天 水 圍 預 留 區 輕 鐵 支 線 及
屯 門 杯 渡 路 青 麟 路 之 輕 鐵 架 空 路 軌
1.1 EIA Study Brief
1.2 Background Information
1.3 Previous Studies and Environmental Benefits
1.4 Structure of EIA Report
2.1 Alignment
2.2 Neighbouring Environment
2.3 LR Operations
2.4 Preliminary Construction Programme
2.5 Cumulative Impacts
3.1 Study Objectives
3.2 Study Scope
4 AVAILABLE TECHNICAL Information
5.1 Legislation and Standards
5.1.1... Hong Kong Air Pollution Control Ordinance
5.1.2... Air Pollution Control (Construction Dust) Regulation
5.2 Major Construction Activities
5.3 Recommendations
5.4 Conclusion
6 Operational Noise Assessment
6.1 Legislation and Standards
6.1.1... Railway Noise Criteria – Airborne Noise
6.1.2... Fixed Plant Noise Criteria
6.2 Noise Sensitive Receivers (NSRs)
6.2.1... NSR Locations
6.2.2... Area Sensitivity Ratings
6.3 Airborne Noise Assessment
6.3.1... Assessment Methodology
6.3.1.1..... Train Noise Data and Operational Data
6.3.1.2..... Correction for Rail Deterioration
6.3.1.3..... Correction for Train Speeds
6.3.1.4..... Correction for Distance
6.3.1.5..... Correction for Deck Reflection
6.3.1.6..... Correction for Joints
6.3.1.7..... Wheel Squeal
6.3.1.8..... Conversion to SEL
6.3.1.9..... Correction for Train Frequency
6.3.1.10... View Angle
6.3.1.11... Correction for Façade Reflection
6.3.1.12... Cumulative Noise Impacts from West Rail
6.3.1.13... Structure Re-radiated Noise from Viaduct Structure
6.3.1.14... Normal, Abnormal and Emergency Operation
6.3.2... Assessment Results
6.4 Fixed Plant Noise Assessment
6.4.1... Noise Sources
6.4.2... Assessment Methodology
6.4.3... Assessment Results
6.4.3.1..... Transformer Noise
6.4.3.2..... Other Noise Sources
6.5 Recommendations
6.6 Conclusion
7 Construction Noise Assessment
7.1 Legislation and Standards
7.1.1... Noise Standards in Normal Working Hours
7.1.2... Noise Standards in Restricted Hours
7.2 Assessment Methodology
7.2.1... Noise Prediction Methodology
7.2.2... Noise Mitigation Strategy
7.2.2.1..... M1: Level One Mitigation Measures
7.2.2.2..... M2: Level Two Mitigation Measures
7.2.2.3..... M3: Level Three Mitigation Measures
7.2.2.4..... M4: Level Four Mitigation Measures
7.3 Construction Noise Assessment
7.3.1... Noise Sensitive Receivers
7.3.2... Potential Sources of Impacts
7.3.3... Cumulative Construction Noise Impact with West Rail Construction
7.3.4... Predictions of Impacts
7.3.5... Evaluation of Impacts
7.3.5.1..... Pui To Road Grade Separation
7.3.5.2..... LT1 Grade Separation
7.3.5.3..... Tin Shui Wai Reserve Zone Extension
7.3.6... Recommended Mitigation Measures
7.3.6.1..... Good Site Practices and Noise Management Techniques
7.3.6.2..... Scheduling of Construction Works Outside School Examination Period
7.3.6.3..... Use of “Quiet” Equipment and Working Methods (M1)
7.3.6.4..... Purpose Built Temporary Noise Barriers (M2)
7.3.6.5..... Movable Noise Barriers (M2)
7.3.6.6..... Delocalization of Equipment in Critical Areas (M3)
7.3.6.7..... Local Reduction of Number of Plant Operating in Critical Areas where Practicable (M3)
7.3.6.8..... Limiting Operation Time of Construction Equipment On-Site (M4)
7.3.7... Prediction of Mitigated Noise Levels
7.3.7.1..... Pui To Road Grade Separation
7.3.7.2..... LT1 Grade Separation
7.3.7.3..... Tin Shui Wai Reserve Zone Extension
7.3.7.4..... Cumulative Impacts Within LRT Worksites
7.3.8... Further Mitigation to be Considered by the Contractor
7.4 Conclusion
8.1 Legislation and Standards
8.1.1... Water Pollution Control Ordinance (WPCO)
8.1.2... Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
8.1.3... The Deep Bay “Zero Discharge Policy”
8.1.4... Construction Site Drainage Guidelines
8.2 Assessment Methodology
8.2.1... Construction Phase
8.2.2... Operational Phase
8.3 Assessment Results
8.3.1... Construction Phase
8.3.1.1..... Water Sensitive Receivers (WSRs)
8.3.1.2..... Baseline Conditions
8.3.1.3..... Potential Source of Impact
8.3.1.4..... Prediction and Evaluation of Impact
8.3.2... Operation Phase
8.3.2.1..... Baseline Conditions
8.3.2.2..... Potential Sources of Impacts
8.3.2.3..... Predication and Evaluation of Impacts
8.4 Recommendations
8.4.1... Construction Phase
8.4.1.1..... Construction Runoff
8.4.1.2..... Sewage Effluent
8.4.1.3..... Residual Impacts
8.4.2... Operation Phase
8.4.2.1..... Runoff from Rail Track
8.4.2.2..... Residual Impacts
8.5 Conclusion
9 Waste Management Implications
9.1 Legislation and Standards
9.2 Assessment Methodology
9.2.1... Types and Nature of Waste Generated
9.2.1.1..... Construction Phase
9.2.1.2..... Operational Phase
9.2.2... Proposed Waste Management Methods
9.3 Assessment Results
9.3.1... Potential Sources and Prediction of Impacts
9.3.1.1..... Construction Phase
9.3.1.2..... Operational Phase
9.3.2... Evaluation of Impacts
9.3.2.1..... Construction Phase
9.3.2.2..... Operational Phase
9.4 Recommendations
9.4.1... Construction Phase
9.4.1.1..... Waste Management Hierarchy
9.4.1.2..... Storage, Collection and Transport of Waste
9.4.1.3..... Excavated Material
9.4.1.4..... Construction and Demolition Material
9.4.1.5..... Chemical Waste
9.4.1.6..... General Refuse
9.4.2... Operational Phase
9.4.2.1..... General Refuse and Industrial Waste
9.4.2.2..... Chemical Waste
9.5 Conclusion
10 Cultural Heritage Assessment
10.1 Legislation and Standards
10.2 Assessment Methodology
10.2.1. Relevant Information from West Rail Project
10.2.2. Liaison with AMO
10.2.3. Field Evaluation
10.3 Assessment Results
10.3.1. Tin Shui Wai Reserve Zone Extension
10.3.2. Grade Separation of Junction LT1
10.3.3. Grade Separation of Junctions J6, Mj7 and Mj8
10.4 Recommendations
10.5 Conclusion
11 Landscape and Visual Impacts
11.1 Legislation and Standards
11.2 Landscape Impact Assessment Methodology
11.3 Visual Impact Assessment Methodology
11.4 Mitigation Measures
11.5 Residual Impacts
11.6 Review of Planning and Development Control Framework
11.7 Assessment Results for Tin Shui Wai Reserve Zone
11.7.1. Existing Landscape and Visual Context
11.7.2. Impacts
11.7.3. Recommended Mitigation Measures During Construction / Operation
11.8 Assessment Results for Grade Separation for Tsing Lun Road, Tuen Mun
11.8.1. Existing Landscape and Visual Context
11.8.2. Impacts
11.8.3. Recommended Mitigation Measures During Construction / Operation
11.9 Assessment Results for Grade Separation At Pui To Road, Tuen Mun
11.9.1. Existing Landscape and Visual Context
11.9.2. Impacts
11.9.3. Recommended mitigation measures during construction/operation
11.10 Funding, Implementation, Management and Maintenance
11.11 Summary of Landscape Impacts
11.12 Conclusions
12 environmental monitoring and auditing programme
12.1 EM&A Manual for EIA Study
12.2 Amendments to EM&A Manual
12.3 Implementation Schedule
12.4 Environmental Management Plans (EMP)
13 recommendations and conclusions
14 Summary of Environmental Outcomes
16 references
APPENDICES
Appendix 1 Layout of
Proposed LRT Works
Appendix 2 Locations and
Description of Representative Noise Sensitive Receivers
Appendix 3 Building Plans
for Tin Shui Wai Reserve Zone (Provided by HKHA)
Appendix 4 Predicted Train
Frequency and Speed (Provided by KCR)
Appendix 5 Updated Noise
Calculations for West Rail (for 12-car trains)
Appendix 6 Normal, Abnormal
and Emergency Operations for LRT
Appendix 7 Predicted
Cumulative Train Noise Impacts
Appendix 8 Not Used
Appendix 9 Fixed Plant
Noise Assessment
Appendix 10 Separation Distance of NSRs
to Construction Sites
Appendix 11 Construction Plant
Inventory & Construction Schedule
Appendix 12 Sound Power Level of
Quiet Equipment
Appendix 13 List of Declared and
Deemed Monuments
Appendix 14 Photos Taken During Field
Evaluation
Appendix 15 Letter from TDD
FIGURES
Figure 2.1 Location
Plan
Figure 2.2a Layout
of Proposed LRT Works (Tin Shui Wai Reserve Zone)
Figure 2.2b Layout
of Proposed LRT Works (Pui To Road, Tuen Mun)
Figure 2.2c Layout
of Proposed LRT Works (Lam Tei)
Figure 6.1 Maximum
Structure Reradiated Noise from Existing LRT Viaduct Near MJ9
Figure 8.1 Location
of Water Sensitive Receivers and Monitoring Locations (Tin Shui Wai Area)
Figure 8.2 Location
of Water Sensitive Receivers and Monitoring Locations (Tuen Mun River)
Figure 8.3 Location
of Water Sensitive Receivers and Monitoring Locations (Tuen Mun Typhoon Shelter
and Gazaetted Beach)
Figure 11.1 Tin
Shui Wai Reserve Zone LRT Extension Landscape Impact Assessment Survey Plan
Figure 11.2 Typical
views of Landscape character units within Tin Shui Wai Reserve Zone
Figure 11.3 Tin
Shui Wai Reserve Zone LRT Extension Visual Impact Assessment Survey Plan
Figure 11.4 Tin
Shui Wai Reserve Zone LRT Extension Illustrative views of Landscape mitigation
measures
Figure 11.5 Tin
Shui Wai Reserve Zone LRT Extension Illustrative views of Landscape mitigation
measures
Figure 11.6 Tin
Shui Wai Reserve Zone LRT Extension Illustrative views of Landscape mitigation
measures
Figure 11.7 Tin
Shui Wai Reserve Zone LRT Extension Illustrative views of Landscape mitigation
measures
Figure 11.8 Tin
Shui Wai Reserve Zone LRT Extension Illustrative views of Landscape mitigation
measures
Figure 11.9 Grade
Separation of LRT at Tsing Lun Road, Tuen Mun Landscape Impact Assessment
Survey Plan
Figure 11.10 Typical
views of Landscape character units within Tsing Lun Road Area
Figure 11.11 Grade
Separation of LRT at Tsing Lun Road, Tuen Mun Visual Impact Assessment Survey Plan
Figure 11.12 Lam
Tei LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.13 Lam
Tei LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.14 Lam
Tei LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.15 Grade
separation of LRT at Pui To Road, Tuen Mun Landscape Impact Assessment Survey
Plan
Figure 11.16 Typical
views of Landscape character units within Pui To Road, Tuen Mun
Figure 11.17 Typical
views of Landscape character units within Pui To Road, Tuen Mun
Figure 11.18 Grade
Separation of LRT at Pui To Road, Tuen Mun Visual Impact Assessment Survey Plan
Figure 11.19 Pui
To Road LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.20 Pui
To Road LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.21 Pui
To Road LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.22 Pui
To Road LRT Extension Illustrative views of Landscape mitigation measures
Figure 11.23 Pui
To Road LRT Extension Illustrative views of Landscape mitigation measures
ABBREVIATIONS
AAB |
Antiquities Advisory Board |
AMO |
Antiquities and Monuments Office |
ANL |
Acceptable Noise Levels |
APCO |
Air Pollution Control Ordinance |
AQO |
Air Quality Objectives |
ASR |
Area Sensitivity Ratings |
BNL |
Basic Noise Levels |
BOD5 |
5-day Biochemical Oxygen Demand |
CNP |
Construction Noise Permit |
COD |
Chemical Oxygen Demand |
CRN |
Calculation of Rail Noise |
CRTN |
Calculation of Road Traffic Noise |
DB |
Decibels |
DDC |
Detailed Design Consultant |
DO |
Dissolved Oxygen |
DPA |
Development Permission Area |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EM&A |
Environmental Monitoring and Auditing |
EPD |
Environmental Protection Department |
FMC |
Fill Management Committee |
HKAQO |
Hong Kong Air Quality Objectives |
HKHA |
Hong Kong Housing Authority |
HKPSG |
Hong Kong Planning Standards and Guidelines |
Hz |
Hertz |
KCR/KCRC |
Kowloon-Canton Railway Corporation |
LR/LRT |
Light Rail |
NCO |
Noise Control Ordinance |
NSR |
Noise Sensitive Receiver |
OZP |
Outline Zoning Plan |
PCW |
Prescribed Construction Work |
PME |
Powered Mechanical Equipment |
ppm |
Parts per Million |
ProPECC |
Professional Persons Environmental Consultative Committee |
PS |
Particular Specification |
PTI |
Public Transport Interchange |
RSP |
Respirable Suspended Particulates |
SEL |
Sound Exposure Level |
SPME |
Specified Powered Mechanical Equipment |
SS |
Suspended Solids |
SSC |
Suspended Sediment Concentration |
SWL |
Sound Power Level |
TIS |
Tin Shui Wai |
TM |
Technical Memorandum |
TOC |
Total Organic Carbon |
TSP |
Total Suspended Particulates |
VSR |
Visually Sensitive Receivers |
WBTC |
Works Branch Technical Circular |
WCO |
Water Control Objectives |
WCZ |
Water Control Zone |
WDO |
Water Disposal Ordinance |
WPCO |
Water Pollution Control Ordinance |
WQO |
Water Quality Objectives |
WR |
West Rail |
WSR |
Water Sensitive Receivers |
Ove Arup & Partners (OAP) was commissioned by Kowloon Canton Railway Corporation (KCRC) as the EIA Consultant for the Light Rail Transit (LRT) works for Tin Shui Wai Reserve Zone and Grade Separation of the LRT with Pui To Road and Tsing Lun Road in Tuen Lun.
An application (No ESB-27/1999) for an EIA study brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by KCR on 19 October 1998 with a project profile (No. PP-040/1999). The project profile covers a designated project under the EIAO by virtue of the Section A.2 of the Schedule 2, Part 1 of the EIAO. Pursuant to Section 5(7)(a) of EIAO, EPD issued a study brief (ref: EIA Study Brief No: ESB-027/1999) [1] to KCR to conduct the necessary EIA study.
The existing Light Rail (LR) system was introduced to serve residents of Tuen Mun and Yuen Long in September 1988 with an initial network of 24km, 6 routes and 41 stops. To cater for the continual development and population growth of the Northwest New Territories, the LR had further expanded in Tuen Mun and Tin Shui Wai in stages since early 1990s. In March 1995, Phase 3 of Tin Shui Wai Extension, the last portion of the existing LR extension works, was put into passenger service. The whole LR network now comprises 32 km of double track, 8 routes and 57 stops. The average daily patronage in 1998 was 350,000, including 37,000 on LR feeder bus.
The existing LR network will be expanded to meet the increasing travel demand due to the introduction of the West Rail (WR). In addition to the current role of internal public transport, LR will also provide major feeder transport service to WR passengers at four WR stations, namely, Yuen Long, Tin Shui Wai, Siu Hong and Tuen Mun. It is therefore important to develop integrated design solutions at WR/LR interchanges in order to ensure the pedestrian linkages are safe, efficient and user friendly to the passengers. Tin Shui Wai Phase 4 Extension and Tin Shui Wai Reserve Zone Extension will also be built to improve the accessibility of WR in the eastern and northern parts of Tin Shui Wai.
A section of the existing LR tracks running at-grade along Pui To Road in Tuen Mun, and another section that crosses the Tsing Lun Road at-grade junction in northern part of Tuen Mun will be elevated. The signalling system for the operation of the LR vehicles will be replaced by a new system in the new extensions, and subsequent replacement to the entire LR system.
