Environmental Permit No. EP-578/2020
環境許可證編號EP-578/2020

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

SECTION 10

環境影響評估條例

(499)

10

 

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE

A DESIGNATED PROJECT

建造及營辦指定工程項目的環境許可證

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to the Drainage Services Department (hereinafter referred to as the “Permit Holder”) to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:

根據《環境影響評估條例》(環評條例) 10條的規定,環境保護署長(署長)將本環境許可證批予渠務 (下稱許可證持有人”) 以建造及營辦B 所說明的指定工程項目,但須遵守C 所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據

 

Application No.

申請書編號

AEP-578/2020

Document in the Register:

登記冊上的文件:

 

(1)   Improvement of Yuen Long Town Nullah (Town Centre Section) (Register No. AEIAR-223/2020) :

-   Environmental Impact Assessment (EIA) Report  [Hereafter referred to as the EIA Report]

-   Environmental Monitoring and Audit (EM&A) Manual [Hereafter referred to as the EM&A Manual”]

-   Executive Summary

 

元朗市明渠改善工程(市區中心段) (登記編號AEIAR-223/2020):

-   環境影響評估報告 [下稱環評報告”]

-   環境監察及審核手冊  [下稱環監手冊”]

-   行政摘要

 

(2) The Director’s letter of approval of the EIA Report dated 31 July 2020 (Reference : Ax(1) to EP2/N6/F/155)

署長於2020731 發出批准環評報告的信件 (檔案編號:Ax(1) to EP2/N6/F/155)

 

(3) Application for Environmental Permit submitted on 20 August 2020 (Application No. AEP-578/2020)

2020820 提交的環境許可證申請文件 (申請書編: AEP-578/2020)

 

 

 

 

 

 

17 September 2020

          20209 17

Date

日期

 

(LAU Chi Fai, Stanley)

Acting Principal Environmental Protection Officer

for Director of Environmental Protection

環境保護署長

(署理首席環境保護主任 劉志輝 代行)


PART B (DESCRIPTION OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):

下列為本環境許可證 (下稱許可證”) A 所提指定工程項目的說明

 

Title of Designated Project

指定工程項目的名稱

Improvement of Yuen Long Town Nullah (Town Centre Section)

[This designated project is hereafter referred to as “the Project”]

 

元朗市明渠改善工程 (市區中心段)

[本指定工程項目下稱 工程項目”]

 

Nature of Designated Project
指定工程項目的性質

(1) Construction of a dry weather flow pumping station with an installed capacity of more than 2,000 m3 per day and a boundary which is less than 150 m from existing residential areas.

(2) Construction of dry weather flow interceptors which discharge into an area which is less than 300m from the nearest boundary of sites of special scientific interest and conservation area.

 

(1) 建造一個旱季污水泵水站,而其裝置的泵水能力超過每天2,000立方米,且其一條界線距離一個現有的住宅區的最近界線少於150米。

(2) 建造旱季截流裝置,而該工程排水入一個地區,該地區距離現有的具有特別科學價值的地點及自然保育區的最近界線少於300 米。

 

Location of Designated Project

指定工程項目的地點

The Project is located at Yuen Long Town Nullah (Town Centre Section). The location of the Project is shown in Figure 1 of this Permit

 

工程項目位於元朗市明渠(市區中心段)工程項目的位置載於本許可證1

 

Scale and Scope of Designated Project

指定工程項目的規模和範圍

 

The Project includes:

 

-             Construction of dry weather flow interceptors along and within the Yuen Long Town Nullah;

 

-             Construction of continuous u-channels adjacent to either side of the retaining walls;

 

-             Construction of a dry weather flow pumping station with capacity of 18,000 m3/day; and

 

-             Laying twin rising mains of approximately 400m long to convey the intercepted dry weather flow to the Yuen Long Effluent Polishing Plant (upgraded from the existing Yuen Long Sewage Treatment Works).

