operation
2.57
All recommendations in the approved Turfgrass Management
Plan under Condition 2.26 of this Permit shall be fully implemented and
maintained during operation phase of the Project.
Measures to Minimise Noise Impact during Operation
2.58
All recommendations in the approved Noise Mitigation
Plan under Condition 2.27 of this Permit shall be fully implemented and
maintained during operation phase of the Project.
3.
Environmental Monitoring and
Audit (EM&A) Requirements
3.1
The Permit Holder shall
implement the EM&A programme in accordance with the procedures and requirements
as set out in the EM&A Manual. Any
major changes to the programme shall be justified by the ET leader and verified
by the IEC as conforming to the requirements set out in the EM&A Manual,
and shall seek the prior approval from the Director before implementation.
3.2
The EM&A programme shall include a 1-year period of water quality
impact monitoring during operation phase as detailed in the EM&A Manual,
and Annex 3 and Figure 5 of this Permit. The Permit Holder shall, no later than
two months before the end of the monitoring period, submit a Review Report on the
need, if any, of extending the operation phase water quality monitoring
programme with full justifications.
The Review Report shall be certified by
the ET leader and verified by the IEC for the approval by the Director. Details of the extended operation phase water quality monitoring programme in the
approved Review Report shall be fully implemented.
3.3
The
Permit Holder shall take samples, measurements and
necessary remedial actions in accordance with the requirements of the EM&A
Manual by:
(i)
conducting baseline
environmental monitoring;
(ii)
conducting impact
monitoring;
(iii)
carrying out remedial
actions described in the Event/Action Plans of the EM&A Manual in
accordance with the time frame set out in the Event/Action Plans, or as agreed
by the Director, in case where specified criteria in the EM&A Manual are
exceeded; and
(iv)
logging and keeping records of the details of (i) to (iii) above for all
parameters within 3 working days of the collection of data or completion of
remedial action(s), for the purpose of preparing and submitting the monthly
EM&A Reports and to make available the information for inspection on site.
3.4
The
Permit Holder shall submit 4 hard copies and 1
electronic copy of relevant Baseline Monitoring Report(s) to the Director at least one month before the commencement of
construction of the Project. The
submission(s) shall be certified by the ET Leader and verified by the IEC as
having complied with the requirements as set out in the EM&A Manual before
submission to the Director. Additional
copies of the Baseline Monitoring Report(s) shall be provided upon
request by the Director.
3.5
The
Permit Holder shall submit 1 hard copy and 1 electronic copy of Monthly
EM&A Reports for the construction and operation phases of the Project to
the Director, within 2 weeks after the end of the reporting month. The monthly EM&A Reports shall
include an executive summary of all environmental audit results, together with
actions taken in the event of non-compliance (exceedances) of the environmental
quality performance limits (Action and Limit Levels), complaints received and
emergency events relating to violation of environmental legislation (such as
illegal dumping). The submissions
shall be certified by the ET Leader and verified by the IEC as having complied
with the requirements as set out in the EM&A Manual before submission to
the Director. Additional copies of
the Monthly EM&A Reports shall be provided upon request by the Director.
3.6
All
environmental monitoring and audit data submitted under this Permit shall be
true, valid and correct.
4.
Electronic Reporting of EM&A
Information
4.1
To facilitate public
inspection of the Baseline Monitoring Report(s) and Monthly EM&A Reports
via the EIAO Internet Website and at the EIAO Register Office, electronic
copies of these Reports shall be prepared in Hyper Text Markup Language (HTML)
(version 4.0 or later) and in Portable Document Format (PDF version 1.3 or
later), unless otherwise agreed by the Director and shall be submitted at the
same time as the hard copies as described in Conditions 3.4 and 3.5 above. For the HTML version, a content page
capable of providing hyperlink to each section and sub-section of these Reports
shall be included in the beginning of the document. Hyperlinks to all figures, drawings and
tables in these Reports shall be provided in the main text from where the
respective references are made. All
graphics in these Reports shall be in interlaced GIF, JPEG or PDF format unless
otherwise agreed by the Director. The
content of the electronic copies of these Reports must be the same as the hard
copies
4.2
The Permit Holder shall,
within 6 weeks after the commencement of construction of the Project, set up a
dedicated Internet website and notify the Director in writing the Internet
address where the environmental monitoring data and project information is to
be placed. All environmental
monitoring data described in Condition 4.1 above shall be made available to the
public via the abovementioned dedicated Internet website in the shortest
possible time and in any event no later than 2 weeks after the relevant
environmental monitoring data are collected or become available, unless
otherwise agreed with the Director.
