Environmental Permit No. FEP-01/272/2007/B
環境許可證編號FEP-01/272/2007/B
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
Sections 10 & 13
環境影響評估條例
(第499章)
第 10 及13 條
FURTHER ENVIRONMENTAL PERMIT TO CONSTRUCT A
DESIGNATED PROJECT
建造指定工程項目的新的環境許可證
A部 (許可證主要部分)
Pursuant to
Sections 10 and 12 of the Environmental Impact Assessment Ordinance (the
Ordinance), the Director of Environmental Protection (the Director) grants the
Further Environmental Permit (No. FEP-01/272/2007/A) to Dragages – Nishimatsu Joint Venture (hereinafter referred to
as the “Permit Holder”) on 28 January 2008. Pursuant to Section 13 of the
Ordinance, the Director amends the Further Environmental Permit (No. FEP-01/272/2007/A)
based on the Application No. VEP-290/2009. The amendments described below, are
incorporated into this Environmental Permit (No. FEP-01/272/2007/B). This
Environmental Permit as amended is for the construction of the designed project
described in Part B of this Permit subject to the conditions described
in Part C of this Permit.
根據《環境影響評估條例》(環評條例)第10及12 條的規定,環境保護署署長(署長)於
The issue of this Environmental Permit is
based on the documents, approvals or permissions described below:
本新的環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:
Application
No. 申請書編號: |
VEP-290/2009 |
Document in
the Register: 登記冊上的文件: |
(1) Drainage Improvement in (1) 港島北部雨水排放系統改善計劃港島西雨水排放隧道(登記冊檔號: AEIAR-099/2006) [下稱”環評報告”] (2) The Director’s letter of approval of
the EIA report dated 7 April 2006 [Ref.: (28) in EP2/G/I/113] (2) 署長於 (3) Application documents for Environmental Permit
submitted by the Permit Holder on 30 March 2007 (Application No.
AEP-272/2007) [Hereinafter referred to as “the EP Application Document”] (3) 許可證持有人於 (4) Environmental Permit issued on 26 April 2007
(No. EP-272/2007) (4) 於 (5) Application documents for Variation of
Environmental Permit submitted by the Permit Holder on 9 October 2007
(Application No. VEP-241/2007) [Hereinafter referred to as “the VEP
Application Document (VEP – 241/2007)”] (5) 許可證持有人於 (6) Environmental Permit issued on (6) 於 (7) Application for Further Environmental Permit
submitted on 10 January 2008 (Application No. FEP-086/2008) for construction
of the designated project (7) 於 (8) Environmental Permit
issued on 28 January 2008 (No. FEP-01/272/2007/A) for construction of the
designated project (8) 於 (9) Application documents
for Variation of Environmental Permit submitted by the Permit Holder on 11
June 2009 (Application No. VEP-290/2009) [Hereinafter referred to as “the VEP
Application Document (VEP-290/2009)”] (9) 許可證持有人於 |
|
Application No. 申請書編號: |
Date of Application 申請日期 |
List of Amendments Incorporated into this
Environmental Permit 已包含在本環境許可證內的修訂項目 |
Date of Amendment 修訂日期 |
||
|
VEP-290/2009 |
|
Vary Condition 更改在環境許可證編號FEP-01/272/2007/A C部的第2.9項條件。 Amend the Figure 3 attached to the Environmental
Permit (No. FEP-01-272/2007/A). |
25 June 2009 2009年6月25日 |
||
25 June 2009 __________________________________
Date 日期 |
|
(Mrs. Shirley LEE) Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任 李韓琇玲女士代 行) |
||||
PART B (DESCRIPTIONS OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project mentioned in
Part A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of
Designated Project 指定工程項目的名稱 |
Drainage
Improvement in 港島北部雨水排放系統改善計劃 - 港島西雨水排放隧道 [這指定工程項目下稱“工程項目”] |
Nature of
Designated Project |
To construct
and operate a main drainage tunnel and adits within the boundary of the Pok
Fu Lam, Tai Tam, Aberdeen and Lung Fu Shan Country Parks 於薄扶林、大潭、香港仔及龍虎山郊野公園範圍內建造及營辦雨水排放主隧道及連接隧道。 |
Location of
Designated Project 指定工程項目的地點 |
The drainage
tunnel alignment starts from the Eastern Portal near Haw Par Mansion in Tai
Hang and ends at the Western Portal located to the north of Cyberport running
underneath the the Pok Fu Lam, Tai Tam, Aberdeen and Lung Fu Shan Country
Parks. The locations of the main drainage tunnel, two portals and the
country parks are shown in Figures 1 to 3
