PWP ITEM No. 4338DS -
IMPROVEMENT AND UPGRADING OF THE SEWERAGE SYSTEMS IN SHA TIN / MA ON SHAN NEW TOWN
PROJECT PROFILE
Drainage Services Department
The Government of the Hong Kong Special Administrative Region
March 2006
Contents
|
|
|
Page |
1. |
Basic Information |
|
1 |
|
|
|
|
2. |
Outline of Planning and Implementation Programme |
|
2 |
|
|
|
|
3. |
Possible Impacts on Environment |
|
3 |
|
|
|
|
4. |
Major Elements of the Surrounding Environment |
|
6 |
|
|
|
|
5. |
Environmental Protection Measures to be Incoporated in the Design and further Environmental Implications |
|
6 |
|
|
|
|
6. |
Summary of Potential Environmental Impacts and Mitigation Measures |
|
11 |
1 Basic Information
1.1 Project Title
The title of this project is “Ma On Shan Area 108 Pumping Station” (hereinafter referred to as the “Project”).
1.2 Purpose and Nature of the Project
The Project aims at achieving an increase in sewage conveyance capacity from the residential area at Sai Sha [for catchment area, please refer to drawing no. DDN/338DS/1812 in Appendix A] and involves the construction of a new Ma On Shan Area 108 Pumping Station adjacent to the existing one. After completion of the new Pumping Station, the existing one will operate as a standby (hereinafter, the proposed Ma On Shan Area 108 Pumping Station is called the Pumping Station).
1.3 Name of Project Proponent
Drainage Services Department (DSD) is the works department while Environmental Protection Department is the client department.
1.4 Location and Scale of the Project
The existing Ma On Shan Area 108 Pumping Station is situated at the junction of Sha On Street and Sai Sha Road. The new Pumping Station will be constructed adjacent to the existing one, i.e. within GI/C zoning of the Ma On Shan Outline Zoning Plan No. S/MOS/13. The location and layout of the Pumping Station is shown on drawing no. DDN/338DS/1818C in Appendix A. Since the existing pumping station will be preserved, no demolition works is expected. The design average dry weather flow of the Pumping Station is approximately 14,500m3/day. The Pumping Station will be a single-storey building with the inlet chamber and the wet well being underground and enclosed with covers.
1.5 Rationale for Site Selection
The Pumping Station is situated adjacent to the existing Ma On Shan Area 108 Pumping Station and within the area reserved for the existing pumping station. By locating the new Pumping Station adjacent to the existing one, most of the existing sewers can be maintained and nuisance due to substantial modifications of existing sewerage system is avoided.
The Pumping Station will also make use of the by-pass route of the existing Ma On Shan Area 108 Pumping Station. Due to site constraints, laying a new by-pass pipe for overflow to another discharge point is impractical.
1.6 Number and Type of Designated Project
Since the nearest residential block (Lee Wing House of Lee On Estate) is about 75m away from the Pumping Station which has a proposed capacity of approximately 14,500m3/day, the Pumping Station is classified as a Designated Project under Schedule 2, Part I, F.3(b) of the Environmental Impact Assessment Ordinance (EIAO).
1.7 Contact Person
Mr. S. H. Leung
Engineer, Sewerage Projects Division, Drainage Services Department
44/F, Revenue Tower, 5 Glouces ter Road, Wanchai, Hong Kong
Tel: 2594 7364
Fax: 2827 8700
2.1 The Project is delivered by DSD using in-house resources. The Sewerage Projects Division and the Electrical and Mechanical Projects Divison of DSD are jointly responsible for the planning, design and construction supervision of the Project. The construction will be carried out by a qualified contractor. The Sewage Treatment Division 1 of DSD will be responsible for operating and maintaining the Pumping Station.
2.2 The Project is currently under the detailed design stage. The tentative implementation programme is as below: -
Design: Up to June 2006
Tender: July 2006 – October 2006
Construction & Commissioning: November 2006 – December 2010
Operation & Maintenance: January 2011
2.3 Interaction with Other Projects
There are no major projects in the vicinity of the Project with overlapping implementation programmes that will have significant environmental impacts due to cumulative effects. The construction of rising main across Sai Sha Road will not overlap with the construction of the Pumping Station.
