Environmental Permit No. EP-141/2002/A
環境許可證編號 EP-141/2002/A
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER
499)
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A
DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section
10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director
of Environmental Protection (the Director) grants this environmental permit
to the Major Works Project Management Office, Highways Department (hereinafter
referred to as the “Permit Holder”) to construct and operate the designated
project described in Part B subject to the conditions
specified in Part C. The issue of this environmental
permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予路政署主要工程管理處(下稱“許可證持有人”)以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據﹕-
Application
No. 申請書編號 |
VEP-188/2005 |
|
|||||||||||
Document
in the Register : 登記冊上的文件: |
(1) Widening of
Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange –
Preliminary Design and Ground Investigation Assignment (Register No.:
AEIAR-059/2002) -
Final Environmental Impact Assessment Report
(December 2001) [Hereinafter referred to as the “EIA Report”] -
Final EIA Executive Summary (December 2001)
[Hereinafter referred to as the “Executive Summary”] -
Environmental Monitoring and Audit Manual (December
2001) [Hereinafter referred to as the “EM&A Manual”] (1) 元朗公路藍地至十八鄉段擴闊工程 – 初步設計及土地勘測 (登記冊編號: AEIAR-059/2002) -
環境影響評估報告 (2001年12月) [下稱「環評報告」] -
環境影響評估行政摘要 (2001年12月) [下稱「行政摘要」] -
環境監察及審核計劃 (2001年12月) [下稱「環監計劃」] (2) The
Director’s letter of approval of the EIA report dated 22 May 2002 (Reference:
(26) in Ax(1) to EP2/N6/A/62 IV) (2) 署長於 (3) Application
documents including all attachments submitted by the Permit Holder on 29 May
2002 (Application No. AEP-141/2002) (3) 申請文件包括許可證持有人於 (4) Application
for Variation of an Environmental Permit No. VEP-188/2005 and attached
documents submitted by the Permit Holder on 25 July 2005 (4) 許可證持有人於 |
|
|||||||||||
|
|
|
|||||||||||
|
|||||||||||||
22 August 2005 |
|
|
|||||||||||
Date 日期 |
|
(Mr H.M. WONG) Principal Environmental Protection Officer (Strategic Assessment) for Director of Environmental Protection 環境保護署署長 首席環境保護主任(策略評估)黃漢明代行 |
|||||||||||
PART B (DESCRIPTIONS
OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project
mentioned in Part A of this environmental permit (hereinafter
referred to as the “Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Projects 指定工程項目的名稱 |
Widening of Yuen Long
Highway between Tan Kwai Tsuen and Shap Pat Heung Interchange [The above designated project is hereinafter referred to as “the
Project”] 元朗公路丹桂村至十八鄉段擴闊工程 [這工程項目下稱"工程項目"] |
Nature
of Designated Projects |
Major improvements to existing roads. 現有道路之重大改善工程。 |
Location of Designated
Projects 指定工程項目的地點 |
The section of Yuen Long Highway between Tan Kwai Tsuen and Shap Pat
Heung Interchange. The location of the Project is shown in Figure
|
Scale and Scope of Designated Project(s) 指定工程項目的規模和範圍 |
(a)
Widening of the section of Yuen Long Highway between Tan Kwai Tsuen and Shap Pat Heung Interchange from dual
2-lane to dual 3-lane, together with a (a) 把介乎丹桂村及十八鄉交匯處之間的一段元朗公路由雙程雙線分隔車路擴闊至雙程三線分隔車路,包括每邊行車路上 (b)
Modification of the existing interchanges along Yuen Long Highway to suit the
above widening; (b) 修改元朗公路現有的交匯處以配合上述的擴闊工程; (c)
Modification and widening of existing highway structures, i.e. culverts,
bridges, underpasses, pedestrian subways, etc. to suit the widening; (c) 修改及擴闊現有的公路設施,即暗渠、橋樑、下通路、行人隧道等,以配合上述的擴闊工程; (d)
Realignment of the various slip roads connecting Yuen Long Highway to suit
the above widening; (d) 把各條接駁元朗公路的連接路重新定線,以配合上述的擴闊工程; (e)
Provisioning/re-provisioning of associated civil, geotechnical, landscaping,
drainage and water mains diversion works, public lighting such as
conventional street lighting, underpass / tunnel lighting, high mast lighting
and pedestrian subway lighting, traffic aids (including overhead sign
gantries), central divider / parapets, noise barriers and traffic control and
surveillance system (TCSS), police observation platforms along the widened
