Environmental Permit No.: FEP-01/341/2009
環境許可證編號:FEP-01/341/2009
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10條及12條
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED
PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant
to Section 10 and Section 12 of the Environmental Impact Assessment Ordinance
(EIAO), the Director of Environmental Protection (the Director) grants this further environmental permit to the CLP Power Hong Kong Limited (hereinafter referred to as the
"Permit Holder") to
construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit
is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條及12條的規定,環境保護署署長(署長)將本新的環境許可證批予中華電力有限公司 (下稱“許可證持有人”),以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:
Application
No. 申請書編號 |
FEP-158/2014
|
|||
Document in the Register: 登記冊上的文件: |
(1)
Project
Profile – “ (Register No.: PP-285/2006) 工程項目簡介 ― “香港東南水域海上風力發電場” (登記冊編號:PP-285/2006) (2) (Register No.: AEIAR-
140/2009) Hereinafter referred to as “the
EIA Report” 香港東南水域海上風力發電場–環境影響評估報告,行政摘要,環境監察及審核手冊 (登記冊編號: AEIAR-140/2009) 下稱“環評報告” (3)
Application
for Environmental Permit on 7 April 2009 (Application No.: AEP-341/2009) 於 (4)
The
Director’s letter of approval of the EIA Report dated 3 August 2009
referenced f(8) in EP2/N8/D/ 署長於 (5) Environmental
Permit (No.: EP-341/2009) issued on 4 August 2009 於2009年8月4日簽發的環境許可證(許可證編號: EP-341/2009) (6)
Application
for Further Environmental Permit submitted on 13 November 2014 (Application
No.: FEP-158/2014) 於2014年11月13日提交的新的環境許可證申請文件(申請書編號: FEP-158/2014) |
|||
24 November
2014 |
||||
|
Date 日期 |
|
(Louis P. L. CHAN) Principal Environmental Protection Officer (Regional Assessment
) for Director of Environmental Protection 環境保護署署長 (首席環境保護主任(區域評估) 陳檳林代行) |
|
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the
designated project mentioned in Part A of this
environmental permit (hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱 |
(This
designated project is hereafter referred to as “the Project”) 香港東南水域海上風力發電場 (本指定工程項目下稱“工程項目”) |
Nature of Designated Project 指定工程項目的性質 |
Public
utility electricity power plant 公用事業電力廠 |
Location of Designated Project 指定工程項目的地點 |
Southeastern
Waters of the HKSAR – approximately 香港東南水域–清水灣半島及東果洲東面對開分別約 The
location and configuration of the Project is shown in Figure 1 of this Permit. 工程項目的地點及結構形態展示於本許可證圖1內 |
Scale and Scope of Designated Project |
The
Project involves construction and operation of an approximately 200MW wind
farm in the southeastern waters of HKSAR. The Project includes up to 67 wind
turbines, an offshore transformer platform, sub sea
collection and transmission cables and research mast. 工程項目包括在香港東南面水域建造及營辦200兆瓦海上風力發電場。工程項目包括最多67台風機,海上變壓器平台,海底的收集和輸電纜和資料研究塔。 |
C 部 (許可證條件)
1.
General Conditions
一般條件
1.1
The Permit Holder and any person working on
the Project shall comply with all conditions set out in this Permit. Any
non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap.499) and may become the subject
of appropriate action being taken under the Ordinance.
許可證持有人及任何從事工程項目的人士必須符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例)(第499章)的規定,而當局可根據環評條例採取適當行動。
1.2
The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control
Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Waste
Disposal Ordinance (Cap. 354) and Dumping at Sea Ordinance (Cap. 466). This
Permit does not of itself constitute any ground of defense against any
proceedings instituted under any legislation or imply any approval under any
legislation.
許可證持有人須經常確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章)、《空氣污染管制條例》(第311章)、《水污染管制條例》(第358章)、《廢物處置條例》(第354章)及《海上傾倒物料條例》(第466章)。本許可證本身不會就根據任何法例提起的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3
The
Permit Holder shall make copies of this Permit together with all documents
referred to in this Permit and the documents referred to in Part
A of the Permit readily available at all times for inspection by the
Director or his authorized officers at all sites/offices covered by this
Permit. Any reference to the Permit shall include all documents referred to in
the Permit and also the relevant documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件或本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地 / 辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4
The Permit Holder shall give a copy of this
Permit to the person(s) in charge of the site(s) and ensure that such person(s)
fully understands all conditions and all requirements incorporated by the
Permit. The site(s) refers to site(s) of construction and operation of the
Project and shall mean the same hereafter.
