Environmental Permit No. EP-611/2022
環境許可證編號EP-611/2022
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO
CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) grants this environmental permit to the CLP Power Hong Kong Limited (hereinafter referred to as the
“Permit Holder”) to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based
on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予香港中華電力有限公司 (下稱“許可證持有人”) 以建造及營辦B部 所說明的指定工程項目,但須遵守C部 所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據﹕
Application No. 申請書編號 |
|
登記冊上的文件: |
(1)
Project Profile – Installation of Proposed Cable
Route from Cheung Sha to Tung Chung (Register No. PP-641/2022) 工程項目簡介 - 長沙至東涌市之電纜鋪設安裝工程 (登記冊編號 : PP-641/2022) (2) The Director’s
letter of permission to apply directly for environmental permit dated 17 May
2022 (Ref.:
EP 2/N9/D/200) 署長於2022年5月17日發出准許直接申請環境許可證的信件 (檔案編號 : EP 2/N9/D/200) (3) Application for
Environmental Permit submitted on 25 May 2022
(Application No. AEP-611/2022) 於2022年5月25日提交的環境許可證申請 (申請書編號: AEP-611/2022) |
20 June 2022
2022年6月20 日
Date 日期 |
|
(Victor W. T. YEUNG) Principal
Environmental Protection Officer for Director of
Environmental Protection 環境保護署署長 (首席環境保護主任 楊維德 代行) |
PART B (DESCRIPTION OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the
designated project mentioned in Part A of this
environmental permit (hereinafter
referred to as “Permit”):
下列為本環境許可證 (下稱“許可證”) A部 所提述的指定工程項目的說明﹕
Title of Designated Project 指定工程項目的名稱 |
Installation of Proposed Cable Route from Cheung Sha to Tung Chung [This
designated project is hereafter referred to as “the Project”] 長沙至東涌市之電纜鋪設安裝工程 [本指定工程項目下稱“工程項目”] |
Nature of Designated Project |
Earthworks within an existing
country park (Item Q.1, Part I, Schedule 2 of the EIAO). 位於現有郊野公園內的土木工事 (環評條例附表2第 I 部的Q.1項)。 |
Location of Designated Project 指定工程項目的地點 |
The section
of the proposed cable route with earthworks within existing country parks is located along the old Tung Chung Road as shown in Figure 1 of this Permit. 位於現有郊野公園內的電纜鋪設土木工事的部分位於舊東涌道沿線,如本許可證的圖1所示。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
The section of the proposed cable route that falls within
country parks is approximately 3.3 km in length. The proposed cable route
will be installed along existing pavement / road surface through newly constructed trenches/ducts and six new pipe
bridges. 位於郊野公園內的擬建電纜約長3.3 千米。該擬議電纜會沿著現有行人徑/行車路的路面,以新建的纜槽/纜管和六條新建的管道鋪設。 |
C部 (許可證條件)
一般條件
許可證持有人及任何建造或營辦工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例) (第499章) 的規定,而當局可根據環評條例採取適當行動。
1.2 The Permit
Holder and any
person constructing or operating the Project shall ensure full compliance with all legislation from time to time in
force including, without limitation to, the Noise Control Ordinance (Cap. 400),
Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance
(Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance
(Cap. 354). This Permit does not of itself constitute any ground of defence
against any proceedings instituted under any legislation or imply any approval
under any legislation.
許可證持有人及任何建造或營辦工程項目的人士須確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章) 、《空氣污染管制條例》(第311章)、《水污染管制條例》(第358章)、《海上傾倒物料條例》(第466章) 及《廢物處置條例》(第354章)。本許可證本身不會就根據任何法例提出的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 The Permit
Holder shall make copies of this Permit together with all documents referred to
in this Permit and the documents referred to in Part
A of this Permit readily available at all times for inspection by the
Director or his authorised officers at all sites covered by this Permit. Any
reference to this Permit shall include all documents referred to in this Permit
and also the relevant documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部 所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 The Permit
Holder shall give a copy of this Permit to the person(s) in charge of the
site(s) and ensure that such person(s) fully understands all conditions and all
requirements incorporated in this Permit. The site(s) refers to
site(s) of construction and operation of the Project and shall mean the same
hereafter.
