Environmental
Permit No. EP-136/2002/B
環境許可證編號
EP-136/2002/B
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10及13條
ENVIRONMENTAL PERMIT TO DECOMMISSION
A DESIGNATED PROJECT
解除運作指定工程項目的環境許可證
PART A (MAIN
PERMIT)
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (the EIAO), the Director of Environmental Protection (the
Director) grants the environmental permit (EP-136/2002) to the Civil
Engineering and Development Department (formerly known as the Civil
Engineering Department and hereinafter referred to as the “Permit Holder”) on
22 May 2002. Pursuant to Section
13 of the EIAO, the Director amends the Environmental Permit based on the
Application No. VEP-239/2007. The
amendments, described below, are incorporated into this Environmental Permit
(EP-136/2002/B). This
Environmental Permit as amended is for the decommission of the designated
project described in Part B subject to the
conditions specified in Part C.
The issue of this environmental permit is based on
the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)於2002年5月22日將環境許可證(編號EP-136/2002)批予土木工程拓展署
(前稱土木工程署,下稱“許可證持有人”)。根據環評條例第13條的規定,署長因應更改環境許可證的申請編號VEP-239/2007修訂環境許可證。以下修訂已包含在本環境許可證內(編號EP-136/2002/B)。本經修訂的環境許可證作為解除運作本許可證B部所說明的指定工程項目,但須遵守C部所列明的條件。
本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:
Application No. 申請書編號 |
VEP-239/2007 |
Document in the Register : 登記冊上的文件: |
(1) Environmental
Impact Assessment – Demolition of Buildings and Structures in the Proposed
Kennedy Town Comprehensive Development Area Site : Final EIA Report, EM&A
Manual and Executive Summary (Register No.: AEIAR-058/2002) [Hereinafter
referred to as “the EIA Report”] (1) 堅尼地城綜合發展區拆卸工程 環境影響評估 :
最終環境影響評估報告, 環境監察及審核手冊 及 行政摘要 (登記冊編號:AEIAR-058/2002)
[下稱“環評報告”] (2)
The Director’s letter of approval of the EIA
Report dated 16 April 2002, ref: EP2/H1/KT/PT2/85 Ax 1 (2) 環境保護署署長於2002年4月16日發出批准環評報告的信件
(檔案編號: EP2/H1/KT/PT2/85 Ax 1) |
|
(3) Application
for an Environmental Permit No. AEP-136/2002 received on 24 April 2002 (3) 於2002年4月24日收到的環境許可證申請文件編號AEP-136/2002 (4) Environmental
Permit issued on 22 May 2002 (Permit No. EP-136/2002) (4) 於2002年5月22日簽發的環境許可證
(許可證編號EP-136/2002) (5) Application
documents for Variation of Environmental Permit including all attachments
submitted by the Permit Holder on 4 April 2007 (Application No. VEP-234/2007) (5) 許可證持有人於2007年4月4日提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-234/2007) (6) Application
documents for Variation of Environmental Permit including all attachments
submitted by the Permit Holder on 27 September 2007 (Application No. VEP-239/2007) (6)
許可證持有人於2007年9月27日提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-239/2007) |
Application No. 申請書編號 |
Date of Application 申請日期 |
List of Amendments Incorporated into this
Environmental Permit 已包含在本環境許可證內的修訂項目 |
Date of Amendment 修訂日期 |
VEP-234/2007 |
4 April 2007 2007年4月4日 |
Add a
new condition before each of the following conditions in Part C of Environmental
Permit No. EP-136/2002: Conditions
1.8, 1.12, 1.13 and 2.5. 在環境許可證編號EP-136/2002 C部第1.8, 1.12, 1.13 和2.5 項條件前各加入一項新的條件。 Vary
Conditions 1.7, 1.11, 1.14, 2.3, 2.4, 2.5 and 2.7 in Part C of Environmental
Permit No. EP-136/2002. 更改環境許可證編號EP-136/2002 C部第1.7, 1.11, 1.14,
2.3, 2.4, 2.5 和 2.7 項條件。 Renumber
the permit conditions in Part C of the Environmental Permit No. EP-136/2002/A
where appropriate. 把環境許可證編號EP-136/2002/A C部的條件適當地重新編號。 Renumber
Figure 2 and Figure 3 to Figure 7 and Figure 6 respectively. 把圖2和圖3依序重新編號為圖7和圖6。 Add 4
new figures and numbered as Figures 2 to 5. 加入4張新的圖並編號為圖2至圖5。 |
30 April 2007 2007年4月30日 |
VEP-239/2007 |
27 Sep 2007 2007年9月27日 |
Amend
Phase 1 Part 1 Project Boundary to align with curb line at northern end of Sai
See Street. Amend Figures 2 and 3 accordingly. 沿西市街北端路邊更改第一階段工程範圍。
相應地更改圖2和圖3。 |
18
Oct 2007 2007年10月18日 |
18 October 2007 2007年10月18日 |
|
|
|
Date 日期 |
|
(Mrs. Shirley LEE) Principal Environmental Protection Officer for the Director of Environmental Protection 環境保護署署長 (首席環境保護主任李韓琇玲代行) |
|
PART B (DESCRIPTIONS OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project
mentioned in Part A of this environmental permit
(hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱 “許可證”)A部所提述的指定工程項目的說明:
Title of Designated Projects 指定工程項目的名稱 |
Demolition of Buildings
and Structures in the Proposed Kennedy Town Comprehensive Development Area
Site [The above designated projects are hereinafter referred to
as “the Project”] 堅尼地城綜合發展區拆卸工程 [上列指定工程項目下稱“工程項目”] |
Nature of
Designated Projects |
Decommissioning of a municipal incinerator 解除一個市政焚化爐的運作 |
Location of Designated Projects 指定工程項目的地點 |
Kennedy
Town. The location of the
Project is shown on Figure 1 attached
to this Permit. 堅尼地城。工程項目的地點如本環境許可證的圖1所示。 |
Scale and Scope of Designated Project(s) 指定工程項目的規模和範圍 |
Decommissioning of a municipal incinerator,
including demolition of the existing chimneys, buildings and structures in
the proposed Kennedy Town Comprehensive Development Area site of about 3.4
ha. where the existing incinerator locates, remediation of contaminated soil
and wastes within the site, and subsequent disposal of the remediated soil
and wastes. 解除一個市政焚化爐的運作,包括拆卸該焚化爐所在地面積約3.4公頃的 「堅尼地城綜合發展區」內現有的煙囪、大樓及建築物,整治及處置污染了的土壤及物料。 |
PART C (PERMIT CONDITIONS)
1. General
Conditions
1.1 The
Permit Holder and any person working on the Project shall comply with all
conditions set out in this Permit.
