Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (the EIAO), the Director of Environmental Protection (the
Director) grants the Environmental Permit (No. EP-324/2008) to the Highways
Department (hereinafter referred to as the “Permit Holder”) on 23 December 2008. Pursuant to Section 13
of the Ordinance, the Director amends the
Environmental Permit based on the Application No. VEP-480/2015. The amendments, described
below, are incorporated into the Environmental Permit (No. EP-324/2008/D). This
Environmental Permit as amended is for the construction and operation of the designated project described in Part B subject to the conditions specified in Part C.
根據環境影響評估條例 (環評條例) 第10條的規定,環境保護署署長(署長)於2008年12月23日將環境許可證(編號EP-324/2008)批予路政署(下稱“許可證持有人”)。根據條例第13條的規定,署長因應更改環境許可證的申請編號VEP-480/2015修訂環境許可證。下文說明的修定,已包含在本環境許可證內(EP-324/2008/D)。本經修定的環境許可證,適用於建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。
Application No. 申請書編號 |
VEP-480/2015 |
Document in the
Register: 登記冊上的文件: |
(1) Agreement No.
CE 73/98 Investigation Assignment for Widening of Tolo
Highway/ Fanling Highway between Island House Interchange
and Fanling: – Environmental Impact Assessment
Report (March 2000) [Hereinafter referred to as the “EIA Report”] – Environmental Monitoring and Audit
Manual (March 2000) [Hereinafter referred to as the “EM&A Manual”] – Environmental Impact Assessment
Executive Summary (March 2000) [Hereinafter referred to as the “EIA Executive
Summary”] (Register No.
AEIAR-037/2000) (1) 協議書編號CE 73/98 舊政務司官邸附近道路交匯處與粉嶺之間的吐露港公路 / 粉嶺公路擴闊工程之研究勘測: – 環境影響評估報告 (2000年3月) [下稱 「環評報告」] – 環境監察及審核手冊 (2000年3月) [下稱「環評摘要」] – 環境影響評估行政摘要 (2000年3月) [下稱「環監手冊」] (登記冊編號 : AEIAR-037/2000) (2) The Director’s
letter of approval of the EIA Report dated 14 July 2000, ref.: (70) in
EP2/N5/A/23 III. (2) 署長於2000年7月14日發出批准環評報告的信件,檔案編號:(70) in EP2/N5/A/23 III。 (3) Application for Environmental
Permit submitted on 25 November 2008 (Application No. AEP-324/2008) (3) 於2008年 11月25日提交的環境許可證申請 (申請書編號:AEP-324/2008) (4) Environmental Permit
issued on 23 December 2008 (Permit No.: EP-324/2008) (4) 於2008年12月23日發出的環境許可證(許可證編號: EP-324/2008) (5) Application for Variation of an
Environmental Permit submitted on 4 January 2012 (Application No.
VEP-351/2012) (5) 於2012年1月4日提交的更改環境許可證申請 (申請書編號: VEP-351/2012) (6) Environmental Permit issued on 31
January 2012 (Permit No. EP-324/2008/A) (6) 於2012年1月31日發出的環境許可證 (許可證編號: EP-324/2008/A) (7) Application for
Variation of an Environmental Permit submitted on 24 February 2014 (Application
No. VEP-429/2014) (7) 於2014年2月24日提交的更改環境許可證申請 (申請書編號: VEP-429/2014) (8) Environmental Permit issued on 17 March 2014 (Permit No.
EP-324/2008/B) (8) 於2014年3月17日發出的環境許可證 (許可證編號: EP-324/2008/B) (9) Application for Variation of an
Environmental Permit submitted on 9 March 2015 (Application No.
