Environmental Permit No. EP-364/2009/A
環境許可證編號EP-364/2009/A
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10及13條
ENVIRONMENTAL PERMIT TO CONSTRUCT
DESIGNATED PROJECT
建造指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the Ordinance), the Director of Environmental Protection (the Director) granted the Environmental Permit (No. EP-364/2009) to Highways Department (hereinafter referred to as the "Permit Holder") on 17 August 2009. Pursuant to Section 13 of the Ordinance, the Director amends the Environmental Permit based on the Application No. VEP-321/2010. The amendments, described below, are incorporated into this Environmental Permit (No. EP-364/2009/A). This Environmental Permit as amended is for the construction of the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)於2009年8月17日將環境許可證(編號EP-364/2009)批予路政署(下稱 “許可證持有人”)。根據條例第13條的規定,署長因應更改環境許可證的申請編號VEP-321/2010俢訂環境許可證編號。以下俢訂已包含在本環境許可證(編號EP-364/2009/A)內。本經俢訂的環境許可證作為建造本許可證B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:
Application No. 申請書編號 |
VEP-321/2010 |
Document in the Register : 登記冊上的文件:
|
1. Central - Wan Chai Bypass and Island Eastern Corridor Link (Register No.: AEIAR-041/2001) -
Environmental
Impact Assessment Report (July 2001) - Environmental Monitoring and Audit Manual - Executive Summary
2. The Director’s letter of approval of the CWB&IECL EIA Report dated 31 August 2001 referenced (19) in Ax(2) to EP2/H4/A/10 II.
3. Wan Chai Development Phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) -
Environmental
Impact Assessment Report (December 2007) - Environmental Monitoring and Audit Manual - Executive Summary - Further information received from the Civil Engineering and Development Department on 11 March 2008, 9 April 2008 and 14 November 2008 under Section 8(1) of the Environmental Impact Assessment Ordinance
4. The Director’s letter of approval of the WDII&CWB EIA Report dated 11 December 2008 referenced (85) in EP2/H4/S3/15 Pt.2.
5. Central Reclamation Phase III – Studies, Site Investigation, Design and Construction (Register No.: AEIAR-040/2001) -
Environmental
Impact Assessment Report (July 2001) - Environmental Monitoring and Audit Manual - Executive Summary
6. The Director’s letter of approval of the CRIII EIA Report dated 31 August 2001 referenced (19) in Ax(4) to EP2/H4/C/09 II.
7. Environmental Permit Issued – Permit No.: EP-356/2009 issued to Civil Engineering and Development Department on 30 July 2009 for construction of the following designated projects: (i) Permanent and temporary reclamation works including associated dredging works in Wan Chai Development Phase II (WDII) area (referred to as “DP3” in the WDII&CWB EIA Report); (ii) Wan Chai East Sewage Outfall (referred to as “DP5” in the WDII&CWB EIA Report); and (iii) Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui (referred to as “DP6” in the WDII&CWB EIA Report).
8. Application for Environmental Permit and attachments submitted by the Permit Holder on 27 July 2009 (Application No.: AEP-364/2009)
9. Environmental Permit (No. EP-364/2009) issued on 17 August 2009
10. Application documents for Variation of Environmental Permit including all attachments submitted by the Permit Holder on 28 July 2010 (Application No. VEP-321/2010)
1. 中環及灣仔繞道和東區走廊連接路設計及建築工程 (登記冊編號: AEIAR─041/2001) - 環境影響評估報告 (2001年7月) [下稱「CWB&IECL環評報告」] - 環境監察審核手冊 - 行政摘要
2. 署長於2001 年8月31日發出CWB&IECL環評報告的批准信,檔案編號: (19) in Ax(2) to EP2/H4/A/10 II
3. 灣仔發展計劃第二期及中環灣仔繞道 (登記冊編號: AEIAR-125/2008) · 環境影響評估報告 (2007年12月) [下稱「WDII&CWB環評報告」] · 環境監察審核手冊 · 行政摘要 · 土木工程拓展署根據條例第8.(1)條於2008年3月11日、2008年4月9日及2008年11月14日所提交的進一步資料
