Reference of the Approved EIA Report in the
Register : AEIAR-146/2009
Conditions of Approval under Section 8(3)
of the EIA Ordinance (the Ordinance)
The EIA Report
as exhibited under Section 7(1) of the Ordinance is approved by the Director on
the following conditions:
1.
The project proponent shall not, for
the marine bored piles construction, carry out formation of underwater sockets
into rock in May to June which is the peak calving season of Chinese White Dolphins;
2.
The project proponent shall not use
underwater percussive piling for the project; and
3.
The project proponent shall increase
the frequency of monitoring of Total Suspended Particulates (TSP) level, in
consultation with the Environmental Protection Department, to ensure that
appropriate mitigation measures, including stoppage of works if necessary,
would be taken to mitigate any upsurge of TSP level.
Environmental
Protection Department
October 2009