Environmental Permit No. EP-167/2003/D

環境許可證編號  EP-167/2003/D

 

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Section 10 & 13

 

環境影響評估條例

(499)

10條及第13

 

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A DESIGNATED PROJECT

建造及營辦指定工程項目的環境許可證

 

Part A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of Environmental Protection (the Director) granted the environmental permit (No. EP-167/2003) to The Hong Kong and China Gas Company limited (hereinafter referred to as the “Permit Holder”) on 30 May 2003.  Pursuant to Section 13 of the EIAO, the Director amends the Environmental Permit EP-167/2003/C based on the Application No. VEP-211/2006.  The amendments described below are incorporated into this Environmental Permit (EP-167/2003/D). This Environmental Permit as amended is for the construction and operation of the designated project described in Part B of this Permit subject to the conditions specified in and attached to Part C of this Permit.

 

根據環境影響評估條例(環評條例)第10條的規定,環境保護署署長(署長)2003530將環境許可證(編號EP-167/2003)批予香港中華煤氣有限公司。根據環評條例第 13條的規定,署長因應申請書編號 VEP- 211/2006修訂環境許可證編號 EP-167/2003/C。下文說明的修訂,已包含在本環境許可證內(編號EP-167/2003/D)。本經修訂的環境許可證,適用於建造及營辦本許可證B所說明的指定工程項目,但須遵守本許可證C所列明及附載的條件。

 

The issue of this amended environmental permit is based on the documents, approvals or permissions described below:

 

本經修訂的環境許可證乃依據下列文件、批准或許可條件而簽發 -

 

 

Application No.

申請書編號

VEP 211/2006

 

Document in the Register :

登記冊上的文件:

 

(1) Proposed Submarine Gas Pipelines from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong

(Register No.: AEIAR-071/2003)

-          Environmental Impact Assessment Report (4 March 2003) [Hereinafter referred to as the “EIA Report”]

-          Environmental Impact Assessment Executive Summary (4 March 2003) [Hereinafter referred to as the “EIA Executive Summary”]

-          Environmental Monitoring and Audit Manual (4 March 2003)

[Hereinafter referred to as the “EM&A Manual”]

 

(1) 從深圳秤頭角液化天然氣接收站連接至香港大埔煤氣製造廠之海底輸氣管道(登記冊編號: AEIAR-071/2003)

-          環境影響評估報告 (200334) [下稱環評報告”]

-          環境影響評估行政摘要 (200334) [下稱環評行政摘要”]

-          環境監察及審核手冊 (200334) [下稱環監手冊”]

 

(2) The Director’s letter of approval of the EIA Report dated 23 April 2003 (Reference: (37) in EP2/G/H/120 II)

(2) 署長於2003423發出批准環評報告的信件 (檔案編號: (37) in EP2/G/H/120 II)

  

(3) Application documents including all attachments submitted by the Permit Holder on 2 May 2003 (Application No. AEP-167/2003)

(3) 申請文件包括許可證持有人於200352提交的所有附件(申請書編號:AEP-167/2003)

 

(4) Environmental Permit (Permit No. EP-167/2003) issued on 30 May 2003

(4) 20035 30日發出的環境許可證(許可證編號:EP-167/2003)

 

(5) Application for Variation of an Environmental Permit on 30 December 2004 including all attachments submitted (Application No. VEP-161/2004)

(5) 20041230提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-161/2004)

 

(6) Environmental Permit (Permit No. EP-167/2003/A) issued on 24 January 2005

(6) 20051 24日發出的環境許可證(許可證編號:EP-167/2003/A)

 

(7) Application for Variation of an Environmental Permit on 26 April 2005 including all attachments submitted (Application No. VEP-175/2005)

(7) 2005426提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-175/2005)

 

(8) Environmental Permit (Permit No. EP-167/2003/B) issued on 13 May 2005

(8) 20055 13日發出的環境許可證(許可證編號:EP-167/2003/B)

 

(9) Application for Variation of an Environmental Permit including all attachments submitted on 5 August 2005 (Application No. VEP-191/2005)

(9) 200585提交的更改環境許可證申請包括所有附件(申請書編號:VEP-191/2005

 

(10) Environmental Permit (Permit No. EP-167/2003/C) issued on 12 August 2005

(10) 20058 12日發出的環境許可證(許可證編號:EP-167/2003/C)

 

(11) Application for Variation of an Environmental Permit including all attachments submitted on 28 February 2006 (Application No. VEP-211/2006)

(11) 2006228提交的更改環境許可證申請包括所有附件(申請書編號:VEP-211/2006

 

Application No.

申請書編號

Date of Application

申請日期

 

List of Amendments Incorporated into this Environmental Permit

已包含在本環境許可證內修訂項目

 

Date of Amendment

修訂日期

 

VEP-161/2004

 

30 December 2004

 

20041230

 

Vary Figure 1 in Part C of Environmental Permit No. EP-167/2003.更改環境許可證編號 EP-167/2003 C 圖一。

24 January 2005

 

20051 24

VEP-175/2005

26 April 2005

 

2005426

Vary Condition 3.6 in Part C of the Environmental Permit EP-167/2003/A

 

更改環境許可證編號 EP-167/2003/A C 3.6 項條件。

 

Vary Condition 3.7 in Part C of the Environmental Permit EP-167/2003/A

 

更改環境許可證編號 EP-167/2003/A C 3.7 項條件。

 

Vary Condition 3.8 in Part C of the Environmental Permit EP-167/2003/A

 

更改環境許可證編號 EP-167/2003/A C 3.8 項條件。

 

Vary Condition 3.9 in Part C of the Environmental Permit EP-167/2003/A

更改環境許可證編號 EP-167/2003/A C 3.9 項條件。

 

Addition of Figure 4 and Figure 5

 

加入圖四及圖五。

 

13 May 2005

 

2005513

VEP-191/2005

5 August 2005

 

200585

Addition of Conditions 3.2a and 3.2b in Part C of the Environmental Permit EP-01/167/2003/B

 

加入環境許可證編號 EP-01/167/2003/B C 3.2a 3.2b 項條件。

 

Vary Conditions 3.2, 3.3 & 4.1 in Part C of the Environmental Permit EP-01/167/2003/B

 

更改環境許可證編號 EP-01/167/2003/B C 3.2, 3.3 4.1項條件。

 

Addition of Appendices A & B

 

加入附錄AB

 

 

12 August 2005

 

