Environmental Permit
No. EP-004/1998/D
環境許可證編號EP-004/1998/D
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10 & 13
環
境
影
響
評
估
條
例
(第
499章
)
第
10 及
13 條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A
DESIGNATED PROJECT
建
造
及
營
辦
指
定
工
程
項
目
的
環
境
許
可
證
PART
A (MAIN PERMIT)
A部
(許
可
證
主
要
部
分)
Pursuant
to Section 10 of the Environmental Impact Assessment Ordinance (the Ordinance),
the Director of Environmental Protection (the Director) granted the
Environmental Permit (No. EP-004/1998) to KOWLOON-CANTON RAILWAY CORPORATION
(the "Permit Holder") on 16 September 1998. Pursuant to Section 13 of
the Ordinance, the Director amends the Environmental Permit No. EP-004/1998/C based
on the Application No. VEP-067/2002. The amendments described
below, are incorporated into this Environmental Permit (EP-004/1998/D). This
Environmental Permit as amended is for the construction and operation of the
designated projects described in Part B of this Permit subject to the
conditions described in and attached to Part C of this Permit. .
根 據 環 境 影 響 評 估 條 例 (條 例)
第 10條 的 規 定 , 環 境 保 護 署 署 長 (署 長) 於 1998年
9月 16日 將 環 境 許 可 證 (編 號 EP-004/1998) 批 予 九 廣 鐵 路 公 司 (下 稱 "許 可 證 持 有 人 ")。 根 據 條 例 第 13條 的 規 定 , 署 長 因 應 更 改 環 境 許 可 證
的 申 請 編 號 VEP-067/2002 修 訂 環 境 許 可 證 編 號
EP-004/1998/C。 以 下 修 訂 已 包 含 在 本 環 境 許 可 證 內 (EP-004/1998/D)。 本 經 修 訂 的 環 境 許 可 證 作 為 建 造 及 營 辦 本 許 可 證 B 部 所 說 明 的 指 定 工 程 項 目 , 但 須 遵 守 本 許 可 證 C 部 所
說 明 及 附 載 的 條 件 。
This
Environmental Permit is based on the documents, approval and permissions
described below :
本 環 境 許 可 證 乃 依 據 下 列 的 文 件 、
批 准 及 許 可 條 件 而 簽 發 :
Application
No. |
VEP-067/2002 |
Document
in the Register : |
(a)
West Rail - Final Assessment Report West Kowloon to Tuen Mun Centre -
Environmental Impact Assessment, its Technical Annexes, and Final Landscape
Design Strategy, Report Vol.1 (Register No. EIA-149/1998) [Hereafter referred
to as the EIA report] (b)
Application documents submitted by
Permit Holder including all attachments on 19 August 1998 (Application No.
AEP-004/1998) (c)
Environmental Permit issued on 16
September 1998 (Permit No. EP-004/1998) (d)
Application documents for Variation of
an Environmental Permit including all attachments by Permit Holder submitted
on 21 July 2000. (Application No. VEP-020/2000) (e)
Environmental Permit issued on 18
August 2000 (Permit No. VEP-020/2000/A/EP-004) (f)
Application documents for Variation of
an Environmental Permit including all attachments by Permit Holder submitted
on 29 May 2001. (Application No. VEP-045/2001) (g)
Environmental Permit issued on 27 June
2001 (Permit No. EP-004/1998/B) (h)
Application documents for Variation of
an Environmental Permit including all attachments by Permit Holder submitted
on 11 March 2002. (Application No. VEP-062/2002) (i)
Environmental Permit issued on 9 April
2002 (Permit No. EP-004/1998/C) (j)
Application documents for Variation of
an Environmental Permit including all attachments by Permit Holder submitted
on 10 June 2002. (Application No. VEP-067/2002) (a)
西 部 鐵 路
-最 終 評 估 報 告 西 九 龍 至 屯 門 中 - 環 境 影 響
評 估 、 其 技 術 附 件 及 最 終 景 觀 美 化 設 計 策 略 報 告 第 一 冊 (登 記 冊
檔 號 :EIA-149/1998) [下 稱 "環 評 報 告 "] (b)
許 可 證 持 有 人 於 1998 年 8 月 19 日 提 交 之 申 請 文 件 包 括 所 有 附 件 (申 請 書 編 號
AEP-004/1998) (c)
於
1998 年 9 月 16日 發 出 的 環 境 許 可 證 (許 可 證 編 號
EP-004/1998) (d)
許 可 證 持 有 人 於 2000年 7月 21日 提 交 申 請 文 件 包 括 所 有 附 件 (申 請 書 編 號
VEP-020/2000) (e)
於
2000年 8月 18日
發 出 的 環 境 許 可 證 (許 可 證 編 號
VEP-020/2000/A/EP-004 ) (f)
許 可 證 持 有 人 於 2001年 5月 29日 提 交 之 申 請 文 件 包 括 所 有 附 件 (申 請 書 編 號
VEP-045/2001) (g)
於
2001年 6月 27日
發 出 的 環 境 許 可 證 (許 可 證 編 號 EP-004/1998/B ) (h)
許 可 證 持 有 人 於 2002年 3月 11日 提 交 之 申 請 文 件 包 括 所 有
附 件 (申 請 書 編 號 VEP-062/2002) (i)
於
2002年 4月 9日 發
出 的 環 境 許 可 證 (許 可 證 編 號 EP-004/1998/C ) (j)
許 可 證 持 有 人 於 2002年 6月 10日 提 交 之 申 請 文 件 包 括 所 有 附 件 (申 請 書 編 號
VEP-067/2002) |
Application
No. 申 請 編 號 |
Date
of Application 申 請 日 期 |
List
of Amendments Incorporated into Environmental Permit 已 包 含 在 環 境 許 可 證 內 的 修 訂 項 目 |
Date
of Amendments 修 訂 日 期 |
VEP- 020/2000 |
21
July 2000 |
Add conditions 2.20, 3.14,
Notes 6a, 6b and 6c to Part C of Environmental Permit No. EP-004/1998 Add
reference information to conditions 5.2, 5.6 and 5.10 in Part C of
Environmental Permit No. EP-004/1998 Delete
Figure 1 and Figure 2 in condition 3.8, and subsequent variation of condition
3.14 in Part C of Environmental Permit No. EP-004/1998 Add
the register reference no. of the EIA Report to conditions 1.7, 2.4, 2.5,
2.6, 2.7, 2.9, 2.12, 2.13, 2.14, 2.16, 2.17, 2.18, 2.19, 3.1, 3.3, 3.4, 3.5,
3.6, 5.5, 5.7, 5.8, 5.10 and 6.3 of Part C of Environmental Permit No.
EP-004/1998 |
18
August 2000 |
|
2000年 7月 21日 |
在 環 境 許 可 證 編 號 EP-004/1998的 C 部 內 加 入 第 2.20, 3.14, ,註 6a, 6b及 6c 項 條 件 在 環 境 許 可 證 編 號 EP-004/1998的 C部 內 第 5.2, 5.6及
5.10加 入 參 考 資 料 在 環 境 許 可 證 編 號 EP-004/1998的 C 部 內 刪 除 第 3.8項
條 件 之 圖 1及 圖 2 , 及 跟 隨 修 改 第
3.14 項 條 件 在 環 境 許 可 證 編 號 EP-004/1998 C 部 內 的 第 1.7, 2.4, 2.5, 2.6, 2.7, 2.9, 2.12, 2.13, 2.14,
2.16, 2.17, 2.18, 2.19, 3.1, 3.3, 3.4, 3.5, 3.6, 5.5, 5.7, 5.8, 5.10 及 6.3項 條 件 加 上 登 記 冊 檔 案 編 號 |
2000年 8月 18日 |
VEP- 045/2001 |
29
May 2001 |
Vary conditions 2.20 and
3.14 in Part C of Environmental Permit No. VEP-020/2000/A/EP-004 Add
Notes 6a, 6b and 6c to Part C of Environmental Permit No.
