Environmental Permit No. EP-235/2005/B
環境許可證編號 EP-235/2005/B

 

 

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Sections 10 & 13

 

環境影響評估條例

(499)

1013

 

ENVIRONMENTAL PERMIT TO CONSTRUCT

A DESIGNATED PROJECT

 

建造指定工程項目的環境許可證

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of Environmental Protection (the Director) grants the environmental permit (EP-235/2005) to the Civil Engineering and Development Department (hereinafter referred to as the “Permit Holder”) on 23 December 2005.  Pursuant to Section 13 of the EIAO, the Director amends the Environmental Permit based on the Application No. VEP-244/2007.  The amendments, described below, are incorporated into this Environmental Permit (EP-235/2005/B).  This Environmental Permit as amended is for the construction of the designated project described in Part B subject to the conditions specified in Part C.  The issue of this environmental permit is based on the documents, approvals or permissions described below:

 

根據環境影響評估條例(環評條例)10條的規定,環境保護署署長(署長)20051223日將環境許可證(編號EP-235/2005)批予土木工程拓展署 (下稱“許可證持有人”)。根據環評條例第13條的規定,署長因應更改環境許可證的申請編號VEP-244/2007修訂環境許可證。以下修訂已包含在本環境許可證內(編號EP-235/2005/B)。本經修訂的環境許可證作為建造本許可證B部所說明的指定工程項目,但須遵守C部所列明的條件。 本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據

 

Application No.

申請書編號:

VEP-244/2007

 

Document in the Register:

登記冊上的文件:

 

(1) Project Profile – Landslide Preventive Works at Po Shan, Mid-Levels (Register No.: PP-267/2005)

(1) 工程項目簡介半山區寶珊地段防止山泥傾瀉工程(登記冊檔號: PP-267/2005)

 

(2) The Director’s letter of permission to apply directly for environmental permit dated 28 November 2005 [Ref.: (17) in EP2/H11/Q/05 Pt. 2]

(2) 署長於20051128日 發出批准直接申請環境許可證的信件 [檔案編號 : (17) in EP2/H11/Q/05 Pt. 2]

 

(3) Application for Environmental Permit submitted by the Permit Holder on 30 November 2005 (Application No. AEP-235/2005)

(3) 許可證持有人於2005 11 30 日提交的環境許可證申請(申請書編號:AEP-235/2005

 

(4) Environmental Permit issued on 23 December 2005 (Permit No. EP-235/2005)

(4) 2005 12 23 日簽發的環境許可證(許可證編號:EP-235/2005

 

 

(5) Application documents for Variation of Environmental Permit including all attachments submitted by the Permit Holder on 20.6.2006 (Application No. VEP-219/2006)

(5) 許可證持有人於2006620日提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-219/2006)

 

(6) Environmental Permit issued on 7 July 2006 (Permit No. EP-235/2005/A)

(6) 200677日簽發的環境許可證(許可證編號:EP-235/2005/A

 

(7) Documents for Surrender of Environmental Permit including all attachments submitted by the Permit Holder on 7.12.2006 (Application No. SEP-043/2006)

(7) 許可證持有人於2006127日提交的交回環境許可證文件包括所有附件(申請書編號:SEP-043/2006)

  (8)  Landslide Preventive Works at Po Shan, Mid-levels – Natural Terrain Risk Mitigation Measures : Environmental Impact Assessment (EIA) Report, Executive Summary, Executive Summary and Environmental Monitoring & Audit (EM&A) Manual (Register No.: AEIAR-112/2007 ) [Hereinafter referred to as the “EIA Report”]

(8)  半山區寶珊地段防止山泥傾瀉工程 - 設計及施工 (天然山坡滑坡災害緩減工程) : 環境影響評估報告,行政摘要及環境監察及審核手冊 (登記冊編號: AEIAR-112/2007) [下稱「環評報告」]

  (9) The Director’s letter of approval of the EIA report with Conditions dated 22 October 2007 (Reference: (13) in EP2/H11/Q/06 Pt.2)

(9)  署長於20071022日發出批准環評報告的信件(檔案編號: (13) in EP2 / H11 / Q / 06 Pt.2

 

(10) Application documents for Variation of Environmental Permit including all attachments submitted by the Permit Holder on 12.11.2007 (Application No. VEP-244/2007)

(10) 許可證持有人於20071112日提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-244/2007)

 

 

 


Part B (DESCRIPTIONS OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit

(hereinafter referred to as the “Permit”):

下列為本環境許可證(下稱“許可證”)A所提述的指定工程項目的說明:

 

Title of Designated Project

指定工程項目的名稱

 

Landslide Preventive Works at Po Shan, Mid-Levels

[This designated project is hereinafter referred to as “the Project”]

 半山區寶珊地段防止山泥傾瀉工程

[這指定工程項目下稱“工程項目”]

 

Nature of Designated Project
指定工程項目的性質

 

To construct drainage adits and repair existing surface channels and associated catchpits within the boundary of the Pok Fu Lam Country Park and Special Area; as well as to construct soil nails.

