Environmental Permit No. FEP-07/364/2009/A
環境許可證編號 FEP-07/364/2009/A
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10條及12條
FURTHER
ENVIRONMENTAL PERMIT TO CONSTRUCT
A
DESIGNATED PROJECT
建造指定工程項目的新的環境許可證
A部 (許可證主要部分)
Pursuant
to Sections 10 and 12 of the Environmental Impact Assessment Ordinance (EIAO),
the Director of Environmental Protection (the Director) grants this further
environmental permit to Chun Wo -
CRGL - MBEC Joint Venture (Chun Wo Construction and Engineering Company
Limited, China Railway Group Limited and China Major Bridge Engineering Co.,
Ltd. as partners) (hereinafter referred to as the “Permit Holder”) to
construct the designated project described in Part B
subject to the conditions specified in Part C. The issue of this further environmental permit is based on the documents,
approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條及12條的規定,環境保護署署長(署長)將本新的環境許可證批予俊和-中國中鐡-中鐡大橋局聯營 (俊和建築工程有限公司、中國中鐡股份有限公司及中鐡大橋局股份有限公司為合伙人) (下稱 “許可證持有人”),以建造B部所說明的指定工程項目,但須遵守C部所列明的條件。本新的環境許可證是依據下列文件、批准或許可而簽發:
Application No. 申請書編號 |
FEP-120/2011 |
|||
Documents in the Register : 登記冊上的文件: |
1.
Central - Wan Chai Bypass and -
Environmental Impact
Assessment Report (July 2001) -
Environmental Monitoring
and Audit Manual -
Executive Summary 2.
The Director’s letter of approval of the
CWB&IECL EIA Report dated 31 August 2001 referenced (19) in Ax(2) to
EP2/H4/A/ 3.
Wan Chai Development Phase II and Central-Wan
Chai Bypass (Register No.:
AEIAR-125/2008) -
Environmental Impact
Assessment Report (December 2007) -
Environmental Monitoring
and Audit Manual -
Executive Summary -
Further information
received from the Civil Engineering and Development Department on 11 March
2008, 9 April 2008 and 14 November 2008 under Section 8(1) of the EIAO 4.
The Director’s letter of approval of the
WDII&CWB EIA Report dated 11 December 2008 referenced (85) in EP2/H4/S3/ 5.
Central Reclamation Phase III – Studies, Site
Investigation, Design and Construction (Register
No.: AEIAR-040/2001) -
Environmental Impact
Assessment Report (July 2001) -
Environmental Monitoring
and Audit Manual -
Executive Summary 6.
The Director’s letter of approval of the CRIII
EIA Report dated 31 August 2001 referenced (19) in Ax(4) to EP2/H4/C/09 II. 7.
Environmental Permit Issued – Permit No.:
EP-356/2009 issued to Civil Engineering and Development Department on 30 July
2009 for construction of the following designated projects: (i) Permanent and temporary reclamation works
including associated dredging works in Wan Chai Development Phase II (WDII)
area (referred to as “DP (ii) Wan Chai East Sewage Outfall (referred to as “DP (iii) Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui
(referred to as “DP 8.
Application for Environmental Permit including
all attachments submitted on 27 July 2009 (Application No.: AEP-364/2009). 9.
Environmental
Permit issued – Permit No.: EP-364/2009 issued on 17 August 2009. 10.
Application for Variation of Environmental
Permit including all attachments submitted on 28 July 2010 (Application No.
VEP-321/2010) 11.
Environmental
Permit issued – Permit No.: EP-364/2009/A issued on 4 August 2010. 12.
Application
for Further Environmental Permit including all attachments submitted on 1
February 2011 (Application No.: FEP-120/2011). 1. 中環及灣仔繞道和東區走廊連接路設計及建築工程 (登記冊編號: AEIAR─041/2001) -
環境影響評估報告 (2001年7月) [下稱「CWB&IECL環評報告」] -
環境監察審核手冊 -
行政摘要 2.
署長於 3.