2005812

VEP-211/2006

28 February 2006

Vary the description of Scale and Scope of Designated Project(s) in Part B of the Environmental Permit EP-167/2003/C

 

更改環境許可證編號 EP-167/2003/C  B 部的「指定工程項目的規模和範圍」的說明。

 

Addition of Conditions 3.2c, 3.3a and 3.11 in Part C of the Environmental Permit EP-167/2003/C

 

加入環境許可證編號 EP-167/2003/C C 3.2c, 3.3a and 3.11 項條件。

 

Vary Conditions 4.1 and 4.2 in Part C of the Environmental Permit EP-167/2003/C

 

更改環境許可證編號 EP-167/2003/C C 4.14.2項條件。

 

Addition of Appendices C, D, E & F

 

加入附錄C, D, E F

 

20 March 2006

 

          

 

 

 

 

 

 

 

 

Date

日期

 

(David T. W. WONG)

Principal Environmental Protection Officer

for Director of Environmental Protection

環境保護署署長

(首席環境保護主任王德威代行)

 


Part B (DESCRIPTIONS OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):

下列為本環境許可證(下稱許可證”)A部所提述的指定工程項目的說明:

  

Title of Designated Projects

指定工程項目的名稱

Proposed Submarine Gas Pipelines from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong

[This designated project is hereinafter referred to as “the Project”.]

 

從深圳秤頭角液化天然氣接收站連接至香港大埔煤氣製造廠之海底輸氣管道

[本指定工程項目下稱"工程項目"]

 

Nature of Designated Projects
指定工程項目的性質

Submarine gas pipelines.

 

海底輸氣管道

 

Location of Designated Projects

指定工程項目的地點

The location of the Project is shown in Figure 1 attached to this Permit.

 

工程項目的位置載於本許可證夾附的圖1

 

Scale and Scope of Designated Project(s)

指定工程項目的規模和範圍

Construction and operation of twin 450mm diameter submarine gas pipelines of approximately 28.5km in length.  The submarine pipelines will be buried to the seabed mainly by jetting method except that a short section of pipelines in Mirs Bay will be laid after dredging.  Armour rock backfill or grout mattresses will be applied afterwards to the various sections as indicated in Figure 2 and Figure 6 of this Permit respectively.

 

建造及營辦兩條長約28.5公里,直徑450毫米的海底輸氣管道。輸氣管道主要會用水力噴注法埋於海床,但位於大鵬灣的一小段會用挖掘工程敷設。 各段管道敷設完成後會進行護面塊石回填或灌漿護蓋工程,分別如本許可證2及圖6所示。 

 

 

 


Part C (PERMIT CONDITIONS)

 

1.         General Conditions

 

1.1        The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit.  Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of appropriate action being taken under the Ordinance.

 

1.2               The Permit Holder shall ensure full compliance with all legislation from time to time in force including, without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354).  This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.

 

1.3               The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorised officers at all sites/offices covered by this Permit.  Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the EIA Ordinance Register Office.

 

1.4               The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit.  The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.

 

1.5               The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.  The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6               The Permit Holder shall construct and operate the Project in accordance with the project descriptions in Part B of this Permit.

 

1.7               The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and recommendations described in the EIA Report, EIA Executive Summary, EM&A Manual (Register No. AEIAR-071/2003), other relevant documents in the EIAO Register Office, the information and mitigation measures described in this Permit, mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under ongoing surveillance and monitoring activities during all stages of the Project.  Where recommendations referred to in the documents of the EIAO Register Office are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

 

1.8               All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise as specified by the Director.

 

1.9               All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit.  Any variations of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions.  Any non-compliance with the submissions may constitute a contravention of the EIAO (Cap.499).  All submissions or any variation of the submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) referred to respectively in Conditions 2.1 and 2.2 below, before submitting to the Director under this Permit.

 

1.10            The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the EIAO Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection.  For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11            All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the EIAO Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong).  Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

 

1.12            The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than one month prior to the commencement of construction of the Project.  The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

 

1.13            For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.

  

2.                  Measures Before Commencement of Construction of the Project

 

Employment of Environmental Monitoring and Audit (EM&A) Personnel

 

2.1               An Environmental Team (ET) shall be established no later than one month before the commencement of construction of the Project.  The ET shall be headed by an ET Leader.  The ET Leader shall be a person who has at least 7 years' experience in EM&A or environmental management.  The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual.  The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the findings of the EIA Report and each and every non-compliance with the recommendations of the EIA Report or this Permit.  This log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the recommendations of the EIA Report and this Permit or by the Director or his authorized officers.  Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader.  Failure by the Permit Holder to replace the ET Leader, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.  The ET shall not be in any way an associated body of the Contractor or the IEC for the Project.

 

2.2               The Permit Holder shall employ an Independent Environmental Checker (IEC) no later than one month before the commencement of construction of the Project.  The IEC shall be a person who has at least 7 years' experience in EM&A or environmental management.  The IEC shall be responsible for duties defined in the EM&A Manual, and shall audit the overall EM&A programme, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit.  In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit.  The IEC shall verify the contemporaneous records of the log-book(s) mentioned in Condition 2.1 of this Permit.  The IEC shall notify the Director by fax transmission, within 24 hours of receipt of notification from the ET Leader of each and every occurrence, change of circumstances or non-compliance with the recommendations of the EIA Report or this Permit, which might affect the monitoring or control of adverse environmental impacts.  Where the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined in the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC.  Failure by the Permit Holder to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation.  Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition.  The IEC shall not be in any way an associated body of the Contractor or the ET for the Project.

 

3.                  Submission and Measures During Construction of the Project

 

Management Organization of Main Construction Companies

 

3.1               The Permit Holder shall, within two weeks after the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project, including the portion of the pipelines outside the Hong Kong Special Administrative Region (SAR) boundary.  The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

 

Construction Methods

 

3.2               The Project shall be constructed by using the appropriate installation techniques for the various sections of the pipelines alignment as described in the EIA Report and this Permit, and as indicated in Figures 1 and 2 of this Permit.

 

3.2a      Jetting works for the pipeline between Location E and Location G shown in Figure 1 of this Permit shall be carried out by completing three jetting passes for each 2 kilometre section before moving onto the next 2 kilometre section along the alignment of the pipeline.  The jetting machine shall complete the entire 2 kilometre section in one single pass before returning to the start of the section to begin the next pass, and the next pass shall not commence within 2 hours after the preceding pass has been completed.  Jetting works for the next 2 kilometre section shall not commence within 12 hours after completion of the preceding section.