VEP-020/2000/A/EP-004 Add
reference information to conditions 5.2, 5.6 and 5.10 in Part C of
Environmental Permit No. VEP-020/2000/A/EP-004 Vary
condition 5.3 with respect to the change from 12-car train to 9-car train in
Part C of Environmental Permit No. VEP-020/2000/A/EP-004 |
27
June 2001 |
|
|
Vary condition 6.1 with
respect to the change in maximum speed at the section between Tin Shui Wai
and Siu Hong in Part C of Environmental Permit No. VEP-020/2000/A/EP-004 |
|
|
2001年 5月 29日 |
在 環 境 許 可 證 編 號 VEP-020/2000/A/EP-004的
C 部 內 更 改 第 2.20 及 3.14 項 條 件 在 環 境 許 可 證 編 號 VEP-020/2000/A/004的 C 部 加 上 註 6a, 6b, 6c 在 環 境 許 可 證 編 號 VEP-020/2000A/EP-004的 C部 內 第 5.2, 5.6及
5.10項 條 件 加 入 參 考 資 料 在 環 境 許 可 證 編 號 VEP-020/2000/A/EP-004的 C部 內 , 就
12卡 碟 形 制 動 電 氣 化 列 車 至 9卡 碟 形 制 動 電
氣 化 列 車 之 改 動 , 修 改 第 5.3項 條 件
在 環 境 許 可 證 編 號 VEP-020/2000/A/EP-004的 C部 內 , 就 天 水 圍 至
兆 康 一 段 之 最 高 時 速 之 改 動 , 修 改 第 6.1項 條 件 |
2001年 6月 27日 |
VEP- 062/2002 |
11
March 2002 |
Vary conditions 2.20 and
3.14 in Part C of Environmental Permit No. EP-004/1998/B Add Note 6a to Part C of
Environmental Permit No. EP-004/1998/B Add reference
information to conditions 5.2 and 5.10 in Part C of Environmental Permit No.
EP-004/1998/B Add Figure 1, Figure 2 and
Figure 3 to the Environmental Permit No. EP-004/1998/B and subsequent
variation of the figure number in Figure 1 and condition 3.12 of the
Environmental Permit No. EP-004/1998/B. |
9 April 2002 |
|
2002年 3月 11日 |
在 環 境 許 可 證 編 號 EP-004/1998/B的 C 部 內 更 改 第 2.20 及 3.14 項 條 件 在 環 境 許 可 證 編 號 EP-004/1998/B的 C 部 加 上 註 6a 在 環 境 許 可 證 編 號 EP-004/1998/B 的 C部 內 第 5.2及 5.10項 條
件 加 入 參 考 資 料 在 環 境 許 可 證 編 號 EP-004/1998/B加 上 圖 1, 圖 2及 圖 3,及 跟 隨 修 改
環 境 許 可 證 編 號 EP-004/1998/B圖 1及 第 3.12項 條 件 的 附 圖 編 號 |
2002年 4月 9日 |
VEP-
067/2002 |
10
June 2002 |
Vary conditions 2.20 and
3.14 in Part C of Environmental Permit No. EP-004/1998/C Add Note 6a to Part C of
Environmental Permit No. EP-004/1998/C Add reference
information to conditions 5.2, 5.7 and 5.10 in Part C of Environmental Permit
No. EP-004/1998/C |
8
July 2002 |
|
2002年 6月 10日 |
在 環 境 許 可 證 編 號 EP-004/1998/C的 C 部 內 更 改 第 2.20 及 3.14 項 條 件 在 環 境 許 可 證 編 號 EP-004/1998/C的 C 部 加 上 註 6a 在 環 境 許 可 證 編 號 EP-004/1998/C的 C部 內 第 5.2 , 5.7 及
5.10項 條 件 加 入 參 考 資 料 |
2002年 7月 8 日 |
_________________ Date |
________________________________________ (K.
S. CHAN) |
PART
B (DESCRIPTIONS OF DESIGNATED PROJECT)
B部 (指 定 工 程 項 目 的 說 明 )
Hereunder
is the description of the designated project mentioned in Part A of this
environmental permit :
下
列
為
本
環
境
許
可
證
A 部
所
提
述
的
指
定
工
程
項
目
的
說
明
:
Title of Designated Project |
West
Rail, Phase I |
Nature of Designated Project |
A
railway and its associated stations |
Location of Designated Project |
Kowloon
to Tuen Mun |
Scale and Scope of Designated Project(s) |
The
Project is an electrified double-tracked railway system including the railway
alignment, all railway premises, depots, tracks, cuttings, embankments,
tunnels, stations, goods and rail yards, car parks and other areas for
ancillary uses but excludes non-railway developments above stations or above
other railway property. The Project includes the following four sections: |
1.
General Conditions
1.1 The
Permit Holder shall ensure full compliance with all conditions of this
Environmental Permit (the Permit). Any non-compliance with this Permit may
constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap. 499) and shall be definite ground for enforcement action or permit
cancellation where applicable.
1.2 This
Permit shall not remove the responsibility of the Permit Holder to comply with
any legislation currently in force such as Noise Control Ordinance (Cap.400),
Air Pollution Control Ordinance (Cap.311), Water Pollution Control Ordinance
(Cap.358), Dumping at Sea Ordinance (Cap.466), the Waste Disposal Ordinance
(Cap.354) and others.
1.3 The
Permit Holder shall make copies of this Permit available at all times for
inspection by the Director at all sites covered by this Permit.
1.4 The
Permit Holder shall give a copy of this Permit to the person(s) in charge of
the site(s).
1.5 The
Permit Holder shall display a copy of this Permit on the construction site(s)
at all vehicular site entrances/exits for public information at all times. The
Permit Holder shall ensure that the most updated information about the
environmental permit, including any amended permit, is displayed at such
locations. If the Permit Holder surrenders a part or the whole of the Permit,
the notice he sends to the Director of Environmental Protection shall also be
displayed at the same locations as the original Permit.
1.6 The
Permit Holder shall construct and operate the Project in accordance with the
project descriptions in Part B of this Permit.
1.7 The
Permit Holder shall ensure that the Project is designed, constructed and
operated in accordance with the information and recommendations contained in
the EIA report [ref: register no EIA 149/1998].
2.
Submissions or Measures before Commencement of Construction of Certain
Sections of the Project
2.1 The
Permit Holder shall employ an Environmental Manager with at least 7 years of
experience in environmental monitoring and auditing or environmental
management. The Environmental Manager shall be responsible for supervising the
environmental monitoring and audit programme and executing the duties as
recommended in the Environmental Monitoring and Audit Manual to be prepared in
accordance with section 2.18 of this Permit.
