Environmental
Permit No. EP-122/2002/A
環境許可證編號 EP-122/2002/A
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第 10 及 13 條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental
Impact Assessment Ordinance (the Ordinance), the Director of Environmental
Protection (the Director) granted the Environmental Permit (No. EP-122/2002) to
the Civil Engineering and Development
Department (hereinafter referred to as the “Permit Holder”)
(formerly known as the Territory Development Department) on 7 March 2002.
Pursuant to Section 13 of the Ordinance, the Director amends the Environmental
Permit based on the Application No. VEP-247/2007. The amendments described
below, are incorporated into this Environmental Permit (No. EP-122/2002/A).
This Environmental Permit as amended is for the construction and operation of the
designated projects described in Part B of this Permit
subject to the conditions described in and attached to Part C
of this Permit.
根據《環境影響評估條例》(條例)第10條的規定,環境保護署署長(署長)於 2002 年 3月 7日將環境許可證 (編號EP-122/2002) 批予 土木工程拓展署(下稱 “許可證持有人”) (曾稱為拓展署)。根據條例第13條的規定,署長因應更改環境許可證的申請編號VEP-247/2007 修訂環境許可證。以下修訂已包含在本環境許可證內 (編號 EP-122/2002/A)。本經修訂的環境許可證作為建造及營辦本許可證B部所說明的指定工程項目,但須遵守本許可證 C 部所說明或附載的條件。
The issue of this environmental permit is based on
the documents, approvals or permissions described below:
本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據﹕-
Application
No. 申請書編號: |
VEP-247/2007 |
Document in the Register: 登記冊上的文件: |
Central Reclamation Phase III – Studies, Site Investigation, Design and Construction (Register No.: AEIAR-040/2001) – Environmental Impact Assessment Report Volumes 1 and 2 (July 2001) and Environmental Impact Assessment Executive Summary (July 2001) [Hereinafter referred to as the “EIA Report”] – Environmental Monitoring and Audit Manual (July 2001) [Hereinafter referred to as the “EM&A Manual”]
The Director’s letter of approval of the EIA Report dated 31 August 2001(ref (19) in Ax (4) to EP2/H4/C/09 II)
Application for an Environmental Permit No. AEP–122/2002
Environmental Permit Issued – Permit No.: EP-122/2002 issued on 7 March 2002
Application for Variation of
an Environmental Permit No. VEP-247/2007. [Hereafter referred to as “the Application No. VEP-247/2007”]
中環填海計劃第III期– 研究、實地堪測、設計與建築(登記冊編號:AEIAR-040/2001) – 環境影響評估報告第一冊及第二冊(2001年7月)及環境影響評估行政摘要(2001年7月) [下稱“環評報告”] – 環境監察及審核手冊(2001年7月) [下稱”環監手冊”]
環境保護署署長於2001年8月31日發出批准環評報告的信件(檔案編號: (19) in Ax (4) to EP2/H4/C/09 II)
申請環境許可證編號AEP-122/2002
已簽發的環境許可證– 許可證編號EP-122/2002; 於2002年3月7日簽發。
申請更改環境許可證編號 VEP-247/2007。 [下稱 “申請書編號 VEP-247/2007”] |
Application No. 申請 編號 |
Date of Application 申請 日期 |
List of Amendments Incorporated into Environmental
Permit 已包含在環境許可證內的修訂項目 |
Date of Amendments 修訂 日期 |
VEP-247/2007 |
30 November 2007 2007年11月30日 |
Vary Condition 3.3 in Part C of Environmental Permit
No. EP-122/2002 更改環境許可證編號EP-122/2002 C部第 3.3項條件。 |
27 December
2007 2007年12月27日 |
27-12-2007 |
|
|
Date 日期 |
|
(Mrs. Shirley
LEE) Principal
Environmental Protection Officer for Director
of Environmental Protection 環境保護署署長 (首席環境保護主任 李韓琇玲女士代行) |
PART B (DESCRIPTIONS OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱 “許可證”) A部所提述的指定工程項目的說明:
Title of Designated Projects 指定工程項目的名稱 |
1. Central Reclamation Phase III 2. Roads P1, P2, D6, D7, D8, D9 and D11 3. Central - Wan Chai Bypass Tunnel 4. North Island Line protection works
[This/these projects is/are hereinafter referred to as “the Project(s)”]
1. 中環填海計劃第III期 2. P1, P2, D6, D7, D8, D9 and D11公路 3. 中環及灣仔繞道隧道 4. 北港島線鐵路保護工程
|
|
Nature of Designated Projects |
1. Reclamation works (including associated dredging works) of about 18 ha in size. 2. About 1.05km of primary distributor and about 0.85km of district distributor. 3. About 0.95km of Central - Wan Chai Bypass Tunnel. 4. About 0.5km of North Island Line protection works.
