1.1
Establishment
Phase
1.1.1
The dust control measures required under the Air
Pollution Control (Construction Dust) Regulation should be
implemented. Working areas where
excavation or earthmoving operation are taking place
shall be sprayed with water or a dust suppression chemical. Any stockpiling of excavated material
shall be covered by impervious sheeting or sprayed with water or a dust
suppression chemical. The
following site facilities shall also be provided as part of the establishment phase
to prevent potential dust impact during the fill bank operation and
decommissioning:
·
Erect site hoarding of at least 2.4m high along the
northern and eastern boundaries of the site except at the site entrance/
exit. Before occupation take place
at the Recovery Park Phase I and II, site hoarding of at least 2.4m high should
also be erected along the western boundary of the fill bank;
·
Install/
refurnish vehicle wheel washing facilities including high pressure water jets
provided at designated vehicle exit points;
·
Pave/
refurnish designated main haul roads with concrete, bituminous materials,
hardcores or metal plates;
·
At the
barging point, the drop height between the barge and dump trucks shall be
minimized;
·
Tipping halls
provided for transfer of public fill from trucks to barges shall be top and
3-sides enclosed.
1.2
Operational
Phase
1.2.1
Any works that involve the stockpiling
of dusty materials are regulated under the Air Pollution Control
(Construction Dust) Regulation as regulatory work. In accordance with the requirements of
the Air Pollution Control (Construction Dust) Regulation, sufficient
dust control/ mitigation measures shall be implemented to ensure full
protection of the nearby Air Sensitive Receivers (ASRs). The dust control measures that are
considered to be particularly relevant to the operation (and decommissioning)
of the fill bank are summarised below.
Site
Haul Road
1.2.2
Public fill delivery trucks entering
or leaving the fill bank shall be required to follow the designated main haul
route that is covered with concrete, bituminous materials, hardcores or metal
plates. The main haul roads
provided for regular transport of public fill from the barge handling area to
the public fill stockpiling area shall also be constructed with similar
materials to minimise dust emissions.
The main haul roads for delivery of public fill by trucks shall be
routed away from the eastern boundary of the fill bank. Water lorries and/or road sweepers
shall be provided and used in dust suppression. The designated main haul roads shall be watered at
approximately every 2 hours to ensure that the roads are kept sufficiently
dampened. Truck speed shall be
controlled to within 10 km/hr.
Trucks using the fill bank should be checked to have valid dumping licence. The buffer distance between the
designated haul roads and the nearby ASRs has been optimised based on the
current design of the fill bank.
Loading/
unloading of Public Fill
1.2.3
All dusty fill material shall be
sprayed with water or a dust suppression chemical prior to loading, unloading
or transfer so as to maintain the fill material wet, except for situations
where the moisture content of the dusty material is a matter of concern. Frequent water (at least three times
per day) of the worksites with active dusty operations is recommended. The frequency shall be increased when
the weather is dry.
1.2.4
Loading of public fill delivered by
barges to the site shall be sprayed with water at the material landing point to
minimize dust emission except when the materials are sufficiently dampened when
landed. Any mist spraying applied
should only dampen the dusty material and overwatering should be avoided.
Site
Entrance/ Exit
1.2.5
Vehicle washing facilities including
high pressure water jet installed at the existing exits shall be maintained and
operated by designated staff to ensure that these dust control measures are
being used. Before leaving the
fill bank site, every vehicle shall be washed to remove any dusty materials
from its body and wheels.
1.2.6
Trucks carrying dusty load entered to
the site shall be sprayed with water once the impervious sheeting covering the
load is removed.
Stockpiling
of Public Fill
1.2.7
Based on the preliminary design of the
fill bank with respect to the area allocated for stockpiling of public fill, a
minimum buffer distance of 20 m shall always be maintained between the edge of
the public fill stockpiling area of the fill bank and the nearest air sensitive
receivers at the River Trade Terminal.