3.1 During Construction Stage
3.1.1 Air Quality
Dust may be generated from construction activities, mainly due to earthworks or handling and transportation of construction / demolition materials.
3.1.2 Noise
The major sources of construction noise are associated with the use of powered mechanical equipment (PME) such as air compressors, generators, hydraulic or pneumatic breakers, backhoes, etc. A detailed noise impact assessment is attached in Appendix C.
3.1.3 Water Quality
Muddy water may be generated from the construction activities such as dust suppression sprays, dewatering during excavation, washing of construction equipment, etc.
3.1.4 Landscape and Visual
The existing site of the Pumping Station is a concrete paved area with no existing trees or amenity planting within the proposed site boundary. The existing condition of the Project site is shown in the photos listed in Appendix E. At the Pumping Station, the appearance of a normal low-rise building construction site will be seen. The presence of construction plant and materials, site traffic and temporary lighting is expected.
3.1.5 Waste
Construction and demolition (C&D) material and waste such as excavated spoil (soil and rock), concrete and unusable cement/grouting mixes, wood/metal scraps, and packaging materials will be generated.
3.1.6 Ecology
Since the Pumping Station is located at an urbanized area and does not involve any reclamation or dredging activities, no impact on ecology is expected during the construction stage.
3.1.7 Cultural Heritage
No impact on historical monuments or buildings is expected during the construction stage.
3.1.8 Traffic
The Pumping Station does not involve excavation on public roads. Only a small amount of traffic will be generated by the construction of the designated project and the associated impact on traffic in the area will be minimal.
3.2 During Operation and Maintenance Stage
3.2.1 Odour
The inlet chamber and wet well of the Pumping Station may be sources of odour nuisance.
3.2.2 Water Quality
The Pumping Station is designed to convey sewage collected from residential areas near Sai Sha to Shatin Sewage Treatment Works for treatment and disposal. Implementation of the project will enhance the water quality of the surrounding environment, and will not cause any adverse impacts under normal operation. Under emergency situation such as prolonged power failure, sewage bypass into Tolo Harbour may occur. However, with the implementation of preventive measures described in paragraph 5.2.2, the probability of sewage bypass will be extremely remote.
3.2.3 Noise
The pumps and extraction fans of the deodourizer are potential noise sources during operation and maintenance of the Pumping Station. A detailed noise impact assessment is attached in Appendix C.
3.2.4 Waste
Mechanically raked bar screens will be installed at the inlet chamber to prevent large solid materials in sewage from entering the pumps and thus causing damage to them. A small quantity of screenings will thus be generated.
3.2.5 Landscape and Visual
No tree or amenity planting will be affected by the Project. The potential visual impact during operation and maintenance stage is the presence of a completed low-rise building.
3.2.6 Ecology
The Pumping Station is designed to expand the capacity of the existing Ma On Shan Area 108 Pumping Station. Implementation of the project will further minimize the chance of overflow along existing by-pass route to Starfish Bay and will not cause any additional adverse impact to ecology. The proposed preventive measures for minimizing the ecological impacts of the existing by-pass route during the operation and maintenance stage are detailed in paragraph 5.2.2.
3.2.7 Traffic
The delivery of materials and removal of screenings will be infrequent and will have insignificant impacts on traffic flow in the area.
3.2.8 Cultural Heritage
No impacts on historical monuments or buildings are expected during the operation stage.
This section is to outline the existing and planned sensitive receivers that might be affected by the Project. In addition, it also outlines the major elements of the surrounding environment that may affect the project.
4.1 Existing Sensitive Receivers and Sensitive Parts of Natural Environment
The locations of the sensitive receivers are shown in Appendix B.
There are three residential development near the Pumping Station, namely: (i) Lee On Estate (SR1 – approx. 75m away), (ii) Monte Vista (SR2 – approx. 130m away) and (iii) Wu Kai Sha Village (SR3 – approx. 130m away).
4.2 Planned Sensitive Receivers and Sensitive Parts
The locations of the sensitive receivers are shown in Appendix B.
The property development at Wu Kai Sha Station (SR4 – approx. 70m away) of Ma On Shan Railway is planned to have their population intake in mid 2008. As such, it is expected that the future residents will be some of the sensitive receivers of the Pumping Station.