1. 面積約為18公頃的填海工程(包括相聯的挖泥工程)。 2. 建造及營辦約1.05公里長的主要幹路及約0.85公里長的地區幹路。 3. 約0.95公里長的中環及灣仔繞道隧道。 4. 約0.5公里長的北港島線鐵路保護工程。 |
|
Location of Designated Projects 指定工程項目的地點 |
Central District in
港島的中環。工程項目的地點如本環境許可證的圖1至4所示。 |
|
Scale and Scope of Designated Project(s) 指定工程項目的規模和範圍 |
The Project(s) include reclamation of about 18ha of land in Central; construction and operation of about 1.05km of primary distributor and 0.85km of district distributor; construction of about 0.95km of Central – Wan Chai Bypass Tunnel; and construction of about 0.5km of North Island Line protection works.
工程項目包括:在中環進行面積約為18公頃的填海工程;建造及營辦約1.05公里長的主要幹路及約0.85公里長的地區幹路;建造約0.95公里長的中環及灣仔繞道隊道;及建造0.5公里長的北港島線鐵路保護工程。 |
|
|
|
|
1. General Conditions
1.1 The Permit Holder shall ensure full
compliance with all conditions of this environmental permit. Any non-compliance
may constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap. 499) and may become the subject of appropriate action being taken under
the Ordinance.
1.2 The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any ground of defense against any proceedings instituted under any legislation.
1.3 The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.
1.4 The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to the site(s) of the construction of the Project(s) and should mean the same hereinafter.
1.5 The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended Permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).
1.6 The Permit Holder shall construct the Project(s) as described in Part B of this Permit.
1.7 The Permit Holder shall ensure that the
Project(s) is/are designed, constructed and operated in accordance with the
information and recommendations described in the EIA Report (Register No.
AEIAR-040/2001); or mitigation measures described in this Permit, or mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, or mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project(s). Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8 All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director, within one month of the receipt of the Director’s comments or otherwise specified by the Director.
1.9 All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance. All submissions or any variations of the submissions shall be verified and certified by the Independent Environmental Checker (IEC) referred to in Condition 2.2 below, before submitting to the Director under this Permit.
1.10 The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.
1.11 The Permit Holder shall notify the Director in writing the commencement date(s) of construction of the Project(s) at least one week before the commencement of construction of the Project(s). The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date(s) of the construction.
1.12 All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.
2. Submissions or Measures before commencement of Construction of the Project(s)
2.1
An Environmental Team (ET) shall be established by the Permit Holder no
later than one month before the commencement of construction of the Project(s).
The ET shall not be in any way an associated body of the Contractor or the
Independent Environmental Checker (IEC) for the Project(s).The ET shall be
headed by an ET Leader. The ET Leader shall be a person who has at least 7
years' experience in environmental monitoring and auditing (EM&A) or
environmental management. The ET and the ET Leader shall be responsible for the
implementation of the EM&A programme in accordance with the requirements as
contained in the EM&A Manual. The ET Leader shall keep a contemporaneous
log-book of each and every circumstance or change of circumstances which may
affect the environmental impact assessment and each and every non-compliance
with the recommendations of the EIA Report or this Permit. This log-book shall
be kept readily available for inspection by all persons assisting in
supervision of the implementation of the recommendations of the EIA Report and
this Permit or by the Director or his authorized officers. Failure to maintain
records in the log-book, failure to discharge the duties of the ET Leader as
defined in the EM&A Manual or failure to comply with this Condition would
entitle the Director to require the Permit Holder by notice in writing to
replace the ET Leader. Failure by the Permit Holder to make replacement, or
further failure to keep contemporaneous records in the log-book despite the
employment of a new ET Leader may render the Permit liable to suspension,
cancellation or variation.
