Environmental Permit No. EP-614/2022
Àô¹Ò³\¥iÃÒ½s¸¹EP-614/2022
ENVIRONMENTAL IMPACT
ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
Àô¹Ò¼vÅTµû¦ô±ø¨Ò
(²Ä499³¹)
²Ä10±ø
ENVIRONMENTAL PERMIT TO CONSTRUCT
AND OPERATE
A DESIGNATED PROJECT
«Ø³y¤ÎÀç¿ì«ü©w¤uµ{¶µ¥ØªºÀô¹Ò³\¥iÃÒ
A³¡ (³\¥iÃÒ¥Dn³¡¤À)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) grants this environmental permit to the MTR Corporation Limited (hereinafter referred to as the ¡§Permit Holder¡¨) to
construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based
on the documents, approvals or permissions described below:
®Ú¾Ú¡mÀô¹Ò¼vÅTµû¦ô±ø¨Ò¡n(Àôµû±ø¨Ò) ²Ä10±øªº³W©w¡AÀô¹Ò«OÅ@¸p¸pªø(¸pªø)±N¥»Àô¹Ò³\¥iÃҧ天»´äÅK¸ô¦³¤½¥q (¤UºÙ¡§³\¥iÃÒ«ù¦³¤H¡¨) ¥H«Ø³y¤ÎÀç¿ìB³¡ ©Ò»¡©úªº«ü©w¤uµ{¶µ¥Ø¡A¦ý¶·¿í¦uC³¡ ©Ò¦C©úªº±ø¥ó¡C¥»Àô¹Ò³\¥iÃÒªºµo¥X¡A¤D¥H¤Uªí©Ò¦Cªº¤å¥ó¡B§åã©Î³\¥i§@¬°®Ú¾Ú¡R
Application No. ¥Ó½Ð®Ñ½s¸¹ |
AEP-614/2022 |
µn°O¥U¤Wªº¤å¥ó¡G |
-
Tung Chung Line Extension (Register No. AEIAR-235/2022) : Environmental Impact Assessment (EIA)
Report [Hereafter referred to as ¡§the EIA Report¡¨] -
Environmental
Monitoring and Audit (EM&A) Manual [Hereafter referred to as ¡§the EM&A Manual¡¨] -
Executive
Summary ªF¯F綫©µ綫 (µn°O¥U½s¸¹¡GAEIAR-235/2022):
-
Àô¹Ò¼vÅTµû¦ô³ø§i
[¤UºÙ¡§Àôµû³ø§i¡¨] -
Àô¹ÒºÊ¹î¤Î¼f®Ö¤â¥U
[¤UºÙ¡§ÀôºÊ¤â¥U¡¨] -
¦æ¬FºKn (1)
The
Director¡¦s letter of approval of the EIA Report dated 12 July 2022 (Reference: (15) in EP2/N9/A/186
Pt.5) ¸pªø©ó2022¦~7¤ë
12 ¤éµo¥X§åãÀôµû³ø§iªº«H¥ó (ÀÉ®×½s¸¹¡G(15) in EP2/N9/A/186 Pt.5) (2)
Application
for Environmental Permit submitted on 13 July 2022 (Application No.