4.3 Major Elements of the Surrounding Environment Affecting the Project
There are no major elements of the surrounding environment affecting the Project.
5 Environmental Protection Measures to be Incorporated in the Design and further Environmental Implications
5.1 During Construction Stage
5.1.1 Air Quality
The effect of dust generated from the construction works is expected to be insignificant with the implementation of proper mitigation measures. The impacts will be minimized by the adoption of proper working methods such as regular water spraying and providing wheel-washing facilities.
5.1.2 Water Quality
The construction activities of the Project will include excavation, earthworks, and general concrete building works. The contractor will be required to provide, where necessary, a silt removal facility so as to remove any silt before discharge of site runoff into the nearby stormwater drains. The mitigation measures should be provided prior to the commencement of excavation. The design of temporary on-site drainage and silt removal facilities will follow the guidelines stipulated in the EPD’s Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94). With the above mitigation measures, no adverse impacts on water quality are expected during the course of construction.
5.1.3 Noise
Common construction plants including backhoes, concrete mixers, vibratory pokers, pneumatic breakers and the like will be used. Furthermore, temporary hoardings will be erected during construction of the pumping station to screen off any noise. The Contractor has to comply with the relevant regulations and the Noise Control Ordinance to limit the construction noise within the acceptable limit during the construction stage. Construction activities will be carried out in the daytime (0700 – 1900) and will avoid working on Sunday or public holidays. A quantitative noise assessment is provided in Appendix C. The use of quiet construction equipment and implementation of good site practices as mitigation measures are identified. Noise from the daytime construction shall comply with the relevant noise limit of 75dB(A) Leq(30 minutes) for domestic premises specified in the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). A valid Construction Noise Permit is required under the Noise Control Ordinance in case the construction works to be carried out during nighttime (1900 – 0700), Sundays and public holidays.
5.1.4 Waste
The Contractor will be required to sort all C&D material and waste into different categories for reuse on site and disposal at public filling, landfills, or recycling facilities as appropriate. The total C&D material generated is estimated to be about 5,600m3 and approximately half of them can be reused on site. The rest will be disposed of to the Public Filling Facility at Tsuen Kwan O Area 137. No chemical waste is identified under this project.
5.1.5 Landscape and Visual
No endangered tree species are identified within the project site. Site hoardings will be erected around the site area as far as possible to minimize the potential impacts to nearby pedestrians.
5.2 During Operation Stage of Pumping Station
5.2.1 Odour
To minimize the potential odour problem, the inlet chamber, screen chamber, wet well, etc. will be located underground, and enclosed by a reinforced concrete superstructure. In addition, a deodourizer with a forced ventilation system will be installed to remove odour. As adopted in other similar sewage pumping stations, e.g. Nam San Wai Sewage Pumping Station, the removal efficiency of H2S by the proposed deodourizer to be installed will be 99.5%. The exhaust of the proposed deodourizer shall be located in a direction away from the nearby sensitive receivers as far as practicable, i.e. facing north of the Pumping Station.
5.2.2 Water Quality & Ecology
The emergency by-pass of the sewage will make use of the by-pass routing currently in use by the existing Ma On Shan Area 108 Pumping Station. The by-pass discharge point is located at Starfish Bay of Tolo Harbour (please refer to Appendix D).
A sub-tidal diving survey at Starfish Bay was carried out on 20 February 2006. Marine organisms such as algae, mussels, bivalves, sea cucumber and sea anemones were observed during the inspection. As no coral or other uncommon species of marine organisms were found, the sub-tidal zone of Starfish Bay is considered to contain only common species as found in other Hong Kong waters. Nevertheless, according to the final report of Environment and Conservation Fund project 23/99 – “A study of soft shore habitats in Hong Kong for conservation and education purposes” carried out by City University of Hong Kong, the shores at Lok Wo Sha area are ranked as with important conservative potential. As such, this project will implement a series of measures to minimize the probability of sewage by-pass.
To minimize the probability of sewage by-pass, three duty and one standby pumps, one duty and one standby mechanical screens, as well as an approximate one-hour emergency storage will be provided to cater for breakdown and maintenance of the duty pumps and mechanical screens. Furthermore, the existing Ma On Shan Area 108 Pumping Station will be retained and it provides a standby backup capacity of 13,800 m3/day (approximately one-third of the peak flow capacity of the Pumping Station) when the equipment at the Pumping Station fails.