VEP-470/2015) (9) 於2015年3月9日提交的更改環境許可證申請 (申請書編號: VEP-470/2015) (10) Environmental Permit
issued on 27 March 2015 (Permit No. EP-324/2008/C) (10) 於2015年3月27日發出的環境許可證 (許可證編號: EP-324/2008/C) (11) Application for Variation of an
Environmental Permit submitted on 19 August 2015 (Application No. VEP-480/2015) (11) 於2015年8月19日提交的更改環境許可證申請 (申請書編號: VEP-480/2015) |
Application No. 申請 編號 |
Date of Application 申請 日期 |
List of Amendments Incorporated
into Environmental Permit 已包含在環境許可證內的修訂項目 |
Date of Amendments 修訂 日期 |
VEP-351/2012 |
4 January 2012 2012年1月4日 |
(1) Add item (v) to “Scale and Scope of
Designated Project” in Part B of Environmental Permit No. EP-324/2008 (1) 於環境許可證編號EP-324/2008 B部的“指定工程項目的規模和範圍”加入項目(v) (2) Vary Condition 1.7, 2.4, 2.6, 2.9 in Part C of Environmental Permit No. EP-324/2008 (2) 更改環境許可證編號EP-324/2008 C部條件第1.7, 2.4, 2.6, 2.9 (3) Vary Figure 4d in Part C of Environmental Permit No. EP-324/2008 |
31 January 2012 2012年1月31日 |
VEP-429/2014 |
24 February 2014 2014年2月24日 |
(1) Vary Condition 2.8 in Part C of Environmental Permit No. EP-324/2008/A (1) 更改環境許可證編號EP-324/2008/A C部條件第2.8 (2) Vary Figure 4d in Part C of Environmental Permit No. EP-324/2008/A (2)
更改環境許可證編EP-324/2008/A C部的附圖4d (3) Add Figure 4d(i) in Part C of
Environmental Permit No. EP-324/2008/A |
17 March 2014 2014年3月17日 |
VEP-470/2015 |
3 March 2015 2015年3月9日 |
(1) Vary Condition 2.5(iv) in Part C of Environmental Permit No. EP-324/2008/B (1) 更改環境許可證編EP-324/2008/B C部條件第2.5(iv) (2) Vary Figure 2d in Part C of Environmental Permit No. EP-324/2008/B (2) 更改環境許可證編EP-324/2008/B |
27 March 2015 2015年3月27日 |
VEP-480/2015 |
19 August 2015 2015年8月19日 |
(1)
Vary Figure 4e in Part
C of Environmental Permit No. EP-324/2008/C. (1)
更改環境許可證編EP-324/2008/C (2)
Add Figure 4e(i) in Part C of Environmental Permit No. EP-324/2008/C (2)
於環境許可證編號EP-324/2008/C |
27 August 2015 2015年8月27日 |
2015年8月27 日
Date 日期 |
|
(Maurice K.L. YEUNG) Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任楊國良代行) |
PART B (DESCRIPTION OF DESIGNATED
PROJECT)
B部 (指定工程項目的說明)
Hereunder
is the description of the designated project mentioned in Part A of this environmental permit (hereinafter
referred to as “the Permit”):
下列為本環境許可證 (下稱“許可證”) A部 所提述的指定工程項目的說明:
Title of Designated
Project 指定工程項目的名稱 |
Widening of Tolo Highway/Fanling Highway between Island House
Interchange and Fanling [Hereinafter referred
to as "the Project"] 舊政務司官邸附近道路交匯處與粉嶺之間的吐露港公路 / 粉嶺公路擴闊工程 [本指定工程項目下稱"工程項目" ] |
Nature of Designated
Project 指定工程項目的性質 |
A major improvement to existing expressways 對現有快速公路作重大改善工程 |
Location of Designated
Project 指定工程項目的地點 |
Tolo Highway / Fanling
Highway between Island House Interchange and Fanling 舊政務司官邸附近道路交匯處與粉嶺之間的吐露港公路 / 粉嶺公路 The
location of the Project is shown in Figure 1 of this Permit. 指定工程項目的位置載於本許可證圖1。 |
Scale and Scope of
Designated Project 指定工程項目的規模和範圍 |
The
Project mainly consists of the followings:- 工程項目主要範圍包括以下各項:- (i) Widening of a 5.7km section of
Tolo Highway and 3.0km section of Fanling Highway between Island
House Interchange and Wo Hop Shek Interchange from the existing dual 3-lane
to dual 4-lane, including construction of new vehicular bridges; (ii) Widening of interchange sections at Island
House Interchange, Tai Po North Interchange, and Lam Kam Road Interchange
from dual 2-lane to dual 3-lane, including realignment of various slip roads; (iii) Improvement to the existing substandard merging
arrangement at the southbound carriageway of Wo Hop Shek Interchange; (iv) Modification and reconstruction of
highways, vehicular bridges, underpasses and footbridges; and (v) Construction
of Kau Lung Hang Vehicular Bridge. (i)
擴闊舊政務司官邸附近道路交匯處與和合石交匯處之間一段長5.7公里的吐露港公路及一段長3公里的粉嶺公路,由雙程三線分隔行車道改為雙程四線分隔行車道; (ii) 擴闊舊政務司官邸附近道路交匯處、大埔北交匯處和林錦公路交匯處的路段,由雙程雙線分隔行車道改為雙程三線分隔行車道;大埔北交匯處南行車道則由雙線行車改為四線行車。上述工程包括為各連接路重新定線; (iii)
改善現有於和合石交匯處的南行行車道不合規格的匯合安排; (iv)