AEP-614/2022) ©ó2022¦~7¤ë13¤é ´£¥æªºÀô¹Ò³\¥iÃҥӽФå¥ó (¥Ó½Ð®Ñ½s¸¹: AEP-614/2022) |
9 August 2022
2022¦~8¤ë 9 ¤é
Date ¤é´Á |
|
(Simon M.K.HO) Acting Principal
Environmental Protection Officer for Director of
Environmental Protection Àô¹Ò«OÅ@¸p¸pªø (¸p²zº®uÀô¹Ò«OÅ@¥D¥ô¦ó¤å¨Î¥N¦æ) |
PART B (DESCRIPTION OF
DESIGNATED PROJECT)
B³¡ («ü©w¤uµ{¶µ¥Øªº»¡©ú)
Hereunder is the description of the
designated project mentioned in Part A of this
environmental permit (hereinafter
referred to as the ¡§Permit¡¨):
¤U¦C¬°¥»Àô¹Ò³\¥iÃÒ (¤UºÙ¡§³\¥iÃÒ¡¨) A³¡ ©Ò´£zªº«ü©w¤uµ{¶µ¥Øªº»¡©ú¡R
Title of Designated Project «ü©w¤uµ{¶µ¥Øªº¦WºÙ |
Tung Chung Line Extension [This
designated project is hereafter referred to as ¡§the Project¡¨] ªF¯F綫©µ綫[¥»«ü©w¤uµ{¶µ¥Ø¤UºÙ ¡§¤uµ{¶µ¥Ø¡¨] |
Nature of Designated Project |
(1) A railway and its associated stations; and ÅK¸ô¤Î¨ä¬ÛÁp¨®¯¸¡F¤Î (2)
A road or railway tunnel more than 800m in length
between portals ¤J¤f¤§¶¡ªºªø«×¶W¹L800¦Ìªº¦æ¨®ÀG¹D©ÎÅK¸ôÀG¹D |
Location of Designated Project «ü©w¤uµ{¶µ¥Øªº¦aÂI |
The Project is located at Tung Chung. The location of the Project is shown in Figure 1 of this Permit ¤uµ{¶µ¥Ø¦ì©óªF¯F¡C¤uµ{¶µ¥Øªº¦ì¸m¸ü©ó¥»³\¥iÃÒ¹Ï1 |
Scale and Scope of
Designated Project «ü©w¤uµ{¶µ¥Øªº³W¼Ò©M½d³ò |
The Project includes: -
Construction of a new Tung Chung East (TCE)
Station (at-grade) and diversion of a section of existing Tung Chung Line
(TCL); -
Extending the existing Tung Chung Line from the
existing overrun tunnel of Tung Chung Station (TUC) to the new Tung Chung
West (TCW) Station (in the form of a tunnel); -
Construction of a new TCW Station (underground)
and overrun tunnel; -
Construction of the Emergency Access Point
(EAP)/Emergency Egress Point (EEP) building; and -
Construction of station associated facilities
(entrances, vent shaft structures, etc.). ¤uµ{¶µ¥Ø¥]¬A: -
«Ø³y·sªF¯FªF¯¸(¦a±)¤Î§ï¹D³¡¤À²{¦³ªºªF¯F綫¡F -
¥Ñ²{¦³ªF¯F¯¸¶V¦ìÀG¹D©µ¦ù¦Ü·sªF¯F¦è¯¸ªºÅK¸ô¡]ÀG¹D§Î¦¡¡^¡F -
«Ø³y·sªF¯F¦è¯¸¡]¦a©³¡^¤Î¶V¦ìÀG¹D¡F -
«Ø³yºò«æ¥X¤J¦aÂI«Ø¿vª«¡F¤Î -
«Ø³y¨®¯¸¬ÛÃö³]¬I¡]¥X¤J¤f¡B³q·¤«µ²ºcµ¥¡^¡C |
1.2 The Permit
Holder and any
person constructing or operating the Project shall ensure full compliance with all legislation from time to time in
force including, without limitation to, the Noise Control Ordinance (Cap. 400),
Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance
(Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance
(Cap. 354). This Permit does not of itself constitute any ground of defence
against any proceedings instituted under any legislation or imply any approval
under any legislation.
1.3 The Permit
Holder shall make copies of this Permit together with all documents referred to
in this Permit and the documents referred to in Part
A of this Permit readily available at all times for inspection by the
Director or his authorised officers at all sites covered by this Permit. Any
reference to this Permit shall include all documents referred to in this Permit
and also the relevant documents in the Register.
1.4 The Permit
Holder shall give a copy of this Permit to the person(s) in charge of the
site(s) and ensure that such person(s) fully understands all conditions and all
requirements incorporated in this Permit. The site(s) refers to
site(s) of construction and operation of the Project and shall mean the same
hereafter.
1.5 The Permit
Holder shall display conspicuously a copy of this Permit on the construction
site(s) at all vehicular site entrances/exits or at a convenient location for public¡¦s information at
all times. The Permit Holder
shall ensure that the most updated information about this Permit, including any
amended Permit, is displayed at such locations. If the Permit Holder
surrenders a part or the whole of this Permit, the notice he sends to the
Director shall also be displayed at the same locations as the original
Permit. The suspended, varied or cancelled
Permit shall be removed from display at the construction site(s).
