Environmental Permit No. EP-077/2000/B
環境許可證編號 EP-077/2000/B
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
Section 10 & Section 13
環
境
影
響
評
估
條
例
(第
499章
)
第
10 及
13 條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A
DESIGNATED PROJECT
建
造
及
營
辦
指
定
工
程
項
目
的
環
境
許
可
證
PART
A (MAIN PERMIT)
A部
(許
可
證
主
要
部
分
)
Pursuant to Section 10
of the Environmental Impact Assessment Ordinance (the Ordinance), the Director
of Environmental Protection (the Director) granted the Environmental Permit
(No. EP-077/2000) to the Highways Department (hereinafter referred to as the
"Permit Holder") on 28.8.00. Pursuant to Section 13 of the Ordinance,
the Director amends the Environmental Permit No. EP-077/2000/A based on the
Application No. VEP-189/2005. The amendments described below, are incorporated
into this Environmental Permit (EP-077/2000/B). This Environmental Permit
as amended is for the construction and operation of the designated projects
described in Part B of this Permit subject to the conditions
described in and attached to Part C of this Permit.
根
據
環
境影
響
評
估
條例(條例)
第
10條的
規
定
,
環
境保
護
署
署
長
(署
長)
於2000 年 8月 28日 將
環
境許
可
證(編 號 EP-077/2000) 批
予
路
政
署
(下
稱
"許
可
證持
有
人")
。
根
據
條例第13條的
規
定
,
署
長因 應 更改環 境許 可 證的 申請 編 號VEP-189/2005 修訂
環
境許
可
證編
號
EP-077/2000/A 。
以 下 修訂 已 包 含 在 本環 境許 可 證內 (EP-077/2000/B) 。 本經
修訂
的
環
境許
可
證作 為 建造
及 營辦
B 部所說明
的
指
定
工
程
項目,
但
須遵
守
本許
可
證
C 部所說明
或
附
載
的
條件。
This
Environmental Permit is based on the documents, approvals and permissions
described below:
本環境許可證乃依據下列文件、批准及許可條件而簽發 –
Application No. 申請書編號: |
VEP-189/2005 |
Document in the Register: 登記冊上的文件: |
EIA for
Salisbury Road Underpass and Associated Road Improvement Works, including
Middle Road Circulation System. 梳 士 巴 利 道 隧 道 及 有 關 道 路 改 善 工 程 ﹐ 包 括 中 間 道 交 通 疏 導 系 統 -- 環 境 影 響 評 估 報 告 (登 記 冊 編 號 :AEIAR-016/1999) (2卷 1999年 4月 ) Environmental
Permit issued – Permit No.: EP-077/2000 issued on 28 August 2000. 已 簽 發 的 環 境 許 可 證 - 許 可 證 編 號 : EP-077/2000 於 2000年8 月28日 簽 發。 Application
for Variation of an Environmental Permit No. VEP-156/2004. [Hereafter
referred to as “the Application VEP-156/2004”] 申 請 更 改 環 境 許 可 證 編 號 VEP-156/2004。 [下 稱 “申 請 書 編 號 VEP-156/2004”] Environmental
Permit issued – Permit No.: EP-077/2000/A issued on 29 October 2004. 已 簽 發 的 環 境 許 可 證 - 許 可 證 編 號 : EP-077/2000/A 於 2004年 10 月29日 簽 發。 Application
for Variation of an Environmental Permit No. VEP-189/2005. [Hereafter
referred to as “the Application VEP-189/2005”] 申 請 更 改 環 境 許 可 證 編 號 VEP-189/2005。 [下 稱 “申 請 書 編 號 VEP-189/2005”] |
Application No. 申請 編號 |
Date of Application 申請 日期 |
List of Amendments
Incorporated into Environmental Permit 已包含在環境許可證內的修訂項目 |
Date of Amendments 修訂 日期 |
VEP-156/2004 |
2 October 2004 |
Vary Condition 2.10 in Part C of Environmental
Permit No. EP-077/2000 |
29 October 2004 |
|
2004年 10月2日 |
更 改 環 境 許 可 證 編 號EP-077/2000 C部 第 2.10 項 條 件 |
2004年 10月 29
日 |
VEP-189/2005 |
28 July 2005 |
Vary Conditions 2.9 and
2.10 in Part C of Environmental Permit No. EP-077/2000/A |
22 August 2005 |
|
2005年 7月28日 |
2005年 8 月 22
日 |
22 August 2005 |
______________________________________
環境保護署署長 (署理首席環境保護主任覺碩代行) |
PART
B (DESCRIPTIONS OF DESIGNATED PROJECT)
B部
(指
定
工
程
項
目
的
說
明
)
Hereunder is the description
of the designated project mentioned in Part A of this
environmental permit:
(hereinafter referred to as the "Permit")
下
列
為
本
環
境
許
可
證
(下
稱
"許
可
證")
A部所提述
的
指
定
工
程
項目的
說明
:
Title of Designated
Project |
Salisbury Road Underpass and Associated Road Improvement Works,
including Middle Road Circulation System [This designated project is
hereinafter referred to as "the Project"] 梳
士 巴 利 道 隧 道 及 有 關 道 路 改 善 工 程 ﹐ 包 括 中 間 道 交 通 疏 導 系 統
[這 指 定 工 程 項 目 下 稱
"工 程 項 目"] |
Nature of Designated
Project |
Construction and operation of a four-lane, 130m underpass and its
associated roadworks. 興
建 和 運 作 一 條 四 線 及
130米 長 的 行 車 隧 道 及 有 關 的 道 路 改 善 工 程 。 |
Location of Designated Project |
Tsim Sha Tsui. The location of the project is shown in Figure
1 attached to this Permit. (Same as Figure 2.1 in the EIA Report).