The provision for LRT in the Tin Shui Wai Reserve Zone was initiated in the previous engineering investigation study for Tin Shui Wai and Reserve Zone [22] in 1997. The engineering feasibility for the LRT alignment and associated facilities (stops, rectifier stations and terminus) have been endorsed.
The
introduction of the proposed LRT extension in Tin Shui Wai Reserve Zone would
provide an efficient and direct connection with the West Rail Tin Shui Wai
Station. According to the OZP S/TSW/3
dated 1998 for Tin Shui Wai Area, there would be about 129,000 population in
the Tin Shui Wai reserve zone.
The entire population will be benefited from the introduction of the
proposed LRT, especially for the connection with West Rail network.
The structure of this EIA report is outlined below for easy reference:
Section |
Title |
Aims |
1 |
Introduction |
An introduction of the
background information and the layout of the EIA report |
2 |
Project Description |
A description of the extent
and details of the project available |
3 |
Study Objectives and Scope |
Outline the objectives and
scope for various environmental aspects |
4 |
Available Technical
Information |
List the key information
reviewed in this EIA study |
5 |
Air Quality Assessment |
Present the legislation,
methodology and recommendations for air quality impacts during construction
phase |
6 |
Operational Noise
Assessment |
Present the legislation,
methodology and recommendations for operational noise impacts |
7 |
Construction Noise
Assessment |
Present the legislation,
methodology and recommendations for construction noise impacts |
8 |
Water Quality Assessment |
Present the legislation,
methodology and recommendations for water quality impacts |
9 |
Waste Management
Implications |
Present the legislation,
methodology and recommendations for waste management |
10 |
Cultural Heritage
Assessment |
Present the legislation,
methodology and recommendations for cultural heritage |
11 |
Landscape and Visual
Impacts |
Present the legislation,
methodology and recommendations for landscape and visual impacts |
12 |
Environmental Monitoring
and Auditing Programme |
Present the legislation,
methodology and recommendations for EM&A |
13 |
Recommendations and
Conclusions |
Summary of the findings
and recommendations |
14 |
Summary of Environmental
Outcomes |
Summarise environmental
outcomes and benefits |
15 |
Implementation Schedule |
Summarise implementation
responsibility for environmental mitigation measures |
16 |
References |
List of relevant reference
information |
The proposed light railway extension and alteration works are located in Tin Shui Wai and Tuen Mun (Figure 2.1). The light railway in Tin Shui Wai Reserve Zone lies within the formed LRT reserve and is approximately 2.6km long and has 6 stops. The track will be on ballast and at grade for all the sections.
The grade separation work in Pui To Road and Lam Tei involves elevating the existing trackworks near Junctions J6, Mj7, Mj8 and LT1. The future horizontal alignment would generally follow the existing alignment. For the viaduct at LT1, a safety enclosure will be provided for the entire viaduct and paved track would be employed due to the constraints imposed by the overhead electricity power lines. Temporary track diversion will be located directly to the west of the existing track. The temporary track will be on ballast and at grade.
For the viaduct section in Pui To Road Grade Separation, a composite structure consisting of a concrete deck supported by steel portals will be adopted. All the steel elements of the portals will be encased in concrete. Except for the track directly underneath the deck of the future West Rail Tuen Mun Station, ballast track will be employed.
Temporary track diversion in Pui To Road will be close to the existing track. All steel elements of the temporary structure will also be encased in concrete.
Figure 2.2a to 2.2c show the layout of the proposed LRT works. Detailed drawings of the layout are given in Appendix 1.
The developments alongside the proposed alignment have been completed. These developments include the following:
Area |
Developments
along alignment |
Reserve Zone |
· Residential areas and Government / Institution / Community |
Pui To Road |
· Residential areas and Schools |
Tsing Lun Road |
· Residential areas |
Table 2.1 : Summary
of Developments Along Alignment
All the existing residential premises are with openable windows. Some of the schools are provided with air conditioning. A detailed description of these developments is given in Appendix 2.
The normal operating period of the proposed LRT would be from 0530 to 0130 hours. As advised by LR, the AM peak would start from 0630 hours in the morning. The train frequency during PM peak would be lower than the frequency during AM peak.
It is planned to
start the construction work by early 2001. The construction period would last for approximately 3
years. A tentative construction
programme is given in Appendix 11.
This assessment
has taken into account the cumulative impacts (both during operational and
construction phases) from West Rail.
In accordance
with the current construction schedules of LRT and West Rail, the two projects
have no over-lapping construction period except that the LRT site formation
work at Pui To Road (ie LRT Tuen Mun Station and San Fat LR Stop) would be
overlapping with beam erection and station construction of West Rail. This arrangement has been taken into
account in the assessment.
The objectives of this EIA study are:
a) To describe the proposed project and associated works together with the requirements for carrying out the proposed project;
b) To identify and describe the elements of the community and environment likely to be affected by the proposed and / or likely to cause adverse impacts to the proposed project, including both the natural and man-made environment.
c) To identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;
d) To identify any negative impacts on sites of cultural heritage and to proposed measures to mitigate these impacts;
e) To identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;
f) To propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the project;
g) To identify, predict and evaluate the residual (ie after practicable mitigation) environmental impacts and the cumulative effects expected to arise during the construction and operational phases of the project in relation to the sensitive receivers and potential affected uses;
h) To identify, assesses and specify methods, measures and standards, to be included in the detailed design, construction and operation of the project which are necessary to mitigate these environmental impacts and reducing them to acceptable levels;
i) To investigate the extent of side-effects of proposed mitigation measures that may lead to other forms of impacts;
j) To identify constraints associated with the mitigation measures recommended in the EIA study;
k) To design and specify the environmental monitoring and audit requirements, if required, to ensure the implementation and the effectiveness of the environmental protection and pollution control measures adopted.
l) The objectives of the EIA study are to describe the proposed LRT works and identify elements of the community and environment likely to be adversely affected. The landscape and visual component of the EIA will identify any potential landscape and visual impacts during construction and upon completion, assess the scale and severity of such impacts and propose mitigation measures.
According to the study brief [1], the EIA study shall address the following aspects:
a) Air quality impact;
b) Noise impact;
c) Water quality impact;
d) Waste management implications;
e) Impact on cultural heritage;
f) Landscape and visual impact; and
g) Environmental Monitoring and Audit (EM&A) requirements.
A summary of the key information reviewed in this study is given below:
Description |
Date |
Final Assessment Report, West Kowloon to Tuen Mun Centre, Contract
No. TS-900 Environmental Impact Assessment Report |
Feb 1999 |
Final Assessment Report, Technical Annexes, Contract No. TS-900,
Environmental Impact Assessment |
Feb 1999 |
Environmental Monitoring and Audit Manual, West Kowloon to Tuen Mun
Centre, Contract TS-900, Environmental Impact Assessment |
Sept 1998 |
Archaeological Action Plan, Contract DD901, Environmental Support
Services |
Feb 1999 |
Essential Public Infrastructure Works, Final EIA Report, Contract No.
DD-901, Environmental Support Services |
May 1999 |
Supplement to the Archaeological Action Plan, The Au Tau Area,
Contract No DD-901, Environmental Support Services |
May 1999 |
Agreement No CE 66/96, Planning and Development Study on North West
New Territories, Environmental Assessment, Technical Paper No. 6, Report No.
0208/TEC/T6.1 |
Apr 1999 |
Agreement No CE 10/95, Tin Shui Wai Development, Engineering
Investigations for Development of Areas 3, 30 & 31 of the Development
Zone and the Reserve Zone, Final Investigation Report, Vol 1 - Main Text,
Executive Summary, EIA |
Mar 1997 |
Agreement No CE 12/97, Tin Shui Wai Further Development, Design and
Construction – Intensification of Areas 104 and 108b, Feasibility Assessment
on Noise, Air Quality and Solid Waste Impacts, 0188/ENG/R6.2 |
Jun 1998 |
Agreement No CE 12/97, Tin Shui Wai Further Development,
Intensification of Areas 104 and 108b, Final Report on Sewerage Impact
Assessment, 0188/ENG/R4.2 |
Jun 1998 |
Agreement No CE 12/97, Tin Shui Wai Further Development,
Intensification of Areas 104 and 108b, Final Report on Traffic Impact
Assessment, 0188/ENG/R5.2 |
Jun 1998 |
Lam Tei & Yick Yuen - Outline Zoning Plan, S/TM-LTYY/1 |
Jun 1996 |
Tuen Mun - Outline Zoning Plan, S/TM/11 |
Jan 1999 |
Table 4.1 : Summary of Available Key Information
The Air Pollution Control Ordinance (APCO) [3] requires that the impacts from all air pollutant emissions from industrial activities and other sources to comply with the Hong Kong Air Quality Objectives (HKAQO). The HKAQO stipulates a set of air quality objectives for 7 common air pollutants. The following table summarises the HKAQO.
|
Concentration in
micrograms per cubic metre (i) |
||||
Pollutant |
1
Hour (ii) |
8
Hour (iii) |
24
Hours (iii) |
3
Months (iv) |
1
Year (iv) |
Sulphur Dioxide |
800 |
|
350 |
|
80 |
Total Suspended Particulates |
500 |
|
260 |
|
80 |
Respirable Suspended Particulates (v) |
|
|
180 |
|
55 |
Carbon Monoxide |
30,000 |
10,000 |
|
|
|
Nitrogen Dioxide |
300 |
|
150 |
|
80 |
Photochemical Oxidants (as ozone) (vi) |
240 |
|
|
|
|
Lead |
|
|
|
1.5 |
|
Table 5.1: Hong Kong Air Quality Objectives
Notes: (i) Measured
at 298K(25 oC) and 101.325 kPa (one atmosphere).
(ii) Not
to be exceeded more than three times per year.
(iii) Not
to be exceeded more than once per year.
(iv) Yearly
and three monthly figures calculated as arithmetic means.
(v) Respirable
suspended particulates means suspended particles in air with nominal
aerodynamic diameter of 10 micrometres and smaller.
(vi) Photochemical
oxidants are determined by measurement of ozone only.
This regulation [4] stipulates the construction dust control requirements for both Notifiable (eg site formation) and Regulatory (eg road opening) Works to be carried out by the Contractor. The requirements for various Notifiable and Regulatory Works are given in Parts 1 & 2 of the Regulation respectively. Part 3 of the Regulation stipulates the general control requirements (eg site boundary and entrance) for construction dust. The control requirements for individual activities (eg stockpiling of dusty material) are given in Part 4 of the Regulation.
Except for the grade separation works in Tuen Mun, all the rail sections of the proposed alignment in Tin Shui Wai Reserve Zone will be at-grade. Site formation work has been completed and it is not necessary to conduct extensive excavation work.
For the at-grade section, the key construction activities to be carried out include minor site clearance, laying of ballast and track. These activities would not generate large amount of construction dust.
The grade separation works in Pui To Road and Tsing Lun Road would involve bore piling and the construction of superstructure for the viaduct. Again, these activities would not generate large amount of construction dust.
The Contractor is obliged to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation. This requirement should be incorporated by the Detailed Design Consultant (DDC) into the Particular Specification (PS) for the civil work. The PS should also draw the Contractor’s attention to the relevant latest Practice Notes issued by EPD.
The Contractor should also be requested to conduct an audit and monitoring programme during the construction stage to ensure the construction dust impacts are controlled with the HKAQO. Detailed requirements for the audit and monitoring programme are given in Section 12.
Construction air quality impact should be minor and effective control can be achieved by implementing the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation and an audit and monitoring programme.
Railway noise is controlled under the Noise Control Ordinance (NCO)[5] and the associated Technical Memorandum on Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (TM-Places) [14] .
The acceptable Noise Levels (ANLs) for different Area Sensitivity Ratings (ASRs) are summarised below:
ASR |
Time
Period (see Note 1) |
Acceptable Noise Levels
(ANL), L eq, 30 min |
A |
Day & evening |
60 dB(A) |
|
Night |
50 dB(A) |
B |
Day & evening |
65 dB(A) |
|
Night |
55 dB(A) |
C |
Day & evening |
70 dB(A) |
|
Night |
60 dB(A) |
Table 6.1: Acceptable Noise Levels (ANLs)
Note
1: Day
: 0700 to 1900 hours
Evening
: 1900 to 2300 hours
Night
: 2300 to 0700 hours
Additional corrections shall also be applied if the measured noise level is qualified for tonality and intermittency.
The TM-EIA [13] and HKPSG [19] also provide criteria for railway noise. These criteria are given below:
Parameters |
Criterion, dB(A) |
Ref |
Maximum A-weighted sound pressure level, Lmax (2300-0700hrs) |
85 |
TM-EIA |
Equivalent Continuous Sound Level, Leq (24 hours) |
65 |
HKPSG |
Table 6.2: Noise Criteria Stipulated in TM-EIA and HKPSG
Similar to railway noise, noise from associated fixed plant (eg rectifier station) is controlled by the NCO. In addition, according to TM-EIA, fixed plant noise should also be designed to be 5dB(A) below the ANL stipulated in the TM-Places. A summary of the noise limits for fixed plant is given in the following table.
|
|
Noise Limit, L eq,
30 min , dB(A) |
|
ASR |
Time
Period (see Note 1) |
ANL |
HKPSG |
A |
Day & evening |
60 |
55 |
|
Night |
50 |
45 |
B |
Day & evening |
65 |
60 |
|
Night |
55 |
50 |
C |
Day & evening |
70 |
65 |
|
Night |
60 |
55 |
Table 6.3: Noise Levels for Fixed Plant Noise
Note
1: Day
: 0700 to 1900 hours
Evening
: 1900 to 2300 hours
Night
: 2300 to 0700 hours
The study area for the noise impact assessment will include all noise sensitive receivers within 300m from the project boundaries. With the shielding from the first row of building blocks, the second row of NSRs will generally be protected. The assessment therefore focuses on the first row of NSRs that have direct line of sight to the operating trains within the project boundaries.
NSRs are chosen in accordance with Annex 13 of the TM-EIAO. Both existing and future planned uses will be included. The existing NSRs are identified through desktop review and site surveys. The planned NSRs are identified in the latest Outline Zoning Plans, and other building plans provided by Housing Authority (Appendix 3). The drawings in Appendix 2 illustrate the location plans and detailed descriptions of the NSRs proposed for the EIA study. A summary of these sensitive receivers is given below:
Works |
NSR / Use |
Horiz dist to rail / viaduct |
Remarks |
Tin Shui Wai
Reserve Zone |
Government /
Institution / Community (GIC) |
> 15m |
Subject to
detailed design by others |
|
Residential
areas |
15 – 60m |
With openable
windows |
Grade separation
work in Pui To Street |
School along
Pui To Road |
40m |
Provided with
A/C |
|
Residential
blocks |
10 – 40m |
With openable
windows |
Grade
separation work in Tsing Lun Road |
1-2 storey
houses |
> 20m |
With openable
windows |
Table 6.4: Summary of Noise Sensitive Receivers close to the Alignment
The building plans for some of the future residential areas in Tin Shui Wai Reserve Zone area are not available. In order to estimate the noise impacts on these areas, the nearest NSRs are assumed to be 15m from the site boundary, and with a view angle of 180m on the future LRT alignment.
Appendix 2 also presents the Area Sensitivity Ratings (ASRs) for the identified NSRs assumed for operational noise assessment. The ASRs for the NSRs are determined by reviewing the traffic flow data available, the TS-900 EIA report for West Rail and the existence of any Influencing Factors.
The following table summaries the ASRs for the identified NSRs.
NSRs
|
ASRs |
Residential houses near LT1, along Ng Lau Road in Lam Tei (within 100m from Tuen Mun Road) Residential blocks in Siu Hong Court near Lam Tei (within 100m from Tuen Mun Road) |
C |
Existing residential blocks along Pui To Road |
B |
Future top-side property in West Rail Tuen Mun Centre (within 100m from industrial area) |
C |
Future residential areas in Tin Shui Wai Reserve Zone |
B |
Table 6.5: Summary of Area Sensitivity Ratings for Identified NSRs
The ASRs assumed are indicative only based on the latest information available. It should be noted that fixed noise sources are controlled under Section 13 of the NCO. At the time of investigation, EPD will determine noise impact from concerned fixed noise sources on the basis of prevailing legislation and practices being in force, taking account of contemporary conditions / situations of adjoining land uses.
KCR has provided the train noise data in Lmax for LRV (both new and existing trains). The Lmax data has been converted to SEL using established train noise prediction methodology[25]. A summary of the noise data and the corresponding operating conditions is given below:
Parameters |
Noise Data / Operating Conditions |
Lmax |
: 65 dB(A) |
Track
form |
: Ballast track in well maintained condition |
Speed |
: 50kph |
Distance |
: 25m |
Length
of train |
: 40m (for 2-car trains) |
Table 6.6 Summary of Train Noise Data Provided by KCR
A 3dB(A) correction is included in the prediction model to allow for the rail deterioration.