Within the buffer zone, no dusty material shall be stockpiled and no
loading/ unloading and similar activities should be allowed. As shown in Figure
7, an area of 100m x 100m in the north-eastern corner of the stockpiling area
shall be managed by the contractor as a “truckload control zone”. Number of trucks
travelling to the control zone shall be limited to a maximum of 64 vehicles per
hour, and a daily maximum of 633 vehicles per day. Similarly, a minimum buffer zone of 20 m shall be maintained
between the edge of the public fill stockpiling area and the nearest air
sensitive land uses at Recovery Park Phase I and Phase II along the western
boundary of the site.
1.2.8
Stockpiling activities at the fill
bank shall be administrated by the contractor with care in proper manner to
minimise dust emissions from loading/ unloading activities and wind erosion,
and to avoid segregation, deterioration, erosion or instability of the
stockpiled material.
1.2.9
The portions of site and stockpiling
height allocated by the project engineers in the stockpiling of public fill shall
be followed in the daily operation of the fill bank. Temporary slope surfaces shall be covered with tarpaulin
sheets or other impermeable sheets, or sprayed with water or a dust suppression
chemical, or protected by other methods approved by CED. The amount of mist spraying should be
just enough to dampen the material surface without over-watering, which could
otherwise result in unnecessary surface water runoff. Final slope surfaces shall be treated by compaction,
followed by hydroseeding, vegetation planting or other suitable surface
stabiliser approved by CED to prevent the washing away of stockpiled material.
Transfer
of Material with Belt Conveyor System
1.2.10
Any belt conveyor systems used for
transfer of dusty materials shall be enclosed on top and 2 sides. Every transfer point between two
conveyors shall be totally enclosed.
An effective belt scraper or equivalent device shall be installed at the
head pulley of every belt conveyor to dislodge fine particles that may adhere
to the belt surface, and to reduce carrying back of fine particles on the
return belt. The belt conveyer
shall be equipped with bottom plates or other similar means to prevent falling
of material from the return belt.
Every stockpiling belt conveyor shall be provided with a mechanism to
adjust its level such that the vertical distance between the belt conveyor and
the material landing point is maintained at no more than 1m. Dusty material loaded from a belt
conveyor outlet to stockpiles, storage bins, trucks, barges and other open
areas shall be sprayed with water or a dust suppression chemical.
General
Site Management
1.2.11
Appropriate working methods should be
devised and arranged to minimise dust emissions and to ensure any installed air
pollution control system and measures are operated in accordance with their
design merits. In the event of
malfunctioning of any control system or equipment, the relevant dusty
activities shall stop until the relevant control system or equipment are restored
to proper functioning.
1.2.12
Frequent mist spraying should be
applied on dusty areas. The
frequency of spraying required will depend upon local meteorological conditions
such as rainfall, temperature, wind speed and humidity. The amount of mist spraying should be
just enough to dampen the material without over-watering.
1.3
Decommissioning
Phase
1.3.1
The dust control measures recommended
for the operational phase shall continue to be applicable during the
decommissioning phase of the project.
During loadout of material from the stockpiling area of the fill bank,
the material handled shall also be sprayed with water or a dust suppression
chemical before and after the transfer of material so as to maintain the entire
surface of the material sufficiently dampened. At the 100m x 100m “control zone”, loadout of material shall
be limited to a maximum of 64 truckloads per hour and 633 truckloads per day. The
contractor shall implement these measures in accordance with the requirements
of the Air Pollution Control (Construction Dust) Regulation. The vertical distance between barges
and material unloading platform at the barging point shall be minimized in
operation to reduce dust generation.
The tipping hall at the barging point shall be enclosed on top and three
sides. All public fill delivery
trucks carrying dusty load leaving the fill bank shall be required to be
covered entirely by clean impervious sheeting in prior to ensure that the dusty
materials do not leak from the vehicles.
1.4
Environmental
Monitoring and Audit
1.4.1
The implementation of the above dust
control measures shall be checked by an Environmental Monitoring and Audit
(EM&A) programme.
2.
Noise Management
Noise Management
2.1.1
The following noise management
measures are recommended to be implemented by the contractor as good site
practices during the establishment, operation and decommissioning of the fill
bank.