更改和重建公路,行車橋,行車隧道及行人天橋;及 (v)
興建九龍坑行車橋 |
1 General Conditions
1.1 The permit holder and any person working on the Project
shall comply with all conditions of this Permit. Any non-compliance by
any person may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap. 499) and may become the subject of appropriate
action being taken under the Ordinance.
1.2 The Permit Holder shall ensure full compliance with all
legislation from time to time in force including without limitation to the
Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311),
Water Pollution Control Ordinance (Cap. 358) and Waste Disposal Ordinance
(Cap.354). This Permit does not of itself constitute any ground of defense against any proceedings instituted under
any legislation or imply any approval under any legislation.
1.3 The Permit Holder shall make copies of this Permit
together with all documents referred to in this Permit or the documents
referred to in Part A of the Permit
readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by
this Permit. Any reference to the Permit shall include all documents
referred to in the Permit and also the relevant documents in the Register.
1.4 The Permit Holder shall give a copy of this Permit to the
person(s) in charge of the site(s) and ensure that such person(s) fully
understands all conditions and all requirements incorporated by the
Permit. The site(s) refers to site(s) of construction and operation of
the Project and shall mean the same hereafter.
1.5 The Permit Holder shall display conspicuously a copy of
this Permit on the Project site(s) at all vehicular entrances/exits or at a
convenient location for public information at all times. The Permit
Holder shall ensure that the most updated information about the Permit,
including any amended permit, is displayed at such locations. If the
Permit Holder surrenders a part or the whole of the Permit, the notice he sends
to the Director shall also be displayed at the same locations as the original
Permit. The suspended, varied or cancelled Permit shall be removed from
display at the Project site(s).
1.6 The Permit Holder shall construct and operate the Project
in accordance with the project descriptions in Part B of
this Permit.
1.7 The Permit Holder shall ensure that the Project is
designed, constructed and operated in accordance with the information and all
recommendations described in the EIA Report (Register No: AEIAR-037/2000), the
application documents including all attachments (Application No. AEP-324/2008,
VEP-351/2012, VEP-429/2014, VEP-470/2015 and VEP-480/2015), other relevant documents in the Register; and the
information or mitigation measures described in this Permit, and mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, and mitigation measures to be recommended under on going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded or impliedly amended in this Permit.
1.8 All submissions, as required under this Permit, shall be
rectified and resubmitted in accordance with the comments, if any, made by the
Director within one month of the receipt of the Director’s comments or
otherwise specified by the Director.
1.9 All submissions approved by the Director, all submissions
deposited without comments by the Director, or all submissions rectified in
accordance with comments by the Director under this Permit shall be construed
as part of the permit conditions described in Part C of
this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions.
Any non-compliance with the submissions may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap. 499). All submissions or
any variation of the submissions shall be certified by the Environmental Team
(ET) Leader and verified by the Independent Environmental Checker (IEC)
referred to in Conditions 2.1 and 2.2 below, before submitting to the Director
under this Permit.