4. 署長於2008 年12月11日發出批准WDII&CWB環評報告的信件,檔案編號: (85) in EP2/H4/S3/15 Pt. 2
5. 中環填海計劃第III期 - 研究、實地堪測、設計與建築(登記冊編號:AEIAR-040/2001) · 環境影響評估報告 (2001年7月) [下稱「CRIII環評報告」] · 環境監察審核手冊 · 行政摘要
6. 署長於2001 年8月31日發出 CRIII環評報告的批准信,檔案編號: (19) in Ax(4) to EP2/H4/C/09 II
7. 已簽發的環境許可證– 許可證編號EP-356/2009; 於2009年7月30日簽發與土木工程拓展署以建造以下指定工程項目: (i) 在灣仔發展計劃第二期的永久及臨時填海工程(包括相聯挖泥工程) (WDII&CWB環評報告內稱“DP3”) (ii) 灣仔東污水排水口(WDII&CWB環評報告內稱“DP5”);及 (iii) 灣仔至尖沙咀海底輸水管的挖泥工程(WDII&CWB環評報告內稱“DP6”)。
8. 許可證持有人於2009 年7 月27 日提交的環境許可證申請文件及附件(申請書編號: AEP-364/2009)
9. 已簽發的環境許可證 (編號 : EP-364/2009) 於 2009年 8 月 17日簽發
10. 許可證持有人於2010年 7月28日提交的更改環境許可證申請文件包括所有附件(申請書編號:VEP-321/2010)
|
Application No. 申請書編號 |
Date of Application 申請日期 |
List of Amendments Incorporated into this Environmental Permit 已包含在本環境許可證內的修訂項目
|
Date of Amendment 修訂日期 |
VEP-321/2010 |
28 July 2010 2010年7月28日 |
1) Vary Condition 2.10(c) in Part C of Environmental Permit No. EP-364/2009.
更改環境許可證編號EP-364/2009, C部條件第 2.10(c) 項
2) Vary Condition 2.15 in Part C of Environmental Permit No. EP-364/2009.
更改環境許可證編號EP-364/2009, C部條件第2.15 項
3) Amend Figures 4a., 4b, 4d, 4e and 4f of Environmental Permit No. EP-364/2009
更改環境許可證編號EP-364/2009圖 4a, 4b, 4d, 4e 及 4f
4) Add Figure 4g
加入圖 4g
|
4 August 2010 2010年 8 月 4 日 |
4 August 2010 2010 年 8 月 4 日 |
|
|
Date 日期 |
|
(YEUNG Wai Tak, Victor) Acting Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (署理首席環境保護主任 楊維德 代行)
|
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱
|
Central – Wan Chai Bypass (CWB) including its Road Tunnel and Slip Roads (This designated project is hereafter referred to as “the Project”)
中環灣仔繞道,包括其行車隧道及連接路 (本指定工程項目下稱“工程項目”) |
Nature of Designated Project 指定工程項目的性質
|
The Project will involve construction of: · a trunk road; and · its road tunnel more than 800m in length between portals.
此工程項目涉及興建: · 一條主幹道; 及 · 其入口之間的長度超過800米的行車隧道。
|
Location of Designated Project 指定工程項目的地點
|
From Central to North Point, Hong Kong. The location of the Project is shown in Figure 1 of this Permit.
由香港中環至北角。 工程項目的地點展示於本許可證圖1內。 |
Scale and Scope of Designated Project |
The scope of the Project includes: · a dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter(CBTS); · the Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area; · tunnel control buildings and ventilation buildings; · slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area; · associated road lighting, road signing, traffic control and surveillance system; and · other associated works.
Remarks: (a) The scope of the Project does not include (i) the tunnel structure works of the CWB within Central Reclamation Phase III (CRIII) area in Central waterfront area; (ii) the permanent and temporary reclamation and associated dredging works related to the CWB construction; and (iii) the Road P2 and other roads which are classified as primary/district distributor roads in Wan Chai waterfront area near Hong Kong Convention and Exhibition Centre (referred to as “DP2” in the WDII&CWB EIA Report (Register No. AEIAR-125/2008). (b) The tunnel structure works of the CWB within CRIII area are separately covered by environmental permit No. EP-122/2002 and further environmental permit No. FEP-01/122/2003, and their subsequently amended versions, issued to Civil Engineering and Development Department and its contractor, Leighton-China State-Van Oord Joint Venture, respectively. (c) The permanent and temporary reclamation and associated dredging works related to the CWB construction are separately covered by environmental permit No. EP-356/2009 issued to Civil Engineering and Development Department.