carriageway and interchanges, fire hydrants and fire supply mains; and (e) 提供/重設相關的土木、土力、景觀美化、渠務及水管改道工程、公共照明例如普通街燈、下通路/行車隧道照明、高桅燈及行人隧道照明、交通輔助設施(包括架空高架道路標誌)、道路中央分隔欄/防撞欄、隔音屏障和交通管制及監察系統 (TCSS)、沿著已擴闊的行車道及交匯處的警察瞭望平台、消防栓和消防供水管; 及 (f) Rehabilitation of the existing highway pavement
to extend its service life to that of the new pavement. (f) 修復現行的公路路面使其使用期限延長至與新路面同一水平。 |
1. General
Conditions
1.1 The
Permit Holder shall ensure full compliance with all conditions of this
environmental permit. Any
non-compliance may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap. 499) and may become the subject of appropriate
action being taken under the Ordinance.
1.2
The Permit Holder
shall ensure full compliance with all legislation from time to time in force
including but without limitation to the Noise Control Ordinance (Cap. 400),
Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance
(Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance
(Cap. 354). This Permit does not
of itself constitute any ground of defence against any proceedings instituted
under any legislation.
1.3
The Permit Holder
shall make copies of this Permit together with all documents referred to in
this Permit or the documents referred to in Part A of
the Permit readily available at all times for inspection by the Director or
his authorised officers at all sites/offices covered by this Permit. Any reference to the Permit shall include
all documents referred to in the Permit and also the relevant documents in
the Register.
1.4
The Permit
Holder shall give a copy of this Permit to the person(s) in charge of the
site(s) and ensure that such person(s) fully understands all conditions and all
requirements incorporated by the Permit. The site(s) refers to site(s) of
construction and operation of the Project and shall mean the same hereafter.
1.5
The Permit
Holder shall display conspicuously a copy of this Permit on the construction
site(s) at all vehicular site entrances/exits or at a convenient location for
public’s information at all times.
The Permit Holder shall ensure that the most updated information about
the Permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or
the whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site(s).
1.6
The Permit Holder
shall construct and operate the Project in accordance with the project descriptions
in Part B of this Permit.
1.7
The Permit
Holder shall ensure that the Project is designed, constructed and operated in
accordance with the information and all recommendations described in the EIA
Report (Register No.:
AEIAR-059/2002), other relevant documents in the
Register; and the information or mitigation measures described in this Permit,
and mitigation measures to be recommended in submissions that shall be
deposited with or approved by the Director as a result of permit conditions
contained in this Permit, and mitigation measures to be recommended under on
going surveillance and monitoring activities during all stages of the Project.
Where recommendations referred to in the documents of the Register are not
expressly referred to in this Permit, such recommendations are nevertheless to
be implemented unless expressly excluded or impliedly amended in this Permit.
1.8
All deposited
submissions, as required under this Permit, shall be rectified and resubmitted
in accordance with the comments, if any, made by the Director within one month
of the receipt of the Director’s comments or otherwise as specified by the
Director.
1.9
All submissions
approved by the Director, all submissions deposited without comments by the
Director, and all submissions rectified in accordance with comments by the
Director under this Permit shall be construed as part of the permit conditions
described in Part C of this Permit. Any variation of
the submissions shall be approved by the Director in writing or as prescribed
in the relevant permit conditions. Any non-compliance with the submissions
may constitute a contravention of the Environmental Impact Assessment Ordinance.