1.10 The Permit Holder shall release all finalized
submissions, as required under this Permit, to the public by depositing copies
in the Environmental Impact Assessment Ordinance Register Office, or in any
other places, or any internet websites as specified by the Director, or by any
other means as specified by the Director for public inspection. For this
purpose, the Permit Holder shall provide sufficient copies of the submissions.
1.11 All submissions to the Director required under this
Permit shall be delivered either in person or by registered mail to the
Environmental Impact Assessment Ordinance Register Office (currently at 27/F,
Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies
of all finalized submissions required under this Permit shall be prepared in
Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable
Document Format (PDF version 4.0 or later), unless otherwise agreed by the
Director and shall be submitted at the same time as the hard copies.
1.12 The Permit Holder shall notify the Director in writing
the commencement date of construction of the Project no later than one month
prior to the commencement of construction of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement date of the construction.
1.13 For the purpose of this Permit, “commencement of
construction” does not include works related to site clearance and preparation
or other works as agreed by the Director.
2 Specific Conditions
Submissions or Measures to be implemented
before Construction of the Project
Employment of Environmental Monitoring and
Audit (EM&A) Personnel
2.1 An Environmental Team (ET) shall be established by the
Permit Holder no later than one month before the commencement of construction
of the Project. The ET shall not be in any way an associated body of the
Contractor or the Independent Environmental Checker (IEC) for the Project. The
ET shall be headed by an ET Leader. The ET Leader shall be a person who
has at least 7 years of experience in environmental monitoring and auditing
(EM&A) or environmental management. The ET and the ET Leader shall be
responsible for the implementation of the EM&A programme in accordance with
the EM&A requirements as contained in the EM&A Manual of the Project.
The ET Leader shall keep a contemporaneous log-book of each and every
instance or circumstance or change of circumstances, which may affect the compliance
with the recommendations of the EIA Report and this Permit. The ET Leader
shall notify the IEC within one working day of the occurrence of any such
instance or circumstance or change of circumstances. The ET Leader’s log-book
shall be kept readily available for inspection by all persons assisting in
supervision of the implementation of the recommendations of the EIA Report and
this Permit or by the Director or his authorized officers. Failure to
maintain records in the log-book, failure to discharge the duties of the ET
Leader as defined in the EM&A Manual or failure to comply with this
Condition would entitle the Director to require the Permit Holder by notice in
writing to replace the ET Leader. Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous
records in the log-book despite the employment of a new ET Leader may render
the Permit liable to suspension, cancellation or variation.
2.2 An IEC shall be employed by the Permit Holder no later
than one month before commencement of construction of the Project. The
IEC shall not be in any way an associated body of the Contractor or the ET for
the Project. The IEC shall be a person who has at least 7 years of
experience in EM&A or environmental management. The IEC shall be
responsible for duties defined in the EM&A Manual and shall audit the
overall EM&A performance, including the implementation of all environmental
mitigation measures, submissions required in the EM&A Manual, and any other
submissions required under this Permit. In addition, the IEC shall be
responsible for verifying the environmental acceptability of permanent and
temporary works, relevant design plans and submissions under this Permit.
The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this
Permit. The IEC shall notify the Director by fax, within one working day
of receipt of notification from the ET Leader of each and every occurrence,
change of circumstances or non-compliance with the EIA Report and this Permit,
which might affect the monitoring or control of adverse environmental impacts
from the Project. In the case where the IEC fails to so notify the
Director of the same, fails to discharge the duties of
the IEC as defined in the EM&A Manual or fails to comply with this
Condition, the Director may require the Permit Holder by notice in writing to
replace the IEC. Failure to replace the IEC as directed or further
failure to so notify the Director despite employment of a new IEC may render
the Permit liable to suspension, cancellation or variation. Notification
by the Permit Holder is the same as notification by the IEC for the purpose of
this Condition.
Management Organization of Main Construction
Companies
2.3 The Permit Holder shall, no later than two weeks before the
commencement of construction of the Project, inform the Director in writing the
management organization of the main construction companies and/or any form of
joint ventures associated with the construction of the Project. The
submitted information shall include at least an organization chart, names of
responsible persons and their contact details.