 於薄扶林郊野公園及特別地區內建造地下排水道及修葺現有的地面排水渠及相連的排水井; 及建造泥釘。

 

Location of Designated Project

指定工程項目的地點

Po Shan, Mid-Levels. The location of the Project is shown in Figure 1 attached to this Permit.

 半山區寶珊地段。工程項目的位置見載於本許可證夾附的1

 

Scale and Scope of Designated Project(s)

指定工程項目的規模和範圍

The project includes the following works at the Po Shan area

 

Part I (see Figures 2)

(a)     Construction of two 3.5m diameter underground drainage adits, each of lengths 260m and 175m respectively, with sub-vertical drains;

(b)     Construction of 300 nos. of soil nails and 80 nos. raking drains; and

(c)     Repairing of 1,200m long existing surface channels and associated catchpits (including removal of concrete for those surface channels in poor conditions and casting of concrete for the replacement channels) at the Po Shan area.

 

Part II (see Figure 3):

(d) installation about 700 numbers of soil nails and about 60 numbers of raking drains in the natural terrain;

(d)     rock slope stabilisation works at upper portion of the natural terrain; and

(f)     other associated works.

 

 工程包括於寶珊地段

 

第一部份 (2):

(a)       建造兩條直徑3.5米,分別長260米及175米的地下排水道裝設垂直排水管道;

(b)     建造300泥釘及80 支斜管;

(c)    修葺現有1,200米長的地面排水渠及相連的排水井(包括拆除地面排水渠的混凝土破損部份,並重新灌注混凝土作為排水渠翻新用途).

 

第二部份 ( 3):

(d)  在有關地區的天然地形上裝設約700口泥釘和約60根傾斜排水管;

(e)  在天然地形的上半部進行石坡保護穩固措施工程;

(f)  其他相關設施工程

 

 

Application No.

申請書編號

Date of Application

申請日期

List of Amendments Incorporated into Environmental Permit

已包含在本環境許可證內修訂項目

Date of Amendment

修訂日期

VEP-219/2006

 

20 June 2006

2006620

Amend the “Scale and Scope of Designated Project” in Part B

更改B部的《指定工程項目的規模和範圍》

 

Amend Figures 1 and 2 and add Figure 5

更改圖12加入5

 

Amend Conditions 1.7, 2.1 and 2.3 in Part C of Environmental Permit No. EP-235/2005

更改C部的條件第1.7, 2.12.3

 

Add Condition 2.7 in Part C of the Environmental Permit EP-235/2005

加入環境許可證編號 EP-235/2005 C 部第2.7項條件。

7 July 2006

200677

 

 

 

 

SEP-043/2006

7 December 2006

2006127

Surrender part of the works area, about 26m2 along the downhill side of Lugard Road near the south-eastern end of the site, as proposed under EP-235/2005/A.

 

交回環境許可證編號EP-235/2005/A 擬用的工地東南端, 一輻位於盧吉道山坡下, 26平方米的工地 .

 

7 December 2006

2006127

VEP-244/2007

12 November 2007

Amend the “Scale and Scope of Designated Project” in Part B

更改B部的《指定工程項目的規模和範圍》

 

Re-number Figures 3 to 5

3 5 重新編號

 

Add Figures 3, 7 to 8-1 and 8-2

加入3, 7 8-1 8-2

 

Amend Conditions 1.7, 1.12, 1.13 and 2.1 to 2.7 in Part C of Environmental Permit No. EP-235/2005/A

更改環境許可證編號 EP-235/2005/A  C部的條件第1.7, 1.12, 1.13, 2.1 2.7

 

Add Conditions 2.8 to 2.16, 3.1 to 3.5 and 4.1 in Part C of the Environmental Permit EP-235/2005/A

加入環境許可證編號 EP-235/2005/A  C部第2.8 2.16, 3.1 3.5 4.1項條件。

23 November 2007

 

 

 

 

 

 

23 November 2007

200711 23

 

 

 

Date

日期

 

(Mrs. Shirley LEE)

Principal Environmental Protection Officer

for the Director of Environmental Protection

環境保護署署長

(首席環境保護主任李韓琇玲代行)

 

 

 


PART C (PERMIT CONDITIONS)

1.         General Conditions

 

1.1        The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499) and may become the subject of appropriate action being taken under the Ordinance.

