Environmental Permit No.
EP-136/2002/E
Àô¹Ò³\¥iÃÒ½s¸¹ EP-136/2002/E
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
Àô¹Ò¼vÅTµû¦ô±ø¨Ò
(²Ä499³¹)
²Ä10¤Î13±ø
ENVIRONMENTAL
PERMIT TO DECOMMISSION
A
DESIGNATED PROJECT
¸Ñ°£¹B§@«ü©w¤uµ{¶µ¥ØªºÀô¹Ò³\¥iÃÒ
A³¡ (³\¥iÃÒ¥Dn³¡¤À)
Pursuant to
Section 10 of the Environmental Impact Assessment Ordinance (the EIAO), the
Director of Environmental Protection (the Director) grants the environmental
permit (EP-136/2002) to the Civil Engineering and Development Department
(formerly known as the Civil Engineering Department and hereinafter referred to
as the ¡§Permit Holder¡¨) on 22 May 2002.
Pursuant to Section 13 of the EIAO, the Director amends the
Environmental Permit based on the Application No. VEP-475/2015. The amendments, described below, are
incorporated into this Environmental Permit (EP-136/2002/E). This Environmental Permit as amended is
for the decommission of the designated project
described in Part B subject to the conditions
specified in Part C.
The issue of
this environmental permit is based on the documents, approvals or permissions
described below:
®Ú¾Ú¡mÀô¹Ò¼vÅTµû¦ô±ø¨Ò¡n(Àôµû±ø¨Ò)²Ä10±øªº³W©w¡AÀô¹Ò«OÅ@¸p¸pªø(¸pªø)©ó2002¦~5¤ë22¤é±NÀô¹Ò³\¥iÃÒ(½s¸¹EP-136/2002)§å¤©¤g¤ì¤uµ{©Ý®i¸p («eºÙ¤g¤ì¤uµ{¸p¡A¤UºÙ¡§³\¥iÃÒ«ù¦³¤H¡¨)¡C®Ú¾ÚÀôµû±ø¨Ò²Ä13±øªº³W©w¡A¸pªø¦]À³§ó§ïÀô¹Ò³\¥iÃÒªº¥Ó½Ð½s¸¹VEP-475/2015 ×qÀô¹Ò³\¥iÃÒ¡C¥H¤U×q¤w¥]§t¦b¥»Àô¹Ò³\¥iÃÒ¤º(½s¸¹EP-136/2002/E)¡C¥»¸g×qªºÀô¹Ò³\¥iÃÒ§@¬°¸Ñ°£¹B§@¥»³\¥iÃÒB³¡©Ò»¡©úªº«ü©w¤uµ{¶µ¥Ø¡A¦ý¶·¿í¦uC³¡©Ò¦C©úªº±ø¥ó¡C
¥»Àô¹Ò³\¥iÃÒªºµo¥X¡A¤D¥H¤Uªí©Ò¦Cªº¤å¥ó¡B§åã©Î³\¥i§@¬°®Ú¾Ú¡G
Application No. ¥Ó½Ð®Ñ½s¸¹ |
VEP-475/2015 |
Document in
the Register : µn°O¥U¤Wªº¤å¥ó¡G |
(1) Environmental Impact Assessment ¡V Demolition
of Buildings and Structures in the Proposed Kennedy Town Comprehensive
Development Area Site : Final EIA Report, EM&A Manual and Executive
Summary (Register No.: AEIAR-058/2002) [Hereinafter referred to as ¡§the EIA
Report (Register No.: AEIAR-058/2002)¡¨] (1) °í¥§¦a«°ºî¦Xµo®i°Ï©î¨ø¤uµ{ Àô¹Ò¼vÅTµû¦ô : ³Ì²×Àô¹Ò¼vÅTµû¦ô³ø§i, Àô¹ÒºÊ¹î¤Î¼f®Ö¤â¥U ¤Î ¦æ¬FºKn (µn°O¥U½s¸¹¡GAEIAR-058/2002) [¤UºÙ¡§Àôµû³ø§i(µn°O¥U½s¸¹¡GAEIAR-058/2002)¡¨] (2)
The
Director¡¦s letter of approval of the EIA Report dated 16 April 2002, ref:
EP2/H1/KT/PT2/85 Ax 1 (2) Àô¹Ò«OÅ@¸p¸pªø©ó2002¦~4¤ë16¤éµo¥X§åãÀôµû³ø§iªº«H¥ó (ÀÉ®×½s¸¹: EP2/H1/KT/PT2/85 Ax 1) |
|
(3) Application for an Environmental Permit
No. AEP-136/2002 received on 24 April 2002 (3) ©ó2002¦~4¤ë24¤é¦¬¨ìªºÀô¹Ò³\¥iÃҥӽФå¥ó½s¸¹AEP-136/2002 (4) Environmental Permit issued on 22 May
2002 (Permit No. EP-136/2002) (4) ©ó2002¦~5¤ë22¤éñµoªºÀô¹Ò³\¥iÃÒ (³\¥iÃÒ½s¸¹EP-136/2002) (5) Application documents for Variation of
Environmental Permit including all attachments submitted by the Permit Holder
on 4 April 2007 (Application No. VEP-234/2007) (5)
³\¥iÃÒ«ù¦³¤H©ó2007¦~4¤ë4¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó¥]¬A©Ò¦³ªþ¥ó(¥Ó½Ð®Ñ½s¸¹¡GVEP-234/2007) (6)
Application
documents for Variation of Environmental Permit including all attachments
submitted by the Permit Holder on 27 September 2007 (Application No.
VEP-239/2007) (6)
³\¥iÃÒ«ù¦³¤H©ó2007¦~9¤ë27¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó¥]¬A©Ò¦³ªþ¥ó(¥Ó½Ð®Ñ½s¸¹¡GVEP-239/2007) (7)
Application
documents for Variation of Environmental Permit including all attachments
submitted by the Permit Holder on 4 June 2009 (Application No. VEP-287/2009) (7)
³\¥iÃÒ«ù¦³¤H©ó2009¦~6¤ë4¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó¥]¬A©Ò¦³ªþ¥ó(¥Ó½Ð®Ñ½s¸¹¡GVEP-287/2009) (8) Application documents for Variation of
Environmental Permit including all attachments submitted by the Permit Holder
on 20 October 2011 (Application No. VEP-337/2011) (8)
³\¥iÃÒ«ù¦³¤H©ó2011¦~10¤ë20¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó¥]¬A©Ò¦³ªþ¥ó(¥Ó½Ð®Ñ½s¸¹¡GVEP-337/2011) (9)
Environmental
Impact Assessment ¡VAlternative Ground Decontamination Works at the Proposed
Kennedy Town Comprehensive Development Area Site: Final EIA Report, EM&A
Manual and Executive Summary (Register No.: AEIAR-188/2015) [Hereinafter
referred to as ¡§the EIA Report (Register No.:AEIAR-188/2015)¡¨] (9)
°í¥§¦a«°ºî¦Xµo®i°Ï´À¥N¤g¦a°£¦Ã¤uµ{ - Àô¹Ò¼vÅTµû¦ô : ³Ì²×Àô¹Ò¼vÅTµû¦ô³ø§i, Àô¹ÒºÊ¹î¤Î¼f®Ö¤â¥U ¤Î ¦æ¬FºKn (µn°O¥U½s¸¹¡GAEIAR-188/2015) [¤UºÙ¡§Àôµû³ø§i (µn°O¥U½s¸¹¡GAEIAR-188/2015)¡¨] (10) Application documents for Variation of
Environmental Permit including all attachments submitted by the Permit Holder
on 27 May 2015 (Application No. VEP-475/2015) (10) ³\¥iÃÒ«ù¦³¤H©ó2015¦~5¤ë27¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó¥]¬A©Ò¦³ªþ¥ó(¥Ó½Ð®Ñ½s¸¹¡GVEP-475/2015) |
Application No. ¥Ó½Ð®Ñ½s¸¹ |
Date of Application ¥Ó½Ð¤é´Á |
List of Amendments Incorporated into this
Environmental Permit ¤w¥]§t¦b¥»Àô¹Ò³\¥iÃÒ¤ºªº×q¶µ¥Ø |
Date of Amendment ×q¤é´Á |
VEP-234/2007 |
4 April 2007 2007¦~4¤ë4¤é |
Add a new condition before each of the following conditions in Part C of Environmental Permit No. EP-136/2002: Conditions 1.8, 1.12, 1.13 and 2.5. ¦bÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002 C³¡²Ä1.8, 1.12, 1.13 ©M2.5 ¶µ±ø¥ó«e¦U¥[¤J¤@¶µ·sªº±ø¥ó¡C Vary Conditions 1.7, 1.11, 1.14, 2.3, 2.4, 2.5 and 2.7 in Part C of Environmental Permit No. EP-136/2002. §ó§ïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002 C³¡²Ä1.7, 1.11, 1.14, 2.3, 2.4, 2.5 ©M 2.7 ¶µ±ø¥ó¡C Renumber the permit conditions in Part C of the Environmental Permit No. EP-136/2002/A where appropriate. §âÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/A C³¡ªº±ø¥ó¾A·í¦a«·s½s¸¹¡C Renumber Figure 2 and Figure 3 to Figure 7 and Figure 6 respectively. §â¹Ï2©M¹Ï3¨Ì§Ç«·s½s¸¹¬°¹Ï7©M¹Ï6¡C Add 4 new figures and numbered as Figures 2 to 5. ¥[¤J4±i·sªº¹Ï¨Ã½s¸¹¬°¹Ï2¦Ü¹Ï5¡C |
30 April 2007 2007¦~4¤ë30¤é |
VEP-239/2007 |
27 Sep 2007 2007¦~9¤ë27¤é |
Amend Phase 1 Part 1 Project Boundary to align with curb line at northern end of Sai See Street. Amend Figures 2 and 3 accordingly. |
18 Oct 2007 2007¦~10¤ë18¤é |
VEP-287/2009 |
4 Jun 2009 2009¦~6¤ë4¤é |
Vary Conditions 1.1, 1.12 to 1.15, 2.5(g) to (p), 2.7 and 3.1 in Part C of Environmental Permit No. EP-136/2002/B to include reference to the temporary use of Phase 1 site by the holder of Environmental Permit No. EP-313/2008 to carry out Phase 1 Part 2 of the Project. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/B
C³¡²Ä1.1¶µ, 1.12¶µ¦Ü1.15¶µ, 2.5(g) ¶µ ¦Ü (p) ¶µ, ²Ä2.7¶µ ©M 3.1¶µ, ¥HÅã¥ÜÀô¹Ò³\¥iÃÒEP-313/2008¸¹ªº«ù¦³¤H±NÁ{®É¨Ï¥Î¥»¤uµ{¶µ¥Ø²Ä1¶¥¬qªº¤u¦a½d³ò, ¥H¶i¦æ¥»¤uµ{²Ä1¶¥¬q²Ä2³¡¤À¶µ¥Ø¡C Vary Condition 2.5(b) in Part C of Environmental Permit No. EP-136/2002/B to remove from Phase 1 Part 1 of the Project the demolition of the existing piers at the harbourfront at the northern boundary of the site. Amend Figures 2 by removing the notation ¡§existing piers to be demolished¡¨ accordingly. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/B
C³¡²Ä2.5(b) ¶µ, ±q¤uµ{¶µ¥Ø²Ä1¶¥¬q²Ä1³¡¤À¤¤, §R°£¥_³¡Ãä¬É®ü®Ç²{¦³½XÀYªº©î¨ø¤uµ{¡C ¬ÛÀ³¦a§R°£¹Ï2¤º¤§ª`ÄÀ ¡§existing piers to be demolished¡¨¡C |
29 June 2009 2009¦~6¤ë29¤é |
VEP-337/2011 |
20 Oct 2011 2011¦~10¤ë20¤é |
Vary Conditions 2.5(q) in Part C of Environmental Permit No. EP-136/2002/D to remove the requirement for demolition of the additional concrete paving at Phase 1 Site during Phase 2. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.5(q) ¶µ, ¥H²¾°£©ó¥»¤uµ{¶µ¥Ø²Ä2¶¥¬q®É©î¨ø¥»¤uµ{¶µ¥Ø²Ä1¶¥¬qªº¤u¦a½d³ò¤º¥[¾Qªº²V¾®¤gÂл\¤§n¨D¡C |
15 November 2011 2011¦~11¤ë15¤é |
VEP-475/2015 |
27 May 2015 2015¦~ 5¤ë 27 ¤é |