灣仔發展計劃第二期及中環灣仔繞道 (登記冊編號: AEIAR-125/2008) ·
環境影響評估報告 (2007年12月) [下稱「WDII&CWB環評報告」] ·
環境監察審核手冊 ·
行政摘要 ·
土木工程拓展署根據條例第8(1)條於 4.
署長於 5.
中環填海計劃第III期 - 研究、實地堪測、設計與建築(登記冊編號:AEIAR-040/2001) ·
環境影響評估報告 (2001年7月) [下稱「CRIII環評報告」] ·
環境監察審核手冊 ·
行政摘要 6.
署長於 7.
已簽發的環境許可證– 許可證編號EP-356/2009; 於 (i)
在灣仔發展計劃第二期的永久及臨時填海工程(包括相聯挖泥工程) (WDII&CWB環評報告內稱“DP (ii) 灣仔東污水排水口(WDII&CWB環評報告內稱“DP (iii) 灣仔至尖沙咀海底輸水管的挖泥工程(WDII&CWB環評報告內稱“DP 8.
於 9.
已簽發的環境許可證 - 許可證編號 : EP-364/2009 於 2009年8 月17日簽發。 10.
於2010年 11.
已簽發的環境許可證 - 許可證編號 : EP-364/2009/A 於 2010年8 月4日簽發。 12.
於2011 年2月1 日提交的新的環境許可證申請文件包括所有附件(申請書編號: FEP-120/2011)。 |
|||
|
25
February 2011 2011年 2 月 25 日 |
|
||
|
Date 日期 |
|
(Ken Y.K. WONG ) Principal Environmental Protection
Officer for Director of Environmental Protection 環境保護署署長 (署理首席環境保護主任 黃耀光 代 行) |
|
PART
B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder
is the description of the designated project mentioned in Part A of this
environmental permit (hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱 |
Central-Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link (This designated
project is hereinafter referred to as “the Project”) - as part of
the “Central–Wan Chai Bypass including its Road Tunnel and Slip Roads” (the
CWB project) which is covered in the Environmental Permit No. EP-364/2009/A 中環灣仔繞道 – 北角段隧道及東區走廊連接路 (本指定工程項目下稱“工程項目”) -
此工程為 “中環灣仔繞道(包括其行車隧道及連接路)” (CWB工程項目)的一部份,受已簽發的環境許可證 - 許可證編號 : EP-364/2009/A的管制 |
Nature of Designated Project 指定工程項目的性質 |
The
Project is a part of the Central-Wan Chai Bypass project. (The CWB project
will involve construction of a trunk road and its road tunnel more than 此工程項目是中環灣仔繞道工程項目的一部份。(CWB工程項目涉及興建一條主幹道;及其入口之間的長度超過 |
Location of Designated Project 指定工程項目的地點 |
North Point
and Central. The location of
the Project is shown in Figures 北角和中環。 工程項目的地點展示於本許可證圖 |
Scale and Scope of Designated Project |
The scope of
the Project mainly includes: ·
Construction of a 300-metre-long
tunnel at North Point; ·
Construction of an approach road to
the tunnel; ·
Modification of the section of Island
Eastern Corridor between ·
Modification of the junction of ·
Demolition of Rumsey Street Flyover
eastbound in Central; ·
Sub-structure works of the ·
Associated works including landscaped
deck, noise barriers, noise semi-enclosures, road drainage and landscaping
works. (part of the CWB project ) Remarks: l The
permanent and temporary reclamation and associated dredging works related to
the CWB construction are separately covered by the environmental permit No. EP-356/2009
issued to the Civil Engineering and Development Department (CEDD). 工程項目的範圍主要包括: ·
建造一段位於北角的 ·
建造與隧道接駁的連接路; ·
改建介乎興發街與保良局余李慕芬紀念學校之間的一段東區走廊; ·
改建維園道與興發街之交界處; ·
清拆中環林士街天橋東行線之橋面; ·
東面通風大樓底部構造及行政大樓地基工程; 以及 ·
相關工程,包括園景平台、隔音屏障、半密封式隔音罩、道路排水及綠化等工程。 (CWB工程項目的一部份) 備註: l
中環灣仔繞道相關的永久及臨時填海工程(包括相聯挖泥工程) 已包括在簽發與土木工程拓展署的環境許可證(許可證編號: EP-356/2009)。 |
1. General
Conditions
1.1
The
Permit Holder and any person working on the Project shall comply with all conditions
set out in this Permit. Any non-compliance by any person may constitute a
contravention of the Environmental Impact Assessment Ordinance (Cap.499) and
may become the subject of appropriate action being taken under the Ordinance.
