Environmental Permit
No. FEP-05/356/2009
環境許可證編號 FEP-05/356/2009
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10條及12條
FURTHER
ENVIRONMENTAL PERMIT TO CONSTRUCT
DESIGNATED
PROJECT
建造指定工程項目的新的環境許可證
A部 (許可證主要部分)
Pursuant
to Sections 10 and 12 of the Environmental Impact Assessment Ordinance (EIAO),
the Director of Environmental Protection (the Director) grants this further environmental
permit to Gammon-Leader Joint
Venture (Gammon Construction
Limited and Leader Civil Engineering Corp. Ltd. as partners) (hereinafter
referred to as the "Permit Holder") to construct the designated
project described in Part B subject to the
conditions specified in Part C. The issue of this further environmental permit is based on the documents,
approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條及12條的規定,環境保護署署長(署長)將本新的環境許可證批予金門-利達聯營(金門建築有限公司及利達土木工程有限公司為合伙人)(下稱 “許可證持有人”),以建造B部所說明的指定工程項目,但須遵守C部所列明的條件。本新的環境許可證是依據下列文件、批准或許可而簽發:
Application No. 申請書編號 |
FEP-123/2011 |
|||
Documents in the Register : 登記冊上的文件: |
1.
Wan Chai
Development Phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) -
Environmental Impact Assessment Report (December 2007) -
Environmental Monitoring and Audit Manual -
Executive Summary -
Further information received from the Civil
Engineering and Development Department on 11 March 2008, 9 April 2008 and 14
November 2008 under Section 8(1) of the EIAO 2.
The
Director’s letter of approval of the EIA Report dated 11 December 2008
referenced (85) in EP2/H4/S3/ 3.
Application
for Environmental Permit and attachments submitted on 3 July 2009
(Application No.: AEP-356/2009) 4.
Environmental
Permit issued – Permit No.: EP-356/2009 issued on 30 July 2009. 5. Application
for Further Environmental Permit and attachments submitted on 28 February 2011
(Application No.: FEP-123/2011) 1. 灣仔發展計劃第二期及中環灣仔繞道 (登記冊編號: AEIAR-125/2008) ·
環境影響評估報告 (2007年12月) [下稱「環評報告」] ·
環境監察審核手冊 ·
行政摘要 ·
土木工程拓展署根據條例第8(1)條於 2. 署長於 3.
於2009 年7 月3 日提交的環境許可證申請文件及附件(申請書編號: AEP-356/2009) 4.
已簽發的環境許可證 - 許可證編號 : EP-356/2009 於 5.
於2011 年2 月28 日提交的新的環境許可證申請文件及附件(申請書編號: FEP-123/2011。
[下稱 “申請書編號 FEP-123/2011”] |
|||
|
24 March 2011 2011 年 3 月 24 日 |
|
||
|
Date 日期 |
|
(Ken Y.K. WONG) Principal Environmental Protection
Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任 黃耀光 代行) |
|
PART B
(DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder
is the description of the designated project mentioned in Part
A of this environmental permit (hereinafter referred to as “the
Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱 |
Wan Chai Development Phase II -
Central-Wan Chai Bypass over MTR Tsuen Wan Line (Contract No.
HK/2010/06)-Marine Work (The
designated project is hereafter collectively referred to as “the Project”) – as part of the “permanent and
temporary reclamation works including associated dredging works in Wan Chai
Development Phase II (WDII) area”
(i.e. part of the designated project
referred to as “DP 灣仔發展計劃第二期-橫跨港鐵荃灣線段的中環灣仔繞道(合約號碼 HK/2010/06) -海事工程 (上述指定工程項目以下統稱“工程項目”) - 此工程為 “灣仔發展計劃第二期的永久及臨時填海工程(包括相聯挖泥工程)” 的一部份。(亦是環評報告內稱 “DP |
Nature of Designated Project 指定工程項目的性質 |
The
Project is a part of the following designated projects: (i) reclamation
works (including associated dredging works) more than (ii) dredging
operations which are less than in
the Wan Chai Development Phase II and Central-Wan Bypass (WDII & CWB)
project 此工程項目屬於灣仔發展計劃第二期及中環灣仔繞道中,以下指定工程項目的一部份: (i) 面積超過 (ii)
距離海水進水口少於 |
Location of Designated Project 指定工程項目的地點 |
At the harbour
side of Wan Chai (West) Sewage Screening Plant and to the west of Hong Kong
Convention and Exhibition Centre. The location
of the Project is shown in Figure 1a
and Figure 1b of this Permit. 位於灣仔西污水處理廠對出海面及香港會議展覽中心(“會展”)西面。 |
Scale and Scope of Designated Project |
The scope of the
Project mainly includes: ·
installation of
marine bored piles along both sides of the existing MTR immersed tube; ·
installation of
two rows of steel sheet piles along the bored piles walls; ·
associated
dredging works approximately (i.e. part of the
designated project referred to as “DP 工程項目的範圍主要包括: ·
在現有港鐵荃灣線管道兩旁安裝鑽孔樁。 ·
沿鑽孔樁安裝兩行板樁。 ·
為安裝預制式混凝土箱形組件, 於荃灣線管道兩旁進行相聯挖泥工程 (大約一萬八千立方米)。 (亦是環評報告內稱 “DP |
1. General
Conditions
1.1
The
Permit Holder and any person working on the Project shall comply with all conditions
set out in this Permit. Any non-compliance by any person may constitute a
contravention of the Environmental Impact Assessment Ordinance (Cap.499) and
may become the subject of appropriate action being taken under the Ordinance.