Vary Conditions 1.7, 2.1, 2.2, 2.7, 2.20 & 3.1 in Part C of Environmental Permit No. EP-136/2002/D to incorporate the EIA Report (Register No. AEIAR 188/2015). קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä1.7 ¶µ, 2.1 ¶µ, 2.2 ¶µ, 2.7¶µ, 2.20¶µ¤Î3.1¶µ, ¥H¥[¤JÀôµû³ø§i(µn°O¥U½s¸¹¡GAEIAR-188/2015)¡C Delete Condition 2.3 in Part C of Environmental Permit No. EP-136/2002/D. §R°£Àô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.3¶µ¡C Renumber the items under Condition 2.5 in Part C of the Environmental Permit No. EP-136/2002/D where appropriate for update of the Phase 2 work. ¦]À³¶µ¥Ø²Ä2¶¥¬q¤uµ{, §âÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡ªº²Ä2.5¶µ¤º²Ó¶µ¾A·í¦a«·s½s¸¹¡C Renumber Condition 2.5(q) as 2.5(v) in Part C of Environmental Permit No. EP-136/2002/D to add on-site reuse of remediated soil and 7-year Programme. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.5(q)¶µ¦¨¬°2.5(v) ¶µ¥H¥[¤Jì¦a«¥Î³B²z«áªd¤g¤Î7¦~¤uµ{¶µ¥Øp¹º¡C Renumber Conditions 2.11, 2.12, 2.13 and 2.14 as Conditions 2.5(g), 2.5(h), 2.5(i) and 2.5(j) in Part C of Environmental Permit No. EP-136/2002/D. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.11¶µ, 2.12¶µ, 2.13¶µ¤Î2.14¶µ¦¨¬°2.5(g) ¶µ, 2.5(h) ¶µ, 2.5(i) ¶µ¤Î2.5(j) ¶µ¡C Renumber Condition 2.15 as Condition 2.18 in Part C of Environmental Permit No. EP-136/2002/D and incorporate new remediation methods for Phase 2 works. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.15¶µ¦¨¬°²Ä2.18¶µ¨Ã¥[¤J²Ä2¶¥¬q¤uµ{ªº¤g¦a¦Ã¬V¾ãªv¤èªk¡C Renumber Condition 2.16 as Condition 2.19 in Part C of Environmental Permit No. EP-136/2002/D and update the remediation standards from ¡§Dutch B levels¡¨ to ¡§Risk-Based Remediation Goals¡¨ Standard. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.16¶µ¦¨¬°²Ä2.19¶µ¥H¥[¤J¥H§ó§ï¡u²üÄõB¼Ð·Ç¡v¦Ü¡u«ö·ÀIÂç©wªº¤g¦a¦Ã¬V¾ãªv¼Ð·Ç¡v¡C |
25 June 2015 2015¦~6¤ë25¤é |
|
|
Renumber Condition 2.17 as Condition 2.5(k) in Part C of Environmental Permit No. EP-136/2002/D. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.17¶µ¦¨¬°²Ä2.5(k)¶µ¡C Renumber Condition 2.18 as Condition 2.20 in Part C of Environmental Permit No. EP-136/2002/D and incorporate new mitigation measures for the Phase 2 remediation works. קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.18 ¶µ¦¨¬°²Ä2.20¶µ, ¥H§ó·s¤uµ{¶µ¥Ø²Ä2¶¥¬qªº·s½w¸Ñ±¹¬I¡C Renumber Condition 2.19 as Condition 2.23 in Part C of Environmental Permit No. EP-136/2002/D קïÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.19 ¶µ¦¨¬°²Ä2.23¶µ¡C Add New Conditions 2.5(w) for submission of a detailed updated Project Programme for Phase 2 works. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.5(w)¶µ¥H´£¥æ§ó·sªº²Ä2¶¥¬q¤uµ{¶µ¥Øp¹º¡C Add New Conditions 2.11 and 2.12 in Part C of Environmental Permit No. EP-136/2002/D to incorporate ecological precautionary measures for Phase 2 of the Project. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.11¶µ¤Î2.12¶µ¥H¥[¤J²Ä2¶¥¬q¤uµ{ªº¥ÍºA¹w¨¾±¹¬I¡C Add New Conditions 2.13 and 2.14 in Part C of Environmental Permit No. EP-136/2002/D for the submission of a Review Report for the area occupied by New World First Bus Depot. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.13¶µ¤Î2.14¶µ¥H°w¹ï·s¥@¬É²Ä¤@¤Ú¤h¼t¦û¥Î¤g¦aªºÀË°Q³ø§i¡C Add New Condition 2.15 in Part C of Environmental Permit No. EP-136/2002/D for the submission of Updated EM&A Manual for Biopile System Discharge Emissions and Ambient Hydrocarbon Monitoring ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.15 ¶µ¥H´£¥æ§ó·sªºÀôºÊ¤â¥U¥HºÊ¹î¡u¥Íª«°ïªk¡v¨t²Î±Æ©ñ¤Î¤j®ð¤ºªº¬´²B¤Æ¦Xª«¡C Add New Condition 2.16 in Part C of Environmental Permit No. EP-136/2002/D for the submission of Construction Noise Management Plan. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.16 ¶µ¥H´£¥æ«Ø¿v¾¸µºÞ²zp¹º¡C |
|
|
|
Add New Condition 2.17 in Part C of Environmental Permit No. EP-136/2002/D for the submission of Construction Site Drainage Management Plan. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.17 ¶µ¥H´£¥æ«Ø¿v¦a½L´ë°ÈºÞ²zp¹º¡C Add New Condition 2.21 in Part C of Environmental Permit No. EP-136/2002/D for the submission of Landscape Plan. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D C³¡²Ä2.21 ¶µ¥H´£¥æ¶é´º³]pp¹ºÁ`¹Ï¡C Add Condition 2.22 in Part C of Environmental Permit No. EP-136/2002/D for the submission of Remediation Report for the Phase 2 remediation works. ¥[¤J·sªºÀô¹Ò³\¥iÃÒ½s¸¹EP-136/2002/D
C³¡²Ä2.22¶µ¥H´£¥æ¤uµ{¶µ¥Ø²Ä2¶¥¬q¤g¦a°£¦Ã¤uµ{ªº¾ãªv³ø§i¡C Add Appendix C to provide a) remediation methods; b) criteria for on-site reuse of treated soil; and c) key mitigation measures for Phase 2 of the Project. ¥[¤Jªþ¥óC¥H´£¨Ña) ¤g¦a°£¦Ã¤èªk; b) ¸g³B²zªºªd¤g²{³õ¦A¥Î¼Ð·Ç; c)¥Dn½w¸Ñ±¹¬I¡C Add Appendix D to show the typical cross section and oblique view of a ¡§Biopile¡¨ for indicative purpose. ¥[¤Jªþ¥óD¥HÅã¥Ü¡u¥Íª«°ïªk¡vªº¤Á±¹Ï¤Î±×¨¤¹Ï¡C Renumber Appendix C as Appendix E to change the remediation standards from ¡§Dutch B levels¡¨ to ¡§Risk-Based Remediation Goals¡¨ Standard. קïªþ¥óC ¦¨¬°ªþ¥óE¥H§ó§ï¡u²üÄõB¼Ð·Ç¡v¦Ü¡u«ö·ÀIÂç©wªº¤g¦a¦Ã¬V¾ãªv¼Ð·Ç¡v¡C Vary Figure 5 to show the phase 2 Project Boundary; location of proposed future waterfront promenade and location of the New World First Bus Depot. קï¹Ï¤¥HÅã¥Ü¶µ¥Ø²Ä2¶¥¬q¤uµ{½d³ò; «Øij®üÀتø´Y ¤Î·s¥@¬É²Ä¤@¤Ú¤h¼t¦ì¸m¡C Add Figure 8 to show the indicative layout of zones for Phase 2 remediation works. ¥[¤J¹Ï¤K¥HÅã¥Ü¤uµ{¶µ¥Ø²Ä2¶¥¬q¤g¦a°£¦Ã¤uµ{®Éªº°Ï°ì¤À§G¡C |
|
25 June 2015 2015¦~6¤ë 25¤é |
|
|
|
Date ¤é´Á |
|
(Ken
Y.K. WONG) Principal
Environmental Protection Officer for
the Director of Environmental Protection Àô¹Ò«OÅ@¸p¸pªø (º®uÀô¹Ò«OÅ@¥D¥ô ¶ÀÄ£¥ú ¥N¦æ) |
|
PART B (DESCRIPTIONS OF DESIGNATED PROJECT)
B³¡ («ü©w¤uµ{¶µ¥Øªº»¡©ú)
Hereunder is
the description of the designated project mentioned in Part A
of this environmental permit (hereinafter referred to as the ¡§Permit¡¨):
¤U¦C¬°¥»Àô¹Ò³\¥iÃÒ(¤UºÙ ¡§³\¥iÃÒ¡¨)A³¡©Ò´£zªº«ü©w¤uµ{¶µ¥Øªº»¡©ú:
Title of Designated Projects «ü©w¤uµ{¶µ¥Øªº¦WºÙ |
Demolition of Buildings and Structures in the
Proposed Kennedy Town Comprehensive Development Area Site [The above designated projects are
hereinafter referred to as ¡§the Project¡¨] °í¥§¦a«°ºî¦Xµo®i°Ï©î¨ø¤uµ{ [¤W¦C«ü©w¤uµ{¶µ¥Ø¤UºÙ¡§¤uµ{¶µ¥Ø¡¨] |
Nature of Designated
Projects |
Decommissioning of a
municipal incinerator ¸Ñ°£¤@Ó¥«¬FµI¤ÆÄlªº¹B§@ |
Location of Designated Projects «ü©w¤uµ{¶µ¥Øªº¦aÂI |
Kennedy
Town. The location of the Project
is shown on Figure 1 attached to
this Permit. °í¥§¦a«°¡C¤uµ{¶µ¥Øªº¦aÂI¦p¥»Àô¹Ò³\¥iÃÒªº¹Ï1©Ò¥Ü¡C |
Scale and Scope of Designated Project(s) «ü©w¤uµ{¶µ¥Øªº³W¼Ò©M½d³ò |
Decommissioning of a
municipal incinerator, including demolition of the existing chimneys,
buildings and structures in the proposed Kennedy Town Comprehensive
Development Area site of about 3.4 ha. where the
existing incinerator locates, remediation of contaminated soil and wastes
within the site, and subsequent disposal of the remediated soil and wastes. ¸Ñ°£¤@Ó¥«¬FµI¤ÆÄlªº¹B§@¡A¥]¬A©î¨ø¸ÓµI¤ÆÄl©Ò¦b¦a±¿n¬ù3.4¤½³¼ªº ¡u°í¥§¦a«°ºî¦Xµo®i°Ï¡v¤º²{¦³ªº·Ï§w¡B¤j¼Ó¤Î«Ø¿vª«¡A¾ãªv¤Î³B¸m¦Ã¬V¤Fªº¤gÄ[¤Îª«®Æ¡C |
1. General
Conditions
1.1 The
Permit Holder and any person working on the Project shall comply with all
conditions set out in this Permit. Any
non-compliance by any person may constitute a contravention of the Environmental
Impact Assessment Ordinance (Cap.499) and may become the subject of appropriate
action being taken under the Ordinance. Upon completion of
Phase 1 Part 1 of the Project (see Condition 2.5), the holder of Environmental
Permit No. EP-313/2008 will take over the Phase 1 site from the Permit
Holder for the construction of the West Island Line (WIL). The holder of
Environmental Permit No. EP-313/2008 is required, through conditions
under EP-313/2008 or any subsequent variations, to follow up with relevant
conditions set out in this Permit
in relation to the temporary use of the Phase 1 site (which is named as
"Works Area B" in Environmental Permit No. EP-313/2008) during his
occupation of the Phase 1 site, in particular Conditions 1.12 to 1.15, 2.5(g)
to (u), 2.7 and 3.1. Upon
completion of the temporary use of the Phase 1 site for the construction of the
WIL, the holder of Environmental Permit No. EP-313/2008 will return the Phase 1
site to the Permit Holder for the implementation of Phase 2 of the Project.
