Environmental Permit No. FEP-04/129/2002

       環境許可證編號 FEP-04/129/2002

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Sections 10 & 12

 

環境影響評估條例

(499)

10條及第12

 

FURTHER ENVIRONMENTAL PERMIT TO CONSTRUCT A PART OF THE DESIGNATED PROJECT

 

就建造指定工程項目其中部份而發出新的環境許可證

 

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Sections 10 and 12 of the Environmental Impact Assessment Ordinance (the Ordinance), the Director of Environmental Protection (the Director) grants this environmental permit to MAEDA CORPORATION (hereinafter referred to as the “Permit Holder”) to construct the designated project described in Part B subject to the conditions specified in Part C.  The issue of this environmental permit is based on the documents, approvals or permissions described below:

 

根據環境影響評估條例第1012條的規定﹐環境保護署署長 (署長) 將本環境許可證批予前田建設工業株式會 (下稱許可證持有人)以建造B部所說明的指定工程項目﹐但須遵守C部所說明或附載的條件。本環境許可證的發出﹐乃以下表所列的文件、批准或許可作為根據﹕-

 

Application No.

申請書編號:

FEP-059/2002

 

Document in the Register :

登記冊上的文件 :

 

(1)     Sheung Shui to Lok Ma Chau Spur Line – Environmental Impact Assessment Tunnel/Viaduct Option, Final Report, January 2002.

-     Volume 1 of 5 EIA Report (Part 1)

-     Volume 2 of 5 EIA Report (Part 2)

-     Volume 3 of 5 Appendices (Part 1)

-     Volume 4 of 5 Appendices (Part 2)

-     Volume 5 of 5 Figures and Drawings

-     Executive Summary

(Register No. AEIAR-052/2002) [hereinafter referred to as the “EIA Report”]

 

(1) 上水至落馬洲支線 - 環境影響評估 - 隧道/高架橋方案,最後報告 (二零零二年一月)

第一冊 環境影響評估報告 (第一部份)

第二冊 環境影響評估報告 (第二部份)

第三冊 附件(第一部份)

第四冊 附件(第二部份)

第五冊 圖表及繪圖

摘要

(登記冊編號 : AEIAR-052/2002) [下稱環評報告”]

 

(2)     The Director’s letter of approval of the EIA Report dated 11 March 2002, (ref: (111) in Ax (4) to EP2/G/A/101 IV)

 

(2) 環境保護署署長於2002311日發出批准環評報告的信件(檔案編號: (111) in Ax (4) to EP2/G/A/101 IV)

 

(3)     Application for environmental permit on 11 March 2002 (Application No. AEP-129/2002)

 

(3)  許可證持有人於2002311日提交的許可証申請文件(申請書編號: AEP-129/2002)

 

(4)     The Environmental Permit No. EP-129/2002 issued on 6 April 2002

 

(4) 200246日發出的環境許可証 No. EP-129/2002

 

(5)  Application for Further Environmental Permit on 2 July 2002 (Application No. FEP-050/2002)

 

(5) 200272申請之新的環境許可証 (申請書編號: FEP-050/2002)

 

(6)  The Further Environmental Permit No. FEP-01/129/2002 issued on 26 July 2002

 

(6)     2002726日發出之新的環境許可証 No. FEP-01/129/2002

 

(7)     Application for Variation of Environmental Permit on 16 August 2002 (Application No. VEP-071/2002)

 

(7) 2002816申請之更改後的環境許可証 (申請書編號: VEP-071/2002)

 

(8)  The Environmental Permit No. EP-01/129/2002/A issued on 23 August 2002

 

(8)      2002823日發出的環境許可証 No. EP-01/129/2002/A

 

(9)  Application for Further Environmental Permit on 15 November 2002 (Application No. FEP-057/2002)

 

(9) 20021115申請之新的環境許可証 (申請書編號: FEP-057/2002)

 

(10) Application for Variation of Environmental Permit on 26 November 2002 (Application No. VEP-080/2002)

 

(10)20021126申請之更改後的環境許可証 (申請書編號: FEP-080/2002)

 

(11)  Application for Further Environmental Permit on 26 November 2002 (Application No. FEP-058/2002)

 

(11)      20021126日申請之新的環境許可証(申請書編號: FEP-058/2002)

 

(12)      The Further Environmental Permit No. FEP-02/129/2002 issued on 7 December 2002

 

(12) 2002127發出之新的環境許可証 No. FEP-02/129/2002

 

(13)      The Further Environmental Permit No. FEP-03/129/2002 issued on 11 December 2002

 

