Environmental
Permit No. EP-420/2011/B
Àô¹Ò³\¥iÃÒ½s¸¹ EP-420/2011/B
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(
CHAPTER 499 )
Sections 10 & 13
Àô¹Ò¼vÅTµû¦ô±ø¨Ò
( ²Ä499³¹ )
²Ä 10¤Î13±ø
ENVIRONMENTAL
PERMIT TO CONSTRUCT A DESIGNATED PROJECT
«Ø³y«ü©w¤uµ{¶µ¥ØªºÀô¹Ò³\¥iÃÒ
A³¡ ( ³\¥iÃÒ¥Dn³¡¤À)
Pursuant
to Section 10 of the Environmental Impact Assessment Ordinance (the Ordinance),
the Director of Environmental Protection (the Director)
granted the environmental permit (No. EP-420/2011) to the Antiquities and Monuments Office,
Leisure and Cultural Services Department (
hereinafter referred as the ¡§Permit Holder¡¨ ) on 14
September 2011. Pursuant to
Section 13 of the EIAO, the Director amends the Environmental Permit No. EP-420/2011/A based on the Application
No. VEP-515/2016. The amendments, described below, are
incorporated into this Environmental Permit (No. EP-420/2011/B). This Environmental
Permit as amended is for construction of the designated project described in Part B of
this Permit subject to the conditions specified in or attached to Part C
of this Permit. The issue of this
environmental permit is based on the documents, approvals or permissions
described below : ¡V
®Ú¾ÚÀô¹Ò¼vÅTµû¦ô±ø¨Ò(¥»±ø¨Ò)²Ä10±øªº³W©w¡AÀô¹Ò«OÅ@¸p¸pªø(¸pªø) ©ó
Application No. ¥Ó½Ð®Ñ½s¸¹ |
VEP¡V515/2016 |
Document in the Register
µn°O¥U¤Wªº¤å¥ó |
(1)
Project
Profile ¡V ¡§Restoration to Yan Tun Kong Study Hall
at Ping Shan, Yuen Long, New Territories¡¨ (
Register No. : PP-422/2010 ) ¤uµ{¶µ¥Ø²¤¶ ¡V ¡§ ·s¬É¤¸®Ô«Ì¤s¤¯´°©£®Ñ«Ç×´_¤uµ{
¡¨ ( µn°O¥U½s¸¹¡GPP-422/2010 ) (2)
The
Director¡¦s letter of permission to apply directly for environmental permit
dated 12 October 2010 ( Ref. : (14) in EP2/N6/Q/138 ) ¸pªø©ó (ÀÉ®×½s¸¹
: (14 ) in EP2/N6/Q/138) (3) Application for Environmental Permit submitted on 18 August 2011 (
Application No. : AEP-420/2011 ) ©ó (¥Ó½Ð®Ñ½s¸¹ : AEP-420/2011) (4) Bat Survey Report submitted on 9 August 2011 ©ó (5) Environmental Permit (No. EP-420/2011)
issued on 14 September 2011
©ó2011¦~9¤ë14¤éñµoªºÀô¹Ò³\¥iÃÒ(½s¸¹
: EP-420/2011) |
|
(6) Application for Variation of an
Environmental Permit including attachment submitted by the Permit Holder on 5
April 2013 ( Application No. VEP- 400/2013 ) ³\¥iÃÒ«ù¦³¤H©ó2013¦~4¤ë5 ¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó(¥Ó½Ð®Ñ½s¸¹: VEP-400 /2013)©Mªþ¥ó (7) Environmental Permit (No. EP-420/2011/A) issued on 22 April 2013
©ó2013¦~4¤ë22¤éñµoªºÀô¹Ò³\¥iÃÒ(½s¸¹: EP-420/2011/A) (8)