All finalised
submissions and plans required in this Permit shall be made available to the
public via the dedicated Internet website in the shortest possible time and in
any event no later than 2 weeks after the submissions and plans are approved by
or deposited with the Director, unless otherwise agreed with the Director. The Permit Holder shall maintain the dedicated website for public access
of the environmental monitoring data, reports and finalised submissions and
plans throughout the entire construction period and during the first 3-year
period after commencement of operation of the Project, or otherwise as agreed
by the Director.
4.3
The Internet website as
described in Condition 4.2 above shall enable user-friendly public access to
the environmental monitoring data and project information including the Project
Profile, EIA Report, environmental permit(s) and finalised submissions and
plans required under this Permit. Unless
otherwise agreed by the Director, the Internet website shall have features
capable of:
(i)
providing access to all environmental
monitoring data of this Project collected
since the commencement of construction;
(ii)
providing access to all finalised submissions as
required under this Permit;
(iii)
searching by date;
(iv)
searching
by types of monitoring data; and
(v)
hyperlinking to relevant monitoring data after searching.
Notes:
1.
This Permit consists of three
parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions). Any person relying on this permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
2.
If there is a breach of any
condition of this Permit, the Director or his authorised officer may, with the
consent of the Secretary for the Environment,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit
Holder shall not carry out any associated works without the permission of the
Director or his authorised officer.
3.
The Permit Holder may apply under
Section 13 of the EIAO to the Director for a variation of the conditions of
this Permit. The Permit Holder
shall replace the original permit displayed on the Project site by the amended
permit.
4.
A person who assumes the
responsibility for the whole or a part of the Project may, before he assumes
responsibility of the Project, apply under Section 12 of the EIAO to the
Director for a further environmental permit.
5.
Under Section 14 of the EIAO, the
Director may with the consent of the Secretary
for the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site.
6.
If this Permit is cancelled or
surrendered during construction or operation of the Project, another
environmental permit must be obtained under the EIAO before the Project could
be continued. It is an offence
under Section 26(1) of the EIAO to construct or operate a designated project
listed in Part I of Schedule 2 of the EIAO without a
valid environmental permit.
7.
Any person who constructs or
operates the Project contrary to the conditions in the Permit, and is convicted
of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment
to a fine of $2 million and to
imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2
years;
(iii)
on a first summary conviction to a
fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in
any case where the offence is of a continuing nature, the court or magistrate
may impose a fine of $10,000 for each day on which he is satisfied the offence
continued.
8.
The Permit Holder may appeal
against any condition of this Permit under Section 17 of the EIAO within 30
days of receipt of this Permit.
9.
The
Notes are for general reference only and that the Permit Holder should refer to
the EIAO for details and seek independent legal advice.
Environmental
Permit No. EP-571/2019
環境許可證編號 EP-571/2019
| Figure 1 | Figure 2 | Figure 3 | Figure 4 | Figure 5 |
[ Back to First Page ] / [ Back to Main Index ]
Annex 1 Restriction Hours for Powered
Mechanical Equipment within Restriction Zones
Month |
Restriction Hours for Powered Mechanical
Equipment to be stopped within Restriction Zones (starting time until 07:00 of the
following day) |
January |
16:30 |
February |
17:00 |
March |
17:30 |
April |
17:30 |
May |
17:30 |
June |
18:00 |
July |
18:00 |
August |
17:30 |
September |
17:00 |
October |
16:30 |
November |
16:30 |
December |
16:30 |
[This
annex was prepared based on Table 10.9.1 of the approved EIA Report (Register
No.: AEIAR-221/2019)]
Annex 2 Application Rates and Area of
Agrochemicals
Proposed
agrochemicals and corresponding application area
Agrochemicals [1] |
Turf[3] |
|||
Green |
Tee |
Fairway |
Rough |
|
Fungicides [4][5] |
||||
Daconil |
✓ |
✓ |
✓ |
✓ |
Bayleton |
✓ |
✓ |
✓ |
✓ |
Herbicides [4] |
||||
Monosodium Methanearsonate (MSMA) |
✓ |
✓ |
✓ |
✓ |
Roundup/ Glyphosate |
|
|
[2] |
[2] |
Monument |
✓ |
✓ |
✓ |
✓ |
Ronstar
(Pre-emergence) |
✓ |
✓ |
✓ |
✓ |
Insecticides [5] |
||||
Chlorpyrifos |
✓ |
✓ |
✓ |
✓ |
Fipronil |
✓ |
✓ |
✓ |
✓ |
Fertilizers |
||||
Anderson 18-9-18 |
✓ |
✓ |
|
|
Gypsum/ Dolomite |
✓ |
✓ |
✓ |
✓ |
Ferrous Sulfate |
✓ |
✓ |
✓ |
✓ |
Nitrophoska
12:12:17:2 |
|
✓ |
✓ |
✓ |
Notes:
[1]
The
selection of agrochemicals shall be reviewed by the Permit Holder and stated in
Turfgrass Management Plan under Condition 2.26 of this
Permit.
