Environmental Permit
No. FEP-01/376/2009
Àô¹Ò³\¥iÃÒ½s¸¹ FEP-01/376/2009
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
Àô¹Ò¼vÅTµû¦ô±ø¨Ò
(²Ä499³¹)
²Ä10¤Î12±ø
FURTHER
ENVIRONMENTAL PERMIT TO CONSTRUCT
A
DESIGNATED PROJECT
«Ø³y«ü©w¤uµ{¶µ¥Øªº·sªºÀô¹Ò³\¥iÃÒ
A³¡ (³\¥iÃÒ¥Dn³¡¤À)
Pursuant
to Section 10 and 12 of the Environmental Impact Assessment Ordinance (EIAO),
the Director of Environmental Protection (the Director) grants this further environmental
permit to China State ¡V Leader Joint Venture (hereinafter referred to as the "Permit Holder") to
construct the designated project described in Part B
subject to the conditions specified in Part C. The issue of this further environmental permit is based on the documents,
approvals or permissions described below:
®Ú¾Ú¡mÀô¹Ò¼vÅTµû¦ô±ø¨Ò¡n(Àôµû±ø¨Ò)²Ä10±ø¤Î12±øªº³W©w¡AÀô¹Ò«OÅ@¸p¸pªø(¸pªø)±N¥»·sªºÀô¹Ò³\¥iÃҧ天¤¤°ê«Ø¿v ¡V §Q¹FÁpÀç(¤UºÙ ¡§³\¥iÃÒ«ù¦³¤H¡¨)¡A¥H«Ø³yB³¡©Ò»¡©úªº«ü©w¤uµ{¶µ¥Ø¡A¦ý¶·¿í¦uC³¡©Ò¦C©úªº±ø¥ó¡C¥»·sªºÀô¹Ò³\¥iÃÒ¬O¨Ì¾Ú¤U¦C¤å¥ó¡B§åã©Î³\¥i¦Óñµo¡G
Application No. ¥Ó½Ð®Ñ½s¸¹ |
FEP-161/2015
|
|||
Document in the Register : µn°O¥U¤Wªº¤å¥ó: |
1.
Wan Chai Development Phase II and Central-Wan
Chai Bypass (Register No.: AEIAR-125/2008) -
Environmental Impact
Assessment Report (December 2007) -
Environmental Monitoring
and Audit Manual -
Executive Summary -
Further information
received from the Civil Engineering and Development Department on 11 March
2008, 9 April 2008 and 14 November 2008 under Section 8(1) of the EIAO 2.
The Director¡¦s letter of approval of the WDII&CWB
EIA Report dated 11 December 2008 referenced (85) in EP2/H4/S3/ 3.
Central Reclamation Phase III ¡V Studies, Site
Investigation, Design and Construction (Register
No.: AEIAR-040/2001) -
Environmental Impact
Assessment Report (July 2001) -
Environmental Monitoring
and Audit Manual -
Executive Summary 4.
The Director¡¦s letter of approval of the CRIII
EIA Report dated 31 August 2001 referenced (19) in Ax(4)
to EP2/H4/C/09 II. 5.
Environmental Permit Issued ¡V Permit No.:
EP-356/2009 issued to Civil Engineering and Development Department on 30 July
2009 for construction of the following designated projects: (i) Permanent and temporary reclamation works
including associated dredging works in Wan Chai Development Phase II (WDII)
area (referred to as ¡§DP (ii) Wan Chai East Sewage Outfall (referred to as ¡§DP (iii) Dredging for the Cross-harbour
Water Mains from Wan Chai to Tsim Sha Tsui (referred to as ¡§DP 6.
Environmental
Permit Issued ¡V Permit No.: EP-364/2009 issued to Highways Department on 17
August 2009 for construction of the ¡§Central-Wan Chai Bypass¡¨ (CWB) including
its Road Tunnel and Slip Roads (referred to as ¡§DP 7.
Application for Environmental Permit and
attachments submitted by the Permit Holder on 20 October 2009 (Application
No.: AEP-376/2009). 8.