2.2 An IEC shall be employed by the Permit Holder no later than one month before the commencement of construction of the Project(s). The IEC shall not be in any way an associated body of the Contractor or the ET for the Project(s). The IEC shall be a person who has at least 7 years' experience in EM&A or environmental management. The IEC shall be responsible for duties defined in the EM&A Manual and shall audit the overall EM&A programme, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit. The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by fax, within 24 hours of each and every change of circumstances or non-compliance with the recommendations of the EIA Report or this Permit, which might affect the monitoring or control of adverse environmental impacts from the Project(s). In case the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation. Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition.
3. Submissions or Measures for the Construction Period of the Project(s)
3.1 The Permit Holder shall, within 4 weeks after the commencement of construction of the Project(s), inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project(s). The submitted information shall include at least an organization chart, names of responsible persons and their contact details.
3.2
The
Permit Holder shall carry out dredging and filling works in phases for the
Project(s) in accordance with:
(a) the sequence shown in Figure 5 to avoid formation of embayed water bodies and prevent water pollution problems; and
(b) the specified maximum dredging and filling volumes together with the maximum hourly dredging rates for each phase of activities shown in Table 1.
Any changes to the dredging and filling requirements in items (a) and (b) above shall be certified by the ET Leader and verified by the IEC as conforming to the recommendations contained in the EIA report. The changes shall be immediately documented in the following monthly EM&A report and be made available to the public, following the requirements in Conditions 5.2 and 5.3 below, via internet access in the shortest possible time and in no event later than 2 weeks after the changes have been certified.
3.3 All underwater filling works using marine sand shall be carried out behind seawalls to avoid dispersion of suspended solids into the sea outside the works limit. The seawalls shall be located in accordance with Figure 5 and shall be substantially completed with their top levels above +2.5mPD at the time of filling. All filling works shall be at least 100m or more from any incomplete section of the seawall leading to the sea. In the event that the aforesaid conditions cannot be achieved, suitable silt curtains shall be provided around the filling works to prevent the dispersion of suspended solids.
All underwater filling works using public fill shall be carried out behind fully enclosed seawalls, with their top levels above +2.5mPD at the time of filling. The locations of these fully enclosed seawalls are shown in Figure 5.
Alternatively, the Permit Holder may use "Type A Fill" for underwater filling works in the Final Reclamation Area West (FRAW) as shown in Figure 5 meeting the following requirements to reduce the potential water quality impacts:
i. 'Type
A Fill' shall be natural soil material;
ii. 'Type
A Fill' shall have less than 20% (by mass) of its particles passing through a
0.063mm sieve;
iii. The
Permit Holder shall carry out the filling works behind seawalls to avoid
dispersion of suspended solids into the sea outside the works limit. The
seawalls shall be located in accordance with Figure
5 and shall be substantially completed with their top levels above +2.5mPD
at the time of filling;
iv. All
filling works shall be at least 100m or more from any incomplete section of the
seawall leading to the sea;
v. The
filling rate shall not be greater than 7,000m3 per day;
vi. The
fill material shall be sprayed with water to increase the water content;
vii. The
filling operation through split hopper barges shall be carried out at an
interval of not less than 1 hour in order to avoid the build up of suspended
solids within the FRAW;
viii. The
filling works area shall be fully enclosed by a layer of silt curtain to
control the release of suspended solids out of the works area. The silt curtain shall extend from the
water surface to the seabed;
ix. Two
layers of silt curtains shall be installed across the gap(s) left by incomplete
section(s) of the seawall. The
silt curtains shall extend from the water surface to the bottom of the seawall
gap(s) to control the release of suspended solids into the
x. The
Permit Holder shall deposit with the Director an operation plan for the silt
curtain system mentioned in (viii) and (ix) above. The plan shall be deposited at least 1 week prior to the
commencement of the filling works using the 'Type A Fill'. The operation plan
shall take into account the opening and closing of the silt curtains to allow
for the essential movement of marine vessels within the FRAW while reducing the
potential dispersion of suspended solids out of the filling works area or into
the harbour.