許可證持有人須把本許可證的複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5
The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular site
entrances/exits or at a convenient location for public’s information at all
times. The Permit Holder shall ensure that the most updated information about
the Permit, including any amended Permit, is displayed at such locations. If
the Permit Holder surrenders a part or the whole of the Permit, the notice he
sends to the Director shall also be displayed at the same locations as the
original Permit. The suspended, varied or cancelled Permit shall be removed
from display at the Project site(s).
許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6
The Permit Holder shall construct and
operate the Project in accordance with the project description in Part B of this Permit.
許可證持有人須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7
The Permit Holder shall ensure that the
Project is designed, constructed and operated in accordance with the
information and recommendations described in the approved EIA Report (Register
No.: AEIAR–140/2009), the application documents including all
attachments (Application No. AEP-341/2009), other relevant documents in the
Register, and the information and mitigation measures described in this Permit,
and mitigation measures to be recommended in the submissions that shall be
deposited with or approved by the Director as a result of the permit conditions
contained in this Permit, and mitigation measures to be recommended under on going surveillance and monitoring activities during all
stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or amended in this Permit.
許可證持有人須確保工程項目的設計、建造及營辦,按照下述資料及措施辦理:經批准環評報告(登記冊編號:AEIAR-140/2009) 所說明的資料及各項建議;申請文件包括所有附件(申請編號:AEP-341/2009) ;登記冊內的其他相關文件;本許可證所說明的資料或緩解措施;根據本許可證內載的條件須存放或經署長批准的提交文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊內的文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或修訂。
1.8
All deposited submissions, as required under
this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by
the Director within one month of the receipt of the Director’s comments or
otherwise as specified by the Director.
所有按本許可證規定存放的文件,須在接獲署長的意見(如有者)後1個月內(除非署長另行指定),根據署長的意見加以修正並再向署長提交。
1.9
All submissions approved by the Director,
all submissions deposited without comments by the Director, and all submissions
rectified in accordance with comments by the Director under this Permit shall
be construed as part of the permit conditions described in Part
C of this Permit. Any variation of the submissions shall be approved by
the Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the
Environmental Impact Assessment Ordinance. All submissions or any variation of
the submissions shall be certified by the Environmental Team (ET) Leader and
verified by the Independent Environmental Checker (IEC) referred to in
Conditions 2.1 and 2.2 below, before submitting to the Director under this
Permit.
署長批准的所有提交文件、署長沒有給予意見的所有存放文件、或根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證C部說明的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有不符合提交文件的情況,則可能違反《環境影響評估條例》(第499章)的規定。所有提交文件或提交文件的任何修訂本,均須分別按下文條件第2.1及2.2項所述由環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10
The Permit Holder shall release all
finalized submissions as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the Director,
or by any means as specified by the Director, for public inspection. For this
purpose, the Permit Holder shall provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾知道,方法是把有關文件複本存放於環評條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或採取署長指定的任何其他方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11
The Permit Holder shall notify the Director
in writing the commencement date of construction of the Project no later than one
month prior to the commencement of construction of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement date of the construction.
許可證持有人須在工程項目的建造工程展開前,至少提早1個月以書面方式把建造工程的施工日期通知署長。施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.12
All submissions to the Director required
under this Permit shall be delivered either in person or by registered mail to
the Environmental Impact Assessment Ordinance Register Office (currently at
27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hardcopies.
本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環評條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第4.0或較後版本)製作,除非另獲署長同意,並須與硬複本同時提交。
1.13
For the purpose of this Permit,
“commencement of construction” does not include works related to site clearance
and preparation, or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理及預備的工程,或署長同意的其他工程。
2.