Over the past five years, there is only one by-pass incident for the existing Ma On Shan Area 108 Pumping Station due to power failure in March 2001. As such, in order to minimize the chance of power failure, a dual power supply will be provided for the Project by CLP. Furthermore, the existing Ma On Shan Area 108 Pumping Station is supported by an emergency generator, which can maintain the functioning of the duty pumps to provide a 13,800 m3/day flow capacity. In addition, a telemetry system will also be provided in order to transmit signals showing irregularity or any operational problem of the Pumping Station to the existing Shatin Sewage Treatment Works such that immediate actions can be taken. With these measures incorporated into the design of the pumping station, it is anticipated that the chance of emergency sewage bypass will be extremely remote. As a result, the impact of emergency by-pass on the ecology of Starfish Bay is considered minimal. An assessment for the scenarios of emergency is attached as Appendix G.
It is considered that with the implementation of this project and the above precautionary measures, the project will bring about environmental benefits as the chance of sewage by-pass will be greatly minimized when compared with the existing arrangement.
5.2.3 Noise
During the operation of the Pumping Station, all pumps will be enclosed inside the substructure of the Pumping Station and acoustic filters will be installed at the extraction fans of the deodourizers. According to the quantitative assessment attached in Appendix C, with the above design of the Pumping Station, no adverse noise impacts are anticipated and further mitigation measure are not required.
5.2.4 Waste
The screenings of sewage at the inlet works of the Pumping Station will be put in plastic bags or storage containers. This operation will be conducted inside the Pumping Station. The screenings would then be transported to landfills for disposal. As such, no adverse waste impacts are anticipated.
5.2.5 Landscape and Visual
The existing site of the Pumping Station is a concrete paved area with no existing trees or amenity planting within the proposed site boundary. The existing condition of the Project site is shown in the photos listed in Appendix E. It is anticipated that the parties most concerned with the visual impacts brought by the Pumping Station will be from Lee On Estate and the future property development of Wu Kai Sha Railway Station. As the existing Ma On Shan Area 108 Pumping Station is maintained as part of the emergency backup measures to minimize the chance of overflow by-pass (please refer to paragraph 5.2.2), its external finishes will be refurbished to match with those of the proposed Pumping Station. Elevations and plan showing the conceptual design of the appearance of the Pumping Station is shown in Appendix F. As the site is surrounded by retaining walls of Sai Sha Road and a nearby substation of CLP, the lower half of the proposed Pumping Station will be out of the sight of most residents. The external finishings and architectural features of the roof and upper half of the Pumping Station is designed with aesthetic consideration to allow the structure to blend with the surroundings. With the implementation of a green roof design (roof covered by green planting), the landscape of the site will be improved when compared with the current concrete paving appearance. Drawings showing the architectural and landscape proposal are attached in Appendix F. Advice on aesthetic aspect is also being sought from ArchSD according to ETWB Technical Circular No. 8/2005.
