Environmental Permit No. EP-330/2009/A
環境許可證編號EP-330/2009/A

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

SECTIONS 10 & 13

環境影響評估條例

(499)

1013

 

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE

A DESIGNATED PROJECT

建造及營辦指定工程項目的環境許可證

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) granted the Environmental Permit (No. EP-330/2009) to the Drainage Services Department (hereinafter referred to as the “Permit Holder”) on 23 February 2009.  Pursuant to Section 13 of the EIAO, the Director amends the Environmental Permit (No. EP-330/2009) based on the Application No. VEP-310/2010. The amendments described below are incorporated into this Environmental Permit (No. EP-330/2009/A). This Environmental Permit as amended is for the construction and operation of the designated project described in Part B of this Permit subject to the conditions specified in Part C of this Permit. The issue of this Environmental Permit is based on the documents, approvals or permissions described below:

根據環境影響評估條例(環評條例) 10條的規定,環境保護署署長(署長)2009223將環境許可證 (編號EP-330/2009) 批予渠務署 (下稱許可證持有人”)。根據環評條例第13條的規定,署長因應更改環境許可證的申請(編號VEP-310/2010)修訂環境許可證(編號 EP-330/2009)。以下修訂已包含在本環境許可證內(編號EP-330/2009/A)。本經修訂的環境許可證作為建造及營辦本許可證B所說明的指定工程項目,但須遵守本許可證C所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕

 

 

Application No.

申請書編號

VEP-310/2010

 

Documents in the Register:

登記冊上的文件

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Documents in the Register:

登記冊上的文件

 

 

(1)

 

 

 

 

(2)

 

 

 

 

 

(3)

 

 

 

 

(4)

 

 

 

 

(5)

Project Profile – “Western Interceptor Sewer Sewage Pumping Station” (Register No.: PP-375/2008)

工程項目簡介 – “西部主幹污水泵房 (登記冊編號: PP-375/2008)

 

The Director’s letter of permission to apply directly for environmental permit dated 19 January 2009 (Reference: (19) in EP2/N4/F/97)

署長於2009119發出准許直接申請環境許可證的信件 (檔案編號:(19) in EP2/N4/F/97)

 

Application for environmental permit submitted by the Permit Holder on 29 January 2009 (Application No. AEP-330/2009)

許可證持有人於2009129提交的環境許可證申請 (申請書編號:AEP-330/2009)

 

Environmental Permit (No. EP-330/2009) issued on 23 February 2009

2009223簽發的環境許可證(編號EP-330/2009)

 

 

Application for Variation of an Environmental Permit including all attachments submitted by the Permit Holder on 15 January 2010 (Application No. VEP-310/2010)

許可證持有人於2010115提交的更改環境許可證申請包括所有附件(申請書編號:VEP-310/2010

 

 

 

Application No.

申請書編號

Date of Application

申請日期

List of Amendments Incorporated into this Environmental Permit

已包含在本環境許可證內的修訂項目

Date of Amendment

修訂日期

VEP-310/2010

15 January 2010

2010115

-      Vary Conditions 2.1 and 2.4 in Part C of the Environmental Permit (No. EP-330/2009)

-      更改環境許可證(編號EP-330/2009) C的第2.1 2.4項條件

 

-      Vary Figure 1 and Figure 2 of the Environmental Permit (No. EP-330/2009)

-      更改環境許可證(編號 EP-330/2009) 12

8 February 2010

201028

 

 

 

 

 

 

            8 February 2010

           201028

Date

日期

 

(WONG Hon-meng)

Principal Environmental Protection Officer

for Director of Environmental Protection

環境保護署署長

(首席環境保護主任黃漢明代行)


PART B (DESCRIPTION OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):

下列為本環境許可證 (下稱許可證”) A所提的指定工程項目的說明﹕

 

Title of Designated Project

指定工程項目的名稱

Western Interceptor Sewer Sewage Pumping Station

[This designated project is hereinafter referred to as “the Project”]

西部主幹污水泵房

[本指定工程項目下稱 工程項目”]

 

Nature of Designated Project
指定工程項目的性質

A sewage pumping station with an installed capacity of more than 2,000 m3 per day and a boundary of which is less than 150 m from an existing or planned residential area and educational institution (Items F.3(b)(i) and F.3(b)(iii) of Part I of Schedule 2 of EIAO).