Environmental Permit
Issued ¡V Permit No.: EP-376/2009 issued on 13 November 2009. 9.
Application for
Further Environmental Permit including all attachments submitted on 6 March
2015 (Application No.: FEP ¡V 161/2015). 1. ÆW¥Jµo®ip¹º²Ä¤G´Á¤Î¤¤ÀôÆW¥J¶¹D (µn°O¥U½s¸¹: AEIAR-125/2008) ¡P
Àô¹Ò¼vÅTµû¦ô³ø§i (2007¦~12¤ë) [¤UºÙ¡uWDII&CWBÀôµû³ø§i¡v] ¡P
Àô¹ÒºÊ¹î¼f®Ö¤â¥U ¡P
¦æ¬FºKn ¡P
¤g¤ì¤uµ{©Ý®i¸p®Ú¾Ú±ø¨Ò²Ä8.(1)±ø©ó 2. ¸pªø©ó2008¦~ 3. ¤¤Àô¶ñ®üp¹º²ÄIII´Á - ¬ã¨s¡B¹ê¦a³ô´ú¡B³]p»P«Ø¿v(µn°O¥U½s¸¹:AEIAR-040/2001) ¡P
Àô¹Ò¼vÅTµû¦ô³ø§i (2001¦~7¤ë) [¤UºÙ¡uCRIIIÀôµû³ø§i¡v] ¡P
Àô¹ÒºÊ¹î¼f®Ö¤â¥U ¡P
¦æ¬FºKn 4. ¸pªø©ó2001¦~ 5. ¤wñµoªºÀô¹Ò³\¥iÃÒ¡V ³\¥iÃÒ½s¸¹EP-356/2009; ©ó2009¦~7¤ë30¤éñµo¤©¤g¤ì¤uµ{©Ý®i¸p¥H«Ø³y¥H¤U«ü©w¤uµ{¶µ¥Ø: (i) ¦bÆW¥Jµo®ip¹º²Ä¤G´Áªº¥Ã¤[¤ÎÁ{®É¶ñ®ü¤uµ{(¥]¬A¬ÛÁp«õªd¤uµ{) (WDII&CWBÀôµû³ø§i¤ººÙ¡§DP (ii)
ÆW¥JªF¦Ã¤ô±Æ¤ô¤f(WDII&CWBÀôµû³ø§i¤ººÙ¡§DP (iii)
ÆW¥J¦Ü¦y¨F©C®ü©³¿é¤ôºÞªº«õªd¤uµ{(WDII&CWBÀôµû³ø§i¤ººÙ¡§DP 6. ¤wñµoªºÀô¹Ò³\¥iÃÒ¡V ³\¥iÃÒ½s¸¹EP-364/2009; ©ó 7. ³\¥iÃÒ«ù¦³¤H©ó2009¦~10¤ë20¤é´£¥æªºÀô¹Ò³\¥iÃҥӽФå¥ó¤Îªþ¥ó(¥Ó½Ð®Ñ½s¸¹: AEP-376/2009) 8. ¤wñµoªºÀô¹Ò³\¥iÃÒ¡V ³\¥iÃÒ½s¸¹EP-376/2009 ©ó2009¦~11¤ë13¤éñµo 9. ©ó2015¦~3¤ë6¤é´£¥æªº·sªºÀô¹Ò³\¥iÃҥӽФå¥ó¥]¬A©Ò¦³ªþ¥ó(¥Ó½Ð®Ñ½s¸¹: FEP-161/2015) |
|||
|
31 March 2015 2015 ¦~ 3 ¤ë 31 ¤é |
|
||
|
Date ¤é´Á |
|
(Mr. Ken Y.K. WONG) Principal
Environmental Protection Officer for
Director of Environmental Protection Àô¹Ò«OÅ@¸p¸pªø (º®uÀô¹Ò«OÅ@¥D¥ô ¶ÀÄ£¥ú ¥N¦æ) |
|
PART B
(DESCRIPTION OF DESIGNATED PROJECT)
B³¡ («ü©w¤uµ{¶µ¥Øªº»¡©ú)
Hereunder
is the description of the designated project mentioned in Part
A of this environmental permit (hereinafter referred to as ¡§the
Permit¡¨):
¤U¦C¬°¥»Àô¹Ò³\¥iÃÒ(¤UºÙ¡§³\¥iÃÒ¡¨)A³¡©Ò´£zªº«ü©w¤uµ{¶µ¥Øªº»¡©ú:
Title of Designated Project «ü©w¤uµ{¶µ¥Øªº¦WºÙ |
Road P2 and
other roads which are classified as primary/district distributor roads (referred to as ¡§DP P2¸ô¤Î¨ä¥L¤ÀÃþ¬°¥Dn·F¸ô©Î¦a°Ï·F¸ôªº¹D¸ô(WDII&CWBÀôµû³ø§i¤ººÙ¡§DP |
Nature of Designated Project «ü©w¤uµ{¶µ¥Øªº©Ê½è |
The Project
will involve construction of primary and district distributor roads. ¦¹¤uµ{¶µ¥Ø¯A¤Î«Ø³y¥Dn·F¸ô¤Î¦a°Ï·F¸ô¹D¸ô¡C |