All submissions or any variation of the submissions shall be certified by
the Environmental Team (ET) Leader and verified by the Independent Environmental
Checker (IEC) referred to in Conditions 2.1 and 2.2
below, before submitting to the Director under this Permit.
1.10
The Permit
Holder shall release all finalised submissions as required under this Permit,
to the public by depositing copies in the Environmental Impact Assessment
Ordinance Register Office, or in any other places, or any internet websites as
specified by the Director, or by any means as specified by the Director, for
public inspection. For this purpose, the Permit Holder shall provide sufficient
copies of the submissions.
1.11
The Permit
Holder shall notify the Director in writing the commencement date of construction
of the Project no later than one month prior to the commencement of construction
of the Project. The Permit Holder shall notify the Director in writing
immediately if there is any change of the commencement date of the
construction.
1.12
All submissions to the
Director required under this Permit shall be delivered either in person or by
registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalised
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hardcopies.
1.13
For the purpose of this
Permit, “commencement of construction” does not include works related to site
clearance and preparation, or other works as agreed by the Director.
2.
Measures and Submissions for Commencement of the
Project
2.1
An ET shall be
established by the Permit Holder no later than one month before the
commencement of construction of the Project. The ET shall be headed by an ET
Leader. The ET Leader shall be a person who has at least 7 years' experience in
environmental monitoring and auditing (EM&A) or environmental management.
The ET and the ET Leader shall be responsible for the implementation of the
EM&A programme in accordance with the requirements as contained in the
EM&A Manual. The ET Leader shall keep a contemporaneous log-book of each
and every circumstance or change of circumstances which may affect the
environmental impact assessment and each and every non-compliance with the
recommendations of the EIA Report or this Permit. This log-book shall be kept
readily available for inspection by all persons assisting in supervision of the
implementation of the recommendations of the EIA Report and this Permit or by
the Director or his authorized officers. Failure to maintain records in the
log-book, failure to discharge the duties of the ET Leader as defined in the
EM&A Manual or failure to comply with this Condition would entitle the
Director to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit Holder to make replacement, or further failure to
keep contemporaneous records in the log-book despite the employment of a new ET
Leader may render the Permit liable to suspension, cancellation or variation.
The ET shall not be in any way an associated body of the Contractor or the IEC
for the Project.
2.2
An IEC shall be employed by
the Permit Holder no later than one month before the commencement of
construction of the Project. The IEC shall be a person who has at least 7
years' experience in EM&A or environmental management. The IEC shall be
responsible for duties defined in the EM&A Manual and shall audit the
overall EM&A programme, including the implementation of all environmental
mitigation measures, submissions required in the EM&A Manual, and any other
submissions required under this Permit. In addition, the IEC shall be
responsible for verifying the environmental acceptability of permanent and
temporary works, relevant design plans and submissions under this Permit. The
IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit. The
IEC shall notify the Director by fax, within 24 hours of each and every change
of circumstances or non-compliance with the recommendations of the EIA Report
or this Permit, which might affect the monitoring or control of adverse
environmental impacts from the Project. In case the IEC fails to so notify the
Director of the same, fails to discharge the duties of the IEC as defined in
the EM&A Manual or fails to comply with this Condition, the Director may
require the Permit Holder by notice in writing to replace the IEC. Failure to
replace the IEC as directed or further failure to so notify the Director
despite employment of a new IEC may render the Permit liable to suspension,
cancellation or variation. Notification by the Permit Holder is the same as
notification by the IEC for the purpose of this Condition. The IEC shall not be
in any way an associated body of the Contractor or the ET for the Project.
2.3
The Permit
Holder shall, within one month before the commencement of construction of the
Project, deposit with the Director 3 sets of construction noise mitigation
proposal to mitigate the construction noise impact arising from the Project.
