Project Title: Tsim Sha Tsui Station Northern Subway
Reference of the Approved EIA Report in the Register: AEIAR-127/2008
Condition of Approval under Section 8(3) of the EIA
Ordinance (the Ordinance)
The EIA Report as exhibited under
Section 7(1) of the Ordinance is approved by the Director of Environmental
Protection with the following condition:
1.
the Project Proponent shall
appoint a certified landscape architect to advise on, monitor and ensure proper
implementation of the tree preservation plan for the project; to provide
information related to tree surveys, tree preservation methods, survival rate
and location of transplanted trees; and to update the amenity value of the
three Delonix trees as mentioned in the approval EIA report (see Note 1). The Project
Proponent shall make the above information related to tree preservation available
to the public.
Environmental Protection Department
December 2008
………………………………………..
Note 1: The
three Delonix trees referred to should include the ones along Haiphong Road;
adjacent to Entrance A1 as shown in landscape resources LR04 of Table 7.4 and
Figure