(13) 20021211日發出之新的環境許可証 No. FEP-03/129/2002

 

(14)      The Environmental Permit No. EP-129/2002/A issued on 11 December 2002

 

(14) 20021211日發出的環境許可証 No. EP-129/2002/A

 

(15)      Application for Further Environmental Permit on 24 December 2002 (Application No. FEP-059/2002)

 

(15) 20021224日申請之新的環境許可証(申請書編號: FEP-059/2002)

 

 

 

 

 

 January 2003

 

 

 

 

 

 


Date

日期

 

(Elvis W K AU)

Assistant Director of Environmental Protection

(Environmental Assessment and Noise)

for Director of Environmental Protection

環境保護署署長
(
環境保護署助理署長(環境評估及噪音)代行)

 


PART B (DESCRIPTIONS OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit :

下列為本環境許可證A部所提及的指定工程項目的說明:

 

 

 

Title of Designated Project

指定工程項目的名稱

 

KCRC East Rail Extensions Contract LCC-202 – West Section Alignment and Associated Works [This designated project is hereinafter referred to as “the Project”]

九廣鐵路東鐵發展 合約編號 LCC-202 - 西邊路段及相關工程[本指定工程項目下稱工程項目”]

 

Nature of Designated Project
指定工程項目的性質

 

 

Construction of a railway viaduct.

 

建造一條高架鐵路。

 

 

Location of Designated Project

指定工程項目的地點

 

The project starts from Chau Tau terminates at Lok Ma Chau.

 

The location of the Project is shown on Figures 1 and 3 attached to this Permit.

 

工程由落馬洲的洲頭火車站開始。

 

工程項目的地點如本環境許可證內圖一所示。

 

 

Scale and Scope of Designated Project(s)

指定工程項目的規模和範圍

 

Construction of a section of the Lok Ma Chau Spurline as follows:

 

(i)                   Approximately 1.6km elevated track alignment between an abutment at Chau Tau and the approaches to Lok Ma Chau Terminus; and

 

(ii)                 Approx. 0.2km track on ramp from the tunnel ramp at Chau Tau to the viaduct abutment.

 

建造上水至落馬洲支線鐵路其中的一段:               

 

(i)                 由洲頭的橋架伸延至落馬洲火車站長約1.6公里的高架鐵路;

 

(ii)               由洲頭的隧道路段至高架橋橋架長約0.2公里的斜坡路段

 

 


PART C (PERMIT CONDITIONS)

 

1.         General Conditions

 

1.1       The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit.  Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap.499) and may become the subject of appropriate action being taken under the Ordinance.

 

1.2       The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap.400), Air Pollution Control Ordinance (Cap.311), Water Pollution Control Ordinance (Cap.358), Dumping at Sea Ordinance (Cap.466), the Waste Disposal Ordinance (Cap.354).  This Permit does not of itself (a) constitute any ground of defense against any proceedings instituted under any legislation or (b) imply any approval under any legislation.

 

1.3       The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit.  Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

 

1.4       The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit.  The site(s) refers to site(s) of construction and/or operation of the Project(s) and shall mean the same hereafter.

 

1.5       The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.  The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6              The Permit Holder shall construct the Project as described in Part B of this Permit.

 

1.7              The Permit Holder shall ensure that the Project is constructed in accordance with the information and recommendations described in the EIA report (Register No. AEIA-052/2002); other relevant documents in the Register; and the information or mitigation measures described in this Permit, or mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, or mitigation measures to be recommended under on-going surveillance and monitoring activities during all stages of the Project.  Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit. 

 

1.8              This Permit shall not remove the responsibility of any person to comply with the conditions set out in Part C of the Environmental Permit No. EP-129/2002/A or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance.

 

1.9              All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director's comments or otherwise as specified by the Director.

 

1.10          All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit.  Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions.  All submissions or any variation of the submissions shall be certified by the Environmental Team (ET) Leader referred to in Condition 2.1 of this permit and verified by the Independent Environmental Checker (IEC), established under condition 2.2 of the Environmental Permit No. EP-129/2002/A, or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance, before submitting to the Director under the Permit.

