Environmental Permit No. FEP-01/613/2022
環境許可證編號
  FEP-01/613/2022


Link to Project EIA
Information
項目環評資料連結

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)

SECTIONS 10 AND 12

環境影響評估條例

(499)

10條及12

 

FURTHER ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE

A DESIGNATED PROJECT

建造及營辦指定工程項目的環境許可證

 

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

 

Pursuant to Sections 10 and 12 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) grants this further environmental permit to the Canvest – Paul Y. Joint Venture (hereinafter referred to as the “Permit Holder”) to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this further environmental permit is based on the documents, approvals or permissions described below:

根據《環境影響評估條例》(環評條例) 10條及12條的規定,環境保護署署長(署長)將本新的環境許可證批予粵豐 - 保華聯營(下稱許可證持有人”) 以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本新的環境許可證的發出,乃以下表所列的文件、批准或許可作為根據

 

 

Application No.

申請書編號

FEP-222/2024

Document in the Register:

登記冊上的文件:

 

(1)    Project Profile Development of a Grease Trap Waste Treatment Facility and Minor Modifications and Enhancement Works at North Lantau Transfer Station

(Register No.: PP-646/2022)

工程項目簡介 北大嶼山廢物轉運站隔油池廢物處理設施及小型改建及提升工程

(登記冊編號:PP-646/2022)

 

(2)  The Director’s letter of permission to apply directly for Environmental Permit dated 28 Jun 2022 (Reference: (29) in EP2/N2/G/69)

署長於2022628日發出准許直接申請環境許可證的信件 (檔案編號:(29) in EP2/N2/G/69)

 

(3)  Application for Environmental Permit submitted on 29 Jun 2022 (Application No. AEP-613/2022)

2022629 提交的環境許可證申請文件 (申請書編: AEP-613/2022)

 

(4)  Environmental Permit (No. EP-613/2022) issued on 7 Jul 2022

202277日簽發的環境許可證 (許可證編號:EP-613/2022)

 

(5)  Application for Further Environmental Permit including all attachments submitted on 6 Mar 2024 (Application No. FEP-222/2024)

202436 提交的新的環境許可證申請文件包括所有附件 (申請書編: FEP-222/2024)

 

                               

 

26 March 2024

               20243 26

Date

日期

 

(Queenie Y. C. NG)

Acting Principal Environmental Protection Officer

    for Director of Environmental Protection

環境保護署署長

(署理首席環境保護主任 吳沅清 代行)


PART B (DESCRIPTION OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this further environmental permit (hereinafter referred to as the “Permit”):

下列為本新的環境許可證 (下稱許可證”) A部所提的指定工程項目的說明﹕

 

Title of Designated Project

指定工程項目的名稱

Development of a Grease Trap Waste Treatment Facility and Minor Modifications and Enhancement Works at North Lantau Transfer Station

[This designated project is hereafter referred to as “the Project”]

 

北大嶼山廢物轉運站隔油池廢物處理設施及小型改建及提升工程[本指定工程項目下稱 工程項目”]

 

Nature of Designated Project
指定工程項目的性質

A refuse transfer station

垃圾轉運站

 

Location of Designated Project

指定工程項目的地點

The Project is located within the existing North Lantau Transfer Station, Sham Shui Kok Drive, Siu Ho Wan, North Lantau. The location of the Project is shown in Figure 1 of this Permit

工程項目位於北大嶼山小蠔灣深水角徑北大嶼山廢物轉運站。工程項目的位置載於本許可證圖1

 

Scale and Scope of Designated Project

指定工程項目的規模和範圍

The Project involves the construction and operation of a grease trap waste treatment facility with a daily design throughput of 300 tonnes and implementation of minor modifications and enhancement works including replacement of aged plants, upgrading of odour control system, provision of on-shore power supply for marine vessels etc. at the North Lantau Transfer Station.

 

工程項目包括於現有北大嶼山廢物轉運站內建造和營運一所每天處理量300公噸隔油池廢物處理設施,以及進行小型改建及提升工程,包括更換已老

化的設備、提升廢物轉運大樓内現有的除味系統、加設岸電設施等

 

 


PART C (PERMIT CONDITIONS)

C (許可證條件)

 

1.         General Conditions

            般條件

 

1.1       The Permit Holder and any person constructing or operating the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of appropriate action being taken under the EIAO.