1.2
The
Permit Holder shall ensure full compliance with all legislation from time to
time in force including without limitation the Noise Control Ordinance (Cap.
400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control
Ordinance (Cap. 358), Waste Disposal Ordinance (Cap. 354), Occupational Safety
and Health Ordinance (Cap. 509) and Factories and Industrial Undertakings
Ordinance (Cap. 59). This Permit
does not of itself constitute any ground of defense against any proceedings
instituted under any legislation.
1.3
The
Permit Holder shall make copies of this Permit together with all documents
referred to in this Permit or the documents referred to in Part
A of the Permit readily available at all times for inspection by the
Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall
include all documents referred to in the Permit and also the relevant documents
in the Register.
1.4
The
Permit Holder shall give a copy of this Permit to the person(s) in charge of
the site and ensure that such person(s) fully understands all conditions and
all requirements incorporated by the Permit. The site refers to the site of the
Project and should mean the same hereinafter.
1.5
The
Permit Holder shall display conspicuously a copy of this Permit on the site at all
vehicular site entrances/exits or at a convenient location for public¡¦s
information at all times. The
Permit Holder shall ensure that the most updated information about the Permit,
including any amended Permit, is displayed at such locations. If the Permit Holder surrenders a part or
the whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit
shall be removed from display at the site.
1.6
The Permit
Holder shall carry out the Project as described in Part B
of this Permit.
1.7
The
Permit Holder shall ensure that the Project is designed and constructed in
accordance with the information and all recommendations described in the EIA
Reports (Register No. AEIAR-058/2002 and Register No. AEIAR-188/2015), the
application documents for environmental permits and relevant documents in the
Register listed in Part A of this Permit; the
information or mitigation measures described in this Permit, mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, and mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents in the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8
The
Project shall be implemented in two Phases, with Phase 1 containing 2 Parts, as
described in detail in Condition 2.5 of this Permit. A tentative programme
for the Project was set out in the Application No. VEP-234/2007.
1.9
All
submissions as required under this Permit, shall be rectified and resubmitted in
accordance with the comments, if any, made by the Director, within one month of
the receipt of the Director¡¦s comments or otherwise specified by the Director.
1.10
All
submissions approved by the Director, all submissions deposited without
comments by the Director, or all submissions rectified in accordance with
comments by the Director under this Permit shall be construed as part of the
permit conditions described in Part C of this Permit. Any variation of the submissions shall
be approved by the Director in writing or as prescribed in the relevant permit
conditions. All submissions or any
variations of the submissions made after the establishment of an Environmental
Team (ET) and employment of an Independent Environmental Checker (IEC) referred
to in Conditions 2.1 and 2.2 below shall be certified by the ET Leader and verified
by the IEC before submitting to the Director under this Permit.
1.11
The
Permit Holder shall release all finalized submissions, as required under this
Permit, to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office, or in any other places, or any internet
websites as specified by the Director, or by any other means as specified by
the Director for public inspection.
For this purpose, the Permit Holder shall provide sufficient copies of
the submissions.
1.12
The
Permit Holder shall notify the Director in writing the commencement dates of
the three different phases of the Project: (a) Phase 1 Part 1, (b) Phase 1 Part
2 and (c) Phase 2 of the Project at least one month prior to the commencement
of each of the above three different phases of the Project respectively. The
Permit Holder shall notify the Director in writing immediately if there is any
change of any of the commencement dates.
Unless specified otherwise, the commencement of the Project shall be
taken to mean the commencement of the Phase 1 Part 1 of the Project. The holder
of Environmental Permit No. EP-313/2008 is required, through conditions under
EP-313/2008 or any subsequent variations, to follow up with this condition with
respect to notifying the Director the commencement date of Phase 1 Part 2, i.e.
temporary use of the Phase 1 site (which is named as ¡§Works Area B¡¨ in the
Environmental Permit No. EP-313/2008) for the construction of the WIL.
1.13
The
Permit Holder shall notify the Director in writing the completion dates of all
three different phases of the Project: (a) Phase 1 Part 1, (b) Phase 1 Part 2
and (c) Phase 2 of the Project within one month of the completion of each of
the above three different phases of the Project respectively. The holder of
Environmental Permit No. EP-313/2008 is required, through conditions under
EP-313/2008 or any subsequent variations, to follow up with this condition with
respect to notifying the Director the completion date of Phase 1 Part 2, i.e.
temporary use of the Phase 1 site (which is named a ¡§Works Area B¡¨ in the
Environmental Permit No. EP-313/2008) for the construction of the WIL.
1.14
The
Permit Holder shall notify the Director in writing the date of handing over the
site, or any part of the site, to any other party for the purpose of redevelopment
of the area at least one month prior to the handing over of the area. The Permit Holder shall notify the
Director in writing immediately if there is any change of the handing over
date. The holder of Environmental Permit No. EP-313/2008 is required, through
conditions under EP-313/2008 or any subsequent variations, to follow up with this
condition with respect to notifying the Director his exit from or handing over
of the Phase 1 site upon completion of Phase 1 Part 2, i.e. temporary use of
the Phase 1 site (which is named as ¡§Works Area B¡¨ in the Environmental Permit
No. EP-313/2008) for the construction of the WIL.
1.15
The
Permit Holder shall notify the Director in writing the commencement date for temporarily
using the site, or any part of the site, for the purpose as described in
Condition 2.5(m) at least one month prior to the commencement of temporary use
of the area. The Permit Holder shall
notify the Director in writing immediately if there is any change of the commencement
date for such temporary use. The holder of Environmental Permit No. EP-313/2008
is required, through conditions under EP-313/2008 or any subsequent variations,
to follow up with this condition with respect to notifying the Director the
commencement date for temporarily using the Phase 1 site (which is named as
¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008) for the
construction of the WIL under Phase 1 Part 2 of the Project.
1.16
All
submissions to the Director required under this Permit shall be delivered
either in person or by registered mail to the Environmental Impact Assessment
Ordinance Register Office (currently at 27/F, Southorn
Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF)
(version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies.
1.17
For
the purpose of this Permit, ¡§commencement of each Phase and/or each Part of a
Phase of the Project¡¨ does not include works related to site investigation,
contamination confirmatory investigation, or other works as agreed by the
Director. Any damage to the
existing concrete ground slab caused by site investigation, contamination
confirmatory investigation, or other works as agreed by the Director shall be
repaired as soon as practicable such that the structural integrity of the
existing concrete ground slab is maintained so as to avoid exposing the soil
underneath as far as practicable.
2.
Special Conditions
2.1
An
Environmental Team (ET) shall be established by the Permit Holder no later than
one month before the commencement of the Project. The ET shall be headed by an
ET Leader. The ET Leader shall be a person who has at least 7 years' experience
in environmental monitoring and auditing (EM&A) or environmental
management. The ET and the ET Leader shall be responsible for the duties
defined in the EM&A Manuals of the EIA Reports (Register No. AEIAR-058/2002
and Register No. AEIAR-188/2015). The ET Leader shall be responsible for the
implementation of the EM&A programme in accordance
with the EM&A requirements as contained in the EM&A Manuals. The ET
Leader shall keep a contemporaneous log-book of each and every instance or
circumstance or change of circumstances which may affect the environmental
impact assessment and each and every non-compliance
with the recommendations of the EIA Reports (Register No. AEIAR-058/2002 and Register
No. AEIAR-188/2015) or this Permit. This log-book shall be kept readily
available for inspection by all persons assisting in supervision of the
implementation of the EIA Report recommendations and this Permit or by the
Director or his authorized officers. Failure to maintain records in the
log-book, failure to discharge the duties of the ET Leader as defined in the
EM&A Manuals or failure to comply with this Condition would entitle the
Director to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit Holder to make replacement,
or further failure to keep contemporaneous records in the log-book despite the
employment of a new ET Leader may render the Permit liable to suspension,
cancellation or variation. The ET shall not be in any way an associated body of
the Contractor or the IEC for the Project.