 

1.11          The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection.  For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.12          The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than one month prior to the commencement of construction of the Project.  The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

 

1.13          All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong).  Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

 

1.14          For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.

 

2.                  Submissions or Measures before Commencement of Construction of the Project

 

            Employment of Environmental Monitoring and Audit (EM&A) Personnel

 

2.1              An Environmental Team (ET) shall be established by the Permit Holder no later than one month before the commencement of construction of the Project.  The ET shall be headed by an ET Leader.  The ET Leader shall be a person who has at least 7 years’ experience in environmental monitoring and auditing (EM&A) or environmental management.  The ET team and the ET Leader shall be responsible for the duties defined in the EM&A Manual submitted and approved under Condition 2.3 of the Environmental Permit No. EP-129/2002/A, or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance.  The ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual.  The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and each and every non-compliance with the recommendations of the EIA Report (Register No. AEIAR-052/2002) or this Permit.  This log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the EIA Report recommendations and this Permit or by the Director or his authorized officers.  Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader.  Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.  The ET shall not be in any way an associated body of the IEC for the Project.

 

2.2              All submissions for approval and deposition under Sections 2, 3, 4 and 5 of this Permit shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendation contained in the EIA Report before submission to the Director.

 

High Degree of Transparency of the Project

 

2.3              To ensure a high degree of transparency regarding the monitoring data and results in view of the public concern about the Project, all environmental monitoring and audit data and results, and all submissions and all performance test data and results required by this Permit shall be made available by the Permit Holder to the public through a dedicated web site to be set up by the Kowloon-Canton Railway Corporation (KCRC) under Condition 6.2 of the Environmental Permit No. EP-129/2002/A, or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance, in the shortest possible time and in no event later than two weeks after such information is available.

 

3.                  Submissions or Measures for the Construction of the Project

 

            Management Organization of Main Construction Companies

 

3.1.            The Permit Holder shall, within one month after the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project.  The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

 

Works Areas of the Project

 

3.2.            No extension of the works boundary and works areas as indicated in Figure 2of this permit shall be permitted without the written approval of the Director.  To avoid environmental impacts to the study area as indicated in Figure 3 of this Permit, all key construction activities of Project shall be within the works boundary and the works areas.

 

            Submission on Rail Noise Mitigation Measures

 

3.3.            No later than one month before the commencement of construction of viaduct track superstructure sections of the Project, 4 sets of design drawings with explanatory statements showing details of mitigation measures to be used on all viaducts track superstructure sections of the Project.  Before submission to the Director, the drawings shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report.  The mitigation measures shall include, but are not limited to the following requirements: -

 

(a)                At least 1.2 metres high parapet walls above the safety walkway together with absorptive central plenum forming a noise reduction plenum system on all viaduct sections; and

 

(b)               Floating Slab Track (FST) at a resonant frequency of 16 Hz and low stiffness shear type base plates of at least 13kN/mm shall be in the track form design throughout the tunnel wherever there is existing or potential for future development along the alignment to ensure no impact arising from the ground borne noise and vibration.  Low vibration track (LVT) shall be used on viaducts.

 

            All mitigation measures set out in the drawings shall be fully and properly implemented.

 

 

            Submission of Drainage Layouts and Management Plan

 

3.4.            The Permit Holder shall, within one month after the commencement of construction of relevant part of the Project, submit to the Director for approval 4 sets of the drainage system layout and management plan for the relevant part of the works areas.  The submission shall include details of the facilities and measures to manage pollution arising from surface runoff from the works areas and to reduce surface runoff sediments and pollutants entering the watercourses.  Before submission to the Director, the drainage layouts and management plan shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report.  All measures as recommended in the approved drainage plan(s) shall be fully and properly implemented by the Permit Holder and any contractor working on the Project in accordance with the details set out in the submission throughout the construction period.

 

Submission of the Waste Management Plan (WMP)

 

3.5.            The Permit Holder shall, within one month after the commencement of construction of the Project, submit to the Director for approval 4 sets of Waste Management Plan (WMP) for the relevant part of the works areas.  Before submission to the Director, the WMP shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report.  The WMP shall describe the arrangements for avoidance, reuse, recovery and recycling, storage, collection, treatment including dewatering of spoil and disposal of different categories of waste to be generated from the construction activities and shall indicate the disposal location(s) of all surplus excavated spoil and other waste.  A trip ticket system shall be included in the WMP.  Surplus excavated spoil and other waste shall only be disposed of at designated public filling areas unless otherwise approved by the Director.  All measures recommended in the approved WMP shall be fully and properly implemented by the Permit Holder and any person working on the Project throughout the construction period.

 

3.6.            No disposal of waste, spoil, soil, excavated materials or materials alike arising from the Project shall be allowed at any locations unless otherwise approved by the Director under Condition 3.5 of this permit.  No such materials shall be dumped onto any ecologically sensitive areas identified in the EIA Report, unless such materials are necessary for the ecological enhancement measures required under this Permit.