The train speeds
for various rail sections are prepared by KCRC and LRT (Appendix 4). These speeds are the practical average
travel speed, taking into account the speed limits at junctions and across
roads.
The correction of Lmax for train speeds is based on the following equation [25]:
Change of Lmax
with speed = 30 log (V1 / V2) dB(A)
Where V1 and V2 are
the average train speeds.
The correction of Lmax for distance is based on the following equation:
Change of Lmax
with distance = 10 log (d1 / 25) dB(A)
Where d1 is the distance between
track and receiver.
Ballast track would be used for the track in Tin Shui Wai reserve Zone. For the grade separation works in Pui To Road, ballast track will be used except for the section directly underneath the deck of the future West Rail Tuen Mun Station. For the grade separate work in Tsing Lun Road, paved track will be used. The following corrections are applied for the reflection from the deck of viaduct.
· Viaduct with ballast track = 1.5dB(A)
· Viaduct without ballast track = 2.5dB(A)
There will be no cross-over in the proposed LRT. A 7dB(A) correction is included in the model to represent the argumentation in noise due to thermal expansion joints.
It has been advised by KCR that Continuously Welded Rail (CWR) will be adopted for the proposed LRT works. There would be neither thermal expansion joints nor structural breaks for the rail on viaduct.
Wheel squeal would occur when wheelset negotiate sharp curves. For non-resilient wheels, researches have indicated that it may have squeal when the radius of curvature is less than 100 times of the wheelbase [25]. Other study [31] has concluded that resilient wheels are effective measures to control wheel squeal noise. That report also quoted that the use of resilient wheels would control squeal noise for radius of curvature less than 30m.
It has been advised by KCR that both the existing and future LRT trains are provided with resilient wheels, with a wheelbase of about 1.9m. For a conservative assessment however, this assessment has incorporated wheel squeal correction of 3dB(A) for curves with radius of curvatures less than 200m (including temporary track). For NSRs within 25m from such a curve, an additional correction of 3dB(A) would be allowed.
The calculation of SEL from L max is based on the following equation [25] |
SEL = L max + 10 log (L/V) +10.5 –10 log (4D / (4D2+1) + 2 tan-1 (1/2D)) Where L = train length, m V = train speed, kph d = Distance from track, m D = d / L |
The predicted train frequencies (for before Year 2003 and up to Year 2011) during AM peak hour for various alignment sections has been provided by KCR . The train frequency for before Year 2003 will be adopted for the assessment on the temporary diversion in Pui To Road and Tsing Lun Road.
It has also been advised by LRT that the hourly train frequency during early morning before 0700 hours (ie 0630 to 0700 hours) would be 100% of the AM peak (Appendix 4). The train frequency during AM peak will therefore be adopted for the night-time noise assessment.
The correction of SEL for train frequency is calculated based on the following equation:
Change of SEL with train
frequency = 10 log (N1) dB(A)
Where N1 is the train frequency
for the rail segment.
The correction for view angles is based on the following equation:
Change of SEL with view
angle = 10 log (f/180) dB(A)
Where f is the view angle.
A 2.5dB(A) correction will be applied for all receivers to account for the façade reflection effect.
The proposed LRT alignments are arranged alongside the West Rail alignment in Tsing Lun Road, Lam Tei. For NSRs that are affected by both the LRT and West Rail alignments, additional noise contributions from West Rail has been included in the noise assessment to determine the cumulative noise impacts. The noise contributions from West Rail were extracted from the West Rail calculations (Appendix 5).
In order to estimate the magnitude of re-radiated noise from viaduct structure, noise measurements have been conducted to establish the noise re-radiated from existing LRT viaduct structures.
The location was close to Junction MJ9 (ie under the viaduct connecting Fung Tai Stop and Siu Hong Stop, and near Tuen Mun Government Primary School). The measurement location was directly underneath the existing concrete viaduct, with a head room of approximately 5-6m. Ballast track was installed. Trains were travelling at approximately 40-50kph.
The measured train noise levels are corrected to a distance of 25m (Figure 6.1) for comparison with the train noise data provided by KCR. A summary of the comparison is given below:
Location |
Measured L max, dB(A) |
Dist corr, dB(A) |
Corrected Lmax,
dB(A) |
LRT Noise Data, Lmax
dB(A) |
Near Tuen Mun Government Primary School |
60 – 63 |
-8 |
52 – 55 |
65 |
Table 6.7: Comparison of Measured Structure Re-radiated Noise and KCR’s Noise Data
The corrected structure re-radiated noise levels are at least 10dB(A) less than the noise data of 65dB(A) Lmax (at the reference conditions) provided by KCR. In this respect, the noise contribution from structure re-radiated noise from concrete viaduct structure would be more than 10dB(A) below the calculated airborne noise impacts. Since the cumulative noise impacts (ie with contributions from West Rail) will be controlled to within the ANL limits, the structure re-radiation noise would not have significant contributions on the cumulative noise impacts.
As advised by LRT, the definitions of Normal, Abnormal and Emergency Operations for LRT are as follows (see Appendix 6):
Normal The day-to-day operations without any interruption causing service delay.
Abnormal - The planned or expected event / happening which is not day-to-day or infrequent nature (eg engineering or operational adjustment catering for extended LRV services) or incidents resulting in service disruption less than 20 minutes).
Emergency - An unexpected occurrence that has environmental impact (eg spillage of chemical) or major incident as defined in the Procedure Manual of Contingencies.
Under the “Abnormal Operations”, the operation time of LRT will be extended from 0130 hours by another 1 –2 hours. These “Abnormal Operations” will occur during special periods (eg Chinese New Year and Christmas). Although the services period is extended in these occasions, the hourly train frequency will remain the same as that during “Normal” operation. The noise assessment during “Normal” operations will therefore also cover the “Abnormal” operation periods.
The controlling noise parameter would be the night-time noise impacts (ie Leq, 30 min) since the train frequency during early morning (ie 0630 to 0700) would be 100% of AM peak and the noise criterion before 0700 hours would be the one for night-time period. Given that the Lmax is only 65dB(A) at 25m from track, all the NSRs would not be exposed to noise levels exceeding the stipulated 85dB(A) Lmax criterion.
Air-borne rail noise prediction has been conducted according to the methodology described above. Appendix 7 presents a summary of the predicted cumulative train noise impacts.
Results indicate that the cumulative noise impacts (for year up to 2011) at all the NSRs would be within the stipulated noise limits. A summary of the predicted cumulative noise impacts for representative NSRs is given below (see Appendix 7 for details):
NSR |
Description |
Predicted
Noise Impacts, dB(A) |
Criteria,
dB(A) |
Compliance |
N105 |
TSW Area 31
Phase 1 Block 1 |
54 |
55 |
Yes |
N115 |
TSW Area 30
Block 4 |
54 |
55 |
Yes |
N123 |
TSW Area 102
Block 4 |
53 |
55 |
Yes |
N127 |
TSW Area 102
Block 15 |
52 |
55 |
Yes |
N130 |
TSW Area 102
Block 18 |
46 |
55 |
Yes |
N138 |
TSW Area 110
Phase 2 |
49 |
55 |
Yes |
N149 |
TSW Area 111
Block 1 |
52 |
55 |
Yes |
N151 |
TSW Area 111
Block 5 |
52 |
55 |
Yes |
N153 |
TSW Area 111
Block 9 |
52 |
55 |
Yes |
N45 |
Castle Peak
Catholic Primary School |
50* |
65 |
Yes |
N50 |
Tuen Mun Town
Plaza (Block 1) |
47* |
55 |
Yes |
N55 |
Tuen Mun Town
Plaza (Block 8) |
49* |
55 |
Yes |
N83 |
Future top-side
property in West Rail Tuen Mun Centre (within 100m from industrial area) |
55* |
60 |
Yes |
N48 |
Kam Wah Garden |
49* |
55 |
Yes |
N70 |
Residential
houses near LT1, along Ng Lau Road in Lam Tei (within 100m from Tuen Mun
Road) |
49* |
60 |
Yes |
N73 |
Yau Tze Tin
Memorial College |
54* |
65 |
Yes |
Table 6.8 : Summary of Predicted Cumulative Noise Impacts (up to 2011)
* with
West Rail contribution
During the construction period when temporary diversion at Pui To Road and LT1 are required, the predicted cumulative noise impacts are also within the criteria. The following table summaries the results.
Description |
Predicted Noise Impacts, dB(A) |
Criteria, dB(A) |
Compliance |
|
N70 |
Residential houses near LT1, along Ng Lau Road in
Lam Tei (within 100m from Tuen Mun Road) |
54* |
60 |
Yes
|
N45 |
Castle Peak Catholic Primary School |
50* |
65 |
Yes
|
N50 |
Tuen Mun Town Plaza (Block 1) |
48* |
55 |
Yes
|
N48 |
Kam Wah Garden |
49* |
55 |
Yes
|
Table 6.9 : Summary of Predicted Cumulative Noise Impacts (before 2003)
·
with West Rail contribution
The proposed LRT works include a rectifier station (ie R16 for Tin Shui Wai Reserve Zone) that is a potential fixed noise source. It has been advised that the transformer to be installed in the rectifier stations would be similar to those that have been currently installed in Tuen Mun and Tin Shui Wai areas. Transformer bays will be provided with a concrete cover and opened on one side. Other equipment (eg switching gears) will be accommodated in plant rooms.
Noise measurement results indicate that the outdoor transformers in existing rectifier stations would generate a noise level of 64 – 66dB(A) at a distance of 2m, when there are two transformers operating simultaneously. The measurements were taken during peak hour when the loading of the transformers was close to the maximum.
The assessment assumes “point source” dispersion with correction factors of 3dB(A) for tonality and 3dB(A) for façade effect. Possible screening effects from the rectifier station structure have not been included for a conservative assessment. All the transformers in the rectifier stations are assumed to be operating in the noise assessment.
The noise impacts caused by the transformers have been conducted based on the measured transformer noise levels and the methodology described above. Calculations indicated that the predicted noise impacts, based on the measured noise data for existing transformers, would be in the range of 41-47 dB(A) for the NSRs near R16. These noise levels are within the NCO-5 limit of 50dB(A). Calculations of noise impacts are presented in Appendix 9.
Although the predicted noise impacts are within the specified noise limits, the Detailed Design Consultant is still recommended to orientate the transformer bays in such a way that the open sides are not facing the nearest NSRs, and preferably facing onto a main road, if it is practicable.
Other potential noise sources in rectifier station include the ventilation system for switch rooms. It is recommended that a review to be conducted during the Detailed Design Stage to ensure that adequate noise attenuation treatments (eg silencers, acoustic louvres) are incorporated into the detailed design of the ventilation system to ensure compliance with the relevant noise criteria.
The findings of operational noise assessments indicate that there would not be any adverse impacts on the neighbouring NSRs. It is not required to implement specific noise mitigation measures for the proposed LRT Works. However, the following recommendations should be implemented during the design and operational stages of the proposed works.
· The railway operator should ensure that the worst-case noise level of 65 dB(A) Lmax at 25m from straight and well maintained ballast track is always achieved.
· The Detailed Design Consultant should ensure that the structure re-radiated noise from viaduct structure is at least 10dB(A) below the noise criteria of 65 dB(A) Lmax at 25m, at 50kph.
· The Detailed Design Consultant should ensure that the noise level at 2m from the transformer bays in the rectifier would be less than 66dB(A).
· The Detailed Design Consultant should orientate the open side of transformer bays in rectifier station to face away from the nearest NSRs, and preferably facing onto a main road, if practicable.
· The Detailed Design Consultant should conduct a detailed review on ventilation systems in the rectifier stations to determine the need for any noise attenuation (eg silencers, acoustic louvres etc).
Assessments of airborne noise and structure re-radiated noise have been conducted based on the train noise data provided by KCR and the methodology described in this section. Results indicate the cumulative noise impacts would be within the stipulated noise criteria. Recommendations are given for the railway operator and the Detailed Design Consultants to ensure compliance with the requirements given in TM-EIA.
Control over the generation of construction noise in Hong Kong is governed by the NCO[5] and the EIAO[2] and their subsidiary requirements. Various Technical Memoranda (TMs) have been issued under the NCO and the EIAO to stipulate control approaches and criteria. These TMs prescribe the maximum permitted noise levels for the use of Powered Mechanical Equipment (PME) and certain construction activities and processes, according to the type of equipment or activity, the perceived noise climate of the area, and the working hours of equipment operation and usage. The TMs applicable to the control of noise from construction activities in current proposed LRT works are:
· Technical Memorandum on Noise from Construction Work other than Percussive Piling [15] (TM-CW);
· Technical Memorandum on Noise from Construction Work in Designated Areas [16] (TM-DA); and
· Technical Memorandum on Environmental Impact Assessment Process [13] (TM-EIA).
Noise arising from general construction works during normal working hours is governed by the TM-EIA under the EIAO. The following table presents the recommended noise standards.
Uses |
Acceptable Noise Standards Leq (30mins), dB(A) |
All domestic premises including temporary housing accommodation |
75 |
Hotels and hostels |
75 |
Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required |
70 65 (During examinations) |
Note: The above standards
apply to uses which rely on opened windows for ventilation.
Table 7.1: Noise Standards for Daytime (0700 to 1900 hours) Construction Activities
In accordance with the TM-EIA, the noise criteria as laid down in the above table for the construction of designated project shall be met as far as practicable. All practicable mitigation measures shall be exhausted and the residual impacts are minimised.
The NCO provides statutory controls on general construction works during the restricted hours (ie 1900 to 0700 hours from Monday to Saturday and at any time on Sundays or public holidays). The use of Powered Mechanical Equipment (PME) for construction works during the restricted hours would require a Construction Noise Permit (CNP). The TM-CW details the procedures adopted by EPD for assessing such application. The granting of a CNP is subject to conditions stated in the permit and it may be revoked at any time for failure to comply with the stated conditions.
In addition to the general controls on the use of PME during the restricted hours, the use of Specified Powered Mechanical Equipment (SPME) and the undertaking of Prescribed Construction Work (PCW) during the restricted hours in a designated area are controlled by the TM-DA. Construction plant or equipment classified as SPME under the TM-DA includes hand-held breakers, bulldozers, concrete mixer lorries, dump trucks and poker vibrators. PCW includes the erection or dismantling of formwork or scaffolding, hammering, handling of rubble, wooden boards, steel bars, or scaffolding material, and the disposal of rubble through plastic chutes.
The TM-DA details the procedures that would generally be adopted by EPD for assessing the use of SPME during the restricted hours and for determining whether a CNP would be issued.
Maximum noise levels from construction activities during the restricted hours at affected NSRs are controlled under the TMs and shall not exceed the specified Acceptable Noise Levels (ANLs). These ANLs are stipulated in accordance with the Area Sensitivity Ratings (ASRs) established for the NSRs. The ANLs for construction works in designated areas are more stringent than those given in the TM-CW, as reflected from the corresponding Basic Noise Levels (BNLs) stated in the following table.
Time Period |
Area Sensitive Ratings |
||
A |
B |
C |
|
All weekdays during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the day and evening (0700 to 2300 hours) |
60(45) |
65(50) |
70(55) |
All days during the night-time (2300 to 0700 hours) |
45(30) |
50(35) |
55(40) |
Note: Figures in brackets are BNLs for
SPME construction work in designated areas
Table 7.2: BNLs for Construction Noise other than Percussive Piling
The eastern section of Pui To Road Grade Separation site (from Tuen Mun River Channel) lies within the Designated Area as defined in the Noise Control Designated Area Plan no. EPD/NP/KLN-01. Tin Shui Wai Reserve Zone Extension, LT1 Grade Separation and the western section of Pui To Road Grade Separation do not lie within the Designated Area.
Under the current plan of construction schedule from periods March 2001 to November 2003, the construction works would be carried out at normal working hours only (ie 0700 to 1900 hours on any day other than Sunday or public holiday) and it would not be required to carry out construction works during the restricted hours (ie 1900 to 0700 hours from Monday to Saturday and at any time on Sundays and public holidays). This assessment therefore focuses on the construction works during the normal working hours.
However, should construction works during restricted hours are found to be necessary, the Contractor shall apply for a Construction Noise Permit (CNP) from the Noise Control Authority. Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take into account of contemporary conditions/situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP. Nothing in this EIA Report shall bind the Noise Control Authority in making his decision. If a CNP is to be issued, the Noise Control Authority shall include in it any condition he thinks fit. Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.