 

3.2b      Jetting works for the pipeline between Location A and Location D shown in Figure 1 of this Permit shall be carried out by completing three jetting passes.  Each jetting pass shall be continued and completed for the entire section before retuning to the start of the section to begin the next pass.

3.2c      For a section of the pipeline of about 200 metres long between Location H and Location J shown in Figure 1 of this Permit where jetting can only be proceeded to about 1.1 metres to 1.3 metres below seabed level due to the presence of oyster shell deposits in the area, backfilling of armour rock will be replaced by grout mattresses for protection of the submarine pipeline.  The method statement for installation of the grout mattresses described in Appendix F of this Permit shall be followed. 

 

 

Pilot Test on Jetting Performance

 

3.3               A pilot test on the jetting technique as described in Appendix A of this Permit shall be fully and properly carried out for the purpose of verifying the water quality modelling predictions in the supporting assessment submitted with the application for variation of an Environmental Permit (Application No. VEP-191/2005) and the EIA Report.  The results of the pilot test shall provide the basis to determine any remedial actions during the subsequent jetting operation.  If the results indicate that the modelling predictions are being exceeded, remedial action, such as reduction in jetting speed, shall be taken immediately after the pilot test to ensure that exceedance of the Action and Limit levels for impact monitoring as defined in the EM&A Manual will not occur.  The remedial action, including any reduction in jetting speed, shall be certified by the ET Leader and verified by the IEC as conforming to the predicted environmental performance in the EIA Report.

 

 

Pilot Test on Grouting Performance

 

3.3a      A pilot test shall be carried out in accordance with the testing method as described in Appendix C of this Permit for the purpose of verifying the environmental performance of the grouting operation during installation of the grout mattress. If the grouting operation causes more than three or more consecutive exceedances in the water quality parameters being monitored during the pilot test, modifications to the subsequent operation shall be made and remedial actions shall be taken before continuing the remaining grout mattress installation works.  The modifications and remedial actions shall be certified by the ET Leader and verified by the IEC as conforming to the environmental performance assessment submitted with the application for variation of an Environmental Permit (Application No. VEP 211/2006).


 

Mitigation Measures

 

3.4               To mitigate water quality impact arising from the construction works of the Project, the forward speed of the jetting machine for the construction of pipelines section between Location A to Location C, as shown in Figure 1 of this Permit, shall not exceed 67.5 metres per hour and 1.08 kilometres per day; and that for the construction of pipelines section between Location C to Location G shall not exceed 67.5 metres per hour and 1.62 kilometres per day.

 

3.5               Silt curtain shall be installed as indicated in Figure 3 of this Permit and properly maintained when works are being carried out at the Tai Po landing point site and the shore approach section, and when jetting works are being carried out within 2 kilometres from the proposed landing point at the seawall of the Tai Po Industrial Estate, except during the pilot test on jetting performance as required in Condition 3.3 above.  Any proposal to modify the length of silt curtain shall be supported by EM&A results and submitted for the agreement by the Director before implementation.  The environmental acceptability of such modification shall also be certified by the ET Leader and verified by the IEC before submission to the Director.

 

3.6               Grab dredger shall be used for the dredging works between Location D to Location E as shown in Figure 1 of this Permit, and no more than three grab dredgers operating with a separation distance of no less than 1,000 m between each other shall be allowed to dredge at any one time along the pipelines route.

 

3.7               The dredging rate for each grab dredger during dredging between Location D to Location E, as shown in Figure 1 of this Permit, shall not exceed 250 cubic metres per hour and 6,000 cubic metres per day.

 

3.8               To avoid localised aesthetic impacts at the sea surface due to escape of marine mud from the ascending grab to the upper layer of the water column, frame type silt curtain with details shown in Figure 4 and Figure 5 of this Permit shall be employed at each grab dredger for dredging between Location D to Location E as shown in Figure 1 of this Permit.  The silt curtains shall be properly maintained throughout the dredging operation.

 

3.9               All barges used for the transport of dredged materials shall be fitted with tight bottom seals and filled to an appropriate level to ensure that dredged materials do not spill over during transport to the disposal site, and adequate free board shall be maintained to ensure that the decks are not washed by wave action.

 

3.10            Dredging works and jetting works of the Project shall not be carried out simultaneously.

3.11            The Measures for Pollution Prevention and Control in Appendix E of this Permit shall be fully and properly implemented during the grout mattress installation works.  Amongst other measures, an appropriate number of experienced and properly equipped divers shall be deployed to observe and monitor the underwater works for any abnormalities throughout the whole grouting process.  Effective communication between the divers and the operators on board the construction vessel shall be maintained. The maximum grout pumping rate shall not be greater than 1cubic metre per ten minutes (1 cu.m/10 min).  Should there be any signs of leakage or spillage, the grouting operation shall be stopped immediately.  Appropriate remedial actions and/or mitigation in Appendix E of this Permit shall be implemented. 

 

 

4.                  Environmental Monitoring and Audit (EM&A) Requirements During Construction Period

 

4.1               Subject to amendments as stated in Appendix B of this Permit, the EM&A programme for the construction of the Project shall be implemented in accordance with the procedures and requirements set out in the EM&A Manual.  The EM&A programme for the grout mattress installation works of the Project shall also be implemented in accordance with the procedures and requirements set out in Appendix D of this Permit.  Any changes to the EM&A programme shall be justified by the ET Leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual, and shall be submitted to the Director for approval.

 

4.2               Samples, measurements and necessary remedial actions shall be taken in accordance with the requirements of the EM&A Manual and Appendix D of this Permit by:

(a)                conducting baseline environmental monitoring on water quality and marine ecology;

(b)                conducting impact monitoring on water quality and marine ecology;

(c)                carrying out remedial actions described in the Event/Action Plans of the EM&A Manual in accordance with the time frame set out in the Event/Action Plans, or as agreed by the Director, in case where specified criteria in the EM&A Manual of this Permit are exceeded; and

(d)                logging and keeping records of the details of (a) to (c) above for all parameters in accordance with the time requirements set out in the EM&A Manual and in Appendix D of this Permit and in any event no later than three working days of the collection of data or completion of remedial action(s), for the purpose of preparing and submitting the monthly EM&A Reports and to make available the information for inspection on site.