1.2
The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Air Pollution Control Ordinance (Cap. 311), Water Pollution
Control Ordinance (Cap. 358), Noise Control Ordinance (Cap. 400), and Waste
Disposal Ordinance (Cap. 354). This
Permit does not of itself constitute any ground of defense against any
proceedings instituted under any legislation or imply any approval under any
legislation.
1.3
The Permit Holder shall make copies of
this Permit together with all documents referred to in this Permit and the
documents referred to in Part A of this Permit
readily available at all times for inspection by the Director or his authorized
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
1.4
The Permit Holder shall give a copy of
this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated by
the Permit. The site(s) refers to site(s) of construction of the Project and
shall mean the same hereafter.
1.5
The Permit Holder shall display
conspicuously a copy of this Permit on the construction site(s) at all
vehicular site entrances/exits or at a convenient location for public’s
information at all times. The Permit Holder shall ensure that the most updated
information about the Permit, including any amended Permit, is displayed at
such locations. If the Permit Holder surrenders a part or the whole of this
Permit, the notice he sends to the Director shall also be displayed at the same
locations as the original Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site(s).
1.6
The Permit Holder shall construct the
Project in accordance with the project description in Part
B of this Permit (hereafter referred to as “the Project”).
1.7
The Permit Holder shall ensure that the
Project is designed and constructed in accordance with the relevant information
and recommendations described in the approved CWB&IECL EIA Report (Register
No. AEIAR-041/2001), the approved WDII&CWB EIA Report (Register No.
AEIAR-125/2008), the approved CRIII EIA Report (Register No. AEIAR-040/2001),
the Environmental Permit No.: EP-356/2009 issued on 30 July 2009 for marine
works as described in Part A of this Permit; the
Application for Environmental Permit including all attachments (Application No.
AEP-364/2009); the Environmental Permit No. EP-364/2009 issued on 17 August
2009; the Application for Variation of Environmental Permit including all
attachments (Application No. VEP-321/2010); the amended Environmental Permit
No. EP-364/2009/A issued on 4 August 2010; the Application for Further
Environmental Permit including all attachments (Application No. FEP-120/2011)
and other relevant documents in the Register, the information and mitigation
measures described in this Permit, mitigation measures to be recommended in
submissions that shall be deposited with or approved by the Director as a
result of permit conditions contained in this Permit, and mitigation measures
to be recommended under on-going surveillance and monitoring activities during
all stages of the Project. Where recommendations referred to in the documents
of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit. The Project is part of the CWB project. As stated in the Application for
Environmental Permit including all attachments (Application No.: AEP-364/2009)
for the CWB project, the CWB project is covered by the approved CWB&IECL
EIA Report (Register No. AEIAR-041/2001) and the WDII&CWB EIA Report (Register
No. AEIAR-125/2008) mentioned in Part A of this
Permit. The corresponding coverage
of the two EIA reports is shown in Figure
1.8
All deposited submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within one month of the receipt of the Director’s
comments or otherwise specified by the Director.
1.9
All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C
of this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap.499). All submissions or any
variation of the submissions shall be certified by the Environmental Team (ET)
Leader and verified by the Independent Environmental Checker (IEC) referred to
in Conditions 2.1 and 2.2 below before submitting to the Director under this
Permit.
1.10
The Permit Holder shall release all
finalized submissions, as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of the submissions.