Any non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap.499) and may become the subject
of appropriate action being taken under the Ordinance.
1.2
The Permit Holder shall
ensure full compliance with all legislation from time to time in force
including without limitation the Noise Control Ordinance (Cap. 400), Air
Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap.
358), Waste Disposal Ordinance (Cap. 354), Occupational Safety and Health
Ordinance (Cap. 509) and Factories and Industrial Undertakings Ordinance (Cap. 59). This Permit does not of itself
constitute any ground of defense against any proceedings instituted under any
legislation.
1.3
The Permit Holder shall
make copies of this Permit together with all documents referred to in this
Permit or the documents referred to in Part A of the
Permit readily available at all times for inspection by the Director or his
authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall
include all documents referred to in the Permit and also the relevant documents
in the Register.
1.4
The Permit Holder shall
give a copy of this Permit to the person(s) in charge of the site and ensure
that such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The site
refers to the site of the Project and should mean the same hereinafter.
1.5
The Permit Holder shall
display conspicuously a copy of this Permit on the site at all vehicular site
entrances/exits or at a convenient location for public’s information at all
times. The Permit Holder shall
ensure that the most updated information about the Permit, including any
amended Permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the
Permit, the notice he sends to the Director shall also be displayed at the same
locations as the original Permit.
The suspended, varied or cancelled Permit shall be removed from display
at the site.
1.6
The Permit Holder shall
carry out the Project as described in Part B of this
Permit.
1.7
The Permit Holder shall
ensure that the Project is designed and implemented in accordance with the
information and recommendations described in the EIA Report (Register No.
AEIAR-058/2002); the Application for
Environmental Permit (Application No. AEP-136/2002) received on 24 April
2002, the Application for
Variation of Environmental Permit including all attachments submitted by the
Permit Holder on 4 April 2007 (Application No. VEP-234/2007), other relevant
documents in the Register; and the information or mitigation measures described
in this Permit, or mitigation measures to be recommended in submissions that
shall be deposited with or approved by the Director as a result of permit
conditions contained in this Permit, or mitigation measures to be recommended
under on going surveillance and monitoring activities during all stages of the
Project. Where recommendations
referred to in the documents of the Register are not expressly referred to in
this Permit, such recommendations are nevertheless to be implemented unless
expressly excluded or impliedly amended in this Permit.
1.8
The Project shall be
implemented in two Phases, with Phase 1 containing 2 Parts, as described in
detail in Condition 2.5 of this Permit.
A tentative programme for the Project was set out in the Application No.
VEP-234/2007.
1.9
All submissions as
required under this Permit, shall be rectified and resubmitted in accordance
with the comments, if any, made by the Director, within one month of the
receipt of the Director’s comments or otherwise specified by the Director.
1.10
All submissions approved
by the Director, all submissions deposited without comments by the Director, or
all submissions rectified in accordance with comments by the Director under
this Permit shall be construed as part of the permit conditions described in Part C of this Permit.
Any variation of the submissions shall be approved by the Director in
writing or as prescribed in the relevant permit conditions. All submissions or any variations of
the submissions made after the establishment of an Environmental Team (ET) and
employment of an Independent Environmental Checker (IEC) referred to in
Conditions 2.1 and 2.2 below shall be certified by the ET Leader and verified
by the IEC before submitting to the Director under this Permit.
1.11
The Permit Holder shall
release all finalized submissions, as required under this Permit, to the public
by depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any other means as specified by the Director for public
inspection. For this purpose, the
Permit Holder shall provide sufficient copies of the submissions.
1.12
The Permit Holder shall
notify the Director in writing the commencement dates of the three different
phases of the Project: (a) Phase 1 Part 1, (b) Phase 1 Part 2 and (c) Phase 2
of the Project at least one month prior to the commencement of each of the
above three different phases of the Project respectively. The Permit Holder
shall notify the Director in writing immediately if there is any change of any
of the commencement dates. Unless
specified otherwise, the commencement of the Project shall be taken to mean the
commencement of the Phase 1 Part 1 of the Project.
1.13
The Permit Holder shall
notify the Director in writing the completion dates of all three different
phases of the Project: (a) Phase 1 Part 1, (b) Phase 1 Part 2 and (c) Phase 2
of the Project within one month of the completion of each of the above three
different phases of the Project respectively.
1.14
The Permit Holder shall
notify the Director in writing the date of handing over the site, or any part
of the site, to any other party for the purpose of redevelopment of the area at
least one month prior to the handing over of the area. The Permit Holder shall notify the
Director in writing immediately if there is any change of the handing over
date.
1.15
The Permit Holder shall
notify the Director in writing the commencement date for temporarily using the
site, or any part of the site, for the purpose as described in Condition 2.5(h)
at least one month prior to the commencement of temporary use of the area. The Permit Holder shall notify the
Director in writing immediately if there is any change of the commencement date
for such temporary use.
1.16
All submissions to the
Director required under this Permit shall be delivered either in person or by
registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF)
(version 4.0 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies.
1.17
For the purpose of this
Permit, “commencement of each Phase and/or each Part of a Phase of the Project”
does not include works related to site investigation, contamination
confirmatory investigation, or other works as agreed by the Director. Any damage to the existing concrete
ground slab caused by site investigation, contamination confirmatory
investigation, or other works as agreed by the Director shall be repaired as
soon as practicable such that the structural integrity of the existing concrete
ground slab is maintained so as to avoid exposing the soil underneath as far as
practicable.
2.