6.1 The potential environmental impacts and proposed mitigation measures to be incorporated into the design and construction of the upgrading of Ma On Shan Area 108 Pumping Station are summarized in Table 1 below: -
Project Stage |
Potential Environmental Impact |
Mitigation Measure |
Relevant Section in the Project Profile |
Construction |
Minor dust nuisance |
(1) Adopt proper working methods such as spray of water (2) Provide wheel washing facilities (3) Control by contract specification
|
5.1.1 |
Construction |
Water quality impact |
(1) Control of construction surface run-off according to ProPECC PN 1/94, EPD’s Practice Note for Professional Persons, Construction Site Drainage (2) Control by contract specification |
5.1.2 |
Construction |
Minor noise impact |
(1) Erect Temporary hoarding (2) Construction activities will be carried out in daytime as far as possible (3) Comply with relevant regulations and Noise Control Ordinance (4) Use of quiet plant (5) Control by contract specification |
5.1.3 / Appendix C |
Construction |
Minor waste impact |
(1) C&D material and waste will be sorted as far as practicable (2) C&D material will be reused on site or disposed of to a designated public fill area (3) Control by contract specification |
5.1.4 |
Construction |
Minor landscape and visual impact |
(1) Site hoardings will be erected (2) Control by contract specification |
5.1.5 |
Operation |
Odour nuisance |
(1) All odour sources will be enclosed (2) Deodourizer will be installed to remove odour. |
5.2.1 |
Operation |
Water quality & ecology impact |
No impact during normal operation. Measures to minimize abnormal situations and the possibility of sewage bypass to Tolo Harbour: (1) Standby pump and mechanical screen will be provided (2) Dual power supply will be provided (3) Emergency storage capacity will be provided (4) Existing pumping station with emergency power generator will serve as a backup (5) Telemetry system will be provided to send signals showing irregularities or any operation problem from the Pumping Station to Shatin Sewage Treatment Works |
5.2.2 |
Operation |
Noise impact |
(1) Pumps will be enclosed inside the substructure of the Pumping Station (2) Acoustic filters will be installed at the extraction fans of the deodourizers |
5.2.3 |
Operation |
Waste generation |
(1) Screenings will be enclosed and disposed of to NENT |
5.2.4 |
Operation |
Landscape and visual impact |
(1) Architectural aspects of the superstructures, including color scheme, types of external finishing and layout of the pumping station is carefully designed taking into account of ArchSD’s advice and the surrounding features. A green roof design is adopted to replace the current concrete paving appearance. (2) The structure is proposed to be a single-storey building. |
5.2.5 |
- END OF TEXT –
-
NOISE IMPACT ASSESSMENT
Introduction
This section presents an assessment of potential noise impact from the construction and operation of the Project to the nearby sensitive receivers near the proposed site. Appropriate mitigation measures have been recommended, where necessary, to alleviate the potential noise impacts to acceptable levels.
Environmental Legislation, Policies, Plans, Standards and Criteria
Noise impacts were assessed in accordance with the criteria and methodology given in the Technical Memoranda made under the Noise Control Ordinance (NCO).
The Noise Control Ordinance (NCO) provides the statutory framework for noise control. The NCO invokes the following four Technical Memoranda, which define the technical means for noise assessment:
s Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM);
s Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM);
s Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and
s Technical Memorandum on Noise from Percussive Piling (PP-TM).
With regard to the assessment of the operational noise impacts, the NCO designates acceptable noise levels for Noise Sensitive Receivers (NSRs) on the basis of an Area Sensitivity Rating (ASR), based on the characteristics of the area within which they are located such as rural, village, low-density residential, or urban. Within these areas, the presence of "influencing factors" (such as the presence of industrial activities or major roads) can further affect the ASR and therefore the acceptable noise level (see Table 1).
Table 1: Area Sensitivity Ratings
Type of Area Containing NSR |
Degree to which NSR is affected by Influencing Factor |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
Rural Area |
A |
B |
B |
Urban Area |
B |
C |
C |
Low density residential area consisting of low-rise or isolated high-rise developments |
A |
B |
C |
Area other than those above |
B |
B |
C |
Construction Activities
Under the GW-TM, noise from construction activity is not restricted during the period 0700 - 1900 hours on weekdays, except Public Holidays. However, the EIAO-TM identifies a daytime general construction noise limit of 75 dB(A) Leq (30 minutes) for domestic premises. This standard was used as an assessment criterion in the construction noise assessment.
Operation Activities
Table 2 : Acceptable Noise Levels (ANLs) (dB(A))
Time Period |
ASR A |
ASR B |
ASR C |
Day (0700 to 1900 hours) |
60 |
65 |
70 |
Evening (1900 to 2300 hours) |
|||
Night (2300 to 0700 hours) |
50 |
55 |
60 |
Noise Criteria arising from the New Proposed Equipment
Table 3: Noise Criteria for Operational Noise Levels (dB(A))
|
ANL |
Adopted Noise Criteria |
Day (0700 to 1900 hours) |
65 |
60 |
Evening (1900 to 2300 hours) |
||
Night (2300 to 0700 hours) |
55 |
50 |
Description of the Environment
The Project site is located at the intersection between Sai Sha Road and Sha On Street.
Assessment Methodology
Construction Phase
The assessment followed the procedures given in the GW-TM. For the assessment of noise from PME, the distance attenuation was estimated using the standard formula:
Distance Attenuation in dB(A) = 20 log D + 8 [where D is the distance in metres]
Sound Power Levels of the equipment were taken from BS5228:Part 1:1997 and Table 3 of the GW-TM. Groups of equipment likely to be employed for each construction task are shown in Annex 1A. The equipment lists are considered realistic and practicable.