2.2 The
Permit Holder shall employ an Independent Environmental Checker with at least 7
years of experience in environmental monitoring and auditing or environmental
management. The Independent Environmental Checker shall verify the overall
environmental performance of the Project, including the implementation of all
the environmental mitigation measures, submissions relating to environmental
monitoring and auditing, and any other submissions required under this Permit.
2.3 Environmental
Team(s) shall be established prior to the commencement of construction of
relevant sections of the Project, described in Part B of this Permit. The
Environmental Team(s) shall be headed by a team leader who has at least 7 years
experience in environmental monitoring auditing or environmental management.
2.4 Before
the commencement of construction of relevant sections of the Project described
in Part B of this Permit, the Permit Holder shall deposit with the Director 3
sets of 1 to 1000 scale layout drawings with an explanatory statement showing
the works boundary, railway and tunnel alignment, environmental mitigation
measures recommended in the EIA report [ref: register no EIA 149/1998] and any
other facilities assessed in the EIA report. The drawings shall be certified by
the Environmental Manager and verified by the Independent Environmental Checker
as conforming to the findings and recommendations of the EIA report [ref:
register no EIA 149/1998]. The Project shall be constructed in accordance with
the information and recommendations contained in the EIA report [ref: register
no EIA 149/1998] and the drawings deposited with the Director. All measures set
out in the drawings shall be fully implemented. (See Note 6)
2.5 Before
the commencement of construction of track sections not in tunnel, the Permit
Holder shall deposit with the Director 3 sets of drawings with an explanatory
statement showing all the noise mitigation measures. The drawings shall be
certified by the Environmental Manager and verified by the Independent
Environmental Checker as conforming to the findings and recommendations of the
EIA report [ref: register no EIA 149/1998]. The Project shall be constructed in
accordance with the information and recommendations contained in the EIA report
[ref: register no EIA 149/1998] and the drawings deposited with the Director.
All measures set out in the drawings shall be fully implemented. In particular,
the following requirements shall be included :
(a)
the use of resilient rail baseplates for
track on viaduct, to reduce vibration transmission to the viaduct structure and
thereby reduce re-radiated noise from the structures;
(b) for
the track on viaduct, mounting the track on a floating slab system to further
reduce vibration transmission to the viaduct structure;
(c) the
use of extended wheel skirts and adsorptive lining beneath the car, to create
an acoustic plenum in the under-car area;
(d) the
creation of a second acoustic plenum on either side of the car, using either a
walkway at the side of the track or a purpose-built construction. This would
also incorporate absorptive lining in the area beneath the plenum;
(e) edge
walls with sound adsorption; and
(f) barriers
and enclosures.
2.6 Before
the commencement of construction of West Rail Depot, the Permit Holder shall
deposit with the Director three sets of drawings with an explanatory statement
showing the mitigation measures for fixed plant noise. The drawings shall be
certified by the Environmental Manager and verified by the Independent
Environmental Checker as conforming to the findings and recommendations of the EIA
report [ref: register no EIA 149/1998]. The Project shall be constructed in
accordance with the information and recommendations contained in the EIA
report[ref: register no EIA 149/1998 and the drawings deposited with the
Director. (See Note 6). All measures set out in the drawings shall be fully
implemented. In particular, the following noise sources shall be addressed :
(a) train rolling noise at West Rail Depot;
(b) ventilation
fans, vents and buildings;
(c) chiller
plant;
(d) cooling
water pumping station; and
(e) traction
sub-stations.
2.7 The
Permit Holder shall submit to the Director for approval three sets of landscape
master plan(s) 1 to 1000 scale together with a master implementation schedule
before the commencement of construction of relevant sections of the Project
described in Part B of this Permit. The drawings shall be expanded based on the
Landscape Strategy Report of the EIA report[ref: register no EIA 149/1998] and
shall show the conceptual landscape proposals within the works boundary to be
in accordance with the recommendations of the EIA report[ref: register no EIA
149/1998] during the construction and operation of the Project. It shall also
include a management and maintenance schedule indicating clearly how the
landscape areas will be managed and maintained. The landscape drawings shall be
certified by the Environmental Manager, and verified by the Independent
Environmental Checker. All measures recommended in the approved drawings shall
be fully implemented in accordance with the details and time schedule set out
in the approved landscape master plan(s). (See Note 6).
2.8 Three
sets of detailed landscape drawings shall be submitted to the Director for
approval before the commencement of landscape and visual mitigation works of
the relevant section(s) of the Project or part(s) thereof. Such drawings shall
expand on the approved landscape master plan(s) and shall show the detailed
landscape proposals during the construction and operation of the Project. The
landscape drawings shall be certified by the Environmental Manager, and
verified by the Independent Environmental Checker. All measures recommended in
the approved drawings shall be fully implemented in accordance with the details
and time schedule set out in the approved landscape drawings.
2.9 The
Permit Holder shall submit a field evaluation programme and an archaeological
action plan for each of the Central, Northern and Western Sections in
accordance with the requirements of the EIA Report [ref: register no EIA 149/1998]
before commencement of construction of the relevant sections, and obtain the
approval of the Director on the programmes and action plans. The field
evaluation programme and the archaeological action plans shall be certified by
the Environmental Manager, and verified by the Independent Environmental
Checker. All measures recommended in the approved programme and action plans
shall be fully implemented in accordance with the details and time schedules
set out in the approved programme and action plans. In particular, the
proposals for mitigation measures to the archaeological resources revealed
during the field evaluation shall be included. (See Note 6).
2.10
The design of the West Rail Depot shall avoid direct impacts to the Kwan Tai
Shing Kung temple and associated grove situated to the north-east of Cheung Po
and provide for buffer zone around the temple during construction;
2.11
The external design of the Tin Shui Wai Station shall avoid adverse impacts to
the Tsui Shing Lau Pagoda and be compatible with the local cultural
environment.
2.12
For the Western Section, a condition survey on the Tsui Shing Lau Pagoda shall
be carried out as recommended in the EIA report [ref: register no EIA 149/1998]
and deposited to the Director. The condition survey shall be undertaken prior
to and following the completion of works and sample vibration monitoring shall
be undertaken during construction. A vibration limit of 2mm/s peak particle
velocity should be applied to all construction related activities. The condition
survey shall be certified by the Environmental Manager, and verified by the
Independent Environmental Checker as conforming to the information and
recommendation contained in the EIA report [ref: register no EIA 149/1998]
before being deposited with the Director.
2.13
Before the commencement of construction of the Northern Section and the 270m
alignment from North Portal of Tai Lam Tunnel to West Rail Depot of the
Project, the Permit Holder shall submit a Habitat Creation and Management Plan
as recommended in the EIA report [ref: register no EIA 149/1998] and obtain the
approval of the Director on the Habitat Creation and Management Plan. Before
submission to the Director, the Habitat Creation and Management Plan shall be
certified by the Environmental Manager and verified by the Independent
Environmental Checker.
2.14
Before the commencement of the construction of Central Section and Western
Section, the Permit Holder shall submit and obtain approval of the Director for
the Contamination Assessment Plans (CAP) of the potentially contaminated sites
in accordance with the information and recommendations contained in the EIA
report [ref: register no EIA 149/1998] and Annex 19, Section 3 of the TM.