Submissions or measures for Commencement of the
Project
工程項目展開前須提交的文件或採取的措施
2.1 An
Environmental Team (ET) shall be established by the Permit Holder no later than
one month before the commencement of construction of the Project. The ET shall
not be in any way an associated body of the Contractor or the Independent
Environmental Checker (IEC) for the Project. The ET shall be headed by an ET
Leader. The ET leader shall be a person who has at least 7 years of experience
in environmental monitoring and auditing (EM&A) or environmental
management. The ET and the ET Leader shall be responsible for the
implementation of the EM&A programme in accordance
with the EM&A requirements as contained in the EM&A Manual to be
submitted in Condition 4.1 below. The ET Leader shall keep a contemporaneous
log-book of each and every instance or circumstance or change of circumstances,
which may affect the compliance with the recommendations of the EIA Report
(Register No. AEIAR – 140/2009) and this Permit. The
ET Leader shall notify the IEC within one working day of the occurrence of any
such instance or circumstance or change of circumstances. The ET Leader’s
log-book shall be kept readily available for inspection by all persons
assisting in supervision of the implementation of the recommendations of the
EIA Report (Register No. AEIAR – 140/2009) and this Permit or
by the Director or his authorized officers. Failure to maintain records
in the log-book, failure to discharge the duties of the ET Leader as defined in
the EM&A Manual or failure to comply with this Condition would entitle the
Director to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit Holder to make replacement,
or further failure to keep contemporaneous records in the log-book despite the
employment of a new ET Leader may render the Permit liable to suspension,
cancellation or variation.
在工程項目的建造工程展開前,許可證持有人須至少提早1個月成立一個環境小組。環境小組不得與工程項目的承辦商或獨立環境查核人有任何聯繫。環境小組須由一名環境小組組長帶領。環境小組組長須在環境監察及審核或環境管理方面至少有7年經驗。環境小組及環境小組組長須按下文條件第4.1項規定提交的環境監察及審核手冊(「環監手冊」)內載的規定,執行環境監察及審核計劃。環境小組組長須保存一本記錄冊,同時記載可能會影響不符合環評報告(登記冊編號:AEIAR-140/2009)建議或本許可證的情況的每件事項、每種情況或每次情況變化。環境小組組長須在發生任何類似事件、情況或情況變化後1個工作天內通知獨立環境查核人。存放環境小組組長的記錄冊的地方,須可供協助督導執行環評報告(登記冊編號:AEIAR-140/2009)建議及本許可證的所有人士、署長或獲授權人員隨時查閱。環境小組組長如未能在記錄冊保存記錄、未能執行環監手冊所列明的環境小組組長職務,或未能符合本條件的規定,署長有權以書面要求許可證持有人撤換環境小組組長。許可證持有人如未能安排人選替補,或在聘用新環境小組組長後仍未能在記錄冊保存同期的記錄,或會導致許可證遭暫時吊銷、取消或更改。
2.2 An IEC shall
be employed by the Permit Holder no later than one month before commencement of
construction of the Project. The IEC shall not be in any way an associated body
of the Contractor or the ET for the Project. The IEC shall be a person who has
at least 7 years of experience in EM&A or environmental management. The IEC
shall be responsible for duties defined in the EM&A Manual to be submitted
in Condition 4.1 below and shall audit the overall EM&A performance,
including the implementation of all environmental mitigation measures,
submissions required in the EM&A Manual, and any other submissions required
under this Permit. In addition, the IEC shall be responsible for verifying the
environmental acceptability of permanent and temporary works, relevant design
plans and submissions under this Permit. The IEC shall verify the log-book(s)
mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by
fax, within one working day of receipt of notification from the ET Leader of
each and every occurrence, change of circumstances or non-compliance with the
EIA Report (Register No. AEIAR – 140/2009) and this Permit,
which might affect the monitoring or control of adverse environmental impacts
from the Project. In the case where the IEC fails to so notify the
Director of the same, fails to discharge the duties of
the IEC as defined in the EM&A Manual or fails to comply with this
Condition, the Director may require the Permit Holder by notice in writing to
replace the IEC. Failure to replace the IEC as directed or further failure to
so notify the Director despite employment of a new IEC may render the Permit
liable to suspension, cancellation or variation. Notification by the Permit
Holder is the same as notification by the IEC for the purpose of this Condition.