[2]
Spot
spray, hence the application area is not fixed.
[3]
Percentage
of green: 3%, tee:2%, fairway: 35% and rough: 60%.
[4]
The use
of salt water will also be explored as fungi control or weed control.
[5]
Fungicides/
insecticides will be applied to at most one of the golf course parts Green,
Tee, Fairway or Rough at a time. The use of fungicides/ insecticides in Fairway
may be sub-divided into multiple times according to the turfgrass
species and it is anticipated that fungicides/ insecticides will seldom be used
in Rough.
Application rates of agrochemicals
Agrochemicals |
Application Rate in Each Application (kg/ha) |
Application Frequency |
Fungicides |
||
Daconil |
8.2 |
Weekly |
Bayleton |
3.0 |
Biweekly |
Herbicides |
||
Monosodium Methanearsonate (MSMA) |
[1] |
[4] |
Roundup/ Glyphosate |
[2] |
[4] |
Monument |
[1] |
[4] |
Ronstar |
[1] |
[4] |
Insecticides |
||
Chlorpyrifos |
3.0 |
[5] |
Fipronil |
0.014 |
Annually |
Fertilizers |
||
Anderson 18-9-18 |
54.3 |
Monthly |
Gypsum/ Dolomite |
Soil pH
dependent |
Monthly |
Ferrous Sulfate |
[3] |
Monthly |
Nitrophoska
12:12:17:2 |
100.0 |
Monthly |
Notes:
[1] Rate of application dependent on: (a) target weeds,
(b) turfgrass mix with types of weed, and (c) product
type.
[2]
Spot
spray, strength dependent on target weeds and their stage of growth.
[3]
Rate
dependent on turf grass species and their acceptable level of injury symptoms.
[4]
Herbicides
will only be applied, when needed.
[5]
Apply
when pests appear.
[This
annex was prepared based on Tables 2.8 and 2.9 of the approved EIA Report
(Register No.: AEIAR-221/2019)]
Annex 3 Water Quality Monitoring Programme
for Impact Monitoring during Operation Phase
Item |
Details |
||||||||||||||||||||||||
Monitoring
Period |
First year of the operation phase. The Permit Holder shall, no
later than two months before the end of the monitoring period, submit a
Review Report on the need, if any, of extending the operation phase water
quality monitoring programme with full
justifications under Condition 3.2 of this Permit. |
||||||||||||||||||||||||
Monitoring
Frequency |
Bi-weekly |
||||||||||||||||||||||||
Monitoring
Locations |
The location of the monitoring
stations are shown in Figure 5 of this Permit. |
||||||||||||||||||||||||
Monitoring
Parameters |
The
monitoring parameters shall be based on the approved Turfgrass
Management Plan under Condition 2.26 of this Permit, and should include Total
inorganic nitrogen (TIN), total phosphorus (TP), specific fungicide (e.g. chlorothalonil (active ingredient of Daconil))
and specific insecticide (e.g. chlorpyrifos). |
[This
annex was prepared based on EM&A Manual Tables 7.6
and 7.7 of the approved EIA Report (Register No.: AEIAR-221/2019)]