 

Submission of the Contamination Assessment Plan (CAP)

 

3.7.            No later than one month before the commencement of construction at the potentially contaminated land as stated in section 10.7.6 of the EIA Report, the Permit Holder shall submit to the Director for approval 4 copies of the Contamination Assessment Plan (CAP) with exact sampling locations and testing parameters.  A site investigation shall be carried out in accordance with the approved CAP.  If land contamination is confirmed by the site investigation, the Permit Holder shall submit to the Director for approval 4 copies of a Remediation Assessment Plan (RAP) including a Contamination Assessment Report (CAR).  All remediation actions in the approved RAP shall be fully and properly implemented.  No work on the identified potentially contaminated sites shall be carried out unless and until the CAP and RAP submitted under this condition are approved by the Director.

 

            Submission of the Landscape Plan

 

3.8.            The Permit Holder shall, within six months after the commencement of construction of the Project, submit to the Director for approval 4 sets of landscape plan(s), of scale 1 to 1000 or other appropriate scale as agreed by the Director.  The drawings shall show the detailed landscape proposals based on the approved tree felling application during the construction and operational stages of the Project as stated in sections 12.10 to 12.11.10 of the EIA Report and shall include an implementation programme of landscape works, in particular not less than 4 hectares of compensatory planting within the works boundary. The submission shall be certified by ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report.  Additional copies may be required by the Director.  All measures recommended in the approved landscape plan(s) shall be fully and properly implemented in accordance with the details and time schedule set out in the submission.

 

Measures to Mitigate Ecological Impacts

 

3.9.            No construction access and activities of the Project shall be allowed on the ground surface of Long Valley area as shown in Figure 4 attached to this Permit.

 

3.10.        Contractor access shall be restricted to the works areas required for working along the whole alignment of the Project and particularly at Lok Ma Chau and San Tin where work is required in fishponds, unless otherwise agreed by the Director.

 

3.11.        Temporarily impacted fishponds within the works boundary and works areas as described in the submission under Condition 2.6 of the Environmental Permit No. EP-129/2002/A, or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance, shall be properly reinstated after construction is completed.

 

Measures to Mitigate Construction Noise Impacts

 

3.12.        To mitigate the construction noise impacts, gap-free noise barriers of material at least 10 kg/m2 shall be installed at locations as indicated in Figure 5 attached to this Permit and shall be maintained throughout the construction period.

 

3.13.        No movement of spoil to any areas other than the works areas of the Sheung Shui to Lok Ma Chau Spur Line as indicated in Figure 2 of this Permit shall be carried out during restricted hours [i.e. between 1900 to 0700 hours of any working days (from Monday to Saturday) and at any time on public holidays].

 

Measures to Mitigate Rail Noise Impacts

 

3.14.    All noise mitigation measures as recommended in the submission deposited under Condition 3.3 of this permit shall be fully and properly implemented.

 

Measures to Mitigate Water Quality Impacts

 

3.15.    Prior to the operation of the sewage treatment plant at the Lok Ma Chau station, not less than 5 hectares of reedbed/marsh area at location indicated in Figure attached to this Permit, shall be established.  The reedbed/marsh area shall include at least 2 hectares of reedbed for wastewater polishing purpose.  The implementation of measures for the establishment of the reedbed/marsh area shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA report.

 

3.16.        Works for diversion of Chau Tau Channel shall be carried out in the dry season (from November to March) only.

 

3.17.        To mitigate environmental impacts due to site runoff and other potential water pollution caused by construction activities, all mitigation measures as recommended in the approved drainage layouts and management plan under Condition 3.4 of this Permit shall be fully and properly implemented throughout the construction period.

 

Measures to Mitigate Landscape and Visual Impacts

 

3.18.        To mitigate landscape and visual impacts of the Project, mitigation measures described in Appendix A of this Permit shall be fully and properly implemented throughout the construction period.

 

24-hour Dedicated Hotline for Public Complaints and Enquiries

 

3.19.        The Permit Holder shall display conspicuously the telephone number of the 24-hour hotline, set up by the KCRC under Condition 3.35 of the Environmental Permit No. EP-129/2002/A , or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance, on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.

 

  

4.                  Environmental Monitoring and Audit of the Project

 

4.1.            The EM&A programme shall be implemented as set out in the EM&A Manual approved under Condition 2.3 of the Environmental Permit No. EP-129/2002/A, or where applicable the equivalent condition in any subsequent environmental permit amended by the Director under the Environmental Impact Assessment Ordinance.  Any changes to the EM&A programme shall be justified by the IEC as conforming to the requirements set out in the EM&A Manual and shall be submitted to the Director for approval.