污水泵水站,而其裝置的泵水能力超過每天2,000立方米其一條界線距離現有的或計劃中的住宅區及教育機構少於150

(環評條例附表2I部的F.3(b)(i)F.3(b)(iii))

 

Location of Designated Project

指定工程項目的地點

At the junction of Lung Mun Road and Wong Chu Road, Tuen Mun. The location of the Project is shown in Figure 1 attached to this Permit.

屯門龍門路及皇珠路交界處工程項目的位置載於本許可證夾附的1

 

Scale and Scope of Designated Project

指定工程項目的規模和範圍

 

Construction and operation of a sewage pumping station with a designed capacity (average dry weather flow) of about 54,630 m3 per day.   

建造及營辦一個設計容量(平均旱季流量)約為每天54,630立方米的污水泵水站。

 

 


PART C (PERMIT CONDITIONS)

C部(許可證條件)

 

 

1.         General Conditions

            一般條件

 

1.1       The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of appropriate action being taken under the EIAO.

          許可證持有人及任何從事工程項目的人士必須符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反環境影響評估條例環評條例)(499的規定,而當局可根據環評條例採取適當行動。

 

1.2       The Permit Holder shall ensure full compliance with all legislation from time to time in force including, without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.

          許可證持有人須經常確保完全符合現行法例的規定,包括但不限於噪音管制條例(第400章),空氣污染管制條例(第311章),水污染管制條例(第358章)及廢物處置條例(第354章)。本許可證本身不會就根據任何法例提出的訴訟構成任何抗辯理由,或根據任何法例默示任何批准。

 

1.3       The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorised officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

          許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。

 

1.4       The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.

          許可證持有人須把本許可證的複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。

 

 

 

 

1.5       The Permit Holder shall display conspicuously a copy of this Permit on the Project site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended Permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit.  The suspended, varied or cancelled Permit shall be removed from display at the Project site(s).

          許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。

 

1.6       The Permit Holder shall construct and operate the Project in accordance with the project description in Part B of this Permit.

          許可證持有人須依據本許可證B的工程項目說明,建造及營辦工程項目。

 

1.7       The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and recommendations described in the Project Profile (Register No. PP-375/2008), the Application for Environmental Permit (Application No. AEP-330/2009), and the information and mitigation measures described in this Permit.  Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

          許可證持有人須確保工程項目的設計、建造及營辦是按照工程項目簡介(登記冊編號:PP-375/2008)所說明的資料及建議;環境許可證申請文件(申請書編號:AEP-330/2009);以及本許可證所說明的資料及緩解措施辦理。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。

 

1.8       All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise as specified by the Director.

          所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內(除非署長另行指定),根據署長的意見加以修正並再向署長提交。

 

1.9       All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499).  

          署長批准的所有提交文件、署長沒有給予意見的所有存放文件、或根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證C說明的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有不符合提交文件的情況,可能違反環境影響評估條例499的規定。

 

1.10     The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the EIAO Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

          許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾知道,方法是把有關文件複本存放於環評條例登記冊辦事處、署長指定的任何其他地方、署長指定的任何互聯網網站或採取署長指定的任何方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。

 

1.11     All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the EIAO Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

          本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環評條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,並須與硬複本同時提交。

 

1.12     The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than two weeks before the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

          許可證持有人須在工程項目的建造工程展開前至少兩個星期,以書面方式把工程項目建造工程的施工日期通知署長。施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。

 

1.13     For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.

          為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。

 

 

 

 

 

 

 

2.                  Specific Conditions

          特定條件

 

2.1       To minimise odour impact during operation of the Project, the screening facilities and wet well shall be located underground and enclosed by a reinforced concrete structure.

          為盡量減低工程項目營辦期間的氣味影響,隔篩設施及濕井須設於地底,並以鋼筋混凝土結構覆蓋

 

2.2       To minimise odour impact during operation of the Project, a deodorizer with a forced ventilation system and a H2S removal efficiency of at least 99.5% shall be installed and properly maintained. 