Construction Noise Management
·
All construction works should be carried out during the
non-restricted hours (i.e. 7:00 a.m. to 7:00 p.m. on weekdays other than General Holidays);
·
Before the commencement of any work that may generate a
significant noise impact, the Contractor should submit to the Engineer for
approval the method of working, equipment and sound-reducing measures (e.g. use
of silenced type of equipment) intended to be used
Operational/ Decommissioning Phase Noise
Management
·
The noise standards specified in the Technical Memorandum for the Assessment of
Noise from Places Other Than Domestic Premises, Public Places or Construction
Sites shall be met;
·
The fill bank should not be in operation from 8:00 p.m.
to 8:00 a.m. the next day;
·
Before the commencement of any work that may generate a
significant noise impact, the Contractor should submit to the Engineer for
approval the method of working, equipment and sound-reducing measures (e.g. use
of silenced type of equipment) intended to be used
3.
Water Quality Control Measures
Water Quality Control Measures
3.1.1
Potential water quality impact during
the establishment, operation and decommissioning of the fill bank shall be
controlled with the following as basic principles:
·
Prevent or minimise the likelihood of the identified
pollutants being in contact with rainfall or runoff; and
·
Measures to abate pollutants in the stormwater runoff.
3.1.2
These principles shall be achieved
through the implementation of adequately designed water quality control
measures as Best Management Practices (BMPs). The guidelines for handling and disposal of construction
site discharges as detailed in EPD’s ProPECC Note PN1/94 “Construction Site
Drainage” should be followed.
Provision
of Stormwater Interception Facilities and Buffer Zone
3.1.3
Trapezoidal surface channels should be
constructed to intercept polluted surface runoff. These channels shall be equipped with sand/ de-silting traps
such that the effluent discharged from the site during the establishment,
operation and decommissioning phases will meet the discharge limits specified
in the Technical Memorandum on Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Waters. Annex IV shows the typical design of
sand trap (CED Drawing No. GC 1034).
3.1.4
Before completion of the surface
drainage channels at the commencement of the project, earth bunds and sand bag
barriers shall be used at required locations to effectively divert stormwater
to available drainage channels constructed under the reclamation works. The temporary drainage facilities
provided shall allow polluted stormwater to be diverted to existing
intercepting channels before stockpiling of public fill should begin. The intercepting channels shall be
equipped with sand/ silt removal facilities to allow the stormwater to be
treated before discharge at the designated outfalls. Effluent discharged shall
meet the relevant discharge limits specified in the Technical Memorandum.
3.1.5
To minimise potential water quality
impact associated with polluted surface water runoff, a minimum buffer distance
of 50m will be provided between the edge of the stockpiling area of the fill
bank and the seafront. Open
channels and/or other effective drainage system shall be constructed at the
perimeter of the site for intercepting and directing runoff to sand/ silt
removal facilities prior to discharge.
The unpaved area on the seaward side of the channels shall be covered
with gravel and formed with slope so that polluted stormwater will be
intercepted by the channels.
Excavated
Material generated during Establishment
3.1.6
Any excavated material generated near
the seafront (e.g. from the construction of the barging point) not required to
be backfilled immediately should be transported away from the seafront to avoid
potential water quality impact especially during the rainy season.
Sorted
Public Fill
3.1.7
Public fill transported to the
stockpiling area for storage should not contain unsuitable material such as
peat, vegetation, timber, organic, soluble or perishable material, dangerous or
toxic material, floatable materials (such as bottle, plastic bags, foam box),
and materials susceptible to combustion.
Surface
Protection Measures for Slope
3.1.8
Public fill at the stockpiling area
should be handled with care in proper manner that will not result in
segregation, deterioration, erosion or instability of the material. The designated positions for the
unloading of fill material in the daily operation of the fill bank should be
followed. Temporary slope surfaces
shall be covered as far as practicable and as soon as possible with tarpaulin
sheets or other impermeable sheets, or protected by other methods approved by
CED when rainstorms are likely, especially when a rainstorm is imminent or
forecast. Final slope surfaces
shall be treated by compaction, followed by hydroseeding, vegetation planting
or other suitable surface stabiliser approved by CED to prevent the washing
away of stockpiled material.