工程項目的範圍包括: · 一條從現有的中環林士街天橋交接處,伸展至銅鑼灣避風塘東面的現有東區走廊交接處,約長4.5公里的三線雙向行車道路及約長3.7公里的隧道; · 在現有的中環林士街天橋附近,用以連接中環區其他道路的中環交匯處; · 隧道管理大樓及通風大樓; · 連接主幹道與灣仔北和銅鑼灣地區現有道路的連接道; · 相關的道路照明、道路標誌和交通管制及監察系統; 及 · 其他相關工程。
備註: (a) 本許可證不包括: (i) 中環灣仔繞道位於中環填海第三期地區內的隧道結構建造工程、(ii) 中環灣仔繞道相關的永久及臨時填海工程(包括相聯挖泥工程)及(iii) 在WDII&CWB環評報告中提及的指定工程項目DP2,位於灣仔海旁地區,近香港會議展覽中心的P2路和其他分類為主要幹道或地區幹道的道路。 (b) 中環灣仔繞道位於中環填海第三期地區內的隧道結構建造工程已包括在簽發與土木工程拓展署的環境許可證(許可證編號: EP-122/2002)及簽發與其承辦商Leighton-China State-Van Oord Joint Venture的新的環境許可證(許可證編號: FEP-01/122/2003)及其各自的更新版本。 (c) 中環灣仔繞道相關的永久及臨時填海工程(包括相聯挖泥工程) 已包括在簽發與土木工程拓展署的環境許可證(許可證編號: EP-356/2009)。
|
1. General
Conditions
1.1
The Permit Holder and
any person working on the Project shall comply with all conditions set out in
this Permit. Any non-compliance by any person may constitute a contravention of
the Environmental Impact Assessment Ordinance (EIAO) (Cap.499) and may become
the subject of appropriate action being taken under the Ordinance.
1.2
The
Permit Holder shall ensure full compliance with all legislation from time to
time in force including, without limitation to, the Air Pollution Control
Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Noise
Control Ordinance (Cap. 400), and Waste Disposal Ordinance (Cap. 354).
This Permit does not of itself constitute any ground of defense against any
proceedings instituted under any legislation or imply any approval under any legislation.
1.3
The
Permit Holder shall make copies of this Permit together with all documents
referred to in this Permit and the documents referred to in Part A of
this Permit readily available at all times for inspection by the Director or
his authorized officers at all sites/offices covered by this Permit. Any
reference to the Permit shall include all documents referred to in the Permit
and also the relevant documents in the Register.
1.4
The
Permit Holder shall give a copy of this Permit to the person(s) in charge of
the site(s) and ensure that such person(s) fully understands all conditions and
all requirements incorporated by the Permit. The site(s) refers to site(s) of
construction of the Project and shall mean the same hereafter.
1.5
The
Permit Holder shall display conspicuously a copy of this Permit on the
construction site(s) at all vehicular site entrances/exits or at a convenient
location for public’s information at all times. The Permit Holder shall ensure
that the most updated information about the Permit, including any amended
Permit, is displayed at such locations. If the Permit Holder surrenders a part
or the whole of this Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or
cancelled Permit shall be removed from display at the construction site(s).
1.6
The
Permit Holder shall construct the Project in accordance with the project
description in Part B of this Permit (hearafter referred to as “the
Project”).
1.7
The
Permit Holder shall ensure that the Project is designed and constructed in
accordance with the relevant information and recommendations described in the
approved CWB&IECL EIA Report (Register No. AEIAR-041/2001), the approved
WDII&CWB EIA Report (Register No. AEIAR-125/2008), the approved CRIII EIA
Report (Register No. AEIAR-040/2008), the Environmental Permit No.: EP-356/2009
issued on 30 July 2009 for marine works as described in Part A of this
Permit; the Application for Environmental Permit (Application No. AEP-364/2009);
the Environmental Permit No. EP-364/2009 issued on 17 August 2009; the
Application for Variation of an Environmental Permit (Application No.