許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 The Permit
Holder shall display conspicuously a copy of this Permit on the Project site(s)
at all vehicular site entrances/exits or at a convenient location for public’s
information at all times. The Permit Holder shall ensure that the most updated
information about this Permit, including any amended Permit, is displayed at
such locations. If the Permit Holder surrenders a part or the whole of
this Permit, the notice he sends to the Director shall also be displayed at the
same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site(s).
許可證持有人須在工程項目工地所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回本許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。
1.6 The Permit
Holder and any person constructing or operating the Project shall construct and
operate the Project in accordance with the project description in Part B of this Permit.
許可證持有人及任何建造或營辦工程項目的人士須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7 The Permit
Holder and any person constructing or operating the Project shall ensure that
the Project is designed, constructed
and operated in accordance with the information and recommendations described
in the Project Profile (Register
No.: PP-641/2022); the application documents for environmental permits; other relevant document in the Register;
the information and mitigation measures described in this Permit; mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, and mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded in this Permit or otherwise agreed by the
Director.
許可證持有人及任何建造或營辦工程項目的人士須確保工程項目按照下述資料設計、建造及營辦:工程項目簡介(登記冊編號 : PP-641/2022)所說明的資料及相關建議;環境許可證的申請文件; 登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證所載的條件須提交予署長存放或獲署長批准的文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或另獲署長同意。
1.8 All
submissions, as required under this Permit, shall be rectified and resubmitted
in accordance with the comments, if any, made by the Director within one month
of the receipt of the Director’s comments or otherwise as specified by the
Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內或署長另行指定的期限內,根據署長的意見加以修正及重新提交。
1.9 All submissions approved by the Director,
all submissions deposited without comments by the Director, or all submissions
rectified in accordance with comments by the Director under this Permit shall
be construed as part of the permit conditions described in Part C of this
Permit. Any variation of the submissions shall be approved by the Director in
writing or as prescribed in the relevant permit conditions. Any non-compliance
with the submissions may constitute a contravention of the EIAO (Cap. 499). All
submissions or any variation of submissions shall be certified by the
Independent Environmental Checker referred to in Conditions 2.1 below before
submitting to the Director under this Permit.
所有提交予署長並獲批准的文件、所有提交予署長存放而沒有收到署長意見的文件,或根據本許可證提交並已依照署長的意見作出修訂的所有文件,將詮釋為本許可證C部 所說明的許可證條件的一部分。對提交文件所作的任何修訂,均須獲得署長的書面批准,或符合有關許可證條件所述。凡與所提交的文件有不符合的情況,均可能構成違反環評條例
(第499章)。所有提交文件或提交文件的任何修訂本,均須按下文條件第2.1項所述的獨立環境查核人核證,然後才按本許可證規定向署長提交。
1.10 The
Permit Holder shall release all finalised submissions as required under this
Permit to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office, or in any other places, or any internet
websites as specified by the Director, or by any other means as specified by
the Director for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何方法,以供公眾查閱。為此,許可證持有人須提供足夠數量的複本。
1.11 The
Permit Holder shall submit and / or deposit all submissions within the time as
specified in the Conditions of this Permit. All submissions to the
Director required under this Permit shall be delivered either in person or by
registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130
Hennessy Road, Wanchai, Hong Kong). Electronic copies
of all finalised submissions required under this Permit shall be prepared in
Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable
Document Format (PDF version 1.3 or later), unless otherwise agreed by the
Director and shall be submitted at the same time as the hard copies.
許可證持有人須在本許可證條件所列明的時間內,提交及/或存放所有文件。本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子複本,均須以超文本標示語言(HTML)(第4.0或較後版本)和便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,電子複本須與硬複本同時提交。
1.12 The
Permit Holder shall notify the Director in writing the commencement date of
construction of the Project (including the commencement date of construction of
the various concerned works areas and the proposed pipe bridges) no later than 1 month prior to the commencement of construction of the Project.