 

工程項目包括:

 

-             沿元朗市明渠內建造旱季污水截流系統;

 

-             於元朗市明渠兩側的擋土牆附近興建U 形截流管道;

 

-         建造一個每日18,000 立方米處理能力的旱季污水泵房;以及

 

-         鋪設兩條約400 米長的壓力管道,將截獲的旱季流輸送到元朗淨水設施(將由現有的元朗污水處理廠升級而成)。

 


PART C (PERMIT CONDITIONS)

 

GENERAL CONDITIONS

           

1.1       The Permit Holder and any person constructing or operating the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of appropriate action being taken under the EIAO.

 

1.2       The Permit Holder and any person constructing or operating the Project shall ensure full compliance with all legislation from time to time in force including, without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.

 

1.3       The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of this Permit readily available at all times for inspection by the Director or his authorised officers at all sites covered by this Permit. Any reference to this Permit shall include all documents referred to in this Permit and also the relevant documents in the Register.

 

1.4       The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated in this Permit. The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.

 

1.5       The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public’s information at all times. The Permit Holder shall ensure that the most updated information about this Permit, including any amended Permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of this Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6       The Permit Holder and any person constructing or operating the Project shall construct and operate the Project in accordance with the project description in Part B of this Permit.

 

1.7       The Permit Holder and any person constructing or operating the Project shall ensure that the Project is designed, constructed and operated in accordance with the information and recommendations described in the approved EIA Report (Register No.: AEIAR-223/2020); the application documents for environmental permits; other relevant document in the Register; the information and mitigation measures described in this Permit; mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on-going surveillance and monitoring activities during all stages of the Project.  Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded in this Permit or otherwise agreed by the Director.

  

1.8       All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise as specified by the Director.

 

1.9       All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the EIAO (Cap. 499). All submissions or any variation of submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below before submitting to the Director under this Permit.

 

1.10     The Permit Holder shall release all finalised submissions as required under this Permit to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any means as specified by the Director, for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11     The Permit Holder shall submit and / or deposit all submissions within the time as specified in the Conditions of this Permit. All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalised submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

 

1.12     The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than 2 months prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

 

1.13     For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.

 

 

SPECIFIC CONDITIONS

           

2.                  Employment or Submissions before Construction of the Project

 

Employment of Environmental Team (ET)

 

2.1              An ET shall be established by the Permit Holder no later than 3 months before the commencement of construction of the Project.  The ET shall not be in any way an associated body of the Contractor or the Independent Environmental Checker (IEC) for the Project.  The ET shall be headed by an ET Leader and supported by relevant specialists including Registered Landscape Architect who forms part of the ET to carry out works relating to landscape aspects including but not limited to auditing the mitigation measures to ensure compliance with the recommendations of the approved EIA Report (Register No. AEIAR-223/2020) and to certify submissions for the Project as required under Condition 2.6. The ET Leader shall be a person who has at least 7 years of experience in environmental monitoring and auditing (EM&A) or environmental management.  The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual of the Project.  The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances, which may affect the compliance with the recommendations of the EIA Report (Register No: AEIAR-223/2020) and this Permit.  The ET Leader shall notify the IEC within one working day of the occurrence of any such instance or circumstance or change of circumstances.  The ET Leader’s log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the recommendations of the EIA Report (Register No.: AEIAR-223/2020) and this Permit or by the Director or his authorized officers.  Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader.  Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render this Permit liable to suspension, cancellation or variation.

 

Employment of Independent Environmental Checker (IEC)

 

2.2              An Independent Environmental Checker (IEC) shall be employed by the Permit Holder no later than 3 months before the commencement of construction of the Project.  The IEC shall not be in any way an associated body of the Contractor or the ET for the Project.  The IEC shall be a person who has at least 7 years of experience in EM&A or environmental management.  The IEC shall be responsible for duties defined in the EM&A Manual and shall audit the overall EM&A performance, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit.  In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit.  The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit.  The IEC shall notify the Director by fax or email, within one working day of receipt of notification from the ET Leader of each and every change of circumstances or non-compliance with the recommendations of the EIA Report (Register No.: AEIAR-223/2020) and this Permit, which might affect the monitoring or control of adverse environmental impacts from the Project.  In case the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined in the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC.  Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation.  Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition.