attached to this Permit. 雨水排放隧道的起點始於大坑虎豹別墅邊旁的東面入水口,終點於西面出水口位於數碼港以北,途經薄扶林、大潭、香港仔及龍虎山郊野公園。主隧道、兩個出入水口及郊野公園的位置見載於本許可證夾附的圖1至3。 |
Scale and Scope
of Designated Project(s) 指定工程項目的規模和範圍 |
Construction of
a 建造一條直徑6.25至7.25米、約長11千米的地下雨水排放主隧道、兩個出入水口及一系列連接隧道及豎井。 |
1. General
Conditions
1.1 The
Permit Holder and any person working on the Project shall comply with all
conditions set out in this Permit. Any non-compliance by any person may
constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap. 499) and may become the subject of appropriate action being taken under
the Ordinance.
1.2 The Permit Holder
shall ensure full compliance with all legislation from time to time in force
including without limitation to the Noise Control Ordinance (Cap. 400), Air
Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap.
358), Waste Disposal Ordinance (Cap. 354) and Country Parks Ordinance (Cap.
208). This Permit does not of itself constitute any ground of defence against
any proceedings instituted under any legislation or imply any approval under
any legislation.
1.3 The Permit Holder
shall make copies of this Permit together with all documents referred to in
this Permit or the documents referred to in Part A of the Permit readily
available at all times for inspection by the Director or his authorised
officers at all sites/offices covered by this Permit. Any reference to
the Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
1.4 The Permit Holder
shall give a copy of this Permit to the person(s) in charge of the site(s) and
ensure that such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The site(s) refers to site(s) of construction of
the Project and shall mean the same hereafter.
1.5 The Permit Holder
shall display conspicuously a copy of this Permit on the construction site(s)
at all vehicular site entrances/exits or at a convenient location for public
information at all times. The Permit Holder shall ensure that the most
updated information about the Permit, including any amended permit, is
displayed at such locations. If the Permit Holder surrenders a part or the
whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied
or cancelled Permit shall be removed from display at the construction site(s).
1.6 The Permit Holder
shall construct the Project in accordance with the project descriptions in Part
B of this Permit.
1.7 The Permit Holder
shall ensure that the Project is designed and constructed in accordance with
the information and all recommendations described in the EIA Report (Register
No.: AEIAR-099/2006), the EP
Application Document, the VEP Application Documents, other relevant documents in
the Register, the information or mitigation measures described in this Permit,
mitigation measures to be recommended in submissions that shall be deposited
with the Director as a result of permit conditions contained in this Permit,
and mitigation measures to be recommended under on going surveillance and
monitoring activities during construction stage of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8 All submissions, as
required under this Permit, shall be rectified and resubmitted in accordance
with the comments, if any, made by the Director within one month of the receipt
of the Director’s comments or otherwise specified by the Director.
1.9 All submissions
deposited without comments by the Director, or all submissions rectified in
accordance with comments by the Director under this Permit shall be construed
as part of the permit conditions described in Part C of this Permit.
Any variation of the submissions shall be approved by the Director in writing
or as prescribed in the relevant permit conditions. Any non-compliance
with the submissions may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap. 499). All submissions or any variation of the
submissions shall be certified by the Environmental Team (ET) Leader and
verified by the Independent Environmental Checker (IEC) referred to in
Conditions 2.1 and 2.2 below, before submitting to the Director under this
Permit.