1.11
All submissions to the Director required
under this Permit shall be delivered either in person or by registered mail to
the Environmental Impact Assessment Ordinance Register Office (currently at
27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic
copies of all finalized submissions required under this Permit shall be
prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in
Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by
the Director and shall be submitted at the same time as the hard copies.
1.12
The Director shall be notified in
writing the commencement date of construction of the Project no later than one
month prior to the commencement of construction of the Project. The Director
shall be notified in writing immediately if there is any change of the
commencement date of the construction. (see note 8)
1.13
For the purpose of this Permit,
“commencement of construction” does not include works related to site clearance
and preparation or other works as agreed by the Director.
1.14
This Permit shall not remove the
responsibility of Highways Department and any person working on the
“Central-Wan Chai Bypass including its Road Tunnel and Slip Roads” (the “CWB
project”) to comply with the conditions set out in Part C of the Environmental
Permit No. EP-364/2009 or where applicable any subsequent environmental permit
(EP) amended by the Director under the Ordinance.
2
Special Conditions
Submissions or Measures to be implemented before Construction of the Project
Employment of Environmental Monitoring
and Audit (EM&A) Personnel
Environmental Project Committee (ENPC)
(a) the ET Leader;
(b) the IEC; and
(c) the permit holders of any
environmental permit(s) and further environmental permit(s), for the whole
Project.
The Community Liaison Group formed under
Condition 2.4 of this Permit shall also work under the ENPC set-up to
facilitate any necessary liaison works to address potential cumulative
environmental impact issues arising from the whole Project. The ENPC shall make recommendation and
update under Condition 2.5(a) of this Permit on how to enhance the monitoring
and audit of the environmental performance of the whole Project on top of
requirements as set out in Conditions 3.1 to 4.3 of
this Permit or corresponding requirements set out under subsequent
Environmental Permits issued for the whole Project. (see notes 7 and 8)
Community Liaison Group
2.4
A
Community Liaison Group (CLG) comprising representatives from the relevant
concerned and affected parties, including owners’ corporations, management
offices, local committees and schools of affected areas, including the North
Point and Tin Hau areas, shall be set up, to facilitate
communication, enquiries and complaints handling on all environmental issues,
including the follow up on the implementation of remedial mitigation
measures. The CLG shall be set up
before the commencement of construction of the relevant component(s) of the
WDII and CWB project. The Director shall be notified with the actual date of
setting up the CLG, the membership, the terms of reference and the contact
details. A designated complaint
hotline shall also be set up for the Project to address such concerns and
complaints in an efficient manner. The detailed arrangements of the CLG
shall be reported to the ENPC and its activities be reflected as update under
Condition 2.5(a) of this Permit. (see notes 7 and 8)
Submission of Updated EM&A Manual
2.5
Four
hard copies and one electronic copy of an updated EM&A Manual for the
Project shall be submitted, no later than one month before the commencement of
construction of the Project, to the Director for approval. The updated EM&A
Manual shall:
(a)
make
recommendations on how to take into account the ENPC and Community Liaison
Group requirements as stipulated in Conditions 2.3 and 2.4 of this Permit respectively;
(b)
include
a real-time on-site monitoring system of the noise level around the works sites
at North Point and Tin Hau areas during the construction phase; and
(c)
take
into account the relevant EM&A requirements from the approved CWB&IECL
EIA Report (Register No. AEIAR-041/2001), the approved WDII&CWB EIA Report
(Register No. AEIAR-125/2008), the latest works schedules, division of
responsibilities among different contracts (if any) in the Project, latest
project information, latest environmental mitigation measures including the
restriction imposed on the use of pneumatic breakers to demolish the existing
Island Eastern Corridor as set out in Condition 2.9(a) of this Permit
Before submission to the Director, the
updated EM&A Manual shall be certified by the ET and verified by the IEC as
conforming to the relevant information and recommendations contained in the
approved CWB&IECL EIA Report (Register No. AEIAR-041/2001), the approved
WDII&CWB EIA Report (Register No: AEIAR-125/2008), the approved CRIII EIA
Report (Register No. AEIAR-040/2001), the application documents for
environmental permit including all attachments (Application No. AEP-364/2009)
and other relevant documents in the Register. All measures recommended in the updated
EM&A Manual approved under this Condition shall be fully and properly
implemented according to the requirements and time schedule(s) set out in the updated
EM&A Manual approved under this Condition (hereinafter referred to as the
“updated EM&A Manual”).