Maintenance
of Sand/ Silt Removal Facilities
3.1.9
Adequately designed and constructed
catchpits, sand and silt removal facilities and intercepting channels should be
maintained, and the deposited silt and grit should be removed weekly and on a
need basis especially during the onset of and after each rainstorm to ensure
that these facilities are functioning properly at all times during the
establishment, operation and decommissioning phases.
Wheel
Washing Facilities
3.1.10
All vehicles and plant bodies should
be cleaned before they leave the fill bank site to ensure that no earth, mud or
debris is deposited by them on roads.
A wheel washing bay should be provided at the site exit and wash-water
should have sand and silt settled out or removed before the water is being
reused or discharged into storm drains.
The section of construction road between the wheel washing bay and the
public road should be paved with concrete, bituminous materials or hardcores to
reduce vehicle tracking of soil and to prevent site run-off from entering
public road drains.
Wastewater
from Site Facilities
3.1.11
Sewage from toilets and similar
facilities should be discharged into a foul sewer, or chemical toilets should
be provided. Should the use of
chemical toilets be necessary, these should be provided by a licensed
contractor, who will be responsible for appropriate disposal and maintenance of
these facilities. Wastewater
collected from canteen kitchens, including that from basins, sinks and floor
drains, should be discharged into foul sewers via grease traps. Drainage system provided at car parking
areas shall be provided with oil interceptors in addition to sand/ silt removal
facilities.
Use
of Barges
3.1.12
All barges used in the transportation
of fill material during the operation/ decommissioning stages should be
properly licensed under the Shipping and Port Control Ordinance, and of
appropriate size such that adequate clearance is maintained between the vessels
and the sea bed at all states of the tide to ensure that undue turbidity is not
generated by turbulence from vessel movement or propeller wash. All vessels
used for transportation of fill material should have tight fitting seals to
their bottom openings to prevent leakage of material during transport. For the transfer of public fill from
the berthing barges to Tuen Mun Area 38, the following design measures shall be
specified in the Technical Specification as environmental protection measures:
·
When backhoe fixed on an appropriately design flat-top
pontoon is in use, the reach of the backhoe shall be controlled to within the
flat-top pontoon of sufficient length to avoid accidental dropping of public
fill into the sea;
·
When hopper barges with mobile crane is in use,
guardrails or equivalent shall be fixed alongside the berthing faces to guide
the movement of the crane to avoid accidental dropping of fill material into the
sea;
·
When derrick barges with built-in crane are in use, the
reach of the jig shall be controlled to within the length of the barge to avoid
accidental dropping of public fill into the sea
3.1.13
These recommended measures for
transfer of public fill from barges to the fill bank are illustrated in Figure
M1 through Figure M3. The design
of the specific transfer methods shall be as such that the pathway of material
delivery from barge to the waterfront will not be directly on top of the marine
water to effectively prevent the dropping of material to the sea. Should other equivalent transfer
methods and environmental protection measures are proposed by the future
contractor, these shall be subject to approval of CED and DEP.
3.1.14
Barges should not be filled to a level
which may cause overflow of material during loading or transportation. Barge
effluents (e.g. muddy water) should be properly collected and treated prior to
disposal. The work activities should not cause any visible foam, oil, grease,
scum, litter or other objectionable matters to be present on the water in the
vicinity of the barging point.
3.1.15
A waste collection vessel shall be
deployed to remove floating refuse on the sea near the fill bank for proper
disposal.
Construction
Site Drainage Guidelines
3.1.16
Other best management practices to
reduce stormwater and non-point source pollution recommended under ProPECC PN
1/94 on Construction Site Drainage should be properly followed.
3.1.17
The Contractor shall be responsible
for the design and implementation of the water pollution control measures. If the above measures are not
sufficient to restore any water quality impact monitored to acceptable levels,
upon gaining advice through discussion with the Independent Environmental Checker (IEC) and Engineer’s Representative
(ER) and the contractor, the Environmental Team (ET) shall propose some
other mitigation measures for implementation by the Contractor. The ET shall carry out regular site
audit to ensure timely implementation of the BMPs by the contractor.
Environmental
Monitoring and Audit
3.1.18
The implementation of the above water
pollution control measures shall be checked by an Environmental Monitoring and
Audit
(EM&A) programme.