Location of Designated Project «ü©w¤uµ{¶µ¥Øªº¦aÂI |
Wan Chai harbourfront area, The location
of the Project is shown in Figure 1A
of this Permit. »´äÆW¥J®ü®Ç¡C ¤uµ{¶µ¥Øªº¦aÂI®i¥Ü©ó¥»³\¥iÃÒ¹Ï1A ¤º¡C |
Scale and Scope of Designated Project |
The scope of
the Project includes: ¡P
a dual 2-lane primary distributor
road, Road P2, approximately ¡P
other new primary and district
distributor roads connecting to the slip roads of the Central-Wan Chai Bypass
with a total length of approximately Remarks: (a)
The scope of the Project does not
include any reclamation or dredging works. (b)
The reclamation and associated
dredging works related to the Project within Wan Chai Development Phase II
(WDII) project area in Wan Chai harbourfront are
separately covered by the environmental permit No.
EP-356/2009 issued to Civil Engineering and Development Department. (c)
The reclamation and associated
dredging works related to the Project within the Central Reclamation Phase
III (CRIII) project area in Central habourfront
area are separately covered by the environmental permit No.
EP-122/2002 and further environmental permit No. FEP-01/122/2003, and their
subsequently amended versions, issued to Civil Engineering and Development
Department and its contractor, Leighton-China State-Van Oord Joint Venture,
respectively. ¤uµ{¶µ¥Øªº½d³ò¥]¬A: ¡P
¤@±ø¬ùªø ¡P
¨ä¥LÁ`ªø¬ù ³Æµù: (a)
¥»³\¥iÃÒ¤£¥]¬A¥ô¦ó¶ñ®ü©Î«õªd¤uµ{¡C (b)
¦³Ãö¦¹¤uµ{¶µ¥Ø¦ì©óÆW¥J®ü®ÇÆW¥Jµo®ip¹º²Ä¤G´Á¦a°Ï¤ºªº¶ñ®ü¤Î¬ÛÁp«õªd¤uµ{¤w¥]¬A¦bñµo»P¤g¤ì¤uµ{©Ý®i¸pªºÀô¹Ò³\¥iÃÒ(³\¥iÃÒ½s¸¹: EP-356/2009)¡C (c)
¦³Ãö¦¹¤uµ{¶µ¥Ø¦ì©ó¤¤Àô®ü®Ç¤¤Àô¶ñ®ü²Ä¤T´Á¦a°Ï¤ºªº¶ñ®ü¤Î¬ÛÁp«õªd¤uµ{¤w¥]¬A¦bñµo»P¤g¤ì¤uµ{©Ý®i¸pªºÀô¹Ò³\¥iÃÒ(³\¥iÃÒ½s¸¹: EP-122/2002)¤Îñµo»P¨ä©Ó¿ì°ÓLeighton-China State-Van Oord Joint
Ventureªº·sªºÀô¹Ò³\¥iÃÒ(³\¥iÃÒ½s¸¹: FEP-01/122/2003)¤Î¨ä¦U¦Ûªº§ó·sª©¥»¡C |
1. General
Conditions
1.1
The
Permit Holder and any person working on the Project shall comply with all
conditions set out in this Permit. Any non-compliance by any person may
constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap.499) and may become the subject of appropriate action being taken under
the Ordinance.