(see note 8)
Management
Organization of Main Construction Companies
2.6
The
Permit Holder shall, no later than one month before the commencement of
construction of the Project covered by this Permit, inform the Director in
writing the management organization of the main construction companies and/or
any form of joint ventures associated with the construction of the Project. The
submitted information shall include at least an organization chart, names of
responsible persons and their contact details. The management organization
information submitted under this Condition shall contribute towards the
relevant part of the ENPC and CLG that will set up under Conditions 2.3 and 2.4
of this Permit. (see note 8)
Submission
of Works Schedule and Location Plans
2.7
The
Permit Holder shall deposit a detailed works schedule of the Project with the
Director at least one month before the commencement of the works of the
Project. The schedule shall include an updated works programme indicating
dates of commencement of construction activities. This schedule to be submitted shall
govern the various milestones and anticipated schedule of submissions as
reflected in Conditions 2.5, 2.6, 2.8, 2.9, 2.13, 3.3, 3.4 and 4.2 of this Permit. (see note 8)
2.8
The Permit
Holder shall deposit with the Director location and layout plans in the scale
of 1:1,000 or other appropriate scale of the Project at least two weeks before
the commencement of the works of the Project. The plans shall be
submitted with an explanatory statement detailing the works boundaries, the
works areas, vertical and horizontal alignments of the CWB, its tunnel, slip
roads, ventilation buildings/vent shaft(s) and any other major facilities; and
the locations of key environmental mitigation measures, including landscaped
deck at eastern tunnel portal, noise semi-enclosures and barriers and low noise
road surfacing as mentioned in Conditions 2.10 and 2.11 of this Permit (see
note 8)
Measures to Mitigate Construction Noise Impact
2.9
To
mitigate construction noise impact, the Permit Holder shall deposit with the
Director, at least two weeks prior to the commencement of construction of the
corresponding component(s) of the Project, four hard copies and one electronic
copy of the construction noise management plan, consisting of layout plan(s) in
the scale of 1:1,000 or other appropriate scale and explanatory statement(s)
showing the noise mitigation measures to include:
(a)
the use of pneumatic breakers, if required to demolish
the existing Island Eastern Corridor, to be confined to the period from 0900 to
1700 hours on weekdays (Monday to Friday), and the pneumatic breakers shall not
be used any time on Saturdays, Sundays and general holidays, and during examination hours of the schools affected by the works site,
including:
(i)
Hong Kong Baptist Church Henrietta
Secondary School; and
(ii)
Po Leung Kuk Yu
(b)
the installation of two types of
noise barriers for particular items of powered mechanical equipments and
construction works at the locations
as shown in Figure 2 of this Permit, including that temporary noise barriers (
(c)
the
use of movable/temporary noise barriers, the use of quiet powered mechanical
equipments and the adoption of multiple-phase construction schedules, where
appropriate.