許可證持有人及任何建造或營辦工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例) (499) 的規定,而當局可根據環評條例採取適當行動。

 

1.2       The Permit Holder and any person constructing or operating the Project shall ensure full compliance with all legislation from time to time in force including, without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.

許可證持有人及任何建造或營辦工程項目的人士須確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(400) 、《空氣污染管制條例》(311)、《水污染管制條例》(358) 、《海上傾倒物料條例(466) 及《廢物處置條例》(354)。本許可證本身不會就根據任何法例提的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。

 

1.3       The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of this Permit readily available at all times for inspection by the Director or his authorised officers at all sites covered by this Permit. Any reference to this Permit shall include all documents referred to in this Permit and also the relevant documents in the Register.

許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A 所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。

 

1.4       The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated in this Permit. The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.

許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。

 

1.5       The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public’s information at all times. The Permit Holder shall ensure that the most updated information about this Permit, including any amended Permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of this Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

許可證持有人須在建造工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回本許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從建造工地除下,不再展示。

 

1.6       The Permit Holder and any person constructing or operating the Project shall construct and operate the Project in accordance with the project description in Part B of this Permit.

許可證持有人及任何建造或營辦工程項目的人士須依據本許可證B部的工程項目說明,建造及營辦工程項目。

 

1.7       The Permit Holder and any person constructing or operating the Project shall ensure that the Project is designed, constructed and operated in accordance with the information and recommendations described in the Project Profile (Register No.: PP-646/2022); the application documents for environmental permits; other relevant document in the Register; the information and mitigation measures described in this Permit; mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on-going surveillance and monitoring activities during all stages of the Project.  Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded in this Permit or otherwise agreed by the Director.      

許可證持有人及任何建造或營辦工程項目的人士須確保工程項目按照下述資料設計、建造及營辦:工程項目簡介(登記冊編號:PP-646/2022)所說明的資料及相關建議;環境許可證的申請文件;登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證載的條件須提交署長存放或獲署長批准的文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或另獲署長同意。

 

1.8       All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise as specified by the Director.

所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內署長另行指定的期限內,根據署長的意見加以修正及重新提交。

 

1.9       All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the EIAO (Cap. 499).

所有提交署長並獲批准的文件、所有提交署長存放而沒有收到署長意見的文件或根據本許可證提交並已依照署長的意見作出修訂的所有文件,將詮釋為本許可證C部所說明的許可證條件的一部分。對提交文件所作的任何修訂,均須獲得署長的書面批准,或符合有關許可證條件所述。凡與所提交的文件有不符合的情況,均可能構成違反環評條例 (499)

 

1.10     The Permit Holder shall release all finalised submissions as required under this Permit to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any means as specified by the Director, for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何方法,以供公眾查閱。此,許可證持有人須提供足夠數量的複本。

 

1.11     The Permit Holder shall submit and / or deposit all submissions within the time as specified in the Conditions of this Permit. All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalised submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

許可證持有人須在本許可證條件所列明的時間內,提交/或存放所有文件。本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子本,均須以超文本標示語言(HTML)(4.0或較後版本)和便攜式文件格式(PDF)(1.3或較後版本)製作,除非另獲署長同意,電子本須與硬複本同時提交。

 

1.12     The Permit Holder shall notify the Director in writing the commencement date of construction of the Projectno later than 1 month prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

許可證持有人須在工程項目建造工程展開前最少個月,以書面方式把工程項目建造工程的展開日期通知署長。建造工程的展開日期如有任何更改,許可證持有人必須立即以書面方式通知署長。

 

1.13     For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.

為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。

 

1.14     The Permit Holder shall notify the Director in writing the commencement date of operation of the proposed Grease Trap Waste Treatment Facility (GTWTF) no later than 1 month prior to the commencement of operation of the proposed GTWTF. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of operation.