在工程項目的建造工程展開前,許可證持有人須至少提早1個月聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商或環境小組有任何聯繫。獨立環境查核人須在環境監察及審核或環境管理方面至少有7年經驗。獨立環境查核人須執行按下文條件第4.1項規定提交的環監手冊所列明的職務,以及審核整體環境監察及審核表現,包括實施所有環境緩解措施、提交環監手冊規定的文件,以及提交本許可證所要求的其他文件。此外,獨立環境查核人須核實永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據本許可證提交的文件,並須核實本許可證條件第2.1項所述的記錄冊。在每次出現事故、情況變化或不符合核准環評報告(登記冊編號:AEIAR-140/2009)及本許可證的情況,而可能會妨礙工程項目所造成不良環境影響的監察或控制工作時,獨立環境查核人須在接獲環境小組組長通知後1個工作天內以傳真方式通知署長。獨立環境查核人如未能通知署長有關情況,未能執行環監手冊所列明的獨立環境查核人職務,或未能符合本條件的規定,署長可以書面要求許可證持有人撤換獨立環境查核人。如未能按指示撤換獨立環境查核人,或在聘用新獨立環境查核人後仍未能通知署長有關情況,則或會導致許可證遭暫時吊銷、取消或更改。為執行本條件,許可證持有人的通知等同獨立環境查核人的通知。
2.3 The Permit
Holder shall, at least two weeks before the commencement of construction of the
Project, inform the Director in writing the management organization of the main
construction companies and/or any form of joint ventures associated with the
construction of the Project. The submitted information shall include at
least an organization chart, names of responsible persons and their contact
details.
在工程項目的建造工程展開前,許可證持有人須至少提早2個星期,把主要建造公司及/或以任何形式與建造工程相關的合營企業的管理架構,以書面通知署長。提交的資料須至少包括一份組織圖、負責人的姓名及聯絡資料。
2.4 The
Permit Holder shall submit to the Director for approval, at least six month
before the commencement of construction of the Project, three hard copies and
one electronic copy of the final layout of the wind farm turbines with
demonstrations that the final layout, among the possible alternative layouts,
has minimized the footprint of the project and maximized the distance of the
turbines from Ninepin Group and Ung Kong Group.
在工程項目的建造工程展開前,許可證持有人須至少提早6個月,把3份硬複本及1份電子版本的風力發電場最終佈局提交署長批准。最終佈局須是在各可能方案中,佔地範圍最少,而風機距離果洲群島及甕缸群島則最遠。
2.5 The
Permit Holder shall conduct marine geophysical comprising seismic and magnetic
surveys at least six months before commencement of any marine construction
works. The marine geophysical survey shall be conducted according to a
specification prepared by a qualified geophysicist and certified by a qualified
marine archaeologist. Three hard copies and one electronic copy of the survey
report shall be deposited with the Director, no later than 2 weeks upon
completion of the survey.
在任何海事建造工程展開前,許可證持有人須至少提早6個月,進行海上地質測量,包括地震勘測及磁力測量。海上地質測量須按照由合資格地質物理學家擬備及經合資格海洋考古學家核實的規格進行。許可證持有人須在完成測量後2個星期內,向署長存放3份硬複本及1份電子版本的測量報告。
2.6 The Permit Holder shall submit to the
Director for approval, at least six months before the commencement of the
construction of the project, three hard copies and one electronic copy of
fisheries enhancement plan incorporating suitable enhancement measures, such as
deployment of artificial reefs, to be developed in consultation with the
fishery sector and the Agriculture, Fisheries and Conservation Department.
在工程項目的建造工程展開前,許可證持有人須至少提早6個月,把3份硬複本及1份電子版本的漁業改善計劃書提交署長批准。計劃書內容須包括經諮詢漁業界及漁農自然護理署後提出如發展人工漁礁的改善漁業措施。
2.7 The
Permit Holder shall deposit with the Director, 6 months before cable laying
works of the project, three hard copies and one electronic copy of the cable
laying programme with demonstrations that jetting
works at the southern section of the cable alignment has best been programmed
in the dry season to avoid impact on amphioxus.
在工程項目的電纜鋪設工程展開前,許可證持有人須至少提早6個月,向署長存放3份硬複本及1份電子版本的鋪設電纜時間表,說明南面的電纜水力噴注工程已盡最大可能編排在旱季進行,以避免對文昌魚帶來影響。
2.8 The
Permit Holder shall deposit with the Director, at least six months before the
commencement of the construction of the project, three hard copies and one
electronic copy of a landscape and visual plan incorporating measures,
including adoption of regular pattern of turbines, slender and elegant design
of turbine tower, use of non-reflective material and visually neutral/
recessive colour scheme for construction of offshore
structures and night-time lighting control.