The proposal shall indicate the exact locations and details of the temporary
noise barriers and the arrangement of the number and type of equipment,
procedure and sequence of construction. The submission shall be certified by
the ET leader and verified by the IEC as conforming to the information and
recommendations contained in the EIA Report.
2.4
The Permit Holder shall, within one month after the commencement of
construction of the Project, submit to the Director 3 sets of Waste Management
Plan (WMP) for approval. The WMP shall take into account the relevant findings
and recommendations in the waste management section of the EIA Report. Before
submission to the Director, the WMP shall be certified by the ET Leader and
verified by the IEC as conforming to the information and recommendations
contained in the EIA Report.
2.5
The
Permit Holder shall, within one month after the commencement of construction of
the Project, inform the Director in writing the management organization of the
main construction companies and/or any form of joint ventures associated with
the construction of the Project.
The submitted information shall include at least an organization chart,
names of responsible persons and their contact details.
2.6
The
Permit Holder shall, within one month after the commencement of construction of
the Project, deposit with the Director 3 sets of landscape proposal to mitigate
the potential landscape and visual impacts arising from the construction and
operation of the Project. The landscape
proposal shall include an explanatory statement, design drawings and layout
plans at a scale 1 to 1000 or other scale as agreed by the Director. The
submission shall include an implementation programme with clear identification
of the responsibility for funding, implementation, management and maintenance
of the landscape and visual mitigation measures as recommended in the EIA
Report. The submission shall be certified by the ET leader and verified by the
IEC as conforming to the information and recommendations contained in the EIA
Report. The Permit Holder shall make available additional copies to the
Director upon his request.
2.7
The construction work of the
Project at the section from
3.
Measures for Construction and Operation of the Project
3.1
To mitigate the construction noise impact arising from the Project, all
measures recommended in the construction noise mitigation proposal deposited
under Condition 2.3 shall be fully implemented.
3.2
The Permit Holder shall fully implement all
the measures recommended in accordance with the requirements and time schedule(s)
set out in the approved WMP. Before obtaining
the Director’s approval on the WMP as required under Condition 2.4, no disposal
of waste, spoil, soil, excavation materials or materials obtained from the Project site
shall be allowed at any locations.
3.3
To mitigate the traffic noise
impact arising from the operation of the Project, noise barriers shall be
implemented in accordance with Tables 1 and 2 and Figures
2, 3 & 4. Noise barriers as shown in Table 1 and Figure
2 shall be fully implemented before the operation of the Project. Noise
barriers as shown in Table 2 and Figures 3 & 4 for
planned developments shall be fully implemented before the population intake
at relevant planned developments. The noise barriers shall be continuous structures with no gap or opening
except where access road is required. The Permit Holder shall properly maintain
the noise barriers during the operation of the Project.
3.4
All measures recommended in
the landscape proposal deposited under Condition 2.6 of this Permit shall be
fully implemented and maintained.
3.5
To carry out the
construction work in accordance with the programme deposited under Condition
2.7.
4.
Environmental Monitoring and Audit Requirements during
Construction of the Project
4.1
The EM&A programme shall
be implemented as set out in the EM&A Manual. Any changes to the programme
shall be justified by the ET leader and verified by the IEC as conforming to
the information and requirements contained in the EM&A Manual before
submission to the Director for approval.
4.2
The Permit Holder shall take
samples and measurements in accordance with the requirements of the EM&A
Manual by:
(a)
conducting baseline
environmental monitoring on noise, water and air quality; and
(b)
conducting impact monitoring
on noise, water and air quality.
4.3
The remedial actions described
in the Event/Action Plans of the EM&A Manual shall be fully and properly
carried out in accordance with the time frames set out in the Event/Action
Plans, or as agreed by the Director.
4.4
Records of measurements and
actions taken under Conditions 4.2 and 4.3 respectively of this Permit shall be
logged and kept, within 3 working days of the collection of data or completion
of action, for the purpose of preparing and submitting the EM&A reports and
making the information available for inspection on site.