The following procedures apply to the assessment of construction noise impacts:
· locate representative NSRs that may be affected by the works;
· determine plant items for corresponding construction activities based on the agreed plant inventories with KCRC;
· determine the sound power levels of the plant items according to the information stated in the TM-CW or other recognised sources of reference, where appropriate;
· calculate the correction factors based on the distance between the NSRs and the notional noise source positions of the work sites;
· apply corrections including façade, distance, barrier attenuation, acoustic reflection where applicable, in the calculations;
·
predict construction noise levels at the NSRs in the absence of any
mitigation measures;
·
conduct assessment of noise impacts at NSRs to quantify the level of
impact, in accordance with TM-CW.
An in-house program was used to facilitate the
analysis of the construction noise calculations. The initial program runs were conducted without any
mitigation measures. Where noise
level exceedances were identified, further runs were made assuming different
combinations of mitigation measures to be incorporated to control noise
impacts.
Where noise exceedances from assessment criteria were found at the NSRs, appropriate mitigation measures would be evaluated and recommended. A systematic approach to the evaluation of mitigation measures has been adopted, consisting of four levels of mitigation (and combination of each level) as described below.
Mitigation |
Description |
M1:
Level One |
Selection of quiet plant and working methods |
M2: Level Two |
Construction of temporary noise barriers |
M3: Level Three |
Delocalization of equipment and/or local reduction of number of plant items |
M4: Level Four |
Limiting equipment operating time |
Table 7.3: Construction Noise Mitigation Strategy
Some models of plant are quieter than the standard types listed in the TM-CW. Quiet plant is defined as PME whose actual SWL is less than the value specified in the TM-CW for the same piece of equipment. The benefits achieved in using quiet plant will depend on Contractor’s selection of working method. Examples of SWLs of specific silenced PME that may be used in the construction of the project worksites are given in BS5228 Part I, detailed in Section 7.3.5.3.
In general, noise barriers of 3 to 5 metres high located on site boundaries between noisy construction activities and NSRs could give up to 5-10 dB(A) reduction from screening. With careful consideration in the location of site access for the effectiveness of the barriers, barriers in the form of site hoardings could achieve this level of reduction. Certain types of PME, such as generators and compressors, can be partially or completely enclosed to give a total SWL reduction of 15-25 dB(A). Movable barriers that can be located close to noisy plant can also be very effective at screening NSRs from particular plant. This measure is particularly effective for low-rise noise sensitive premises or schools.
For the same set of plant items, delocalization of equipment or avoiding all equipment operating at the same site location would reduce the noise impact from construction activities on nearby NSRs. This approach is very effective for construction work site of linear shape. Delocalization of identical plant may include eg separating two dump trucks (or two concrete lorry mixers or two excavators) by more than 200m apart such that they would not be operated at the same working area. For the NSR close to the construction work site (less than 50m), the noise contribution from the distant PME would be insignificant.
Selection of the number and types of construction plant is usually left to the Contractor to allow flexibility in devising efficient working methodologies. However, in combination with the selection of quiet plant and noise barriers, limiting plant numbers may be required to provide further mitigation of construction noise levels at source in critical areas.
By restricting the percentage of operation of PME to 50% within 30-minute period, a noise reduction of 3 dB(A) could be achieved. Construction plant including dump truck may be used with careful attention to ensure that the engines are switched off or only idling at low power setting when not in direct use. For these PME the operating time should be carefully controlled so that they are only operating for 15 minutes in every consecutive 30-minute period.
NSRs have been identified in accordance with HKPSG
and the TM-EIA. A comprehensive list of all the identified NSRs for assessment
of operational noise impacts was prepared and presented in Appendix 2. These NSRs would also be affected by
the construction works during the construction stage. The worst affected NSRs during the construction phase of the
proposed LRT works have been considered.
The study areas will consist of three separated worksites. The three worksites that have been taken into consideration for the assessment are:
· Pui To Road Grade Separation (Worksite 1);
· LT1 Grade Separation (Worksite 2); and
· Tin Shui Wai Reserve Zone Extension (Worksite 3)
The landuses in the vicinity of the proposed alignment and LRT stops include schools and residential developments. The key representative NSRs for construction noise assessment are listed in the table. The separation distances of the NSRs to the construction sites are described in detail in Appendix 10.
Site
Area |
NSR |
Description |
Worksite 1- Pui To
Road Grade Separation |
N42# |
Fire Station and Ambulance |
N46 |
Top Court |
|
N47 |
Man Shing Building |
|
N48 |
Kam Wah Garden Block 1 |
|
N49 |
Kam Wah Garden Block 2 |
|
N50 |
Tuen Mun Town Plaza Block 1 |
|
N51 |
Tuen Mun Town Plaza Block 2 |
|
N53 |
Sun Court Podium |
|
N55 |
Tuen Mun Town Plaza Block 8 |
|
N200 |
San Fat Estate |
|
Worksite 2-LT1 Grade
Separation |
N64 |
2-storey residential house |
N65 |
3-storey residential house |
|
N66 |
Care Home for the Elderly |
|
N68 |
2-storey residential house |
|
N69 |
2-storey residential house |
|
N71 |
1-storey residential house |
|
N72 |
2-storey residential house |
|
N73 |
You Tze Tin Memorial
College |
|
N74 |
Siu Tai House |
|
N76 |
Siu Ping House |
|
Worksite 3- Tin Shui
Wai Reserve Zone |
N35 |
Shap Pat Heung Rural
Committee Kung Yik She Secondary School |
N38 |
Lynwood Court Block 10 |
|
N89 |
Tin Shui Wai Area 105 Phase
1 Block 5 |
|
N106 |
Tin Shui Wai Area 31 Phase
1 Block 2 |
|
N107 |
Tin Shui Wai Area 31 Phase
1 Block 3 |
|
N115 |
Tin Shui Wai Area 30 Block
4 |
|
N118 |
Tin Shui Wai Area 31 Phase
1 Primary School |
|
N120 |
Tin Shui Wai Area 31 Phase
2 Primary School |
|
N123 |
Tin Shui Wai Area 102 Phase
1 Block 4 |
|
N129 |
Tin Shui Wai Area 102 Phase 5 Block 17 |
|
N137 |
Tin Shui Wai Area 110 Phase
2 Block 11 |
|
N138 |
Tin Shui Wai Area 110 Phase
2 Block 10 |
|
N155 |
Tin Shui Wai Area 30 Phase
1 Block 6 Domestic (4/F-6/F) |
|
N155a |
Tin Shui Wai Area 30 Phase
1 Block 6 Kindergarten (3/F) |
# It was advised by the management of the
Fire Station and Ambulance that there were no staff quarters and residential
accommodations within the Fire Station area, and the Fire Station is not
considered as NSR in this assessment.
Table 7.4: Listing of Key Representative NSRs for Construction Noise Assessment
Potential impacts on NSRs during the construction
phase of the project will arise mainly from PME to be operated at the
construction worksites. The
proposed LRT alignment will be both at grade and elevated. The construction period would be from
March 2001 to November 2003 according to KCRC. The LRT extension and alteration construction works will
include the following key activities:
·
at-grade alignment construction;
·
standard viaduct construction (R.C. structure); and
·
LRT stop construction.
The activities that may introduce potential noise
impacts will include:
·
site clearance and formation activities where it is proposed that
excavator, vibratory rollers and dump trucks are used;
·
LRT stop construction where it is proposed to use concrete lorry mixers
and pokers;
·
track laying involving tampering machine and mobile crane operation;
·
piling where it is proposed to use reverse circulation drills, concrete
lorry mixers and pokers;
·
pile cap construction involving excavator/loader, concrete lorry mixer
and poker operations;
·
column construction where it is proposed to use concrete lorry mixers,
pokers and mobile cranes; and
·
superstructure construction where it is proposed to use concrete lorry
mixers, pokers and mobile cranes.
The construction of the proposed LRT works involves
different construction activities and plant at different stages. KCRC has provided construction plant
inventories with the necessary quantity of plant to carry out the construction
works. It is understood that the
use of these plant and equipment would be KCRC’s preferred approach to the
construction. Appendix 11 gives
details of these plant inventories and construction schedules. This construction noise assessment has
been based on these plant inventories for impact modelling.
A brief description of works to be undertaken at
each worksite and the total SWLs for the plant in the absence of any mitigation
measures are presented in the following table.
Site
Area |
Activity No. |
Construction
Activities Description |
Total Unmitigated SWL(1).
dB(A) |
Worksite 1 – Pui To Road Grade Separation |
1 |
Site Clearance (SCF) |
121 |
2 |
Piling (PIL) |
122 |
|
3 |
Pile Cap Construction (PCC) |
122 |
|
4 |
Backfilling (BF) |
119 |
|
5 |
Column Construction (CLC) |
122 |
|
6 |
Superstructure Construction (SSC) |
122 |
|
7 |
Track Laying (TRL) |
120 |
|
8 |
Installation of Overhead Line Cable (OLC) |
118 |
|
9 |
Site Reinstatement (SRE) |
121 |
|
10 |
Road Reinstatement (RRE) |
114 |
|
Worksite 2 – LT1 Grade Separation |
1 |
Site Clearance (SCF) |
121 |
2 |
Piling (PIL) |
122 |
|
3 |
Pile Cap Construction (PCC) |
122 |
|
4 |
Backfilling (BF) |
119 |
|
5 |
Column Construction (CLC) |
122 |
|
6 |
Superstructure Construction (SSC) |
123 |
|
7 |
Track Laying (TRL) |
120 |
|
8 |
Installation of Overhead Line Cable (OLC) |
118 |
|
9 |
Site Reinstatement (SRE) |
121 |
|
10 |
Road Reinstatement (RRE) |
114 |
|
Worksite 3 – Tin Shui Wai Reserve Zone
Extension |
1 |
Site Clearance and Formation (SCF) |
125 |
2 |
LRT Stop Construction (LSC) |
122 |
|
3 |
Backfilling (BF) |
119 |
|
4 |
Track Laying (TRL) |
120 |
|
5 |
Installation of Overhead Line Cable (OLC) |
119 |
[1]
Based on
KCRC’s plant inventories
Table 7.5: Total Unmitigated SWLs for Construction Activities
The construction works will generally be restricted
to normal daytime working hours.
Construction noise impacts are predicted in the following sections.
In accordance with the current construction
schedules of LRT and West Rail (Appendix 11), the two projects have no
over-lapping construction period except that the LRT site formation work at Pui To Road (ie LRT Tuen Mun Station
and San Fat LR Stop) would be
overlapping with beam erection and station construction of West Rail.
In order to address the cumulative noise impact from
West Rail construction during the overlapping period, all identified LRT NSRs
at Pui To Road have been detail examined with the EPD endorsed West Rail Final
EIA Report. This establishes the noise criteria for LRT construction such that
the overall construction noise level at all NSRs will be within the 75dB(A)
daytime construction noise limit. Table 7.7 below summarises the findings of
the examination.
NSR |
Description |
Maximum Noise Contribution from West Rail Construction, dB(A) |
Adopted
LRT Construction Noise Criteria, dB(A) |
N46 |
Top Court |
#71 |
73 |
N47 |
Man Shing Building |
#71 |
73 |
N48 |
Kam Wah Garden Block 1 |
#71 |
73 |
N49 |
Kam Wah Garden Block 2 |
#71 |
73 |
N50 |
Tuen Mun Town Plaza Block 1 |
#71 |
73 |
N51 |
Tuen Mun Town Plaza Block 2 |
#71 |
73 |
N53 |
Sun Court Podium |
#71 |
73 |
N55 |
Tuen Mun Town Plaza Block 8 |
#71 |
73 |
N200 |
San Fat Estate |
#75 |
- (Note 2) |
Note:
1.
The maximum
noise contributions from West Rail construction are taken from the Final EIA
Report for West Rail.
2.
It was
advised by Housing Department that San Fat Estate was
scheduled to evacuate by March 2001 whereas LRT
construction at that location would commence at April 2001. San Fat Estate is
therefore not considered as NSRs in the assessment.
Table 7.6: Cumulative Construction Noise Criteria
The adopted LRT construction noise criteria of
73dB(A) for the above NSRs may be relaxed with a detailed assessment on West
Rail construction plant schedule. It is recommended that such detailed
construction noise impact assessment be conducted during the construction stage
in order to allow more flexibility for the Contractor to select different plant
items to suit his own construction method and schedule.
Façade
noise levels at the NSRs were calculated [27] based on the SWLs and
corrections for distance attenuation given in the TM-CW. The predicted unmitigated maximum
noise levels at the key representative NSRs at ground level zone during the
construction phase of the LRT works are shown below.