 

4.3               All EM&A data submitted under this Permit shall be true, valid and correct.

 

4.4               Three hard copies and one electronic copy of the Baseline Monitoring Report shall be submitted to the Director at least two weeks before the commencement of construction of the Project.  The submission shall be certified by the ET Leader and verified by the IEC.  Additional copies of the submission shall be made available to the Director upon his request.

 

4.5               Three hard copies and one electronic copy of monthly EM&A Report shall be submitted to the Director within two weeks after the end of the reporting month.  The EM&A Reports shall include a summary of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels).  The submissions shall be certified by the ET Leader and verified by the IEC.  Additional copies of the submission shall be provided to the Director upon request by the Director.

 

Monitoring of Corals

 

4.6               The impacts on corals shall be monitored in accordance with Section 4 of the EM&A Manual when jetting works are being carried out within the Tolo Channel (between Wong Wan Tsui and Wong Chuk Kok Tsui) and when dredging works on the Shenzhen side of this Project are being carried out within 1 kilometre of the Hong Kong SAR boundary.

 

Consideration of Using Additional Silt Curtain based on EM&A Results

 

4.7               If the EM&A results indicate that the elevation of suspended sediment concentrations caused by the Project at the coral sites, in particular at Fung Wong Fat, is likely to exceed the Limit Level of 10 mg/L, the installation of additional silt curtain to protect the corals shall be considered, together with other potential mitigation measures, under the Event and Action Plan and implemented accordingly, if found necessary.

 

5.                  Electronic Reporting of EM&A Information

 

5.1               To facilitate public inspection of the Baseline Monitoring Report and monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Condition 4 above of this Permit.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made.  All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director.  The content of the electronic copies of these Reports must be the same as the hard copies.

 

5.2               The Permit Holder shall, within three weeks after the commencement of construction of the Project, set up a dedicated Internet web site and notify the Director in writing the Internet address where the environmental monitoring data and project information is to be placed.  All environmental monitoring data described in Condition 5.1 above shall be made available to the public via the abovementioned dedicated Internet web site in the shortest possible time and in any event no later than two weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director. 

 

5.3               The Internet web site as described in Condition 5.2 above shall enable user-friendly public access to the environmental monitoring data and project information including the documents (1) to (3) listed in Part A of this Permit, and this Environmental Permit.  The Internet web site shall have features capable of:

 

(a)               providing access to all environmental monitoring data of this Project collected as required under this Permit;

(b)               providing access to all finalized submissions as required under this Permit;

(c)               searching by date;

(d)               searching by types of monitoring data (water quality and marine ecology); and

(e)               hyperlinking to relevant monitoring data after searching; 

 

or otherwise as agreed by the Director.

 

Notes :

 

1.                   This Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions).  Any person relying on this Permit should obtain independent legal advice on the legal implications under the Ordinance, and the following notes are for general information only.

 

2.                   If there is a breach of any condition of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, Transport and Works, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

 

3.                   The Permit Holder may apply under Section 13 of the Environmental Impact Assessment Ordinance (the “Ordinance) to the Director for a variation of the conditions of this Permit.  The Permit Holder shall replace the original permit displayed on the construction site by the amended permit.

 

4.                   A person who assumes the responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.

 

5.                   Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for the Environment, Transport and Works, suspend, vary or cancel this Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site.

 

6.                   If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the Ordinance before the construction or operation of the Project could be continued.  It is an offence under Section 26(1) of the Ordinance to construct or operate a designated project listed in Part I of Schedule 2 of the Ordinance without a valid environmental permit.

 

7.                   Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable: -

 

(i)              on a first conviction on indictment to a fine of $2 million and to imprisonment for 6 months;

 

(ii)            on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;

 

(iii)           on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

 

(iv)          on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

 

(v)            in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.

 

8.                   The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

 

9.                   The Notes are for general reference only and that the Permit Holder should refer to the Ordinance for details and seek independent legal advice.


Appendix A    

Pilot Test on Jetting Performance

In order to verify the modelling predictions in the EIA Report and the supporting assessment submitted with the application for variation of an Environmental Permit (Application No. VEP-191/2005), a pilot test will be conducted during jetting works commencing from either the Tai Po landing point or  the Hong Kong Special Administrative Region (HKSAR) waters boundary.  If the jetting operation commences at the Tai Po landing point, the pilot test will be conducted in accordance with Section 3.2.5 of the EM&A Manual.  If the jetting operation commences at the HKSAR boundary, the procedure and requirements for the pilot test as set out in the following paragraphs below shall supersede the corresponding parts in Section 3.2.5 of the EM&A Manual.

Commencement of Jetting at the HKSAR Boundary

The pilot test will consist of intensive water quality monitoring of all three jetting passes along the first 2-km sectionThe sea area to be monitored will cover 400 metres perpendicular to the first 2-km section on both sides of the pipeline alignment.

Stations

A set of monitoring stations will be arranged perpendicularly to the jetting alignment.  Monitoring locations will be fixed throughout the whole monitoring.  The locations of the stations are illustrated in Figure A1.

Monitoring Programme

The jetting works in Mirs Bay between Location E and Location G, shown in Figure 1 of this Permit will be carried out 24 hours per day and the expected jetting programme is outlined in Table A1 below:

 

Table A1         Jetting Programme in Mirs Bay

Day Number

Time**

Activity

Day 1

00:00 - 24:00

First 1.62km of Pass 1

Day 2

00:00 – 05:40

Remaining 0.38km of Pass 1

05:40 - 07:40

Dredger relocates to the start of the 2km section

07:40 - 24:00

First 1.1km of Pass 2

Day 3

00:00 - 13:20

Final 0.9km of Pass 2

13:20 - 15:20

Dredger relocates to the start of the 2km section

15:20 - 24:00

First 585m of Pass 3

Day 4

00:00 - 21:00

Final 1.4km of Pass 3

           Note:  **  Works will proceed continuously for 24 hours each day.  The start time on Day 1 is assumed to be 00:00 for the purposes of presentation of the programme. The actual start time should be confirmed by the contractor.

 

The water quality impact of all three jetting passes will be monitored. For each jetting pass, the monitoring line will be located 100m from the start of the 2 km section.  Monitoring will begin when the pass commences and continue until the completion of the pass.  The monitoring will be repeated when the next pass begins after relocation of the jetting machine.

Frequency

The same requirements as set out in Section 3.2.5 of the EM&A Manual shall apply. 