Special Conditions
2.1
An Environmental Team (ET)
shall be established by the Permit Holder no later than one month before the
commencement of the Project. The ET shall be headed by an ET Leader. The ET
Leader shall be a person who has at least 7 years' experience in environmental
monitoring and auditing (EM&A) or environmental management. The ET and the
ET Leader shall be responsible for the duties defined in the EM&A Manual of
the EIA Report (Register No. AEIAR-058/2002). The ET Leader shall be
responsible for the implementation of the EM&A programme in accordance with
the EM&A requirements as contained in the EM&A Manual. The ET Leader
shall keep a contemporaneous log-book of each and every instance or
circumstance or change of circumstances which may affect the environmental
impact assessment and each and every non-compliance with the recommendations of
the EIA Report (Register No. AEIAR-058/2002) or this Permit. This log-book
shall be kept readily available for inspection by all persons assisting in
supervision of the implementation of the EIA Report recommendations and this
Permit or by the Director or his authorized officers. Failure to maintain
records in the log-book, failure to discharge the duties of the ET Leader as
defined in the EM&A Manual or failure to comply with this Condition would
entitle the Director to require the Permit Holder by notice in writing to
replace the ET Leader. Failure by the Permit Holder to make replacement, or
further failure to keep contemporaneous records in the log-book despite the
employment of a new ET Leader may render the Permit liable to suspension,
cancellation or variation. The ET shall not be in any way an associated body of
the Contractor or the IEC for the Project.
2.2
An Independent
Environmental Checker (IEC) shall be employed by the Permit Holder no later
than one month before the commencement of the Project. The IEC shall be a person who has at
least 7 years' experience in environmental monitoring and audit (EM&A) or
environmental management. The IEC
shall be responsible for the duties defined in the EM&A Manual of the EIA
Report (Register No. AEIAR-058/2002), and shall audit the overall EM&A
programme described in the EIA Report (Register No. AEIAR-058/2002), including
the implementation of all environmental mitigation measures, submissions
required in the EM&A Manual, and any other submissions required under this
Permit. In addition, the IEC shall
be responsible for verifying the environmental acceptability of permanent and
temporary works, relevant design plans and submissions under this Permit. The IEC shall verify the log-book(s)
mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by fax, within 24 hours of
each and every occurrence, change of circumstances or non-compliance with the
EIA Report (Register No. AEIAR-058/2002) or this Permit, which might affect the
monitoring or control of adverse environmental impact. Where the IEC fails to so notify the
Director of the same, fails to discharge the duties of the IEC as defined in
the EM&A Manual or fails to comply with this Condition, the Director may
require the Permit Holder by notice in writing to replace the IEC. Failure to
replace the IEC as directed or further failure to so notify the Director
despite employment of a new IEC may render the Permit liable to suspension,
cancellation or variation.
Notification by the Permit Holder is the same as notification by the IEC
for the purpose of this Condition. The IEC shall not be in any way an
associated body of the Contractor or the Environmental Team for the Project.
2.3
All submissions for
approval and deposition under Conditions 2.5, 2.7, 2.13(b), 2.15(b), 2.17, 3.4
and 3.5 of this Permit shall be verified and certified by the IEC as conforming
to the information and recommendations contained in the EIA Report and the
approved Waste Management Plan before submission to the Director.
2.4
The Permit Holder shall,
within one month after the commencement of each Phase and each Part of a
Phase of the Project, inform the Director in writing of the management
organization of the main companies and/or any form of joint ventures associated
with the carrying out of the Project. The submitted information shall include
at least an organization chart, names of responsible persons including the ET
Leader and the IEC, and their contact details. The different phases or part of a Phase are defined under
Condition 2.5 of this Permit.
Phased Approach for Implementing the Project and
Implementation Requirements
2.5
The Project shall be
implemented in two Phases with the following conditions.
Phase 1 Part 1
(a)
The Site area for both
Part 1 and Part 2 of Phase 1 of the Project is shown in Figure 2 of this Permit. At the time of notification of
commencement of Phase 1 Part 1 of the Project as required under Condition 1.12,
the Permit Holder shall deposit with the Director an updated Project programme,
to be accompanied by layout plans with detailed descriptions and drawings of
mitigation measures in scale of 1:1000 or in other suitable scale as agreed by
the Director, showing clearly the relevant works in Phase 1 Part 1 of the
Project.
(b)
Phase 1 Part 1 of the
Project includes demolition and clearance of all existing chimneys, buildings
and ancillary structures above the existing concrete ground slab in the Phase 1
Site area where the former Kennedy Town Incinerator Plant (KTIP) and the
Kennedy Town Abattoir (KTA) are located, and the demolition and clearance of
existing piers on the waterfront adjacent to the KTIP and KTA. The Phase 1 Part 1 also includes the
removal of asbestos containing materials and dioxin/furan contaminated wastes
within the Phase 1 Site.
(c)
Hoardings shall be erected
around the Phase 1 Site at the commencement of Phase 1 Part 1 of the Project
and shall be properly maintained throughout Phase 1 of the Project to restrict
access of the Phase 1 Site to only authorized site staffs and workers.
(d)
Throughout Phase 1 Part 1,
the existing concrete ground slab within the Phase 1 Site shall not be
demolished but shall be retained intact as far as practicable. Before completion of the Phase 1 Part 1
of the Project, inspection shall be carried out on the condition of the
existing concrete ground slab and existing drainage system with the view to
identify and repair any surface cracks such that their structural integrity is
maintained to avoid exposing the soil underneath as far as practicable. Such inspection and repair shall be carried
out every month thereafter until the commencement of Phase 1 Part 2 of the
Project. Where the inspection and
repair work fall within the reporting month of the monthly Environmental
Monitoring & Audit (EM&A) report described under Condition 3.5 of this
Permit, the inspection findings and repair work carried out shall be reported
in that monthly EM&A report.
(e)
With the exception of
drainage facilities required for the proper function of the site drainage
system, the existing underground facilities such as refuse bunkers, lift pits,
underground chambers and openings, and sub-sided areas within the Phase 1 Site
area shall be cleaned up and backfilled with clean soil to about 130 mm from
the top level of adjacent ground slab.