2.2
An
Independent Environmental Checker (IEC) shall be employed by the Permit Holder
no later than one month before the commencement of the Project. The IEC shall be a person who has at
least 7 years' experience in environmental monitoring and audit (EM&A) or
environmental management. The IEC
shall be responsible for the duties defined in the EM&A Manuals of the EIA
Reports (Register No. AEIAR-058/2002 and Register No. AEIAR-188/2015), and
shall audit the overall EM&A programme described
in the EIA Reports (Register No. AEIAR-058/2002 and Register No. AEIAR-188/2015),
including the implementation of all environmental mitigation measures,
submissions required in the EM&A Manuals, and any other submissions
required under this Permit. In
addition, the IEC shall be responsible for verifying the environmental
acceptability of permanent and temporary works, relevant design plans and
submissions under this Permit. The
IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by fax,
within 24 hours of each and every occurrence, change of circumstances or
non-compliance with the EIA Reports (Register No. AEIAR-058/2002 and Register
No. AEIAR-188/2015) or this Permit, which might affect the monitoring or
control of adverse environmental impact. Where the IEC fails to so notify the Director
of the same, fails to discharge the duties of the IEC
as defined in the EM&A Manuals or fails to comply with this Condition, the
Director may require the Permit Holder by notice in writing to replace the IEC.
Failure to replace the IEC as directed or further failure to so notify the
Director despite employment of a new IEC may render the Permit liable to
suspension, cancellation or variation. Notification by the Permit Holder is the
same as notification by the IEC for the purpose of this Condition. The IEC
shall not be in any way an associated body of the Contractor or the
Environmental Team for the Project.
2.3
[Deleted]
2.4
The
Permit Holder shall, within one month after the commencement of each Phase and
each Part of a Phase of the Project, inform the Director in writing of the
management organization of the main companies and/or any form of joint ventures
associated with the carrying out of the Project. The submitted information
shall include at least an organization chart, names of responsible persons including
the ET Leader and the IEC, and their contact details. The different phases or part of a Phase
are defined under Condition 2.5 of this Permit.
Phased Approach for Implementing the
Project and Implementation Requirements
2.5
The
Project shall be implemented in two Phases with the following conditions.
Phase 1 Part 1
(a)
The
Site area for both Part 1 and Part 2 of Phase 1 of the Project is shown in Figure 2 of this Permit. At the time of notification of
commencement of Phase 1 Part 1 of the Project as required under Condition 1.12,
the Permit Holder shall deposit with the Director an updated Project programme, to be accompanied by layout plans with detailed
descriptions and drawings of mitigation measures in scale of 1:1000 or in other
suitable scale as agreed by the Director, showing clearly the relevant works in
Phase 1 Part 1 of the Project.
(b)
Phase
1 Part 1 of the Project includes demolition and clearance of all existing
chimneys, buildings and ancillary structures above the existing concrete ground
slab in the Phase 1 Site area where the former Kennedy Town Incinerator Plant
(KTIP) and the Kennedy Town Abattoir (KTA) are located. The Phase 1 Part 1 also includes the
removal of asbestos containing materials and dioxin/furan contaminated wastes
within the Phase 1 Site.
(c)
Hoardings
shall be erected around the Phase 1 Site at the commencement of Phase 1 Part 1
of the Project and shall be properly maintained throughout Phase 1 of the
Project to restrict access of the Phase 1 Site to only authorized site staffs and
workers.
(d)
Throughout
Phase 1 Part 1, the existing concrete ground slab within the Phase 1 Site shall
not be demolished but shall be retained intact as far as practicable. Before completion of the Phase 1 Part 1
of the Project, inspection shall be carried out on the condition of the
existing concrete ground slab and existing drainage system with the view to
identify and repair any surface cracks such that their structural integrity is
maintained to avoid exposing the soil underneath as far as practicable. Such inspection and repair shall be
carried out every month thereafter until the commencement of Phase 1 Part 2 of
the Project. Where the inspection
and repair work fall within the reporting month of the monthly Environmental
Monitoring & Audit (EM&A) report described under Condition 3.5 of this
Permit, the inspection findings and repair work carried out shall be reported
in that monthly EM&A report.
(e)
With
the exception of drainage facilities required for the proper function of the
site drainage system, the existing underground facilities such as refuse bunkers, lift pits, underground chambers and openings, and
sub-sided areas within the Phase 1 Site area shall be cleaned up and backfilled
with clean soil to about 130 mm from the top level of adjacent ground
slab. A layer of concrete cover of
not less than 130 mm thickness shall then be laid on top of the clean soil to
fill up the underground facilities such that the top level of the concrete
cover on top of the clean soil above the underground facilities matches the top
level of adjacent ground slab. Before completion of the Phase 1 Part 1 of the
Project, inspection shall be carried out on the condition of the concrete
covers and existing drainage facilities retained for the proper function of the
site drainage system, with the view to identify and repair any surface cracks
such that their structural integrity is maintained to avoid exposing the soil
underneath as far as practicable.
Such inspection and repair shall be carried out every month thereafter until
the commencement of Phase 1 Part 2 of the Project. Where the inspection and repair work
fall within the reporting month of the monthly Environmental Monitoring &
Audit (EM&A) report described under Condition 3.5 of this Permit, the
inspection findings and repair work carried out shall be reported in that
monthly EM&A report.
(f)
Phase
1 Part 1 of the Project shall not involve any excavation work that may disturb
or expose any part of the soil underneath the existing concrete slab.
Control on Demolition
(g)
Non-blasting
methods shall be used for the demolition of all structures within the project
site boundary including buildings and chimneys.
(h)
All
Asbestos Containing Materials (ACM) shall be removed prior to commencement of
demolition works except for those ACM removal works that are constrained by
access and have to be handled while the demolition work progresses.
Remediation and Disposal
of Wastes contaminated by Dioxins and/or Furans
(i)
Treatment
and disposal of wastes contaminated with dioxins and/or furans as identified in
Appendix A of this permit and in the CCI findings shall be
carried out in accordance with the approved WMP and shall include the following
steps:
a.
conduct
pilot mixing and Toxicity Characteristic Leachate Procedures (TCLP) tests for
the contaminated wastes to verify the effectiveness of the mix and establish
the necessary cement to wastes ratio for the purpose of compliance with the 1
part per billion toxicity equivalent (1 ppb TEQ) TCLP criteria;
b.
inform the Director the results of the pilot tests for confirmation of the
disposal site. If the pilot tests
identify that some of the contaminated wastes would need to be disposed of as
Chemical Wastes, the fallback option to be adopted to dispose of the Chemical
Wastes and the associated method statements shall be provided together with the
results of the pilot tests;
c.
treat
the contaminated wastes by mixing with cement;
d.
seal the treated wastes into steel drums lined with plastic sheeting after
passing the TCLP test as stated in Appendix B of this Permit. Duplicate samples of the treated wastes
may need to be collected for parallel testing by another qualified laboratory
if requested by the Director; and
e.
dispose of the drummed material in Condition 2.5(i)(d) above
to a Government landfill agreed by the Director under Condition 2.15(i)(b)
above.
(j)
Testing
shall be conducted on samples taken from any materials left on the North, South,
East, West and underneath of the removed materials to confirm that all
contaminated materials failing to meet the criteria of 1 ppb TEQ have been
removed for treatment. Duplicate
samples of the materials may need to be collected for parallel testing by
another qualified laboratory if requested by the Director.
Submission of
Remediation Reports
(k)
Six
hard copies and one electronic copy of Remediation Report(s) shall be deposited
with the Director after the completion of the remediation and disposal of
contaminated soil and wastes at specific site areas. The Remediation Report(s) shall
demonstrate that the remediation and disposal work for the site area that it
covers has been undertaken according to the specified methodology and has been
shown to be adequate. The Remediation Report(s) shall be submitted at least
four weeks before the concerned handed over to other parties for redevelopment.
The Remediation Report for works covered in Phase 1 Part 1 of the Project shall
be submitted at least four weeks before commencement of Phase 1 Part 2 of the Project.¡¨
The Remediation Report for works covered in Phase 1 Part 1 of the Project shall
be submitted at least four weeks before commencement of Phase 1 Part 2 of the
Project.
Phase 1 Part 2
(l)
At the
time of notification of commencement of Phase 1 Part 2 of the Project as
required under Condition 1.12, the Permit Holder shall deposit with the
Director a detailed updated Project programme, to be
accompanied by layout plans with detailed descriptions and drawings of
mitigation measures in scale of 1:1000 or in other suitable scale as agreed by
the Director, showing clearly the relevant works in Phase 1 Part 2 of the
Project. The Project shall be
implemented according to the updated programme. The holder of Environmental Permit No. EP-313/2008
is required, through conditions under EP-313/2008 or any subsequent variations,
to follow up with this condition during the temporary use of the Phase 1 site
(which is named as ¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008)
for the construction of the WIL.
(m)
Phase
1 Part 2 of the Project includes the temporary use of the Phase 1 Site as site office
and for the storage of common construction materials, the provision of
mitigation measures to avoid any potential release of additional underground
contaminants into the environment resulting from the above temporary use of the
site, and the provision of mitigation measures to avoid impacts on workers on
Phase 1 Site and the general public nearby, including residents and
passers-by. It also includes the
removal of temporary site office and facilities for the storage of common
construction materials before completion of the Phase 1 Part 2. The holder of
Environmental Permit No. EP-313/2008 is required, through conditions under
EP-313/2008 or any subsequent variations, to follow up with this condition
during the temporary use of the Phase 1 site (which is named as ¡§Works Area B¡¨
in the Environmental Permit No. EP-313/2008) for the construction of the WIL.
(n)
Under
Phase 1 Part 2 of the Project, the Permit Holder shall not use or carry out any
activity in the Phase 1 Site other than the site office and storage of common
construction materials as proposed. The holder of Environmental Permit No. EP-313/2008
is required, through conditions under EP-313/2008 or any subsequent variations,
to follow up with this condition during the temporary use of the Phase 1 site
(which is named as ¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008)
for the construction of the WIL.
(o)
At
locations within the Phase 1 Site area identified to be temporarily used as
site office and for storage of common construction materials, an additional
concrete paving of not less than 200 mm thickness shall be provided. The indicative extent of this additional
concrete paving, as extracted from the Application No. VEP-234/2007, is shown in Figure
3 of this Permit. The holder of Environmental Permit No. EP-313/2008 is
required, through conditions under EP-313/2008 or any subsequent variations, to
follow up with this condition during the temporary use of the Phase 1 site
(which is named as ¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008)
for the construction of the WIL.