1.6 The Permit
Holder and any person constructing or operating the Project shall construct and
operate the Project in accordance with the project description in Part B of this Permit.
1.7 The Permit
Holder and any person constructing or operating the Project shall ensure that
the Project is designed, constructed
and operated in accordance with the information and recommendations described
in the approved
EIA Report (Register No.: AEIAR-235/2022); the application documents for environmental permits; other relevant document in the Register;
the information and mitigation measures described in this Permit; mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, and mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded in this Permit or otherwise agreed by the
Director.
1.8 All
submissions, as required under this Permit, shall be rectified
and resubmitted in accordance with the comments, if any, made by the Director
within one month of the receipt of the Director¡¦s comments or otherwise as
specified by the Director.
1.9 All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C of this
Permit. Any variation of the submissions shall be approved by the Director in
writing or as prescribed in the relevant permit conditions. Any non-compliance
with the submissions may constitute a contravention of the EIAO (Cap. 499). All submissions or any variation of submissions shall be certified by
the Environmental Team (ET) Leader and verified by the Independent
Environmental Checker (IEC) referred to in Conditions 2.1 and 2.5 below before
submitting to the Director under this Permit.
1.10 The
Permit Holder shall release all finalised submissions as required under this
Permit to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office, or in any other places, or any internet
websites as specified by the Director, or by any means as specified by the
Director, for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
1.11 The
Permit Holder shall submit and / or deposit all submissions within the time as
specified in the Conditions of this Permit. All submissions to the Director required under this Permit
shall be delivered either in person or by registered mail to the Environmental
Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai,
Hong Kong). Electronic copies of all finalised submissions required under this
Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 1.3 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hard copies.
1.12 The
Permit Holder shall notify the Director in writing the commencement date of
construction of the Project no later than 2 months prior to the commencement
of construction of the Project. The Permit Holder shall notify the Director in
writing immediately if there is any change of the commencement date of the
construction.
Employment or Submissions before Construction of the Project
Employment
of Environmental Team (ET)
2.1 An
ET shall be established by the Permit Holder no later than 2 months before the commencement
of construction of the Project. The ET shall not be in any way an associated
body of the Contractor or the IEC for the Project. The ET shall be headed by an ET Leader
and supported by relevant specialists including Terrestrial Ecologist,
certified Arborist and registered Landscape Architect or related professional.
The ET Leader shall be a person who has at least 7 years of experience in
environmental monitoring and auditing (EM&A) or environmental management.
2.2 The ET Leader, or an ET Leader representative
who shall be a member of the ET with at least 5 years of experience in EM&A
or environmental management, shall work full time on-site during construction
stage of the Project.
2.3 The ET and
the ET Leader shall be responsible for duties defined in the EM&A Manual
and this Permit, including implementation of the EM&A programme in
accordance with the EM&A requirements as contained in the EM&A Manual
of the Project; and site inspections to audit the Contractor¡¦s site practice
and work methodologies with respect to environmental mitigation measures contained
in the EM&A Manual of the Project and/or as required under this Permit and
to take pro-active actions to pre-empt environmental problems. The ET Leader shall be responsible for:
(i)
certifying
the environmental acceptability of permanent and temporary works, relevant
plans and submissions required in the EM&A Manual and/or under this
Permit. Certification(s) shall be
documented in the upcoming EM&A monthly report;
(ii)
notifying
the IEC within 1 working day of the occurrence of each and
every instance or circumstance or change of circumstances, which may
affect the compliance with the recommendations of the approved EIA Report
(Register No. AEIAR-235/2022) and/or this Permit. Notification(s) shall be documented in
the upcoming EM&A monthly report; and
(iii)
keeping
a contemporaneous log-book of any such instance or
circumstance or change of circumstances, which may affect the compliance with
the EIA Report (Register No. AEIAR-235/2022) and/or this Permit. The format of the log-book
shall be certified and approved by the IEC. The log-book
shall be kept readily available for inspection by all persons assisting in
supervision of the implementation of the recommendations of the approved EIA
Report (Register No. AEIAR-235/2022) and this Permit or by the Director or his
authorized officers.