尖
沙 咀 。 圖 1顯
示 工 程 的 位 置 。
(與 環 評 報告 圖 2.1相同
)。 |
Scale and Scope of
Designated Project(s) |
Construction and operation of a four-lane 130m underpass at the
junction of Salisbury Road and Chatham Road, and widening of Salisbury Road
from Shangri-La Hotel to Kowloon Park Drive (approximately 1.0 km in length).
興
建 和 運 作 一 條 四 線 及
130米 長 的 行 車 隧 道 於 梳 士 巴 利 道 及 漆 咸 道 交 界 ﹐ 及 擴 闊 一 段 由 九 龍 香 格 里 拉 酒 店 至 九 龍 公 園 徑 的 梳 士 巴 利 道 (全
長 約 1千
米
)。 |
1 General
Conditions
1.1 The Permit Holder shall ensure
full compliance with all conditions of this environmental permit. Any
non-compliance may constitute a contravention of the EIAO (Cap. 499) and may
become subject of appropriate action to be taken under the Ordinance.
1.2 The Permit Holder shall ensure,
from time to time, full compliance with all legislation in force including but
without limitation to the Noise Control Ordinance (Cap. 400), Air Pollution
Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358) and
Waste Disposal Ordinance (Cap. 354). This Permit does not of itself constitute
any ground of defence against any proceedings instituted under any legislation.
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit
or the documents referred to in Part A of this Permit
readily available at all times for inspection at all sites/offices covered
by this Permit. Any reference to the Permit shall include all documents referred
to in the Permit and also the relevant documents in the Register.
1.4 The Permit Holder shall give
a copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated by the Permit.
1.5 The Permit Holder shall
display a copy of this Permit on the construction sites at all vehicular site
entrances/exits or at a convenient location for public information at all
times. The Permit Holder shall ensure that the most updated information about
the Permit, including any amended permit, is displayed at such locations. If
the Permit Holder surrenders a part or the whole of the Permit, the notice he
sends to the Director shall also be displayed at the same locations as the
original Permit. The suspended, varied or cancelled Permit shall be removed
from display at the construction sites.
1.6 The Permit Holder shall construct
and operate the Project as described in Part B of this
Permit.
1.7 The Permit Holder shall
ensure that the Project is designed, constructed and operated in accordance
with the information and recommendations described in the EIA Report (Register
No. AEIAR-016/1999); other relevant documents in the Register; and the
information or mitigation measures described in this Permit, or mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, or mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8 All deposited submissions as
required under this Permit, shall be rectified and re-submitted in accordance
with the comments, if any, made by the Director, within one month of the
receipt of the Director's comments or otherwise specified by the Director.
1.9 All submissions approved by the Director,
all submissions deposited without comments by the Director, or all submissions
rectified in accordance with comments by the Director under this Permit shall
be construed as part of the permit conditions described in Part
C of this Permit. Any variation of the submissions shall be approved by
the Director in writing or as prescribed in the relevant permit conditions.
Any non-compliance with the submissions may constitute a contravention of
the EIAO.
1.10 The Permit Holder shall release all finalized
submissions, as required under this Permit, to the public by depositing copies
in the EIAO Register Office, or in any other places, or any internet websites
as specified by the Director, or by any other means as specified by the
Director for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
1.11 The Permit Holder shall notify the Director in
writing the commencement date of construction of the Project at least one month
before the commencement of construction of the Project. The Permit Holder shall
notify the Director in writing immediately if there is any change of the
commencement date of the construction.
1.12 All submissions to the Director required under
this Permit shall be delivered either in person or by registered mail to the
EIAO Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road,
Wanchai, Hong Kong).
2.