1.2
The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Air Pollution Control Ordinance (Cap. 311), Water Pollution
Control Ordinance (Cap. 358), Noise Control Ordinance (Cap. 400), and Waste
Disposal Ordinance (Cap. 354). This
Permit does not of itself constitute any ground of defense against any
proceedings instituted under any legislation or imply any approval under any
legislation.
1.3
The Permit Holder shall make copies of
this Permit together with all documents referred to in this Permit and the
documents referred to in Part A of this Permit
readily available at all times for inspection by the Director or his authorized
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
1.4
The Permit Holder shall give a copy of
this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated by
the Permit. The site(s) refers to site(s) of construction and operation of the
Project and shall mean the same hereafter.
1.5
The Permit Holder shall display
conspicuously a copy of this Permit on the construction site(s) at all
vehicular site entrances/exits or at a convenient location for public¡¦s
information at all times. The Permit Holder shall ensure that the most updated
information about the Permit, including any amended Permit, is displayed at
such locations. If the Permit Holder surrenders a part or the whole of this
Permit, the notice he sends to the Director shall also be displayed at the same
locations as the original Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site(s).
1.6
The Permit Holder shall construct and
operate the Project in accordance with the project description in Part B of this Permit (hereafter referred to as ¡§the
Project¡¨).
1.7
The Permit Holder shall ensure that the
Project is designed, constructed and operated in accordance with the relevant
information and recommendations described in the approved WDII&CWB EIA
Report (Register No. AEIAR-125/2008), the approved CRIII EIA Report (Register
No. AEIAR-040/2001), the Environmental Permit No.: EP-356/2009 issued on 30
July 2009 for marine works as described in Part A
of this Permit; the Application for Environmental Permit (Application No. AEP-376/2009)
and other relevant documents in the Register, the information and mitigation
measures described in this Permit, mitigation measures to be recommended in
submissions that shall be deposited with or approved by the Director as a
result of permit conditions contained in this Permit, and mitigation measures
to be recommended under on-going surveillance and monitoring activities during
all stages of the Project. Where recommendations referred to in the documents
of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit.
1.8
All deposited submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within one month of the receipt of the
Director¡¦s comments or otherwise specified by the Director.
1.9
All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall
be approved by the Director in writing or as prescribed in the relevant permit
conditions. Any non-compliance with the submissions may constitute a
contravention of the Environmental Impact Assessment Ordinance (Cap.499). All
submissions or any variation of the submissions shall be certified by the
Environmental Team (ET) Leader and verified by the Independent Environmental
Checker (IEC) employed for the CWB project before submitting to the Director
under this Permit (see note 7).
1.10
The Permit Holder shall release all
finalized submissions, as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of the submissions.
1.11
All submissions to the Director required
under this Permit shall be delivered either in person or by registered mail to
the Environmental Impact Assessment Ordinance Register Office (currently at
27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies.
1.12
The Permit Holder shall notify the Director in writing the commencement
date of construction of the
Project no later than one month prior to the commencement of construction of
the Project. The Permit Holder shall notify the Director in writing immediately
if there is any change of the commencement date of the construction.
1.13
For the purpose of this Permit, ¡§commencement of construction¡¨ does not
include works related to site clearance and preparation or other works as
agreed by the Director.