VEP-321/2010) and other relevant documents in the Register, the information and
mitigation measures described in this Permit, mitigation measures to be
recommended in submissions that shall be deposited with or approved by the
Director as a result of permit conditions contained in this Permit, and
mitigation measures to be recommended under on-going surveillance and
monitoring activities during all stages of the Project. Where recommendations
referred to in the documents of the Register are not expressly referred to in
this Permit, such recommendations are nevertheless to be implemented unless
expressly excluded or impliedly amended in this Permit. As stated in the Application
for Environmental Permit and its attachments (Application No.: AEP-364/2009), the
Project is covered by the
approved CWB&IECL EIA Report (Register No. AEIAR-041/2001) and the
WDII&CWB EIA Report (Register No. AEIAR-125/2008) mentioned in Part A
of this Permit. The corresponding coverage of the two EIA reports is shown
in Figure 1 of this Permit. The western part of the Project starts from the western
boundary of the Project and ends at the eastern boundary of the CRIII area near
Lung
King Street,
Wan Chai. The eastern part of the Project starts from the eastern
boundary of the CRIII area and ends at the eastern boundary of the Project. The
western part of the Project is covered by the approved CWB&IECL EIA Report
(Register No. AEIAR-041/2001) with the clarifications stated in the Application
for Environmental Permit and its attachments (Application No.: AEP-364/2009).
The eastern part of the Project is covered by the approved WDII&CWB EIA
Report (Register No. AEIAR-125/2008)).
1.8
All
deposited submissions, as required under this Permit, shall be rectified and
resubmitted in accordance with the comments, if any, made by the Director
within one month of the receipt of the Director’s comments or otherwise
specified by the Director.
1.9
All
submissions approved by the Director, all submissions deposited without
comments by the Director, or all submissions rectified in accordance with
comments by the Director under this Permit shall be construed as part of the
permit conditions described in Part C of this Permit. Any variation of the
submissions shall be approved by the Director in writing or as prescribed in
the relevant permit conditions. Any non-compliance with the submissions may
constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap.499). All submissions or any variation of the submissions shall be
certified by the Environmental Team (ET) Leader and verified by the Independent
Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below before submitting to the Director under this Permit.
1.10
The
Permit Holder shall release all finalized submissions, as required under this
Permit, to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office, or in any other places, or any internet
websites as specified by the Director, or by any other means as specified by
the Director for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
1.11
All
submissions to the Director required under this Permit shall be delivered
either in person or by registered mail to the Environmental Impact Assessment
Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy
Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions
required under this Permit shall be prepared in Hyper Text Markup Language
(HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0
or later), unless otherwise agreed by the Director and shall be submitted at
the same time as the hard copies.
1.12
The
Permit Holder shall notify the Director in writing the commencement date of
construction of the Project no later than one month prior to the commencement
of construction of the Project. The Permit Holder shall notify the Director in
writing immediately if there is any change of the commencement date of the
construction.
1.13
For
the purpose of this Permit, “commencement of construction” does not include
works related to site clearance and preparation or other works as agreed by the
Director.
1.14 The Permit Holder shall notify the Director in writing the commencement date of operation of the Project no later than one month prior to the commencement of operation of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the operation.
2
Special Conditions
Submissions or Measures to be implemented before Construction of the Project
Employment of
Environmental Monitoring and Audit (EM&A) Personnel
Environmental Project Committee (ENPC)
(a) the ET Leader;
(b) the IEC; and
(c) the permit holders of any environmental permit(s) and further environmental permit(s) for the whole Project.
The Community Liaison Group formed under Condition 2.4 of this Permit shall also work under the ENPC set-up to facilitate any necessary liaison works to address potential cumulative environmental impact issues arising from the whole Project. The ENPC shall make recommendation and update under Condition 2.5(a) of this Permit on how to enhance the monitoring and audit of the environmental performance of the whole Project on top of requirements as set out in Conditions 3.1 to 4.3 of this Permit or corresponding requirements set out under subsequent Environmental Permits issued for the whole Project.
Community Liaison Group
2.4
The Permit Holder shall liaise with the permit holder of environmental
permit No. EP-356/2009 on jointly setting up a Community Liaison Group (CLG) comprising
representatives from the relevant concerned and affected parties, including
owners’ corporations, management offices, local committees and schools of
affected areas, including the North Point and Tin Hau areas, to facilitate
communication, enquiries and complaints handling on all environmental issues,
including the follow up on the implementation of remedial mitigation
measures. The Permit Holder shall set up the CLG before the commencement
of construction of the relevant component(s) of the WDII and CWB Project. The
Permit Holder shall notify the Director the actual date of setting up the CLG, the
membership, the terms of reference and the contact details. A designated
complaint hotline shall also be set up for the Project to address such concerns
and complaints in an efficient manner. The detailed arrangements of the CLG shall be reported to the ENPC
and its activities be reflected as update under Condition 2.5(a) of this
Permit. .