Generally, all works would be carried out in the non-restricted hours (0700-1900 hours). In the event that the construction activities are undertaken during restricted hours, it would be the responsibility of the contractor to ensure compliance with the NCO and the relevant TMs. In such cases, the contractor will be required to submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued. Therefore, the potential noise impacts of construction works within restricted hours are not formally assessed in this assessment report. In order to avoid any potentially adverse noise impact, indicative assessment for representative NSRs have been undertaken.
As the E&M works are mainly installation work, limited number of PME would be used. Also most of the E&M works would be carried out indoors. Thus it is considered that the E&M works would not contribute to the cumulative impact at the NSRs.
Due to the limited space of the Project site, parallel construction tasks with grouping of PME as listed in Annex 1A is considered not practical. The construction tasks as listed in Annex 1A will only be carried out in sequence. The construction noise levels of civil works which are considered to be significant at the NSR has been assessed.
Noise impact was assessed on the basis of the following three conservative assumptions:
· All PME items required for a particular construction activity would be located at the notional source position, which was at a position mid-way between the appropriate geographical centre of the construction site and its boundary nearest to the NSR;
· A +3 dB(A) facade correction was added to the predicted noise levels to account for the facade effect at each NSR; and
· Noise impacts at the nearest sensitive facades of the residential buildings to the source positions were assessed.
Currently, there are no other construction activities proposed to be undertaken concurrently with this Project during construction period. Therefore, no cumulative construction noise impact was anticipated.
Operation Phase
The assessment followed the procedures given in the IND-TM. For the assessment of noise from equipment, the distance attenuation was estimated using the standard formula as mentioned above.
The estimated SWL of other equipment were taken with reference to the specifications of similar items of equipment provided by contractor/plant supplier and other similar projects.
Noise impact was assessed on the basis of the following three conservative assumptions:
· All items (including both duty and standby items) are in operation together;
· A +3 dB(A) facade correction was added to the predicted noise levels to account for the facade effect at each NSR; and
· Noise impacts at the nearest sensitive facades of the residential buildings to the source positions were assessed.
Identification of Environmental Impacts
Major potential noise impacts arising from the Project would be:
· Construction; and
· Operation noise.
Noise Sensitive Receivers (NSRs)
Potential noise sensitive receivers (NSRs) have been identified in accordance with the criteria set out in the EIAO TM and through site inspection. The representative sensitive receivers are shown in Table 5. Locations of the NSRs are shown in Annex 3.
Table 5: NSR identified under this Project
NSR |
Description |
Type of Use |
Approx. Distance from Pumping Station Boundary (m) |
SR1 |
Lee On Estate |
Residential |
75 |
SR2 |
Monte Vista |
Residential |
130 |
SR3 |
Wu Kai Sha Village |
Residential |
130 |
SR4 |
Wu Kai Sha Station Property Development |
Residential |
70 |
Since SR4 is nearest to the Project Site, it is considered as the most critical case and put into detailed assessment.
Prediction and Evaluation of Environmental Impacts
Construction Phase
Operation Phase
Mitigation of Potential Adverse Environmental Impacts
Construction Phase
Use of Quiet PME
To reduce construction noise impacts, silenced type of air compressor, which are in accordance with BS5228:Part 1:1997, is recommended. The total SWL of PME for each construction activities were calculated and are summarized in Annex 1B. The equipment lists are considered realistic and practicable.
A detailed calculation of construction noise impact for the mitigated scenario is presented in Annex 1B. The largest total SWL is 116 dB(A). With a Distance Attenuation of 45 dB(A) and addition of 3 dB(A) façade effect, the SPL will be 74 dB(A). The results indicate that the cumulative construction noise levels predicted at SR4 would comply with the daytime noise criterion of 75 dB(A).
Good Site Practice
In addition to quiet PME, good site practices listed below should be adopted to further abate any residual impacts during the construction phase of the Project and should be included in the contract:
· Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction phase;
· Silencers or mufflers on construction equipment should be utilised, if found necessary, to further reduce noise, and should be properly maintained during the construction phase;
· Mobile plant should be sited as far away from NSRs as possible;
· Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
· Plant known to emit noise strongly in one direction, should, where possible, be orientated so that the noise is directed away from nearby NSRs; and
· Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.