Measures to Mitigate Operational Noise Impact
2.10
To
mitigate traffic noise from road operation, the following noise barriers and semi-enclosures
shall be installed before the commencement of operation of the road project
unless otherwise specified in this Permit. The locations and indicative designs
of the noise semi-enclosures and barriers are shown in Figures
(a)
about
(b)
about
(c)
about
(d)
about
(e)
about
(f)
about
2.11
To
mitigate traffic noise from road operation, low noise road surfacing
shall be paved on the sections
of the CWB with speed limit of
Measures to Mitigate
Air Quality Impact
2.12
If the
Project involves construction of any air ventilation system and/or air
mitigation measures for the operational phase of the CWB project, at
least one month prior to the commencement of construction of the corresponding
component(s) of air ventilation system and air mitigation measures for the
operational phase of the CWB project, four hard copies and one electronic copy
of the operational air quality management plan shall be deposited with the
Director to manage and mitigate operational air quality impact. The operational air quality management
plan shall consist of design drawings in the scale of 1:1,000 or other
appropriate scale and explanatory statements showing air quality mitigation
measures include:
(a)
the
construction of the West Ventilation Building (WVB) at the location as shown in
Figure 1a of this Permit, and that WVB shall follow the exhaust related design
criteria as shown in Table 1a of this Permit;
(b)
the
construction of the Central Ventilation Building (CVB) at the location as shown
in Figure
(c)
the
construction of the East Ventilation Building (EVB) and its vent shaft at the
locations as shown in Figure 1a of this Permit, and that EVB shall follow the
exhaust related design criteria as shown in Table 1b of this Permit;
(d)
an
electrostatic precipitator system shall be installed to reduce the dust
emission from the EVB operation.
The electrostatic precipitator system shall be designed to have a dust
removal efficiency of 80% to reduce the level of respirable suspended
particulates; and
(e)
the
ventilation system of the Eastern Portal of the CWB Tunnel shall follow the
zero portal emission design as described in Section
The submission(s) shall be certified by the
ET Leader and verified by the IEC as conforming to the relevant information and
recommendations contained in the approved CWB&IECL EIA Report (Register No.
AEIAR-041/2001), the approved WDII&CWB EIA Report (Register No.
AEIAR-125/2008) and the approved CRIII EIA Report (Register No. AEIAR-040/2001)
before deposit with the Director. All measures recommended in the finalised
submission(s) under this Condition shall be fully and properly implemented.
Measures covered by other pollution control Ordinances shall not be included in
the submission(s) on the operational air quality management plan. (see note 8)
Measures to Mitigate Landscape and
Visual Impact
2.13
To
reduce the landscape and visual impact during construction and operation stages
of the Project, the Permit Holder shall implement a series of landscape and
visual mitigation measures. The
Permit Holder shall, at least one month before the commencement of
corresponding parts of landscape works of the Project, deposit with the
Director four hard copies and one electronic copy of landscape plan(s). The landscape plan(s) shall show the
design details, locations, implementation programme, maintenance and management
schedules, and drawings in the scale of 1:1,000 or other appropriate scale of
the landscape and visual mitigation measures of the Project. Before submission
to the Director, the landscape plan(s) shall be certified by the ET Leader and
verified by the IEC as conforming to the relevant information and
recommendations contained in the approved CWB&IECL EIA Report (Register No.
AEIAR-041/2001) and the WDII&CWB EIA Report (Register No. AEIAR-125/2008).
All measures recommended in the finalised submission(s) under this Condition
shall be fully and properly implemented. (see note 8)
2.14
The
landscape plan(s) to be submitted under Condition 2.13 of this Permit shall
include measures to mitigate the landscape and visual impact of the road
traffic noise semi-enclosures and barriers. The noise semi-enclosures and barriers
shall mainly compose of:
(a)
transparent
panels, translucent panels and/or green roof with translucent skylight in the
upper part where appropriate; and
(b)
green
panels with planters in the lower part where appropriate,
as shown in Figures
3
Environmental Monitoring and
Audit Requirements
3.1
The
EM&A programme shall be implemented in accordance with the procedures and
requirements as set out in the updated EM&A Manual approved under Condition
2.5 of this Permit. Any major changes to the programme
shall be justified by the ET Leader and verified by the IEC as conforming to
the information and requirements contained in the updated EM&A Manual
approved under Condition 2.5 of this Permit before submission to the Director for
approval. The EM&A programme
shall include, among other items, the air quality and noise monitoring and
audit details to cover the different construction phases; and the appropriate
timing for putting in place a real-time on-site monitoring system of the noise
level around the works sites at North Point and Tin Hau areas during the
construction phase of the Project, but the real-time monitoring system shall be
in place no later than two weeks before the commencement date of demolition
works of the existing Island Eastern Corridor. The real-time noise monitoring results
shall be presented in the Internet website as described in Condition 4.2 of
this Permit. (see notes 7 and 8)
3.2
Samples,
measurements and necessary remedial actions shall be taken in accordance with
the requirements of the updated EM&A Manual by:
(a)
conducting baseline
environmental monitoring;
(b)
conducting
impact monitoring;
(c)
carrying out
remedial actions described in Event/Action Plans of the updated EM&A Manual
approved
under Condition 2.5 of this Permit in accordance with the time frames set out in Event/Action Plans, or as
agreed by the Director, in case where specified criteria in the updated
EM&A Manual approved under Condition 2.5 of this Permit are exceeded; and
(d)
logging and
keeping records of details of (a) to (c) above for all parameters within 3 working
days of collection of data or completion of remedial action(s), for the purpose
of preparing and submitting the monthly EM&A Reports and to make available
for inspection on site.