1.10 The Permit Holder
shall release all finalized submissions, as required under this Permit, to the
public by depositing copies in the Environmental Impact Assessment Ordinance
Register Office, or in any other place, or any internet websites as specified
by the Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient
copies of the submissions.
1.11 All submissions to
the Director required under this Permit shall be delivered either in person or
by registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong
Kong). Electronic copies of all finalized submissions required under this
Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 1.3 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as
hard copies.
1.12 The Permit Holder
shall notify the Director in writing the commencement date of construction of
the Project at least two weeks before the commencement of construction of the
Project, the Eastern Portal and the marine-based works at Western Portal.
The Permit Holder shall notify the Director in writing immediately if there is
any change of the commencement date of the construction.
1.13 For the purpose of
this Permit, “commencement of construction” does not include works related to
site clearance and preparation, or other works as agreed by the Director.
2. Special Conditions
2.1 An
ET shall be established no later than one month before commencement of
construction of the Project. The ET shall not be in any way an associated body
of the Contractor or the IEC for the Project. The ET shall be headed by an ET
Leader. The ET leader shall be a person who has at least 7 years of
experience in environmental monitoring and auditing (EM&A) or environmental
management. The ET and the ET Leader shall be responsible for the
implementation of the EM&A programme in accordance with the requirements as
contained in the EM&A Manual (Register No. AEIAR-099/2006) of the
Project. In addition, the ET Leader shall be responsible for certifying
the environmental acceptability of permanent and temporary works, relevant
design plans and submissions under this Permit. The ET Leader shall keep
a contemporaneous log-book of each and every instance or circumstance or change
of circumstances which may affect the environmental impact assessment and each
and every non-compliance with the recommendations of the approved EIA Report
(Register No. AEIAR-099/2006), the EP Application Document and the VEP
Application Documents, or this Permit. The ET Leader shall notify the
Independent Environmental Checker (IEC) within one working day of the
occurrence of any such instance or circumstance or change of circumstances. The
ET Leader’s log-book shall be kept readily available for inspection by all
persons assisting in supervision of the implementation of the recommendations
of the approved EIA Report (Register No. AEIAR-099/2006), the EP Application
Document and the VEP Application Documents, or this Permit or by the Director
or his authorized officers. Failure to maintain records in the log-book,
failure to discharge the duties of the ET Leader as defined in the EM&A
Manual or failure to comply with this Condition would entitle the Director to
require the Permit Holder by notice in writing to replace the ET Leader.
Failure by the Permit Holder to make replacement, or further failure to keep
contemporaneous records in the log-book despite the employment of a new ET
Leader may render the Permit liable to suspension, cancellation or variation.
2.2 An
IEC shall be employed no later than one month before commencement of
construction of the Project. The IEC shall not be in any way an associated body
of the Contractor or the ET for the Project. The IEC shall be a person who has
at least 7 years of experience in EM&A or environmental management. The IEC
shall be responsible for duties defined in the EM&A Manual (Register No.
AEIAR-099/2006) of the Project and shall audit the overall EM&A programme,
including the implementation of all environmental mitigation measures,
submissions required in the EM&A Manual, and any other submissions required
under this Permit. In addition, the IEC shall be responsible for verifying the
environmental acceptability of permanent and temporary works, relevant design
plans and submissions under this Permit. The IEC shall verify the log-book(s)
mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by
fax, within one working day of receipt of notification from the ET Leader of
each and every occurrence, change of circumstances or non-compliance with the
approved EIA Report (Register No.AEIAR-099/2006), the EP Application Document
and the VEP Application Documents, or this Permit, which might affect the
monitoring or control of adverse environmental impacts from the Project.