Application for
Variation of an Environmental Permit including attachment submitted by the Permit
Holder on 9 December 2016 ( Application No. VEP- 515/2016 ) ³\¥iÃÒ«ù¦³¤H©ó2016¦~12¤ë9¤é´£¥æªº§ó§ïÀô¹Ò³\¥iÃҥӽФå¥ó(¥Ó½Ð®Ñ½s¸¹: VEP-515 /2016)©Mªþ¥ó |
Application No. ¥Ó½Ð®Ñ½s¸¹ |
Date of
Application
¥Ó½Ð¤é´Á
|
List of Amendments Incorporated into Environmental Permit
¤w¥]§t¦b¥»Àô¹Ò³\¥iÃÒ¤ºªº×q¶µ¥Ø |
Date of Amendment ×q¤é´Á |
VEP-400/2013 |
5
April 2013 2013¦~4¤ë5¤é |
(i) Vary condition §ó§ïÀô¹Ò³\¥iÃÒ½s¸¹EP-420/2011 ªºC³¡ªº²Ä2.1 ¶µ±ø¥ó (ii) Add in Figure 2 ·s¼W¹Ï2 |
22
April 2013 2013¦~4¤ë22¤é |
VEP-515/2016 |
9
December 2016 2016¦~12¤ë9¤é |
Vary condition §ó§ïÀô¹Ò³\¥iÃÒ½s¸¹EP-420/2011/A ªºC³¡ªº²Ä2.1 ¶µ±ø¥ó |
5 January 2017 2017¦~1¤ë5 ¤é |
5 January 2017
2017¦~1¤ë 5 ¤é
|
Date ¤é´Á |
|
(WONG Chuen-fai ) Principal Environmental Protection
Officer (Strategic Assessment) for Director of Environmental Protection Àô¹Ò«OÅ@¸p¸pªø (º®uÀô¹Ò«OÅ@¥D¥ô(µ¦²¤µû¦ô)¶À¶Ç½÷¥N¦æ) |
PART B (
DESCRIPTION OF DESIGNATED PROJECT )
B³¡ («ü©w¤uµ{¶µ¥Øªº»¡©ú)
Hereunder is the
description of the designated project mentioned in Part A
of this environmental permit (hereinafter referred to as the ¡§Permit¡¨) :
¤U¦C¬°¥»Àô¹Ò³\¥iÃÒ (¤UºÙ ¡§³\¥iÃÒ¡¨ ) A³¡©Ò´£zªº«ü©w¤uµ{¶µ¥Øªº»¡©ú:
Title of Designated Project
«ü©w¤uµ{¶µ¥Øªº¦WºÙ |
Restoration
to Yan Tun Kong Study Hall at Ping Shan, Yuen Long,
New Territories ·s¬É¤¸®Ô«Ì¤s¤¯´°©£®Ñ«Ç×´_¤uµ{ [ This designated project is hereinafter
referred to as ¡§the Project¡¨ ] [ ³o«ü©w¤uµ{¶µ¥Ø¤UºÙ ¡§¤uµ{¶µ¥Ø¡¨ ] |
Nature of Designated Project «ü©w¤uµ{¶µ¥Øªº©Ê½è |
Restoration works in a declared monument ©óªk©w¥jÂݶi¦æ×´_¤uµ{ |
Location of Designated Project
«ü©w¤uµ{¶µ¥Øªº¦aÂI |
Ping
Shan, Yuen Long ¤¸®Ô«Ì¤s Location of the Project is shown in Figure 1 of this Permit. ¤uµ{¶µ¥Øªº¦ì¸m¸ü©ó¥»³\¥iÃÒ¹Ï1¡C |
Scale
and Scope of Designated Project(s) «ü©w¤uµ{¶µ¥Øªº³W¼Ò©M½d³ò |
The
scope of project works include ¡X ¤uµ{½d³ò¥]¬A ¡X (i)
demolish later-added reinforced concrete
structures, false ceiling panels, concrete and cement based screed floor at
the Study Hall and restore the floor to its original design and materials in
the existing layout; ©î¨ø®Ñ«Ç¤º«á¥[ªº¾d©T¥Û«Ëµ²ºc¡B°²¤Ñªá¡B¥Û«Ë¤Î¤ôªd¾Q¦a¡A¥H¤Î´_צa±©ó즳§G§½ªº³]p¤Îª«®Æ¡F (ii)
repair, replace and reconstruct the timber roof
structure including purlins, battens, rafters,
truss beams and other timber support, etc., restore and reconstruct the traditional
Chinese tiled roofs. Repair and