A layer of concrete cover of not less than 130 mm thickness shall then
be laid on top of the clean soil to fill up the underground facilities such
that the top level of the concrete cover on top of the clean soil above the
underground facilities matches the top level of adjacent ground slab. Before
completion of the Phase 1 Part 1 of the Project, inspection shall be carried
out on the condition of the concrete covers and existing drainage facilities
retained for the proper function of the site drainage system, with the view to
identify and repair any surface cracks such that their structural integrity is
maintained to avoid exposing the soil underneath as far as practicable. Such inspection and repair shall be
carried out every month thereafter until the commencement of Phase 1 Part 2 of
the Project. Where the inspection
and repair work fall within the reporting month of the monthly Environmental
Monitoring & Audit (EM&A) report described under Condition 3.5 of this
Permit, the inspection findings and repair work carried out shall be reported
in that monthly EM&A report.
(f)
Phase 1 Part 1 of the
Project shall not involve any excavation work that may disturb or expose any
part of the soil underneath the existing concrete slab.
Phase 1 Part 2
(g)
At the time of
notification of commencement of Phase 1 Part 2 of the Project as required under
Condition 1.12, the Permit Holder shall deposit with the Director a detailed
updated Project programme, to be accompanied by layout plans with detailed
descriptions and drawings of mitigation measures in scale of 1:1000 or in other
suitable scale as agreed by the Director, showing clearly the relevant works in
Phase 1 Part 2 of the Project. The
Project shall be implemented according to the updated programme.
(h)
Phase 1 Part 2 of the
Project includes the temporary use of the Phase 1 Site as site office and for
the storage of common construction materials, the provision of mitigation
measures to avoid any potential release of additional underground contaminants
into the environment resulting from the above temporary use of the site, and
the provision of mitigation measures to avoid impacts on workers on Phase 1
Site and the general public nearby, including residents and passers-by. It also includes the removal of temporary
site office and facilities for the storage of common construction materials
before completion of the Phase 1 Part 2.
(i)
Under Phase 1 Part 2 of
the Project, the Permit Holder shall not use or carry out any activity in the
Phase 1 Site other than the site office and storage of common construction materials
as proposed.
(j)
At locations within the
Phase 1 Site area identified to be temporarily used as site office and for
storage of common construction materials, an additional concrete paving of not
less than 200 mm thickness shall be provided. The indicative extent of this additional concrete paving, as
extracted from the Application No. VEP-234/2007, is shown in Figure 3 of this Permit.
(k)
No temporary use, to
include site office and storage of common construction material, at the Phase 1
Site shall be allowed until Remediation Report(s) has been deposited with the
Director in accordance with Condition 2.17 below after the completion of
the remediation and disposal of dioxin/furan contaminated wastes at specific
site areas proposed for temporary use.
(l)
No temporary use, to
include site office and storage of common construction material, at the Phase 1
Site shall be allowed until the identified locations for such temporary uses
have been provided with the pre-requisite additional concrete paving as
stipulated in Condition 2.5(j) above.
(m)
Throughout the entire
period of Phase 1 Part 2, the additional concrete paving to avoid exposing the
contaminated soil underneath shall remain intact and shall not be
demolished. Within 7 days, and
every month thereafter, of the start of use of the Site for temporary site
office and/or storage of common construction materials, inspection shall be
carried out on the condition of the additional concrete paving, the site
drainage and the foul sewerage systems to identify, with the view to
repair/remedy any surface cracks such that the structural integrity of these
systems is maintained and the soil underneath will not be disturbed or exposed
as far as practicable.
(n)
To allow natural air
dispersion of any entrapped vapour contaminants that might be released from the
soil and groundwater, the site office to be erected in the Phase 1 Site shall
be properly designed and constructed to create and maintain a clear void of at
least 500 mm height between the underside of the site office floor and the top
of the additional concrete paving below.
The indicative design is shown in Figure
4 of this Permit.
(o)
To further safeguard
against seepage of any vapour contaminants into site offices from the soil and
groundwater, the site office to be erected in the Phase 1 Site shall be
properly designed and constructed to incorporate gas-resistant membranes
flooring. The indicative design is
shown in Figure 4 of this Permit.
(p)
Phase 1 Part 2 of the
Project, including any additional site drainage and/or foul sewerage works,
shall not involve any excavation work that may disturb or expose any part of
the soil underneath the existing concrete slab and the additional concrete
paving.
Phase 2
(q)
The Phase 2 Site area is
shown in Figure 5 of this
Permit. Phase 2 of the Project
shall commence as soon as practicable after the completion of all Phase 1 Part
2 works and shall not be delayed.
Phase 2 of the Project shall comprise the demolition of the additional
concrete paving described above to allow temporary use as site office and
storage of common construction material, demolition of existing concrete ground
slab, demolition of any additional site drainage and/or foul sewerage works,
demolition of the existing Cadogan Street Temporary Garden, refuse collection
point, bus depot and public car park.
Phase 2 of the Project shall also include remediation and subsequent
disposal of contaminated soil below ground level within the Phase 2 Site area.
Contamination Confirmatory Investigation
2.6
To cater for the phased
approach for implementing the Project, a proposal on the contamination
confirmatory investigation (CCI) shall be submitted, before the commencement of
the Project, to the Director for approval. The Permit Holder shall agree with
the Director the timing for submitting the CCI proposal. The CCI proposal shall provide details
of the CCI programme to tie in, in terms of the timing and location, with each
Phase and each Part of a Phase of the Project. The CCI programme shall state the
timing for submission of the CCI findings, review of the waste treatment and
disposal method, and preparation and submission of the Waste Management Plan
taking into account relevant CCI findings as required under Condition 2.7. The CCI shall provide further
information on the extent of contamination at the Investigation Areas A, B, C
and D shown in Figure
6 of this Permit in addition
to those assessed in the EIA Report (Register No. AEIAR-058/2002). Six hard copies and one electronic copy
of the relevant findings of the CCI shall be deposited with the Director before
the commencement of each Phase of the Project.
Submission of Waste Management Plan
2.8
The WMP shall include, but
not limited to, the following information for each type of the wastes relevant to the specific Project Phase/Part
that it is intended to cover. The
types of wastes to be covered should include asbestos containing materials,
dioxin/furan contaminated wastes, contaminated soil, and construction and
demolition materials.