1.2
The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Air Pollution Control Ordinance (Cap. 311), Water Pollution
Control Ordinance (Cap. 358), Noise Control Ordinance (Cap. 400), Dumping at
Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself
constitute any ground of defense against any proceedings instituted under any
legislation or imply any approval under any legislation.
1.3
The Permit Holder shall make copies of
this Permit together with all documents referred to in this Permit and the
documents referred to in Part A of this Permit
readily available at all times for inspection by the Director or his authorized
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
1.4
The Permit Holder shall give a copy of
this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated by
the Permit. The site(s) refers to site(s) of construction of the Project and
shall mean the same hereafter.
1.5
The Permit Holder shall display
conspicuously a copy of this Permit on the construction site(s) at all
vehicular site entrances/exits or at a convenient location for public’s
information at all times. The Permit Holder shall ensure that the most updated
information about the Permit, including any amended Permit, is displayed at
such locations. If the Permit Holder surrenders a part or the whole of this
Permit, the notice he sends to the Director shall also be displayed at the same
locations as the original Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site(s).
1.6
The Permit Holder shall construct the
Project in accordance with the project description in Part
B of this Permit (hereafter referred to as “the Project”).
1.7
The Permit Holder shall ensure that the
Project is designed and constructed in accordance with the information and
recommendations described in the approved EIA Report (Register No.
AEIAR-125/2008), the Application for Environmental Permit (Application No. AEP-356/2009),
the Environmental Permit No. EP-356/2009 issued on 30 July 2009, the
Application for Further Environmental Permit (Application No. FEP-123/2011) and
other relevant documents in the Register, the information and mitigation
measures described in this Permit, mitigation measures to be recommended in
submissions that shall be deposited with or approved by the Director as a
result of permit conditions contained in this Permit, and mitigation measures
to be recommended under on-going surveillance and monitoring activities during
all stages of the Project. Where recommendations referred to in the documents
of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit.
1.8
All deposited submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within one month of the receipt of the
Director’s comments or otherwise specified by the Director.
1.9
All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C
of this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap.499). All submissions or any
variation of the submissions shall be certified by the Environmental Team (ET)
Leader and verified by the Independent Environmental Checker (IEC) referred to
in Conditions 2.1 and 2.2 below before submitting to the Director under this
Permit.
1.10
The Permit Holder shall release all
finalized submissions, as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of the submissions.
1.11
All submissions to the Director required
under this Permit shall be delivered either in person or by registered mail to
the Environmental Impact Assessment Ordinance Register Office (currently at
27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic
copies of all finalized submissions required under this Permit shall be
prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in
Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by
the Director and shall be submitted at the same time as the hard copies.
1.12
The Director shall be notified in
writing the commencement date of construction of the Project no later than one month
prior to the commencement of construction of the Project. The Director shall be
notified in writing immediately if there is any change of the commencement date
of the construction. (see note 8)
1.13
For the purpose of this Permit,
“commencement of construction” does not include works related to site clearance
and preparation or other works as agreed by the Director.
1.14
This Permit shall not remove the
responsibility of Civil Engineering and Development Department and any person
working on the marine works of Wan Chai Development Phase II and Central-Wan Chai
Bypass Project (the “WDII&CWB project”) to comply with the conditions set
out in Part C of the Environmental Permit No. EP-356/2009 or where applicable
any subsequent environmental permit (EP) amended by the Director under the
Ordinance.