In the case where the IEC fails to so notify the Director of the same, fails to
discharge the duties of the IEC as defined in the EM&A Manual or fails to
comply with this Condition, the Director may require the Permit Holder by
notice in writing to replace the IEC. Failure to replace the IEC as directed or
further failure to so notify the Director despite employment of a new IEC may
render the Permit liable to suspension, cancellation or variation. Notification
by the Permit Holder is the same as notification by the IEC for the purpose of
this Condition.
2.3 The
Permit Holder shall, no later than two weeks before the commencement of
construction of the Project, inform the Director in writing the management organization
of the main construction companies and/or any form of joint ventures associated
with the construction of the Project. The submitted information shall
include at least an organization chart, names of responsible persons and their
contact details.
2.4 The
Permit Holder shall, no later than two weeks before the commencement of
construction of the Project, deposit with the Director six hard copies and one
electronic copy of the construction programme showing the commencement and
completion dates of major items of construction works and the relevant
mitigation measures to be implemented. The construction programme shall
be certified by the ET Leader and verified by the IEC as conforming to the
information, requirements and recommendations set out in the approved EIA
report (Register No. AEIAR-099/2006) and the EP Application Document. The
Permit Holder shall inform the Director accordingly in writing in case of any
subsequent changes of items contained in this submitted construction programme.
2.5 A community liaison
office shall be set up and remain in operation throughout the entire
construction stage of the Project to receive and respond to complaints or
enquiries on environmental nuisances or pollution caused by the Project and to
follow up on the implementation of remedial mitigation measures.
Mitigation measures for constructing the
main drainage tunnel
2.6 To
protect the country parks, no construction works shall be carried out on the
ground surface within Tai Tam,
2.7 To
minimize seepage of groundwater and to avoid potential drawdown of the
watertable during construction of the main drainage tunnel, a double-shielded
Tunnel Boring Machine shall be adopted to construct the tunnel. If
alternative construction method is to be proposed, the Permit Holder shall
deposit six hard copies and one electronic copy of the method statement with
the Director no later than one month before commencement of the main drainage
tunnel construction. Before submission to the Director, the method
statement shall be certified by the ET Leader and verified by the IEC to
confirm its effectiveness in avoiding drawdown of the watertable.
Mitigation measures for constructing the
Eastern and Western Portals
2.8 To
minimize construction noise impacts, the Permit Holder shall:-
(a) deposit
four hard copies and one electronic copy of a noise enclosure design plan with
the Director no later than 2 weeks before commencement of construction works at
the Eastern Portal. This noise enclosure deign plan shall show: the
location/layout (in the scale of 1:1000) and design details (in the scale of 1:50
or other appropriate scale) of the noise enclosure; and specifying the material
used for the noise enclosure. The superficial surface density of the
material shall be no less than
(b) provide
the noise enclosure at the Eastern Portal in accordance with the submission
deposited under Condition 2.8(a) above; and
(c)
use only quiet plants that shall meet noise performance specifications as
stated below to construct the Eastern and Western Portals:
(i) Air compressor with Sound Power Level
(SWL) not exceeding 103dB(A);
(ii) Hydraulic breaker with SWL not
exceeding 110dB(A);
(iii) Bulldozer with SWL not
exceeding 104dB(A);
(iv) Concrete lorry mixer with SWL not exceeding
100dB(A);
(v) Concrete pump with
SWL not exceeding 107dB(A);
(vi) Truck with SWL not exceeding
104dB(A);
(vii) Excavator with SWL not exceeding 106dB(A);
(viii) Wheeled loader with SWL
not exceeding 106dB(A);
(ix) Poker with SWL not exceeding
100dB(A);
(x) Electric saw, wood with
SWL not exceeding 106dB(A); and
(xi) Crane, lorry with SWL
not exceeding 102dB(A).
If other plant/plants not specified above
is/are to be used, the noise performance of this alternative proposal shall be
certified by the ET Leader and verified by the IEC as conforming to the
information, requirements and recommendations as set out in the approved EIA
report and the EP Application Document.