2.4
Failure to maintain records in the log-book,
failure to discharge the duties of the ET Leader as defined in the EM&A
Manual or failure to comply with Condition 2.3 above would entitle the Director
to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit
Holder to make replacement or further failure to keep contemporaneous records
in the log-book despite the employment of a new ET
Leader may render this Permit liable to suspension, cancellation or variation.
Employment of
Independent Environmental checker (IEC)
2.5 An
IEC shall be employed by the Permit Holder no later than 2 months before the commencement
of construction of the Project. The
IEC shall not be in any way an associated body of the Contractor or the ET for
the Project. The IEC shall be a
person who has at least 7 years of experience in EM&A or environmental
management.
2.6 The appointment of IEC
shall be approved by the Director before being appointed by the Permit
Holder. The IEC, or an IEC
representative who shall be a person with at least 5 years of experience in
EM&A or environmental management, shall work full time on-site during
construction stage of the Project. The Permit Holder
shall also provide supporting team to the IEC or to the IEC representative. The IEC or the IEC
representative shall report directly to the Director on matters relating to the
EM&A programme and environmental impacts of the Project.
2.7 The
IEC shall be responsible for duties defined in the EM&A Manual and this
Permit, including the following:
(i)
auditing
the overall EM&A performance, including the implementation of all
environmental mitigation measures and monitoring activities on site,
submissions required in the EM&A Manual, and/or under this Permit. Finding(s) of the audit(s) shall be
documented in the upcoming EM&A monthly report;
(ii)
verifying
the environmental acceptability of permanent and temporary works, relevant
design plans and submissions required in the EM&A Manual and under this
Permit. Verification(s) shall be documented in the upcoming EM&A monthly report;
(iii)
verifying
the log-book(s) mentioned in Condition 2.3(iii). The IEC shall sign off with a date on
the log-book after verification.
(iv)
notifying
the Director by fax or email, within one working day of receipt of notification
from the ET Leader, or identification by the IEC and his team, of each and
every change of circumstances or suspected and/or potential non-compliance with
the recommendations (such as construction methods, mitigation measures, and
environmental standards) of the approved EIA Report (Register No.
AEIAR-235/2022), the EM&A Manual and this Permit, which might affect the
monitoring or control of adverse environmental impacts arising from the
Project. Notification by the
Permit Holder is the same as notification by the IEC for the purpose of this Condition;
(v)
liaising
closely with the Director;
(vi)
accompanying
the Director in carrying out site inspections and attending meetings when requested;
(vii)
offering
objective and professional advice on environmental issues, when requested, and
to respond to questions and enquiries from the Director on the project, the
EM&A programme and duties discharged by the IEC, with the support of
relevant information, documents and records as
appropriate; and
(viii)
allocating
adequate resources, including any necessary specialist support, for discharging
the duties required in the EM&A Manual and/or this Permit.
2.8 If
the Director considers the IEC fails to discharge the duties of the IEC as
defined in the EM&A Manual or in this Permit, the Director may require the
Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed
or further failure to so notify the Director despite employment of a new IEC
may render this Permit liable to suspension, cancellation
or variation.
Setting up of Community Liaison Group
2.9 The Permit Holder
shall, no later than 1 month before the commencement of construction of the
Project, set up a community liaison group, comprising representatives of affected
parties, including local committees, residents and schools in the affected
areas along the alignment, for maintaining regular
communication with the local and relevant stakeholders on issues concerning
noise, air, traffic, waste management, landscape and recreational spaces etc.
arising from the Project, and handling complaints on environmental issues
related to the Project. The Permit Holder shall take a proactive approach to
disseminate information to the group, promote community cooperation and
participation and implement suitable local environmental enhancement works. All
relevant information of the Project including the progress of construction and
operation and environmental monitoring and audit results should be provided to
the group. Designated
complaint hotlines shall be set up for the project to address related concerns
and enquiries in an efficient manner. The Permit Holder shall
inform the Director in writing the membership and terms of reference of the
group.