 

1.2        The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Waste Disposal Ordinance (Cap. 354) and Country Parks Ordinance (Cap. 208). This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.

 

1.3        The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorised officers at all sites/offices covered by this Permit.  Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

 

1.4        The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction of the Project and shall mean the same hereafter.

 

1.5        The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.  The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6        The Permit Holder shall construct the Project in accordance with the project descriptions in Part B of this Permit.

 

1.7        The Permit Holder shall ensure that the Project is designed and constructed in accordance with the information and all recommendations described in the Project Profile (Register No.: PP-267/2005), the information and recommendations described in the EIA Report and Approval Conditions (Register No. AEIAR-112/2007), the application documents including all attachments (Application No. VEP-244/2007), the information and mitigation measures described in this Permit, mitigation measures to be recommended in submissions that shall be deposited with the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

 

1.8        All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise specified by the Director.

 

1.9        All submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit.  Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions.  Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499).

 

1.10      The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other place, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection.  For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11      All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong).  Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as hard copies.

 

1.12      The Permit Holder has already commenced construction of Part I of the Project.  The Permit Holder shall notify the Director in writing the commencement date of construction of Part II of the Project at least one week before the commencement of construction of Part II of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction of Part II of the Project.

 

1.13      For the purpose of this Permit, “commencement of construction” of Part II of the Project does not include works related to site preparation, or other works as agreed by the Director.

 

2      Special Conditions

 

The following Conditions 2.1 to 2.2 inclusive are applicable to the entire Project (both Parts I and II)

 

2.1.     No tree felling shall be allowed within the Pok Fu Lam Country Park and Special Area.

 

2.2       The Permit Holder shall set up and operate a community liaison office throughout the construction of the Project to receive and respond to complaints or enquires on environmental nuisances or pollution caused by the Project and to implement remedial mitigation measures.

 

The following Conditions 2.3 to 2.7 inclusive are only applicable to Part I of the Project

 

2.3        To minimize disturbance to the Pok Fu Lam Country Park and Special Area, no site clearance woks shall be permitted within the Country Park and Special Area.  Instead of heavy powered mechanical equipment, only hand-held tools, such as gasoline powered hand-held breaker and vibratory porker, shall be used within the Country Park and Special Area.

  

2.4       To minimise environmental impacts from the construction of drainage adits and the environmental side-effects of the ancillary activities associated with the Project,

(a)     tunnel boring machine(s) shall be employed for constructing the adits lying within the Pok Fu Lam Country Park and Special Area;

(b)    no blasting shall be permitted within the Pok Fu Lam Country Park and Special Area;

(c)    noise enclosure as shown in Figure 4 shall be adopted when using hand-held breaker and grout pump during construction of portal sections of the adits;

(d)    the construction of soil nails and associated raking drains shall not be carried out concurrently with other construction activities associated with Part I of the Project; and

(e)    Noise insulating fabric as shown in Figure 5 shall be adopted to cover drill rigs during construction of soil nails.  The insulating fabric shall have no openings or gaps and shall achieve at least 5dB(A) noise reduction.  The Permit Holder shall fully implement all measures as recommended in the specification for noise insulating fabric, including sizes, locations and installation details, as deposited with the Director on 22 September 2006 under Environmental Permit No. EP-235/2005/A.

 2.5      The Permit Holder shall monitor the ground water table within the Pok Fu Lam Country Park and Special Area during construction.  The Permit Holder shall implement all measures recommended in the ground water monitoring plan deposited with the Director on 5 August 2006 under Environmental Permit No. EP-235/2005/A.

 

2.6       To mitigate impacts on the rest garden as shown in Fig. 2 due to the construction of drainage adits, tree transplantation within the garden shall be implemented as shown in Figure 6. The Permit Holder shall, within 4 weeks after completion of the restoration works for the rest garden, deposit with the Director three hard copies and one electronic copy of the as-built record of tree transplantation and restoration.

 

2.7       To minimize noise impact from the repair works for the surface channels and associated catchpits, the repairs works shall not be carried out concurrently with other construction activities associated with Part I of the Project.