Special Conditions
2.1 An Environmental Team (ET)
shall be established at least one month before the commencement of construction
of the Project. The ET shall be headed by the ET Leader who has at least 7
years' experience in environmental monitoring and audit (EM&A) or
environmental management. The ET Leader shall be responsible for the
implementation of the EM&A programme in accordance with the EM&A
requirements as contained in the EIA Report and the approved EM&A Manual
submitted under Condition 2.4 of this Permit. In addition, the ET Leader shall
be responsible for certifying the environmental acceptability of permanent and
temporary works, relevant design plans and submissions under this Permit.
2.2 An Independent Environmental
Checker (IEC) shall be employed at least one month before the commencement of
construction of the Project. The IEC shall have at least 7 years' experience in
EM&A or environmental management. The IEC shall audit the overall EM&A
programme including the implementation of all environmental mitigation
measures, submissions relating to EM&A, and any other submissions required
under this Permit. In addition, the IEC shall be responsible for verifying the
environmental acceptability of permanent and temporary works, relevant design
plans and submissions under this Permit.
2.3 All submissions for approval
and deposition under Sections 2 and 3 of this Permit shall be certified by the
ET Leader and verified by the IEC as conforming to the information and
recommendation contained in the EIA Report before submission to the Director.
2.4 At least 2 weeks before commencement
of the construction of the Project, the Permit Holder shall submit an EM&A
manual for the construction of the Project to the Director for approval. No
construction works shall commence before the Director has approved the EM&A
manual. The EM&A manual approved under this condition shall hereinafter be
referred to as the "EM&A Manual".
2.5 The Permit Holder shall,
within 4 weeks after the commencement of construction of the Project, inform
the Director in writing the management organization of the main construction
companies and/or any form of joint ventures associated with the construction of
the Project. The submitted information shall include at least an organization
chart, names of responsible persons and their contact details.
2.6 No rock crushing, on-site
concrete batching or blasting activity shall be carried out throughout the
entire construction period.
2.7 The underpass shall be
constructed in accordance with section 2 of the EIA Report. The underpass shall
provide not more than two traffic lanes in each direction.
Measures to Mitigate
Landscape and Visual Impacts
2.8 Within 4 weeks after the
commencement of construction of the Project, 5 sets of detailed master
landscape drawing(s) shall be submitted to the Director for approval. The
drawing(s) shall show the locations of trees within the project boundary.
2.9 The tree felling plan as
recommended in the Existing Trees Assessment Schedule in Appendix A of the
Application No. VEP-189/2005 shall be strictly adhered to.
2.10 The compensatory planting (4 times the
number of trees felled) and tree transplanting works as recommended in section
8 of the EIA Report and the Existing Trees Assessment Schedule in Appendix A of
the Application No. VEP-189/2005 shall be fully implemented. The Permit Holder
shall notify the Director in writing the date of completion of construction of
the Project and the date the Project commences operation at least 2 weeks
before the completion of construction of the Project or the commencement of
operation. Five (5) sets of detailed landscape as-built drawing(s) showing the
final locations of tree plantings within the project boundary to demonstrate
compliance with the approved submissions under Condition 2.8 shall be deposited
with the Director within two months after the completion of construction of the
Project or the Project commences operation, whichever is the sooner.
2.11 All measures described in Annex A to
mitigate landscape and visual impacts shall be fully implemented throughout the
entire construction period.
Measures to Mitigate
Construction Waste Impacts
2.12 Three sets of Waste Management Plan for
the construction stage of the Project shall be submitted to the Director for
approval within 6 weeks after the commencement of construction of the Project.
The Plan shall describe the arrangements for avoidance, reuse, recovery and
recycling, storage, collection, treatment and disposal of different categories
of waste to be generated from the construction activities and shall include the
recommended mitigation measures on waste management in section 6 of the EIA
Report. Such a management plan shall include the designation of areas for
segregation and temporary storage of reusable and recyclable materials and
disposal location of different categories of waste. All measures in the
approved Waste Management Plan shall be fully implemented throughout the entire
construction period.
3.
Environmental
Monitoring and Audit (EM&A) during the Construction Period
3.1 Samples and measurements
shall be taken in accordance with the requirements of the EM&A Manual
submitted under Condition 2.4 of this Permit by:
(a)
conducting baseline air quality monitoring as set out in the EM&A
Manual; and
(b)
conducting impact monitoring on air
quality and construction waste as set out in the EM&A Manual;
3.2 The remedial actions
described in the Event/Action Plans of the EM&A Manual shall be fully and
properly carried out, in accordance with the time frame(s) set out in the Event
/ Action Plan, or as agreed by the Director.
3.3 Records of the details of
Conditions 3.1 and 3.2 above shall be logged and kept, within 3 working days of
the collection of data or completion of remedial action(s), for the purpose of
preparing and submitting the monthly EM&A Reports and making the information
available for inspection on site.
3.4 All EM&A data submitted
under this Permit shall be true, valid and correct.