 

Submission of Environmental Permit (EP) Submission Schedule

 

2.3              The Permit Holder shall, no later than 1 month before the commencement of construction of the Project, submit the EP Submission Schedule for fulfilling the submission requirements as contained in this Permit and shall report the progress in fulfilling the submission requirements in the monthly Environmental Monitoring and Audit (EM&A) reports submitted under Condition 6.4 of this Permit.  The Permit Holder shall inform the Director no later than 2 weeks before the scheduled submission date of the EP submission in writing in case of any subsequent change(s) to the submitted EP Submission Schedule.  The EP Submission Schedule or any subsequent change(s) to the EP Submission Schedule shall be certified by the ET Leader and verified by the IEC before submitting to the Director under this Permit.

 

Submission of Management Organisation

 

2.4              The Permit Holder shall, no later than 1 month before the commencement of construction of the Project, inform the Director in writing the management organisation of the main construction companies and / or any form of joint ventures appointed for the Project. The information shall include at least an organisation chart, names of responsible persons and their contact details.

 

Submission of Updated Environmental Monitoring and Audit (EM&A) Manual

 

2.5              The Permit Holder shall update the EM&A Manual to include the latest EM&A requirements in accordance with the information and recommendations described in the EIA Report (Register No. AEIAR-223/2020) and by taking into account any specific site conditions that may be changed before construction of the Project. The Permit Holder shall, no later than 2 months before the commencement of construction of the Project, submit 4 hard copies and 1 electronic copy of an updated EM&A Manual to the Director for approval. The updated EM&A Manual shall include but not limited to:

 

(i)             a water quality monitoring plan (WQMP) to detect potential adverse water quality impacts at the Project and downstream area directly affected by the construction of the Project.  With reference to the excavation works in the nullah as mentioned in Condition 3.1 of this Permit, the WQMP shall include details of the monitoring locations, monitoring frequency, parameters to be monitored, and additional measures to be taken in the event of heavy rainfall during dry season to ensure that the water quality is not adversely affected; and

 

(ii)           an Event/Action Plan for water quality monitoring.

 

The updated EM&A Manual shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations of the EIA Report (Register No. AEIAR-223/2020), and taking into account any specific requirements with respect to the latest site conditions of the Project. All measures recommended in the updated EM&A Manual approved under this Condition shall be fully and properly implemented in accordance with the requirements and time schedule(s) set out in the updated EM&A Manual. The EM&A Manual approved under this Condition shall hereinafter be referred to as the “updated EM&A Manual”.

 

Submission of Landscape and Visual Mitigation Plan

 

2.6       The Permit Holder shall, no later than 1 month before the commencement of construction of the Project or otherwise approved by the Director, deposit with the Director 4 hard copies and 1 electronic copy of a Landscape and Visual Mitigation Plan (LVMP).  The LVMP shall include design details, recommendations of landscape and visual mitigation measures, implementation programme, maintenance and management schedules, and drawings in the scale of 1:1,000 or other appropriate scale, as agreed with the Director, of the landscape and visual mitigation measures.  The LVMP shall include an implementation schedule in table form to clearly list out the mitigation measures to be implemented, and the implementation party, location, timing and environmental performance required for implementation of the mitigation measures.  If there are any change(s) to the landscape and visual mitigation measures in the approved LVMP, the Permit Holder shall, no later than 1 month before the implementation of such change(s), submit 4 hard copies and 1 electronic copy of the Updated LVMP with clear indication of the proposed change(s). Before submission to the Director, the LVMP or any Updated LVMP shall be certified by the Registered Landscape Architect employed under Condition 2.1 and the ET Leader, and verified by the IEC as conforming to the relevant information and recommendations on landscape and visual mitigation measures contained in the approved EIA report (Register No. AEIAR-223/2020), or otherwise approved by the Director. All landscape and visual mitigation measures recommended in the LVMP or any Updated LVMP shall be fully implemented. The Permit Holder shall make available additional copies of the LVMP or any Updated LVMP to the Director upon request.