Submission of Updated EM&A Manual
2.4 The Permit Holder shall, no later than two months before
the commencement of construction of the Project, submit to the Director for
approval four hard copies and one electronic copy of an updated EM&A Manual
for the Project. Before submission to the Director, the EM&A Manual
shall be certified by the ET and verified by the IEC as conforming to the
information and recommendations contained in the EIA Report (Register No:
AEIAR-037/2000), the application documents including all attachments (Application No. AEP-324/2008, VEP-351/2012, VEP-429/2014, VEP-470/2015 and VEP-480/2015) and other relevant documents in the
Register. The EM&A Manual
shall include the latest information on the EM&A requirements for air
quality, noise, water quality, waste management, cultural heritage and
ecological aspects. All measures recommended in the approved EM&A
Manual shall be fully and properly implemented according to the requirements
and time schedule(s) set out in the approved EM&A Manual.
Measures to Mitigate Construction Noise
Impact
2.5 To mitigate construction noise impact arising from the
Project, the following temporary noise barriers shall be erected before
commencement of construction:-
(i) 3.5
m and 5.5 m high temporary noise barrier at culvert construction
work area as shown in Figure
2(a);
(ii) 3
m high temporary noise barrier along the northern edge of Bridge 12 at
ground level and 2 m high temporary noise barrier along the northern
edge of Bridge 12 at bridge level as shown in Figure 2(b);
(iii) 2.5
m high temporary noise barrier along Tai Wo Service Road West and 3.5
m and 7 m high temporary noise barrier along Tai Wo Service Road
West near Tai Hang as shown in Figure
2(c);
(iv) 7
m high temporary noise barrier along Tai Wo Service Road West near Tai Wo
Footbridge work area as shown in Figure 2(d); and
(v) 2.5
m high temporary noise barrier near river diversion work area as shown
in Figure 2(e).
Submission of Landscape Plan
2.6 The Permit Holder shall, at least two months before the
commencement of construction of the Project, submit to the Director for
approval four hard copies and one electronic copy of a landscape plan(s) showing
details of the landscape measures and compensatory ecological planting,
including boundaries of proposed works areas, trees within the works areas that
require and do not require removal, compensatory ecological planting of about
5.5 hectares including native species. The plan shall also include tree
transplantation and compensation arising from the construction
of Kau Lung Hang Vehicular Bridge. The plan(s), of
scale 1 to 1000 or other appropriate scale as agreed by the Director, shall
include details on locations, size, number and species of planting,
implementation programme, maintenance and management
schedules. The submission shall be certified by the ET Leader and
verified by the IEC as conforming to the information, requirements and
recommendations set out in the approved EIA Report (Register No:
AEIAR-037/2000), the application documents including all attachments
(Application No. AEP-324/2008, VEP-351/2012,
VEP-429/2014, VEP-470/2015 and VEP-480/2015) and other relevant documents in the Register.
Measures to Mitigate Ecological Impacts
2.7 Capture-surveys on the native frog species of Rana
guentheri, tadpoles and fish shall be conducted within the Ma Wat River
Northern Meander, location of which is shown in Figure 3, before commencement of
construction works of the Project. Any of these species caught during the
surveys shall be relocated to nearby undisturbed meander or river channel.
Measures and Submissions to be Implemented during
Construction and Operation of the Project
Measures to Mitigate Traffic Noise Impact
2.8 The Permit Holder shall implement
the following mitigation measures before commencement of operation of the
Project to mitigate the traffic noise impact arising from the Project:-
(i) Construction
of noise barriers in accordance with the details shown in Figure
4a - 4e, 4d(i) and 4e(i); and
(ii) Provide
low noise road surface at both the widened and reconstructed road
sections covered under the Project.