Before submission to the Director, the Contamination Assessment Plans shall be
certified by the Environmental Manager and verified by the Independent
Environmental Checker. (See Note 6)
2.15
Before the commencement of the construction of Central Section and Western
Section, the Permit Holder shall submit and obtain the approval of the Director
Contamination Assessment Reports (CAR) based on the endorsed Contamination
Assessment Plans in accordance with Annex 19, Section 3 of the TM. During the
preparation of the Contamination Assessment Report, if land contamination is
confirmed, Remediation Action Plans (RAP) are required in accordance with Annex
19, Section 3 of the TM and shall be submitted as a combined report with the
CAR to the Director for approval. Before submission to the Director, the
results of the Contamination Assessment Reports and any Remediation Action
Plans shall be certified by the Environmental Manager and verified by the
Independent Environmental Checker. All measures recommended in the approved
Remediation Action Plans shall be fully implemented in accordance with the
requirements and time schedule set out in the approved Remediation Action
Plans.
2.16
Before the commencement of the construction, the Permit Holder shall deposit
with the Director waste management plan(s) as recommended in the EIA report
[ref: register no EIA 149/1998]. Before submission to the Director, the waste
management plan shall be certified by the Environmental Manager and verified by
the Independent Environmental Checker. Measures covered by the Waste Disposal
Ordinance shall not be included in the waste management plan(s). All measures
recommended in the approved waste management plan(s) shall be fully implemented
in accordance with the requirements and time schedule(s) set out in the waste
management plan(s). (See Note 6).
2.17
Before the commencement of the construction of the Central Section, the Permit
Holder shall deposit with the Director a detailed construction risk assessment
of the work site located south west of Kwai Hei Streeet, Kwai Fong as
recommended in the EIA report[ref: register no EIA 149/1998]. The report shall,
with reference to Annex A, address the risks of landfill gas accumulation in
temporary structures, storage facilities and the processes and activities to be
undertaken at the site and shall be certified by the Environmental Manager, and
verified by the Independent Environmental Checker. All measures recommended in
the report shall be fully implemented in accordance with the requirements and
time schedule set out in the report deposited with the Director. (See Note 6).
2.18
In accordance with the information and recommendations contained in the EIA
report[ref: register no EIA 149/1998], the Permit Holder shall deposit an
Environmental Monitoring and Audit (EM&A) Manual with the Director within
one month of the issuance of this Permit. The EM&A Manual shall satisfy the
requirements as prescribed in section 10, SCHEDULE 4 of the Environmental
Impact Assessment Ordinance and Annex 21 of the Technical Memorandum on
Environmental Impact Assessment Process. The EM&A Manual shall be certified
by the Environmental Manager and verified by the Independent Environmental
Checker before submission to the Director. (See Note 6).
2.19
In accordance with the information and recommendation contained in the EIA
report [ref: register no EIA 149/1998], the Permit Holder shall deposit an
Implementation Schedule with the Director within one month of the issuance of
this Permit. The Implementation Schedule shall contain a schedule of all
mitigation measures recommended in the EIA report, listing out what the
mitigation measures are, by whom, when, where and to what requirements, and
including the key environmental monitoring and audit requirements. The
implementation Schedule shall be certified by the Environmental Manager and
verified by the Independent Environmental Checker before submission to the
Director. All measures included in the Implementation Schedule shall be fully
implemented. (See Note 6).
2.20
The Permit Holder pursuant to
(I)
The Application for Variation No. VEP-067/2002
with respect to
(a) revision
of the 86m long full noise enclosure at Tuen Mun Station to semi-noise
enclosure; and provide additional enclosure on the north of this enclosure;
(II)
The Application for Variation No. VEP-062/2002
with respect to
(b) increase
in the elevation of viaduct by approximately 8m at Yick Yuen;
(III)
The Application for Variation No. VEP-045/2001
with respect to
(c)
reduction
of train length from 12 cars to 9 cars with increase in train frequency from 30
to 40 trains per hour during 0600 to 0700;
(d)
reduction of train speed between Tin Shui Wai
and Siu Hong from 130km/h to 100km/h;
(e)
revised locations of noise enclosure and
additional height noise barriers at the north of Kam Sheung Road Station, near
Pok Oi Hospital, the west of Long Ping Station, the west of Tin Shui Wai
Station, Tin Sam Tsuen to Lam Tei and Tuen Mun;
(IV)
The Application for Variation No. VEP-020/2000
(f) the construction method for the Tsing Tsuen Tunnel;
(g) the revised alignment in Tsuen Wan;
(h) the increased quantities of marine mud at Tsuen Wan Bay;
shall
within 45 days, provide supplementary information for the Director's approval
of any changes necessary to the submissions previously made to the Director in
fulfilment of conditions 2.4, 2.5, 2.6, 2.7, 2.8, 2.9, 2.14, 2.16, 2.17, 2.18
and 2.19 above. All supplementary information shall be certified by the
Environmental Manager and verified by the Independent Environmental Checker
before submission to the Director. All mitigation measures arising from
submitted supplementary information shall be fully implemented in accordance
with the details and time schedule set out in the approved supplementary
information.
2.21
All finalised submissions, as required under this part of the permit, shall be
released to the public if requested by the Director, by depositing copies in
the Environmental Impact Assessment Ordinance Register Office or any other
places or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of submissions.
3.
Submissions or Measures during the Construction Period.
3.1 Within
two months of commencement of construction of each of the Southern, Central,
Northern and Western sections of the Project, the Permit Holder shall deposit
with the Director environmental management plan(s) as recommended in the EIA
Report [ref: register no EIA 149/1998]. Before their submission to the
Director, the environmental management plan(s) shall be certified by the
Environmental Manager and verified by the Independent Environmental Checker.
3.2 Within
6 months of the commencement of construction of the Northern Section and the
270m alignment from North Portal of Tai Lam Tunnel to West Rail Depot of the
Project, the Permit Holder shall submit an implementation programme for the
Habitat Creation and Management Plan submitted under condition 2.13 and obtain
the approval of the Director. Before its submission to the Director, the
implementation programme shall be certified by the Environmental Manager and verified
by the Independent Environmental Checker. All measures recommended in the
approved Habitat Creation and Management Plan and its implementation programme
shall be fully implemented.
3.3 All
design or construction measures described in the submissions approved or
deposited under section 2, and conditions 3.1 and 3.2 above shall be fully
implemented. Any changes to the measures shall be justified by Environmental
Manager and verified by the Independent Checker as conforming to the
requirements of the EIA Report [ref: register no EIA 149/1998]. (See Note 6).
3.4 In
accordance with the information and recommendations contained in the EIA Report
[ref: register no EIA 149/1998] and with reference to Annex B, measures to
mitigate environmental impacts from site run-off and drainage shall be
implemented.
3.5 In
accordance with the information and recommendations contained in the EIA Report
[ref: register no EIA 149/1998]) and with reference to Annex C, measures to
mitigate water quality impacts during tunneling and station construction shall
be implemented.
3.6 In
accordance with the information and recommendations contained in the EIA Report
[ref: register no EIA 149/1998] and with reference to Annex D, measures to
mitigate water quality impacts during reclamation work and other construction
activities shall be implemented.
3.7 For
the construction of the Central Section at Tsuen Wan Bay Reclamation, the
combined rate of filling and dredging shall not be exceeding 15,000cu.m. per
day for filling and 1,000cu.m. per day for the duration of the 16-hour working
days for dredging. The status of compliance with these rates shall be reported
in the monthly EM&A reports in condition 4.5 of this Permit.