在工程項目的建造工程展開前,許可證持有人須至少提早6個月,向署長存放3份硬複本及1份電子版本的景觀及視覺圖則,闡述包括整齊的風機排列、細長而優雅的風機塔設計、離岸的搭建物使用不反光物料及採用視覺中性/不顯著的色調,以及控制晚間照明等措施。
2.9 The Permit
Holder shall, within six months upon the issue of this Environment Permit
(EP-341/2009), set up a Stakeholder Liaison Group comprising representatives of
concerned parties, including those related to fishery sector, environmental and
hiking groups, to advise on the design, construction and operation of the
project and shall inform the Advisory Council on the Environment (ACE) and the
Director in writing the membership and terms of reference of the Stakeholder
Liaison Group and should take into account ACE’s views. The Permit holder
shall, within one month of the dates of the meetings, place all minutes of
meetings, relevant documents and associated papers of the Stakeholder Liaison
Group on the dedicated website to be set up by the Permit Holder under
Condition 5.2 below.
在本環境許可證發出6個月內(EP-341/2009),許可證持有人須成立包括漁業界、環保及遠足組織等相關團體組成的持份者聯絡小組,就工程項目的設計、建造及營辦提供意見。許可證持有人須以書面通知環境諮詢委員會及署長有關聯絡小組的成員名單及職權範圍,並考慮環境諮詢委員會的意見。許可證持有人須於開會日期後的1個月內,把聯絡小組所有會議記錄、相關及相聯文件上載於許可證持有人按下述條件第5.2項規定而設立的專用網站內。
3.
Submissions or Measures during Construction
and Operation of the Project
工程項目建造及營辦期間須提交的文件或採取的措施
3.1
The
cable alignment shall be arranged to avoid potential impacts upon
archaeological target A1 as shown in Figure
2 of this permit. A
電纜路線的安排須避免對本許可證圖2所示考古目標A1造成潛在的影響。在每個已識別的潛在考古目標的四周須設直徑150米的緩衝區,其內不得作永久性工程或臨時停泊建造保養的船隻。有關緩衝區的分隔須利用船上的GIS系統,以便海上船舶的操控。
3.2
Transmission
power cables and collection power cables shall be installed by jetting only,
with the exception of the section located at
輸電纜和集電纜只可以噴注方式安裝,位於將軍澳的纜段則除外,該處或需進行挖泥以防護錨泊。挖泥區見本許可證圖3。 挖泥工程在同一時間不得使用多於2部抓斗式挖泥機,每個挖泥點相隔最少100米。2部挖泥機每天總挖泥量共計不得多於6,300立方米。為了盡量減少沉積物溢出,須使用保養良好的密封式抓斗挖泥機。
3.3
Only
one jetting machine shall be deployed for cable laying
at a time. Jetting speed shall not exceed
電纜鋪設工程每次只可用1部水力噴注機。在本許可證圖4所示將軍澳與東龍洲南面之間的部分,噴速每小時不得多於75米。至於電纜的餘段及風力發電場的陣列電纜,噴速則為每小時不多於150米。
3.4
Silt
curtains shall be provided, in accordance with Figure 5 attached to this Permit,
closely surrounding the dredging point at all time throughout the dredging
operation to minimize dispersion of sediment plumes.
在整段挖泥工程進行期間須按本許可證圖5所示設置隔泥幕,緊密圍繞挖泥點,盡量減少沉積物股流擴散。
3.5
There
shall not be more than three wind turbine or offshore transformer platform foundation
installations occur concurrently. Suction caisson foundation shall be adopted
for the wind turbines and offshore transformer platform. The pumping rate for
seawater removal from the suction caissons during foundation installation shall
not exceed
在同一時間內不得裝置多於3座風機或海上變壓器平台地基。風機及海上變壓器平台須採用吸力式沉箱地基。在地基安裝期間,吸力式沉箱的泵水率,以每座地基計每小時不得多於1
200立方米或以每一水泵計每小時不得多於300立方米。在地基及風機下層結構安裝期間,須在工程躉船四周250米範圍實行海洋哺乳動物禁區。
4.