3.5 One hard copy and one soft
copy of the Baseline Monitoring Report shall be submitted to the Director at
least one month before the commencement of any construction works. The Report
shall include but without limitation to the details of the baseline air quality
monitoring. Additional copies of the submission shall be provided to the
Director upon request from the Director.
3.6 One hard copy and one soft
copy of monthly EM&A Report shall be submitted to the Director within 2
weeks after the end of the reporting month. Additional copies of the submission
shall be provided to the Director upon request from the Director.
4.
Electronic Reporting
of EM&A Information
4.1 To facilitate public
inspection of the Baseline Monitoring Report and monthly EM&A Reports via
the EIAO Internet Website and at the EIAO Register Office, electronic copies of
these Reports, prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 4.0 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hard copies as described in Conditions 3.5 and 3.6 above. For the HTML version,
a content page capable of providing hyperlink to each section and sub-section
of these Reports shall be included in the beginning of the document. Hyperlinks
to all figures, drawings and tables in these Reports shall be provided in the
main text from where the respective references are made. All graphics in these
Reports shall be in interlaced GIF format unless otherwise agreed by the
Director. The content of the electronic copies of these Reports must be the
same as the hard copies.
4.2 All environmental monitoring data
described in Condition 4.1 above shall be made available to the public via
internet access in the form of a website, in the shortest possible time and in
no event later than 2 weeks after the relevant environmental monitoring data
are collected or become available, unless otherwise agreed with the Director.
The Permit Holder shall notify the Director in writing within 6 weeks after the
commencement of works the internet address where the environmental monitoring
data are to be placed. The internet address and the relevant environmental
monitoring data shall be made available to the public via the EIAO Internet
Website and the EIAO Register Office.
4.3 The internet website as
described in Condition 4.2 above shall enable user-friendly public access to
the monitoring data with features capable of:
(a)
providing access to all environmental monitoring data collected since
the commencement of works;
(b)
searching by date;
(c)
searching by types of monitoring data
(air quality and construction waste); and
(d)
hyperlinking to relevant monitoring data
after searching;
or
otherwise as agreed by the Director.
Notes:
1.
This Permit consists of three parts, namely,
PART A (Main Permit), PART B (Description
of Designated Project) and PART C (Permit Conditions).
Any person relying on this Permit should obtain independent legal advice on
the legal implications under the Ordinance, and that the following notes are
for general information only.
2.
The Permit Holder may apply under section
13 of the Ordinance to the Director for a variation of the conditions of this
Permit. The Permit Holder shall replace the original Permit displayed on the
construction site by the amended Permit.
3.
A person who assumes the responsibility
for the whole or a part of the designated project may, before he assumes
responsibility of the designated project, apply under section 12 of the
Ordinance to the Director for a further environmental permit.
4.
Under section 14 of the Ordinance, the
Director may, with the consent of the Secretary for the Environment, Transport
and Works, suspend, vary or cancel this Permit. The suspended, varied or
cancelled Permit shall be removed from the display at the construction site.
5.
If this Permit is cancelled or
surrendered during the construction or operation of the Project, another
environmental permit must be obtained under the Ordinance before the Project
could be continued. It is an offence under section 26(1) of the Ordinance to
construct or operate a designated project listed in Part I of schedule 2 of the
Ordinance without a valid environmental permit.
6.
Any person who constructs or operates the
Project contrary to the conditions in the Permit, and is convicted of an
offence under the Ordinance, is liable-
(i)
on a first conviction on indictment to a fine of $2 million and to
imprisonment for 6 months;
(ii)
on a second or subsequent conviction on
indictment to a fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine
at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a
continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
7. The Permit Holder may
appeal against any condition of this Permit under section 17 of the Ordinance
within 30 days of receipt of this Permit.
Environmental Permit No. EP-077/2000/B
環
境
許
可
證
編
號
EP-077/2000/B
Annex A
Measures to Mitigate
Landscape and Visual Impacts During Construction
1. At all parts of all
works areas and construction sites and throughout the entire construction
period, the following mitigation measures shall be implemented to minimize the
landscape and visual impact of the construction works:
(a)
site works shall be screened by hoardings;
(b)
the surface of the hoardings shall be
treated in order to enhance their visual interest and harmony with surrounding
landscape/townscape;
(c)
temporary buildings (e.g. site office)
shall be located in least visually prominent locations;
(d)
vegetation within the work site area
shall be retained whenever possible;
(e)
fences shall be provided around all the
low, circular raised planters to ensure that materials and debris will not be
dumped on tree roots;
(f)
pedestrian routes shall be re-routed away
from the work site and through well defined public access wherever possible;
(g)
transplanting of existing vegetation shall
be carried out under the supervision of a professional landscape architect;
[ Back to First Page ] / [ Back to Main Index ]