3.8 For
the Tsuen Wan Central Salt Water Pumping Station at Tsuen Wan Bay Reclamation,
silt curtain mitigation around dredging shall be adapted to maintain the
flushing water intakes at acceptable levels.
3.9 Storm
water culverts, including Tai Ho and Ma Tau Pa Culverts, shall be relocated
along the existing coastline before dredging and reclamation filling being
undertaken in order to avoid water quality impacts.
3.10
To mitigate the cultural heritage and archaeological impacts during
construction:
(a)
The Director shall be informed
immediately if any antiquities are discovered during the course of the
construction works to further assess the cultural value of the items;
(b) Direct
impact to any historical buildings or structures identified shall be avoided.
Devices shall be attached to the walls of those historical buildings next to
the working site so as to monitor the impact of vibration on the structural
stability of the historic buildings; and
(c) a
buffer zone of at least 5m shall be adopted between the Lau's residence at Tung
Shing Lei (east of Yuen Long) and the site boundary for the construction work
to avoid direct impacts to the buildings.
3.11
During the construction of the Northern Section, native species shall be
included in the plant list for revegetation of finished cut slope and lineside
planting.
3.12
The following measures shall be undertaken to protect the marsh habitat
adjacent to Kam Tin Road as shown in Figure 4:
(a)
Bunding, sheet piling shall be installed
at the works boundary within and adjacent to the marsh to prevent dewatering of
the marsh outside the work areas. Such devices shall be removed on the
completion of construction works;
(b) Solid
fencing shall be installed at the boundary of works area within and adjacent to
the marsh. The works boundary shall be regularly inspected and any necessary
maintenance of the fencing shall be undertaken within 24 hours; and
(c) Works
areas at the marsh that are not permanently occupied by the Project shall be
reinstated back to original conditions immediately after the completion of the
construction.
3.13
Fish ponds that are temporarily disturbed during construction shall be
reinstated back to fish ponds after completion of construction.
3.14
The Permit Holder pursuant to
(I) The Application for Variation No.
VEP-067/2002 with respect to
(a) revision
of the 86m long full noise enclosure at Tuen Mun Station to semi-noise
enclosure; and provide additional enclosure on the north of this enclosure;
(II) The Application for Variation No. VEP-062/2002 with respect to
(b) increase
in the elevation of viaduct by approximately 8m at Yick Yuen;
(III)
The Application for Variation No. VEP-045/2001
with respect to
(c)
reduction
of train length from 12 cars to 9 cars with increase in train frequency from 30
to 40 trains per hour during 0600 to 0700;
(d)
reduction of train speed between Tin Shui Wai
and Siu Hong from 130km/h to 100km/h;
(e)
revised locations of noise enclosure and
additional height noise barriers at the north of Kam Sheung Road Station, near
Pok Oi Hospital, the west of Long Ping Station, the west of Tin Shui Wai
Station, Tin Sam Tsuen to Lam Tei and Tuen Mun;
(IV) The
Application for Variation No. VEP-020/2000
(f) the construction method for the Tsing Tsuen Tunnel;
(g) the revised alignment in Tsuen Wan;
(h) the increased quantities of marine mud at Tsuen Wan Bay;
shall
within 45 days, provide supplementary information for the Director's approval
of any changes necessary to the submissions previously made to the Director in
fulfilment of condition 3.1. All supplementary information shall be certified
by the Environmental Manager and verified by the Independent Environmental
Checker before submission to the Director. All measures in the approved
supplementary information shall be fully implemented in accordance with the
details and time schedule set out in the approved supplementary information.
(See note 6).
3.15
All finalised submissions, as required under this part of the permit, shall be
released to the public if requested by the Director, by depositing copies in
the Environmental Impact Assessment Ordinance Register Office or any other
places or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of submissions.
4.
Environmental Monitoring and Audit During Construction
4.1 Any
changes to the EM&A arrangements as required under the EM&A Manual or
under the Implementation Schedule shall be justified by the Environmental
Manager, and verified by the Independent Environmental Checker in the monthly
EM&A Reports and submitted to the Director under condition 4.5.
4.2 EM&A
requirements shall be implemented as set out in the EM&A Manuals and
monthly EM&A Reports unless the changes are justified in the monthly
EM&A Reports submission, verified by the Independent Environmental Checker
and approved by the Director.
4.3 Samples
and measurements shall be taken in accordance with the requirements of noise,
air quality, water quality monitoring, ecological in the EM&A Manual by:
(a) conducting baseline air, noise and water quality monitoring at the specified locations and frequencies;
(b) conducting
impact monitoring on air quality, water quality, noise quality, and ecological
resources at the specified locations and frequencies;
(c) in
cases where specified criteria in the EM&A Manual are exceeded, carrying
out remedial actions in accordance with Event Contingency Plans, to be set out
in the EM&A Manual; and
(d) logging
and keeping records of the details of (a) to (c) above, within 3 working days
of the collection of data or completion of remedial action, for the purposes of
preparing and submitting EM&A Reports, and to make available for
information for inspection on site,
4.4 Ten
copies of the Baseline Monitoring Report certified by the Environmental
Manager, and verified by the Independent Environmental Checker shall be
submitted to the Director one month before the commencement of any major
construction works that would affect the monitoring results.
4.5 Ten
copies of monthly EM&A Reports certified by the Environmental Manager, and
verified by the Independent Environmental Checker shall be submitted to the
Director within 10 working days from the end of the reporting month.
4.6 The
submitted reports as required in condition 4.4 and 4.5 shall be rectified in
accordance with the comments made by the Director within one month or otherwise
specified by the Director.
4.7 Actions
described in the action plan(s) of the EM&A Manual shall be carried out, in
accordance with the time frame set out in the action plan(s), or as agreed by
the Director.
4.8 All finalised submissions, as required under
this part of the Permit, shall be released to the public by depositing copies
in the Environmental Impact Assessment Ordinance Register Office or any other
places or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of submissions.
5.
Submissions or Measures before Operation of the Project
5.1 All
design or operational measures described in the submissions approved, or
deposited under section 2 and section 3 above, shall be fully implemented.
5.2 In
accordance with the information and recommendations contained in the EIA Report
[ref: register no EIA 149/1998], the information contained in the Application
for Variation No. VEP-020/2000, Environmental Permit No. VEP-020/2000/A/EP-004,
Application for Variation No. VEP-045/2001, Environmental Permit No. EP-004/1998/B,
Application for Variation No. VEP-062/2002, Environmental Permit No. EP-004/1998/C,
Application for Variation No. VEP-067/2002 and any approved supplementary
information arising therefrom, the Permit Holder shall submit an Operational
Environmental Monitoring and Audit (EM&A) Manual for the approval by the
Director prior to the commissioning of the project. The Operational EM&A
Manual shall satisfy the requirements as prescribed in section 10, SCHEDULE 4
of the Environmental Impact Assessment Ordinance and Annex 21 of the Technical
Memorandum on Environmental Impact Assessment Process. The Operational EM&A
Manual shall be certified by the Environmental Manager and verified by the
Independent Environmental Checker before submission to the Director. In
particular, the requirements on landfill gas hazard monitoring, maintenance,
precautionary and emergency measures, with reference to Annex E, shall be
included. (See Note 6).