Reporting

The same requirements as set out in Section 3.2.5 of the EM&A Manual shall apply.

Actions

The results of the pilot test will indicate how the jetting works are performing in comparison with the modelling predictions presented in the supporting assessment submitted with the application for variation of an Environmental Permit (Application No. VEP-191/2005).    If the results indicate that the modelling predictions are being exceeded, the Contractor will take remedial actions, such as reduction in jetting speed, to ensure that exceedances of the appropriate Action and Limit levels for the Impact Monitoring will not occur during subsequent jetting works.  For the purpose of checking whether the jetting machine is performing according to the modelling predictions, the following protocols should be adopted to analyse the monitoring results.

The monitoring results refer to the pilot test stations as presented in Figure A1

Step 1      Analyse the results of monitoring for the three jetting passes of the 2 km section to determine the range of SS values recorded at the monitoring stations.  The data analysis should focus on bed layer results at the stations located 400m from the jetting alignment as these are most relevant to the impact assessment on the key sensitive coral sites. 

Step 2      The recorded values should then be compared against the coral tolerance criterion of an elevation of 10 mg L-1 above ambient.

Step 3      If the SS elevations are less than the coral tolerance criterion then no further actions are required as a result of the pilot test.  If the SS elevations are greater over three consecutive monitoring events on any one jetting pass then the percentage deviations should be determined.  For example if the pilot test indicates that the 400m stations record three consecutive elevations of 12 mg L-1 then the performance of the jetting machine can be seen to differ consistently by + 20 % from the predictions in the supporting assessment submitted with the application for variation of an Environmental Permit (Application No. VEP-191/2005).  The data from the other monitoring stations should be examined to determine whether the jetting machine is the cause of the exceedance.  If the 400m stations record higher values than the stations closer to the jetting machine then it may indicate that other factors have caused the exceedances.

Step 4      Based on the findings of Step 3 the Contractor in conjunction with the ET Leader and IEC should decide on appropriate reductions to the jetting rate. Remedial actions associated with exceedances of Action and Limit levels are discussed in Section 3.3 of the EM&A Manual.


Appendix B

Amendments to Other Relevant Sections of the EM&A Manual

for Jetting Works at Mirs Bay

For the jetting works within the Tolo Harbour and Channel between Location A and Location D as shown in Figure 1 of this permit, the same EM&A programme as set out in the EM&A Manual shall be implemented.  For the jetting works at Mirs Bay between Location E and Location G as shown in Figure 1 of this permit, the relevant sections of the EM&A Manual are amended below which shall be followed in the EM&A programme. 

(a)    Section 3.2.7 - Monitoring Locations & Frequency – Impact Monitoring

The 9th paragraph is replaced by the following paragraph:

“Zone C shall be monitored during jetting works within 2 km of the boundary of the Tung Ping Chau Marine Park.  One impact station (C1) on the boundary of the Tung Ping Chau Marine Park and one control station (C2) north of the alignment will be monitored.  During jetting the stations will be monitored daily within 3 hour window of 1.5 hour before or after mid-flood and mid-ebb tides.  At least four numbers of the monitoring should be conducted between 19:00 to 05:00 hour when the jetting is in operation during night time”  

(b)   Section 3.3 - Water Quality Compliance

The requirements to review the performance of the monitoring programme after the first pass of the original jetting programme as set out in the 4th paragraph shall apply when the second 2 km section of the jetting works in Mirs Bay is completed.

(c)    Section 4.3 – Marine Ecology Compliance – Action Event Plan

The requirements to review the monitoring results after the first pass of the original jetting programme as set out in the second last sentence of the last paragraph of Section 4.3 shall apply when the first 2 km section of the jetting works in Mirs Bay is completed.

(d)    General

 

The jetting rate of 1.08 km per day as referred to the original jetting programme should be referred as 67.5 metres per hour under the modified jetting programme.


Appendix C

Pilot Test on Grouting Performance

 

To ensure that the grout mattress installation works will not cause any significant impacts to water quality and marine ecological system, a pilot test shall be conducted to confirm the environmental performance of the grouting operations.  In respect of water quality monitoring, this pilot test shall be similar to that for jetting as described in Appendix A of this Permit and Section 3.2.5 of the EM&A Manual.  In addition, coral surveys shall be conducted based on the same methodology described in Section 4 of the EM&A Manual. 

 

Water Quality Monitoring

 

1.   Parameters: suspended solids, turbidity and pH.

 

2.   Monitoring locations: 4 fixed monitoring stations, namely M1, M2, M3 and M4, located on both sides of the grouting barge as shown in Figure A2. Stations M1 and M4 are 200 m from the barge while M2 and M3 are 100 m away. 

 

3.   Duration: 3 Days

 

4.   Frequency: Every 3 hours for 72 hours continuously.  

 

5.   Monitoring method:

 

(a)    Three depths: 1 m below surface, mid-depth and 1 m above seabed;

(b)    Number of replicates at each depth: 2

(c)    Other requirements: same as Sections 3.2.2, 3.2.3 and 3.2.4 of the EM&A Manual.

 

6. Reporting:  

      The monitoring results shall be submitted to EPD and AFCD in the following schedule:

(a)    Turbidity and pH data - within 24 hours after the monitoring results are recorded in the field.  

(b)    SS data - within 48 hours after the water samples are received by the testing laboratory.

(c)    Video footage taken by divers for the underwater grouting operation: 24 hours after video recording.

 


7.   Exceedance Criteria:

 

Parameter

Station

Depth

Exceedance Criteria

Other Conditions

SS

M1 or M4

Bed Layer

13 mg/L

For any parameter, if lower level is measured at M2 or M3, the exceedance will not be considered to be caused by the works and it will not be recorded as an exceedance event.

Turbidity

M1 or M4

Bed Layer

13 NTU

pH

M1 or M4

Bed Layer

8.5

 

8.   Actions

The results of the pilot test will indicate how the grout mattress installation works is performing in comparison with the assessment made under the Application No. VEP 212/2006 for variation of the Environmental Permit No. EP-167/2003/C that the works will not cause any significant impact on water quality and marine ecological system.   In this connection, the following actions shall be taken according to the monitoring results of the pilot test:

 

(a)    If there are no record of three consecutive exceedance events for any specific parameter during the pilot test, no further water quality monitoring is required except that ad hoc water quality impact monitoring will be triggered by accidental incidents .