To ensure that the use of 'Type
A Fill' will not result in unacceptable water quality impact, an additional
water quality monitoring programme shall be implemented to monitor the
effectiveness of the control and mitigation measures. The additional water quality monitoring programme plan shall
be certified by the ET Leader and verified by the IEC as adequate to monitor
the effectiveness of the measures and allow triggering of follow up actions to
avoid unacceptable impacts. The monitoring programme plan shall be deposited
with the Director at least 1 week before the commencement of the filling works
using 'Type A Fill'. The supplementary
water quality programme shall form part of the EM&A programme stated in
Condition 4.1 of this Permit.
3.4 Closed grab dredgers shall be used during dredging of the Project(s) to avoid dispersion of suspended solids into the sea.
3.5 The Permit Holder shall properly maintain all
barges for transporting dredged materials for the Project(s) to prevent leakage
of fill materials to the sea during loading and transport.
3.6 The Permit Holder shall not stockpile any dredged marine sediment on site to avoid runoff and odour nuisances.
3.7 The Permit Holder shall install silt screens at
the cooling water intakes and Wan Chai WSD intake, with locations shown in Figure 6, when carrying out dredging works
of the Project(s) to prevent suspended solids from being drawn into the above
intakes. The Permit Holder shall properly maintain the silt screens and
regularly remove the floating debris and any substances blocking the screens
until completion of the dredging and filling works of the Project(s).
3.8 In addition to the measures required in
Condition 3.7, where dredging works of the Project(s) is to be carried out
concurrently with that of the Wan Chai Development Phase II project (of which
the location is shown in Figure 1), the
Permit Holder shall install silt curtains around dredging locations in the
Project(s) to prevent dispersion of suspended solids into the sea. The Permit
Holder shall properly maintain the silt curtains and regularly remove the
floating debris and any substances blocking the curtains until the completion
of the dredging works of the Project(s) and the Wan Chai Development Phase II
project.
3.9 Upon completion of the eastern seawall of
the Project(s) as shown in Figure 7, the
Permit Holder shall use silt curtain(s) that extend from the water surface to
the seabed to channel water discharge flow from Culvert L to locations outside
the embayment area shown in Figure 7.
The Permit Holder shall properly maintain the silt curtain(s) until the Wan
Chai Development Phase II contractor takes possession of the above embayment
area.
3.10 The
Permit Holder shall collect floating debris within the works limit of the Project(s)
shown in Figure 1 at least once everyday
during the reclamation period. In the water body near the cooling water
intakes, the Permit Holder shall collect debris at least three times a day to
prevent accumulation of large debris which would affect the intake operations.
The frequency of collecting floating debris shall be documented in the monthly
EM&A reports and be made available to the public, following the
requirements in Conditions 5.2 and 5.3 below, via internet access in the
shortest possible time and in no event later than 2 weeks after
implementation.
3.11
The Permit Holder shall
deposit with the Director 3 sets of drawings of appropriate scales, say 1:500,
showing the exact locations and details of temporary noise barriers to mitigate
construction noise impacts on the Central Barracks and City Hall respectively
from the following works (as shown in Figures
8 to 10):
(a) Road P2 and drainage works to the north of Central Barrack (Figure 8);
(b) Central-Wan Chai Bypass and drainage works to the north of Central Barrack (Figure 8);
(c) Hong Kong Station Extended Overrun Tunnels to the north of Central Barracks (Figure 9);
(d) North Island Line protection works to the north of Central Barracks (Figure 9); and
(e) Culvert F extension piling works to the north of City Hall (Figure 10).