Submission of Construction Works
Phasing Schedule
2.10 The Permit Holder
shall, no later than 1 month before the commencement
of construction of the Project, deposit 3 hard copies and 1
electronic copy of a Construction Works Phasing Schedule (the
Schedule) with the Director. The Schedule shall include at least the
following information:
(i) a
detailed works programme showing the planned timing for the commencement and completion
of the major construction works including the phased implementation
programme for the realignment of the existing TCL; and the number of Works
Contract(s) involved under the Project; and
(ii) location plan(s) in
appropriate scale delineating the works boundary and works areas of each Works
Contract of the Project.
Submission of Environmental
Permit (EP) Submission Schedule
2.11 The Permit Holder shall, no later
than 1 month before the commencement of construction of the Project, deposit an
EP Submission Schedule to set out a timeline for EP submissions in this Permit
and shall report the progress in fulfilling the submission requirements in the
monthly Environmental Monitoring and Audit (EM&A) reports submitted under
Condition 3.4 of this Permit. The
Permit Holder shall inform the Director no later than 2 weeks before the scheduled
submission date of the EP submission in writing in case of any subsequent
change(s) to the submitted EP Submission Schedule.
Submission of Management Organization
2.12 The Permit Holder shall, no later than 2
weeks before the commencement of construction of the Project, inform the
Director in writing the following information:
(i) the management
organization of the main construction companies and / or any form of joint
ventures associated with the construction of the Project;
(ii) the management
organization of the ET;
(iii)
the management organization of the IEC and his
team; and
(iv)
the submitted information shall include at
least an organization chart, names of responsible persons and their contact
details.
Submission
of Noise Mitigation Measures Plan(s)
2.13 The Permit Holder
shall, no later than 2 months before the commencement of the construction works
of relevant Works Contract of the Project, submit 3 hard copies and 1
electronic copy of a Construction Noise Management Plan (CNMP) to the Director
for approval. The CNMP shall identify the noise source inventory and assess the
effectiveness of construction noise mitigation measures, including the use of
quieter powered mechanical equipment, noise barriers and noise enclosures as
recommended in the EIA report (Register No. AEIAR-235/2022). To further
mitigate construction noise impacts, the CNMP shall review the practicality of
the use of quieter construction equipment/methods, such as hydraulic crusher/
hand-held concrete crusher for demolition; diamond wire saw/ non-explosive
chemical expansion agent for rock/concrete breaking; silent piling by Press-in
method for sheet piles etc.; when necessary. The
CNMP shall include an implementation schedule in table form to clearly list out
the mitigation measures to be implemented, and the implementation party,
location, timing, and environmental performance required for implementation of
the mitigation measures. All mitigation measures recommended
and requirements specified in the CNMP shall be fully implemented.
2.14 To
mitigate the rail noise impacts, the Permit Holder shall, no later than 2
months before the commencement of construction works for the realignment of the
TCL track in the TCE area, submit 3 hard copies and 1 electronic copy of a Rail
Noise Mitigation Plan (RNMP) to the Director for approval. The Plan shall review the noise
mitigation measures, including the temporary speed reduction of existing TCL
and noise barriers required at various stages of implementation of the
realigned TCL track as shown in Figures
2a-2d of this Permit. The RNMP
shall include an implementation schedule in table form to clearly list out the
mitigation measures to be implemented, and the implementation party, location,
timing, and environmental performance required for implementation of the
mitigation measures. All mitigation measures recommended
and requirements specified in the RNMP shall be fully implemented.
Submission of Plan on Noise Enclosure at Tung Chung Crescent
2.15 The
Permit Holder shall, no later than 2 months before the commencement of
construction works at Tung Chung Crescent (TCC), submit 3 hard copies and 1
electronic copy of a Plan (the Plan) on the proposed noise enclosure at TCC to
the Director for approval. The Plan shall include but not limited to the
details of its design, extent, access point locations and construction vehicle
traffic management as well as the program of erection and demolition of the
enclosure and site reinstatement, and the arrangement for temporary storage of
construction and demolition waste. The Plan shall demonstrate the effectiveness
of the enclosure in mitigating the noise, air and any
other potential environmental nuisances, as well as health and safety hazards
during the construction phase.