 

3.                  Measures during Construction of the Project

 

Measures to Mitigate Water Quality Impacts

 

3.1              Excavation works in the nullah shall only be carried out during dry season, i.e. from November to March of the next year, unless otherwise agreed by the Director.

 

Measures to Mitigate Ecological Impacts

 

3.2              To minimize disturbance to wetland habitats within Wetland Buffer Area and Wetland Conservation Area as well as associated overwintering waterbirds and wetland-dependent species, the construction works for the rising main shall only be carried out outside dry season, i.e. from November to March of the next year, unless otherwise agreed by the Director.

 

 

4.                  Submissions before Commencement of Operation of the Project

 

Submission of Operation Phase Emergency Response Plan(s)

 

4.1              The Permit Holder shall, no later than one month before the commencement of operation of the Project, submit an Operation Phase Emergency Response Plan for approval by the Director. The Emergency Response Plan shall include details on the emergency arrangement in case of breakdown of the dry weather flow interception system.

 

 

5.                  Measures to be Implemented during Operation of the Project

 

Measures to Mitigate Odour Impact

 

5.1               To minimize odour impact during operation of the Project, the following mitigation measures shall be implemented:

 

(i)             the dry weather flow pumping station shall be enclosed inside building structure and maintained with negative pressure; and

 

(ii)           the dry weather flow pumping station shall be equipped with deodorization unit using activated carbon or other equivalent odour removal techniques with an odour removal efficiency of at least 99.5%. The deodorization unit shall be properly and regularly maintained to ensure its effectiveness.

 

 

 

6.                  Environmental Monitoring and Audit (EM&A) Requirements

 

 

6.1              The Permit Holder shall implement the EM&A programme in accordance with the procedures and requirements as set out in the updated EM&A Manual under Condition 2.5 of this Permit. Any changes to the EM&A requirements or programme or termination of the programme shall be justified by the ET Leader and verified by the IEC as conforming to the information and requirements contained in the updated EM&A Manual before submission to the Director for approval.

 

6.2              The Permit Holder shall take samples, measurements and necessary remedial actions in accordance with the requirements of the updated EM&A Manual by:

 

(i)                  conducting baseline environmental monitoring;

 

(ii)                conducting impact monitoring;

 

(iii)               carrying out remedial actions described in the Event/Action Plans of the updated EM&A Manual in accordance with the time frame set out in the Event/Action Plans, or as agreed by the Director, in case where specified criteria in the updated EM&A Manual are exceeded; and

 

(iv)              logging and keeping records of the details of (i) to (iii) above for all parameters within 3 working days of the collection of data or completion of remedial action(s), for the purpose of preparing and submitting the monthly EM&A Reports and to make available the information for inspection on site.

 

6.3              The Permit Holder shall submit 1 hard copy and 1 electronic copy of Baseline Monitoring Report(s) to the Director at least 2 weeks before the commencement of construction of the Project.  The submission(s) shall be certified by the ET Leader and verified by the IEC as having complied with the requirements as set out in the updated EM&A Manual before submission to the Director.  Additional copies of the Baseline Monitoring Report(s) shall be provided upon request by the Director.

 

6.4              The Permit Holder shall submit 1 hard copy and 1 electronic copy of Monthly EM&A Reports to the Director, within 10 working days after the end of the reporting month.  The monthly EM&A Reports shall include an executive summary of all environmental audit results, together with actions taken in the event of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels), complaints received and emergency events relating to violation of environmental legislation.  The submissions shall be certified by the ET Leader and verified by the IEC as having complied with the requirements as set out in the updated EM&A Manual before submission to the Director.  Additional copies of the Monthly EM&A Reports shall be provided upon request by the Director.