(a)
summary of the locational
sources, quantity, level of contamination (if applicable), remediation required
prior to disposal (if applicable), and on-site and off-site disposal methods
for different type of wastes;
(b)
timings for generation,
remediation (if applicable), temporary on-site stockpiling or storage, and
final on-site or off-site disposal of different type of wastes;
(c)
timings for conducting the
pilot tests as required under Conditions 2.13(a) and 2.15(a) as appropriate;
(d)
method statements on the
remediation works to be carried out on different types of contaminated soil and
wastes, and the confirmatory and parallel independent testing to be conducted;
(e)
on-site waste management
measures to control nuisances during the generation, handling, remediation (if
applicable), and temporary stockpiling of the different types of wastes, in
particular for asbestos containing materials, dioxin/furan contaminated wastes
and contaminated soil;
(f)
possible recycling and
reuse of materials;
(g)
location of the disposal
site(s) for various types of wastes;
(h)
confirmation on whether or
not barges would be used for removal of wastes;
(i)
transportation routing(s)
of the removal of various types of wastes from the project site to the disposal
site(s);
(j)
measures to control
nuisances due to transportation of different type of wastes, in particular to
avoid loss of asbestos containing materials, dioxin/furan contaminated wastes
and contaminated soil; to remove possible soil left on the first several
hundred meters of roads by vehicles leaving the site, such as the option of
using specially design road cleansing vehicle; and to reduce dust nuisance from
trucks carrying wastes, such as the option of installing mechanical covers to
trucks;
(k)
trip-ticket system for
waste transfer/disposal operations, including a certification system to confirm
to the disposal site’s operator that the contaminated wastes have been
remediated to meet the specific disposal criteria; and
(l)
responsibilities for
implementation.
2.9
All the measures recommended
in the approved WMP shall be fully implemented in accordance with the
requirements and time schedule(s) set out in the WMP.
2.10
Before obtaining the
Director’s approval on the WMP as required under Condition 2.6, no disposal of
waste, spoil, soil, excavation materials or materials obtained from the Project
site shall be allowed at any locations.
Control on
Demolition
2.11
Non-blasting methods shall
be used for the demolition of all structures within the project site boundary including
buildings and chimneys.
2.12
All Asbestos Containing
Materials (ACM) shall be removed prior to commencement of demolition works
except for those ACM removal works that are constrained by access and have to
be handled while the demolition work progresses.
Remediation and Disposal of Wastes contaminated by
Dioxins and/or Furans
2.13
Treatment and disposal of
wastes contaminated with dioxins and/or furans as identified in Appendix A of this permit and in the CCI findings
shall be carried out in accordance with the approved WMP and shall include the
following steps:
(a)
conduct pilot mixing and
Toxicity Characteristic Leachate Procedures (TCLP) tests for the contaminated
wastes to verify the effectiveness of the mix and establish the necessary
cement to wastes ratio for the purpose of compliance with the 1 part per
billion toxicity equivalent (1 ppb TEQ) TCLP criteria;
(b)
inform the Director the
results of the pilot tests for confirmation of the disposal site. If the pilot tests identify that some
of the contaminated wastes would need to be disposed of as Chemical Wastes, the
fallback option to be adopted to dispose of the Chemical Wastes and the
associated method statements shall be provided together with the results of the
pilot tests;
(c)
treat the contaminated
wastes by mixing with cement;
(d)
seal the treated wastes
into steel drums lined with plastic sheeting after passing the TCLP test as
stated in Appendix B of this
Permit. Duplicate samples of the
treated wastes may need to be collected for parallel testing by another qualified
laboratory if requested by the Director; and
(e)
dispose of the drummed
material in Condition 2.13(d) above to a Government landfill agreed by the
Director under Condition 2.13(b) above.
2.14
Testing shall be conducted
on samples taken from any materials left on the North, South, East, West and
underneath of the removed materials to confirm that all contaminated materials
failing to meet the criteria of 1 ppb TEQ have been removed for treatment. Duplicate samples of the materials may
need to be collected for parallel testing by another qualified laboratory if
requested by the Director.
Remediation and Disposal of Soil Contaminated with
Heavy Metal and/or Hydrocarbons
2.15
Remediation for
contaminated soil identified in Appendix A
of this permit and in the CCI findings shall be carried out in accordance with
the approved WMP and shall include the following steps:
(a)
conduct pilot mixing and
Toxicity Characteristic Leachate Procedures (TCLP) tests for the contaminated
soil to verify the effectiveness of the mix to establish the necessary cement
to soil ratio for the purpose of compliance with the criteria stated in Appendix B of this permit;
(b)
inform the Director the
results of the pilot tests for confirmation of the disposal site;
(c)
soil contaminated with
heavy metal shall be treated by mixing with cement and reused on site after
passing the TCLP test as stated in Appendix B
of this Permit. Duplicate samples of the treated soil may need to be collected
for parallel testing by another qualified laboratory if requested by the
Director;
(d) soil contaminated with petroleum hydrocarbons and/or
polynuclear aromatic hydrocarbons shall be disposed of at a Government landfill
agreed by the Director after passing the TCLP test as stated in Appendix B of this permit. If the contaminated soil fails the
tests, they shall be treated by mixing with cement and subsequently tested to
have passed the TCLP tests before disposed of at the agreed landfill. Duplicate samples of the treated soil
may need to be collected for parallel testing by another qualified laboratory
if requested by the Director; and
2.16
Testing shall be conducted
on soil samples taken from the North, South, East, West face of the excavated
holes, and at the base of the holes to confirm that all contaminated soil
failing to meet the “Dutch B levels” have been removed for treatment. (The “Dutch B” Levels are shown in
Appendix IV of ProPECC PN 3/94 which is also attached at Appendix C of this Permit for ease of
reference.) Duplicate samples of
the soil may need to be collected for parallel testing by another qualified
laboratory if requested by the Director.
Submission of
Remediation Report(s)
2.17
Six hard copies and one
electronic copy of Remediation Report(s) shall be deposited with the Director
after the completion of the remediation and disposal of contaminated soil and
wastes at specific site areas. The
Remediation Report(s) shall demonstrate that the remediation and disposal work
for the site area that it covers has been undertaken according to the specified
methodology and has been shown to be adequate. The Remediation Report(s) shall be submitted at least four
weeks before the concerned area is handed over to other parties for
redevelopment of the site. The
Remediation Report for works covered in Phase 1 Part 1 of the Project shall be
submitted at least four weeks before commencement of Phase 1 Part 2 of the
Project.