5.3 Prior
to the operation of the Project, the Permit Holder shall submit to the
satisfaction of the Director a proposal for performance test(s) to illustrate that
the 9-car disc braked Electric Multiple Unit train would meet the specification
of maximum level (Lmax) not exceeding 82.5dB(A) at 130kph measured at 25m from
the at-grade ballasted tracks. The performance test proposal shall be certified
by the Environmental Manager and verified by the Independent Environmental
Checker.
5.4 Prior
to the operation of the Project, the Permit Holder shall submit to the
satisfaction of the Director a report on performance test of the disc braked
Electric Multiple Unit train on the basis of condition 5.3. The performance
test report shall be certified by the Environmental Manager and verified by the
Independent Environmental Checker.
5.5 For
the Southern Section, the railway shall be fully contained in a box structure
and covered by a landscaped earth mound in accordance with the information and
recommendations contained in the EIA Report [ref: register no EIA 149/1998].
5.6 For
the Central Section, except the 270m at the northern end, the railway shall be
built in a tunnel in accordance with the information and recommendations
contained in the EIA Report [ref: register no EIA 149/1998], the information
contained in the Application for Variation No. VEP-020/2000, Environmental
Permit No. VEP-020/2000/A/EP-004, Application for Variation No. VEP-045/2001 and
any approved supplementary information arising therefrom. (See Note 6).
5.7 For
the Northern Section and Western Section, the noise mitigation measures shall
be constructed in accordance with the information and recommendations contained
in the EIA Report [ref: register no EIA 149/1998], the information contained in
the Application for Variation No. VEP-045/2001, Environmental Permit No. EP-004/1998/B,
Application for Variation No. VEP-062/2002, Environmental Permit No. EP-004/1998/C
and Application for Variation No. VEP-067/2002.
5.8 The
Permit Holder shall liaise with the Fire Service Department to work out an
off-site Emergency Plan for Au Tau Water Treatment Work including the
arrangements for the external services to stop trains from entering the
affected area from either direction in the event of a chlorine release, in
accordance with the information and recommendations in the EIA Report [ref:
register no EIA 149/1998].
5.9 Ventilation
intakes for Kam Tin Station and the shops and offices there should be located
at as high a level as reasonably practicable and should be substantially
enclosed.
5.10
Before operation of the Project, the Permit Holder shall carry out an audit to
confirm that all the agreed environmental measures for the Project's operation
have been fully implemented. The audit shall cover all measures recommended in
the EIA Report [ref: register no EIA 149/1998], described in submissions
approved, or deposited with the Director under section 2, section 3, and
section 5 of this Permit. The result of the audit shall be documented in an
Audit Report and submitted to the Director prior to operation of the Project.
The audit Report shall be certified by the Environmental Manager and verified
by the Independent Environmental Checker as conforming to the findings and
recommendations of the EIA Report [ref: register no EIA 149/1998], the
information contained in the Application for Variation No. VEP-020/2000,
Environmental Permit No. VEP-020/2000/A/EP-004, Application for Variation No.
VEP-045/2001, Environmental Permit No. EP-004/1998/B, Application for Variation
No. VEP-062/2002, Environmental Permit No. EP-004/1998/C, Application for
Variation No. VEP-067/2002 and any submissions approved or deposited with the
Director. (See Note 6).
5.11
All finalised submissions, as required under this part of the Permit, shall be
released to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office or any other places or by any other means
as specified by the Director for public inspection. For this purpose, the
Permit Holder shall provide sufficient copies of submissions.
5.12
Five sets of as-built drawings of scale 1 to 1000 with an explanatory statement
showing the alignment and mitigation measures covered by this Permit, shall be
deposited to the Director within three months after the completion of
construction of each of the Southern, Central, Northern and Western sections.
6.
Environmental Mitigation Measures during Operation Period
6.1 The
maximum train speed shall be 130km/hr except for train speed between Tin Shui
Wai and Siu Hong which is reduced to 100km/hr. Prior to any increase in train
frequency, train length and speed with respect to the initial start-up, a noise
assessment report shall be submitted and obtain approval from the Director. The
noise assessment is to evaluate the adequacy of noise mitigation measures and
develop enhancement programmes. Before its submission to the Director, the
noise assessment report shall be certified by the Environmental Manager and
verified by the Independent Environmental Checker. All measures recommended in
the approved noise assessment report Plan shall be fully implemented in
accordance with the requirements and time schedules set out in the report.
6.2 In
line with the commitment made by the Permit Holder, the multi-plenum system
should be designed to provide the flexibility for future enhancement so that
edge wall barrier heights can be incrementally extended for increased noise
attenuation from 1.2 m upto full enclosure. This is to provide greater
flexibility in the long term land use planning of areas through which the
Project passes and will facilitate, as yet uncommitted, developments, to be
considered in much closer proximity to the railway than would otherwise be the
case.
6.3 In
accordance with the information and recommendations contained in the EIA Report
[ref: register no EIA 149/1998] and Annex F, measures to mitigate the water
quality impact during operation shall be implemented.
6.4 Before
public sewerage becomes available in Kam Tin, waste water and sewage arising
from the proposed Kam Tin Station, KCRC Head Quarter and West Rail Depot (WRD)
shall be collected at holding tanks and transported to Yuen Long Sewage
Treatment Works by road tanker for off-site treatment. Once public sewerage is
available in Kam Tin, waste water and sewage arising from the proposed Kam Tin
Station, KCRC Head Quarter Building and WRD shall be redirected to discharge
directly to the public sewer. Waste water and sewage arising from uses other
than the three above, including stations, railway premises, depots and
ancillary uses, shall be conveyed to public sewer after any pre-treatment.
6.5 The
Permit Holder shall fully implement the EM&A requirements as set out in the
Operational Manual approved under condition 5.2. Any changes to the EM&A
arrangement shall be justified by the Environmental Manager, verified by the
Independent Environmental Checker and approved by the Director.
6.6 The
Permit Holder shall fully implemented the EM&A requirements as set out in
the Operational EM&A Manual approved under condition 5.2. Any changes to
the E M &A arrangements and requirements as set out shall be justified by
the Environmental Manager, verified by the Independent Environmental Checker
and approved by the Director.
6.7 Actions
described in the action plan(s) of the Operational EM&A Manual shall be
carried out, in accordance with the time frame set out in the action plan(s),
or as agreed by the Director.
6.8 All
finalised submissions, as required under this part of the Permit, shall be
released to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office or any other places or by any other means
as specified by the Director for public inspection. For this purpose, the
Permit Holder shall provide sufficient copies of submissions.
Notes:
1. This
Environmental Permit consists of three parts, namely, PART A (Main Permit),
PART B (Description of Designated Project) and part C (Permit Conditions).
2. The
Permit Holder may apply under section 13 of the Environmental Impact Assessment
Ordinance to the Director for a variation of the conditions of this
Environmental Permit. The Permit Holder shall replace the original Permit
displayed on the construction site, by the amended Permit.
3. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under section 12 of
the Ordinance to the Director for a further Environmental Permit.
4. Under
section 14 of the Ordinance, the Director with the consent of the Secretary for
Planning, Environment and Lands, may suspend, vary or cancel this Permit. The
Permit shall be removed from the display on the construction site.
5. If
this Permit is cancelled or surrendered during the construction or operation,
an Environmental Permit must be obtained under the Ordinance before the
construction or operation of the Project could be continued. It is an offence
under section 26(1) of the Ordinance to construct or operate a designated
project without an Environmental Permit.
