Project Title:
Widening of Yuen
Long Highway between Lam Tei and Shap Pat Heung Interchange
Reference of the
Approved EIA Report in the Register : AEIAR-059/2002
Conditions of
Approval under Section 8(3) of the EIA Ordinance (the Ordinance)
Date of Director’s
Decision : 22 May 2002
The
EIA report as exhibited under section 7(1) of the Ordinance is approved on the
condition that the following requirement shall form part of the approved EIA
report:
1.
To
deal with project changes or any key changes in circumstances after the
approval of the EIA report and before the application for environmental permit,
the applicant or the person in charge of the project shall seek written
agreement from the Director of Environmental Protection (the Director) on those
changes that would affect the findings and recommendations of the approved EIA
report, and shall demonstrate to the satisfaction of the Director that the
requirements of the Technical Memorandum issued under the Ordinance can be met
by equivalent or additional measures.
Such information shall be made available to the public and placed on the
Register, as directed by the Director.
Environmental
Protection Department
May
2002