restore the existing plasterwork to the main ridges and gable walls and other
artwork; ºûסB§ó´«¤Î««Ø¤ì«Î³»³¡µ²ºc¡A¥]¬A®ì¼Ù¡BÝܱø¡B®ì¼Ù¬[µ²ºc¤Î¨ä¥L¤ì§÷¤ä¬[µ¥¡A«×©M««Ø¶Ç²Îªº¤¤¦¡¥Ë±«Î³»¡CºûפÎ×´_«Î¯á¤Î¤sÀ𪺦Ƕì¡A¥H¤Î¨ä¥Lø»s¸Ë¹¢¡F (iii)
repair, replace and reconstruct the damaged
carpentry work and other timber decorations such as staircases with handrails
and balustrades, cocklofts, windows, doors, altar, couplets and wood
carvings, etc. to match the existing; «öì¼ËºûסB§ó´«¤Î««Ø¤w´Ý·lªº¤ì§@¤Î¸Ë¹¢¡A¦p¼Ó±è§ß¤â¤ÎÄæªe¡B»Õ¼Ó¡Bµ¡¡Bªù¡B¯«÷ΡB¹ïÁp¤Î¤ìÀJµ¥¡F (iv)
repair and restore all masonry works including
removal of modern paint on walls and columns and other masonry surfaces and
repair and re-point the external and internal brick walls ¡§dentist¡¨
replacement; ºûפÎ×´_¿j¥Ûºc¥ó¡A¥]¬A²M°£¥ÛÀð¡B¥Û¬W¤Î¨ä¥L¿j¥Ûºc¥ó¤Wªº²{¥Nªoº£¡A¥H¤Îºûפº¥~¿jÀð¤Î¤ÄÁ_¡F (v)
restore and replace floor paving throughout the
Study Hall, including canton tiles, lime-sand screed, red sandstone and
granite slabs etc.; ×´_¤Î§ó´«®Ñ«Ç¤ºªº¾Q¦a¡A¥]¬A¼sªF¤j¶¥¿j¡A¦Ç¨F¾Q¦a¡B¬õ¬â©¥¤Îªá±^¥Ûµ¥µ¥¡F (vi)
restore the original window and door openings
and traditional arched doorway with decorative plasterworks throughout the
Study Hall; ×´_®Ñ«Ç¤º©Ò¦³µ¡ªù¶}¤f¤Î¹¢¦³¦Ç¶ìªá¹¢ªº¶Ç²Î«ýªù¡F (vii)
clear and improve drainage works and upgrade
electrical system; ²M²z¤Î§ïµ½±Æ¤ô¡A¨Ã´£¤É¹q¤O¨t²Î¡F (viii)
repair, restore and repaint the plaster works,
mural paintings, friezes and other decorative artworks; and ºûסB×´_¤Î×¹¢¦Ç¶ì¡B¾Àµe¡BªuÀ𪺹¢±a¡A¥H¤Î¨ä¥Lø»s¸Ë¹¢¡F¤Î (ix)
repair and restore roofs and balconies with
application of appropriate waterproofing systems. ºûפÎ×´_«Î³»¤Î¶§¥x¡A¥H¤Î¥[³]¦X¾Aªº¨¾¤ô±¹¬I¡C |
C³¡
( ³\¥iÃÒ±ø¥ó)
1.
General Conditions
¤@¯ë±ø¥ó
1.1 The
Permit Holder and any person working on the Project shall comply with all
conditions set out in this Permit.
Any non-compliance by any person may constitute a contravention of the Environmental
Impact Assessment Ordinance (Cap. 499) and may become the subject of
appropriate action being taken under the Ordinance.
³\¥iÃÒ«ù¦³¤H¥²¶·¿í¦u¥»³\¥iÃÒªº¥þ³¡±ø¥ó¡C¥ô¦ó¤H¤h¦p¦³¤£¿í¦u¥»³\¥iÃÒªº±¡ªp¡A«h¥i¯àºc¦¨¹H¤ÏÀô¹Ò¼vÅTµû¦ô±ø¨Ò( ²Ä499³¹) ªº³W©w¡A¦Ó·í§½¥i®Ú¾Ú±ø¨Ò±Ä¨ú¾A·í¦æ°Ê¡C
1.2
The Permit Holder shall ensure
full compliance with all legislation from time to time in force including
without limitation to the Noise Control Ordinance (Cap. 400), Air Pollution
Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358) and
Waste Disposal Ordinance (Cap. 354).