Operation Phase
The assessment results indicated that during operation phase of the Project, the predicted levels at SR4 would satisfy the requirement of the EIAO-TM and hence mitigation measures would not be required.
Conclusions
Construction Phase
With the adoption of quiet PME and good site practices, the predicted construction noise levels at representative NSRs would not exceed the relevant noise criteria.
Operation Phase
The noise impacts associated with the operation of the Project were also assessed. The assessment result indicated that the unmitigated operation noise levels predicated at representative NSRs would comply with both the daytime and nighttime criteria. Thus no adverse noise impact arising from the Project would be expected.
Powered Mechanical Equipment (PME) for Different |
|
|
|
|
|
|||||
|
Construction Tasks during Normal Daytime Working Hours |
|
|
|||||||
|
(Un-Mitigated Scenario) |
|
|
|
|
|
||||
|
|
|
|
|
|
|
||||
Site Clearance and Set Up Site Office |
|
|
|
|
|
|
||||
Powered Mechanical Equipment |
Reference |
No. Items |
SWL/Item |
On-time |
Barrier |
Total SWL |
|
|
||
(PME) |
|
|
dB(A) |
% |
dB(A) |
dB(A) |
|
|
||
Breaker, excavator mounted |
C2/11 # |
1 |
115 |
100% |
0 |
115 |
|
|
||
Excavator |
C3/97# |
1 |
105 |
100% |
0 |
105 |
|
|
||
Dump Truck |
C9/19# |
1 |
102 |
100% |
0 |
102 |
|
|
||
Air compressor |
C7/40# |
1 |
117 |
100% |
0 |
117 |
|
|
||
Bulldozer |
C9/2 # |
1 |
104 |
100% |
0 |
104 |
|
|
||
Generator |
C7/45# |
1 |
95 |
100% |
0 |
95 |
|
|
|
|
|
|
|
Total = |
120 |
|
|
||||
|
|
|
|
|
|
|||||
Excavation Work |
|
|
|
|
|
|
||||
Powered Mechanical Equipment |
Reference |
No. Items |
SWL/Item |
On-time |
Barrier |
Total SWL |
|
|||
(PME) |
|
|
dB(A) |
% |
dB(A) |
dB(A) |
|
|||
Dump truck |
C9/19# |
1 |
102 |
100% |
0 |
102 |
|
|||
Excavator |
C3/97# |
1 |
105 |
100% |
0 |
105 |
|
|
||
Generator |
C7/45# |
1 |
95 |
100% |
0 |
95 |
|
|
||
Air compressor |
C7/40# |
1 |
117 |
100% |
0 |
117 |
|
|||
Breaker, excavator mounted |
C2/11# |
1 |
115 |
100% |
0 |
115 |
|
|
||
|
|
|
Total = |
119 |
|
|||||
|
|
|
|
|
|
|||||
Concreting Work |
|
|
|
|
|
|
||||
Powered Mechanical Equipment |
Reference |
No. Items |
SWL/Item |
On-time |
Barrier |
Total SWL |
|
|||
(PME) |
|
|
dB(A) |
% |
dB(A) |
dB(A) |
|
|||
Mobile Crane |
C7/114 # |
1 |
101 |
100% |
0 |
101 |
|
|||
Concrete Lorry Mixer |
C6/23# |
1 |
100 |
100% |
0 |
100 |
|
|||
Bar Bender and cutter |
CNP 021@ |
1 |
90 |
100% |
0 |
90 |
|
|||
Concrete pump |
C6/36# |
1 |
106 |
100% |
0 |
106 |
|
|||
Poker (Power Rating limited to 2kW) |
C6/32# |
3 |
100 |
100% |
0 |
105 |
|
|
||
Chipper, hand held |
C6/45# |
1 |
111 |
100% |
0 |
111 |
|
|
||
Saw, circular, wood |
C7/78# |
1 |
106 |
100% |
0 |
106 |
|
|
||
Generator |
C7/45# |
1 |
95 |
100% |
0 |
95 |
|
|
||
Air Compressor |
C7/40# |
1 |
117 |
100% |
0 |
117 |
|
|||
|
|
|
Total = |
119 |
|
|||||
Miscellaneous Work |
|
|
|
|
|
|
||||
Powered Mechanical Equipment |
Reference |
No. Items |
SWL/Item |
On-time |
Barrier |
Total SWL |
|
|||
(PME) |
|
|
dB(A) |
% |
dB(A) |
dB(A) |
|
|||
Excavator |
C3/97# |
1 |
105 |
100% |
0 |
105 |
|
|||
Mobile Crane |
C7/114# |
1 |
101 |
100% |
0 |
101 |
|
|||
Lorry |
C7/122# |
1 |
112 |
100% |
0 |
112 |
|
|||
Compactor |
C3/118# |
1 |
108 |
100% |
0 |
108 |
|
|||
Generator |
C7/45# |
1 |
95 |
100% |
0 |
95 |
|
|
||
Air Compressor |