Landfill Gas Migration Protection Measures
4.1.1
Main site offices of the fill bank shall
be constructed within the site area lying outside the 250m consultation zone of
the restored Siu Lang Shui landfill.
The container office(s) to be set up at the site entrance/ exit which is
situated within the consultation zone of the landfill shall be constructed on a
raised hollow platform, or equivalent measure should be provided.
4.1.2
No underground structures such as
drainage and sewage systems, underground pipelines and chambers shall be
constructed at the site area lying within the consultation zone. Access to the fill bank by the general
public shall be restricted.
4.1.3
During the establishment, operation
and decommissioning phases of the fill bank, hazards may arise as a result of
the flammability of landfill gas or its potentially asphyxiating properties. It
is advisable to include appropriate specified clauses for incorporation in the
contract documents for the project.
In general, the contractor should be aware of, and should inform
supervisor and workers of the following:
·
Methane and carbon dioxide are always likely to be
present in the soil voids;
·
Physical and chemical nature of landfill gas;
·
Methodologies for landfill gas detection;
·
Fire and explosion hazards associated with landfill
gas;
·
Toxicity effects and health hazards associated with
landfill gas;
·
Potential health effects from direct contact with
leachate/ groundwater contaminated by leachate; and
·
Provide the contingency measures for leachate/
groundwater contamination
4.1.4
Precautions should be clearly laid
down and rigidly adhered for activities such as excavation, trenching and
creation of confined or semi-confined spaces, if any, carried out within the
consultation zone of the restored landfill. In addition to normal site safety procedures, gas detection
equipment and appropriate breathing apparatus should be available and used when
entering confined spaces or trenches deeper than 2 metres.
4.1.5
Personnel entering the site shall be
fully informed of the risk associated with potential landfill gas exposure.
4.1.6
Concentration of methane, carbon
dioxide and oxygen within the manholes or the like shall also be checked in
prior and confirmed to be within a safe level before any workers shall enter
any enclosed space situated within the consultation zone of the restored
landfill.
4.1.7
Safety measures including the
following should be covered in the contract document:
·
Proper warning of the potential hazards in the vicinity
of excavation works at existing ground level;
·
Appropriate training for workers who work in, or have
responsibility for “at risk” areas;
·
Preparation of an excavation procedure or code of
practice for excavation works at existing ground level;
·
Prohibition of smoke and naked flames within any ground
level excavation or ground-level confined space;
·
Proper control of welding, flame-cutting or other hot
works from any trench, confined spaces or excavation area;
·
Proper location for mobile offices, equipment stores,
mess rooms, etc.;
·
Provision of adequate fire extinguishing equipment,
fire-resistant clothing and breathing apparatus;
·
Preparation of a “method-of-working” statement covering
all normal and emergency procedures before beginning of any required drilling
operations.
4.1.8
On the unlikely events that any sign
of leachate or leachate-contaminanted groundwater be encountered during the
establishment, operation or decommissioning phases of the fill bank, the
landfill operator should be informed so that this can be collected for proper
treatment and disposal.
5.
Landscape and Visual Control Measures
Landscape and Visual Control Measures
5.1.1
Hydroseeding or coloured geo-textile
matting (dark green/ brown) shall be provided on the slopes of the fill bank
along the eastern, northern and western sides of the fill bank as the slopes of
each layer of platform are formed.
A buffer tree planting strip should be provided along the northern
perimeter of the site where space permits as shown in Figure 12. A row of approximately 3m high native
evergreen tree species with a tall habit when fully grow (e.g. Casuarina
equisetifolia) shall be planted at the early establishment/
operational phase of the project. To ensure the effective implementation of
these measures, a Government approved landscape contractor will be hired to
undertake and maintain the hydroseeding and tree planting works.
5.1.2
The design, colour and finish of
structures at the fill bank should be such that they are visually
recessive. Reflectivity should be
reduced through selection of material or surface treatment. The surface colour
selected should be of an earthy tone with strong natural qualities (e.g. green/
grey/ brown). Use of bold colour
schemes should be avoided. The
existing 2.4m high site hoarding located along Lung Mun Road should be
maintained to help screening of the fill bank.
Figure M1
Figure M2
Figure M3