Project
Title:
Reference of the Approved EIA Report in the
Register: AEIAR-144/2009
Conditions of Approval under section 8(3)
of the EIA Ordinance
The EIA Report
as exhibited under section 7(1) of the EIA Ordinance is approved by the
Director on the following conditions:
1.
The project proponent shall not, for
the marine bored piles located at the west of the Airport Island, carry out formation
of underwater sockets into rock in May to June which is the peak calving season
of Chinese white dolphins;
2.
The project proponent, including its
contractors and subcontractors, shall not use any of the land area in Sham Wat,
Sha Lo Wan, Hau Hok Wan and San Tau as works area, vehicle parking, equipment
storage or other related activities; and
3.
The project proponent shall not use
underwater percussive piling for the project.
Environmental
Protection Department
October 2009