NSR |
Description |
Activities in Each Construction Phase(1,2) |
||||||||||||
|
|
|
SCF |
LSC |
PIL |
PCC |
BF |
CLC |
SSC |
TRL |
OLC |
SRE |
RRE |
|
Worksite1-Pui To |
N46 |
Top
Court |
82 (9) |
- |
83 (10) |
83 (10) |
80 (7) |
83 (10) |
83 (10) |
81 (8) |
79 (6) |
82 (9) |
75 (2) |
|
Road Grade Separation |
N47 |
Man
Shing Building |
84 (11) |
- |
85 (12) |
85 (12) |
82 (9) |
85 (12) |
85 (12) |
83 (10) |
81 (8) |
84 (11) |
77 (4) |
|
|
N48 |
Kam
Wah Garden Block 1 |
85 (12) |
- |
86 (13) |
86 (13) |
83 (10) |
86 (13) |
86 (13) |
84 (11) |
82 (9) |
85 (12) |
78 (5) |
|
|
N49 |
Kam
Wah Garden Block 2 |
84 (11) |
- |
85 (12) |
85 (12) |
82 (9) |
85 (12) |
85 (12) |
83 (10) |
81 (8) |
84 (11) |
77 (4) |
|
|
N50 |
Tuen
Mun Town Plaza Block 1 |
90 (17) |
- |
91 (18) |
91 (18) |
88 (15) |
91 (18) |
91 (18) |
89 (16) |
87 (14) |
90 (17) |
83 (10) |
|
|
N51 |
Tuen
Mun Town Plaza Block 2 |
83 (10) |
- |
84 (11) |
84 (11) |
81 (8) |
84 (11) |
84 (11) |
82 (9) |
80 (7) |
83 (10) |
76 (3) |
|
|
N53 |
Sun
Court Podium |
85 (12) |
- |
86 (13) |
86 (13) |
83 (10) |
86 (13) |
86 (13) |
84 (11) |
82 (9) |
85 (12) |
78 (5) |
|
|
N55 |
Tuen
Mun Town Plaza Block 8 |
86 (13) |
- |
87 (14) |
87 (14) |
84 (11) |
87 (14) |
87 (14) |
85 (12) |
83 (10) |
86 (13) |
79 (6) |
|
|
N200 |
San
Fat Estate |
84 (11) |
- |
84 (11) |
84 (11) |
82 (9) |
84 (11) |
84 (11) |
83 (10) |
81 (8) |
84 (11) |
77 (4) |
|
Worksite2-LT1 |
N64 |
2-storey
residential house |
76 (1) |
- |
77 (2) |
77 (2) |
74 (0) |
77 (2) |
78 (3) |
75 (0) |
73 (0) |
76 (1) |
69 (0) |
|
Grade Separation |
N65 |
3-storey
residential house |
82 (7) |
- |
83 (8) |
83 (8) |
80 (5) |
83 (8) |
84 (9) |
81 (6) |
79 (4) |
82 (7) |
75 (0) |
|
|
N66 |
Care
Home for the Elderly |
74 (0) |
- |
75 (0) |
75 (0) |
72 (0) |
75 (0) |
76 (1) |
73 (0) |
71 (0) |
74 (0) |
67 (0) |
|
|
N68 |
2-storey
residential house |
71 (0) |
- |
72 (0) |
72 (0) |
69 (0) |
72 (0) |
73 (0) |
70 (0) |
68 (0) |
71 (0) |
64 (0) |
|
|
N69 |
2-storey
residential house |
88 (13) |
- |
89 (14) |
89 (14) |
86 (11) |
89 (14) |
90 (15) |
87 (12) |
85 (10) |
88 (13) |
81 (6) |
|
|
N71 |
1-storey
residential house |
88 (13) |
- |
89 (14) |
89 (14) |
86 (11) |
89 (14) |
90 (15) |
87 (12) |
85 (10) |
88 (13) |
81 (6) |
|
|
N72 |
2-storey
residential house |
70 |
- |
71 |
71 |
68 |
71 |
72 |
69 |
67 |
70 |
63 |
|
|
N73 |
You
Tze Tin Memorial College |
74 (4) |
- |
75 (5) |
75 (5) |
72 (2) |
75 (5) |
76 (6) |
73 (3) |
71 (1) |
74 (4) |
67 (0) |
|
|
N74 |
Siu
Tai House |
77 (2) |
- |
78 (3) |
78 (3) |
75 (0) |
78 (3) |
79 (4) |
76 (1) |
74 (0) |
77 (2) |
70 (0) |
|
|
N76 |
Siu
Ping House |
80 (5) |
- |
81 (6) |
81 (6) |
78 (3) |
81 (6) |
82 (7) |
79 (4) |
77 (2) |
80 (5) |
73 (0) |
|
Worksite3-Tin Shui Wai
Reserve zone |
N35 |
Shap
Pat Heung Rural Committee Kung Yik She Secondary School |
76 |
73 |
- |
- |
70 |
- |
- |
71 |
70 |
- |
- |
|
Extension |
N38 |
Lynwood
Court Block 10 |
76 (1) |
73 (0) |
- |
- |
70 (0) |
- |
- |
71 (0) |
70 (0) |
- |
- |
|
|
N89 |
Tin
Shui Wai Area 105 Phase 1 Block 5 |
81 (6) |
78 (3) |
- |
- |
75 (0) |
- |
- |
76 (1) |
75 (0) |
- |
- |
|
|
N106 |
Tin
Shui Wai Area 31 Phase 1 Block 2 |
78 (3) |
75 (0) |
- |
- |
72 (0) |
- |
- |
73 (0) |
72 (0) |
- |
- |
|
|
N107 |
Tin
Shui Wai Area 31 Phase 1 Block 3 |
79 (4) |
76 (1) |
- |
- |
73 (0) |
- |
- |
74 (0) |
73 (0) |
- |
- |
|
|
N115 |
Tin
Shui Wai Area 30 Block 4 |
81 (6) |
78 (3) |
- |
- |
75 (0) |
- |
- |
76 (1) |
75 (0) |
- |
- |
|
|
N118 |
Tin
Shui Wai Area 31 Phase 1 Primary School |
82 (12) |
79 (9) |
- |
- |
76 (6) |
- |
- |
77 (7) |
76 (6) |
- |
- |
|
|
N120 |
Tin
Shui Wai Area 31 Phase 2 Primary School |
89 (19) |
86 (16) |
- |
- |
83 (13) |
- |
- |
84 (14) |
83 (13) |
- |
- |
|
|
N123 |
Tin
Shui Wai Area 102 Phase 1 Block 4 |
85 (10) |
82 (7) |
- |
- |
79 (4) |
- |
- |
80 (5) |
79 (4) |
- |
- |
|
|
N129 |
Tin
Shui Wai Area 102 Phase 5 Block 17 |
85 (10) |
82 (7) |
- |
- |
79 (4) |
- |
- |
80 (5) |
79 (4) |
- |
- |
|
|
N137 |
Tin
Shui Wai Area 110 Phase 2 Block 11 |
83 (8) |
80 (5) |
- |
- |
77 (2) |
- |
- |
78 (3) |
77 (2) |
- |
- |
|
|
N138 |
Tin
Shui Wai Area 110 Phase 2 Block 10 |
80 (5) |
77 (2) |
- |
- |
74 (0) |
- |
- |
75 (0) |
74 (0) |
- |
- |
|
|
N155 |
Tin
Shui Wai Area 30 Phase 1 Block 6 Domestic (4/F-6/F) |
87 (12) |
84 (9) |
- |
- |
81 (6) |
- |
- |
82 (7) |
81 (6) |
- |
- |
|
|
N155a |
Tin Shui Wai Area 30 Phase
1 Block 6 Kindergarten (3/F) |
87 (17) |
84 (14) |
- |
- |
81 (11) |
- |
- |
82 (12) |
81 (11) |
- |
- |
|
Note:
(1) SCF : Site Clearance & Formation; LSC: LRT Stop Construction; PIL: Piling; PCC: Pile Cap Construction; BF: Backfilling; CLC: Column Construction; SSC: Superstructure Construction; TRL: Track Laying; OLC: Installation of Overhead Line Cable; SRE: Site Reinstatement; RRE: Road Reinstatement.
(2) Exceedances from daytime noise criteria (Table 7.1) are shown with brackets
Table 7.7: Unmitigated Predicted Noise Levels at Ground Level Zone of NSRs
The noise impacts at 5th floor level, 10 floor level up to 30 floor level in 5 floor level steps are also predicted, where appropriate for each NSR. Detailed analysis indicates that the predicted unmitigated maximum noise exceedances are between ground level and 5th floor level. Depending on distance and elevation of the NSR under consideration, the noise impact reduces by between 1 to 4 dB(A) for every 5 storeys.
Predicted unmitigated construction noise levels at the NSRs are shown in Table 7.7. It should be noted that the noise levels represent worst case scenarios, since the calculations assume that all of the available plant items for a phase of works are in use for 100% of the time. In practice this is unlikely to be the case as a number of plant items will operate sequentially with spatial constraints within the work site, and all equipment items would unlikely be operated at the same location. As will be seen later, these constraints are recommended as part of the noise mitigation control strategy (M3 and M4) at some critical NSRs.
During the construction of Pui To Road Grade Separation, adverse construction noise impacts would be likely at Tuen Mun Town Plaza Block 1 (N50) due to the limited buffer distances. Site clearance, pile cap construction, column and superstructure constructions all involve use of noisy Powered Mechanical Equipment. Other areas of significant noise impacts include Top Court (N46), Man Shing Building (N47), Kam Wah Garden (N48 and N49), Tuen Mun Town Plaza Block 2 (N51), Sun Court Podium (N53) and Tuen Mun Town Plaza (N55).
The affected floors would include low level, mid-level and high level floors. For N50 Tuen Mun Plaza Block 1, the noise exceedances in these floors are 13~16 dB(A), 10~12 dB(A) and 5~8 dB(A) respectively [27].
The worst affected NSRs would include the ground level and the 5th floor level, as the construction works would involve plant operation at an elevation.
The range of construction noise impacts would be 1 to 16 dB(A) exceeding the daytime criteria. The predicted worst NSRs include Tuen Mun Town Plaza Block 1 (N50).
Adverse construction noise impacts would be anticipated at the low-rise residential houses (N69 and N71), primarily during site clearance, piling and pile cap construction, column and superstructure construction. A maximum noise level of 90 dB(A) was predicted at the 2-storey residential house (N69 and N71) with exceedance of 15 dB(A) above daytime construction noise criterion.
The majority of NSRs that is likely to be affected include low-rise residential houses. The high-rise building blocks including Siu Tai House and Siu Ping House (N74 and N76) will also be affected. The affected floors of these NSRs would include low level floor, mid-level floor and high-level floor. The noise exceedances in these floors are 4~7 dB(A), 3~6 dB(A) and 1~4 dB(A) respectively [27].
Exceedances of up to 19 dB(A) at the key representative NSRs were predicted within this section of LRT Reserve Zone Extension. The impacted areas shall include Kung Yik She Secondary School (N35), Lynwood Court Block 10 (N38), Tin Shui Wai Area 105 Phase 1 Block 5 (N89), Tin Shui Wai Area 31 Phase 1 Blocks 2 & 3 (N106 and N107), Tin Shui Wai Area 30 Block 4 (N115), Tin Shui Wai Area 31 Phases 1 & 2 Primary Schools (N118 and N120), Tin Shui Wai Area 102 Phase 1 Block 4 (N123), Tin Shui Wai Area 102 Phase 5 Block 17 (N129), Tin Shui Wai Area 110 Phase 2 Block 11 (N137) and Tin Shui Wai Area 110 Phase 2 Block 10 (N138). Adverse construction noise impacts would be anticipated at Tin Shui Wai Area 31 Phases 1 & 2 Primary Schools (N118 and N120).
The affected flats would include NSRs at all floor levels. For the high-rise residential blocks N38, N89, N106, N107 and N115, the noise exceedances in low-level, mid-level and high level floors are 3~10 dB(A), 5~10 dB(A) and 3~7 dB(A) respectively.
The predicted noise levels show that unmitigated
construction activities are likely to give rise to adverse daytime noise
impacts at the majority of the NSRs in the vicinity of the proposed alignment,
and mitigation measures are therefore required. Noise emissions from construction sites could be minimised
by the following means:
· use of good site practices to limit noise emissions at the source;
· scheduling of construction works outside school examination periods in critical areas;
· use of “quiet PME” and working methods (M1);
· use of site hoarding as noise barriers (with careful design) to screen noise at ground level zone (M2);
· use of permanent, temporary and movable noise barriers (M2);
· delocalization of equipment and/or local reduction of the number of plant to be used on site, where practicable (M3); and
· limiting the operating time of construction equipment on site and use of smaller equipment (M4).
Based on the analysis of unmitigated impacts, the maximum allowable total sound power levels generated from plant items during daytime construction works (ie 0700 to 1900 hours) are derived, where maximum noise exceedance are predicted. The sound power level limits for the key representative NSRs are summarised in the table below.
NSR |
Description |
Activities in Each Construction Phase(1,2) |
||||||||||||
|
|
|
SCF |
LSC |
PIL |
PCC |
BF |
CLC |
SSC |
TRL |
OLC |
SRE |
RRE |
|
Worksite1- |
N46 |
Top
Court |
112 |
- |
112 |
112 |
112 |
112 |
112 |
112 |
112 |
112 |
112 |
|
Pui To Road |
N47 |
Man
Shing Building |
110 |
- |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
|
Grade Separation |
N48 |
Kam
Wah Garden Block 1 |
109 |
- |
109 |
109 |
109 |
109 |
109 |
109 |
109 |
109 |
109 |
|
|
N49 |
Kam
Wah Garden Block 2 |
110 |
- |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
|
|
N50 |
Tuen
Mun Town Plaza Block 1 |
104 |
- |
104 |
104 |
104 |
104 |
104 |
104 |
104 |
104 |
104 |
|
|
N51 |
Tuen
Mun Town Plaza Block 2 |
111 |
- |
111 |
111 |
111 |
111 |
111 |
111 |
111 |
111 |
111 |
|
|
N53 |
Sun
Court Podium |
109 |
- |
109 |
109 |
109 |
109 |
109 |
109 |
109 |
109 |
109 |
|
|
N55 |
Tuen
Mun Town Plaza Block 8 |
108 |
- |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
|
|
N200 |
San
Fat Estate |
110 |
- |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
110 |
|
Worksite2-LT1
Grade |
N64 |
2-storey
residential house |
120 |
- |
120 |
120 |
120 |
120 |
120 |
120 |
120 |
120 |
120 |
|
Separation |
N65 |
3-storey
residential house |
114 |
- |
114 |
114 |
114 |
114 |
114 |
114 |
114 |
114 |
114 |
|
|
N66 |
Care
Home for the Elderly |
122 |
- |
122 |
122 |
122 |
122 |
122 |
122 |
122 |
122 |
122 |
|
|
N68 |
2-storey
residential house |
125 |
- |
125 |
125 |
125 |
125 |
125 |
125 |
125 |
125 |
125 |
|
|
N69 |
2-storey
residential house |
108 |
- |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
|
|
N71 |
1-storey
residential house |
108 |
- |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
108 |
|
|
N72 |
2-storey
residential house |
126 |
- |
126 |
126 |
126 |
126 |
126 |
126 |
126 |
126 |
126 |
|
|
N73 |
You
Tze Tin Memorial College |
117 |
- |
117 |
117 |
117 |
117 |
117 |
117 |
117 |
117 |
117 |
|
|
N74 |
Siu
Tai House |
119 |
- |
119 |
119 |
119 |
119 |
119 |
119 |
119 |
119 |
119 |
|
|
N76 |
Siu
Ping House |
116 |
- |
116 |
116 |
116 |
116 |
116 |
116 |
116 |
116 |
116 |
|
Worksite3-
Tin Shui Wai Reserve Zone Extension |
N35 |
Shap
Pat Heung Rural Committee Kung Yik She Secondary School |
114 |
114 |
- |
- |
114 |
- |
- |
114 |
114 |
- |
- |
|
|
N38 |
Lynwood
Court Block 10 |
119 |
119 |
- |
- |
119 |
- |
- |
119 |
119 |
- |
- |
|
|
N89 |
Tin
Shui Wai Area 105 Phase 1 Block 5 |
114 |
114 |
- |
- |
114 |
- |
- |
114 |
114 |
- |
- |
|
|
N106 |
Tin
Shui Wai Area 31 Phase 1 Block 2 |
117 |
117 |
- |
- |
117 |
- |
- |
117 |
117 |
- |
- |
|
|
N107 |
Tin
Shui Wai Area 31 Phase 1 Block 3 |
116 |
116 |
- |
- |
116 |
- |
- |
116 |
116 |
- |
- |
|
|
N115 |
Tin
Shui Wai Area 30 Block 4 |
114 |
114 |
- |
- |
114 |
- |
- |
114 |
114 |
- |
- |
|
|
N118 |
Tin
Shui Wai Area 31 Phase 1 Primary School |
108 |
108 |
- |
- |
108 |
- |
- |
108 |
108 |
- |
- |
|
|
N120 |
Tin
Shui Wai Area 31 Phase 2 Primary School |
101 |
101 |
- |
- |
101 |
- |
- |
101 |
101 |
- |
- |
|
|
N123 |
Tin
Shui Wai Area 102 Phase 1 Block 4 |
110 |
110 |
- |
- |
110 |
- |
- |
110 |
110 |
- |
- |
|
|
N129 |
Tin
Shui Wai Area 102 Phase 5 Block 17 |
110 |
110 |
- |
- |
110 |
- |
- |
110 |
110 |
- |
- |
|
|
N137 |
Tin
Shui Wai Area 110 Phase 2 Block 11 |
112 |
112 |
- |
- |
112 |
- |
- |
112 |
112 |
- |
- |
|
|
N138 |
Tin
Shui Wai Area 110 Phase 2 Block 10 |
115 |
115 |
- |
- |
115 |
- |
- |
115 |
115 |
- |
- |
|
|
N155 |
Tin
Shui Wai Area 30 Phase 1 Block 6 Domestic (4/F-6/F) |
108 |
108 |
- |
- |
108 |
- |
- |
108 |
108 |
- |
- |
|
|
N155a |
Tin Shui Wai Area 30 Phase
1 Block 6 Kindergarten (3/F) |
103 |
103 |
- |
- |
103 |
- |
- |
103 |
103 |
- |
- |
|
Table 7.8: Maximum Allowable Sound Power Levels
Note:
(1)
SCF : Site
Clearance & Formation; LSC: LRT Stop Construction; PIL: Piling; PCC: Pile
Cap Construction; BF: Backfilling; CLC: Column Construction; SSC:
Superstructure Construction; TRL: Track Laying; OLC: Installation of Overhead
Line Cable; SRE: Site Reinstatement; RRE: Road Reinstatement.
(2) Sound Power Levels in dB(A).
The above table gives guidance on the total allowable sound powers emitted from unmitigated plant items in different work areas to NSRs. The recommended control philosophies detailed in this section should be incorporated into the Contract Specification and developed in the Implementation Schedule in order to ensure the acceptable environmental performance of construction works will be complied.
The following illustrates a feasible approach to mitigate the predicted noise impacts during the construction phase. It is possible that the Contractor may develop a different package of environmental control measures to meet the required noise standards. Proposed alternative mitigation measures shall be demonstrated to meet or achieve better performances and in full compliance with the TM-EIA noise criteria and compatible with the construction programme.
Good site practice and noise management could
considerably reduce the noise impact from construction site activities on
nearby NSRs. The following
measures should be followed during each phase of construction:
· only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme;
· machines and plant (such as trucks, cranes) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
· plant known to emit noise strongly in one direction, where possible, be orientated so that the noise is directed away from nearby NSRs;
· silencers or mufflers on construction equipment should be properly fitted and maintained during the construction works;
· mobile plant should be sited as far away from NSRs as possible and practicable; and
· material stockpiles, mobile container site office and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
The noise benefits of these techniques can vary according to specific site conditions and operations. The environmental noise climate would certainly be improved through these control practices, although the improvement can only be quantified during implementation when specific site parameters are known.
During school examination periods, the daytime construction noise criterion is 65 dB LAeq, 30 min. which is lower than the normal daytime school criterion (70 dB LAeq, 30 min.) by 5 dB(A). In critical areas, scheduling of construction works outside school examination period to less intrusive periods would definitely reduce the noise impacts on the NSRs and this also relieves the need to incorporate more stringent noise mitigation measures required to ensure compliance with the construction noise criteria.