Mitigation Measures to prevent Nuisances
2.18
Mitigation measures shall
be implemented to prevent pollution, control nuisances, and reduce risk during
the remediation phases, in accordance with the EIA Report (Register No.
AEIAR-058/2002), including but not limited to the following:
(a)
Storage and treatment
operations on the disturbed contaminated soil, wastes, and remediated wastes
prior to their disposal off-site shall be carried out in a covered area with
paved floor bounded by a continuous and impermeable concrete bund of at least
20 cm high to control run-off.
This condition does not apply to storage of remediated soil which has
passed the TCLP test and are intended to be reused on site as stated in
Condition 2.15(c);
(b)
if groundwater extraction
is necessary as part of the work, it shall be collected and reused on site, in particular
for treatment operations on contaminated soil and wastes. If there is any surplus groundwater
required to be discharged after site usage, the Permit Holder shall obtain
prior consent from the Director; and
(c)
mitigation measures
proposed in the WMP and approved under Condition 2.7 to control
nuisances associated with on-site handling and off-site transportation of the
contaminated soil and wastes shall be implemented.
2.19
Mitigation measures shall
be implemented to prevent other demolition related nuisances throughout the
demolition and remediation phases, in accordance with the EIA Report (Register
No. AEIAR-058/2002), including but not limited to the following:
(a)
provide boundary hoarding
of height not less than 5.5 meters measured from street level modified to
perimeter noise barrier form, and made of panels with superficial surface
density not less than 10 kg/m2;
(b)
provide moveable noise
barriers close to powered mechanical equipment (PME) in cases where, in the
opinion of the ET leader, IEC or the Director, such PME has the potential to
cause excessive noise nuisance to sensitive receivers and where a benefit will
result from providing the barriers;
(c)
if necessary, in addition
to the Conditions 2.19(a) and (b), modify continuous operational periods for
noisy plant or take other measures to comply with the construction noise
criteria;
(d)
use adequately designed
and maintained perimeter channels, sediment traps, temporary channels,
temporary diversion and oil interception facilities to mitigate site run-off
impacts;
(e)
divert all clean surface
water around the site; and
(f) provide
bunded areas for generators, and for storage of fuel, oil and chemical wastes.
3.
Environmental Monitoring and Audit (EM&A) for the
Project
3.1
The EM&A programme
shall be implemented as set out in the EM&A Manual of the EIA Report. Any
changes to the programme shall be justified by the IEC as conforming to the
requirements set out in the EM&A Manual and shall be submitted to the
Director for approval. An updated
EM&A Manual with details covering the two different phases of the Project:
(a) Phase1 Part 1 and (b) Phase1 Part 2 of the Project, making reference to the
documents submitted with the Application
for Variation of Environmental Permit (Application No. VEP-234/2007), shall be
submitted to the Director for approval at least 1 month before commencement of
each of the specific phases of the Project: that is (a) Phase 1 Part 1 and (b)
Phase 1 Part 2 of the Project.
3.2
A complaint investigation procedure
shall be set up at least two weeks before the commencement of the Project. The complaint investigation procedure
shall follow the requirements set out in the EM&A programme.
3.3
All environmental
monitoring and audit data submitted under this Permit shall be true, valid and
correct.
3.4
Four hard copies and one
electronic copy of the Baseline Monitoring Report shall be submitted to the
Director at least two weeks before the commencement of the Project. Additional
copies of the submission shall be provided to the Director upon request from
the Director.
3.5
Four hard copies and one
electronic copy of monthly EM&A Report shall be submitted to the Director
within two weeks after the end of the reporting month. Additional copies of the
submission shall be provided to the Director upon request from the Director.
3.6
The actions described in
the Event/Action Plans of the EM&A Manual shall be fully and properly
carried out, in accordance with the time frame(s) set out in the Event/Action
Plan, or as agreed by the Director.
4.
Electronic Reporting of EM&A Information
4.1
To facilitate public
inspection of the Baseline Monitoring Report and monthly EM&A Reports via
the EIAO Internet Website and at the EIAO Register Office, electronic copies of
these Reports shall be prepared in Hyper Text Markup Language (HTML) (version
4.0 or later) and in Portable Document Format (PDF version 4.0 or later),
unless otherwise agreed by the Director and shall be submitted at the same time
as the hard copies as described in Conditions 3.4 and 3.5 of this Permit. For
the HTML version, a content page capable of providing hyperlinks to each
section and sub-section of these Reports shall be included at the beginning of
the document. Hyperlinks to all figures, drawings and tables in these Reports
shall be provided in the main text where the respective references are made.
All graphics in these Reports shall be in interlaced GIF format unless
otherwise agreed by the Director. The content of the electronic copies of these
Reports shall be the same as the hard copies.
4.2
All environmental
monitoring data described in Condition 4.1 above shall be made available to the
public via internet access in the shortest possible time and in no event later
than two weeks after the relevant environmental monitoring data are collected
or become available, unless otherwise agreed with the Director. The Permit
Holder shall notify the Director in writing, within six weeks after the
commencement of the Project, the internet address where the environmental
monitoring data are to be placed. The internet address and the relevant
environmental monitoring data shall be made available to the public via the
EIAO Internet Website and the EIAO Register Office.
4.3
The internet website as
described in Condition 4.2 above shall enable user-friendly public access to
the monitoring data with features capable of:
(a)
providing access to all
environmental monitoring data collected since the commencement of the Project;
(b)
searching by date;
(c)
searching by types of
monitoring data; and
(d)
hyperlinking to relevant monitoring
data after searching;
or
otherwise as agreed by the Director.
Notes :
1. This Permit consists of three parts, namely, PART A (Main Permit), PART B
(Description of Designated Project) and PART C (Permit
Conditions). Any person relying on this permit should obtain independent legal
advice on the legal implications under the Ordinance, and the following notes
are for general information only.
2. The Permit
Holder may apply under Section 13 of the Ordinance to the Director for a variation
of the conditions of this Permit. The Permit Holder shall replace the original
permit displayed on the Project site by the amended permit.
3. A person who
assumes the responsibility for the whole or a part of the designated project
may, before he assumes responsibility of the designated project, apply under
Section 12 of the Ordinance to the Director for a further environmental permit.