This Permit does not of itself constitute any ground of defence against
any proceedings instituted under any legislation or imply any approval under
any legislation.
³\¥iÃÒ«ù¦³¤H¶·¸g±`½T«O§¹¥þ¿í¦u²{¦æªk¨Ò¡A¥]¬A¦ý¤£©ó¾¸µºÞ¨î±ø¨Ò(²Ä400³¹)¡FªÅ®ð¦Ã¬VºÞ¨î±ø¨Ò(²Ä311³¹)¡F¤ô¦Ã¬VºÞ¨î±ø¨Ò(²Ä358³¹)¡F¤Î¼oª«³B¸m±ø¨Ò(²Ä354³¹)¡C®Ú¾Ú¥ô¦óªk¨Ò±È°_ªºªk«ßµ{§Ç¡A¥»³\¥iÃÒ¥»¨¤£¯à§@¬°¥ô¦ó§ÜÅG²z¾Ú©Îµø¬°¬Yªk¨Ò©ÒÀq³\¡C
1.3
The Permit Holder shall
make copies of this Permit together with all documents referred to in this
Permit or the documents referred to in Part A of the Permit readily available at all
times for inspection by the Director or his authorised officers at all
sites/offices covered by this Permit.
Any reference to the Permit shall include all documents referred to in
the Permit and also the relevant documents in the Register.
³\¥iÃÒ«ù¦³¤H¶·½Æ¦L¥»³\¥iÃҤΥ»³\¥iÃÒ©Òzªº©Ò¦³¤å¥ó¡A©Î¥»³\¥iÃÒA³¡©Òzªº¤å¥ó¡A¥H¨Ñ¸pªø©Î¨ä±ÂÅv¤H¤h¦b¥»³\¥iÃÒ©Ò²[»\ªº©Ò¦³¤u¦a/¿ì¨Æ³BÀH®É¬d¾\¡C¤Z´£¤Î¥»³\¥iÃÒ¡A§Y¥]¬A¥»³\¥iÃÒ©Òzªº©Ò¦³¤å¥ó©Mµn°O¥U¤ºªº¬ÛÃö¤å¥ó¡C
1.4
The Permit Holder shall
give a copy of this Permit to the person(s) in charge of the site(s) and ensure
that such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The
site(s) refers to site(s) of construction of the Project and shall mean the
same hereafter.
³\¥iÃÒ«ù¦³¤H¶·§â¥»³\¥iÃÒªº¤@¥÷°Æ¥»¥æ¤©¬ÛÃö¤u¦aªºt³d¤H¡A¨Ã½T«O³o¨Ç¤H¤h§¹¥þ©ú¥Õ¥»³\¥iÃÒ¤º¸üªº©Ò¦³±ø¥ó»P³W©w¡C¤u¦a¬O«ü¥»¤uµ{¶µ¥Øªº«Ø³y¤u¦a¡A¤U¤å©Ò´£¤Îªº¤u¦a¥çÄݦP¤@·N«ä¡C
1.5
The Permit Holder shall
display conspicuously a copy of this Permit on the Project site(s) at all
vehicular site entrances/exits or at a convenient location for public
information at all times. The
Permit Holder shall ensure that the most updated information about the Permit,
including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part
or the whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site(s).