The use of quiet plant is identified as a feasible
solution to tackle adverse noise impacts associated with the construction
works. It is generally known
(supported by field measurement) that particular models of construction
equipment are quieter than standard types given in the TM-CW. Whilst it is generally considered too
restrictive to specify that the Contractor has to use specific models or items
of plant, it is reasonable and practicable to set plant noise performance
specifications for specific PME so that some flexibility in selection of plant
is allowed. A pragmatic approach
would be to request that the Contractor independently verifies the noise level
of the plant proposed to be used and demonstrates through furnishing of these
results, that the plant proposed to be used on the site meets the requirements.
The benefits achievable in this way can be
considerable but will depend on the level of control given to the project
engineer under the contract conditions and the ability and willingness to use
these powers to control the level of environmental noise.
BS5228[20] contains examples of SWLs for
specific silenced PME. Examples
known to be available are given in table below. The total SWLs for each construction activity with the
suggested “quieter” PMEs are detailed in Appendix 12.
Power
Mechanical Equipment (PME) |
Power Rating and/or size |
BS5228 Table No. |
Maximum SWL, dB(A) |
CNP Reference in TM-CW |
SWL in TM-CW |
Asphalt
Paver |
13t |
C8 |
(101) |
CNP004 |
109 |
Concrete
Lorry Mixer |
5m3 |
C6 |
(100) |
CNP044 |
109 |
Dump
Truck |
35
t |
C9 |
(109) |
CNP067 |
117 |
Excavator |
45kW |
C3 |
(106) |
CNP081 |
112 |
Excavator
(idling) |
73kW |
C3 |
96 |
CNP081 |
112 |
Lorry |
35t |
C3 |
(105) |
CNP141 |
112 |
Mobile
Crane |
56kW |
C7 |
(106) |
CNP048 |
112 |
Mobile Crane (idling) |
56kW |
C7 |
99 |
CNP048 |
112 |
Poker
vibrator |
2kW |
C6 |
(102) |
CNP170 |
113 |
Vibratory
Roller |
9kW,
7000kg |
C3 |
(102) |
CNP186 |
113 |
Note: Bracket indicates SWLs
being used in the calculations of mitigated noise levels.
Table 7.9: Listing of “Quiet” Equipment
It should be noted that while various types of silenced equipment could be found in Hong Kong, however, the EPD when processing a CNP application for evening or night time works may apply the noise levels specified in the TM-CW and TM-DA, unless the noise emission of a particular piece of equipment can be validated by certified site measurement or demonstration.
Purpose built temporary noise barriers 3 to 5m high located on the site boundaries between noisy construction activities and NSRs could generally reduce noise levels by up to 5-10 dB(A) through partial screening. It would be possible for the Contractor to provide these in the form of site hoardings to achieve this attenuation effect, provided that the barriers have no openings or gaps and have a superficial surface density of at least 7kg/m2.
Given that the LRT worksite is linear in shape, a 3.5m high site hoarding of adequate surface mass could provide partial screening to NSRs at lower floors from construction works at grade. In general this would provide minimum 5 dB(A) attenuation. This has been assumed in the calculations for low level NSRs provided that the construction activities are at grade. Given the detailed information of site boundary wall and the geometry between the NSRs and the noise sources, the designs of the hoarding can be worked out to meet these requirements or achieve better screening effect.
Movable noise barriers that can be located close to noisy plant and be moved iteratively with the plant along a worksite can be very effective at screening noise from NSRs. A typical design which has been used in Hong Kong is a 3.5 m high wooden framed barrier with a small cantilevered upper portion of superficial density no less than 7kg/m2 on a skid footing with 25mm thick internal sound absorptive lining. Barriers of this type can be placed within a short distance from mobile plant such as an excavator, mobile crane etc.
Where these screening effects can be achieved at upper floors of NSRs, greater benefits would result at lower floors. To affect noise screening to NSR at high level e.g. 5 to 15-storey zones, cantilevered top cover would be required.
It is anticipated that suitably-designed noise barriers could achieve up to 10 dB(A) for static plant and 5dB(A) noise reduction for mobile plant. The noise screening benefit for the plant items considered in this assessment is as follows:
· stationary plant – 10 dB(A) screening for PME e.g. air compressor, stressing rig, water pump, concrete pump, generator, hand-held pneumatic breaker, poker vibrator; and
· mobile plant – 5 dB(A) screening for PME e.g. excavator, roller, dump truck, concrete lorry mixer and mobile crane.
Any barriers designed by the Contractor should satisfy this noise performance in order to control the emission of noise from PME. The Contractor should pay particular attention to ensure barriers are close fitting around plant items thereby gaining greater noise reduction benefit.
For the same set of plant items, delocalization of equipment or avoiding all equipment operating at the same site location would reduce the noise impact from construction activities on nearby NSRs. Inspection of maximum noise exceedance calculations indicate the critical NSRs would be within 50m from the construction worksites. For two identical plant items at distance 200m apart, this would provide minimum 3 dB(A) or even more noise attenuation. In this assessment, 3 dB(A) noise reduction for concrete lorry mixer, excavator, dump truck, mobile crane, piling (reserve circulating drill) and poker is assumed to take into this factor, where required.
In general the selection of the numbers of plant should be left to the Contractor so that in combination with the selection of quiet plant, any further reduction in the total plant noise levels, or the site specific maximum sound power levels can be achieved. This method could be more effective for activities associated with the use of dump trucks and excavators, where limiting operating plant items would be a practicable measure.
In locations where adverse noise impacts may arise, it would be appropriate to restrict the usage of particular noisy equipment operating within certain parts of the site that are very close to the NSRs. The percentage of time that the noisy equipment is allowed in operation may also need to be controlled so as to reduce the noise emissions during critical construction stages.
By restricting the percentage of operation of PME to 50% within 30-minute period, a noise reduction of 3 dB(A) could be achieved. In the assessment, this attenuation has been assumed for dump trucks in critical areas where M4 mitigation control is required. The dump trucks are only operating for 15 minutes in every consecutive 30-minute period.
KCRC has confirmed that the above mitigation measures M1 to M4 as being practicable in completing the construction work on schedule. The noise mitigation measures described above regarding the use of quiet plant, noise barrier, equipment delocalization, local reduction of plant items and/or limiting operation time have been applied and the resultant noise levels with mitigation measures are shown in the table below.
NSR |
Description |
Activities in Each Construction Phase(1,2) |
||||||||||||
|
|
|
SCF |
LSC |
PIL |
PCC |
BF |
CLC |
SSC |
TRL |
OLC |
SRE |
RRE |
|
Worksite1-Pui
To |
N46 |
Top
Court |
73 (0) M3 |
- |
72 (0) M1 |
72 (0) M2 |
70 (0) M1 |
73 (0) M1 |
73 (0) M2 |
73 (0) M2 |
70 (0) M1 |
73 (0) M2 |
72 (0) M2 |
|
Road Grade Separation |
N47 |
Man
Shing Building |
72 (0) M2 |
- |
73 (0) M2 |
73 (0) M2 |
72 (0) M1 |
73 (0) M2 |
73 (0) M2 |
73 (0) M2 |
72 (0) M1 |
73 (0) M3 |
72 (0) M2 |
|
|
N48 |
Kam
Wah Garden Block 1 |
73 (0) M2 |
- |
73 (0) M2 |
73 (0) M2 |
73 (0) M1 |
73 (0) M2 |
73 (0) M2 |
73 (0) M2 |
73 (0) M1 |
73 (0) M3 |
73 (0) M2 |
|
|
N49 |
Kam
Wah Garden Block 2 |
72 (0) M2 |
- |
73 (0) M2 |
73 (0) M2 |
72 (0) M1 |
73 (0) M2 |
73 (0) M2 |
73 (0) M2 |
72 (0) M1 |
73 (0) M3 |
72 (0) M2 |
|
|
N50 |
Tuen
Mun Town Plaza Block 1 |
73 (0) M3 |
- |
73 (0) M3 |
73 (0) M4 |
73 (0) M2 |
73 (0) M4 |
73 (0) M4 |
73 (0) M3 |
73 (0) M2 |
72 (0) M3 |
73 (0) M4 |
|
|
N51 |
Tuen
Mun Town Plaza Block 2 |
73 (0) M2 |
- |
73 (0) M1 |
73 (0) M2 |
71 (0) M1 |
73 (0) M2 |
73 (0) M2 |
73 (0) M3 |
71 (0) M1 |
73 (0) M2 |
73 (0) M2 |
|
|
N53 |
Sun
Court Podium |
73 (0) M2 |
- |
73 (0) M2 |
73 (0) M2 |
73 (0) M1 |
73 (0) M2 |
73 (0) M2 |
73 (0) M2 |
73 (0) M1 |
73 (0) M3 |
73 (0) M2 |
|
|
N55 |
Tuen
Mun Town Plaza Block 8 |
73 (0) M2 |
- |
73 (0) M2 |
73 (0) M4 |
73 (0) M2 |
73 (0) M2 |
73 (0) M3 |
73 (0) M3 |
72 (0) M4 |
73 (0) M4 |
73 (0) M2 |
|
|
N200 |
San
Fat Estate |
72 (0) M2 |
- |
73 (0) M2 |
73 (0) M2 |
72 (0) M1 |
73 (0) M2 |
73 (0) M2 |
73 (0) M2 |
72 (0) M1 |
73 (0) M3 |
72 (0) M2 |
|
Worksite2-LT1
Grade Separation |
N64 |
2-storey
residential house |
67 (0) M1 |
- |
66 (0) M1 |
67 (0) M1 |
74 (0) M0 |
67 (0) M1 |
71 (0) M1 |
75 (0) M0 |
73 (0) M0 |
69 (0) M1 |
69 (0) M0 |
|
|
N65 |
3-storey
residential house |
73 (0) M1 |
- |
72 (0) M1 |
73 (0) M1 |
70 (0) M1 |
73 (0) M1 |
74 (0) M2 |
74 (0) M1 |
70 (0) M1 |
75 (0) M1 |
75 (0) M0 |
|
|
N66 |
Care
Home for the Elderly |
74 (0) M0 |
- |
75 (0) M0 |
75 (0) M0 |
72 (0) M0 |
75 (0) M0 |
69 (0) M1 |
73 (0) M0 |
71 (0) M0 |
74 (0) M0 |
67 (0) M0 |
|
|
N68 |
2-storey
residential house |
71 (0) M0 |
- |
72 (0) M0 |
72 (0) M0 |
69 (0) M0 |
72 (0) M0 |
73 (0) M0 |
70 (0) M0 |
68 (0) M0 |
71 (0) M0 |
64 (0) M0 |
|
|
N69 |
2-storey
residential house |
75 (0) M2 |
- |
75 (0) M2 |
75 (0) M2 |
75 (0) M2 |
75 (0) M2 |
75 (0) M3 |
75 (0) M2 |
73 (0) M2 |
75 (0) M3 |
75 (0) M2 |
|
|
N71 |
1-storey
residential house |
75 (0) M2 |
- |
75 (0) M2 |
75 (0) M2 |
75 (0) M2 |
75 (0) M2 |
75 (0) M3 |
75 (0) M2 |
73 (0) M2 |
75 (0) M3 |
75 (0) M2 |
|
|
N72 |
2-storey
residential house |
70 (0) M0 |
- |
71 (0) M0 |
71 (0) M0 |
68 (0) M0 |
71 (0) M0 |
72 (0) M0 |
69 (0) M0 |
67 (0) M0 |
70 (0) M0 |
63 (0) M0 |
|
|
N73 |
You
Tze Tin Memorial College |
74 (0) M0 |
- |
75 (0) M0 |
75 (0) M0 |
72 (0) M0 |
75 (0) M0 |
66 (0) M1 |
73 (0) M0 |
71 (0) M0 |
74 (0) M0 |
67 (0) M0 |
|
|
N74 |
Siu
Tai House |
68 (0) M1 |
- |
67 (0) M1 |
68 (0) M1 |
75 (0) M0 |
68 (0) M1 |
72 (0) M1 |
69 (0) M1 |
74 (0) M0 |
70 (0) M1 |
70 (0) M0 |
|
|
N76 |
Siu
Ping House |
71 (0) M1 |
- |
70 (0) M1 |
71 (0) M1 |
68 (0) M1 |
71 (0) M1 |
75 (0) M1 |
72 (0) M1 |
68 (0) M1 |
73 (0) M1 |
72 (0) M1 |
|
Worksite3-Tin Shui Wai Reserve Zone |
N35 |
Shap
Pat Heung Rural Committee Kung Yik She Secondary School |
69 (0) M2 |
67 (0) M1 |
- |
- |
65 (0) M1 |
- |
- |
69 (0) M1 |
66 (0) M1 |
- |
- |
|
Extension |
N38 |
Lynwood
Court Block 10 |
73 (0) M1 |
67 (0) M1 |
- |
- |
75 (0) M0 |
- |
- |
69 (0) M1 |
75 (0) M0 |
- |
- |
|
|
N89 |
Tin
Shui Wai Area 105 Phase 1 Block 5 |
73 (0) M2 |
71 (0) M1 |
- |
- |
69 (0) M1 |
- |
- |
73 (0) M1 |
70 (0) M1 |
- |
- |
|
|
N106 |
Tin
Shui Wai Area 31 Phase 1 Block 2 |
75 (0) M1 |
69 (0) M1 |
- |
- |
67 (0) M1 |
- |
- |
71 (0) M1 |
68 (0) M1 |
- |
- |
|
|
N107 |
Tin
Shui Wai Area 31 Phase 1 Block 3 |
75 (0) M1 |
69 (0) M1 |
- |
- |
67 (0) M1 |
- |
- |
71 (0) M1 |
68 (0) M1 |
- |
- |
|
|
N115 |
Tin
Shui Wai Area 30 Block 4 |
73 (0) M2 |
71 (0) M1 |
- |
- |
69 (0) M1 |
- |
- |
73 (0) M1 |
70 (0) M1 |
- |
- |
|
|
N118 |
Tin
Shui Wai Area 31 Phase 1 Primary School |
69 (0) M3 |
68 (0) M2 |
- |
- |
70 (0) M1 |
- |
- |
69 (0) M2 |
68 (0) M2 |
- |
- |
|
|
N120 |
Tin
Shui Wai Area 31 Phase 2 Primary School |
70 (0) M3 |
69 (0) M3 |
- |
- |
70 (0) M2 |
- |
- |
67 (0) M3 |
67 (0) M3 |
- |
- |
|
|
N123 |
Tin
Shui Wai Area 102 Phase 1 Block 4 |
74 (0) M3 |
75 (0) M1 |
- |
- |
73 (0) M1 |
- |
- |
73 (0) M2 |
74 (0) M1 |
- |
- |
|
|
N129 |
Tin
Shui Wai Area 102 Phase 5 Block 17 |
74 (0) M3 |
75 (0) M1 |
- |
- |
73 (0) M1 |
- |
- |
73 (0) M2 |
74 (0) M1 |
- |
- |
|
|
N137 |
Tin
Shui Wai Area 110 Phase 2 Block 11 |
74 (0) M2 |
73 (0) M1 |
- |
- |
71 (0) M1 |
- |
- |
75 (0) M1 |
72 (0) M1 |
- |
- |
|
|
N138 |
Tin
Shui Wai Area 110 Phase 2 Block 10 |
75 (0) M4 |
71 (0) M1 |
- |
- |
69 (0) M1 |
- |
- |
73 (0) M1 |
70 (0) M1 |
- |
- |
|
|
N155 |
Tin
Shui Wai Area 30 Phase 1 Block 6 Domestic (4/F-6/F) |
73 (0) M3 |
72 (0) M2 |
- |
- |
74 (0) M1 |
- |
- |
73 (0) M2 |
75 (0) M1 |
- |
- |
|
|
N155a |
Tin Shui Wai Area 30 Phase
1 Block 6 Kindergarten (3/F) |
69 (0) M3 |
68 (0) M3 |
- |
- |
67 (0) M3 |
- |
- |
68 (0) M3 |
70 (0) M2 |
- |
- |
|
Table 7.10: Mitigated Predicted Noise Levels
Note:
(1)
MM:
Mitigation Measures (see Section 7.3.5 for details of various mitigation
measures M1, M2, M3 & M4).
(2)
The
application sequences of M1, M2, M3 and M4 means that the higher level
mitigation measures have already integrated the lower level measures.
(3)
SCF
: Site Clearance & Formation; LSC: LRT Stop Construction; PIL: Piling; PCC:
Pile Cap Construction; BF: Backfilling; CLC: Column Construction; SSC:
Superstructure Construction; TRL: Track Laying; OLC: Installation of Overhead
Line Cable; SRE: Site Reinstatement; RRE: Road Reinstatement.