4.5
Two hard copies and one
electronic copy of the Baseline Monitoring Report shall be submitted to the
Director at least 2 weeks before commencement of construction of the Project.
The submission shall be verified by the IEC. Additional copies of the submission
shall be made available to the Director upon his request.
4.6
Two hard copies and one electronic
copy of monthly EM&A Report shall be submitted to the Director within 2
weeks after the end of the reporting month. The EM&A Reports shall include
a summary of all noncompliance (exceedances) of the environmental quality
performance limits (Action and Limit Levels). The submissions shall be verified
by the IEC. Additional copies of the submission shall be provided to the
Director upon request by the Director.
4.7
All environmental monitoring
and audit data submitted under this Permit shall be true, valid and correct.
5.
Environmental Monitoring and Audit Requirements during Operation of the
Project
5.1
The Permit Holder shall, at
least 6 months before the operation of the Project, deposit with the Director a
monitoring plan for the purpose of verification of traffic noise assessment, by
comparing the project noise impact predictions with the actual impacts. The
monitoring plan shall contain monitoring locations, monitoring schedules,
methodology of noise monitoring including noise measurement procedures, traffic
counts and speed checks, and methodology of comparison with the predicted
levels. Monitoring shall be conducted in accordance with the deposited
monitoring plan unless with prior justification. Monitoring details and
results, including the comparison between the measured noise levels and the
predicted levels, shall be recorded in a report. The report shall be certified
by the Permit Holder before it is deposited with the Director, within one month
after the completion of the monitoring.
5.2
The Permit Holder shall
deposit with the Director 3 copies of an audit report, certified by the ET
Leader and verified by the IEC, demonstrating the satisfactory completion of
the measures recommended in the landscape proposal as described in Conditions
2.6 and 3.4 of this Permit. The audit report shall be deposited within 3 weeks
after completion of the mitigation measures.
5.3
The Permit Holder shall
deposit with the Director 3 copies of audit report, certified by the ET leader
and verified by the IEC, demonstrating the satisfactory completion of the noise
measures described in Condition 3.3 of this Permit. The audit report shall be
deposited within 3 weeks after completion of the mitigation measures.
6.
Electronic Reporting of EM&A Information
6.1
To facilitate public inspection of the Baseline
Monitoring Report and monthly EM&A Reports via the EIAO Internet Website
and at the EIAO Register Office, electronic copies of these Reports shall be
prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in
Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by
the Director and shall be submitted at the same time as the hardcopies as
described in Conditions 4 and 5 of this Permit. For the HTML version, a content
page capable of providing hyperlink to each section and sub-section of these
Reports shall be included in the beginning of the document. Hyperlinks to all
figures, drawings and tables in these Reports shall be provided in the main
text from where the respective references are made. All graphics in these
Reports shall be in interlaced GIF format unless otherwise agreed by the
Director. The content of the electronic copies of these Reports must be the
same as the hardcopies.
6.2
The
Permit Holder shall, set up a dedicated web site and notify the Director in
writing the Internet address where the environmental monitoring and project
data is to be placed, within six weeks after the commencement of construction
of the Project. All environmental monitoring data described in Condition 6.1
above shall be made available to the public via a dedicated web site to be set
up by the Permit Holder in the shortest possible time and in no event later
than 2 weeks after the relevant environmental monitoring data are collected or
become available, unless otherwise agreed with the Director.
6.3
The Internet website as described in Condition 6.2
above shall enable user-friendly public access to the monitoring and project
data including the EIA report and the environmental permit(s) and the project
profile of the Project. The Internet website shall have features capable of:
(a)
providing access to all environmental monitoring
data collected since the commencement of works;
(b)
searching by date;
(c)
searching by types of monitoring data (noise, water
and air quality); and
(d)
hyperlinks to relevant monitoring data after
searching;
or otherwise as agreed by the Director.