Submission of
Updated EM&A Manual
2.5 The Permit Holder shall, no later than one month before the commencement of construction of the Project, submit to the Director for approval four hard copies and one electronic copy of an updated EM&A Manual for the Project. The updated EM&A Manual shall:
(a) make recommendations on how to take into account the ENPC and Community Liaison Group requirements as stipulated in Conditions 2.3 and 2.4 of this Permit respectively;
(b) include a real-time on-site monitoring system of the noise level around the works sites at North Point and Tin Hau areas during the construction phase;
(c) take into account the relevant EM&A requirements from the approved CWB&IECL EIA Report (Register No. AEIAR-041/2001), the approved WDII&CWB EIA Report (Register No. AEIAR-125/2008), the latest works schedules, division of responsibilities among different contracts in the Project, latest project information, latest environmental mitigation measures including the restriction imposed on the use of pneumatic breakers to demolish the existing Island Eastern Corridor as set out in Condition 2.9(a) of this Permit; and
(d) include a monitoring and audit program on noise during the testing and commissioning stages of ventilation buildings to verify the maximum sound power levels as assumed in the noise assessments contained in the approved CWB&IECL EIA Report (Register No. AEIAR-041/2001) and the WDII&CWB EIA Report (Register No. AEIAR-125/2008). In case the maximum sound power levels under this audit programme exceed those assumed in the EIA Reports, the Permit Holder shall investigate with a view to recommend remedial actions; shall deposit the investigation report with the Director, and implement the recommended remedial actions where appropriate.
Before submission to
the Director, the updated EM&A Manual shall be certified by the ET and
verified by the IEC as conforming to the relevant information and
recommendations contained in the approved CWB&IECL EIA Report (Register No.
AEIAR-041/2001), the approved WDII&CWB EIA Report (Register No:
AEIAR-125/2008), the approved CRIII EIA Report (Register No. AEIAR-040/2008), the
application documents for environmental permit including all attachments
(Application No. AEP-364/2009) and other relevant documents in the
Register. All measures recommended in the updated EM&A Manual approved
under this Condition shall be fully and properly implemented according to the
requirements and time schedule(s) set out in the updated EM&A Manual approved
under this Condition (hereinafter referred to as the “updated EM&A Manual”).
Management
Organization of Main Construction Companies
2.6 The Permit Holder shall, no later than one month before the commencement of construction of the Project covered by this Permit, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project. The submitted information shall include at least an organization chart, names of responsible persons and their contact details. The management organization information submitted under this Condition shall contribute towards the relevant part of the ENPC and CLG that the Permit Holder will set up under Conditions 2.3 and 2.4 of this Permit.
Submission
of Works Schedule and Location Plans
2.7 The Permit Holder shall deposit a detailed works schedule of the Project with the Director at least one month before the commencement of the works of the Project. The schedule shall include an updated works programme indicating dates of commencement of construction activities. This schedule to be submitted shall govern the various milestones and anticipated schedule of submissions as reflected in Conditions 2.5, 2.6, 2.8, 2.9, 2.13, 2.14, 2.16, 3.3, 3.4 and 4.2 of this Permit.
2.8 The Permit Holder shall deposit with the Director location and layout plans in the scale of 1:1,000 or other appropriate scale of the Project at least two weeks before the commencement of the works of the Project. The plans shall be submitted with an explanatory statement detailing the works boundaries, the works areas, vertical and horizontal alignments of the CWB, its tunnel, slip roads, ventilation buildings/vent shaft(s) and any other major facilities; and the locations of key environmental mitigation measures, including landscaped deck at eastern tunnel portal, noise semi-enclosures and barriers and low noise road surfacing as mentioned in Conditions 2.10 and 2.11 of this Permit.