2
Special Conditions
Submissions or Measures to be implemented before Construction of the Project
2.1
[Not Used]
2.2
[Not Used]
Environmental Project Committee (ENPC)
The ENPC shall make recommendation to enhance the monitoring and audit of the environmental performance of the whole project and other relevant nearby projects on top of requirements as set out in Conditions 3.1, 3.2, 3.4 to 4.2 of this Permit or corresponding requirements set out under subsequent Environmental Permits issued for the whole project and other relevant nearby projects. (see notes 7 and 8)
2.4 [Not Used]
2.5 [Not Used]
2.6 [Not Used]
2.7 [Not Used]
2.8 [Not Used]
Submissions and Measures for the Construction Period of the Project
Measures to Mitigate Construction Noise Impact
2.9
To mitigate construction noise
impact particularly on the nearby noise sensitive receiver ¡V Hong Kong Academy
for Performing Arts (Open Arena), the Permit Holder shall deposit with the
Director, at least two weeks prior to the commencement of construction of the
corresponding component(s) of the Project, four hard copies and one electronic
copy of the construction noise management plan, consisting of layout plan(s) in
the scale of 1:1,000 or other appropriate scale and explanatory statement(s)
showing the noise mitigation measures to include the use of movable/temporary
noise barriers, the use of quiet powered mechanical equipments and the adoption
of multiple-phase construction schedules, where appropriate for the construction activities in relation
to the following tasks:
(a)
the
roads for temporary traffic diversion;
(b)
resurfacing;
and
(c)
at-grade roadwork.
Measures to Mitigate Construction Landscape
and Visual Impact
2.10
To reduce the landscape and
visual impact during construction stage of the Project, the Permit Holder shall
implement a series of landscape and visual mitigation measures. The Permit Holder shall, at least one
month before the commencement of corresponding parts of construction landscape
works of the Project, deposit with the Director four hard copies and one
electronic copy of construction landscape plan(s). The construction landscape plan(s) shall
show the design details, locations, implementation programme, maintenance and
management schedules, and drawings in the scale of 1:1,000 or other appropriate
scale of the construction landscape and visual mitigation measures of the
Project. Before submission to the Director, the construction landscape plan(s)
shall be certified by the ET Leader and verified by the IEC as conforming to
the relevant information and recommendations contained in the approved
WDII&CWB EIA Report (Register No. AEIAR-125/2008) and the approved CRIII
EIA Report (Register No. AEIAR-040/2001), in particular Table 10.5, Volume
2-Part B of the approved WDII&CWB EIA Report (Register No. AEIAR-125/2008).
All measures recommended in the finalised submission(s) under this Condition shall
be fully and properly implemented. (see note 8)
3
Environmental Monitoring and
Audit Requirements
3.1 The EM&A programme shall be implemented in accordance with the procedures and requirements as set out in the updated EM&A Manual approved under EP-376/2009 (see note 8). Any major changes to the programme shall be justified by the ET Leader and verified by the IEC employed under EP-376/2009 (see note 7) as conforming to the information and requirements contained in the updated EM&A Manual.
3.2 Samples, measurements and necessary remedial actions shall be taken in accordance with the requirements of the updated EM&A Manual (see note 8) by:
(a)
conducting
baseline environmental monitoring;
(b)
conducting
impact monitoring;
(c)
carrying out
remedial actions described in Event/Action Plans of the updated EM&A Manual
in accordance with the time frames set out in Event/Action Plans, or as agreed
by the Director, in case where specified criteria in the updated EM&A
Manual are exceeded; and
(d)
logging and
keeping records of details of (a) to (c) above for all parameters within 3
working days of collection of data or completion of remedial action(s), for the
purpose of preparing and submitting the monthly EM&A Reports and to make
available for inspection on site.
3.5 All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.
4
Electronic Reporting of
EM&A Information
4.1 To facilitate public inspection of the regular EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hardcopies as described in Conditions 3.4 of this Permit. For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made. All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director. The content of the electronic copies of these Reports must be the same as the hardcopies. (see note 8)
Notes :
1.