Submission of Compensatory Tree Planting Implementation Plan
2.16 The
Permit Holder shall, no later than 2 months before the commencement of the
compensatory tree planting, submit 4 hard copies and 1 electronic copy of a
Compensatory Tree Planting Implementation Plan (the Plan) to the Director for
approval. The
Plan shall include details of the
planting objectives, planting numbers and locations, and list of native tree
species to be used, with the aim to enhance urban biodiversity and
compatibility with the surrounding natural environment. The Permit Holder shall engage a
Terrestrial Ecologist(s) and a certified Arborist(s) in the preparation of the
Plan. The Plan shall be certified
by the ET Leader and verified by the IEC. The relevant authority should be
consulted and advice from Agriculture, Fisheries and Conservation Department
(AFCD) on the Plan should be sought prior to submission to the Director.
Submission of Landscape and Visual Mitigation Plan
2.17 The Permit Holder shall, no
later than 1 month before the commencement of construction
of the Project or otherwise approved by the Director, deposit with the Director
3 hard copies and 1 electronic copy of a Landscape and Visual Mitigation Plan
(the LVMP). The LVMP shall include design details, implementation schedule,
maintenance and management schedules and drawings in the scale of 1:1000 or
other appropriate scale, as agreed with the Director, of the landscape and
visual mitigation measures of the Project. The implementation schedule shall be
in table form to clearly list out the mitigation measures to be implemented,
and the implementation party, location, timing, and environmental performance
required for implementation of the mitigation measures. The LVMP shall be
certified by the ET Leader and the registered Landscape Architect or related
professional and verified by the IEC as conforming to the relevant information
and recommendations, including those described in the EIA Report (Register No.
AEIAR-235/2022). All mitigation measures recommended
and requirements specified in the LVMP or any updated LVMP shall be fully
implemented and maintained for the Project. The LVMP shall show the
landscape and visual mitigation measures of the Project and include at least
the following information:
(i)
Architectural aesthetic
design for built structures and noise barrier;
(ii)
Tree felling and
preservation proposal showing quantity, plant species, location(s) and size of trees to be retained/transplanted/felled, and
location(s) of transplanted trees; and
(iii)
Landscape Plan showing
location(s) of greening works including green roofs, screen planting and any
other landscape enhancement to mitigate landscape impact of the Project.
Submission of Contingency and Response Plan
2.18 The Permit Holder
shall, no later than 2 months before the commencement of relevant part of the
construction works, submit 3 hard copies and 1 electronic copy of a Contingency
and Response Plan (the Plan) for handling any accidental spillage of slurry
arising from the Tunnel Boring Machine (TBM) works to the Director for
approval.
Submission of Wastewater Management Plan
2.19 The Permit Holder
shall, no later than 2 months before the commencement of the construction works
in Tung Chung West, submit 3 hard copies and 1 electronic copy of a Wastewater
Management Plan (the Plan) for the construction works at Tung Chung West to the
Director for approval. The Plan shall include locations of the discharge points
and the treatment arrangements of wastewater including site runoff with a view
to minimising impacts upon the nearby mudflats and other water sensitive areas
in the vicinity. Advice from AFCD on the Plan should be sought prior to
submission to the Director.
Submission of Waste
Management Plan
2.20 The Permit Holder shall, no later than 1 month before the
commencement of construction of the Project, deposit with the Director 3 hard
copies and 1 electronic copy of a Waste Management Plan (WMP). The WMP shall
include estimated volume of different types of waste, e.g.
construction and demolition (C&D materials) materials, land-based marine sediment,
chemical waste, general refuse, etc., and also the
arrangements for avoidance, minimization, recovery, recycling, reuse, storage, collection, treatment and disposal of
different categories of waste to be generated from the construction activities.
The WMP shall also describe the tracking system to be adopted to avoid illegal
dumping or landfilling of C&D materials as required in Condition 2.21 below. The WMP shall
include an implementation schedule in table form to clearly list out the amount
and disposal outlet for the different types of waste arising, mitigation
measures to be implemented, and the implementation party, location, timing, and
environmental performance required for implementation of the mitigation
measures. All mitigation measures recommended and
requirements specified in the WMP and the implementation schedule shall be
fully implemented.