Measures to Mitigate Construction Noise Impact
2.9 To mitigate construction noise impact, the Permit Holder shall deposit with the Director, at least two weeks prior to the commencement of construction of the corresponding component(s) of the Project, four hard copies and one electronic copy of the construction noise management plan, consisting of layout plan(s) in the scale of 1:1,000 or other appropriate scale and explanatory statement(s) showing the noise mitigation measures to include:
(a) the use of pneumatic breakers, if required to demolish the existing Island Eastern Corridor, to be confined to the period from 0900 to 1700 hours on weekdays (Monday to Friday), and the pneumatic breakers shall not be used any time on Saturdays, Sundays and general holidays, and during examination hours of the schools affected by the works site, including:
(i) Hong Kong Baptist Church Henrietta Secondary School; and
(ii) Po Leung Kuk Yu Lee Mo Fan Memorial School;
(b) the installation of two types of noise barriers for particular items of powered mechanical equipments and construction works at the locations as shown in Figure 2 of this Permit, including that temporary noise barriers (5m in height) with cantilevered upper portion (3.5m in length); and temporary noise barriers with height up to the soffit of the bridge deck area shall be installed along the existing Island Eastern Corridor structure during the demolition and construction of substructure for the Island Eastern Corridor and construction of adjacent tunnel approach ramp structure, as shown in Figure 2 of this Permit. Besides, temporary noise barriers shall be provided on temporary working platforms on piers or pile caps for the demolition works of existing piers and crossheads for the marine section of the existing Island Eastern Corridor as shown in Figure 3 of this Permit. The barrier material shall have a surface mass of not less than 14 kg/m2 on skid footing with 25mm thick internal sound absorptive lining; and
(c) the use of movable/temporary noise barriers, the use of quiet powered mechanical equipments and the adoption of multiple-phase construction schedules, where appropriate.
Measures to
Mitigate Operational Noise Impact
2.10 To mitigate traffic noise from road operation, the following noise barriers and semi-enclosures shall be installed before the commencement of operation of the road project unless otherwise specified in this Permit. The locations and indicative designs of the noise semi-enclosures and barriers are shown in Figures 4a and 4b of this Permit:
(a) about 235m length of noise semi-enclosure covering the westbound slip road from the Island Eastern Corridor;
(b) about 230m length of noise semi-enclosure covering the main carriageways (eastbound and westbound) of the Central-Wan Chai Bypass (CWB) and Island Eastern Corridor;
(c) about 135m length of 5.5m high cantilevered noise barrier with 4.5m long cantilever inclined at 45° on the eastbound slip road to the Island Eastern Corridor;
(d) about 95m length of 5.5m high cantilevered noise barrier with 1m long cantilever inclined at 45° on the eastbound slip road to the Island Eastern Corridor;
(e) about 350m length of 3.5m high vertical noise barrier on the eastbound slip road to the Island Eastern Corridor; and
(f) about 265m length of noise semi-enclosure covering the westbound slip road from the Island Eastern Corridor shall be installed before the occupation of planned noise sensitive receivers (NSRs) in the Comprehensive Development Areas (CDA) near Oil Street, North Point, as shown in Figures 4a and 4b of this Permit.
2.11 To mitigate traffic noise from road operation, low noise road surfacing shall be paved on the sections of the CWB with speed limit of 70 km/hour or above (except the section of CWB within the tunnel and beneath the landscaped deck at the eastern portal area) as shown in Figures 4b and 4c of this Permit.
2.12 To reduce operational noise from ventilation facilities, the Permit Holder shall provide silencers to all ventilation fans installed in all ventilation buildings.
Measures to Mitigate
Air Quality Impact
2.13 To mitigate the potential air quality impact arising from the operation of the ventilation buildings and their vent shaft(s), the Permit Holder shall implement a series of air mitigation measures. The Permit Holder shall deposit with the Director, at least one month prior to the commencement of construction of the corresponding component(s) of the Project, four hard copies and one electronic copy of the operational air quality management plan to manage and mitigate operational air quality impact, consisting of design drawings in the scale of 1:1,000 or other appropriate scale and explanatory statements showing air quality mitigation measures include:
(a) the construction of the West Ventilation Building (WVB) at the location as shown in Figure 1 of this Permit, and that WVB shall follow the exhaust related design criteria as shown in Table 1a of this Permit;
(b) the construction of the Central Ventilation Building (CVB) at the location as shown in Figure 1 of this Permit, and that CVB shall follow the exhaust related design criteria as shown in Table 1b of this Permit;
(c) the construction of the East Ventilation Building (EVB) and its vent shaft at the locations as shown in Figure 1 of this Permit, and that EVB shall follow the exhaust related design criteria as shown in Table 1b of this Permit;
(d) an electrostatic precipitator system shall be installed to reduce the dust emission from the EVB operation. The electrostatic precipitator system shall be designed to have a dust removal efficiency of 80% to reduce the level of respirable suspended particulates; and
(e) the ventilation system of the Eastern Portal of the CWB Tunnel shall follow the zero portal emission design as described in Section 2.4.18 of the WDII&CWB EIA Report (Register No. AEIAR-125/2008).