³\¥iÃÒ«ù¦³¤H¶·¦b¦³Ãö«Ø³y¤u¦aªº©Ò¦³¨®½ø¶i¥X¤J¤f©Î¤@³B¤è«K¦aÂI¡AÅã²´¦a®i¥Ü¥»³\¥iÃÒªº°Æ¥»¡A¥H¨Ñ¤½²³¦b¥ô¦ó®É¶¡¤º¾\Äý¡C³\¥iÃÒ«ù¦³¤H¶·½T«O¦³Ãö¥»³\¥iÃÒªº³Ì·s¸ê®Æ¡A¥]¬A¸g×qªº³\¥iÃÒ¡A¦b³o¨Ç¦aÂI®i¥Ü¡C¦pªG³\¥iÃÒ«ù¦³¤H¥æ¦^³\¥iÃÒªº³¡¤À©Î¥þ³¡¡A¨ä°e¥æ¸pªøªº³qª¾®Ñ¡A¥ç¶·¦b®i¥Ü즳³\¥iÃÒªº¦P¤@¦aÂI®i¦C¡C¾D¼È®É¦Q¾P¡B§ó§ï©Î¨ú®øªº³\¥iÃÒ¥²¶·±q¤u¦a°£¤U²¾¨«¡A¤£¦A®i¥Ü¡C
1.6
The Permit Holder shall
construct the Project in accordance with the project descriptions in Part B of this Permit.
³\¥iÃÒ«ù¦³¤H¶·¨Ì¾Ú¥»³\¥iÃÒB³¡ªº¤uµ{¶µ¥Ø»¡©ú¡A«Ø³y¥»¤uµ{¶µ¥Ø¡C
1.7
The Permit Holder shall ensure that the Project is
designed and constructed in accordance with the information and recommendations
described in the Project Profile (Register No. : PP-422/2010) in the Register,
and the information and mitigation measures described in the approved
Bat Survey Report and in this Permit. Where recommendations referred to in the
documents of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit.
³\¥iÃÒ«ù¦³¤H¶·½T«O¤uµ{¶µ¥Øªº³]p¤Î«Ø³y¡A²Å¦Xµn°O¥U¤º¥»¤uµ{¶µ¥Ø²¤¶(µn°O¥U½s¸¹¡GPP-422/2010) ©Ò»¡©úªº¸ê®Æ¤Î«Øij¡F¥H¤Î¸g§å®Öªº½¿½»½Õ¬d³ø§i©M¥»³\¥iÃÒ©Òz¸ê®Æ¤Î½w¸Ñ±¹¬I¡C§Y¨Ïµn°O¥U¤å¥ó©Òzªº«Øij¨S¦³¦b¥»³\¥iÃÒ¤º©ú½T¤Þz¡A³o¨Ç«Øij¤´¶·¹ê¬I¡A°£«D¦b¥»³\¥iÃÒ¤º©ú½T¦aªí¥ÜÁÅ°£©ÎÀq¥Ü¤w×q¡C
1.8
The Permit Holder shall notify the
Director in writing the commencement date of construction of the Project no
later than 2 weeks prior to commencement of construction of the Project. The Permit Holder shall notify the
Director in writing immediately if there is a change of the commencement date
of the construction.
³\¥iÃÒ«ù¦³¤H¶·¦b¤uµ{¶µ¥Ø¬I¤u«e¦Ü¤Ö¨âÓ¬P´Á¡A¥H®Ñ±³qª¾¸pªø¬I¤u¶}©lªº¤é´Á¡C¦p¶}©l¬I¤uªº¤é´Á¦³¥ô¦ó§ó§ï¡A³\¥iÃÒ«ù¦³¤H¥²¶·¥ß§Y¥H®Ñ±³qª¾¸pªø¡C
1.9
For the purpose of this Permit, ¡§commencement of construction¡¨ does not
include works related to site clearance and preparation or other works as
agreed by the Director.
¦]À³¥»³\¥iÃÒªº¥Øªº¡A¡u«Ø³y¤uµ{ªº®i¶}¡v¤£¥]¬A¦³Ãö¤u¦a²M²z¤Î¹w³Æªº¤uµ{¡A©Î¸pªø¦P·Nªº¨ä¥L¤uµ{¡C
2.
Specific Conditions
¯S©w±ø¥ó
2.1 Restoration works for the
rear annex of the Study Hall shall be carried out in the dry season.
Restoration works for the rear annex shall commence
only after it is confirmed that no bat is using the rear annex by the
post-exclusion bat survey in accordance with the Bat Survey Report,
approved under condition 2 of the Permission to Apply Directly for
Environmental Permit (DIR) (No: DIR-207/2010). A letter confirming the absence of bats
shall be deposited to the Director prior to the commencement of any
construction works in the rear annex.