 

The following Conditions 2.8 to 4.1 inclusive are only applicable to Part II of the Project

 

2.8               An Environmental Team (ET) shall be established by the Permit Holder no later than one week before the commencement of construction of Part II of the Project. The ET shall be headed by an ET Leader. The ET Leader shall be a person who has at least 7 years' experience in environmental monitoring and auditing (EM&A) or environmental management. The ET and the ET Leader shall be responsible for the duties defined in the EM&A Manual of the EIA Report. The ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual. The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and each and every non-compliance with the recommendations of the EIA Report or Conditions pertaining to Part II of the Project in this Permit. This log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the EIA Report recommendations and this Permit or by the Director or his authorized officers. Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader. Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation. The ET shall not be in any way an associated body of the Contractor or the IEC for the Project.

2.9               An Independent Environmental Checker (IEC), shall be employed by the Permit Holder no later than one week before the commencement of construction of Part II of the Project.  The IEC shall be a person who has at least 7 years' experience in environmental monitoring and audit (EM&A) or environmental management.  The IEC shall be responsible for the duties defined in the EM&A Manual of the EIA Report, and shall audit the overall EM&A programme described in the EIA Report, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required for Part II of the Project under this Permit.  In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions required for Part II of the Project under this Permit.  The IEC shall verify the log-book(s) mentioned in Condition 2.8 of this Permit.  The IEC shall notify the Director by fax, within 24 hours of each and every occurrence, change of circumstances or non-compliance with the EIA Report or this Permit, which might affect the monitoring or control of adverse environmental impact.  Where the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined in the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation.  Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition. The IEC shall not be in any way an associated body of the Contractor or the Environmental Team for the Project.

2.10            The Permit Holder shall, within two weeks after the commencement of construction of Part II of the Project, inform the Director in writing of the management organization of the main companies and/or any form of joint ventures associated with the carrying out of Part II of the Project. The submitted information shall include at least an organization chart, names of responsible persons including the ET Leader and the IEC, and their contact details.

Vegetation Survey prior to Commencement of Construction of Part II of the Project

2.11            A suitably qualified ecologist with 7 or more years of relevant experience shall be employed to conduct a detailed vegetation survey prior to the commencement of construction in order to identify and label the affected plant species of conservation interest, including but not limited to Small Persimmon, Common Tutcheria, Bird-nest Fern and Chinese Pholidota.

Mitigation Measures during Construction Stage of Part II of the Project

2.12            To avoid or minimize any damage to the root system of existing plants, the ecologist mentioned in Condition 2.11 above shall also advise on the selection and on-site adjustment of the locations of soil nails and raking drains.

2.13            To minimise construction noise impacts from the construction work of Part II of the Project, the following measures shall be implemented:

(a)                For Works Area A as shown in Figure 7 - Movable noise barrier with a typical section as shown in Figures 8-1 and 8-2 shall be used to mitigate the noise generated from concrete mixer.  Noise enclosure with a typical section as shown in Figure 4 shall be used to mitigate the noise generated from air compressor, grouting machine and generator.

 

(b)                Restrictions on the number of construction plants operating simultaneously shown in the Table in Figure 7 shall be followed.  Alternatively, the Permit Holder may deposit a construction noise control plan with an alternative construction plant inventory to demonstrate compliance with construction noise performance as predicted in EIA Report.

 

(c)        Noise insulating fabric, with a typical arrangement as shown in Figure 5 shall be applied for drill rigs operating in Works Area E during construction of soil nails. The noise insulating fabric shall have no openings or gaps at joints, and shall achieve a noise reduction of at least 5 dB(A).  The Permit Holder shall fully implement all measures as recommended in the specification for the noise insulating fabric, including sizes, locations and installation details, as deposited with the Director on 22 September 2006 under Environmental Permit No. EP-235/2005/A.

 

2.14            To avoid the groundwater being affected by the flushing medium of drilling equipment, air shall be used as the flushing medium of the drilling equipment.  In addition, casing shall be provided to the drillhole of soil nail within the permeable colluvium layer to minimize the impact to the groundwater table situated at the permeable soil stratum.

2.15            To facilitate collection of discharge of air, water and grout during grouting of the soil nails, an outlet pipe protruding from the slope surface shall be installed at the drill hole during grouting.

2.16            Compensatory planting due to the loss of trees and vegetations:

(a)    Planting of suitable shrubs/herbs, including Small Persimmon, to be advised by the ecologist mentioned in Condition 2.11, shall be provided within Part II of Project area to compensate for understorey vegetation of woodland habitats affected by works of Part II of the Project.

(b)    To provide suitable habitat for the Short-nosed Fruit Bat after completion of the works of Part II of the Project, Chinese Fan-palm (Livistona chinensis) shall be planted near the existing bat roost in the Part II of the Project area.