(4)
Exceedances
from daytime noise criteria (Table 7.1) are shown with brackets.
With the use of quiet plant and noise barriers (M1+M2), construction noise levels at the majority of NSRs could be controlled within the daytime construction criteria. Noise level exceedances in the range of 3~6 dB(A) were predicted at Tuen Mun Town Plaza Block 1 (N50).
With further mitigation measures of equipment delocalization, local reduction of plant items and limiting the operation time of construction equipment (M1+M2+M3+M4), noise impact at Tuen Mun Town Plaza Block 1 (N50) would be minimised to within TM-EIA daytime recommendations.
With the use of quiet plant and noise barriers (M1+M2), noise level exceedances in the range of 1~3 dB(A) were predicted at the low-rise residential houses (N69 and N71). These noise exceedances are due to superstructure construction.
With further mitigation measures of equipment delocalization and local reduction of plant items (M1+M2+M3), the construction noise levels at the above NSRs could be reduced to the acceptable daytime noise criteria.
With the use of quiet plant and noise barriers (M1+M2), noise level exceedances in the range of 1~8 dB(A) were predicted at Tin Shui Wai Area 31 Phase 1 Primary School (N118), Tin Shui Wai Area 31 Phase 2 Primary School (N120), Tin Shui Wai Area 102 Phase 1 Block 4 (N123) and Tin Shui Wai Area 102 Phase 5 Block 17 (N129) and N138, N155 and N155a.
Construction noise impacts at Tin Shui Wai Area 31 Phase 1 Primary School (N118), Tin Shui Wai Area 102 Phase 1 Block 4 (N123), Tin Shui Wai Area 30 Block 4 (N115), Tin Shui Wai Area 110 Phase 2 Block 11 (N137) and Block 10 (N138), and Tin Shui Wai Area 102 Phase 5 Block 17 (N129), N155 and N155a could be reduced to within the daytime noise limits by delocalization of plant items (M1+M2+M3).
Adverse cumulative noise impacts from the three construction worksites would not be expected provided that noisy construction activities could be scheduled to more than 200m apart. This gives at least 10 dB(A) lower noise at a NSR compared to the noise generated from identical plant within a distance 50m apart.
In view of the locality of the three worksites, there would not be adverse cumulative noise impacts from simultaneous construction works in Pui To Road Grade Separation (Worksite 1) and LT1 Grade Separation (Worksite 2), as these two worksites are separated by more than distance 500m apart. However, there may be slight cumulative noise impact when construction works in the southern section of Tin Shui Wai Reserve Zone Extension and the northern end of Tin Shui Wai Phase 4 Extension (under a separate study proposal) are carried out simultaneously. To eliminate cumulative noise impacts, it is recommended to avoid simultaneous noisy activities within these two zones by scheduling of work areas at a minimum distance 200m apart. With careful management on the scheduling of construction works, the cumulative noise impacts in these areas could be eliminated.
The following mitigation measures shall be implemented by the Contractor in order to reduce construction noise impacts identified in this report.
· The availability of detailed plans or work areas and locations of plant (as opposed to gazetted work boundaries) will enable the Contractor to reduce the amount of uncertainty in the distance corrections applied to source noise levels used in this assessment. As a guide, a doubling of distance from NSRs will achieve a 6dB(A) reduction in noise levels.
· The layout of worksites should be critically reviewed and judiciously planned in order to make best use of existing features which may be able to provide screening of NSRs from plant noise eg site offices, site containers, etc.
· To determine specific SWL measurement of typical plant proposed to be used, particularly those activities that have been identified to be noisy or cause exceedances above daytime noise criteria. These ‘actual’ levels may then be able to be used in place of the values in the TM-CW.
· Use of smaller PME with lower SWL, e.g. smaller excavator, lorry to replace dump truck, where practicable.
· Practicality/cost-effectiveness of portable, full noise barriers for sections of works identified in this report.
· Sequential operation of a limited number of plant items in every 30-minute interval. For example, only excavator and vibratory roller are used in every 30-minute interval while only grader and dump truck are used in the next consecutive 30-minute period, where practicable.
· Use of limiting the operational period of other PME, where appropriate and practicable, as a last resort in order to meet the noise criteria. As an example, if PME could be operated for only 10 minutes out of any 30 minute period, a reduction of 5dB(A) could be achieved.
With the application of one or more of the above recommended methods of mitigation, there is considerable scope practicable to reduce the majority of noise impacts to within the allowable noise limits.
This assessment has predicted that the
unmitigated construction noise impacts associated with the LRT alterations and
extensions would be high at the nearby NSRs. Standard noise mitigation measures have been identified
which could reduce the noise levels to within the noise criteria at most
NSRs. Measures including the use
of silenced PME, installation of movable barriers, delocalization of equipment,
local restrictions on the number of PME in use, limiting the operation time of
construction plant and sequential operation of plant items should be
incorporated into the Contract Specifications and Implementation Schedules.
With the recommended mitigation measures,
construction noise impacts at all NSRs could be controlled to within 75dB(A)
criteria stipulated in the TM.
The preceding assessment has been conducted based on daytime noise criteria and it is understood that evening and night-time works would not be required normally. Where evening and night works are desired by the Contractors, they shall apply for a CNP from EPD.
The regulatory requirements and standards to protect water quality are the Water Pollution Control Ordinance (WPCO) [6] , its subsidiary technical memoranda, and various technical circulars issued by the Works Branch and EPD. Whilst the technical circulars are non-statutory, they are generally accepted as best guidelines in Hong Kong and have been adopted as relevant for this assessment.
Under the WPCO, Hong Kong waters are divided into 10 Water Control Zones (WCZs). Each WCZ has a designated set of statutory Water Quality Objectives (WQO). The standards to be met in each WCZ depend on the classification of the receiving waters (eg inland, inshore, marine or foul sewer). The standards are applied to effluents through licences issued by EPD under Sections 15, 16 and 20 of the WPCO. The relevant standards are set out in the Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters [17] (TM-Waters).
This TM issued under Section 21 of the WPCO defines acceptable discharge limits to different types of receiving waters.
Effluents discharged into the inshore and marine waters of the Victoria Harbour WCZ are subject to standards stipulated in Tables 9a and 9b of the TM. The standards in Tables 10a and 10b of the TM apply to effluents discharged into the inshore and marine waters of the North Western and Western Buffer WCZs respectively. For the Deep Bay WCZ, the standards in Table 8 of the TM apply, although reference should also be made to Section 8.1.3 below.
In this assessment study for the Tin Shui Wai Reserve Zone Extension, the standards for the effluent discharged into the coastal waters of Deep Bay WCZ, which stipulated in Table 8 of TM should be referred, although reference should also be made to Section 8.1.3 below. On the other hand, the assessment study for the Grade Separation Works, the standards for the effluent discharged into the Norther Western WCZ, which stipulated in Tables 10a and 10b of TM should be referred.
Discharges of effluents into the foul sewerage system need to comply with the standards listed in Tables 1 and 2 of the TM.
For cooling water discharges, in addition to the TM requirements (which only apply to discharges of up to 6,000m3 per day), the EPD has required that discharges of between 6,000 and 1,000,000 m3 per day have a temperature of not more than 350C and not more than 100C above influent temperature, and contain not more than 0.2mg/1 of total residual chlorine.
In addition to
Table 8 of the TM, this policy aims to limit the decline of water quality in
Deep Bay and its catchments. It
requires that major developments within Deep Bay catchments and all new
developments in sensitive areas of the catchments do not increase existing
pollution loads by connecting the sewage system of the developments to the
public sewer system. If connection of the public sewer system is not feasible
at the early development stage, (say first five years), the on-site treatment
facilities should be installed as a temporary measure and the connection work
of public sewer system must be completed within this period.
The Practical Note for Professional Persons on Construction Site Drainage (PN1/94) issued by EPD provides basic environmental guidelines for the handling and disposal of construction site discharges to minimise impacts on water quality.
Current construction design was reviewed to assess the proximity of the proposed LRT construction activities to existing and committed WSRs. All WSRs have been identified according to the guidance provided in HKPSG, and verified by field surveys and area appraisals.
Construction type, sequence and duration were reviewed to identify activities likely to impact upon identified freshwater and marine water bodies and WSRs, water courses, streams, ponds and wetland freshwater catchment areas.
Following the identification of WSRs and potential water quality impacts, the scale, extent and severity of potential net (ie unmitigated) construction impacts were evaluated, taking into account all potential cumulative effects including those of adjacent projects, with reference to the WPCO criteria.
In the event that net water quality impacts exceed the appropriate WPCO criteria, practical water pollution control measures/mitigation proposals will be identified to ensure compliance with reference to the WPCO criteria for the beneficial uses of the marine water bodies and fresh water courses. Water quality monitoring and audit requirements will be subsequently developed to ensure the efficacy of the construction stage water pollution control and mitigation measures (Section 12).
Present operational LRT designs were reviewed to assess the proximity of the rail alignment or any associated operational facilities to existing and future committed WSRs in accordance with the HKPSG.
All operational infrastructure proposals and activities were reviewed to identify activities likely to impact upon identified adjacent water bodies, water courses, streams, ponds, wetland freshwater catchment areas and marine WSRs.
Following the review of the LRT operation, the potential adverse effects, scale, extent and severity of potential net (i.e. unmitigated) impacts were assessed and evaluated, with reference to the WPCO criteria.
In the event that net impacts exceed the appropriate criteria, practical water pollution control measures and mitigation proposals will be identified for inclusion in the design to ensure residual impact compliance with reference to the WPCO criteria for the beneficial use of the marine water bodies and fresh water courses.
The potential water quality impacts, which include the impacts on river and marine water quality and drainage, caused by the construction and operation of the Tin Shui Wai Reserve Zone Extension in Yuen Long and Grade Separations in Tuen Mun.
The generation of construction and operational wastewater are key issues as it may cause adverse water quality impacts on WSRs if not properly controlled. The mitigation measures have been recommended to ensure that discharge levels meet the TM-Waters and EPD’s ‘zero discharge’ policy for the Deep Bay catchment.
Potential WSRs likely to be affected by the construction works of proposed Tin Shui Wai Reserve Zone Extension and Grade Separations include:
WSR of Grade Separation at
LT1 near Tsing Lun Road |
Tuen Mun River |
WSRs of Grade Separation
at J6/Mj7/Mj8near Pui To Road |
Tuen Mun River, Tuen Mun Typhoon Shelter and the Gazetted batching
beaches downstream of the Tuen Mun River |
WSRs of Reserve Zone
Extension |
Tin Shui Wai Nullah and the proposed constructed wetland in Tin Shui
Wai Reserve Zone. |
Tin Shui Wai Nullah is a concrete channel which drains the Tin Shui Wai area and discharges into inner Deep Bay. According to EPD’s River Water Quality in HK 1997, there was a marked improvement of the water quality of the nullah. The upstream monitoring station TSR2 was upgraded from “fair” to “good” and the downstream monitoring station TSR1 from “bad” to “fair”, with a substantial decrease in Ammonical-Nitrogen and E.coli (see Table 8.1).
The water quality of Tin Shui Wai nullah is monitored monthly by EPD’s river water monitoring programme. The EPD monitoring data of two monitoring stations TSR1 and TSR2 are summarised and given in Table 8.1. The monitoring locations are shown in Figure 8.1.
Even though the water quality of Tin Shui Wai Nullah was improved in 1997, the overall quality is still unsatisfactory, as reflected by occasional non-compliance with WQOs for BOD5, COD and SS.
The 38 km long Tuen Mun River has a catchment of around 16.5 km2. The upstream section of the river passes through Lam Tei, San Hing Tsuen and Fu Tei. The lower section runs through Tuen Mun town as a 4 km long open nullah. The monitoring data for 1997 showed that the water quality of the lower section (Monitoring Stations TN3 – TN6) of the river was better than the upper section (Monitoring Stations TN1 – TN2). A summary of EPD monitoring data of 1997 for these six monitoring stations is given in Table 8.2. The monitoring locations are shown in Figure 8.2.
Although the water quality of Tuen Mun River was improved when compared with the monitoring data of 1996, the overall water quality is still poor, reflected by non-compliance with the WQOs, particularly the high COD values. It is also reflected by occasional non-compliance for BOD5, SS and DO.
The water quality of the Tuen Mun Typhoon Shelter is well documented by EPD’s Marine Water Quality in Hong Kong in 1997 (Monitoring Stations NT1, and NT3-NT5). A summary of monitoring data of 1997 for those monitoring stations is given in Table 8.3. The monitoring locations are shown in Figure 8.3.
The monitoring results indicate that the water quality in Tuen Mun Typhoon Shelter was generally acceptable with high level of depth-averaged DO, and low Total Nitrogen and E.coli counts.
Water quality of gazetted beaches in Hong Kong is documented in report from EPD’s beach water quality monitoring programme. The water quality of gazetted bathing beaches along the shoreline of Castle Peak Road such as Kadoorie, New Cafeteria and Old Cafeteria beaches, have improved from ‘Poor’ to ‘Fair’ since 1998, although the water quality of Castle Peak beach remains as ‘Poor’.
Water quality of North Western WCZ is also recorded in a report from EPD’s marine quality monitoring programme. A summary of monitoring data of 1997 for monitoring stations NM2 and NM3 is given in Table 8.4. North Western waters are well oxygenated in both surface and bottom layers. High E.coli counts, especially at monitoring station NM3, are reported on occasions, reflecting bacterial loading from the Tuen Mun River and Tuen Mun Typhoon Shelter. The monitoring locations are shown in Figure 8.3.
Parameter |
TSR1 |
TSR2 |
WQOs
for inland waters of Deep Bay WCZ |
DO(mg/L) |
7.6 (5.9 – 17.3) |
10.5 (7.8 – 15.5) |
4mg/L |
BOD5(mg/L) |
14 (3-76) |
3 (1-7) |
3mg/L |
COD(mg/L) |
19 (11-130) |
14 (4-41) |
15mg/L |
Oil and Grease (mg/L) |
0.8 (0.5 – 7.6) |
0.5 (0.5 – 1.2) |
n.a. |
SS (mg/L) |
30 (7 – 140) |
15 (5 – 93) |
Annual Median 20mg/L |
Ammonical N (mg/L) |
2.50 (0.36 – 11.00) |
0.46 (0.12 – 10.00) |
n.a. |
Total KjeldahI N (mg/L) |
4.20 (0.78 – 20.00) |
1.20 (0.23 – 14.00) |
n.a. |
Total P (mg/L) |
0.88 (0.19 – 3.90) |
0.17 (0.05 – 1.70) |
n.a. |
pH value |
8.2 (7.9 – 9.6) |
8.2 (7.6 – 9.5) |
6.5 – 8.5 |
Flow (L/s) |
NM |
28 (3 – 570) |
n.a. |
Table 8.1 : Summary Statistics of 1997 Water Quality of Tin Shui Wai Nullah (TSR)
Notes:
1.
Data
presented are annual arithmetic means, except where specified otherwise.
2.
Data enclosed
in brackets are ranges.
3.
NM indicates
no measurement taken.
4.
n.a. = not
available
Source: EPD (January 1997 – December
1997)
Parameter |
TN1 |
TN2 |
TN3 |
TN4 |
TN5 |
TN6 |
WQOs for inland waters
of North Western WCZ |
DO (mg/L) |
4.0 (1.9–7.9) |
9.2 (7.5–11.50) |
4.4 (0.5–9.5) |
4.5 (2.3–7.2) |
4.5 (0.6–8.5) |
5.2 (2.8–8.6) |
≧4mg/L |
BOD5 (mg/L) |
31 (11-120) |
5 (1–15) |
4 (2-14) |
5 (2-11) |
5 (2-12) |
2 (1–6) |
≦3mg/L |
COD (mg/L) |
48 (13– 20) |
18 (6–77) |
135 (44–280) |
107 |
130 |
140 (20–350) |
≦15mg/L |
Oil and Grease (mg/L) |
2.3 (0.5–25.0) |
1.0 (0.5–3.7) |
0.5 (0.5–1.3) |
0.5 (0.5–1.2) |
0.5 (0.5–1.6) |
0.5 (0.5–1.1) |
n.a. |
SS (mg/L) |
29 (12–320) |
12 (4–3500) |
6 (3–29) |
8 (5–25) |
7 (4-22) |
5 (3–25) |
Annual
Median ≦20mg/L |
Ammonical N (mg/L) |
9.55 (0.39-31.00) |
1.75 (0.19–8.40) |
0.56 (0.07–1.50) |
0.55 (0.24– 1.20) |
0.59 (0.10–1.50) |
0.44 (0.23–0.76) |
n.a. |
Total Kjeldahl N (mg/L) |
12.00 (0.72–38.00) |
2.25 (0.26-13.00) |
0.96 (0.74–2.00) |
1.05 (0.72–2.10) |
1.03 (0.41–2.00) |
0.82 (0.54–1.20) |
n.a. |
Total P (mg/L) |
1.80 (0.21 – 3.90) |
0.47 (0.06 – 3.40 |
0.15 (0.07 – 0.32) |
0.17 (0.09 – 0.26) |
0.16 (0.07 – 0.38) |
0.12 (0.07 – 0.38) |
n.a. |
pH value |
8.0 (7.5 – 8.2) |
7.6 (7.1 – 9.9) |
7.6 (7.4 – 8.2) |
7.7 (7.4 – 8.3) |
7.6 (7.5 – 8.4) |
7.3 (7.0 – 7.9) |
6.5 – 8.5 |
Flow (L/s) |
85 (30-1100) |
27 (8-162) |
NM |
NM |
NM |
NM |
n.a. |
Table 8.2 : Summary Statistics of 1997 Water Quality of Tuen Mun River
Notes:
1.