To minimize the glaring impact on bats, no lighting shall face directly
towards the bat boxes installed in the Study Hall when undertaking restoration
works. Bat boxes
shall be provided at locations as indicated in Figure 2 during construction of the
Project.
®Ñ«Ç«á¼Óªº×´_¤uµ{¥u¥i¦b§ò©u´Á¶¡¶i¦æ¡C«á¼Óªº×´_¤uµ{¡A¶·¨Ì¾Úã³\ª½±µ¥Ó½ÐÀô¹Ò³\¥iÃÒ(No: DIR-207/2010) ªº±ø¥ó2¤U§å®Öªº½¿½»³ø§i¡A¶i¦æ«á´Á½¿½»½Õ¬d¡A¦b½T«O¨S¦³½¿½»¨Ï¥Î®Ñ«Çªº«á¼Ó¡A¤~¥i®i¶}¡C¨Ã¶·¦b«á¼Ó¬I¤u«e¡A¥H®Ñ±³qª¾¸pªø½TÃÒ¨S¦³½¿½»¡C¬°´î»´¯t¥ú¹ï½¿½»ªº¼vÅT¡A¦b×´_¤uµ{¬I¦æ´Á¶¡¡A·Ó©ú³]³Æ¤£¥iª½®g³]¸m¦b®Ñ«Çªº½¿½»½c¡C¦b¤uµ{«Ø³y´Á¶¡¡A¶·«ö·Ó¹Ï2©Ò«ü¥Üªº¦ì¸m´£¨Ñ½¿´T½c¡C
2.2 Only hand-held
powered tools and
hand-held manual tools shall be used for carrying out the restoration works for the
Study Hall.
¬I¦æ®Ñ«Çªº×´_¤uµ{¡A¥u¥i¨Ï¥Î¥iÄ⦡ªº¹q°Ê¤Î¤â°Ê¤u¨ã¡C
2.3 The
permit holder shall conduct bat survey throughout the construction phase as
recommended in the approved Bat Survey Report. Within 2 months after
completion of construction, the permit holder shall submit a Bat Survey Monitoring
Report as
per the requirements in section 7.3 of the Bat Survey Report.
³\¥iÃÒ«ù¦³¤H¶·®Ú¾Ú¤wÀò¼f§åªº½¿½»½Õ¬d³ø§iªº«Øij¡A¦b¬I¤u´Á¶¡¶i¦æ½¿½»½Õ¬d¡C§¹¦¨«Ø³y¤uµ{«áªº¨âӤ뤺¡A³\¥iÃÒ«ù¦³¤H¶·®Ú¾Ú½¿½»½Õ¬d³ø§iªº7.3±ø´£¥æ½¿½»ºÊ¹î³ø§i¡C
2.4 The Permit Holder shall employ
an independent environmental checker to audit the implementation of all
mitigation measures, the carrying out of the monitoring programme,
and the submissions under Condition 2.1 and 2.3, as recommended in the Project
Profile ( Register No. PP-422/2010 ) and the approved Bat Survey Report.
³\¥iÃÒ«ù¦³¤H¶·¸u¥Î¤@¦W¿W¥ßÀô¹Ò¬d®Ö¤H¡A¥H¼f®Ö¤uµ{¶µ¥Ø²¤¶( µn°O¥U½s¸¹¡GPP-422/2010 )¤Î¸g§å®Öªº½¿½»½Õ¬d³ø§i©Ò«Øijªº©Ò¦³½w¸Ñ±¹¬I¡A¼f®ÖºÊ¹îp¹ºªº°õ¦æ¡A¤Î¼f®Ö´£¥æ±ø¥ó2.1¤Î2.3©Ò«Øijªº¤å¥ó¡C
Notes :
µù
1.
This Permit consists of
three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions). Any person relying on this Permit should
obtain independent legal advice on the legal implications under the Ordinance,
and the following notes are for general information only.