The submission(s) shall be certified by the ET Leader and verified by the IEC as conforming to the relevant information and recommendations contained in the approved CWB&IECL EIA Report (Register No. AEIAR-041/2001), the approved WDII&CWB EIA Report (Register No. AEIAR-125/2008) and the approved CRIII EIA Report (Register No. AEIAR-040/2001) before deposit with the Director. All measures recommended in the finalised submission(s) under this Condition shall be fully and properly implemented. Measures covered by other pollution control Ordinances shall not be included in the submission(s) on the operational air quality management plan.
Measures to
Mitigate Landscape and Visual Impact
2.14 To reduce the landscape and visual impact during construction and operation stages of the Project, the Permit Holder shall implement a series of landscape and visual mitigation measures. The Permit Holder shall, at least one month before the commencement of corresponding parts of landscape works of the Project, deposit with the Director four hard copies and one electronic copy of landscape plan(s). The landscape plan(s) shall show the design details, locations, implementation programme, maintenance and management schedules, and drawings in the scale of 1:1,000 or other appropriate scale of the landscape and visual mitigation measures of the Project. Before submission to the Director, the landscape plan(s) shall be certified by the ET Leader and verified by the IEC as conforming to the relevant information and recommendations contained in the approved CWB&IECL EIA Report (Register No. AEIAR-041/2001) and the WDII&CWB EIA Report (Register No. AEIAR-125/2008). All measures recommended in the finalised submission(s) under this Condition shall be fully and properly implemented.
2.15 The landscape plan(s) to be submitted under Condition 2.14 of this Permit shall include measures to mitigate the landscape and visual impact of the road traffic noise semi-enclosures and barriers. The noise semi-enclosures and barriers shall mainly compose of:
(a) transparent panels, translucent panels and/or green roof with translucent skylight in the upper part where appropriate; and
(b) green panels with planters in the lower part where appropriate,
as shown in Figures 4d, 4e, 4f and 4g of this Permit.
Measures to Mitigate Noise and Visual Impacts on Users of Victoria Park
2.16 To reduce the noise and visual impacts of the Slip Road 8, as shown in Figure 1 of this Permit, on users of the Victoria Park during the operation phase of the Project, the Permit Holder shall deposit with the Director, at least one month prior to the commencement of construction of the corresponding component(s) of the Project, four hard copies and one electronic copy of Additional Mitigation Plan for Slip Road 8 consisting of design drawings in the scale of 1:1,000 or other appropriate scale and explanatory statement(s) showing the additional noise and visual mitigation measures such as noise screening structures with aesthetic design. Before submission to the Director, the Additional Mitigation Plan shall be certified by the ET Leader and verified by the IEC as conforming to the relevant information and recommendations contained in the approved WDII&CWB EIA Report (Register No. AEIAR-125/2008) and its approval conditions. The recommended noise and visual mitigation measures in the finalised submission shall be fully and properly implemented prior to the commencement of operation of the Project.
3
Environmental Monitoring and Audit Requirements
3.1 The EM&A programme shall be implemented in accordance with the procedures and requirements as set out in the updated EM&A Manual approved under Condition 2.5 of this Permit. Any major changes to the programme shall be justified by the ET Leader and verified by the IEC as conforming to the information and requirements contained in the updated EM&A Manual approved under Condition 2.5 of this Permit before submission to the Director for approval. The EM&A programme shall include, among other items, the air quality and noise monitoring and audit details to cover the different construction phases. The Permit Holder shall consider the appropriate timing for putting in place a real-time on-site monitoring system of the noise level around the works sites at North Point and Tin Hau areas during the construction phase of the Project, but the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridor. The real-time noise monitoring results shall be presented in the Internet website as described in Condition 4.2 of this Permit.
3.2 Samples, measurements and necessary remedial actions shall be taken in accordance with the requirements of the updated EM&A Manual by:
(a) conducting baseline environmental monitoring;
(b) conducting impact monitoring;
(c) carrying out remedial actions described in Event/Action Plans of the updated EM&A Manual approved under Condition 2.5 of this Permit in accordance with the time frames set out in Event/Action Plans, or as agreed by the Director, in case where specified criteria in the updated EM&A Manual approved under Condition 2.5 of this Permit are exceeded; and
(d) logging and keeping records of details of (a) to (c) above for all parameters within 3 working days of collection of data or completion of remedial action(s), for the purpose of preparing and submitting the monthly EM&A Reports and to make available for inspection on site.
