Project Title:
Relocation of Yiu Lian Floating Dock No.3

 

Reference of the Approved EIA Report in the Register: AEIAR-104/2007

Condition of Approval under Section 8(3) of the EIA Ordinance (the Ordinance)

 

The EIA Report as exhibited under Section 7(1) of the Ordinance is approved by the Director on the condition that the following amendments shall be incorporated into the EIA Report, as shall form part of the approved EIA Report:-

 

1.      The Environmental Monitoring and Audit programme shall be strengthened to include the monitoring of Chinese White Dolphin at the existing site of Yam O Wan to ensure that the project will not cause unacceptable environmental impacts during decommissioning phase of the floating dock.


 

Environmental Protection Department