¥»³\¥iÃÒ¦@¦³3³¡¡A§YA³¡(³\¥iÃÒ¥Dn³¡¤À)¡FB³¡(«ü©w¤uµ{¶µ¥Øªº»¡©ú)¤ÎC³¡(³\¥iÃÒ±ø¥ó)¡C¥ô¦ó´©¤Þ¥»³\¥iÃÒªº¤H¤h¶·´NÀôµû±ø¨Òªºªk«ß§t·N¼x¸ß¿W¥ßªk«ß·N¨£¡A¤Uzµù¸Ñ¥u¨Ñ¤@¯ë°Ñ¦Ò¥Î¡C
2.
If there is a breach of
any conditions of this Permit, the Director or his authorized officer may, with
the consent of the Secretary for the Environment, order the cessation of
associated work until the remedial action is taken in respect of the resultant
environmental damage, and in that case the Permit Holder shall not carry out
any associated works without the permission of the Director or his authorized
officer.
¦p¹H¤Ï¥»³\¥iÃÒªº¥ô¦ó±ø¥ó¡A¸pªø©ÎÀò±ÂÅv¤Hû¥i¦bÀô¹Ò§½§½ªøªº¦P·N¤U°Ç¥O°±¤î¬ÛÃö¤uµ{¡Aª½¦Ü³\¥iÃÒ«ù¦³¤H¬°©Ò³y¦¨ªºÀô¹Ò·l®`±Ä¨ú¸É±Ï¦æ°Ê¬°¤î¡C¦b¦¹±¡ªp¤U¡A³\¥iÃÒ«ù¦³¤H¥¼¸g¸pªø©ÎÀò±ÂÅv¤Hû¦P·N¡A¤£±o¶i¦æ¥ô¦ó¬ÛÃö¤uµ{¡C
3.
The Permit Holder may
apply under Section 13 of the Ordinance to the Director for a variation of the
conditions of this Permit. The Permit Holder shall replace the original permit
displayed on the construction site by the amended permit.
³\¥iÃÒ«ù¦³¤H¥i®Ú¾Ú¥»±ø¨Ò²Ä13±øªº³W©w¦V¸pªø¥Ó½Ð§ó§ï¥»³\¥iÃÒªº±ø¥ó¡C³\¥iÃÒ«ù¦³¤H¶·¥H¸g×qªº³\¥iÃÒ´À´«¦b¤uµ{¶µ¥Øªº¤u¦a¤º®i¥Üªºì¦³³\¥iÃÒ¡C
4.
A person who assumes the
responsibility for the whole or a part of the designated project may, before he
assumes responsibility of the designated project, apply under Section 12 of the
Ordinance to the Director for a further environmental permit.
©Ó¾á¤uµ{¶µ¥Ø¾ã¶µ©Î³¡¤À¤uµ{ªº³d¥ôªº¤H¡A¦b©Ó¾á³d¥ô¤§«e¡A¥i®Ú¾Ú¸Ó±ø¨Ò²Ä12±øªº³W©w¦V¸pªø¥Ó½Ð·sªºÀô¹Ò³\¥iÃÒ¡C
5.
Under Section 14 of the
Ordinance, the Director may with the consent of the Secretary for the
Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled
Permit shall be removed from display at the construction site.
®Ú¾Ú¥»±ø¨Ò²Ä14±øªº³W©w¡A¸pªø¥i¦bÀô¹Ò§½§½ªøªº¦P·N¤U¼È®É¦Q¾P¡B§ó§ï©Î¨ú®ø¥»³\¥iÃÒ¡C¾D¼È®É¦Q¾P¡B§ó§ï©Î¨ú®øªºÀô¹Ò³\¥iÃÒ¥²¶·±q¤uµ{¶µ¥Øªº¤u¦a°£¤U¡A¤£¦A®i¥Ü¡C
6.
If this Permit is
cancelled or surrendered during construction of the Project, another
environmental permit must be obtained under the Ordinance before construction
or operation of the Project could be continued. It is an offence under Section 26(1) of
the Ordinance to construct or operate a designated project listed in Part I of
Schedule 2 of the Ordinance without a valid environmental permit.