6. The
Permit Holder shall in regard to the implementation of conditions 2.4, 2.5,
2.6, 2.7, 2.8, 2.9, 2.14, 2.16, 2.17, 2.18 and 2.19 of the permit, give due
consideration to the requirements of condition 2.20. Similarly, the Permit
Holder shall in regard to condition 3.1, give due consideration to condition
3.14.
(a)
revision of the 86m long full noise enclosure at
Tuen Mun Station to semi-noise enclosure; and provide additional enclosure on
the north of this enclosure;
(b)
increase in the elevation of viaduct by
approximately 8m at Yick Yuen as described in the Application VEP-062/2002;
(c)
Reduction
of train length from 12 cars to 9 cars with increase in train frequency from 30
to 40 trains per hour during 0600 to 0700 as described in the Application
VEP-045/2001;
(d)
Reduction of train speed between Tin Shui Wai
and Siu Hong as described in the Application VEP-045/2001;
(e)
Revised locations of noise enclosure and
additional height noise barriers at the north of Kam Sheung Road Station, near
Pok Oi Hospital, the west of Long Ping station, the west of Tin Shui Wai
Station, Tin Sam Tsuen to Lam Tei and Tuen Mun as described in the Application
VEP-45/2001;
(f) Construction
method for the Tsing Tsuen Tunnel refers to Application VEP-020/2000. Drawing
Nos. WR/07/C01/001, WR/07/C01/002, WR/07/C01/003, WR/07/C01/004, WR/07/C01/005,
WR/07/C01/006;
(g)
Revised alignment in Tsuen Wan refers to
Application VEP-020/2000 Drawing Nos.WR/04/C01/001, WR/04/C01/002,
WR/04/C01/003;
(h)
Quantities of Marine Mud at Tsuen Wan Bay refers
to the total dredge quantity increased from 235,000m3 to 263,000m3
as described in the Application VEP-020/2000.
Environmental
Permit No. EP-004/1998/D
Measures
to Mitigate Landfill Gas Risk During Construction
Temporary
Construction worksite located southwest of Kwai Hei Street at Kwai Chung. The
worksite lies within 50m of the northeast perimeter of the former landfill site
near to gas monitoring wells which have shown up to 20% v/v methane
concentrations. Procedures and measures which can be made during the
construction phase to reduce the risk of gas related problems :
(a) A
detailed risk assessment should be conducted to assess and propose
precautionary measures pertinent to the risks from the proposed construction
methods and machinery to be used in the excavations;
(b) Work
method(s) which outlines the measures to be implemented to reduce the risk of
fires and uncontrolled explosions and asphyxiation of workers shall be
proposed;
(c) Workers
should undergo training about the risks and indications of landfill gas and be
thoroughly versed in first aid and emergency and evacuation techniques in the
event of an incident;
(d) Works
must be carried out in strict adherence to the work methods proposed above;
(e)
Strict adherence to the no smoking
policy;
(f) A
mechanical ventilation system must be in use at all times during which
construction work force are engaged in works inside tunnel(s) or excavation(s)
and these work force shall be evacuated in the event of power outages. Work
must not be carried out in the absence of mechanical ventilation and
supervision of adequately trained safety officer;
(g) All
electrical equipment (including extension leads) used in the works must be
fitted with spark arrestors or be intrinsically safe;
(h) Work
must not be carried out in the absence of fire extinguishers, emergency
breathing apparatus and other safety equipment as deemed necessary by safety
consultant or plan submitted by the construction contractor;
(i) Monitoring
of methane, carbon dioxide and oxygen must be carried out at all times during
works using suitable equipment as recommended above. The actions detailed in
Table 1 below must be carried out in the event of gas trigger levels being
breached;
Table
1 Actions to be carried out in the event of Landfill Gas Detection
Parameter |
Measurement |
Action |
O2 |
<19% |
Increase ventilation to
restore O2 to >19% |
<18% |
Stop works |
|
Evacuate personnel |
||
Increase ventilation to
restore O2 to >19% |
||
CH4 |
>10% LEL |
Prohibit hot works |
Increase ventilation to
restore CH4 to <10% LEL |
||
>20% LEL |
Stop works |
|
Evacuate personnel |
||
Increase ventilation to
restore CH4 level to <10% LEL |
||
CO2 |
>0.5% |
Increase ventilation to
restore CO2 to <0.5% |
>1.5% |
Stop works |
|
Evacuate personnel |
||
Increase ventilation to
restore CO2 to <0.5% |
(j) The
exact frequency of monitoring should be determined prior to the commencement of
works, but should be no less frequent than hourly, and be carried out by a
suitably qualified person. Measurements shall be recorded and kept as a record
of safe working conditions with copies of the site diary. Continuous monitoring
via an automated monitoring system may also be adopted. In this event, the gas
levels specified in Table 1 shall be so programmed to automate the actions in
the table and in the event of the trigger levels being breached, to activate
suitable audible and visual warning devices; and
(k) All
measurements taken are to include at a minimum the areas where personnel are
operating as well as the highest and lowest elevations within tunnel(s).
Measurements are to be carried out with the sensor located not greater than 10
mm from the exposed rock surface and at locations where landfill gas has the
highest potential to enter tunnel(s) such as highly fissured areas, dykes,
identified faults, etc.
Measures
to Mitigate Environmental Impacts from Site Run-off and Drainage
To
mitigate the environmental impacts from site run-off and drainage, the
following shall be implemented:
(a) adequate
maintenance of drainage systems shall be provided to prevent flooding and
overflow during the construction period;
(b) the
boundaries of areas of earthworks shall be marked and surrounded by dykes for
flood protection during the construction period. Temporary ditches should be
provided to facilitate runoff discharge into the appropriate watercourses, via
a silt retention pond. Permanent drainage channels should incorporate sediment
basins or traps and baffles to enhance deposition rates. The design of
efficient silt removal facilities should be based on the guidelines in ProPEC
Practice Note 1/94 issued by the Director of Environmental Protection;
(c) construction
works shall be programmed to minimize surface excavation works during the rainy
season (April to September). All exposed earth shall be stabilized as soon as
possible after earthworks have been completed, or alternatively, within 14 days
of the cessation of earthworks where practicable. If excavation of soil cannot
be avoided during the rainy season, or at any time of year when rainstorms are
likely, exposed slope surfaces should be covered by tarpaulin or other means;
(d) sediment
tanks of sufficient capacity constructed from pre-formed individual cells of
approximately 6 to 8 cu.m. capacity shall be used for settling surface runoff
prior to disposal during the construction period. The system capacity shall be
flexible and able to handle multiple inputs from a variety of sources and
particularly suited to applications where the influent is pumped;
(e) open
stockpiles of construction materials (e.g. aggregates, sand and fill material)
of more than 50 cu.m. shall be covered with tarpaulin or similar fabric during rainstorms.