C7/40# |
1 |
117 |
100% |
0 |
117 |
|
|||
Roller |
C8/25# |
1 |
96 |
100% |
0 |
96 |
|
|
||
|
|
|
Total = |
119 |
|
|||||
Note: |
|
|
|
|
|
|||||
# - BS 5228 Part 1 :1997 |
|
|
|
|
|
|||||
@ - Table 3 of PP-TM |
|
|
|
|
|
|||||
|
|
|
|
|
|
|||||
|
|
|
|
|
||||||
|
|
|
|
|
||||||
|
|
|
|
|
|
|
|
Annex 2 : Calculation of Operational Noise Levels at NSR - Unmitigated |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||
(1) Predicted Cumulative Noise Levels at SR4 |
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||||
Items(#) |
No. |
Remark |
Ref. |
SWL |
Total |
Enclosed |
Enclosure |
Distance |
Distance |
facade correction |
SPL at NSR |
|
|
||||||||||||||||||||||||||||||||||
|
of Items |
|
|
/Item |
|
|
dB(A) |
(m) |
d B(A) |
d B(A) |
|
10^(SPL/10) |
|
||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||
Submersible Pump |
4 |
3 duty + 1 standby |
CNP283 |
85 |
91 |
enclosed |
-20 |
70 |
-45 |
3 |
29 |
816.3265306 |
|
||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||
Exhaust Fan (with acoustic lourve)(@) |
4 |
2 CLP + 2 Deodourizer |
Estimate |
73 |
79 |
|
|
62 |
-44 |
3 |
38 |
6565.633137 |
|
||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||
Mechanically raked fine screen |
2 |
1 duty + 1 standby |
Estimate |
89 |
92 |
enclosed |
-20 |
70 |
-45 |
3 |
30 |
1025.259768 |
|
||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
Total SPL = |
39 |
8407.219436 |
|
||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
Remarks: |
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
(*): Enclosure Reduction is the reduction of SWL due to the enclosure for the equipment in reinforced concrete structure. |
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||||
(@): The standard requirement in exhaust fan with acoustic lourve specified in previous delivered projects is max. 65 dB(A) measured 1m from the acoustic lourve. |
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||
Since the Pumping Station is of a size approximately 15m in width, a reduction of 8m in distance between sound source and receiver is assumed. |
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||
(#) : Only those noisy equipment are included in the table. Other equipment (e.g. monorail, CCTV, etc) which does not have significant noise impact are not included. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Proposed Pumping
Station Sai Sha Road CLP
Substation Lee
On Estate
Existing Condition of Project Site for the Pumping Station
1. Breakdown of Duty Pump
Contingency Measures
(a) For ultimate normal flow condition, activate other duty pumps.
(b) For ultimate peak flow condition, activate standby pump.
2. Breakdown of pumping system at new Pumping Station
Contingency Measures
(a) Storage at new Pumping Station can be used as buffer storage for retention of 1 hour of ultimate normal flow
(b) Activate existing pumping station which can handle the ultimate normal flow
3. Power failure due to breakdown of supply duty main
Contingency Measures
(a) Activate the backup main of the dual power supply system from CLP
4. Power failure of the whole Ma On Shan region
Contingency Measures
(a) Storage at new Pumping Station can be used as buffer storage of the sewage flow.
(b) During the above period, activate the existing pumping station with power supply from the standby emergency generator.