3.5 All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.
4
Electronic Reporting of EM&A Information
4.1 To facilitate public inspection of the Baseline Monitoring Report and regular EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hardcopies as described in Conditions 3.3 and 3.4 of this Permit. For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made. All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director. The content of the electronic copies of these Reports must be the same as the hardcopies.
4.3 The Internet website as described in Condition 4.2 above shall enable user-friendly public access to the monitoring and project data including the approved EIA Reports and the environmental permit(s) of the Project. The Internet website shall have features capable of:
(a) providing access to all environmental monitoring data collected since the commencement of works;
(b) searching by date;
(c) searching by types of monitoring data (noise and air quality); and
(d) hyperlinks to relevant monitoring data after searching;
or otherwise as agreed
by the Director.
Notes :
1. This Permit
consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project)
and PART C (Permit Conditions). Any
person relying on this permit should obtain independent legal advice on the
legal implications under the Ordinance, and the following notes are for general
information only.
2. If there is a
breach of any conditions of this Permit, the Director or his authorized officer
may, with the consent of the Secretary for the Environment, order the cessation
of associated work until the remedial action is taken in respect of the
resultant environmental damage, and in that case the Permit Holder shall not
carry out any associated works without the permission of the Director or his
authorized officer.
3. The Permit
Holder may apply under Section 13 of the Ordinance to the Director for a
variation of the conditions of this Permit. The Permit Holder shall
replace the original permit displayed on the construction site by the amended
permit.
4. A person who
assumes the responsibility for the whole or a part of the designated project(s) may, before
he assumes responsibility of the designated project(s), apply under
Section 12 of the Ordinance to the Director for a further environmental permit.
5. Under Section
14 of the Ordinance, the Director may with the consent of the Secretary for the
Environment, suspend, vary or cancel this Permit. The suspended, varied
or cancelled Permit shall be removed from display at the construction site.
6. If this
Permit is cancelled or surrendered during construction of the Project, another
environmental permit must be obtained under the Ordinance before the Project
could be continued. It is an offence under section 26(1) of the Ordinance
to construct or operate a designated project listed in Part I of schedule 2 of
the Ordinance without a valid environmental permit.
7. Any person who constructs the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable:-
(i) on a first conviction on indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii) on a second or subsequent conviction on indictment to a fine of $ 5 million and to imprisonment for 2 years;
(iii) on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;
(iv) on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and
(v) in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $ 10,000 for each day on which he is satisfied the offence continued.
8. The Permit
Holder may appeal against any condition of this Permit under Section 17 of the
Ordinance within 30 days of receipt of this Permit.
9. The Notes are
for general reference only and that the Permit Holder should refer to the EIA
Ordinance for details and seek independent legal advice.
Environmental Permit No. EP-364/2009/A
環境許可證編號 EP-364/2009/A
Table 1a: Exhaust Related Design Criteria of the West Ventilation Building (based on Table 3.9 of the CWB&IECL EIA Report (Register No. AEIAR-041/2001)*
|
Maximum capacity (m3s-1) |
Exit velocity (m s-1) |
Minimum discharge height (meter above ground) |
Exhaust direction |
West Ventilation Building (WVB)**
|
420 |
8 |
15 |
Vertical
|
Notes: * This Table shall be read in conjunction with Condition 2.13 and Figure 1 of this Permit.
** The vent shaft will be incorporated within the WVB.
Table 1b Exhaust Related Design Criteria of the Central Ventilation Building and the East Ventilation Building and its Vent Shaft (based on Table 3.11 of the WDII&CWB EIA Report (Register No. 125/2008)*
|
Cross-sectional area of stack (m2) |
Exit velocity (m s-1) |
Minimum mid-discharge height (meter above ground) |
Exhaust direction |
Central Ventilation Building (CVB)** |
219 |
8 |
17.5 |
Vertical
|
Vent shaft of the East Ventilation Building (EVB)*** |
94 |
8 |
16.25 |
Inclined 45 degree upward (discharge towards sea direction) |
Notes: * This Table shall be read in conjunction with Condition 2.13 and Figure 1 of this Permit.
** The vent shaft of CVB will be incorporated within the CVB.
*** The vent shaft of EVB will be separated from the EVB and located at the eastern breakwater of the Causeway Bay Typhoon Shelter.
| Figure
1 | Figure
2 | Figure
3 | Figure
4a | Figure
4b | Figure
4c | Figure
4d | Figure
4e | Figure
4f | Figure
4g |