Notes :
1.
This Permit consists of three parts, namely, PART
A (Main Permit), PART B (Description of Designated
Project) and PART C (Permit Conditions). Any person relying
on this Permit should obtain independent legal advice on the legal implications
under the Ordinance, and the following notes are for general information only.
2. The
Permit Holder may apply under Section 13 of the Ordinance to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the construction site by the amended permit.
3. A
person who assumes the responsibility for the whole or a part of the designated
project may, before he assumes responsibility of the designated project, apply
under Section 12 of the Ordinance to the Director for a further environmental
permit.
4. Under
Section 14 of the Ordinance, the Director may with the consent of the Secretary
for the Environment and Food, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site.
5. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the Ordinance
before the construction or operation of the Project could be continued. It is
an offence under Section 26(1) of the Ordinance to construct or operate a
designated project listed in Part I of Schedule 2 of the Ordinance without a
valid environmental permit.
6. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the Ordinance, is liable: -
(i)
on a first
conviction on indictment to a fine of $2 million and to imprisonment for
6 months;
(ii)
on a second or
subsequent conviction on indictment to a fine of $5 million and to imprisonment
for 2 years;
(iii)
on a first
summary conviction to a fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or
subsequent summary conviction to a fine of $1 million and to imprisonment for 1
year; and
(v)
in any case
where the offence is of a continuing nature, the court or magistrate may impose
a fine of $10,000 for each day on which he is satisfied the offence continued.
7. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the Ordinance within 30 days of receipt of this Permit.
Environmental Permit No. EP-141/2002/A
Table
1 – Schedule of noise barriers to be provided before the operation of the
Project
(to
be read in conjunction with Figure 2
attached to this Permit)
Height of barrier (m) |
Location |
Description |
From
Chainage |
To Chainage |
Length of
barrier (m) |
|
|
Yuen Long
Highway |
West bound |
7000 |
7974 |
974 |
|
Yuen Long
Highway |
East bound |
3550 |
3700 |
150 |
||
|
Yuen Long
Highway |
East bound |
5746 |
5881 |
135 |
|
Yuen Long
Highway |
East bound |
6134 |
6506 |
372 |
||
|
Slip road
joining Long |
-- |
-- |
-- |
339 |
|
|
Yuen Long
Highway |
West bound |
6768 |
7000 |
232 |
|
|
Yuen Long
Highway |
East bound |
3700 |
3775 |
75 |
|
|
Slip road
slip off YLH (East bound) from chainage 4336 at Tin Shui Wai West Interchange
merging |
-- |
-- |
-- |
144 |
|
|
Yuen Long Highway |
East bound |
4700 |
4843 |
143 |
|
Yuen Long Highway |
East bound |
6506 |
7940 |
1432 |
||
|
Slip road joining Long |
-- |
-- |
-- |
302 |
|
|
Slip road joining Long |
-- |
-- |
-- |
115 |
|
|
Slip road slip off YLH (West bound) from chainage
4857 at Tin Shui Wai West Interchange merging |
-- |
-- |
-- |
228 |
|
|
Yuen Long Highway |