 

(b)    If three consecutive exceedance events for any specific parameter are recorded, the construction method and activities as well as the relevant water quality monitoring results shall be reviewed immediately by the Contractor in conjunction with the ET and the IEC to determine if the exceedances are due to the works.  If it is determined that the exceedances are due to the works, the grouting operation shall be suspended immediately.  Remedial action shall be taken before continuing the remaining grout mattress installation works.  The remedial action shall be certified by the ET Leader and verified by the IEC as conforming to the environmental performance assessment submitted with the application for variation of an Environmental Permit (Application No. VEP 211/2006).

 

 

Coral Monitoring

 

1. Parameters: Same as the monitoring programme specified in Section 4 of the EM&A Manual.

 

2. Monitoring locations: I6, I7 (Impact) and C1 (Control). 

 

3. Duration: 3 Days

 

4. Frequency: Daily  

 

5. Monitoring method: Same as the monitoring programme specified in Section 4 of the EM&A Manual.

 

6. Reporting: Results will be sent to EPD and AFCD within 48 hours after completion of each day of coral survey 

 

7. Exceedance Criteria: Same as those on the Coral Survey Proforma adopted for the coral monitoring programme specified in the EM&A Manual.

 

(a)        If no exceedance is recorded during the pilot test, then no further coral monitoring is required (except the ad hoc coral impact monitoring).

(b)        If during the pilot test an Action or Limit Level exceedance for any specific coral monitoring parameter is recorded, then the construction method and activities as well as the relevant water quality monitoring results shall be immediately reviewed to determine if the exceedances are due to the works.  If it is determined that the exceedances are due to the works, the grouting operation shall be suspended immediately.  Remedial action shall be taken before continuing the remaining grout mattress installation works.  The remedial action shall be certified by the ET Leader and verified by the IEC as conforming to the environmental performance assessment submitted with the application for variation of an Environmental Permit (Application No. VEP 211/2006).

 


Appendix D 

Environmental Monitoring and Audit (EM&A) for Grout Mattress Installation Works

 

 

Ad Hoc Impact Monitoring Triggered by An Accidental incident

 

Water Quality Monitoring

 

Ad hoc water quality impact monitoring shall be triggered when an accidental incident which may cause pollution to the marine environment occurs during the grout mattress installation works.  Different levels of monitoring will be conducted depending on whether it is a “Major” or “Minor” accidental incident as detailed in Appendix E.  Details of the ad hoc impact monitoring are as follows:

 

1. Parameters: suspended solids, turbidity and pH

2. Monitoring locations: 6 monitoring stations including WQI6, WQI7 (Impact), G6, G7 (Gradient), B1 and B3 (Control) as shown in Figure 3.2c in the EM&A Manual.  

 

3. Duration: 

(a) 1 day for a minor accidental incident (monitoring to be completed within 24 hours on notification of the accidental incident)

(b) 3 days for a major accidental incident (first day of monitoring to be completed within 24 hours on notification of the accidental incident)

 

4. Frequency:  During mid-flood and mid-ebb in each monitoring day

5. Other monitoring requirements: same as Sections 3.2.2, 3.2.3 and 3.2.4 of the EM&A Manual.

6. Reporting:  

      The monitoring results shall be submitted to EPD and AFCD in the following schedule:

(a)    Turbidity and pH data - within 24 hours after the monitoring results are recorded in the field.  

(b)    SS data - within 48 hours after the water samples are received by the testing laboratory.

 

7. Exceedance Levels: 

(a) SS and Turbidity: Action and Limit Levels for SS and turbidity applicable to Zone B (Table 2.3b of the Baseline Monitoring Report – Part B refers).

(b)  pH: Action Level is pH 8.4[1] and Limit Level is pH 8.5[2].  If bed layer pH at the impact station is higher than that at the gradient station, and/or if bed layer pH at the impact station is not greater than the control station, then the Action Level/Limit Level is not exceeded.

 

8. Event-Action Plan - If the Action or Limit Levels are exceeded, the Event-Action Plan stipulated in the EM&A Manual (Table 3.6) shall be followed.

 

Coral Monitoring

 

1.   Parameters: Same as the monitoring programme specified in Section 4 of the EM&A Manual.

 

2.   Monitoring locations: I6, I7 (Impact) and C1 (Control). 

 

3. Duration:

(a) 1 day for a minor accidental incident   (monitoring to be completed within 48 hours on notification of the accidental incident)

(b) 3 days for a major accidental incident  (first day of monitoring to be completed within 48 hours on notification of the accidental incident)

 

4.   Frequency: Daily  

 

5.   Monitoring method: Same as the monitoring programme specified in Section 4 of the EM&A Manual.

 

6.   Reporting: Results shall be sent to EPD and AFCD within 48 hours after completion of each day of coral survey 

 

7.   Exceedance Criteria: Same as those on the Coral Survey Proforma adopted for the coral monitoring programme specified in the EM&A Manual.

 

8. Event-Action Plan - If the Action or Limit Levels are exceeded, the Event-Action Plan stipulated in the EM&A Manual (Section 4.3) shall be followed.

 


 

Post Project Monitoring

 

Water Quality Monitoring

 

Post project water quality monitoring shall be conducted for one day within one week after the completion of grout mattress installation. All monitoring requirements shall be the same as those for the ad hoc water quality impact monitoring.

 

Coral Monitoring

 

Post project coral monitoring shall be conducted for one day within one week after the completion of grout mattress installation. All monitoring requirements shall be the same as those for the ad hoc coral monitoring.


Appendix E

Measure of Pollution Prevention and Control for Grout Mattress Installation Works

 

Release of grout materials to the marine environment is the major concern for the grout mattress installation works.  Measures and actions to prevent and minimise the potential pollution impacts are set out in the table below where:

(a)    Preventive Measures shall be fully and properly implemented; and

(b)    when an accidental incident occurs, Remedial Action/Mitigation Measures shall be taken/implemented.

 

It should be noted that neither the accidental incidents nor the actions/measures listed in the table are exhaustive.  Additional actions/measures, as agreed by the Director, may be taken/implemented where appropriate.

 

 

Accidental incident

Preventive Measure

Remedial Action/Mitigation Measure

Responsible Party  

A. General

 

 

 

Normal operations

Implement appropriate measures of pollution prevention and control

 

 

 

Occurrence of any major or minor accidental incidents

 

1. Notify EPD and the ET within 3 hours after the accidental incident occurs.

2. Take remedial actions and/or implement mitigation measures.

3. Conduct ad hoc impact monitoring for water quality and corals (see Appendix D for details).

4. If any Action or Limit Level exceedance is recorded, the Event-Action Plans for water quality and coral monitoring in the EM&A Manual should be followed (see Appendix D).