2.9
To minimize
water quality impacts on the marine environment near the western waters due to
the construction of the Western Portal, the Permit Holder shall:
(a)
deposit
four hard copies and one electronic copy of a silt curtain proposal with the
Director no later than 2 weeks before commencement of the marine-based
construction works at Western Portal.
The silt curtain shall enclose the site areas targeted for constructing the temporary pier and the armour rock based panel, and
for demolishing the temporary pier (see Note 7). Their respective locations are shown in Figure
3 attached to this permit.
The silt curtain proposal shall specify the
following:
(i)
location
and alignment of the silt curtain system as shown in drawings in the scale of
1:1000;
(ii)
design
details as shown in drawings in scale of 1:50 or other appropriate scale;
(iii)
inspection
requirement to ensure proper functioning of silt curtain system; and
(iv)
rectification
requirements in case of any malfunctioning of the system.
Before submission to the Director, the silt curtain proposal shall be certified
by the ET Leader and verified by the IEC as conforming to the information,
requirements and recommendations as set out in the approved EIA report and the VEP
application document (VEP-290/2009);
(b)
install
and maintain the silt curtain system in accordance with the proposal as
submitted under Condition 2.9(a) above.
The silt curtain system may be removed after the completion of construction
of the temporary pier, and when there is no marine-based construction works being
carried out at the Western Portal; and
(c)
carry
out all construction works for the stilling basin by enclosing the entire basin
inside a watertight enclosure in the form of a temporary cofferdam or a temporary
pier seawall, to avoid spillage of fill material or wastewater into the
sea. The top level of the watertight
enclosure shall be constructed higher than the final backfilled level. The watertight enclosure shall be maintained
on site and inspected to ensure its proper functioning until after the
completion of construction of the stilling basin.
3.
Environmental Monitoring and Audit (EM&A) Requirements
3.1 The
EM&A programme of the Project covering air quality, noise, water quality,
waste management, ecology, cultural heritage, landscape and visual during the
construction stage, shall be implemented in accordance with the procedures and
requirements as set out in the EM&A Manual (Register No. AEIAR-099/2006) of
the Project. The Permit Holder shall review the EM&A requirements or
programme based on the submitted construction programme required under
Condition 2.4. Changes to the EM&A requirements or programme and
termination of the programme shall need justification by the ET Leader and
verified by the IEC to their conformance with the requirements as set out in
the EM&A Manual; and the prior approval from the Director shall be sought
before their implementation.
3.2
Six hard copies and one electronic copy of the Baseline Monitoring Report shall
be submitted to the Director at least two weeks before the commencement of
construction. The submissions shall be certified by the ET Leader and verified
by the IEC as complied with the requirements as set out in the EM&A Manual
before submission to the Director. Additional copies of the submission shall be
provided upon request by the Director.
3.3 Six
hard copies and one electronic copy of the monthly EM&A Reports for the
construction stage shall be submitted to the Director within two weeks after
the end of the reporting month. The monthly EM&A Reports shall include a
summary of all non-compliance with the recommendations in the EIA Report or
this Permit. The submissions shall be certified by the ET Leader and verified
by the IEC as complied with the requirements as set out in the EM&A Manual
before submission to the Director. Additional copies of the submission shall be
provided upon request by the Director.
3.4 All
environmental monitoring and audit results submitted under this Permit shall be
true, valid and correct.
3.5 Any
necessary remedial measures and actions as described in the EM&A Manual
shall be fully and properly carried out, in accordance with the time frame(s)
set out in the EM&A Manual, or as agreed by the Director.
3.6 For
timely access of information by the affected community, the Permit Holder shall
make the impact monitoring results available to the public via internet access
to be set up under Conditions 4.2 and 4.3 below. The monitoring data
shall be certified by the ET Leader and verified by the IEC before releasing to
the public, in the shortest practicable time and in no event later than 2 weeks
after such information is available.