Environmental Monitoring and Audit (EM&A) Requirements
環境監察及審核規定
4.1
The
Permit Holder shall submit to the Director for approval, at least six months before
commencement of the construction of the project, a revised Environmental
Monitoring and Audit Manual, including additional proposal to enhance the
monitoring on water quality covering the following items:
在工程項目的建造工程展開前,許可證持有人須至少提早6個月提交經修訂環境監察及審核手冊,包括下列額外水質監察改善建議,供署長批准:
(a)
Construction
phase monitoring:
建造階段監察:
(i)
Adjustment
in the location of control station from C2 to C
監控站位置由C2調整到 C2’(見圖6所示);
(ii)
Additional
station M10 as shown in Figure 6
to monitor the construction impact to the ecologically important Basalt Island;
and
設額外監測站M10 (見圖6所示),監察建造工程對具重要生態價值的火石洲的影響; 以及
(iii)
Additional
tidal current stations, TC1, TC2, TC3 and TC4 as shown in Figure 6, to monitor the impact of
the wind farm on the surrounding tidal current, salinity-temperature structure.
Proposal should include hourly measurements for tide and current based on
moored instruments, and vertical conductivity-temperature-depth profiles.
設額外潮汐流水站TC1, TC2, TC3 及 TC4 (見圖6所示),監察風力發電場對周圍潮汐流水,鹽度和溫度結構的影響。建議須包括利用繫泊裝置每小時量度潮汐和流水,以及垂直多參數的電導率-溫度-深度剖面。
(b)
Operational
phase monitoring:
營辦階段監察:
(i)
Same
measurement as described under condition 4.1(a)(iii) at TC1, TC2, TC3 and TC4
as shown in Figure 6; and
按條件第4.1(a)(iii)項所述,在TC1, TC2, TC3 及 TC4 (見圖6所示) 作相同的測量;以及
(ii)
Same
measurement as described under condition 4.1(a)(iii)
at TC5 and TC6 as shown in Figure 6.
按條件第4.1(a)(iii)項所述,在TC5 及 TC6 (見圖6所示) 作相同的測量。
4.2
The EM&A programme
shall be implemented in accordance with the procedures and requirements as set
out in the revised EM&A Manual submitted and approved under Condition 4.1
above of this Permit. Any proposed change to the programme
shall be justified by the ET leader and verified by the IEC as conforming to
the information and requirements contained in the EM&A Manual before
submission to the Director for approval.
環境監察及審核計劃須按照本許可證上文條件第4.1項的規定向署長提交並經批准的經修訂環監手冊所載程序及規定執行。環境監察及審核計劃如有更改,在提交署長批准以前,須由環境小組組長提出充分理由,並由獨立環境查核人核實,證明其符合環監手冊所載資料及規定。
4.3
Samples, measurements and necessary
remedial actions shall be taken in accordance with the requirements of the
EM&A Manual by:
取樣、測量及所需的補救行動,均須按照環監手冊的規定進行:
(a) conducting
baseline environmental monitoring;
進行環境基線監測;
(b) conducting
impact monitoring;
進行影響監測;
(c) carrying
out remedial actions described in the Event/Action Plans of the EM&A Manual
in accordance with the time frames set out in the Event/Action Plans, or as
agreed by the Director, in case where specified criteria in the EM&A Manual
are exceeded; and
如超逾環監手冊內指定的標準,則按照環監手冊內的事件/行動計劃所訂明的時限,或如署長所同意的時限,執行事件 / 行動計劃所說明的補救行動;以及
(d) logging
and keeping records of details of (a) to (c) above for all parameters within 3
working days of the collection of data or completion of remedial action(s), for
the purpose of preparing and submitting the monthly EM&A Reports and to
make available for inspection on site.
在收集數據或完成補救行動的3個工作天內,須記錄及備存上文(a)至(c)項各參數的詳情,用作擬備並提交每月環境監察及審核報告,並備妥有關資料以供在工地查閱。
4.4
Three
hard copies and one electronic copy of the Baseline Monitoring Report shall be
submitted to the Director at least 2 weeks before commencement of construction
of the Project. The submission shall be verified by the IEC. Additional copies
of the submission shall be made available to the Director upon his request.
在工程項目的建造工程展開前,須至少提早2個星期向署長提交基線監測報告的3份硬複本及1份電子版本。提交文件須由獨立環境查核人核實。如署長要求,則須提交額外複本。
4.5
Three
hard copies and one electronic copy of monthly EM&A Report shall be
submitted to the Director within 10 working days after the end of the reporting
month. The monthly EM&A Reports shall include a summary of all
non-compliance (exceedances) of the environmental
quality performance limits (Action and Limit Levels). The submissions shall be
verified by the IEC. Additional copies of the submission shall be
provided to the Director upon request by the Director.