Measures should be taken to prevent the washing away of construction materials,
soil, silt or debris into any drainage system;
(f) manholes,
including newly constructed ones, shall always be covered and sealed so as to
prevent silt, construction materials or debris being washed into the drainage
system and storm runoff being directed into foul sewers during the construction
period. At any time of year when rainstorms are imminent or forecast, actions
shall be taken in accordance with the ProPECC Practice Note 1/94 issued by the
Director of Environmental Protection. Particular attention should be paid to
the control of silty surface runoff during storm events, especially for areas
located near steep slopes;
(g) oil
interceptors shall be provided in drainage systems and oils and grease shall be
regularly removed to prevent the release of oils and grease into storm water
drainage systems after accidental spillage during the construction period. The
interceptors should have a bypass to prevent flushing during periods of heavy
rain;
(h) all
vehicles and plant shall be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads during
the construction period. An adequately designed and located wheel washing bay
should be provided at every site exit and wash-water should have sand and silt
settled out and removed at least on a weekly basis to ensure the continued
efficiency of the process. The section of access road leading to, and exiting from,
the wheel-wash bay to the public road should be paved with sufficient backfill
toward the wheel-wash bay to prevent vehicle tracking of soil and silty water
to public roads and drains;
(i) sediment
shall be intercepted before it enters into modified sections of culverts.
Sediment traps should be installed both upstream and downstream of any modified
culvert sections in order to minimise the sediment loading in these culverts.
Vortex tube site traps shall also be installed to provide continuous extraction
of sediment within the modified sections of the culverts;
(j) temporary
and permanent drainage pipes and culverts shall be provided to facilitate
runoff discharge during the construction period. The temporary and permanent
drainage pipes and culverts should be adequately designed for the controlled
release of storm flows. All sediment control measures should be regularly
inspected and maintained to ensure proper and efficient operation at all times
and particularly following rain storms. Temporarily diverted drainage should be
reinstated to its original condition when construction work has finished or the
temporary diversion is no longer required; and
(k) discharge
and surface runoff contaminated by materials from any concrete batching plant
shall be diverted to neutralisation tank to reduce acidity and the treated
discharge should be connected to silt trap to remove suspended solids before
disposing to sewage system.
Measures
to Mitigate the Water Quality Impacts During Tunneling and Station Construction
To
mitigate the water quality impacts during tunneling and station construction:
(a) cut-and-cover
tunnel work shall be conducted segment by segment to limit the amount of
construction runoff generated in the areas during the wet season (April to
September). Temporary open storage of excavated materials used for backfill on
site should be covered with tarpaulin or similar fabric during rainstorms. Any
washout of construction or excavated materials should be diverted through
appropriate sediment traps before discharge to stormwater drainage system.
Ground water pumped out of tunnels should be discharged into the drainage
channels which incorporate sediment traps to enhance deposition rates and to
remove silt; and
(b) spent
bentonite slurries or other grouts used in diaphragm wall construction and in a
separate slurry collection system shall be collected, and reconditioned and
reused wherever practicable.
Measures
to Mitigate Water Quality Impact During Reclamation Work and Other Construction
Activities
To
mitigate the water quality impact during reclamation work and other
construction activities :
(a) any
mechanical grabs shall be designed and maintained to avoid spillage and sealed
tightly while being lifted during the construction period. For dredging of
contaminated mud, closed watertight gabs shall be used;
(b) silt
curtains shall be deployed around dredging areas without jeopardizing the
navigation of ships and ferries along the navigation channels during the
dredging and filling operation;
(c) all
vessels shall be sized so that undue turbidity is not generated by turbulence
from vessel movement or propeller wash during the construction period;
(d) no
foam, oil, grease, sum, litter or other objectionable matter shall be caused to
be present on the water within the site or dumping grounds during the
construction period;
(e) loading
of barges and hoppers shall be controlled to prevent splashing of dredged
material into the surrounding water. Barges or hoppers shall not be filled to a
level which will cause the overflow of materials or polluted water during
loading or transportation;
(f) debris
and rubbish on site shall be collected, handled and disposed of properly to
avoid entering the water column to cause water quality impacts;
(g) to
prevent spilled fuel oils from reaching coastal water, all fuel tanks and
storage areas shall be provided with locks and located on sealed areas, and
within bunds of a capacity equal to 110% of the storage capacity of the largest
tank; and
(h) construction
work force sewage discharges on site shall be connected to existing sewer or
sewage treatment facilities. Portable chemical toilets shall be provided to
construction workers.
Measures
to Mitigate the Landfill Gas Hazard During the Operation of the Project
During
non-operational hours and particularly at the time when the first train travels
through the tunnel each day, there is potential for accumulated gas to be
ignited by an electrical spark caused by the train. To reduce the likelihood of
this occurrence, the measures outlines below shall be adopted:
(a) Ventilation
of the tunnels should be switched on half an hour before the first train is
expected to ensure any accumulated gas is expelled or dispersed within the
tunnels;
(b) Installation
of a permanent gas detection system (with power backup) in the tunnels which is
linked both to the emergency ventilation to be provided in the event of normal
train service disruptions and visual alarms in the nearby station controller
rooms;
(c) It
is understood that a safety check of each line is undertaken every morning
before the trains are permitted to enter any section of track. It is
recommended that the staff who undertake this check are trained in the use of
portable gas detection equipment and that measurement of methane and carbon
dioxide concentrations within the tunnels is added to the daily checking
procedure for this section of the line;
(d) All
maintenance personnel and station staff working within the tunnels should be
educated in the dangers of landfill gas and the signs and symptoms of asphyxia;
(e)
Smoking within the tunnels should
be prohibited at all times;
(f) An
assumed presence of landfill gas should be adopted at all times by maintenance
workers and a strictly regulated "work permit procedure" involving
training, ventilation, gas monitoring (as detailed in the Construction
recommendations section), safety tracking and communication with maintenance
staff, enforcement of the no smoking order and use of only intrinsically safe
equipment and electrical leads;
(g) A
gas detection system (with power backup) should be installed within the
telecommunications and equipment rooms and ventilation requirements designed to
achieve a high rate of air changes per hour during all operational hours. The
failure of the ventilation equipment should be supported by audible alarms and
a power backup system;
(h) Adequate
power and utility supplies for the equipment within the telecommunications
equipment rooms should be provided from either end of the tunnel in preference
to direct connection or routing underground from anywhere between the landfill
and the development;
(i) Monitoring
for methane, carbon dioxide and oxygen as recommended above should be conducted
using equipment with the following indication ranges and the actions prescribed
below taken in instances of exceedances of the criteria given in Table 1 of
Annex A.
(i)
Methane 0-100%LEL
and 0-100%v/v
(ii)
Carbon
dioxide 0-20%
(iii)
Oxygen
0-21
Measures
to Mitigate the Water Quality Impact During the Operation of the Project
To
mitigate the water quality impact during the operation of the Project :
(a) A
surface water drainage system shall be provided to collect operational tunnel
seepage during the operation of the Project. Where oils and lubricating fluids
could be spilt, the operational tunnel discharge and track runoff should pass
through oil and grit/silt interceptors/chambers to remove oil, grease and
sediment before being pumped to the public storm water drainage system via a
rising main. However, washing water from regular tunnel washing shall be
directed to foul sewers after pre-treatment;
(b) All
silt traps and oil interceptors shall be regularly cleaned and maintained
during the operation of the Project;
(c) Contents
of the oil interceptors shall be collected for reuse, or transferred to an
appropriate disposal facility; and
(d) Sanitary
fitments and drainage works shall be provided taking into account the Practice
Note for Professional Persons, No. 5/93 (ProPECC PN 5/93) - Drainage Plans
subject to Comment by the Environmental Protection Department.
Figure 1 | Figure 2 | Figure 3 | Figure 4