West bound |
5160 |
5279 |
119 |
|
|
Slip road slip off YLH (West bound) from chainage
6296 at Tong Yan San Tsuen Interchange merging Long Tin Road |
West bound |
-- |
-- |
443 |
|
Yuen Long Highway |
East bound |
4152 |
4336 |
184 |
Yuen Long Highway |
West bound |
4857 |
5014 |
157 |
|
|
Yuen Long Highway |
East bound |
3388 |
3550 |
162 |
Yuen Long Highway |
West bound |
4160 |
4343 |
183 |
|
Yuen Long Highway |
West bound |
5014 |
5160 |
146 |
|
|
Yuen Long Highway |
East bound |
3775 |
4152 |
377 |
Yuen Long Highway |
East bound |
4843 |
5023 |
180 |
|
Yuen Long Highway |
East bound |
5279 |
5742 |
468 |
|
Yuen Long Highway |
East bound |
6025 |
6134 |
109 |
|
Yuen Long Highway |
West bound |
4343 |
4440 |
97 |
|
|
Yuen Long Highway |
East bound |
5023 |
5279 |
256 |
Yuen Long Highway |
West bound |
3388 |
3446 |
58 |
Table
2 – Schedule of noise barriers to be provided before the population intake at
relevant planned developments
(to be read in conjunction with Figures 3 and 4 attached to this Permit)
Part I:
For existing NSRs and planned developments other than those in Hung Shui Kiu
New Development Area |
||||||
Height of barrier (m) |
Location |
Description |
From
Chainage |
To
Chainage |
Length of
barrier (m) |
|
|
Yuen Long Highway |
East bound |
3550 |
3700 |
150 |
|
Yuen Long Highway |
West bound |
7000 |
7974 |
974 |
||
|
Yuen Long Highway |
East bound |
3700 |
3775 |
75 |
|
|
Slip road slip off YLH (East bound) from chainage
4336 at Tin Shui Wai West Interchange merging |
-- |
-- |
-- |
144 |
|
|
Yuen Long Highway |
West bound |
6768 |
7000 |
232 |
|
|
Yuen Long Highway |
East bound |
4700 |
4843 |
143 |
|
Yuen Long Highway |
East bound |
7448 |
7940 |
480 |
||
Slip road slip off YLH (West bound) from chainage
6296 at Tong Yan San Tsuen Interchange merging Long Tin Road |
West bound |
-- |
-- |
443 |
||
Slip road slip off YLH (East bound) from chainage
5746 at Tong Yan San Tsuen Interchange merging Long Tin Road |
-- |
-- |
-- |
142 |
||
Slip road slip off YLH (West bound) at Tin Shui
Wai West Interchange merging |
-- |
-- |
-- |
59 |
||
Slip road joining Long |
-- |
-- |
-- |
79 |
|
Yuen Long Highway |
East bound |
4152 |
4336 |
184 |
Yuen Long Highway |
West bound |
4857 |
5014 |
157 |
|
Slip road joining Long |
-- |
-- |
-- |
182 |
|
Slip road joining Long |
-- |
-- |
-- |
115 |
|
Yuen Long Highway |
East bound |
6134 |
6247 |
113 |
|
|
Yuen Long Highway |
West bound |
4160 |
4343 |
183 |
Yuen Long Highway |
East bound |
3388 |
3550 |
162 |
|
Yuen Long Highway |
West bound |
5014 |
5160 |
146 |
|
Yuen Long Highway |
East bound |
5746 |
5881 |
135 |
|
Yuen Long Highway |
East bound |
5905 |
6134 |
229 |
|
|
Yuen Long Highway |
East bound |
3775 |
4152 |
377 |
Yuen Long Highway |
West bound |
4343 |
4440 |
97 |
|
Yuen Long Highway |
East bound |
4843 |
5023 |
180 |
|
Yuen Long Highway |
East bound |
5279 |
5742 |
468 |
|
Yuen Long Highway |
East bound |
6300 |
6506 |
206 |
|
Yuen Long Highway |
East bound |
6774 |
7448 |
684 |
|
Slip road slip off YLH (West bound) from chainage
4857 at Tin Shui Wai West Interchange merging |
-- |
-- |
-- |
169 |
|
|
Yuen Long Highway |
West bound |
3388 |
3446 |
58 |
|