The
temporary noise barriers shall be in the form of site hoardings, with heights
ranging from 3 to 5 m, surface density of at least 7 kg/m2 and
cranked top.
The drawings showing the temporary noise barriers shall be certified by the ET Leader and verified by the IEC as conforming to the conclusions and recommendations in the EIA Report. These drawings shall be deposited with the Director at least one month before the construction of the above works.
3.12 The Permit Holder shall construct and place the
temporary noise barriers required in Condition 3.11 as close as possible to the
works described in the same condition to mitigate construction noise impacts on
the Central Barracks and City Hall respectively.
4. Environmental Monitoring and Audit (EM&A) during the Construction Period
4.1 The Permit Holder shall implement the
EM&A programme in accordance with the procedures and requirements in the
EM&A Manual. Any changes to the programme shall be justified by the IEC as
conforming to the requirements set out in the EM&A Manual and shall be
approved by the Director.
4.2 At least 2 weeks before the
commencement of any construction works, the Permit Holder shall set up a
continuous noise monitoring mechanism to the satisfaction of the Director. The mechanism
shall include a system to report the monitoring results on a website within a
period of 2 working days, after the relevant noise monitoring data are
collected or become available. This system shall be provided throughout the
entire construction period. In the event that the measured noise levels exceed
the worst case scenario(s) predicted in the EIA report, the Permit Holder shall
take immediate action(s) to activate remediation measures following the
procedures specified in the EM&A Manual.
4.3 The Permit Holder shall
take samples and measurements in accordance with the requirements in the
EM&A Manual by:
(a) conducting baseline
monitoring on water quality, noise and air quality as set out in the EM&A
Manual;
(b) conducting
impact monitoring on water quality, noise and air quality as set out in the
EM&A Manual;
(c) carrying
out remedial actions in accordance with the Event/Action Plans, as set out in
the EM&A Manual, in cases where specified criteria in the EM&A Manual
are exceeded; and
(d) logging
and keeping records of the details of (a) to (c) above for all parameters
except for construction noise, within 3 working days of the collection of data
or completion of remedial action(s), for the purposes of preparing and
submitting the monthly EM&A Reports and to make available the information
for inspection on site.
4.4 All environmental
monitoring and audit data submitted under this Permit shall be true and
correct.
4.5 Two hard copies and one electronic
copy of the Baseline Monitoring Report shall be submitted to the Director at
least 2 weeks before the commencement of any construction works. The
submissions shall be verified and certified by the IEC. Additional copies of
the submission shall be provided to the Director upon request from the
Director.
4.6 Two hard copies and one
electronic copy of monthly EM&A Report shall be submitted to the Director
within 2 weeks after the end of the reporting month. The submission shall be
certified by the ET Leader and verified by the IEC. Additional copies of the
submission shall be provided to the Director upon request from the
Director.
4.7 The
Permit Holder shall fully and properly carry out actions described in the
Event/Action Plans of the EM&A Manual, in accordance with the time frame
set out in the Event/Action Plans, or as agreed by the Director.
5. Electronic Reporting of EM&A Information
5.1 To facilitate public inspection of the Baseline
Monitoring Report and monthly EM&A Reports via the EIAO Internet Website
and at the EIAO Register Office, electronic copies of these Reports shall be
prepared in Hyper Text Markup Language (HTML)(version 4.0 or later) and in
Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by
the Director and shall be submitted at the same time as the hard copies as
described in Conditions 4.5 and 4.6 of this Permit. For the HTML version, a
content page capable of providing hyperlink to each section and sub-section of
these Reports shall be included in the beginning of the document. Hyperlinks to
all figures, drawings and tables in these Reports shall be provided in the main
text from where the respective references are made. All graphics in these
Reports shall be in interlaced GIF format unless otherwise agreed by he
Director. The content of the electronic copies of these Reports must be the
same as the hard copies.