(see notes 7 and
8)
3.5
All
environmental monitoring and audit data submitted under this Permit shall be
true, valid and correct. (see notes 7 and 8)
4
Electronic Reporting of
EM&A Information
4.1
To facilitate
public inspection of the Baseline Monitoring Report and regular EM&A
Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hardcopies as described in Conditions 3.3 and 3.4 of this Permit. For the HTML version, a
content page capable of providing hyperlink to each section and sub-section of
these Reports shall be included in the beginning of the document. Hyperlinks to
all figures, drawings and tables in these Reports shall be provided in the main
text from where the respective references are made. All graphics in these
Reports shall be in interlaced GIF format unless otherwise agreed by the
Director. The content of the electronic copies of these Reports must be the
same as the hardcopies. (see note 8)
4.3
The
Internet website as described in Condition 4.2 above shall enable user-friendly public access to the
monitoring and project data including the approved EIA Reports and the
environmental permit(s) of the Project. The Internet website shall have
features capable of:
(a)
providing access to all environmental
monitoring data collected since the commencement of works;
(b)
searching by date;
(c)
searching by types of monitoring data (noise
and air quality); and
(d)
hyperlinks to relevant monitoring data after
searching;
or otherwise as agreed
by the Director. (see note 9)
Notes :
1.
This Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project)
and PART C (Permit
Conditions). Any person relying on this permit should obtain independent
legal advice on the legal implications under the Ordinance, and the following
notes are for general information only.
2.
If there is a breach of any conditions of this Permit, the Director or
his authorized officer may, with the consent of the Secretary for the
Environment, order the cessation of associated work until the remedial action
is taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
3. The Permit Holder may apply
under Section 13 of the Ordinance to the Director for a variation of the
conditions of this Permit. The Permit Holder shall replace the original
permit displayed on the construction site by the amended permit.
4. A person who assumes the
responsibility for the whole or a part of the designated project(s) may, before he assumes responsibility of the designated project(s), apply under Section 12 of the Ordinance to the Director for a further
environmental permit.
5. Under Section 14 of the
Ordinance, the Director may with the consent of the Secretary for the
Environment, suspend, vary or cancel this Permit. The suspended, varied
or cancelled Permit shall be removed from display at the construction site.
6. If this Permit is cancelled
or surrendered during construction of the Project, another environmental permit
must be obtained under the Ordinance before the Project could be
continued. It is an offence under section 26(1) of the Ordinance to
construct or operate a designated project listed in Part I of schedule 2 of the
Ordinance without a valid environmental permit.
7. Highways Department (HyD), the Holder of Environmental
Permit (EP) No. EP-364/2009, is required under EP-364/2009, or any subsequent
EP amended by the Director under the Ordinance:
(i)
to establish an
Environmental Team (ET) which shall be headed by an ET Leader;
(ii) to employ an Independent Environmental Checker (IEC);
(iii) to liaise with the Holder
of Environmental Permit No. EP-356/2009 on to jointly set up an Environmental
Project Committee (ENPC); and
(iv) to liaise with the Holder
of Environmental Permit No. EP-356/2009 to jointly set up a Community Liaison
Group (CLG),
for the CWB project.