 

6.5              All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.

 

6.6              To ensure a high degree of transparency regarding the monitoring data and results in view of the public concern about the Project, all environmental monitoring and audit data and results and all submissions and all performance test data and results required by this Permit shall be made available by the Permit Holder to the public through a dedicated website to be set up by the Permit Holder under Condition 7.2 below, in the shortest practicable time and in no event later than 10 working days after such information is available.

 

 

7.                  Electronic Reporting of EM&A Information

           

7.1       To facilitate public inspection of the Baseline Monitoring Report and Monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Conditions 6.3 and 6.4 above.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made.  All graphics in these Reports shall be in interlaced GIF, JPEG or PDF format unless otherwise agreed by the Director.  The content of the electronic copies of these Reports must be the same as the hard copies.

 

7.2       The Permit Holder shall, within 4 weeks after the commencement of construction of the Project, set up a dedicated Internet website and notify the Director in writing the Internet address where the environmental monitoring data and project information is to be placed.  All environmental monitoring data described in Condition 7.1 above shall be made available to the public via the abovementioned dedicated Internet website in the shortest possible time and in any event no later than 2 weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director.  All finalized submissions and plans shall be made available to the public via the dedicated Internet website in the shortest possible time and in any event no later than 2 weeks after the submissions and plans are approved by or deposited with the Director, unless otherwise agreed with the Director. The Permit Holder shall maintain the dedicated website for public access of the environmental monitoring data and reports throughout the entire construction period and until 2 months after the last EM&A report is uploaded, or otherwise as agreed by the Director.

 

7.3       The Internet website as described in Condition 7.2 above shall enable user-friendly public access to the environmental monitoring data and project information including the Project Profile, EIA Report and Environmental Permit(s).  The Internet website shall have features capable of: 

 

(i)                  providing access to all environmental monitoring data of this Project collected since the commencement of construction;

 

(ii)                searching by date;

 

(iii)               searching by types of monitoring data; and

 

(iv)              hyperlinking to relevant monitoring data after searching

 

or otherwise as agreed by the Director.

 

 

Notes:

 

1.         This Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions).  Any person relying on this Permit should obtain independent legal advice on the legal implications under the EIAO, and the following notes are for general information only.

本許可證共有3部,即 A (許可證主要部分)B (指定工程項目的說明) C (許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。

 

2.         If there is a breach of any condition of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。

 

3.         The Permit Holder may apply under Section 13 of the EIAO to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須經修改的許可證替換在工程項目工地內展示的原有許可證。

 

4.         A person who assumes the responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the EIAO to the Director for a further environmental permit.

承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。

 

5.         Under Section 14 of the EIAO, the Director may with the consent of the Secretary for the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project site.

根據環評條例第14條的規定,署長可在取得環境局局長的同意下暫時吊銷、更改或取消許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。

 

6.         If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the EIAO before the Project could be continued.  It is an offence under Section 26(1) of the EIAO to construct or operate a designated project listed in Part I of Schedule 2 of the EIAO without a valid environmental permit.

如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表21部所列明的指定工程項目,即屬犯罪。

 

7.         Any person who constructs or operates the Project contrary to the conditions in this Permit, and is convicted of an offence under the EIAO, is liable:

 

(i)                  on a first conviction on indictment to a fine of $2 million and to   imprisonment for 6 months;

(ii)                on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;

(iii)               on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.

 

如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪

 

(i)                  一經公訴程序首次定罪,可處罰款200萬元及監禁6個月;

(ii)                一經公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;

(iii)               一經簡易程序首次定罪,可處第6級罰款及監禁6個月;

(iv)              一經簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;

(v)                在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。

 

8.         The Permit Holder may appeal against any condition of this Permit under Section 17 of the EIAO within 30 days of receipt of this Permit.

許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。

 

9.         The Notes are for general reference only and that the Permit Holder should refer to the EIAO for details and seek independent legal advice.