(p)
No
temporary use, to include site office and storage of common construction
material, at the Phase 1 Site shall be allowed until Remediation Report(s) has
been deposited with the Director in accordance with Condition 2.5(k) below
after the completion of the remediation and disposal of dioxin/furan
contaminated wastes at specific site areas proposed for temporary use. The
holder of Environmental Permit No. EP-313/2008 is required, through conditions
under EP-313/2008 or any subsequent variations, to follow up with this
condition during the temporary use of the Phase 1 site (which is named as
¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008) for the
construction of the WIL.
(q)
No
temporary use, to include site office and storage of common construction
material, at the Phase 1 Site shall be allowed until the identified locations
for such temporary uses have been provided with the pre-requisite additional
concrete paving as stipulated in Condition 2.5(o) above. The holder of
Environmental Permit No. EP-313/2008 is required, through conditions under
EP-313/2008 or any subsequent variations, to follow up with this condition
during the temporary use of the Phase 1 site (which is named as ¡§Works Area B¡¨
in the Environmental Permit No. EP-313/2008) for the construction of the WIL.
(r)
Throughout
the entire period of Phase 1 Part 2, the additional concrete paving to avoid
exposing the contaminated soil underneath shall remain intact and shall not be
demolished. Within 7 days, and
every month thereafter, of the start of use of the Site for temporary site
office and/or storage of common construction materials, inspection shall be
carried out on the condition of the additional concrete paving, the site drainage
and the foul sewerage systems to identify, with the view to repair/remedy any
surface cracks such that the structural integrity of these systems is
maintained and the soil underneath will not be disturbed or exposed as far as
practicable. The holder of Environmental Permit No. EP-313/2008 is required,
through conditions under EP-313/2008 or any subsequent variations, to follow up
with this condition during the temporary use of the Phase 1 site (which is
named as ¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008) for the
construction of the WIL.
(s)
To
allow natural air dispersion of any entrapped vapour
contaminants that might be released from the soil and groundwater, the site
office to be erected in the Phase 1 Site shall be properly designed and
constructed to create and maintain a clear void of at least 500 mm height
between the underside of the site office floor and the top of the additional
concrete paving below. The
indicative design is shown in Figure
4 of this Permit. The holder of Environmental Permit No. EP-313/2008 is
required, through conditions under EP-313/2008 or any subsequent variations, to
follow up with this condition during the temporary use of the Phase 1 site
(which is named as ¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008)
for the construction of the WIL.
(t)
To
further safeguard against seepage of any vapour
contaminants into site offices from the soil and groundwater, the site office
to be erected in the Phase 1 Site shall be properly designed and constructed to
incorporate gas-resistant membranes flooring. The indicative design is shown in Figure 4 of this Permit. The holder
of Environmental Permit No. EP-313/2008 is required, through conditions under
EP-313/2008 or any subsequent variations, to follow up with this condition
during the temporary use of the Phase 1 site (which is named as ¡§Works Area B¡¨
in the Environmental Permit No. EP-313/2008) for the construction of the WIL.
(u)
Phase
1 Part 2 of the Project, including any additional site drainage and/or foul
sewerage works, shall not involve any excavation work that may disturb or
expose any part of the soil underneath the existing concrete slab and the
additional concrete paving. The holder of Environmental Permit No. EP-313/2008
is required, through conditions under EP-313/2008 or any subsequent variations,
to follow up with this condition during the temporary use of the Phase 1 site
(which is named as ¡§Works Area B¡¨ in the Environmental Permit No. EP-313/2008) for the construction of the WIL.
Phase 2
(v)
The
Phase 2 Site area is shown in Figure
5 of this Permit. Phase 2
of the Project shall commence as soon as practicable after the completion of
all Phase 1 Part 2 works and shall not be delayed. Phase 2 of the Project shall comprise
the demolition of existing concrete ground slab, demolition of any additional
site drainage and/or foul sewerage works, demolition of the existing Cadogan Street Temporary Garden,
refuse collection point, bus depot and public car park. Phase 2 of the Project shall also
include remediation of contaminated soil below ground level within the Phase 2
Site area and the subsequent on-site reuse of the remediated soil. The 7-year programme proposed in the approved EIA Report (Register No.
AEIAR-188/2015) for works in Phase 2 also involves on-site reprovision
of the public car park and refuse collection point.
(w) At the time of notification of commencement
of Phase 2 of the Project as required under Condition 1.12, the Permit Holder
shall deposit with the Director a detailed updated Project programme,
to be accompanied by layout plans with detailed descriptions and drawings of
mitigation measures in scale of 1:1000 or in other suitable scale as agreed by
the Director, having regard to measures described in Conditions 2.20, 2.23 and
Appendix C, showing clearly the relevant works in Phase 2 of the Project. The
Project shall be implemented according to the updated programme.
Submissions and Measures before
commencement of Phase 2 works
Contamination Confirmatory Investigation
2.6
To
cater for the phased approach for implementing the Project, a proposal on the
contamination confirmatory investigation (CCI) shall be submitted, before the
commencement of the Project, to the Director for approval. The Permit Holder
shall agree with the Director the timing for submitting the CCI proposal. The CCI proposal shall provide details
of the CCI programme to tie in, in terms of the
timing and location, with each Phase and each Part of a Phase of the Project.
The CCI programme shall state the timing for
submission of the CCI findings, review of the waste treatment and disposal
method, and preparation and submission of the Waste Management Plan taking into
account relevant CCI findings as required under Condition 2.7. The CCI shall provide further information
on the extent of contamination at the Investigation Areas A, B, C and D shown
in Figure 6 of
this Permit in addition to those assessed in the EIA Report (Register No.
AEIAR-058/2002). Six
hard copies and one electronic copy of the relevant findings of the CCI shall
be deposited with the Director before the commencement of each Phase of the
Project.
Submission of
Waste Management Plan
2.8
The
WMP shall include, but not limited to, the following information for each type of the wastes relevant to
the specific Project Phase/Part that it is intended to cover. The types of wastes to be covered should
include asbestos containing materials, dioxin/furan contaminated wastes,
contaminated soil, and construction and demolition materials.
(a)
summary
of the locational sources, quantity, level of contamination (if applicable), remediation
required prior to disposal (if applicable), and on-site and off-site disposal
methods for different type of wastes;
(b)
timings
for generation, remediation (if applicable), temporary on-site stockpiling or
storage, and final on-site or off-site disposal of different type of wastes;
(c)
timings
for conducting the pilot tests as required under Conditions 2.5(i)(a) as
appropriate;
(d)
method
statements on the remediation works to be carried out on different types of
contaminated soil and wastes, and the confirmatory and parallel independent
testing to be conducted;
(e)
on-site
waste management measures to control nuisances during the generation, handling,
remediation (if applicable), and temporary stockpiling of the different types
of wastes, in particular for asbestos containing materials, dioxin/furan
contaminated wastes and contaminated soil;
(f)
possible
recycling and reuse of materials;
(g)
location
of the disposal site(s) for various types of wastes;
(h)
confirmation
on whether or not barges would be used for removal of wastes;
(i) transportation routing(s) of the removal of
various types of wastes from the project site to the disposal site(s);
(j)
measures
to control nuisances due to transportation of different type of wastes, in
particular to avoid loss of asbestos containing materials, dioxin/furan
contaminated wastes and contaminated soil; to remove possible soil left on the
first several hundred meters of roads by vehicles leaving the site, such as the
option of using specially design road cleansing vehicle; and to reduce dust
nuisance from trucks carrying wastes, such as the option of installing
mechanical covers to trucks;
(k)
trip-ticket
system for waste transfer/disposal operations, including a certification system
to confirm to the disposal site¡¦s operator that the contaminated wastes have
been remediated to meet the specific disposal criteria; and
(l)
responsibilities for implementation.
2.9
All
the measures recommended in the approved WMP shall be fully implemented in
accordance with the requirements and time schedule(s) set out in the WMP.
2.10
Before
obtaining the Director¡¦s approval on the WMP as required under Condition 2.7, no
disposal of waste, spoil, soil, excavation materials or materials obtained from
the Project site shall be allowed at any locations.
Ecological
Precautionary Measures
2.11
Before
commencement of site clearance works, the Project site shall be inspected to
confirm that there are no active bird nests on trees. If any active bird nest
is found, a suitably sized buffer area shall be established around the tree to
minimise human or machinery disturbance until the nest is abandoned.
2.12
Before
commencement of site clearance works, daytime inspection shall be carried out
to confirm that there are no Short-nosed Fruit Bats on trees, particularly Chinese
Fan-palms, within the Project site. If any Short-nosed Fruit Bat is found roosting
on a tree, a suitably sized buffer area shall be established around the tree to
minimise human or machinery disturbance until the bat has left.
Submission
of Review Report for the Area occupied by the New World First Bus Depot
2.13
As the
area occupied by the New World First Bus Depot (Bus Depot) as shown in Figure 5 of this Permit may be
subjected to further contamination since approval of the CAR/RAP in the EIA
Report (Register No. AEIAR-188/2015), the Permit Holder shall, no later than
two months before commencement of work at the Bus Depot area, deposit with the
Director four hard copies and one electronic copy of a Review Report to
confirm:
(a)
the
validity of the approved CAP and CAR/RAP in the EIA Report (Register
No.AEIAR-188/2015);
(b)
whether
there is any potential contaminations due to the continual operation of the Bus
Depot; and
(c)
whether further site investigation is required.
2.14
The Review
Report shall be prepared based on a site appraisal conducted in accordance with
the ¡§Practice Guide for Investigation and Remediation of Contaminated Land¡¨
issued by EPD. If the Review Report confirms that further site investigation is
required, the Permit Holder shall:
(a)
submit
to the Director for approval four hard copies and one electronic copy of a
Supplementary Contamination Assessment Plan (SCAP), which shall include details
of representative sampling and analysis required to determine the nature and
extent of further contamination; and
(b)
no
later than one month after the completion of the site investigation works in
accordance with the approved SCAP, submit to the Director for approval four
hard copies and one electronic copy of Supplementary Contamination Assessment
Report to document the findings of the site investigation works and assessment
on the nature and extent of further contamination and a Supplementary Remediation
Action Plan with necessary remediation measures.