4. Under Section
14 of the Ordinance, the Director may with the consent of the Secretary for the
Environment and Food, suspend, vary or cancel this Permit. The suspended,
varied or cancelled Permit shall be removed from display at the Project site.
5. If this Permit
is cancelled or surrendered during the Project, another environmental permit
must be obtained under the Ordinance before the Project could be continued. It
is an offence under Section 26(1) of the Ordinance to decommission a designated
project listed in Part II of Schedule 2 of the Ordinance without a valid
environmental permit.
6. Any person who
carries out the Project contrary to the conditions in the Permit, and is
convicted of an offence under the Ordinance, is liable: -
(i) on a first
conviction on indictment to a fine of $ 2 million and to imprisonment for 6
months;
(ii)
on a second or subsequent conviction on indictment to a fine of $ 5 million and
to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to imprisonment for 6
months;
(iv)
on a second or subsequent summary conviction to a fine of $1 million and to
imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature, the court or
magistrate may impose a fine of $ 10,000 for each day on which he is satisfied
the offence continued.
7. The Permit
Holder may appeal against any condition of this Permit under Section 17 of the
Ordinance within 30 days of receipt of this Permit.
8. The Notes are
for general reference only and that the Permit Holder should refer to the EIA
Ordinance for details and seek independent legal advice.
9. Occupational
safety and health issues are governed by the Occupational Safety and Health
Ordinance (Cap. 509), and Factories and Industrial Undertakings Ordinance
(Cap.59). The Permit Holder is advised to contact the Labour Department for
requirements relating to occupational safety and health issues.
Environmental Permit No. EP-136/2002/B
環境許可證編號
EP-136/2002/B
Locations
Identified in the EIA Report (AEIAR-058/2002) Requiring
APPENDIX A
Remediation and the Actions Recommended
(Extracted from table 4.3 of the EIA Report,
Register No. AEIAR-058/2002))
Table A Soil/Rubbles/Ash Wastes Remediation Actions Required
Borehole# |
Action Required |
Remove concrete surface and clear uncontaminated surface material and
stockpile |
Proposed depth of Material for Removal or Treatment |
Remedial Action |
Reassurance / Confirmatory Sampling |
TB1 |
Yes |
Concrete down to 0.3m depth |
Immediately below concrete 0.3m to 4.0m |
Immobilisation for 0.3m to 2.0m and 3.0m to
4.0m* TCLP test followed by removal of 2.0m to 3.0m to
landfill. Immobilisation if TCLP
tests exceed criteria **. |
Yes, determine extent of HM (Cd, Cu, Pb, Zn and
Hg) and TPH contamination at edge and base of excavated hole.* |
TB2 |
Yes |
Concrete down to 0.5m depth |
Immediately below concrete 0.5m to 1.5m |
Immobilisation* |
Yes, determine extent of HM (As, Cu, Pb and Zn)
contamination at edge and base of excavated hole.* |
TB3 |
Yes |
Concrete down to 2.5m depth |
2.5m to 3.5m |
Immobilisation * |
Yes, determine extent of HM (Cu, Pb, Zn and Hg)
contamination at edge and base of excavated hole.* |
TB4 |
Yes |
Down to 2.2m depth |
2.2m to 4.2m |
Immobilisation * |
Yes, determine extent of HM (As, Cu, Pb and Zn) contamination
at edge and base of excavated hole.* |
TB5 |
Yes |
Concrete down to 1.8m. Down to 2.5m depth |
2.5m to 4.0m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination
at edge and base of excavated hole.* |
TB8 |
Yes |
Concrete down to 1m. Down to 2.5m |
2.5m to 3.5m |
TCLP test followed by removal of 2.5m to 3.5m to
landfill. Immobilisation if TCLP
tests exceed criteria **. |
Yes, determine extent of PAH contamination at
edge and base of excavated hole.* |
TB9 |
Yes |
Concrete down to 1.0m depth |
1.0m to 2.0m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination
at edge and base of excavated hole.* |
TB10 |
Yes |
Surface rubble/ash and brick material (not soil)
about 1.5m depth. |
1.5 m |
Clear Waste to landfill. Waste to be treated and tested to
meet EPD disposal criteria. |
Yes, determine extent of HM (As, Cd, Cu, Pb, Zn)
TPH and PCDD/PCDF contamination under surface contaminated materials.* |
TB11 |
Yes |
Down to 1.5m depth |
1.5 m |
Clear Waste to landfill. Waste to be treated and tested to
meet EPD disposal criteria. |
Yes, determine extent of HM (Cd, Cu, Pb, and Zn)
and PCDD/PCDF contamination under surface contaminated materials.* |
TB11 |
Yes |
Below hardstanding surface (soil materials) |
1.5 to 4.0m |
Immobilisation* |
Yes, to determine extent of HM (Pb)
contamination at edge and base of excavated hole. |
TB12 |
Yes |
Concrete down to 0.5m |
0.5 to 1.5m |
Immobilisation* |
Yes, determine extent of HM (Cd, Cu, Pb and Zn)
contamination at edge and base of excavated hole.* |
TB13 |
Yes |
Down to 2.5m |
2.5m to 3.5m |
Immobilisation* |
Yes, determine extent of HM (Pb, Zn, Hg)
contamination at edge and base of excavated hole.* |
TB15 |
Yes |
Concrete down to 0.4m |
0.4 to 2.4m |
TCLP test followed by removal of 0.4m to 2.4m to
landfill. Immobilisation if TCLP
tests exceed criteria **. |
Yes, determine extent of HM (As, Cu, Pb, Hg and Zn)
and PAH contamination at edge and base of excavated hole.* |
TB16 |
Yes |
Concrete down to 0.8m |
0.8 to 4.3m |
Immobilisation * |
Yes, determine extent of HM (Cu, Pb and Zn)
contamination at edge and base of excavated hole.* |
TB17 |
Yes |