Yuen Long Highway |
East bound |
5023 |
5279 |
256 |
|
Yuen Long Highway |
East bound |
6247 |
6300 |
53 |
|
Yuen Long Highway |
East bound |
6506 |
6774 |
268 |
|
Slip road joining Long |
-- |
-- |
-- |
458 |
Table
2 – Schedule of noise barriers to be provided before the population intake at
relevant planned developments
(continued)
(to be read in conjunction with Figures 3 and 4 attached to this Permit)
Part II:
For existing NSRs and planned developments including those in Hung Shui Kiu
New Development Area |
||||||
Height of barrier (m) |
Location |
Description |
From
Chainage |
To
Chainage |
Length of
barrier (m) |
|
|
Yuen Long Highway |
West bound |
7000 |
7974 |
974 |
|
|
Slip road slip off YLH (East bound) from chainage
4336 at Tin Shui Wai West Interchange merging |
-- |
-- |
-- |
144 |
|
Yuen Long Highway |
West bound |
6768 |
7000 |
232 |
||
|
Yuen Long Highway |
East bound |
4700 |
4843 |
143 |
|
Slip road joining Long |
-- |
-- |
-- |
79 |
||
Slip road slip off YLH (West bound) from chainage
6296 at Tong Yan San Tsuen Interchange merging Long Tin Road |
West bound |
-- |
-- |
443 |
||
|
-- |
-- |
-- |
63 |
||
Slip road slip off YLH (East bound) from chainage
5746 at Tong Yan San Tsuen Interchange merging Long Tin Road |
-- |
-- |
-- |
142 |
||
Yuen Long Highway |
East bound |
7448 |
7940 |
480 |
||
Slip road slip off YLH (West bound) at Tin Shui
Wai West Interchange merging |
-- |
-- |
-- |
59 |
|
Yuen Long Highway |
East bound |
4152 |
4336 |
184 |
Yuen Long Highway |
West bound |
4857 |
5014 |
157 |
|
Yuen Long Highway |
East bound |
4400 |
4562 |
172 |
|
Slip road joining Long Tin Road and YLH (East
bound) chainage 5905 at Tong Y an San Tsuen Interchange |
-- |
-- |
-- |
182 |
|
Slip road joining Long |
-- |
-- |
-- |
115 |
|
Yuen Long Highway |
East bound |
6134 |
6247 |
113 |
|
|
Yuen Long Highway |
West bound |
4160 |
4343 |
183 |
Yuen Long Highway |
West bound |
5014 |
5160 |
146 |
|
Yuen Long Highway |
East bound |
3388 |
3550 |
162 |
|
|
-- |
-- |
-- |
59 |
|
Yuen Long Highway |
East bound |
5746 |
5881 |
135 |
|
Yuen Long Highway |
East bound |
5905 |
6134 |
229 |
|
|
Yuen Long Highway |
East bound |
4843 |
5023 |
180 |
Yuen Long Highway |
East bound |
5279 |
5742 |
468 |
|
Yuen Long Highway |
West bound |
4343 |
4440 |
97 |
|
|
Yuen Long Highway |
East bound |
3550 |
4152 |
602 |
|
Slip road slip off YLH (East bound) at Tin Shui
Wai West Interchange merging |
-- |
-- |
-- |
50 |
|
Yuen Long Highway |
East bound |
6300 |
6506 |
206 |
|
Yuen Long Highway |
East bound |
6774 |
7448 |
684 |
|
Slip road slip off YLH (West bound) from chainage
4857 at Tin Shui Wai West Interchange merging |
-- |
-- |
-- |
169 |
|
Yuen Long Highway |
East bound |
5023 |
5279 |
256 |
Yuen Long Highway |
West bound |
3388 |
3446 |
58 |
|
|
|
Central divider |
-- |
-- |
76 |
|
Yuen Long Highway |
East bound |
6247 |
6300 |
53 |
|
Yuen Long Highway |
East bound |
6506 |
6774 |
268 |
|
Slip road joining Long |
-- |
-- |
-- |
458 |
|
Yuen Long Highway * |
Central Divider |
3125 |
3263 |
138 |
* The barrier will be implemented
by Deep Bay Link Project (Environmental Permit No. EP-163/2003/D)
[ Back to First Page ] / [ Back to Main Index ]