2.9 The Permit Holder shall deposit five (5) copies of
as-built drawing(s) in 1:1000 scale for the noise barriers required under
Condition 2.8(i) and the requirements in the EIA Report (Register No:
AEIAR-037/2000), the application documents including all attachments (Application No. AEP-324/2008, VEP-351/2012, VEP-429/2014, VEP-470/2015 and VEP-480/2015), and other relevant documents in the Register, to the Director
before commencement of operation of the Project. The drawing(s)
shall be certified by the ET Leader and verified by the IEC to confirm with
Condition 2.8(i) and the requirements in the EIA Report (Register No:
AEIAR-037/2000), the application documents including all attachments
(Application No. AEP-324/2008, VEP-351/2012, VEP-429/2014, VEP-470/2015 and VEP-480/2015), and other relevant documents in the
Register.
Measures to Mitigate Ecological Impacts
2.10 To
compensate for loss of woodlands, the Permit Holder shall implement ecological
compensatory planting in accordance with the approved Landscape Plan submitted
under Condition 2.6 above before operation of the Project.
2.11 Work
areas as shown in the approved Landscape Plan submitted under Condition 2.6
shall be fenced off using physical barriers during the construction stage of
the Project to prevent encroachment of adjacent habitats.
2.12 Trees
located within the works areas but do not require removal as shown in the
approved Landscape Plan submitted under Condition 2.6 shall be fenced off
during the construction stage of the Project and retained thereafter.
Measures to Mitigate Visual and Landscape
Impacts
2.13 All
measures recommended in the approved landscape plan(s) shall be fully and
properly implemented in accordance with the details and programme set out in
the submission.
Measures to Mitigate Water Quality Impacts
within Water Gathering Ground
2.14 For the part of the Project located within Water
Gathering Grounds, to mitigate construction water quality arising from the
Project, the following measures shall be implemented during construction:-
(i) No
stockpiling or storage of earth, building materials, fuel, oil or toxic
materials and other materials which may cause contamination to the Water
Gathering Grounds; and
(ii) Construction
plant which causes pollution to the Water Gathering Grounds due to leakage of
oil or fuel shall be removed from the Water Gathering Grounds immediately.
3 Environmental Monitoring and Audit Requirements
3.1 The EM&A programme shall be implemented
in accordance with the procedures and requirements as set out in the EM&A
Manual of the Project. Any changes to the EM&A programme shall be
justified by the ET Leader and verified by the IEC as conforming to the
requirements set out in the EM&A Manual and shall seek the prior approval
from the Director before implementation.
3.2 Four hard copies and one electronic copy of
Baseline Monitoring Report shall be submitted to the Director at least two
weeks before the commencement of construction. The submissions shall be
certified by the ET Leader and verified by the IEC. Additional copies of
the Baseline Monitoring Report shall be provided upon request by the Director.
3.3 Four hard copies and one electronic copy of
Monthly EM&A Reports for the construction stage shall be submitted to the
Director, within 2 weeks after the end of the reporting month. The
submission shall be certified by the ET Leader and verified by the IEC before
submission to the Director. Additional copies of the Monthly EM&A
Reports shall be provided upon request by the Director.
3.4 The actions described in the Event/Action Plans
of the EM&A Manual shall be fully and properly carried out, in accordance
with the time frame(s) as set out in the Event/Action Plan, or as agreed by the
Director.
3.5 All environmental monitoring and audit data
submitted under this Permit shall be true, valid and correct.
3.6 To ensure a high degree of transparency
regarding the monitoring data and results, all environmental monitoring and
audit data and results and all submissions and all performance test data and
results required by this Permit shall be made available by the Permit Holder to
the public through a dedicated web site to be set up by the Permit Holder under
Condition 4.2 below, in the shortest practicable time and in no event later
than 2 weeks after such information is available.
3.7 Records of measurements and remedial actions
taken under Condition 3.4 of this Permit shall be logged and kept within 3
working days of the collection of data or completion of remedial action, shall be included in the EM&A Reports and shall
be available for inspection on site or as requested by the Director.
4 Electronic Reporting of EM&A Information
4.1 To facilitate public inspection of the
EM&A Manual, Baseline Monitoring Report and Monthly EM&A Reports via
the EIAO Internet Website and at the EIAO Register Office, electronic copies of
these Reports shall be prepared in the Hyper Text Markup Language (HTML)
(version 4.0 or later) and in Portable Document Format (PDF version 4.0 or
later), unless otherwise agreed by the Director and shall be submitted at the
same time as the hard copies as described in Condition 3 of this Permit.