¦p¥»³\¥iÃÒ¦b¤uµ{¶µ¥Ø«Ø³y´Á¶¡³Q¨ú®ø©Î¥æ¦^¡A«h¥²¶·¦bÄ~Äò«Ø³y©ÎÀç¿ì¤uµ{¶µ¥Ø¤§«e¡A®Ú¾Ú¥»±ø¨Ò³W©w¨ú±o¥t¤@¥÷Àô¹Ò³\¥iÃÒ¡C®Ú¾Ú¥»±ø¨Ò²Ä26(1)±øªº³W©w¡A¥ô¦ó¤H¦b¨S¦³¦³®ÄÀô¹Ò³\¥iÃÒªº±¡ªp¤U¡A«Ø³y©ÎÀç¿ì¥»±ø¨Òªþªí2©Ò¦C©úªº«ü©w¤uµ{¶µ¥Ø¡A§YÄݹHªk¡C
7.
Any person who constructs the Project contrary to the conditions
in the Permit, and is convicted of an offence under the Ordinance, is liable ¡X
¦p¥ô¦ó¤H¦b¹H¤Ï¥»³\¥iÃÒªº±ø¥ó¤U«Ø³y¤uµ{¶µ¥Ø¡A®Ú¾Ú¸Ó±ø¨Ò¡A§YÄݹHªk ¡X
(i)
on a first conviction on indictment to a fine of
$2 million and to imprisonment for 6 months;
¤@¸g´`¤½¶Dµ{§Çº¦¸©w¸o¡A¥i³B»@´Ú200¸U¤¸¤ÎºÊ¸T6Ó¤ë¡F
(ii)
on a second or subsequent conviction on
indictment to a fine of $5 million and to imprisonment for 2 years;
¤@¸g´`¤½¶Dµ{§Ç²Ä¤G¦¸©Î¨ä«á¨C¦¸©w¸o¡A¥i³B»@´Ú500¸U¤¸¤ÎºÊ¸T2¦~¡F
(iii)
on a first summary conviction to a fine at level
6 and to imprisonment for 6 months;
¤@¸g´`²©öµ{§Çº¦¸©w¸o¡A¥i³B²Ä6¯Å»@´Ú¤ÎºÊ¸T6Ó¤ë¡F
(iv)
on a second or subsequent summary conviction to a
fine of $1 million and to imprisonment for 1 year; and
¤@¸g´`²©öµ{§Ç²Ä¤G¦¸©Î¨ä«á¨C¦¸©w¸o¡A¥i³B»@´Ú100¸U¤¸¤ÎºÊ¸T1¦~¡F¥H¤Î
(v)
in any case where the offence is of a continuing
nature, the court or magistrate may impose a fine of $10,000 for each day on
which he is satisfied the offence continued.
¦b¥ô¦ó±¡ªp¤U¦p¸Ó¸o¦æÄݳsÄò©Ê½è¡A«hªk°|©Îµô§P©x¥i´N¨ä«H¯Ç¸Ó¸o¦æ³sÄòªº¨C¤@¤Ñ¥t³B»@´Ú10,000¤¸¡C
8.
The Permit Holder may
appeal against any condition of this Permit under Section 17 of the Ordinance
within 30 days of receipt of this Permit.
³\¥iÃÒ«ù¦³¤H¥i¦b±µÀò¥»³\¥iÃÒ«á30¤Ñ¤º¡A®Ú¾Ú±ø¨Ò²Ä17±ø´N¥»³\¥iÃÒªº¥ô¦ó±ø¥ó´£¥X¤W¶D¡C
9.
The Notes are for general
reference only and that the Permit Holder should refer to the EIA Ordinance for
details and seek independent legal advice.
¤Wzµù¸Ñ¥u¨Ñ¤@¯ë°Ñ¦Ò¥Î¡A±ýª¾¦³Ãö¸Ô±¡¡A³\¥iÃÒ«ù¦³¤H¶·°Ñ¾\Àôµû±ø¨Ò¤Î¼x¸ß¿W¥ßªk«ß·N¨£¡C
Environmental
Permit No. EP-420/2011/B
Àô¹Ò³\¥iÃÒ½s¸¹ EP-420/2011/B
[ Back to First Page ] / [
Back to Main Index ]