Submission of Updated EM&A Manual for Biopile
System Discharge Emissions and Ambient Hydrocarbons Monitoring
2.15
The
Permit Holder shall, no later than one month before the commencement of Phase 2
of the Project, submit to the Director for approval four hard copies and one
electronic copy of an updated EM&A Manual for the Project. The updated EM&A Manual shall
include:
(a) updates on the environmental
monitoring and audit requirements relating to Biopile System Discharge
Emissions and Ambient Hydrocarbons (HC) Monitoring as recommended in Chapter 2
of the EM&A Manual of the EIA Report (Register No. AEIAR-188/2015);
(b) drawings in the scale
of 1:5,000 or other appropriate scale as agreed by the Director showing the
proposed locations for conducting Biopile System Discharge Emissions and Ambient
HC Monitoring;
(c) proposed monitoring
methodology and measurement parameters; and
(d) an Event and Action
Plan with proposed immediate remedial action(s).
Submission of Construction Noise Management
Plan
2.16
To avoid
construction noise impact on S.K.H. Lui Ming Choi
Memorial Primary School, the Permit Holder shall, no later than one month
before the commencement of construction of relevant part of the Project, submit
to the Director for approval four hard copies and one electronic copy of a
Construction Noise Management Plan (CNMP) for construction work during
examination periods of the School. The plan shall include:-
(a) a proposal of construction noise mitigation
measures, including the provision of noise barriers and enclosures for
different types of construction activities to be carried out for the Project
where applicable, and any other initiatives proposed by the Permit Holder; and
(b) administrative
measures, including setting up a manned hotline or a channel of communication
with the School, to avoid noisy construction activities during examination).
Submission
of Construction Site Drainage Management Plan
2.17
Four
hard copies and one electronic copy of Construction Site Drainage Management
Plan (CSDMP) with detailed design of the site drainage system and incorporating
the requirements stipulated in S.5.7.1.1 of the EIA Report (Register No.:
AEIAR-188/2015), certified by a qualified civil engineer with suitable drainage
system design experience, shall be submitted to the Director for approval before
commencement of the Phase 2 of the Project. The CSDMP shall include detailed
designs of cut-off channels, earth bunds or similar impervious water barriers for
collecting and preventing site runoff from escaping off-site.
Submissions
and Measures during Phase 2 Works
Remediation of Soil Contaminated with
Heavy Metal and/or Hydrocarbons
2.18
Remediation
for contaminated soil identified in the Contamination Assessment Report /
Remediation Action Plan (CAR/RAP) in Appendix 7.2 of the EIA Report (Register
No. AEIAR-188/2015) and any further site investigation required in Condition 2.13
shall be carried out according to the following methods: :
(a)
The remediation
methods as stated in Appendix C of this permit shall be adopted for the 3
different types of contaminated soil, i.e. Type A contaminated soil (Heavy
Metals) by cement solidification; Type B contaminated soil (Hydrocarbons) by biopiling; and Type C contaminated soil (Heavy Metals and
Hydrocarbons) by biopiling followed by cement
solidification. A typical cross section and oblique view of a biopile is shown
in Appendix D.
(b)
Upon
proper treatment, Type A soil shall be reused on site after passing the TCLP
test as stated in Table C1 of Appendix C of this permit and meeting the
Unconfined Compressive Strength (UCS) test of not less than 1 MPa. Duplicate
samples of the treated soil may need to be collected for parallel testing by
another qualified laboratory if requested by the Director; and
(c)
Upon proper
treatment, Type B soil shall be reused on site after passing the biopile
closure assessment as stated in Table C2 of Appendix C of this permit.
Duplicate samples of the treated soil may need to be collected for parallel
testing by another qualified laboratory if requested by the Director.
(d)
Upon proper
treatment, Type C soil shall be reused on site after passing the TCLP test, UCS
test and biopile closure assessment as required in above Conditions 2.18(b) and
(c). Duplicate samples of the treated soil may need to be collected for
parallel testing by another qualified laboratory if requested by the Director.
2.19
Prior
to backfilling the respective excavation zones with treated soil, confirmatory
sampling shall be conducted to confirm that all contaminated soil has been
removed. The confirmatory sampling will be conducted in accordance with the
requirements stipulated in Section 4.3.3. of CAR/RAP
in Appendix 7.2 of the EIA Report (Register No. AEIAR-188/2015) to meet the Risk
Based Remediation Goals (¡§RBRG¡¨) Standards as shown in Appendix E of this
Permit. Duplicate samples of the soil may need to be collected for parallel
testing by another qualified laboratory if requested by the Director.
Mitigation and Precautionary Measures
2.20
Mitigation
measures shall be implemented to prevent pollution, control nuisances, and
reduce risk during the remediation phases, in accordance with the EIA Reports
(Register No. AEIAR-058/2002 and AEIAR-188/2015), including but not limited to
the following:
(a)
Control
on active works area (i.e. area with concrete paving material removed and
without any cover)
(i) During
excavation works, no more than 1,200 m2 total active works area shall
be in operation at any one zone. The indicative layout of zone groups is shown
in Figure 8 of this Permit.
(ii) No more
than 3,200 m2 total active works area shall be allowed at any one
time over the entire Project site for better control on the potential emission
of hydrocarbons, heavy metals and fugitive dusts.;
(b)
Dust
suppression measures
All active works areas shall be sprayed
with water frequently at no less than once every 2.5 hours. All stockpiled soil
shall be covered with tarpaulin or other impermeable material to minimise potential
emissions of fugitive dust, heavy metals and hydrocarbons.;
(c)
Control
measures during remediation by biopile method:
i) During
biopile operation, the biopiles shall be enclosed by
impervious membrane during bio-degradation process and activated carbon filters
with an installed removal efficiency of at least 99% of Volatile Organic
Compounds (VOC) shall be fitted to the pipe outlet(s) of the biopile(s);
ii) Emissions
from the biopile pipe outlet(s) shall be regularly monitored by a Continuous
Emission Monitoring System to check the performance of the activated carbon
filter system; and
iii) Spent
activated carbon filter shall be replaced regularly to ensure that the measured
total Volatile Organic Compounds (VOC) emission concentration from the system
is below 20 ppm; and
iv) The extraction pump and/or blower for the biopile pipe
network shall be switched off to stop system discharge emission when exceedance
of the monitored total VOC limit of 20 mg/m3 is detected and/or
unacceptable air quality is monitored at the site boundary. Resumption of
biopile system discharge emission shall only be allowed after confirmation and
implementation of appropriate mitigation measures, e.g. replacement of the
activated carbon filter. ;
(d)
Control
measures during remediation by cement solidification method:
The cement
solidification process and the associated storage bins shall be fully
enclosed. Any storage piles shall
be covered with tarpaulin or other impermeable material. Soils that require
both hydrocarbons (HC) and heavy metals (HM) remediation will first go through
HC remediation by biopiling and then through HM remediation
by cement solidification; and
(e)
The Key
Mitigation Measures as stated in Appendix C of this Permit shall be implemented.
Submission of Landscape Plan
2.21
To
reduce the landscape impact due to the Project, four hard copies and one
electronic copy of a Landscape Plan, at least one month before the commencement
of corresponding parts of landscape works of the Project, shall be deposited
with the Director. The Plan shall
include the design details, locations, implementation programme,
maintenance and management schedules, and drawings in the scale of 1:1,000 or
other appropriate scale as agreed by the Director of the landscape mitigation
measures of the Project as recommended in the EIA Report (Register No.: AEIAR ¡V
188/2015). In particular, the Landscape Plan shall show the design of the
waterfront promenade and details of the tree compensatory proposal. Compensatory
tree planting with a minimum ratio of 1:1 in terms of quantity shall be
provided in the proposed future waterfront promenade
Submission of Remediation Report(s)
2.22
Six
hard copies and one electronic copy of Remediation Report(s) shall be submitted
to the Director for approval after the completion of the remediation of corresponding
areas of the Project. The
Remediation Report(s) shall demonstrate that the remediation for the site area
that it covers has been undertaken according to the specified methodology and has
met the treatment Goals at Appendix
E for the intended land use, i.e. Urban Residential, Rural Residential,
Industrial or Public Parks, known at the time of submission. The Remediation
Report(s) shall be submitted at least four weeks before the concerned area(s)
of Phase 2 of the Project is/are handed over to other parties for redevelopment.
Measures for Works in all Phases
2.23
Mitigation
measures shall be implemented to prevent other demolition related nuisances
throughout the demolition and remediation phases, in accordance with the EIA
Report (Register No. AEIAR-058/2002), including but not limited to the
following:
(a) provide boundary hoarding of height not
less than 5.5 meters measured from street level modified to perimeter noise
barrier form, and made of panels with superficial surface density not less than
10 kg/m2;
(b) provide moveable noise barriers close to
powered mechanical equipment (PME) in cases where, in the opinion of the ET
leader, IEC or the Director, such PME has the potential to cause excessive
noise nuisance to sensitive receivers and where a benefit will result from
providing the barriers;
(c) if necessary, in addition to the Conditions
2.23(a) and (b) above, modify continuous operational periods for noisy plant or
take other measures to comply with the construction noise criteria;
(d) use adequately designed and maintained
perimeter channels, sediment traps, temporary channels, temporary diversion and
oil interception facilities to mitigate site run-off impacts;
(e) divert all clean surface water around the
site; and
(f) provide bunded areas for
generators, and for storage of fuel, oil and chemical wastes.
3.
Environmental Monitoring and Audit (EM&A) for the Project
3.1
The
EM&A programme shall be implemented as set out in
the EM&A Manuals of the EIA Reports (Register AEIAR-058/2002 and
EIAR-188/2015). Any changes to the programme shall be
justified by the IEC as conforming to the requirements set out in the EM&A
Manuals and shall be submitted to the Director for approval. An updated EM&A Manual with details
covering the two different phases of the Project: (a) Phase1 Part 1 and (b)
Phase 1 Part 2 of the Project, making reference to the documents submitted with
the Application for Variation of Environmental Permit (Application No. VEP-234/2007), shall be submitted to the Director for approval at least
1 month before commencement of each of the specific phases of the Project: that
is (a) Phase 1 Part 1 and (b) Phase 1 Part 2 of the Project. The holder of
Environmental Permit No. EP-313/2008 is required, through conditions under
EP-313/2008 or any subsequent variations, to follow up with this condition with
respect to submission of an EM&A Manual and implementation of an EM&A programme for Phase 1 Part 2, i.e. temporary use of the
Phase 1 site (which is named as ¡§Works Area B¡¨ in the Environmental Permit No.
EP-313/2008) for the construction of the WIL.
3.2
A
complaint investigation procedure shall be set up at least two weeks before the
commencement of the Project. The
complaint investigation procedure shall follow the requirements set out in the
EM&A programme.
3.3
All
environmental monitoring and audit data submitted under this Permit shall be
true, valid and correct.
3.4
Four
hard copies and one electronic copy of the Baseline Monitoring Report shall be
submitted to the Director at least two weeks before the commencement of the Project.
Additional copies of the submission shall be provided to the Director upon
request from the Director.