在規定提交報告的月份結束後10個工作天內,須向署長提交每月環境監察及審核報告的3份硬複本及1份電子版本。每月環境監察及審核報告須包括各種不符合 (超出) 環境質素表現規限 (行動及極限水平) 情況的摘要。提交文件須由獨立環境查核人核實。如署長要求,則須提交額外複本。
4.6
All
environmental monitoring and audit data submitted under this Permit shall be
true, valid and correct.
根據本許可證提交的所有環境監察及審核數據,均須有效及真實無誤。
4.7
To
ensure a high degree of transparency regarding the monitoring data and results
in view of the public concern about the Project, all environmental monitoring and
audit data and results and all submissions and performance test data and
results required by this Permit shall be made available by the Permit Holder to
the public through a dedicated web site to be set up by the Permit Holder under
Condition 5.2 below, in the shortest practicable time and in no event later
than 2 weeks after such information is available.
基於公眾對工程項目的關注,為確保監察數據及結果具高透明度,許可證持有人須盡快把所有環境監察數據及結果,以及本許可證規定提交的文件及表現測試數據及結果存於按下文條件第5.2項設立的特定網站內,供公眾閱覽,在任何情況下均不得遲於有關資料可供閱覽後的2個星期。
5.
Electronic Reporting of EM&A Information
環境監察及審核資料的電子匯報
5.1 To
facilitate public inspection of the Baseline Monitoring Report and monthly
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hardcopies as described in Condition 4 of
this Permit. For the HTML version, a content page capable of providing
hyperlink to each section and sub-section of these Reports shall be included in
the beginning of the document. Hyperlinks to all figures, drawings and tables
in these Reports shall be provided in the main text from where the respective
references are made. All graphics in these Reports shall be in interlaced GIF,
JPEG or PDF format unless otherwise agreed by the Director. The content of the
electronic copies of these Reports must be the same as the
hardcopies.
為方便公眾透過環評條例互聯網網站及在環評條例登記冊辦事處查閱基線監測報告及每月環境監察及審核報告,以超文本標示語言 (HTML) (第4.0或較後版本) 及便攜式文件格式 (PDF) (第4.0或較後版本) 製作的報告的電子版本,除非另獲署長同意,須與本許可證條件第4項所說明的硬複本同時提交。關於HTML的版本方面,可與報告各節及小節作出超文本連結的目錄須在文件開端加入。報告內各類圖表須在載有相關資料的正文內作出超文本連結。除非另獲署長同意,報告內所有圖形均須以交錯存取的GIF, JPEC或PDF格式制定。報告的電子版本內容,必須與硬複本的內容一致。
5.2 The
Permit Holder shall, within six weeks to the commencement of construction of
the Project, set up a dedicated web site and notify the Director in writing the
Internet address, where the project information, all environmental monitoring
and audit data and reports described in Condition 5.1 above, and all finalized
submissions and plans required under this Permit, are to be placed. All
environmental monitoring and audit data and reports described in Condition 5.1
above shall be made available to the public via this dedicated web site to be
set up by the Permit Holder in the shortest possible time and in no event later
than 2 weeks after the relevant environmental monitoring data and reports
is/are collected or become available, unless otherwise agreed with the
Director. All finalized submissions and plans shall be made available to the
public via this dedicated web site to be set up by the Permit Holder in the
shortest possible time and in no event later than 2 weeks after they are
deposited with or approved by the Director as required under this Permit,
unless otherwise agreed with the Director.
許可證持有人須在工程項目的建造工程展開前6個星期內,設立特定網站存放工程項目資料、上文條件第5.1項說明的所有環境監察數據及報告,以及按本許可證規定提交的文件及圖則定稿,並以書面通知署長網址所在。上文條件第5.1項說明的所有環境監察數據及報告,均須盡快透過上述特定網站供公眾閱覽,在任何情況下均不得遲於有關環境監察數據及報告收集或可供閱覽後的2個星期,除非另獲署長同意。所有提交的文件及圖則定稿,均須盡快透過上述特定網站供公眾閱覽,在任何情況下均不得遲於按本許可證規定向署長存放或經署長批准後的2個星期,除非另獲署長同意。
5.3 The Internet
website as described in Condition 5.2 above shall enable user-friendly public
access to the monitoring and project information including the project profile
of the Project, the EIA report, the environmental permit(s), all environmental
monitoring and audit data and report and all finalized submissions and plans
required under this Permit. Unless otherwise agreed with the Director,
the internet website shall have features capable of:
上文條件第5.2項說明的互聯網網站,必須方便用戶使用,讓公眾容易接達環境監察數據及工程項目資料,當中包括本工程項目簡介、環評報告、環境許可證、所有環境監察數據及報告,以及按本許可證規定提交的文件及圖則定稿。除非另獲署長同意,互聯網網站須具備部件,提供下述功能:
(a)
providing
access to all environmental monitoring data collected since the commencement of
works;
接達工程展開後所收集的全部環境監察數據;
(b)
searching
by date;
按日期搜尋;
(c)
searching
by types of monitoring data (e.g. noise, water and air quality); and
按監察數據類別 (例如噪音、水質及空氣質素) 搜尋;以及
(d) hyperlinks to relevant monitoring data after searching;
在搜尋後與相關的監察數據作出超文本連結;
or otherwise as
agreed by the Director.