3.                  Environmental Monitoring and Audit (EM&A) for Part II of the Project

3.1               The EM&A programme shall be implemented as set out in the EM&A Manual of the EIA Report. Any changes to the programme shall be justified by the IEC as conforming to the requirements set out in the EM&A Manual and shall be submitted to the Director for approval.

3.2               All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.

3.3               Four hard copies and one electronic copy of monthly EM&A Report shall be submitted to the Director within two weeks after the end of the reporting month. Additional copies of the submission shall be provided to the Director upon request from the Director.

3.4               The actions described in the Event/Action Plans of the EM&A Manual shall be fully and properly carried out, in accordance with the time frame(s) set out in the Event/Action Plan, or as agreed by the Director.

Construction Stage Ecological Monitoring

3.5               As part of the EM&A programme, the ecologist mentioned in Condition 2.11 above shall be responsible for carrying out a specific monitoring programme of the plant individuals of conservation interest identified within the proposed works area during the detailed vegetation survey.  The ecologist shall carry out regular monitoring of the trees, shrubs and herbs to check on the health and condition of the plants.  Monitoring should be conducted twice a month cover the whole construction period of Part II of the Project.

4.         Electronic Reporting of EM&A Information

4.1               To facilitate public inspection of monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Condition 3.3 of this Permit. For the HTML version, a content page capable of providing hyperlinks to each section and sub-section of these Reports shall be included at the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text where the respective references are made. All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director. The content of the electronic copies of these Reports shall be the same as the hard copies.

Notes :

1. This Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project) and PART C (Permit Conditions). Any person relying on this permit should obtain independent legal advice on the legal implications under the Ordinance, and the following notes are for general information only.

2. The Permit Holder may apply under Section 13 of the Ordinance to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

3. A person who assumes the responsibility for the whole or a part of the designated project may, before he assumes responsibility of the designated project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.

4. Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project site.

5. If this Permit is cancelled or surrendered during the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued. It is an offence under Section 26(1) of the Ordinance to construct a designated project listed in Part I of Schedule 2 of the Ordinance without a valid environmental permit.

6. Any person who carries out the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable: -

(i)                        on a first conviction on indictment to a fine of $ 2 million and to imprisonment for 6 months;

(ii)                      on a second or subsequent conviction on indictment to a fine of $ 5 million and to imprisonment for 2 years;

(iii)                     on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

(iv)                    on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

(v)                      in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $ 10,000 for each day on which he is satisfied the offence continued.

7. The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

8. The Notes are for general reference only and that the Permit Holder should refer to the EIA Ordinance for details and seek independent legal advice.

Environmental Permit No. EP-235/2005/B

環境許可證編號  EP-235/2005/B


 

Table 1     Tree Schedule

 

 

Tree No.

 

 

Species

Overall Height
(m)

 

Girth
(m)

Crown Spread
(m)

To be

Retained (R)/

Transplanted (T)

T01

Acacia confusa

10

1.25

8

R

T02

Acacia confusa

9

1.25

8

R

T03

Macaranga tanarius

4

0.4

4

T

T90

Cratoxylum ligustrinum

6

0.7

3

T

T91

Bauhinia blakeana

5

0.4

4

R

T92

Bauhinia blakeana

5

0.4

3

R

T93

Bauhinia blakeana

4

0.4

3

R

T94

Bauhinia blakeana

5

0.45

5

R

T95

Melaleuca quinquenervia

9

0.92

4

T

T96

Cratoxylum ligustrinum

6

0.49

3

T

T97

Cratoxylum ligustrinum

8

0.59

4

T

T98

Celtis sinensis

5

0.35

3

R

T99

Celtis sinensis

7

0.45

4

R

T100

Celtis sinensis

8

1.8

6

R

T101

Celtis sinensis

4

0.4

4

R

T102

Celtis sinensis

4

0.3

3

T

T103

Bridelia tomentosa

3

0.35

2

R

T104

Celtis sinensis

3

0.3

2

T

T111

Celtis sinensis

4

0.35

3

R

T200

Caryota ochlandra

4

0.36

3

T

T201

Caryota ochlandra

6

0.4

4

T

T202

Caryota ochlandra

5

0.35

4

T

T203

Caryota ochlandra

5

0.35

4

T

T204

Caryota ochlandra

4

0.34

3

T

T203a

Caryota ochlandra

3

0.25

2

T

 

Notes:      This table is to be read in conjunction with Figure 6.