Environmental Permit No. EP-315/2008/A
環境許可證編號EP-315/2008/A
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10 & 13
環境影響評估條例
(第499章)
第10及13條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) granted the environmental permit (No. EP-315/2008) to the Architectural Services Department (hereinafter
referred to as the “Permit Holder”) on
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)於2008年9月10日將環境許可證(編號EP-315/2008)批予建築署(下稱“許可證持有人”)。根據環評條例第13條的規定,署長因應更改環境許可證的申請編號VEP-300/2009 修訂環境許可證。以下修訂已包含在本環境許可證內(編號EP-315/2008/A)。本經修訂的環境許可證,適用於建造及營辦本許可證B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕
Application No. 申請書編號 |
VEP-300/2009 |
|
Document in
the Register: 登記冊上的文件: |
(1) (2) (3) (4) (5) |
Project Profile – “Proposed Installation of Radio
Repeater Station at Tai Long Au, 工程項目簡介 – “計劃於大埔大浪坳西貢東郊野公園安裝無線電轉發站” (登記冊編號: PP-363/2008) The Director’s letter of permission to apply
directly for environmental permit dated 署長於2008年9月5日發出批准直接申請環境許可證的信件 (檔案編號:(14) in EP2/N5/Q/53) Application for environmental permit submitted by
the Permit Holder on 許可證持有人於2008年9月16日提交的環境許可證申請 (申請書編號:AEP-315/2008) Environmental Permit (Permit No. EP-315/2008) issued
on 於2008年10月9日發出的環境許可證(許可證編號:EP-315/2008) Application for Variation of Environmental Permit
including all attachments submitted by the Permit Holder on 許可證持有人於2009年9月10日提交的更改環境許可證申請包括所有附件(申請書編號:VEP-300/2009) |
Application No. 申請書編號 |
Date
of Application 申請日期 |
List
of Amendments incorporated into this Environmental Permit 已包含在本環境許可證內的修訂項目 |
Date
of Amendments 修訂日期 |
VEP-300/2009 |
2009年9月10日 |
Amend Figure
1 attached to the Environmental Permit No. EP-315/2008 更改在環境許可證編號EP-315/2008夾附的圖1 |
2009年10月7日 |
2009年10月7日
Date 日期 |
|
(Maurice K.L. YEUNG) Principal
Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任楊國良代行) |
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated
project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明﹕
Title
of Designated Project 指定工程項目的名稱 |
Proposed
Installation of Radio Repeater Station at Tai Long Au, [This designated project is hereinafter referred
to as “the Project”] 計劃於大埔大浪坳西貢東郊野公園安裝無線電轉發站 [本指定工程項目下稱 “工程項目”] |
Nature of Designated Project |
Earthworks and building works wholly in 於西貢東郊野公園內進行土木工事及建築工程。 |
Location
of Designated Project 指定工程項目的地點 |
Tai Long Au, 大浪坳西貢東郊野公園。工程項目的位置載於本許可證夾附的圖1。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
An
equipment platform with an area of 13.5 sq.m, consisting of an equipment hut
and four (4) antenna poles 一佔地13.5平方米的設備平台,包括一個儀器櫃和四(4)支天線桿。 |
1. General
Conditions
1.1 The Permit
Holder and any person working on the Project shall comply with all conditions
set out in this Permit. Any non-compliance by any person may constitute a
contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap.
499) and may become the subject of appropriate action being taken under the EIAO.
1.2 The Permit Holder shall ensure
full compliance with all legislation from time to time in force including,
without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution
Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Waste
Disposal Ordinance (Cap. 354) and Dumping at Sea Ordinance (Cap. 466). This
Permit does not of itself constitute any ground of defence against any
proceedings instituted under any legislation or imply any approval under any
legislation.
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit or
the documents referred to in Part A of the Permit readily available at
all times for inspection by the Director or his authorised officers at all
sites/offices covered by this Permit. Any reference to the Permit shall include
all documents referred to in the Permit and also the relevant documents in the
Register.
1.4 The Permit Holder shall give a
copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The site(s) refers to site(s) of construction and operation
of the Project and shall mean the same hereafter.
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular
site entrances/exits or at a convenient location for public’s information at
all times. The Permit Holder shall ensure that the most updated information
about the Permit, including any amended Permit, is displayed at such locations.
If the Permit Holder surrenders a part or the whole of the Permit, the notice
he sends to the Director shall also be displayed at the same locations as the
original Permit. The suspended, varied or cancelled Permit shall be
removed from display at the Project site(s).
1.6 The Permit Holder shall
construct and operate the Project in accordance with the project description in
Part B of this Permit.
1.7 The Permit Holder
shall ensure that the Project is designed, constructed and operated in
accordance with the information and all recommendations described in the Project
Profile (Register No. PP-363/2008); other relevant documents in the Register;
the information or mitigation measures described in this Permit; mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit; and mitigation measures to be recommended under on going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8 All submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within one month of the receipt of the
Director’s comments or otherwise as specified by the Director.
1.9 All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part
C of this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the Environmental
Impact Assessment Ordinance (Cap. 499).
1.10 The Permit Holder shall release all
finalized submissions as required under this Permit, to the public by
depositing copies in the EIAO Register Office, or in any other places, or any
internet websites as specified by the Director, or by any other means as
specified by the Director for public inspection. For this purpose, the Permit
Holder shall provide sufficient copies of the submissions.