2
Special Conditions
Submissions or Measures to be implemented before Construction of the Project
Employment of Environmental Monitoring
and Audit (EM&A) Personnel
Environmental Project Committee
(ENPC)
(a) the ET Leader;
(b) the IEC; and
(c) the permit holders of any environmental
permit(s) and further environmental permit(s) for the whole Project.
The Community Liaison Group formed under
Condition 2.4 of this Permit shall also work under the ENPC set-up to
facilitate any necessary liaison works to address potential cumulative
environmental impact issues arising from the whole Project. The ENPC shall make recommendation and
update under Condition 2.5(a) of this Permit on how to enhance the monitoring
and audit of the environmental performance of the whole Project on top of requirements
as set out in Conditions 3.1 to 4.3 of this Permit or corresponding
requirements set out under subsequent Environmental Permits issued for the
whole Project. (see notes 7 and 8)
Community
Liaison Group
2.4
A
Community Liaison Group (CLG) comprising representatives from the relevant
concerned and affected parties, including owners’ corporations, management
offices, local committees and schools of affected areas, including the North
Point and Tin Hau areas, shall be set up, to facilitate communication,
enquiries and complaints handling on all environmental issues, including the
follow up on the implementation of remedial mitigation measures. The CLG shall be set up before the
commencement of construction of the relevant component(s) of the WDII and CWB project.
The Director shall be notified with the actual date of setting up the CLG, the
membership, the terms of reference and the contact details. A designated complaint hotline shall also
be set up for the Project to address such concerns and complaints in an
efficient manner. The
detailed arrangements of the CLG shall be reported to the ENPC and its
activities be reflected as update under Condition 2.5(a) of this Permit. (see
notes 7 and 8)
Submission of Updated EM&A Manual
2.5
Four
hard copies and one electronic copy of an updated EM&A Manual for the
Project shall be submitted, no later than one month before the commencement of
construction of the Project, to the Director for approval. The updated EM&A
Manual shall:
(a)
make
recommendations on how to take into account the ENPC and Community Liaison
Group requirements as stipulated in Conditions 2.3 and 2.4 of this Permit respectively; and
(b)
take
into account the latest works schedules, division of responsibilities among
different contracts (if any) in the Project, and project information including
the deletion of originally proposed temporary typhoon shelter as mentioned in
Condition 2.10 of this Permit.
Before submission to the Director, the
updated EM&A Manual shall be certified by the ET and verified by the IEC as
conforming to the information and recommendations contained in the EIA Report
(Register No: AEIAR-125/2008), the application documents for environmental
permit including all attachments (Application No. AEP-356/2009) and other
relevant documents in the Register.
All measures recommended in the updated EM&A Manual approved under
this Condition shall be fully and properly implemented according to the
requirements and time schedule(s) set out in the updated EM&A Manual approved
under this Condition (hereinafter referred to as the “updated EM&A Manual”). (see note 8)
Management Organization of Main
Construction Companies
2.6
The
Permit Holder shall, no later than one month before the commencement of
construction of the marine works covered by this Permit, inform the Director in
writing the management organization of the main construction companies and/or
any form of joint ventures associated with the construction of the marine works
of the Project. The submitted information shall include at least an
organization chart, names of responsible persons and their contact details. The
management organization information submitted under this Condition shall
contribute towards the relevant part of the ENPC and CLG that will be set up
under Conditions 2.3 and 2.4 of this Permit. (see note 8)
Submission
of Works Schedule and Location Plans
2.7
The
dredging and reclamation works of the Project shall be carried out in stages. The
Permit Holder shall deposit a detailed works schedule and location plans in the
scale of 1:1,000 or other appropriate scale of the Project to the Director at
least two weeks before the commencement of the marine works of the
Project. The schedule shall include an update works programme indicating
dates of commencement of construction activities. This schedule to be submitted shall
govern the various milestones and anticipated schedule of submissions as reflected
in Conditions 2.5, 2.8, 2.9, 3.3, 3.4 and 4.2 of this Permit. (see note 8)
Submission
of Silt Curtain Deployment Plan
2.8
At
least two weeks prior to the commencement of the marine works, the Permit
Holder shall deposit with the Director four hard copies and one electronic copy
of a silt curtain deployment plan. The silt curtain deployment plan shall be
certified by the ET Leader and verified by the IEC as conforming to the