 

 

Contractor

 

Contractor

 

ET

 

Contractor and ET

B. Dry Grout Transportation

 

 

 

1.  Spillage of dry grout into the sea during transportation to the Derrick Light for storage (Major Event)

1. The grout will be transported in cloth bags of approximately 1 ton. These bags will be stored inside standard steel shipping containers and placed on a derrick barge next to the grouting barge.

 

 

1. Likelihood of dry grout spillage into the sea during transportation to the site is negligible and specific mitigation measure is not considered necessary.

2. If the dry grout is spilled into the sea,

a. Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

Contractor

 

 

 

 

ET

 

Contractor and ET

C. Loading and Mixing

 

 

 

1.   While in storage and during lifting, spillage of a whole bag (Major Event) or part of a burst bag (Minor Event) of dry grout into the sea may occur.

 

 

1. Storage and lifting of the grout bags will follow manufacturer/supplier recommendations.

2. The bags will only be moved out of the steel container when required by the grouting barge.

3. Grout bags will be inspected for damage before lifting.

4. The derrick lighter will lie along side of the grout barge and grout bags shall only be lifted over the barges (no lifting or swinging grout bags over water).

 

 

1. If any grout bags burst:

a. Stop lifting.

b. Store spilt materials in waste container.

c. Remove spilt materials for land disposal or recycling.

2. If dry grout is spilled into the sea,

a. Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

 

Contractor

 

 

 

 

 

ET

 

Contractor and ET

2.   Each grout bag is lifted by crane and placed over the hopper of the grout mixer. The base of the bag (funnel) is located within a chute on top of the hopper. There is a potential for the grout powder to be released and spill into the sea if the seal between the bottom of the bag and the top of the hopper is not tight. (Minor event)

1. During loading of the grout the seal between the bag and the silo will be first checked for tightness.

1. If leakage/spillage occurs:

a. Stop loading and check for cause.

b. Store spilt materials in waste container.

c. Remove spilt material for land disposal or recycling.

d. Check and repair seal.

2. If the dry grout is spilled into the sea,

a. Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

Contractor

 

 

 

 

 

 

ET

 

Contractor and ET

3. The grout is mixed in purpose built grout mixers (propriety equipment). There may be spillage into the sea during the mixing operation due to mechanical failure, improper maintenance and operational error. (Minor event)

 

 

1.  All grout mixing equipment will be set up within a bunded area of a suitable capacity (approximately 7.2m3) to contain the contents of the mixer. The grouting barge also has a sealed deck area to provide secondary spill containment.

2. The equipment will be operated and frequently checked by experienced operators.

3.  Ensure proper maintenance of equipment.

 

1. If leakage/spillage occurs:

a. Stop mixing and check for cause.

b. Deposit spilt material into waste storage tank.

c. Remove for land disposal or recycling.

2.  If the mixed grout is spilled into the sea:

a. Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

Contractor

 

 

 

 

ET

 

Contractor and ET

D. Grout Injection – Delivery Hose

 

 

 

Once mixed the wet grout is pumped by hydraulic pumps from a holding tank through a one-piece hose to the grout mattress.  Potential sources of leakage are:

 

1.   Leakage from pumping equipment 

      (Minor event)

1.  All grout pumping equipment will be set up within a bunded area of a suitable capacity  (approximately 7.2m3) to contain the contents of the mixer. The grouting barge also has a sealed deck area to provide secondary spill containment.

2.    Pumping equipment will be operated by experienced operator.

3.  Pump operation and the grout flow rate will be monitored for any indications of abnormalities.

4. Ensure proper maintenance of equipment.

 

1.  If the pump operation and flow rate indicate any abnormalities such as the amount of grout pumped per mattress exceeds the specified volume, then the pumping operation should stop immediately for leak checks and repair.

2.  If leakage/spillage occurs, all grouting operations should stop and any leaks in the equipment should be repaired before grouting starts again. 

3.  If any grout is spilled into the sea:

a. Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

 

Contractor

 

 

 

 

 

 

 

 

 

ET

 

Contractor and ET

2.   Leakage from delivery hose due to ruptured hose or loose connections

      (Minor event)

 

1.    The delivery hose will be a single continuous hose to minimize connections.

2. The delivery hose and all connections will be inspected for wear and tear prior to pumping commencing.

3. Protective device will be installed to prevent charged hose from chafing.

4.  Pump operation and the grout flow rate will be monitored for any indications of abnormalities.

5. A diver (with CCTV and radio) will be on station to observe the underwater pumping operation at all times for any indications of abnormalities.

1. If the pump operation and flow rate indicate any abnormalities such as the amount of grout pumped per mattress exceeds the specified volume, then the pumping operation should stop immediately for leak checks and repair.

2. If the diver observes any abnormalities such as leaks from the delivery hose or the mattress not being filled properly, the pumping operation should be stopped for checks and repairs.

3. If the delivery hose is ruptured, it should be wrapped with tape for temporary sealing, and then retrieved and replaced by an intact one.

4. If leakage occurs underwater:

a.         Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

 

Contractor

 

 

 

 

 

 

 

 

 

 

 

 

ET

 

Contractor and ET

3.   Leakage from delivery valve (diver held) due to valve malfunction or when connecting and disconnecting the hose with the mattress.

      (Minor event)

1.  The delivery valve at the bottom of the hose will only be opened after it is securely fixed inside the pre-installed grout mattress sleeve.

2.    The pumping will stop immediately when there appears to be a loss of grout at the bleed valve.

3.  The hose will only be disconnected and removed once the surface and delivery valve has been shut The hose will then be immediately removed from the mattress and the mattress sleeve sealed and securely tied.

4.  Pump operation and the grout flow rate will be monitored for any indications of abnormalities.

5. A diver (with CCTV and radio) will be on station to observe the underwater pumping operation at all times for any indications of abnormalities.

 

 

1. If the diver observes any abnormalities such as leaks from the delivery valve or that the mattress not being filled properly, the pumping operation should be stopped for checks and repairs.

2. If the pump operation and flow rate indicate any abnormalities such as the amount of grout pumped per mattress exceeds the specified volume, then the pumping operation should stop immediately for leak checks and repair.