Concrete down to 0.4m |
0.4 to 2.4m |
Immobilisation * |
Yes, determine extent of HM (Pb and Hg)
contamination at edge and base of excavated hole.* |
TB18 |
Yes |
Concrete down to 1.0m |
1.0m to 2.0m |
Immobilisation * |
Yes, determine extent of HM (Pb) contamination
at edge and base of excavated hole.* |
TB19 |
Yes |
Concrete down to 0.6m |
0.6m to 4.0m |
Immobilisation * |
Yes, determine extent of HM (Pb and Hg)
contamination at edge and base of excavated hole.* |
TB20 |
Yes |
Concrete down to 0.3m |
0.3m to 2.3m |
TCLP test followed by removal of 0.3m to 2.3m to
landfill. Immobilisation if TCLP
tests exceed criteria **. |
Yes, determine extent of HM (As, Cu, Pb, Hg, Cd
and Zn) PAH and TPH contamination at edge and base of excavated hole.* |
TB21 |
Yes |
Concrete down to 0.5m |
0.5m to 5.0m |
TCLP test followed by removal of 0.5m to 3.5m to
landfill. Immobilisation if TCLP
tests exceed criteria **. Remaining depth to be
immobilised to 5m * |
Yes, determine extent of HM (Cu, Pb, Hg and Zn)
and TPH contamination at edge and base of excavated hole.* |
TB22 |
Yes |
Concrete down to 0.5m |
0.5 to 1.5m |
Immobilisation * |
Yes, determine extent of HM (Pb) contamination at
edge and base of excavated hole.* |
TB23 |
Yes |
Concrete down to 0.5m |
0.5 to 4m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination
at edge and base of excavated hole.* |
TB24 |
Yes |
Concrete down to 1.2m |
1.2 to 4.2m |
Immobilisation* |
Yes, determine extent of HM (Cu, Pb and Hg) contamination at edge and
base of excavated hole.* |
TB25 |
Yes |
Concrete down to 0.9m. Down to 1.0m |
Depth 1.0m – 4.4m |
TCLP test followed by removal of 1.0m to 2.9m to
landfill. Immobilisation if TCLP
tests exceed criteria **. Immobilisation for remaining 2.9m to 4.4m* |
Yes, to determine extent of HM (Pb, Hg) and PAH
contamination at edge and base of excavated hole.* |
TB26 |
Yes |
Concrete down to 0.8m |
Depth 0.8m – 3.0m |
TCLP test followed by removal of 0.8m to 3.0m to
landfill. Immobilisation if TCLP
tests exceed criteria **. |
Yes, to determine extent of HM (Pb, Cu, Zn, Hg)
and TPH contamination.* |
TB27 |
Yes |
Concrete down to 0.5m and clean soil down to
2.0m |
2.0 to 4.0m |
TCLP test followed by removal of 2.0m to 4.0m to
landfill. Immobilisation if TCLP
tests exceed criteria **. |
Yes, determine extent of HM (Cu and Pb) and PAH
contamination at edge and base of excavated hole.* |
TB28 |
Yes |
Concrete down to 0.4m |
0.4 to 4.4m |
Immobilisation* |
Yes, determine extent of HM (As, Cd, Cu, Pb, and
Zn) contamination at edge and base of excavated hole.* |
TB29 |
Yes |
Concrete down to 0.5m |
0.5 to 3.5m |
Immobilisation* |
Yes, determine extent of HM (Cu, Pb, Hg and Zn)
contamination at edge and base of excavated hole.* |
TB30 |
Yes |
Concrete down to 0.6m |
0.6 to 1.6m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination
at edge and base of excavated hole.* |
Refuse Bunkers |
Yes |
N/A |
N/A |
Landfill disposal * |
Examine bunker refuse prior to demolition. |
# For location of boreholes, please refer to Figure 7 of the Permit
* If contamination confirmed by reassurance sampling extract
a further 1m into the soil, immobilise and resample.
** TCLP test
for all metals identified in Table E1 in EPD Contaminated Sites Investigation
and Remediation Guidance Notes
Criteria
for Soil Contamination and Landfill Disposal of Contaminated
Soil
APPENDIX B
(Extracted from Appendix B of the EIA Report, Register No.
AEIAR-058/2002)
Disposal Criteria for
Contaminated Soil
Metals
(for on-site reuse)
Parameter |
TCLP
Limit (ppm) |
Cadmium |
10 |
Chromium |
50 |
Copper |
250 |
Nickel |
250 |
Lead |
50 |
Zinc |
250 |
Mercury |
1 |
Tin |
250 |
Silver |
50 |
Antimony |
150 |
Arsenic |
50 |
Beryllium |
10 |
Thallium |
50 |
Vanadium |
250 |
Selenium |
1 |
Barium |
1000 |
Source
: Guidance Notes for Investigation and Remediation of Contaminated Sites (EPD
TR1 / 99).
Metals
Toxicity Characteristics Leaching Procedure (TCLP)
test for materials contaminated with heavy metals needs to be carried out in accordance
with the testing frequency and requirements as stipulated in EPD’s Guidance
Notes for Investigation and Remediation of Contaminated Sites.
TPH and PAH
Toxicity Characteristic Leaching Procedure (TCLP)
tests for TPH, PAH and BTEX contaminated materials have to be carried out
according to the testing frequency and requirements as stipulated in EPD’s
“Guidance Notes for Investigation and Remediation of Contaminated Sites. Pre-treatment is required to bring
levels of TPH to below the TCLP limit of 2,500ppm PAH/BTEX to below the TCLP
limit 1,000ppm.
Dioxins and Furans
(PCDD/PCDF)
Toxicity Characteristic Leaching Procedure (TCLP)
tests for PCDD/PCDF contaminated materials have to be carried out with reference
to the requirements as stipulated in EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites.
Pre-treatment is required to bring levels of PCDD/PCDF to below the TCLP
limit of 1ppb PCDD/PCDF (TEQ), subject to TCLP confirmation at a frequency of 1
sample per 100 tonnes of stabilised materials.
N.B.
TEQ = toxicity
equivalent units.
ppm =
mg/kg (miligrams
/ kilogram)
ppm =
mg/g
(micrograms
/ gram)
ppb =
ng/g (nanograms
/ gram)
ppb =
1000pg/g (picograms / gram)
(Extracted
from Appendix IV of ProPECC PN 3/94)
APPENDIX C
---
END OF APPENDIX C ---
| Figure 1 | Figure 2 | Figure 3 | Figure 4 | Figure 5 | Figure 6 | Figure 7 |
[ Back to First Page ] / [ Back to Main Index ]