relevant information and recommendation contained in the approved EIA Report
(Register No: AEIAR-125/2008). The silt curtain deployment plan shall include
plans showing the construction programme and details on the design, operation
and maintenance requirements of the silt curtain(s) as recommended in the approved
EIA Report (Register No: AEIAR-125/2008) and the relevant documents in the EIAO
Register. The typical configuration of silt curtain is shown in Figure 3 for reference. All mitigation measures
recommended in the silt curtain deployment plan shall be fully and properly
implemented by the Permit Holder and any person working on the Project
throughout the construction period. (see notes 8 and 9)
Submission of Silt Screen Deployment
Plan
2.9
The
Permit Holder shall liaise with the owners and the operators of the seawater
intakes as shown in Table
1 of this Permit on details of silt screen
installation, maintenance and removal at the seawater intakes. The indicative
locations of the intakes are shown in Figure 4 and Figure 5 of this Permit for reference. At least two weeks prior to the
commencement of the marine works, the Permit Holder shall deposit with the
Director four hard copies and one electronic copy of a silt screen deployment
plan to provide details of the design, operation and maintenance requirements
of the silt screen systems. The silt screen deployment plan shall be certified
by the ET Leader and verified by the IEC as conforming to the relevant
information and recommendation contained in the approved EIA Report (Register
No: AEIAR-125/2008) and liaison results with the owners and the operators of
the seawater intakes. The typical
configuration of silt screen is shown in Figure 3 for reference. Silt screens shall be installed at
seawater intakes prior to the commencement of the corresponding marine works in
the vicinity as presented in the finalised silt screen deployment plan. To
avoid refuse entrapment and to ensure representative impact monitoring results,
silt screens shall be maintained and refuse around them shall be collected at
regular intervals on a daily basis so that water behind the silt screens be
kept free from floating debris during the impact monitoring period. (see notes 8 and 9)
Measures and Submissions to be Implemented
during Construction of the Project
Prohibition on Implementation of the Originally
Proposed Temporary Typhoon Shelter
2.10
The originally proposed temporary typhoon shelter
(referred to as “DP
Measures to Mitigate Water Quality
Impact
2.11
To
mitigate water quality impact arising from dredging works:
(a)
the total
dredging rates in each of the marine works zones, (i.e. marine works areas for
the Cross Harbour Water Mains and
Wan Chai East Submarine Sewage Pipelines; and
the 5 reclamation shoreline zones as shown in Figure 2 of this Permit), shall
not be more than the maximum daily and hourly production rates as stipulated in
Table 2 of
this Permit;
(b)
dredging
shall be carried out by closed grab dredger(s) for the seawall construction in
all the reclamation shoreline zones and subzones as shown in Figure 2 of this Permit; and
(c)
no
more than one closed grab dredger shall normally be operated at the same time
for seawall construction in each of the reclamation shoreline zones as shown in
Figure 2 of this Permit.
(see note 9)
2.12
To mitigate
the potential water quality impact on seawater intakes close to the dredging
operation, the total dredging rate in the reclamation shoreline zone HKCEC as
shown in Figure 2 of this Permit shall not exceed an hourly rate of
Measures for Waste Management
2.13
The
Permit Holder shall collect and remove floating refuse at regular intervals on
a daily basis to keep the water within the site boundary and the neighbouring
water free from floating refuse.
3
Environmental Monitoring and
Audit Requirements
3.1
The
EM&A programme shall be implemented in accordance with the procedures and
requirements as set out in the updated EM&A Manual approved under Condition
2.5 of this Permit. Any major changes to the programme
shall be justified by the ET Leader and verified by the IEC as conforming to
the information and requirements contained in the updated EM&A Manual approved
under Condition 2.5 of this Permit before submission to the Director for
approval. (see notes 7 and 8)
3.2
Samples,
measurements and necessary remedial actions shall be taken in accordance with
the requirements of the updated EM&A Manual by:
(a)
conducting
baseline environmental monitoring;
(b)
conducting
impact monitoring;
(c)
carrying out
remedial actions described in Event/Action Plans of the updated EM&A Manual
approved
under Condition 2.5 of this Permit in accordance with the time frames set out in
Event/Action Plans, or as agreed by the Director, in case where specified
criteria in the updated EM&A Manual approved under
Condition 2.5 of this Permit are exceeded; and
(d)
logging and
keeping records of details of (a) to (c) above for all parameters within 3
working days of collection of data or completion of remedial action(s), for the
purpose of preparing and submitting the monthly EM&A Reports and to make
available for inspection on site.