5.2 All environmental monitoring data described in
Condition 5.1 above, except for construction noise data described in Condition
4.2 in which reporting is required within 2 working days, shall be made
available to the public via internet access in the shortest possible time and
in no event later than 2 weeks after the relevant environmental monitoring data
are collected or become available, unless otherwise agreed with the Director.
The Permit Holder shall notify the Director in writing, within 6 weeks after
the commencement of works, the internet address where the environmental
monitoring data are to be placed. The internet address and the relevant
environmental monitoring data shall be made available to the public via the
EIAO Internet Website and the EIAO Register Office.
5.3 The
internet website as described in Condition 5.2 above shall enable user-friendly
public access to the monitoring data with features capable of :
(a) providing access to all environmental monitoring data collected since the commencement of works;
(b) searching by date;
(c) searching by types of monitoring data (water quality, noise and air quality); and
(d) hyperlinks to relevant monitoring data after searching;
or otherwise as agreed by the Director.
Notes :
1. This Permit
consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project(s)) and PART C (Permit Conditions). Any person relying on this permit
should obtain independent legal advice on the legal implications under the
Ordinance, and the following notes are for general information only.
2. The Permit Holder may
apply under Section 13 of the Ordinance to the Director for a variation of the
conditions of this Permit. The Permit Holder shall replace the original permit
displayed on the construction site by the amended permit.
3. A person who assumes the
responsibility for the whole or a part of the designated project(s) may, before
he assumes responsibility of the designated project(s), apply under Section 12
of the Ordinance to the Director for a further environmental permit.
4. Under Section 14 of the
Ordinance, the Director may with the consent of the Secretary for the
Environment and Food, suspend, vary or cancel this Permit. The suspended, varied
or cancelled Permit shall be removed from display at the construction site.
5. If this Permit is
cancelled or surrendered during construction or operation of the Project(s),
another environmental permit must be obtained under the Ordinance before the
Project(s) could be continued. It is an offence under Section 26(1) of the
Ordinance to construct or operate a designated project listed in Part I of
Schedule 2 of the Ordinance without a valid environmental permit.
6. Any person who constructs or operates the
Project(s) contrary to the conditions in the Permit, and is convicted of an
offence under the Ordinance, is liable :
(i)
on a first conviction on
indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii)
on a second or
subsequent conviction on indictment to a fine of $ 5 million and to
imprisonment for 2 years;
(iii)
on a first summary
conviction to a fine at level 6 and to imprisonment for 6 months;
(iv) on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v) in any case where the offence is of a
continuing nature, the court or magistrate may impose a fine of $ 10,000 for
each day on which he is satisfied the offence continued.
7. The Permit Holder may
appeal against any condition of this Permit under Section 17 of the Ordinance
within 30 days of receipt of this Permit.
8. The Notes are for
general reference only and that the Permit Holder should refer to the EIA
Ordinance for details and seek independent legal advice.
Environmental Permit No. EP-122/2002/A
環境許可證編號 EP-122/2002/A
Table 1 : Dredging and Filling Schedules
(Modified from Table 10.14 of the EIA report)
Stage |
@Description of activities |
Maximum dredging volume (m3) |
Maximum filling volume (m3) |
Maximum hourly dredging rate (m3/hour) |
1 |
Dredge
Initial Reclamation Area West |
100,000 |
- |
98 |
2 |
Fill
Initial Reclamation Area West |
- |
250,000 |
- |
Dredge
Initial Reclamation Area East |
180,000 |
- |
176 |
|
3 |
Fill
Initial Reclamation Area East |
- |
780,000 |
- |
4 |
Dredge
Final Reclamation Area West |
200,000 |
- |
184 |
5 |
Fill
Final Reclamation Area West |
- |
425,000 |
- |
Dredge
Final Reclamation Area East |
100,000 |
- |
98 |
|
6 |
Fill
Final Reclamation Area East |
- |
780,000 |
- |
@ This should be read in
conjunction with Figure 5.
| Figure
1 | Figure 2 | Figure 3 | Figure 4 | Figure 5 | Figure 6 | Figure 7 | Figure 8 | Figure 9 | Figure 10 |