Project Title: Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road

 

Reference of the Approved EIA Report in the Register: AEIAR-144/2009

Conditions of Approval under section 8(3) of the EIA Ordinance

 

 

The EIA Report as exhibited under section 7(1) of the EIA Ordinance is approved by the Director on the following conditions:

 

1.                          The project proponent shall not, for the marine bored piles located at the west of the Airport Island, carry out formation of underwater sockets into rock in May to June which is the peak calving season of Chinese white dolphins;

 

2.                          The project proponent, including its contractors and subcontractors, shall not use any of the land area in Sham Wat, Sha Lo Wan, Hau Hok Wan and San Tau as works area, vehicle parking, equipment storage or other related activities; and

 

3.                          The project proponent shall not use underwater percussive piling for the project.

 

 

Environmental Protection Department

October 2009