3. If leakage from the valve occurs:

a.         Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

Contractor

 

 

 

 

 

 

 

 

 

ET

 

Contractor and ET

E. Grout Injection - Mattress

 

 

 

1.   During grouting there may be minor leakage from the mattress due to manufacturing defects, damage from handling or overfilling. (Minor event)

1. All mattresses are in palletized and containerized storage to prevent damage before use.

2. Every mattress will be checked for damage prior to placing it on the seabed.

3. Only trained and experienced operators will be allowed to handle the mattress.

4. The mattress will be frequently inspected while being filled underwater. 

5. The grouting operation will stop immediately when there appears to be a loss of grout at the bleed valve.

6. A diver (with CCTV and radio) will be on station to observe the underwater pumping operation at all times for any indications of abnormalities.

 

 

 

1. If leakage from the mattress occurs (except normal bleeding) grouting operation should be stopped.

2. Seal leak using Hessian sacking and/or tie wraps.

3. If leakage from the mattress occurs:

a.         Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

Contractor

 

 

 

 

 

ET

 

Contractor and ET

2.   During grouting the mattress may rupture due to manufacturing defect or damage from handling.

      (Major event)

1. All mattresses are in palletized and containerized storage to prevent damage before use.

2. Every mattress will be checked for damage prior to installation.

3. Only trained and experienced operators will be allowed to handle the mattress.

4. A diver (with CCTV and radio) will be on station to observe the underwater pumping operation at all times for any indications of abnormalities.

1. If the mattress ruptures and the grout released, stop grouting operation until grout material has cured sufficiently to allow close examination.

2. The mattress may be removed if necessary and the grouting process repeated with a new mattress.

3. If a grout filled mattress ruptures underwater:

a.         Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

 

Contractor

 

 

 

 

 

 

ET

 

Contractor and ET

F. Cleaning

 

 

 

1.   Once the grouting operation is complete the equipment (mixer and pump) must be cleaned. There is a potential for spillage of the washing from the cleaning. (Minor event)

1.  All surplus grout will be cleaned out and stored prior to disposal on shore.

2.    All grouting equipment (including hoses) will be cleaned within the bunded area. All cleaning water will be collected and pumped to storage tanks for later disposal onshore.

1. If spillage occurs:

a. Clean up spillage

b. Repair any leaks of the bund.

2. If the washing is spilled into the sea:

a.         Ad hoc impact monitoring should be conducted.

b. If any Action or Limit Level exceedance is recorded, the Event-Action Plan in the EM&A Manual will be followed.

 

Contractor

 

 

 

ET

 

Contractor and ET


Appendix F

 

Method Statement for Grout Mattress Installation Works

 

 

A short section (about 200 m; Figure 1) of the pipelines located in an area with oyster shell deposits as well as the transition zones flanking the deposits will be protected by grout mattresses instead of armour rock. The marine works are expected to take approximately 30 days. Details of the proposed method are presented below.

 

1. Grout Material

 

SikaGrout-214XP, a premixed cementitious grout containing Portland cement, silica sands and additives, will be used to fill the mattresses being laid onto the pipelines. This inorganic based material is non-biodegradable and no hazardous decomposition products are known. It has a low order of acute toxicity, and is expected to be non-hazardous to aquatic species and non-bioaccumulated.

 

2. Mattress

 

The mattresses to be grout-filled are provided by ULO Systems LLC. They are made of woven fabrics permeable to water but allowing only insignificant amount of fines to pass through. Each mattress holds a volume of 4.8 m3 (about 9.1 ton of grout) and is pre-installed with a self-sealing injection point which will be secured with 300 mm cable ties as an added safety measure. Along the pipelines adjoining mattresses will be laid to protect the specified section of the alignment. 

 

3. Barges

 

Two barges are required for the grout mattress installation, one derrick lighter for storage of grout and installation of mattresses.  The other vessel is a flat top barge for grouting operation. The two barges will operate within an exclusion zone surrounding the section of pipeline alignment to be covered by grout mattresses.

 

4. Procedures

 

4.1 Installation of Mattresses

 

a.     Survey of Pipeline - Surface marker buoys will be deployed under the instruction of the Surveyor to mark the pipeline and the transition.  A centerline laid by divers will be used to orientate the divers during the installation of the mattresses.

 

b.     Surface Preparation - The grout mattresses will be assembled into a steel frame on the Mattress Barge prior to lifting into their approximate position using the Derrick.  Final position will be confirmed by the Surveyor.

 

c.     Diver Installation - The diver will orientate the Frame along the centerline and if required will probe for the pipeline using a steel rod (1m) attached to the frame.  Once in position the diver will release the mattress sections and secure them to the seabed using steel pins and/or anchors.  The lifting frame will be recovered to the Mattress Barge and the process will be repeated until all of the mattresses have been laid.

 

4.2  Grout Injection

 

a.     Surface Preparation - The Batching Plant operators will prepare the grout mix in accordance with the Manufacturers Specifications.  The injection will be through 50 mm hoses tendered by divers.  The Diver shall control the flow of grout by verbal instructions to the Dive Supervisor who relay them to the Grout Pump Operator.  The advised maximum pump flow rate is no greater than one cubic metre per ten minutes.  (1m³/10 mins max)

 

b.     Diver Injection - The Diver will purge the hose of water prior to inserting the hose into sleeves pre-installed into the mattress.  The grouting process will continue until small amount of good grout is expelled from a bleed point pre-installed on the mattress.  The Diver will then stop the flow of grout and withdraw the hose from the sleeve.  The sleeves will then be twisted and secured using 300 mm nylon cable ties. On completion of the injection of one section the diver will repeat the procedure until all sections have been completed. Up to two mattresses can be injected using two pumps with divers working independently. In general the grout has initial setting time within 2-3 hours and cured in 24 hours to 32MPa.

 

4.3 Configuration of Grout Mattress Protected Pipeline

 

Figure 6 shows the general configuration of the grout mattress protected pipelines over the oyster bed (Section A) and that in the transition zones (Section B), respectively. For Section A, the grout mattress covered pipelines will be buried by about 0-100 mm of natural backfill. For Section B, the protected pipelines will be covered by natural backfill to an average depth of 1.2 m. The pipeline profile over the general oyster area is also delineated in Figure 6.

 

 


| Figure1| | FigureA1| Figure2| | FigureA2| Figure3| | Figure4| Figure5| Figure6|


 

[ Back to First Page ] / [ Back to Main Index ]