          為盡量減低工程項目營辦期間的氣味影響,須安裝附有壓力通風系統及具備消除至少99.5%硫化氫效能的除臭器,並予以妥善保養維修。

 

2.3       To minimise noise impact during operation of the Project, the pump sets and screening facilities of the pumping station shall be located underground and enclosed by a reinforced concrete structure with acoustic louvers.  Silencers shall be provided for the exhaust fans.

          為盡量減低工程項目營辦期間的噪音影響,泵房的水泵組及隔篩設施均須設於地底,並以附有隔音百葉簾的鋼筋混凝土結構覆蓋。抽氣扇亦須裝設滅聲器。

 

2.4       To minimise the chance of emergency sewage bypass during operation of the Project, one standby pump and dual power supply shall be provided.  A telemetry system shall be provided to transmit signals showing irregularity or operational problem of the pumping station to the Sham Tseng Sewage Treatment Works.

          為盡量減低工程項目營辦期間緊急排放污水的機會,泵房須設有一個備用水泵及雙重電力供應,並須裝設遙測警報系統,以便泵房一旦有異常情況或操作出現問題時可把信號傳送至深井污水處理廠。

 

2.5       To minimise landscape and visual impacts, green roof design, wall planter at the top of the pumping station and screen planting shall be provided and properly maintained during operation of the Project as shown in Figure 2 attached to this Permit. 

          為盡量減低工程項目對景觀及視覺造成的影響,須如本許可證夾附的2所示,在工程項目營辦期間採用綠化屋頂設計、在屋頂栽設外牆花槽及設置屏蔽種植,並予以妥善保養。

 

2.6       To minimise landscape and visual impacts, the entrance gate of the pumping station shall be at least 2 m high and decorated by perforated recycled timber as shown in Figure 2 attached to this Permit.

          為盡量減低工程項目景觀及視覺造成的影響,須如本許可證夾附的2所示,泵房入口大閘須最少為2高,並用透孔的循環再造木材裝飾。

 

 

 

 

 

 

Notes:

註:

 

1.         This Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions).  Any person relying on this permit should obtain independent legal advice on the legal implications under the EIAO, and the following notes are for general information only.

          本許可證共有3部,即A(許可證主要部分);B(指定工程項目的說明)及C(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。

 

2.         If there is a breach of any condition of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

          如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。

 

3.         The Permit Holder may apply under Section 13 of the EIAO to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

          許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須把經修改的許可證替換在工地內展示的原有許可證。

 

4.         A person who assumes the responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the EIAO to the Director for a further environmental permit.

          承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。

 

5.         Under Section 14 of the EIAO, the Director may with the consent of the Secretary for the Environment, suspend, vary or cancel this Permit.  The suspended, varied or cancelled Permit shall be removed from display at the Project site.

          根據環評條例第14條的規定,署長可在環境局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的環境許可證必須從建造工地除下,不再展示。

 

6.         If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the EIAO before the Project could be continued.  It is an offence under Section 26(1) of the EIAO to construct or operate a designated project listed in Part I of Schedule 2 of the EIAO without a valid environmental permit.

          如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2所列明的指定工程項目,即屬犯罪。

 

7.         Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the EIAO, is liable:

          如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪:

 

(i)        on a first conviction on indictment to a fine of $2 million and to   imprisonment for 6 months

一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;

 

(ii)                 on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;

一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;

 

(iii)               on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;

 

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及

 

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.

在任何情況下如該罪行屬連續性質,法院或裁判官可就其信納該罪行連續的每一天另處罰款10,000元。

 

8.         The Permit Holder may appeal against any condition of this Permit under Section 17 of the EIAO within 30 days of receipt of this Permit.

          許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。

 

9.         The Notes are for general reference only and that the Permit Holder should refer to the EIAO for details and seek independent legal advice.

          上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。

 

 

Environmental Permit No. EP-330/2009/A

環境許可證編號EP-330/2009/A

 

 

| Figure 1 | Figure 2 |


[ Back to First Page ] / [ Back to Main Index ]