For the HTML version, a content page capable of providing hyperlink of
each section and sub-section of these Reports shall be included in the
beginning of the document. Hyperlinks to all figures, drawings and tables
in these Reports shall be provided in the main text from where the respective
references are made. All graphics in these Reports shall be interlaced
GIF, JPEG or PDF format unless otherwise agreed by the Director. The
content of the electronic copies of these Reports must be the same as the hard
copies.
4.2 The Permit Holder shall, within six weeks to
the commencement of construction of the Project, set up a dedicated web site
and notify the Director in writing the Internet address, where the project
information, all environmental monitoring and audit data and reports described
in Condition 4.1 above, and all finalized submissions and plans required under
this Permit, are to be placed. All environmental monitoring and audit
data and reports described in Condition 4.1 above shall be made available to
the public via this dedicated web site to be set up by the Permit Holder in the
shortest possible time and in no event later than 2 weeks after the relevant
environmental monitoring data and reports is / are collected or become
available, unless otherwise agreed with the Director. All finalized
submissions and plans shall be made available to the public via this dedicated
web site to be set up by the Permit Holder in the shortest possible time and in
no event later than 2 weeks after they are deposited with or approved by the
Director as required under this Permit, unless otherwise agreed with the
Director.
4.3 The Internet website as described in Condition 4.2 above
shall enable user-friendly public access to the monitoring and project
information including the project profile of the Project, the EIA report, the
environmental permit(s), all environmental monitoring and audit data and report
and all finalized submissions and plans required under this Permit.
Unless otherwise agreed with the Director, the internet website shall
have features capable of: -
(a) providing access to all environmental monitoring data
collected since the commencement of work;
(b) searching by date;
(c) searching by types of monitoring data; and
(d) hyperlinks to relevant monitoring data after searching;
or otherwise as agreed by the Director.
Notes :
1. This
Permit consists of three parts, namely, PART A (Main
Permit), PART B (Description of
Designated Project) and PART C(Permit
Conditions). Any person relying on this permit should obtain independent
legal advice on the legal implications under the Ordinance, and the following
notes are for general information only.
2. If there is a breach of any conditions of this Permit,
the Director or his authorized officer may, with the consent of the Secretary
for the Environment, order the cessation of associated work until the remedial
action is taken in respect of the resultant environmental damage, and in that
case the Permit Holder shall not carry out any associated works without the
permission of the Director or his authorized officer.
3. The Permit Holder may apply under Section 13 of the
Ordinance to the Director for a variation of the conditions of this
Permit. The Permit Holder shall replace the original permit displayed on
the construction site by the amended permit.
4. A person who assumes the responsibility for the whole or
a part of the designated project may, before he assumes responsibility of the
designated project, apply under Section 12 of the Ordinance to the Director for
a further environmental permit.
5. Under
Section 14 of the Ordinance, the Director may with the consent of the Secretary
for the Environment, suspend, vary or cancel this Permit. The suspended,
varied or cancelled Permit shall be removed from display at the construction
site.
6. If this
Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the Ordinance
before the Project could be continued. It is an offence under section
26(1) of the Ordinance to construct or operate a designated project listed in
Part I of schedule 2 of the Ordinance without a valid
environmental permit.
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the Ordinance, is liable:-
(i) on a first conviction
on indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii) on a second or
subsequent conviction on indictment to a fine of $ 5 million and to
imprisonment for 2 years;
(iii) on a first summary
conviction to a fine at level 6 and to imprisonment for 6 months;
(iv) on a second or
subsequent summary conviction to a fine of $1 million and to imprisonment for 1
year; and
(v) in any case where the
offence is of a continuing nature, the court or magistrate may impose a fine of
$ 10,000 for each day on which he is satisfied the offence continued.
8. The Permit Holder may appeal against any condition of
this Permit under Section 17 of the Ordinance within 30 days of receipt of this
Permit.
9. The
Notes are for general reference only and that the Permit Holder should refer to
the EIA Ordinance for details and seek independent legal advice.