或署長同意的其他功能。
Notes :
註:
1. This
Permit consists of three parts, namely, Part A (Main
Permit), Part B (Description of Designated Project)
and Part C (Permit Conditions). Any person relying
on this Permit should obtain independent legal advice on the legal implications
under the Ordinance, and the following notes are for general information
only.
本許可證共有3部,即A部 (許可證主要部分);B部 (指定工程項目的說明) 及C部 (許可證條件)。任何援引本許可證的人士須就條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If
there is a breach of any conditions of this Permit, the Director or his
authorized officer may, with the consent of the Secretary for the Environment,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit
Holder shall not carry out any associated works without the permission of the
Director or his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員可在環境局局長的同意下勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The
Permit Holder may apply under Section 13 of the Ordinance to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the construction site by the
amended permit.
許可證持有人可根據條例第13條的規定向署長申請更改本許可證的條件。許可證持有人須以經修訂的許可證替換在建造工地內展示的原有許可證。
4. A
person who assumes the responsibility for the whole or a part of the designated
project may, before he assumes responsibility of the designated project, apply
under Section 12 of the Ordinance to the Director
for a further environmental permit.
承擔指定工程項目整項或部分工程的責任的人,在承擔責任之前,可根據條例第12條的規定向署長申請新的環境許可證。
5. Under
Section 14 of the Ordinance, the Director may with the consent of the Secretary
for the Environment suspend, vary or cancel this Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site.
根據條例第14條的規定,署長可在環境局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程工地除下,不再展示。
6. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the Ordinance
before the construction or operation of the Project could be continued. It is
an offence under Section 26(1) of the Ordinance to construct or operate a
designated project listed in Part I of Schedule 2 of
the Ordinance without a valid environmental
permit.
如本許可證在工程項目建造或營辦期間取消或交回,則在繼續建造或營辦工程項目之前,必須先根據條例規定取得另一份環境許可證。根據條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦條例附表2第I部所列明的指定工程項目,即屬犯罪。
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the
Ordinance, is liable: -
如任何人在違反本許可證的條件下建造或營辦工程項目,根據條例,即屬犯罪:
(i)
on a
first conviction on indictment to a fine of $2 million and to imprisonment for
6 months;
一經循公訴程式首次定罪,可處罰款200萬元及監禁6個月;
(ii)
on a
second or subsequent conviction on indictment to a fine of $5 million and to
imprisonment for 2 years;
一經循公訴程式第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
on a
first summary conviction to a fine at level 6 and to imprisonment for 6 months;
一經循簡易程式首次定罪,可處第6級罰款及監禁6個月;
(iv) on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
一經循簡易程式第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及
(v)
in any case where the
offence is of a continuing nature, the court or magistrate may impose a fine of
$10,000 for each day on which he is satisfied the offence continued.
在任何情況下如該罪行屬連續性質,法院或裁判官可就其信納該罪行連續的每一天另處罰款10,000元。
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the Ordinance
within 30 days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據條例第17條就本許可證的任何條件提出上訴。
9. The
Notes are for general reference only and that the Permit Holder should refer to
the EIA Ordinance for details
and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱條例及徵詢獨立法律意見。
Environmental
Permit No. FEP –
01/ 341/2009
環境許可證編號 FEP – 01/ 341/2009
| Figure 1 | Figure 2 | Figure 3 | Figure
4 | Figure 5 | Figure 6 |
[ Back to First Page ] / [
Back to Main Index ]