許可證持有人須在議隔油池廢物處理設施開始營辦前最少個月,以書面方式把議隔油池廢物處理設施開始營辦的日期通知署長。開始營辦的日期如有任何更改,許可證持有人須立即以書面方式通知署長。

 

2.         Specific Conditions

            特定條件

          

2.1       The Permit Holder shall employ an Independent Environmental Checker (IEC) to audit the implementation of the environmental mitigation measures recommended in the Project Profile (Register No. PP-646/2022), including the construction & demolition waste disposal record, during the construction phase of the Project.

許可證持有人須聘用一名獨立環境查核人審核所有工程項目簡介(登記冊編號: PP-646/2022)內建議的環境緩解措施實施,包括施工階段處置拆建物料的紀錄

 

2.2       The Permit Holder shall, no later than one month before the operation of the proposed GTWTF, deposit an Audit Report to the Director to confirm all environmental protection measures and design measures described in the Project Profile have been fully implemented. The Audit Report shall pay particular attention to the proposed odour control measures and be verified by the IEC employed under Condition 2.1 above.

許可證持有人須在擬議隔油池廢物處理設施開始營辦前最少個月向署長存放一份審核報告書,以確定工程項目簡介(登記冊編號 : PP-646/2022)所說明的所有環境緩解措施及設計措施均已全面予以實施有關審核報告書須特別關注氣味控制措施並按上文條件第2.1項內所述的獨立環境查核人核實

 

2.3       To minimise odour impact during operation of the Project, the proposed GTWTF shall be enclosed and maintained at negative pressure with the odourous gas extracted and diverted to a two-stage deodorisation system comprising wet chemical scrubbers and activated carbon filters for treatment before discharge to the atmosphere.

為盡量減低工程項目營辦期間的氣味影響,擬議隔油池廢物處理設施須採用密封式設計並保持在負壓狀態,而所收集的氣體須送到包括化學洗滌塔和活性碳吸附器的兩階段式除味系統作處理,再排放到大氣中

 

                                                                                           

Notes:

註:

 

1.         This Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions).  Any person relying on this Permit should obtain independent legal advice on the legal implications under the EIAO, and the following notes are for general information only.

本許可證共有3部,即 A部 (許可證主要部分)B部 (指定工程項目的說明) C部 (許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。

 

2.         If there is a breach of any condition of this Permit, the Director or his authorized officer may, with the consent of the Secretary for Environment and Ecology, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

如違反本許可證的任何條件,署長或獲授權人員徵得環境及生態局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。

 

3.         The Permit Holder may apply under Section 13 of the EIAO to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須經修改的許可證替換在工程項目工地內展示的原有許可證。

 

4.         A person who assumes the responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the EIAO to the Director for a further environmental permit.

承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。

 

5.         Under Section 14 of the EIAO, the Director may with the consent of the Secretary for Environment and Ecology, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project site.

根據環評條例第14條的規定,署長可在取得環境及生態局局長的同意下暫時吊銷、更改或取消許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。

 

6.         If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the EIAO before the Project could be continued.  It is an offence under Section 26(1) of the EIAO to construct or operate a designated project listed in Part I of Schedule 2 of the EIAO without a valid environmental permit.

如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表21部所列明的指定工程項目,即屬犯罪。

 

7.         Any person who constructs or operates the Project contrary to the conditions in this Permit, and is convicted of an offence under the EIAO, is liable:

 

(i)                 on a first conviction on indictment to a fine of $2 million and to   imprisonment for 6 months;

(ii)               on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;

(iii)             on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.

 

如任何人在違反本許可證的條件下建造或營辦工程項目,且被裁定觸犯環評條例所訂明的罪行,即屬犯罪:

 

(i)     一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;

(ii)               一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;

(iii)             一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;

(iv)              一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;

(v)               在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。

 

8.         The Permit Holder may appeal against any condition of this Permit under Section 17 of the EIAO within 30 days of receipt of this Permit.

許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。

 

9.         The Notes are for general reference only and that the Permit Holder should refer to the EIAO for details and seek independent legal advice.

上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。

 

Environmental Permit No. FEP-01/613/2022

環境許可證編號  FEP-01/613/2022

Figure 1 |


Back to First Page ][ Back to Main Index ]