8. HyD, the Holder of EP-364/2009 is required under EP-364/2009, or any
subsequent EP amended by the Director under the Ordinance:
(i)
to
notify the Director in writing the commencement date of construction of the CWB
project;
(ii)
to notify the Director the date of setting up the ENPC;
(iii)
to notify the Director the date of setting up the CLG;
(iv)
to submit to the Director for approval the updated Environmental
Monitoring and Audit Manual (updated EM&A Manual);
(v)
to inform the Director in writing the management organization of the
main construction companies and/or any form of joint ventures associated with
the construction of the CWB project;
(vi)
to deposit with the Director a detailed works schedule and location
plans;
(vii)
to deposit with the Director a
construction noise management plan;
(viii) to
deposit with the Director an operational air quality management plan;
(ix)
to deposit with the Director landscape
plan(s);
(x)
to deposit with the Director an
additional mitigation plan for Slip Road 8;
(xi)
to submit to the
Director the
Baseline Monitoring Report; and
(xii)
to submit to the Director the monthly
EM&A Reports,
for the CWB project.
All submissions or any variation of the
submissions shall be certified by the ET Leader(s) and verified by the IEC
before submitting to the Director.
9. HyD,
the Holder of Environmental Permit EP-364/2009, is required under EP-364/2009,
or any subsequent EP amended by the Director under the Ordinance:
(i)
to implement the proposed construction works of CWB including its Road
Tunnel and Slip Roads, ventilation buildings and vent shaft(s) at the location
shown in Figure 1 of EP-364/2009 together with the relevant environmental
mitigation measures; and
(ii)
to set up a dedicated web site and notify the Director in writing the Internet
address where the environmental monitoring and project data is to be placed,
for the CWB project.
10. Any person who constructs
the Project contrary to the conditions in the Permit, and is convicted of an
offence under the Ordinance, is liable:-
(i)
on a first conviction on
indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $ 5 million and to imprisonment for 2
years;
(iii)
on a first summary
conviction to a fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent
summary conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any case where the
offence is of a continuing nature, the court or magistrate may impose a fine of
$ 10,000 for each day on which he is satisfied the offence continued.
11. The Permit Holder may appeal against any condition of this Permit under
Section 17 of the Ordinance within 30 days of receipt of this Permit.
12. The Notes are for general
reference only and that the Permit Holder should refer to the EIA Ordinance for
details and seek independent legal advice.
Environmental Permit No. FEP-07/364/2009/A
環境許可證編號 FEP-07/364/2009/A
| Figure 1a | Figure 1b | Figure 2 | Figure 3 |
Figure 4a | Figure 4b |
Figure 4c | Figure 4d |
Figure 4e | Figure 4f |
[
Back to First Page ] / [ Back to Main
Index ]
Table 1a: Exhaust
Related Design Criteria of the
|
Maximum capacity (m3s-1) |
Exit velocity (m s-1) |
Minimum discharge height (meter above ground) |
Exhaust direction |
|
420 |
8 |
15 |
Vertical |
Notes: * This
Table shall be read in conjunction with
Condition 2.12 and Figure
** The vent shaft will be incorporated within the WVB.
(see notes 8 and 9)
Table 1b Exhaust
Related Design Criteria of the Central Ventilation Building and the East
Ventilation Building and its Vent Shaft (based on Table 3.11 of the
WDII&CWB EIA Report (Register No. AEIAR-125/2008)*
|
Cross-sectional area of stack (m2) |
Exit velocity (m s-1) |
Minimum mid-discharge height (meter above ground) |
Exhaust direction |
|
219 |
8 |
17.5 |
Vertical |
Vent shaft of
the (EVB)*** |
94 |
8 |
16.25 |
Inclined 45 degree upward
(discharge towards sea direction) |
Notes: * This
Table shall be read in conjunction with
Condition 2.12 and Figure
** The vent shaft of CVB will be incorporated within the
CVB.
*** The vent shaft of EVB will be separated from the EVB and located at the eastern breakwater of the Causeway Bay Typhoon Shelter.
(see notes 8 and 9)