4. Electronic
Reporting of EM&A Information
4.1 To
facilitate public inspection of the Baseline Monitoring Report and the monthly
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in the Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies as described in Conditions 3.2
and 3.3 of this Permit. For the HTML version, a content page capable of
providing hyperlink to each section and sub-section of these Reports shall be
included in the beginning of the document. Hyperlinks to all figures,
drawings and tables in these Reports shall be provided in the main text from
where the respective references are made. All graphics in these Reports
shall be in interlaced GIF format unless otherwise agreed by the Director. The
content of the electronic copies of these Reports must be the same as the hard
copies.
4.2 A
dedicated web site shall be set up and the Director shall be notified in
writing the internet address where the environmental monitoring and project
data is to be placed within six weeks after the commencement of construction of
the Project. All environmental monitoring results described in Condition 4.1
above and all submissions required by this Permit shall be made available to
the public via this dedicated web site in the shortest time practicable, and in
no event later than 2 weeks after the relevant environmental monitoring data
are collected or become available, unless otherwise agreed with the
Director. The dedicated website shall be maintained throughout the entire
construction stage to facilitate public access to environmental monitoring
data.
4.3 The
internet website as described in Condition 4.2 above shall enable user-friendly
public access to the monitoring data and project data including the EIA report,
the environmental permit(s) and project profile of the Project. The internet
website shall have features capable of:
(a) providing access to all environmental
monitoring data collected since the commencement of work and all submissions
under this permit;
(b) searching by date;
(c) searching by types of monitoring
data; and
(d) hyperlinks to relevant monitoring data
after searching;
or otherwise as agreed by the Director.
Notes :
1. This Permit consists of three parts,
namely, PART A (Main Permit), PART B (Description of Designated Project) and
PART C (Permit Conditions). Any person relying on this Permit should obtain
independent legal advice on the legal implications under the Ordinance, and the
following notes are for general information only.
2. If there is a breach of any
conditions of this Permit, the Director or his authorized officer may, with the
consent of the Secretary for the Environment, order the cessation of associated
work until the remedial action is taken in respect of the resultant
environmental damage, and in that case the Permit Holder shall not carry out
any associated works without the permission of the Director or his authorized
officer.
3. The Permit Holder may apply under
Section 13 of the Ordinance to the Director for a variation of the conditions
of this Permit. The Permit Holder shall replace the original permit displayed
on the construction site by the amended permit.
4. A person who assumes the
responsibility for the whole or a part of the designated project may, before he
assumes responsibility of the designated project, apply under Section 12 of the
Ordinance to the Director for a further environmental permit.
5. Under Section 14 of the Ordinance, the
Director may with the consent of the Secretary for the Environment, suspend,
vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site.
6.
If this Permit is cancelled or surrendered during
construction or operation of the Project, another environmental permit must be
obtained under the Ordinance before the construction or operation of the
Project could be continued. It is an offence under Section 26(1) of the
Ordinance to construct or operate a designated project listed in Part I of
Schedule 2 of the Ordinance without a valid environmental permit.
7.
Dragages
– Nishimatsu Joint Venture, holder of the Environmental Permit
FEP-01/272/2007/A for the construction of the Project, deposited the silt
curtain proposal for the construction of the temporary pier in the
Environmental Impact Assessment Register Office on 13 June 2008.
8.
Any person who constructs
the Project contrary to the conditions in the Permit, and is convicted of an
offence under the Ordinance, is liable: -
(i) on
a first conviction on indictment to a fine of $2 million and to imprisonment
for 6 months;
(ii) on a second or
subsequent conviction on indictment to a fine of $5 million and to imprisonment
for 2 years;
(iii) on a first summary
conviction to a fine at level 6 and to imprisonment for 6 months;
(iv) on a second or subsequent
summary conviction to a fine of $1 million and to imprisonment for 1 year; and
(v) in any case where the offence
is of a continuing nature, the court or magistrate may impose a fine of $10,000
for each day on which he is satisfied the offence continued.
9. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the Ordinance within 30 days of receipt of this Permit.
10. The
Notes are for general reference only and that the Permit Holder should refer to
the EIA Ordinance for details and seek independent legal advice.