Measures to be implemented for the Construction of
the Project
Waste
Management Measures
2.21 All dump trucks for
C&D materials transportation and disposal shall be equipped with Global
Positioning System (GPS) or equivalent automatic identification system (AIS)
for real time tracking and monitoring of their travel routings and parking
locations in order to avoid illegal dumping or
landfilling of C&D materials. The data collected by GPS or equivalent AIS
relating to travel routings and parking locations of all dump trucks shall be
recorded properly for checking and auditing by ET and IEC. The audit findings shall be reported in
the Monthly EM&A Report.
Measures
to contain the site runoff at TCW Area
2. 22 To contain the untreated site
runoff being accidentally discharged into the adjoining water bodies, a barrier
such as sheet pile/hoarding with concrete footing shall be installed along the
western boundary of the construction site/ works areas for TCW station as shown
in Figure 3 of this Permit, or as
otherwise approved by the Director.
Further Archaeological
Testing
2.23 The Permit Holder shall
carry out further archaeological testing at the inaccessible area located at
the extreme north end of the proposed TCW station as shown in Figure 4 of this Permit upon the
granting of site access. The Permit Holder shall seek agreement from
Antiquities and Monuments Office (AMO) on the scope of the archaeological
testing prior to the test and deposit with the Director 3 hard copies and 1
electronic copy of Archaeological Report upon completion of the archaeological
testing to record the archaeological testing findings and identify any
necessary mitigation measures.
Consideration
of Hazard
2.24 No overnight
storage of explosive on site shall be permitted for the construction of the
Project.
Employment or Submissions before Operation of the Project
Submission
of Fixed Plant Noise Audit Report
2.25 At least 1 month before
commencement of operation of the Project, the Permit Holder shall carry out
fixed plant noise audit and deposit with the Director 3 hardcopies and
1electronic copy of an audit report showing the design of the planned fixed
plant noise sources associated with the Project complies with the maximum sound
power levels determined in the approved EIA Report (Register No.
AEIAR-235/2022), or as otherwise agreed by the Director. The audit report shall also confirm that
noise emitted from the planned fixed noise sources shall be free of the
characteristics of tonality, impulsiveness and
intermittency.
3 Environmental Monitoring and Audit (EM&A) Requirements
3.1 The Permit Holder shall implement the EM&A programme in
accordance with the procedures and requirements as set out in the EM&A
Manual. Any changes to the EM&A
requirements or programme or termination of the programme shall be justified
by the ET Leader and verified by the IEC as conforming to the information and
requirements contained in the EM&A Manual before submission to the Director
for approval.
3.2 The
Permit Holder shall take samples, measurements and
necessary remedial actions in accordance with the requirements of the EM&A
Manual by:
(i)
conducting baseline environmental monitoring;
(ii)
conducting impact monitoring;
(iii)
carrying out remedial actions described in the
Event/Action Plans of the EM&A Manual in accordance with the time frame set
out in the Event/Action Plans, or as agreed by the Director, in case where
specified criteria in the EM&A Manual are exceeded; and
(iv)
logging and keeping records of the details of (i) to (iii) above for all parameters within 3 working days
of the collection of data or completion of remedial action(s), for the purpose
of preparing and submitting the monthly EM&A Reports and to make available
the information for inspection on site.
3.3 The Permit Holder shall submit 1 hard copy and 1 electronic copy of Baseline Monitoring Report to the Director at least
2 weeks before the commencement of construction of the Project. The
submissions shall be certified by the ET Leader and verified by the IEC as
having complied with the requirements as set out in the EM&A Manual before
submission to the Director. Additional copies of the Baseline Monitoring
Reports shall be provided upon request by the Director.