3.5
Four hard
copies and one electronic copy of monthly EM&A Report shall be submitted to
the Director within two weeks after the end of the reporting month. Additional
copies of the submission shall be provided to the Director upon request from
the Director.
3.6
The
actions described in the Event/Action Plans of the EM&A Manual shall be
fully and properly carried out, in accordance with the time frame(s) set out in
the Event/Action Plan, or as agreed by the Director.
4.
Electronic
Reporting of EM&A Information
4.1
To
facilitate public inspection of the Baseline Monitoring Report and monthly
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies as described in Conditions 3.4
and 3.5 of this Permit. For the HTML version, a content page capable of
providing hyperlinks to each section and sub-section of these Reports shall be
included at the beginning of the document. Hyperlinks to all figures, drawings
and tables in these Reports shall be provided in the main text where the
respective references are made. All graphics in these Reports shall be in
interlaced GIF format unless otherwise agreed by the Director. The content of
the electronic copies of these Reports shall be the same as the hard copies.
4.2
All
environmental monitoring data described in Condition 4.1 above shall be made
available to the public via internet access in the shortest possible time and
in no event later than two weeks after the relevant environmental monitoring
data are collected or become available, unless otherwise agreed with the
Director. The Permit Holder shall notify the Director in writing, within six
weeks after the commencement of the Project, the internet address where the
environmental monitoring data are to be placed. The internet address and the
relevant environmental monitoring data shall be made available to the public
via the EIAO Internet Website and the EIAO Register Office.
4.3
The
internet website as described in Condition 4.2 above shall enable user-friendly
public access to the monitoring data with features capable of:
(a) providing access to all environmental
monitoring data collected since the commencement of the Project;
(b) searching by date;
(c) searching by types of monitoring data; and
(d) hyperlinking to relevant monitoring data
after searching;
or
otherwise as agreed by the Director.
Notes
:
1.
This Permit consists of three parts,
namely, PART A (Main Permit), PART B
(Description of Designated Project) and PART C (Permit
Conditions). Any person relying on this permit should obtain independent legal
advice on the legal implications under the Ordinance, and the following notes
are for general information only.
2.
If there is a breach of any conditions of this Permit, the Director or
his authorized officer may, with the consent of the Secretary for the
Environment, order the cessation of associated work until the remedial action
is taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
3.
The Permit Holder may
apply under Section 13 of the Ordinance to the Director for a variation of the
conditions of this Permit. The Permit Holder shall replace the original permit
displayed on the Project site by the amended permit.
4.
A person who assumes the
responsibility for the whole or a part of the designated project may, before he
assumes responsibility of the designated project, apply under Section 12 of the
Ordinance to the Director for a further environmental permit.
5.
Under Section 14 of the Ordinance, the
Director may with the consent of the Secretary for the Environment, suspend,
vary or cancel this Permit. The suspended, varied or cancelled Permit shall be
removed from display at the Project site.
6.
If this Permit is cancelled or
surrendered during the Project, another environmental permit must be obtained
under the Ordinance before the Project could be continued. It is an offence
under Section 26(1) of the Ordinance to decommission a designated project
listed in Part II of Schedule 2 of the Ordinance without a valid environmental
permit.
7.
Any person who carries out the Project
contrary to the conditions in the Permit, and is convicted of an offence under
the Ordinance, is liable: -
(i)
on a first conviction on indictment to a
fine of $ 2 million and to imprisonment for 6 months;
(ii)
on a second or subsequent conviction on
indictment to a fine of $ 5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine
at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any
case where the offence is of a continuing nature, the court or magistrate may
impose a fine of $ 10,000 for each day on which he is satisfied the offence
continued.
8.
The Permit Holder may appeal against any
condition of this Permit under Section 17 of the Ordinance within 30 days of
receipt of this Permit.
9.
The Notes are for general reference only
and that the Permit Holder should refer to the EIA Ordinance for details and
seek independent legal advice.
10. Occupational
safety and health issues are governed by the Occupational Safety and Health
Ordinance (Cap. 509), and Factories and Industrial Undertakings Ordinance
(Cap.59). The Permit Holder is advised to contact the Labour
Department for requirements relating to occupational safety and health issues.
Environmental Permit No.
EP-136/2002/E
Àô¹Ò³\¥iÃÒ½s¸¹ EP-136/2002/E
| Figure 1 | Figure 2 | Figure 3 | Figure 4 | Figure 5 | Figure 6 | Figure 7 | Figure 8 |
[ Back to First
Page ] / [ Back to
Main Index ]
Locations Identified
in the EIA Report (AEIAR-058/2002) Requiring
APPENDIX A
Remediation and the Actions Recommended
(Extracted from table 4.3 of the EIA Report, Register No. AEIAR-058/2002))
Table
A Soil/Rubbles/Ash
Wastes Remediation Actions Required
Borehole# |
Action Required |
Remove concrete
surface and clear uncontaminated surface material and stockpile |
Proposed depth
of Material for Removal or Treatment |
Remedial Action |
Reassurance /
Confirmatory Sampling |
TB1 |
Yes |
Concrete down to 0.3m depth |
Immediately below concrete 0.3m to 4.0m |
Immobilisation for 0.3m to
2.0m and 3.0m to 4.0m* TCLP test followed by removal of 2.0m to
3.0m to landfill. Immobilisation if TCLP tests exceed criteria **. |
Yes, determine extent of HM (Cd, Cu, Pb, Zn and Hg) and TPH contamination at edge and base of
excavated hole.* |
TB2 |
Yes |
Concrete down to 0.5m depth |
Immediately below concrete 0.5m to 1.5m |
Immobilisation* |
Yes, determine extent of HM (As, Cu, Pb and Zn) contamination at edge and base of excavated
hole.* |
TB3 |
Yes |
Concrete down to 2.5m depth |
2.5m to 3.5m |
Immobilisation * |
Yes, determine extent of HM (Cu, Pb, Zn and Hg) contamination at edge and base of
excavated hole.* |
TB4 |
Yes |
Down to 2.2m depth |
2.2m to 4.2m |
Immobilisation * |
Yes, determine extent of HM (As, Cu, Pb and Zn) contamination at edge and base of excavated
hole.* |
TB5 |
Yes |
Concrete down to 1.8m. Down to 2.5m depth |
2.5m to 4.0m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination at edge and base of excavated hole.* |
TB8 |
Yes |
Concrete down to 1m. Down to 2.5m |
2.5m to 3.5m |
TCLP test
followed by removal of 2.5m to 3.5m to landfill. Immobilisation
if TCLP tests exceed criteria **. |
Yes, determine extent of PAH contamination
at edge and base of excavated hole.* |
TB9 |
Yes |
Concrete down to 1.0m depth |
1.0m to 2.0m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination at edge and base of excavated hole.* |
TB10 |
Yes |
Surface rubble/ash and brick material (not
soil) about 1.5m depth. |
1.5 m |
Clear Waste to
landfill. Waste to be treated and
tested to meet EPD disposal criteria.
|
Yes, determine extent of HM (As, Cd, Cu, Pb, Zn) TPH and PCDD/PCDF contamination under surface
contaminated materials.* |
TB11 |
Yes |
Down to 1.5m depth |
1.5 m |
Clear Waste to
landfill. Waste to be treated and
tested to meet EPD disposal criteria.
|
Yes, determine extent of HM (Cd, Cu, Pb, and Zn) and PCDD/PCDF contamination under surface
contaminated materials.* |
TB11 |
Yes |
Below hardstanding
surface (soil materials) |
1.5 to 4.0m |
Immobilisation* |
Yes, to determine extent of HM (Pb) contamination at edge and base of excavated hole. |
TB12 |
Yes |
Concrete down to 0.5m |
0.5 to 1.5m |
Immobilisation* |
Yes, determine extent of HM (Cd, Cu, Pb and Zn) contamination at edge and base of excavated
hole.* |
TB13 |
Yes |
Down to 2.5m |
2.5m to 3.5m |
Immobilisation* |
Yes, determine extent of HM (Pb, Zn, Hg) contamination at
edge and base of excavated hole.* |
TB15 |
Yes |
Concrete down to 0.4m |
0.4 to 2.4m |
TCLP test followed by removal of 0.4m to
2.4m to landfill. Immobilisation if TCLP tests exceed criteria **. |
Yes, determine extent of HM (As, Cu, Pb, Hg and Zn) and PAH contamination at edge and base of
excavated hole.* |
TB16 |
Yes |
Concrete down to 0.8m |
0.8 to 4.3m |
Immobilisation * |
Yes, determine extent of HM (Cu, Pb and Zn) contamination at edge and base of excavated
hole.* |
TB17 |
Yes |
Concrete down to 0.4m |
0.4 to 2.4m |
Immobilisation * |
Yes, determine extent of HM (Pb and Hg) contamination at edge and base of excavated
hole.* |
TB18 |
Yes |
Concrete down to 1.0m |
1.0m to 2.0m |
Immobilisation * |
Yes, determine extent of HM (Pb) contamination at edge and base of excavated hole.* |
TB19 |
Yes |
Concrete down to 0.6m |
0.6m to 4.0m |
Immobilisation * |
Yes, determine extent of HM (Pb and Hg) contamination at edge and base of excavated
hole.* |
TB20 |
Yes |
Concrete down to 0.3m |
0.3m to 2.3m |
TCLP test followed by removal of 0.3m to
2.3m to landfill. Immobilisation if TCLP tests exceed criteria **. |
Yes, determine extent of HM (As, Cu, Pb, Hg, Cd and Zn) PAH and TPH
contamination at edge and base of excavated hole.* |
TB21 |
Yes |
Concrete down to 0.5m |
0.5m to 5.0m |
TCLP test followed by removal of 0.5m to
3.5m to landfill. Immobilisation if TCLP tests exceed criteria **. Remaining depth to be immobilised to 5m * |
Yes, determine extent of HM (Cu, Pb, Hg and Zn) and TPH contamination at edge and base of excavated
hole.* |
TB22 |
Yes |
Concrete down to 0.5m |
0.5 to 1.5m |
Immobilisation * |
Yes, determine extent of HM (Pb) contamination at edge and base of excavated hole.* |
TB23 |
Yes |
Concrete down to 0.5m |
0.5 to 4m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination at edge and base of excavated hole.* |
TB24 |
Yes |
Concrete down to 1.2m |
1.2 to 4.2m |
Immobilisation* |
Yes, determine extent of HM (Cu, Pb
and Hg) contamination at edge and base of excavated hole.* |
TB25 |
Yes |
Concrete down to 0.9m. Down to 1.0m |
Depth 1.0m ¡V 4.4m |
TCLP test followed by removal of 1.0m to
2.9m to landfill. Immobilisation if TCLP tests exceed criteria **. Immobilisation for remaining
2.9m to 4.4m* |
Yes, to determine extent of HM (Pb, Hg) and PAH contamination at edge and base of excavated
hole.* |
TB26 |
Yes |
Concrete down to 0.8m |
Depth 0.8m ¡V 3.0m |
TCLP test followed by removal of 0.8m to
3.0m to landfill. Immobilisation if TCLP tests exceed criteria **. |
Yes, to determine extent of HM (Pb, Cu, Zn, Hg) and TPH contamination.* |
TB27 |
Yes |
Concrete down to 0.5m and clean soil down to
2.0m |
2.0 to 4.0m |
TCLP test
followed by removal of 2.0m to 4.0m to landfill. Immobilisation
if TCLP tests exceed criteria **. |
Yes, determine extent of HM (Cu and Pb) and PAH contamination at edge and base of excavated
hole.* |
TB28 |
Yes |
Concrete down to 0.4m |
0.4 to 4.4m |
Immobilisation* |
Yes, determine extent of HM (As, Cd, Cu, Pb, and Zn)
contamination at edge and base of excavated hole.* |
TB29 |
Yes |
Concrete down to 0.5m |
0.5 to 3.5m |
Immobilisation* |
Yes, determine extent of HM (Cu, Pb, Hg and Zn) contamination at edge and base of
excavated hole.* |
TB30 |
Yes |
Concrete down to 0.6m |
0.6 to 1.6m |
Immobilisation* |
Yes, determine extent of HM (Pb) contamination at edge and base of excavated hole.* |
Refuse Bunkers |
Yes |
N/A |
N/A |
Landfill disposal * |
Examine bunker refuse prior to demolition. |
# For location of
boreholes, please refer to Figure 7
of the Permit
* If contamination confirmed by reassurance sampling extract a
further 1m into the soil, immobilise and resample.