 

4.2.            Four hard copies and one electronic copy of monthly EM&A Reports shall be submitted to the Director within 2 weeks after the end of the reporting month.  Additional copies of the submission shall be provided to the Director upon request from the Director.

 

4.3.            All environmental monitoring and audit results submitted under this Permit shall be true, valid and correct.

 

4.4.            The actions described in the Event/Action Plans of the EM&A Manual shall be fully and properly carried out, in accordance with the time frame(s) set out in the Event/Action Plan, or as agreed by the Director.

 

5.                   Electronic Reporting of EM&A Information

 

5.1.             To facilitate public inspection of the monthly EM&A Reports via the EIA Ordinance Internet Website and at the EIA Ordinance Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Condition 4.2 of this Permit.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of the EM&A Reports shall be included in the beginning of the document.  Hyperlinks to all figures, drawings and tables in the EM&A Reports shall be provided in the main text from where the respective references are made.  All graphics in the report shall be in interlaced GIF format unless otherwise agreed by the Director.  The content of the electronic copies of these Reports shall be the same as the hard copies.

 

5.2.             All environmental monitoring data described in Condition 5.1 of this permit shall be made available to the public via a dedicated web site, set up by the KCRC in the shortest possible time and in no event later than 2 weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director.



Notes :

 

1.                  This Environmental Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) Part C (Permit Conditions).  Any person relying on this Permit should obtain independent legal advice on the legal implications under the Ordinance, and that the following notes are for general information only.

 

2.                  If there is a breach of any condition of this Permit, the Director or his authorised officer may, with the consent of the Secretary, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorised officer.

 

3.                  The Permit Holder may apply under Section 13 of the Environmental Impact Assessment Ordinance (the “Ordinance”) to the Director for a variation of the conditions of this Environmental Permit.  The Permit Holder shall replace the original Permit displayed on the construction site, by the amended Permit.

 

4.                  A person who assumes responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the Ordinance to the Director for a further Environmental Permit.

 

5.                  Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for Environment, Transport and Works, suspend, vary or cancel this Permit.  The Permit that has been suspended, varied or cancelled shall be removed from the display at the construction site.

 

6.                  If this Permit is cancelled or surrendered during the construction or operation of the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued.  It is an offence under Section 26(1) of the Ordinance to construct or operate a designated project listed in Part I of Schedule 2 of the Ordinance without a valid environmental permit.

 

7.                  Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable :

 

(i)                  on a first conviction of indictment to a fine of $2 million and imprisonment for 6 months;

 

(ii)                on a second or subsequent conviction on indictment to a fine of $5 million and imprisonment for 2 years;

 

(iii)               on a first summary conviction to a fine at level 6 and imprisonment for 6 months;

 

(iv)              on a second or subsequent summary conviction to a fine of $1 million and imprisonment for 1 year; and

 

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied that the offence continued.

 

8.                  The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

 

9.                  The Notes are for general reference only and that the Permit Holder should refer to the EIA Ordinance for details and seek independent legal advice.

 

 

 

Environmental Permit No.: FEP-04/129/2002



Appendix A

 

 

Measures to Mitigate Landscape and Visual Impacts During Construction

 

At all parts of all works areas and construction sites, and throughout the full duration of the construction contract(s), the following mitigation measures shall be implemented to minimise the landscape and visual impact of the construction works:

(i)                      control of night time lighting;

(ii)          erection of decorative screen hoarding;

(vi)                  advance planting for screening;

(vii)                 minimising the height of temporary buildings;

(viii)               careful positioning of construction plant;

(ix)                  regular checks shall be carried out to ensure that the work site boundaries are not exceeded and that no damage is being caused to the surrounding areas;

(x)                    temporary construction sites shall be restored to standards as good as, or better than, the original condition;

(xi)                  replanting of disturbed vegetation shall be undertaken and this shall use predominantly native plant species;

(xii)                 topsoil shall be stripped and stored for re-use in the construction of the soft landscape works;

(xiii)               the locations of work sites associated with the proposed development shall be carefully selected to minimise the potential landscape and visual impacts of the proposed construction works; and

(xiv)               the potential for soil erosion shall be reduced at construction stage by minimising the extent of vegetation disturbance on site and by providing a protective cover (e.g. plastic sheeting or a grass cover established by hydroseeding) over any exposed ground.


Figure 1 | Figure 2 | Figure 3 | Figure 4 | Figure 5


[ Back to First Page ] / [ Back to Main Index ]