3.4 The Permit Holder shall submit 1 hard copy and 1 electronic copy of Monthly EM&A Reports for the construction stage
of the Project to the Director, within 10 working days after the end of the
reporting month. The monthly EM&A Reports shall include an executive summary of all environmental audit results, together with
actions taken in the event of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels),
complaints received and emergency events relating to violation of environmental
legislation. The submissions shall
be certified by the ET Leader and verified by the IEC as having complied with
the requirements as set out in the EM&A Manual before submission to the
Director. Additional copies of the Monthly EM&A Reports shall be
provided upon request by the Director.
3.5 All environmental monitoring and
audit data submitted under this Permit shall be true, valid
and correct.
4. Electronic Reporting
of EM&A Information
4.1 To
facilitate public inspection of the Baseline Monitoring Report and Monthly
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies as described in Conditions 3.3 and 3.4 above. For the HTML
version, a content page capable of providing hyperlink to each section and
sub-section of these Reports shall be included in the beginning of the
document. Hyperlinks to all figures, drawings and tables in these Reports shall
be provided in the main text from where the respective references are
made. All graphics in these Reports shall be in interlaced GIF, JPEG or PDF format unless otherwise agreed by the Director. The content of
the electronic copies of these Reports must be the same as the hard copies.
4.2 The Permit Holder shall, within 6 weeks after the commencement of
construction of the Project, set up a dedicated Internet website and notify the
Director in writing the Internet address where the environmental monitoring
data and project information is to be placed. All environmental
monitoring data described in Condition 4.1 above shall be made available to the
public via the abovementioned dedicated Internet website in the shortest
possible time and in any event no later than 2 weeks after the relevant
environmental monitoring data are collected or become available, unless
otherwise agreed with the Director. All finalized submissions and plans shall be made available to the
public via the dedicated Internet website in the shortest possible time and in
any event no later than 2 weeks after the submissions and plans are approved by
or deposited with the Director, unless otherwise agreed with the Director. The Permit Holder shall maintain the dedicated
website for public access of the environmental monitoring data and reports throughout
the entire construction period and during the first 1-year period of operation
of the Project, or otherwise as agreed by the Director.
4.3 The Internet website as described in Condition 4.2 above shall enable
user-friendly public access to the environmental monitoring data and project
information including the Project Profile, EIA Report and Environmental Permit(s). The Internet website shall
have features capable of:
(i)
providing access to all environmental monitoring data
of this Project collected since the commencement of construction;
(ii)
searching by date;
(iii)
searching by types of
monitoring data; and
(iv)
hyperlinking to relevant
monitoring data after searching
or otherwise as agreed
by the Director.
Notes:
1. This
Permit consists of three parts, namely, Part A
(Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions). Any person relying on this Permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
2. If
there is a breach of any condition of this Permit, the Director or his
authorized officer may, with the consent of the Secretary
for Environment and Ecology, order the cessation of associated work
until the remedial action is taken in respect of the resultant environmental
damage, and in that case the Permit Holder shall not carry out any associated
works without the permission of the Director or his authorized officer.
3. The
Permit Holder may apply under Section 13 of the EIAO to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the Project site by the amended permit.
4. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under Section 12 of
the EIAO to the Director for a further environmental permit.
5. Under
Section 14 of the EIAO, the Director may with the consent of the Secretary for Environment and Ecology, suspend,
vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at
the Project site.
6. If
this Permit is cancelled or surrendered during construction or operation of the Project, another
environmental permit must be obtained under the EIAO before the Project could
be continued. It is an offence
under Section 26(1) of the EIAO to construct or operate a designated project
listed in Part I of Schedule 2 of the EIAO without a valid environmental
permit.
7. Any
person who constructs or operates the Project contrary to the conditions in
this Permit, and is convicted of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment to a fine of $2 million
and to imprisonment for
6 months;
(ii)
on a second or subsequent conviction on indictment to a
fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to
imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine of
$1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature,
the court or magistrate may impose a fine of $10,000 for each day on which he
is satisfied the offence continued.
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the EIAO within 30 days of receipt of this Permit.
9. The
Notes are for general reference only and that the Permit Holder should refer to
the EIAO for details and seek independent legal advice.
Environmental Permit No. EP-614/2022
| Figure 1 | Figure 2a | Figure 2b | Figure 2c | Figure 2d | Figure 3 | Figure 4 |