** TCLP test
for all metals identified in Table E1 in EPD Contaminated Sites Investigation
and Remediation Guidance Notes
--- END OF APPENDIX A ---
Criteria
for Soil Contamination and Landfill Disposal of Contaminated
Soil
APPENDIX B
(Extracted
from Appendix B of the EIA Report, Register No. AEIAR-058/2002)
Disposal Criteria for
Contaminated Soil
Metals (for on-site reuse)
Parameter |
TCLP
Limit (ppm) |
Cadmium |
10 |
Chromium |
50 |
Copper |
250 |
Nickel |
250 |
Lead |
50 |
Zinc |
250 |
Mercury |
1 |
Tin |
250 |
Silver |
50 |
Antimony |
150 |
Arsenic |
50 |
Beryllium |
10 |
Thallium |
50 |
Vanadium |
250 |
Selenium |
1 |
Barium |
1000 |
Source :
Guidance Notes for Investigation and Remediation of Contaminated Sites (EPD TR1
/ 99).
Metals
Toxicity
Characteristics Leaching Procedure (TCLP) test for materials contaminated with
heavy metals needs to be carried out in accordance with the testing frequency
and requirements as stipulated in EPD¡¦s Guidance Notes for Investigation and
Remediation of Contaminated Sites.
TPH and PAH
Toxicity
Characteristic Leaching Procedure (TCLP) tests for TPH, PAH and BTEX
contaminated materials have to be carried out according to the testing
frequency and requirements as stipulated in EPD¡¦s ¡§Guidance Notes for
Investigation and Remediation of Contaminated Sites. Pre-treatment is required to bring levels
of TPH to below the TCLP limit of 2,500ppm PAH/BTEX to below the TCLP limit
1,000ppm.
Dioxins and Furans
(PCDD/PCDF)
Toxicity
Characteristic Leaching Procedure (TCLP) tests for PCDD/PCDF contaminated
materials have to be carried out with reference to the requirements as
stipulated in EPD¡¦s Guidance Notes for Investigation and Remediation of
Contaminated Sites. Pre-treatment
is required to bring levels of PCDD/PCDF to below the TCLP limit of 1ppb
PCDD/PCDF (TEQ), subject to TCLP confirmation at a frequency of 1 sample per
100 tonnes of stabilised
materials.
N.B.
TEQ = toxicity
equivalent units.
ppm =
mg/kg (miligrams / kilogram)
ppm =
mg/g (micrograms
/ gram)
ppb =
ng/g (nanograms / gram)
ppb =
1000pg/g (picograms
/ gram)
---
END OF APPENDIX B ---
Appendix
C
For Phase 2 of the
Project
Remediation Methods[1]
The
following remediation methods are recommended for the 3 different types of
contaminated soil:
¡ Type A
contaminated soil (Heavy Metals): Cement solidification, test, on-site backfilling.
¡ Type B contaminated soil
(Hydrocarbons): Biopiling, test, on-site backfilling.
¡ Type C contaminated soil (Heavy
Metals and Hydrocarbons): Biopiling followed by
cement solidification, test, on-site backfilling.
The
contaminated soil would be excavated and transported to the corresponding
designated areas on-site for appropriate remediation. Trucks would carry the
excavated contaminated soil into the stockpiling areas or remediation works
areas for temporary storage or treatment respectively. Graphic C1 indicates
the workflow during remediation works.
Graphic C1: Flow Chart for Remediation Works
|
Typical Site Layout[2]
A schematic layout
of a typical arrangement for all the works including excavation, cement
solidification plant, biopile and stockpiling areas
for different types of soil is shown in Graphic
C2.
Graphic C2: Schematic Diagram of Typical Site Layout
|
Table C1: Universal Treatment Standards
for On-site Reuse of Cement Solidification Treated Soil
Parameter |
TCLP Limit (mg/L) |
Antimony |
1.15 |
Arsenic |
5 |
Barium |
21 |
Cadmium |
0.11 |
Chromium (total) |
0.6 |
Lead |
0.75 |
Mercury (all others) |
0.025 |
Nickel |
11 |
Zinc |
4.3 |
Note: (1) Universal Treatment Standard: US 40 CFR 268.48.
(2) For other RBRGs metal contaminants Cobalt,
Copper, Manganese, Molybdenum and Tin, they must be reduced by at least 90
percent in mobility for respective metals through cement solidification remediation
treatment. The reduction of mobility of metal contaminants (leachable metals
contaminants) should be confirmed through TCLP tests (i.e. to carry out TCLP
test for the untreated soil and for the soil after treatment and to compare the
concentrations of the metals in the leachates).
(3) The TCLP test for the concerned metal(s)
will be tested both for untreated soil and for soil after treatment in order to
confirm that the requirement of Note (2) can be complied with (i.e. reduced by
at least 90 percent in mobility for the respective metal(s) through cement
solidification remediation treatment).
Criteria for Treated
Soil from Biopile[4]
Table C2: Soil Clean-up Targets for Biopile Closure Assessment
Parameter |
Soil RBRGs ¡V Urban Residential / Rural Residential (mg/kg) |
PAH |
|
Benzo(a)anthracene |
11.4 |
Benzo(a)pyrene |
1.14 |
Benzo(b)fluoranthene |
9.88 |
Benzo(k)fluoranthene |
114 |
Dibenzo(a,h)anthracene |
1.14 |
Indeno(1,2,3-cd)pyrene |
11.4 |
Petroleum Carbon Ranges |
(PCR/TPH) |
C6 - C8 |
545 |
C9 - C16 |
1,330 |
C17 - C35 |
10,000 |
Key Mitigation
Measures[5]
During
excavation, the Contractor shall adopt the following measures:
¡ Properly design and execute
excavation profile;
¡ Fence off the contaminated area
throughout the period of remediation works;
¡ Take precautions when controlling
ground settlement, groundwater and wastewater;
¡ Avoid temporary stockpiling as far
as practical. In case temporary storage is needed, contaminated soil should be
placed in designated area paved with either concrete or lined with impermeable
sheeting, bunded and covered properly with tarpaulins
to prevent cross-contamination of different types of contaminated soil;
¡ Supply of suitable backfill
materials after excavation;
¡ Implement speed control for
vehicles travelling on site;
¡ Properly decontaminate machineries
and vehicles before excavating or taking different contaminated soil and
leaving the excavation zone.
The
following mitigation measures shall be followed during remediation works:
¡ The loading, unloading, handling
and storage of cement should be carried out in an enclosed environment;
¡ The loading, unloading, handling,
transfer or storage of materials that may generate airborne dust emissions such
as untreated soil and oversize materials sorted out from screening plant and stabilised soil stockpiled in designated area should be
carried out in such a manner to prevent or minimise dust emissions.
¡ All practical measures, including
but not limited to speed control for vehicles, should be taken to minimise dust
emissions;
¡ Simultaneous operation of mixing
facilities and other equipment shall be avoided as far as possible to minimise
unnecessary generation of noise nuisance;
¡ Stockpile of untreated soil shall
be covered as far as practicable;
¡ Treated oversize materials can be
used as backfilling material for on-site backfilling. Sorted materials of size
smaller than 5cm will be collected and transferred to the mixing plant for
further remediation;
¡ Treated soils can be broken down
into suitable size for on-site backfilling purpose;
¡ Water used in installation of pipe
piles should as far as practicable be recirculated after sedimentation. Excess
wastewater should go through silt removal facilities before discharge. The
Contractor would be required to obtain a license from EPD under the WPCO for
discharge to the public drainage system.
¡ Housekeeping should be maintained
at all times at the mixing plant as well as among other remediation facilities;
¡ Visual inspection and rinsing (if
needed) of any contaminated soil adhered on the broken concrete slab surface
are recommended; and
¡ A clear separation between treated
and untreated materials is recommended. Furthermore, physical separation of the
temporary stockpiles of different types of soils in clearly designated areas
with appropriate signage and fencing should be provided.
-
End of Appendix C -
Appendix
D
Typical Cross Section
and Oblique View of a Biopile[6]
Graphic D1: General Cross-Section and
Oblique View of a Biopile for indicative purpose |
||
Header pipe connecting to blower and system control
|
||
|
-
End of Appendix D -
(Extracted
from Table 2.1 of
¡§Guidance Manual for Use of Risk-Based Remediation Goals¡¨
APPENDIX E
---
END OF APPENDIX E ---
[1] This part was prepared based
on Section 7.7 and Graphic 7.1 of the EIA Report (Register No.: AEIAR-188/2015).
[2] This part was prepared based on Graphic 7.2 of the EIA Report (Register
No.: AEIAR-188/2015).
[3] This table was prepared based on Table 4.7 of the Appendix 7.2 of the EIA
Report (Register No.: AEIAR-188/2015).
[4] This table was prepared based on Table 4.6 of the Appendix 7.2 of the EIA
Report (Register No.: AEIAR-188/2015).
[5] This part was prepared based on S.7.8.2 of the EIA Report (Register No.:
AEIAR-188/2015).
[6] This part was prepared based on Graphic 3.1 of the EIA Report (Register
No.: AEIAR-188/2015).