(see notes 7 and 8)
3.5
All
environmental monitoring and audit data submitted under this Permit shall be
true, valid and correct. (see notes 7 and 8)
4
Electronic Reporting of
EM&A Information
4.1
To
facilitate public inspection of the Baseline Monitoring Report and regular
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hardcopies as described in Conditions 3.3 and 3.4 of this Permit. For the HTML version, a
content page capable of providing hyperlink to each section and sub-section of
these Reports shall be included in the beginning of the document. Hyperlinks to
all figures, drawings and tables in these Reports shall be provided in the main
text from where the respective references are made. All graphics in these
Reports shall be in interlaced GIF format unless otherwise agreed by the
Director. The content of the electronic copies of these Reports must be the
same as the hardcopies. (see note 8)
4.3
The
Internet website as described in Condition 4.2 above shall enable user-friendly public access to the
monitoring and project data including the approved EIA Report and the
environmental permit(s) and the project profile of the Project. The Internet
website shall have features capable of:
(a)
providing access to all environmental
monitoring data collected since the commencement of works;
(b)
searching by date;
(c)
searching by types of monitoring data; and
(d)
hyperlinks to relevant monitoring data after searching;
or otherwise as agreed by the Director. (see note 9)
Notes :
1.
This Permit consists of three parts, namely, PART A
(Main Permit), PART B (Description of Designated Project)
and PART C (Permit Conditions). Any person relying
on this permit should obtain independent legal advice on the legal implications
under the Ordinance, and the following notes are for general information only.
2.
If there is a breach of any conditions of this Permit, the Director or
his authorized officer may, with the consent of the Secretary for the
Environment, order the cessation of associated work until the remedial action
is taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
3.
The Permit Holder may apply under Section 13 of the Ordinance to the
Director for a variation of the conditions of this Permit. The Permit
Holder shall replace the original permit displayed on the construction site by
the amended permit.
4.
A person who assumes the responsibility for the whole or a part of the
designated project(s) may, before he assumes responsibility of the
designated project(s), apply under Section 12 of the Ordinance to
the Director for a further environmental permit.
5.
Under Section 14 of the Ordinance, the Director may with the consent of
the Secretary for the Environment, suspend, vary or cancel this Permit.
The suspended, varied or cancelled Permit shall be removed from display at the
construction site.
6.
If this Permit is cancelled or surrendered during construction of the
Project, another environmental permit must be obtained under the Ordinance
before the Project could be continued. It is an offence under section
26(1) of the Ordinance to construct or operate a designated project listed in
Part I of schedule 2 of the Ordinance without a valid environmental permit.
7. Civil Engineering and Development Department (CEDD), the
Holder of Environmental Permit (EP) No. EP-356/2009, is required under
EP-356/2009, or any subsequent EP amended by the Director under the Ordinance
a.
to establish an Environmental
Team (ET) which shall be headed by an ET Leader;
b.
to employ an
Independent Environmental Checker (IEC);
c.
to set up an Environmental Project Committee (ENPC); and
d.
to set up a Community Liaison Group (CLG),
for the marine works of the WDII&CWB project.
8. CEDD, the Holder of
EP-356/2009 is required under EP-356/2009, or any subsequent EP amended by the
Director under the Ordinance:
(i)
to
notify the Director in writing the commencement date of construction of the marine works of the
WDII&CWB project;
(ii)
to notify the Director the date of setting up the ENPC;
(iii)
to notify the Director the date of setting up the CLG;
(iv)
to submit to the Director for approval the updated Environmental
Monitoring and Audit Manual (updated EM&A Manual);
(v)
to inform the Director in writing the management organization of the
main construction companies and/or any form of joint ventures associated with
the construction of the marine works;
(vi)
to deposit with the Director a detailed works schedule and location
plans;
(vii)
to deposit with the Director a silt curtain deployment plan;
(viii) to deposit with the
Director a silt screen deployment plan;
(ix)
to deposit with the Director a noise
management plan;
(x)
to deposit with the Director a landscape
plan;
(xi)
to submit to the
Director the
Baseline Monitoring Report; and
(xii)
to submit to the Director the monthly
EM&A Reports,
for the marine works of the WDII&CWB project.