This Permit consists of three parts, namely, PART A
(Main Permit), PART B (Description of Designated Project)
and PART C (Permit Conditions). Any person relying
on this permit should obtain independent legal advice on the legal implications
under the Ordinance, and the following notes are for general information only.
2.
If there is a breach of any conditions of this Permit, the Director or
his authorized officer may, with the consent of the Secretary for the
Environment, order the cessation of associated work until the remedial action
is taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
3.
The Permit Holder may apply under Section 13 of the Ordinance to the
Director for a variation of the conditions of this Permit. The Permit
Holder shall replace the original permit displayed on the construction site by
the amended permit.
4.
A person who assumes the responsibility for the whole or a part of the
designated project(s) may, before he assumes responsibility of the
designated project(s), apply under Section 12 of the Ordinance to
the Director for a further environmental permit.
5.
Under Section 14 of the Ordinance, the Director may with the consent of
the Secretary for the Environment, suspend, vary or cancel this Permit.
The suspended, varied or cancelled Permit shall be removed from display at the
construction site.
6.
If this Permit is cancelled or surrendered during construction or
operation of the Project, another environmental permit must be obtained under
the Ordinance before the Project could be continued. It is an offence
under section 26(1) of the Ordinance to construct or operate a designated
project listed in Part I of schedule 2 of the
Ordinance without a valid environmental permit.
7.
Civil Engineering and Development Department (CEDD), the Holder of Environmental
Permit (EP) No. EP-376/2009, is required under EP-376/2009, or any subsequent EP amended by the Director under the Ordinance:
(i)
to establish an Environmental Team (ET) which
shall be headed by an ET Leader;;
(ii) to employ an Independent Environmental Checker (IEC)
(iii) to
set up an Environmental Project Committee (ENPC); and
(iv) to
set up a Community Liaison Group (CLG),
for the works covered by EP-376/2009.
8.
CEDD, the Holder of EP-376/2009 is required under
EP-376/2009, or any subsequent EP amended by the Director under the
Ordinance:
(i)
to notify the Director in writing the commencement date of construction
of the works of the WDII&CWB project;
(ii)
to notify the Director the date of
setting up the ENPC;
(iii)
to notify the Director the date of setting up the CLG;
(iv)
to submit to the Director for approval the updated Environmental
Monitoring and Audit Manual (updated EM&A Manual);
(v)
to inform the Director in writing the management organization of the
main construction companies and/or any form of joint ventures associated with
the construction of the marine works;
(vi)
to deposit with the Director a detailed works schedule and location
plans;
(vii)
to deposit with the Director a construction
noise management plan;
(viii)
to deposit with the Director a construction
landscape plan;
(ix)
to deposit with the Director an operation landscape plan;
(x)
to submit to the Director the Baseline Monitoring Report; and
(xi)
to submit to the Director the monthly EM&A
Reports.
for the works covered by EP-376/2009.
All submissions or any variation of the submissions shall be certified
by the ET Leader(s) and verified by the IEC before submitting to the Director
9.
CEDD, the Holder of EP-376/2009 is required under
EP-376/2009, or any subsequent EP amended by the Director under the Ordinance, to set up a dedicated web site and notify the Director in writing the
Internet address where the environmental monitoring and project data is to be
placed, for the works covered by EP-376/2009.
10. Any person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the Ordinance, is liable:
(i)
on a first conviction on
indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $ 5 million and to imprisonment for 2
years;
(iii)
on a first summary
conviction to a fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent
summary conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature, the court or
magistrate may impose a fine of $ 10,000 for each day on which he is satisfied
the offence continued.
11. The Permit Holder may
appeal against any condition of this Permit under Section 17 of the Ordinance
within 30 days of receipt of this Permit.
12. The Notes are for general
reference only and that the Permit Holder should refer to the EIA Ordinance for
details and seek independent legal advice.
Environmental Permit No. FEP-01/376/2009
Àô¹Ò³\¥iÃÒ½s¸¹ FEP-01/376/2009
| Figure 1A |
[ Back to First Page ] / [ Back to Main Index ]