1.11 All submissions to the Director required
under this Permit shall be delivered either in person or by registered mail to
the EIAO Register Office (currently at 27/F, Southorn Centre,
1.12 The Permit Holder shall notify the Director
in writing the commencement date of construction of the Project at least two
weeks prior to the commencement of construction of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement date of the construction.
1.13 For the purpose of this Permit, “commencement of
construction” does not include works related to site clearance and preparation,
or other works as agreed by the Director.
2. Specific
Conditions
2.1 The
Project shall only be constructed at the location as shown in Figure 1
of this Permit.
2.2 To minimize impact
on hikers, no construction works shall be carried out on Saturdays, Sundays and
public holidays.
2.3 Only
hand held equipment shall be used for construction.
2.4 No
haul road shall be constructed. All construction materials, equipment and
wastes shall be transported to and from the site by helicopter.
2.5 All
antenna poles and the equipment hut of the radio repeater station shall be
painted in subdue and non-reflective colour. The colour scheme shall be similar
to that of the adjacent utility installations to match with the surroundings.
2.6 Affected
areas of the project site shall be reinstated, and screen planting with
existing tree species shall be carried out to minimize the visual impact.
Notes:
1. This
Permit consists of three parts, namely, Part A (Main Permit), Part B
(Description of Designated Project) and Part C (Permit Conditions). Any person relying on this permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
2. If
there is a breach of any condition of this Permit, the Director or his
authorized officer may, with the consent of the Secretary for the Environment,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit
Holder shall not carry out any associated works without the permission of the
Director or his authorized officer.
3. The
Permit Holder may apply under Section 13 of the EIAO to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the Project site by the amended permit.
4. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under Section 12 of
the EIAO to the Director for a further environmental permit.
5. Under
Section 14 of the EIAO, the Director may with the consent of the Secretary for
the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the Project site.
6. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the EIAO before
the Project could be continued. It
is an offence under Section 26(1) of the EIAO to construct or operate a
designated project listed in Part I of Schedule 2 of the EIAO without a valid
environmental permit.
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment to a fine of $2
million and to imprisonment
for 6 months;
(ii)
on a second or subsequent conviction on indictment to
a fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and
to imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine
of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature,
the court or magistrate may impose a fine of $10,000 for each day on which he
is satisfied the offence continued.
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the EIAO within 30 days of receipt of this Permit.
9. The
Notes are for general reference only and that the Permit Holder should refer to
the EIAO for details and seek independent legal advice.
Environmental Permit No. EP-315/2008/A
1. 一般條件
1.1 許可證持有人及任何從事工程項目的人士必須符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例)(第499章)的規定,而當局可根據環評條例採取適當行動。
1.2 許可證持有人須經常確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章);《空氣污染管制條例》(第311章);《水污染管制條例》(第358章);《廢物處置條例》(第354章);以及《海上傾倒物料條例》(第466章)。本許可證本身不會就根據任何法例提出的訴訟構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地 / 辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 許可證持有人須把本許可證的複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6 許可證持有人須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7 許可證持有人須確保工程項目的設計、建造及營辦,按照下述資料及措施辦理:工程項目簡介(登記冊編號:PP-363/2008)所說明的資料及各項建議;登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證內載的條件須向署長存放或獲署長批准的提交文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。
1.8 所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內(除非署長另行指定),根據署長的意見加以修正並再向署長提交。
1.9 署長批准的所有提交文件、署長沒有給予意見的所有存放文件、或根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證C部說明的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有任何不符合提交文件的情況,可能違反《環境影響評估條例》(第499章)的規定。
1.10 許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或採取署長指定的任何其他方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11 本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言(HTML)(第4.0或較後版本)和便攜式文件格式(PDF)(第4.0或較後版本)製作,除非另獲署長同意,並須與硬複本同時提交。
1.12 許可證持有人須在工程項目的建造工程展開前,至少提早2個星期以書面方式把工程項目建造工程的施工日期通知署長。施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
2. 特定條件
2.1 工程項目的建造須於本許可證圖1所示位置進行。
2.2 逢星期六、星期日及公眾假期不得進行任何建造工程,以盡量減低對郊遊人士的影響。
2.3 只可使用手提建造工具。
2.4 不得闢建運料路。所有建築材料、工具及廢物須以直升機運送往返工地。
2.5 無線電轉發站的所有天線桿及儀器櫃須塗以柔和及不反光的顏色,色調須與相鄰公用設施裝置的顏色近似,以配合周圍環境。
2.6 工地所影響的範圍須予以修復,並須栽種現有的樹木品種作為屏障,以盡量減低視覺的影響。
註:
1. 本許可證共有3部,即A部(許可證主要部分);B部(指定工程項目的說明)及C部(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. 如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. 許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須把經修改的許可證替換在建造工地內展示的原有許可證。
4. 承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. 根據環評條例第14條的規定,署長可在環境局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的環境許可證必須從建造工地除下,不再展示。
6. 如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦條例附表2第1部所列明的指定工程項目,即屬犯罪。
7. 如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪:
(i) 一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii) 一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii) 一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv) 一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及
(v) 在任何情況下如該罪行屬連續性質,法院或裁判官可就其信納該罪行連續的每一天另處罰款10,000元。
8. 許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. 上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
環境許可證編號:EP-315/2008/A
| Figure
1 |