The Permit Holder shall notify the Director in writing immediately if there is
any change of the commencement date of the construction.
許可證持有人須在工程項目的建造工程展開前最少1個月以書面方式把工程項目建造工程(包括各有關工地及擬議管道橋)的展開日期通知署長。建造工程的展開日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
為執行本許可證,「建造工程的展開」不包括有關工地預備的工程,或署長同意的其他工程。
特定條件
Employment
of Independent Environmental Checker
聘用獨立環境查核人
2.1
An Independent Environmental Checker (IEC) shall
be employed by the Permit Holder before commencement of construction of the
Project. The IEC shall not be in any way an associated body of the Contractor
for the Project. The IEC shall be a person who has at least 7 years of
experience in Environmental Monitoring and Audit or environmental management.
The IEC shall audit the implementation of the environmental mitigation measures
recommended in the Project Profile (Register No. PP-641/2022) and required
under this Permit, and to confirm full compliance of the mitigation measures
through a monthly audit report. The Permit Holder shall, no later than 10
working days after the end of each reporting month, submit to the Director 2
hard copies and 1 electronic copy of the monthly audit report prepared by the
IEC.
許可證持有人須在工程項目的建造工程展開前聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商有任何聯繫。獨立環境查核人須在環境監察及審核或環境管理方面最少有7年經驗。獨立環境查核人須審核工程項目簡介 (登記冊編號:PP-641/2022) 內及本許可證條件中建議的環境保護措施的實施工作,並在每月審核報告書確認所有措施的實施完全符合工程項目簡介以及各許可證條件的規定。許可證持有人須在規定提交報告的月份結束後10個工作天內,向署長提交由獨立環境查核人擬備的每月審核報告書的2份硬複本及1份電子複本。
Employment of Ecologist
聘用生態學家
2.2
An ecologist shall be employed by the Permit Holder before commencement
of construction of the Project. The ecologist shall conduct vegetation and fauna surveys as
specified under Conditions 2.3 and 2.4 of this Permit, and certify the
submissions under Conditions 2.3 and 2.4 of this Permit. The ecologist shall be a
person who has at least 3 years of relevant experience. The qualification and experience of the
ecologist shall be verified by the IEC.
許可證持有人須在工程項目的建造工程展開前聘用一名生態學家。生態學家須根據本許可證條件第2.3 及 2.4項進行植物及動物的調查工作,及核證根據本許可證條件第2.3 及 2.4項所提交文件。生態學家須具備至少3年相關經驗,其資格及經驗須由獨立環境查核人核實。
Submission of Updated Vegetation Survey Report(s)
提交更新的植物調查報告
2.3
Before commencement of site clearance works at the concerned works areas,
updated vegetation survey(s) along the proposed cable route within country park
shall be conducted by the qualified ecologist appointed under Condition 2.2
above to confirm presence of any newly colonised flora species of conservation
importance within and in the vicinity of the concerned works area. The Permit
Holder shall, no later than 1 month before commencement of site clearance works
at the concerned works areas, deposit with the Director 4 hard copies and 1
electronic copy of Updated Vegetation Survey Report(s) (UVSR(s)) prepared by
the qualified ecologist appointed under Condition 2.2 above, and verified by
the IEC. The UVSR(s) shall provide details and findings of the updated vegetation
survey(s) including details of the mitigation measures required. The UVSR(s)
shall include an implementation schedule in table form to clearly list out
the mitigation measures to be implemented, the implementation party, location
and timing. The mitigation measures recommended and requirements specified
in the UVSR(s) shall be fully implemented.