All submissions or any variation of the
submissions shall be certified by the ET Leader(s) and verified by the IEC
before submitting to the Director.
9. CEDD,
the Holder of Environmental Permit EP-356/2009, is required under EP-356/2009,
or any subsequent EP amended by the Director under the Ordinance:
(i)
to implement the proposed water mains; the proposed sewage pipelines;
the marine works at reclamation shoreline zones and subzones as shown in Figure
1 and Figure 2 of EP-356/2009 together with the relevant environmental mitigation
measures;
(ii)
not to implement the originally proposed temporary typhoon shelter
(referred to as “DP
(iii)
to set up a dedicated web site and notify the Director in writing the
Internet address where the environmental monitoring and project data is to be
placed,
for the marine works of the WDII&CWB project.
10. Any person who constructs
the Project contrary to the conditions in the Permit, and is convicted of an offence under the
Ordinance, is liable:-
(i)
on a first conviction on
indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $ 5 million and to imprisonment for 2
years;
(iii)
on a first summary
conviction to a fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent
summary conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any case where the
offence is of a continuing nature, the court or magistrate may impose a fine of
$ 10,000 for each day on which he is satisfied the offence continued.
11. The Permit Holder may
appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of
receipt of this Permit.
12. The Notes are for general reference only and
that the Permit Holder should refer to the EIA Ordinance for details and
seek independent legal advice.
Environmental Permit No. FEP-05/356/2009
環境許可證編號 FEP-05/356/2009
| Figure 1a | Figure 1b | Figure 2 | Figure 3 | Figure 4 | Figure 5 |
[ Back to First Page ] / [ Back to Main Index ]
Table
1: Application of
Silt Screens at Interim Construction Stages (based on Table 5.39 of the
approved EIA Report (Register No. AEIAR-125/2008)
Interim Construction Stage |
Locations of Applications of Silt Screens |
Scenario |
WSD saltwater intakes at Sai Wan Ho, Quarry
Bay, Sheung Wan, Kowloon South, Wan Chai Cooling water intakes for Hong Kong Convention
and Exhibition Centre Extension, Hong Kong Convention and Exhibition Centre
Phase I, Telecom House / HK Academy for Performing Arts / Shun On Centre, Wan
Chai Tower / Revenue Tower / Immigration Tower and Sun Hung Kai Centre. |
Scenario 2B with concurrent dredging
activities at Sewage Pipelines Zone and reclamation shoreline zone TCBR |
WSD saltwater intakes at Sheung Wan, Wan Chai. Cooling water intakes for Queensway Government
Offices. Excelsior Hotel & World Trade Centre and Windsor House. |
Scenario |
WSD saltwater intakes at Sheung Wan and
Reprovisioned WSD Wan Chai saltwater intake. Cooling water intakes for MTR South, Excelsior
Hotel & World Trade Centre and reprovisioned Windsor House. |
Note: This Table shall be read in conjunction
with Condition 2.9 of this Permit.
The indicative locations of
the marine work zones, including the 5 reclamation shoreline zones, and the seawater
intakes are shown in Figures 1a, 2, 4 and 5 of this Permit respectively.
(see note 9)
Table
2: Recommended Maximum Dredging Rates (based on Table 5.47 of approved EIA Report (Register
No. AEIAR-125/2008)
Marine
Works Zones |
Maximum
Dredging Rate |
||
Daily
rate / m3 per day |
Hourly
rate / m3 per hour (for 16 hours per day) |
||
Dredging
in reclamation shoreline zones |
|
||
North Point Reclamation (NPR) |
6,000 |
375 |
|
Temporary Causeway Bay Reclamation (TCBR) |
6,000 |
375 |
|
Temporary Public Cargo Working Area Reclamation (TPCWA) |
5,000 |
313 |
|
Wan Chai Reclamation (WCR) |
6,000 |
375 |
|
Hong Kong Convention and Exhibition Centre (HKCEC) |
HKCEC1, HKCEC3W and HKCEC3E subzones |
1,500 |
94 |
HKCEC2W and HKCEC2E subzones |
6,000 |
375 |
|
Dredging
in other marine works zones along pipelines |
|||
Cross Harbour Water Mains |
1,500 |
94 |
|
Wan Chai East Submarine Sewage
Pipelines |
1,500 |
94 |
Note: This
Table shall be read in conjunction with
Condition 2.11 and Figures 1a and 2 of this Permit. (see note 9)