在有關工地範圍的工地清理工程展開前,根據上文條件第2.2項聘用的合資格生態學家應在郊野公園內的擬議電纜鋪設路線進行更新植物調查,以確定有關工地範圍內或附近是否有任何新拓殖的具保育價值的植物物種。許可證持有人須在有關工地範圍的工地清理工程展開前最少1個月,把由生態學家擬備並由獨立環境查核人核實的更新的植物調查報告的4份硬複本及1份電子複本送交署長存放。更新的植物調查報告須提供調查的細節和結果,包括所需緩解措施的細節,並須以列表形式列出實施時間表,清楚列明將會實施的緩解措施、實施者、地點及時間。更新的植物調查報告中建議的所有緩解措施均須全面予以實施。
Submission of Fauna Survey Report(s)
提交動物調查報告
2.4
Before commencement of construction works at the proposed pipe bridges,
fauna survey(s) shall be conducted at the concerned works areas by the
qualified ecologist appointed under Condition 2.2 above to
confirm the presence of any species of conservation importance, particularly amphibian, that could
be affected by the Project. The Permit Holder shall, no later than 2 weeks
after completion of the survey(s), deposit with the Director 4 hard copies and
1 electronic copy of the Fauna Survey Report(s) (FSR(s)) prepared by the
qualified ecologist appointed under Condition 2.2 above, and verified by the
IEC. The FSR(s) shall provide details and findings of the fauna survey(s)
including details of the mitigation measures required. The FSR(s) shall include
an implementation schedule in table form to clearly list out the mitigation
measures implemented or to be implemented, the implementation party, location,
and timing. The mitigation measures recommended and requirements specified
in the FSR(s) shall be fully implemented.
在進行任何擬議管道橋的建造工程之前,根據上文條件第2.2項聘用的合資格生態學家應在有關的工地範圍內進行動物調查以確認可能受項目影響的具保育價值的物種(特別是兩棲動物)的存在。許可證持有人須在動物調查完成後2星期內,把由生態學家擬備並由獨立環境查核人核實的動物調查報告的4份硬複本及1份電子複本送交署長存放。動物調查報告須提供調查的細節和結果,包括所需緩解措施的細節,並須以列表形式列出實施時間表,清楚列明已實施或將會實施的緩解措施、實施者、地點及時間。動物調查報告中建議的所有緩解措施均須全面予以實施。
Measures to Minimise Impacts to Water Quality and
Terrestrial Ecology
減低水質及陸地生態影響的措施
2.5
To minimise potential impacts to the streams/watercourses at the proposed
pipe bridge stream crossings, and to fauna species of conservation importance,
the construction works at the stream crossing sections shall be conducted
during dry season (i.e. from November to January).
為減低對管道橋跨溪纜段的溪澗/水道及具保育價值動物物種的潛在影響,管道橋跨溪纜段的建造工程須在旱季(即從11月至1月)進行。
Notes:
註:
1. This
Permit consists of three parts, namely, Part A
(Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions). Any person relying on this Permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
本許可證共有3部,即 A部 (許可證主要部分);B部 (指定工程項目的說明) 及C部 (許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If
there is a breach of any condition of this Permit, the Director or his
authorized officer may, with the consent of the Secretary for the Environment, order the
cessation of associated work until the remedial action is taken in respect of
the resultant environmental damage, and in that case the Permit Holder shall
not carry out any associated works without the permission of the Director or
his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The
Permit Holder may apply under Section 13 of the EIAO to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須以經修改的許可證替換在工程項目工地內展示的原有許可證。
4. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under Section 12 of
the EIAO to the Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under
Section 14 of the EIAO, the Director may with the consent of the Secretary for the Environment,
suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the Project site.
根據環評條例第14條的規定,署長可在取得環境局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。
6. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the EIAO before
the Project could be continued. It
is an offence under Section 26(1) of the EIAO to construct or operate a
designated project listed in Part I of Schedule 2 of the EIAO without a valid
environmental permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2第1部所列明的指定工程項目,即屬犯罪。
(i)
on a first conviction on indictment to a fine of $2 million
and to imprisonment for 6 months;
(ii)
on a second or subsequent conviction on indictment to a
fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to
imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine of
$1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature,
the court or magistrate may impose a fine of $10,000 for each day on which he
is satisfied the offence continued.
如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪—
(i)
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及
(v)
在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the EIAO within 30 days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for general
reference only and that the Permit Holder should refer to the EIAO for details
and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental Permit No. EP-611/2022
| Figure
1 |