Data
presented are annual arithmetic means, except where specified otherwise.
2.
Data enclosed
in brackets are ranges.
3.
NM indicates
no measurement taken.
4.
n.a. = not
available
Source: EPD (January 1997 – December 1997)
Parameter |
NT1 |
NT3 |
NT4 |
NT5 |
|
Temperature |
|
23.8 (10.5 – 28.5) |
24.2 (18.4 – 28.9) |
23.7 (18.3 – 28.) |
23.7 (18.1 – 28.6) |
Salinity (ppt) |
|
23.9 (8.7 – 30.8) |
22.4 (5.5 – 30.9) |
24.1 (9.1 – 31.0) |
23.5 (7.6 – 31.4) |
DO (% Saturation) |
Surface |
77 (53 – 88) |
72 (47 – 87) |
81 (54 – 95) |
85.8 (61 – 103) |
|
Bottom |
NM |
NM |
77 (53 – 91) |
83.6 (60 – 101) |
DO (mg/L) |
Surface |
5.6 (4.1 – 6.8) |
5.3 (3.6 – 6.7) |
5.9 (4.2 – 6.9) |
6.3 (4.8 – 78) |
|
Bottom |
NM |
NM |
5.7 (4.1 – 6.5) |
6.2 (4.7 – 7.6) |
pH value |
|
7.9 (7.7 – 8.1) |
8.0 (7.8 – 8.2) |
7.9 (7.7 – 8.2) |
7.9 (7.7 – 8.3) |
SS (mg/L) |
|
22.5 (15.0 – 32.0) |
18.3 (8.0 – 40.0) |
19.7 (10.4 – 37.0) |
7.7 (4.2 – 11.7) |
Turbidity (NTU) |
|
8.4 (6.7 – 10.8) |
15.6 (4.6 – 37.2) |
6.7 (3.9 – 9.2) |
4.7 (1.7 – 8.0) |
BOD5 (mg/L) |
|
0.8 (0.6 – 1.1) |
0.8 (0.6 – 1.8) |
0.6 (0.4 – 0.9) |
0.5 (0.4 – 0.7) |
Ammonical N (mg/L) |
|
0.18 (0.08 – 0.24) |
0.26 (0.09 – 0.56) |
0.15 (0.05 – 0.19) |
0.12 (0.03 – 0.16) |
Total KjeldahI N (mg/L) |
|
0.88 (0.56 – 1.30) |
1.06 (0.71 – 1.80) |
0.80 (0.55 – 1.20) |
0.65 (0.22 – 1.00) |
Total Nitrogen (mg/L) |
|
1.27 (0.78 – 1.56) |
1.45 (0.90 – 2.4) |
1.18 (0.75 – 1.40) |
1.06 (0.76 – 1.36) |
Total.P (mg/L) |
|
0.10 (0.07 – 0.15) |
0.12 (0.08 – 0.18) |
0.10 (0.06 – 0.14) |
0.08 (0.05 – 0.13) |
E. coli (cfu/100ml) |
|
2375 (210 – 40000) |
5568 (170 – 700000) |
1708 (134 – 100500) |
540 (39 – 17333) |
Table 8.3 : Summary Statistics of 1997 Water Quality of Tuen Mun Typhoon Shelter
Note:
1.
Except as
specified, data presented are depth-averaged data.
2.
Data presented
are annual arithmetic means except for E.coli data which are geometric means.
3.
Data enclosed
in parentheses are ranges
Source: EPD (1998), Marine Water Quality
in Hong Kong for 1997.
Determinant |
North Western WCZ EPD Monitoring Station |
||
|
NM2 |
NM3 |
|
Temperature (0C) |
|
24.5 (18.1 – 28.8) |
22.6 (17.9 – 25.7) |
Salinity (ppt) |
|
22.8 (6.9 – 31.3) |
28.2 (21.9 – 31.3) |
DO (% Saturation) |
Surface |
85 (62 – 103) |
73 (49 – 89) |
|
Bottom |
90 (77 – 103) |
67 (50 – 89) |
DO (mg/L) |
Surface |
63 (4.8 – 7.8) |
5.4 (3.9 – 6.9) |
|
Bottom |
6.7 (5.6 – 7.8) |
4.9 (3.6 – 6.8) |
SS (mg/L) |
|
7.0 (3.8 – 11.0) |
8.0 (3.7 – 13.2) |
Turbidity (NTU) |
|
5.0 (2.5 – 6.8) |
5.5 (1.9 – 8.0) |
pH value |
|
8.1 (8.0 – 8.2) |
7.6 (6.6 – 8.2) |
BOD5 (mg/L) |
|
0.6 (0.4 – 0.8) |
0.5 (0.3 – 0.7) |
Ammoniacal N (mg/L) |
|
0.10 (0.04 – 0.15) |
0.10 (0.07 – 0.15) |
Total KjeldahI N (mg/L) |
|
0.62 (0.27 – 1.02) |
0.73 (0.39 – 1.02) |
Total P (mg/L) |
|
0.07 (0.05 – 0.13) |
0.08 (0.05 – 0.14) |
E.coli (cfu/100ml) |
|
106 (11 – 4400) |
1358 (250 – 14933) |
Table 8.4 : Summary Statistics of 1997 Marine Water Quality in North Western Waters
Note:
1.
Except as
specified, data presented are depth-average data.
2.
Data
presented are annual arthmetic means except for E. coli data which are annual
geometric means.
3.
Data enclosed
in brackets are ranges.
Source: EPD (January 1997 – December 1997
Potential sources of impacts to water quality from the construction of the elevated grade separations and extension alignments are shown below:
· Construction Runoff ; and
· Sewage effluents generated from the construction workforce.
Construction runoff from site areas may contain high loading of suspended solids (SS) and contaminants. Potential water pollution sources from construction site run off include:
a) Runoff and erosion from site surfaces, drainage channels, earth working areas and stockpiles;
b) Wash water from dust suppression sprays and wheel washing facilities; and
c) Fuel, oil, solvents and lubricants from maintenance of construction machinery and equipment.
Construction runoff may cause physical, biological and chemical effects. The physical effects could cause the increasing of SS from the site, which could cause blockage of drainage channels. Local flooding may also happen in a heavy rainfall situation. The chemical and biological effects caused by the construction runoff are highly dependent upon the chemical and nutrient content of the runoff. Runoff containing significant amounts of concrete and cement-derived material may cause primary chemical effects such as increasing of turbidity and discoloration, elevation in pH, and accretion of pH solids. A number of secondary effects may also result in toxic effects to water biota due to elevated pH values, and reduced decay rates of faecal micro-organisms and photosynthesis rate due to the decreased light penetration.
Once the construction activities commence, there will be an increase of SS levels and turbidity of nearby water bodies such as the proposed constructed wetland in Tin Shui Wai Reserved Zone. The downstream water quality of Tin Shui Wan Nulllah and Tuen Mun River may also be affected by the construction of Reserve Zone Extension and Grade Separations respectively.
The water quality impacts from these construction activities are likely to be minimal provided that site boundaries are well maintained and good construction practices are applied to ensure that litter, fuel, oil, solvents and lubricants are properly managed, stored, handled and disposed.
Sewage effluents will arise from the sanitary facilities provided for the on-site construction workforce. The characteristics of sewage would include high levels of 5-day Biochemical Oxygen Demand (BOD5), Ammonia and E. coli counts.
Portable chemical toilets and proper disposal of sewage will be implemented at site offices to ensure that discharge standards are met. The same practice could be applied for the sewage generated by the construction workers dispersed along the extension alignments. No major water quality impact is expected.
The selected WSRs for the construction phase are also applicable to the operational phase.
Owing to the enforcement of Livestock Waste Control Scheme and the WPCO, it is expected that the surface water quality will be improved gradually. Therefore, the pollution loading from the nearby environment should be reduced gradually.
The runoff from rail track is considered as a potential source of impact to water quality from the operation of the grade separations and extension alignment.
Air conditioning systems are not included in the design of LRT stops. Therefore, cooling water discharge is not considered as a potential source of impact.
Sewage discharge is not considered as a potential source of impact, as no commercial activities are allowed and there are no toilet/restroom facilities provided in the LRT stops. For LRT terminus however, toilets will be provided.
The rail track runoff may be contaminated with SS (including metal chippings from track grindings and corrosion of rolling stock and other equipment). Grinding of rail will take place on a regular basis. Oil and grease arising from the light rail trains may also contaminate the rail track runoff. The requirements in the TM standards will be achieved if appropriate mitigation measures are adopted and implemented in order to minimise the potential contamination sources.
The sewage discharge from the toilets in the terminus will be discharged to the nearby public sewers. No adverse impacts are anticipated.
Appropriate mitigation measures should be implemented to control construction runoff to prevent SS loading entering the water bodies and impacting on downstream WSRs. The surface runoff, soil erosion and sewage effluents should be minimised by proper site management practices.
The guidelines stipulated in the ProPECC PN 1/94 [18] should be followed in order to control the construction site runoff. Good housekeeping and best management practices should be implemented to ensure the runoff from construction site area and any stored excavated material complies with the WPCO and there are no unacceptable impacts on the WSRs caused by the construction activities. All discharge for the construction site areas should be controlled to comply with the TM-Waters. The “zero discharge” policy should also be complied for the construction of alignment of Tin Shui Wai Reserve Zone Extension due to the site areas falling within the Deep Bay WCZ.
Exposed soil areas should be minimised to reduce the contamination of runoff and erosion. The following mitigation measures should be adopted to control the runoff-related impacts:
a) The use of sediment/silt traps; and
b) The adequate maintenance of drainage systems to prevent flooding and overflowing.
The dikes or embankments for flood protection should be implemented around the boundaries of earthwork areas. Temporary ditches should be provided to facilitate the runoff discharge into an appropriate watercourse, through a site/sediment trap. The sediment/silt traps should be incorporated in the permanent drainage channels to enhance deposition rates.
Both temporary and permanent drainage pipes and culverts provided for runoff discharge should be adequately designed for the controlled release of storm flows. All sediment/silt traps should be cleaned and maintained regularly. The temporarily diverted drainage should be reinstated to its original condition when the construction works have finished or the temporary diversion is no longer required.
Wheel washing facilities should be implemented and regularly cleaned and maintained. Sediment, sand and silt in the wash water from the wheel washing facilities should be settled out and removed before discharging in storm drains. A section of the road between the wheel washing bay and the public road should be paved with backfill to prevent wash water or other site runoff entering the public road drain.
Oil interceptors should be provided in the drainage system downstream of any oil/fuel pollution sources. The oil interceptors should be emptied and cleaned regularly to prevent the release of oil and grease into the storm water drainage system after accidental spillage. A bypass should be provided for the oil interceptors to prevent flushing during of heavy rain.
All fuel/oil tanks and chemical storage tanks/areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank, to prevent spilled fuel oils from reaching the receiving water bodies.
By adopting the above mitigation measures with Best Management Practices (BMPs) it is anticipated that the impacts of construction site runoff from the construction site will be reduced to an acceptable levels before discharges.
Portable chemical toilets and sewage holding tanks are recommended to handle the construction sewage generated by workers from both the construction areas and dispersed along the alignment. A licensed contractor should provide appropriate and adequate portable toilets and is responsible for appropriate disposal and maintenance.
Although the runoff from construction areas is expected, the water quality impacts will generally be temporary and localised. Therefore, no residual water quality impacts are expected from the construction phase of the extension alignment, provided that all of the recommended mitigation measures including appropriate drainage and silty runoff collection facilities are adopted.
It is considered that control of discharges from construction activities and proper site management procedures, as mentioned above, no residual water quality impacts is expected.
The impacts from track runoff could be minimised by the adoption of the following mitigation measures:
a) Provide a surface water drainage system in order to collect the track runoff. Where oil and lubricating fluids could be spilt, the track drainage channels discharge should pass through oil/grit interceptors/chambers or sub-soil drainage system, to remove oil, grease and sediment before being pumped to the public stormwater drainage system;
b) The silt traps and oil interceptors should be cleaned and maintained regularly. The efficiency and performance of these facilities are highly dependent on regular cleaning and maintenance; and
c) Oily contents of the oil interceptors should be transferred to an appropriate disposal facility, or to be collected for reuse, if possible.
No residual operational water quality impacts are expected if appropriate drainage and effluent collection systems are adopted and incorporated.
The potential water quality impacts arising from the construction and operational phase of the Tin Shui Wai Reserve Zone Extension in Yuen Long and Grade Separations in Tuen Mun have been assessed. Assessment results indicate that no residual water quality impacts should be generated from the construction and operation of the new LRT extension and grade separation works provided that the recommended mitigation measures are implemented.
The following legislation relates to the handling, treatment and disposal of waste in Hong Kong, and will be considered in assessing potential impacts and their avoidance or mitigation:
a)
The Waste Disposal Ordinance [7]
b)
The Waste Disposal (Chemical Waste) (General) Regulation [8]
c)
The Land (Miscellaneous Provisions)Ordinance [12]
d) The Public Health and Municipal Service Ordinance (Cap 132) – Public Cleansing and Prevention of Nuisances (Urban Council and regional Council) By-laws [9] ; and
e)
Dumping At Sea Ordinance [10]
The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes. Construction and demolition (C&D) material is not directly defined in the WDO but is considered to fall within the category of “trade waste”. Under the WDO, wastes can only be disposed of at sites licensed by EPD.
Under the Waste Disposal (Chemical Waste) (General) Regulation, all producers of chemical wastes (including asbestos) must register with EPD and treat their wastes, either by utilising on-site plant licensed by EPD, or by arranging for a licensed collector to take the wastes to a licensed facility. The regulation also prescribes the storage facilities to be provided on site, including labelling and warning signs, and requires the preparation of written procedures and training to deal with emergencies such as spillage, leakage or accidents arising from the storage of chemical wastes.
Public fill, which are wholly inert
construction wastes, may be taken to the Tseung Kwan O public filling area and
Shatin (Pak Shek Kok) public filling area, which are the only two public
filling areas available in Hong Kong.
Public filling areas usually form part of land reclamation schemes
operated by the Civil Engineering Department (CED). The Land (Miscellaneous
Provisions) Ordinance requires that dumping licenses should be obtained by
individuals or companies who deliver suitable public fill to public filling
areas. The licenses are issued by the CED under delegated powers from the
Director of Lands.
The Public Cleansing and Prevention of Nuisances By-Laws provide further controls on the illegal tipping of wastes on unauthorised (unlicensed) sites.
The following documents and guidelines also relate to waste management and disposal in Hong Kong:
a) Waste Disposal Plan for Hong Kong (December 1989), Planning, Environmental and Lands Branch, Hong Kong Government Secretariat;
b)
Environmental Guidelines for Planning In Hong Kong (1990), Hong Kong
Planning and Standards Guidelines, Hong Kong Government;
c)
New Disposal Arrangements for Construction Waste (1992).
Environmental Protection Department and Civil Engineering Department;
d)
Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes (1992), Environmental Protection Department;
e)
Works Branch Technical Circular No 2/93, Public Dumps;
f)
Works Branch Technical No 16/96, Wet Soil in Public Dumps;
g)
Works Bureau Technical Circular No. 5/98, On Site Sorting of
Construction Waste on Demolition Sites;
h)
Works Bureau Technical Circular No. 5/99, Trip-ticket System for
Disposal of Construction and Demolition Material;
i)
Environmental Protection Department Technical Circular No. 1-1-92,
Classification of Dredged Sediments for Marine Disposal; and
j) Technical Circular No. 22/92, Marine Disposal of Dredged Mud, Works Branch.
The assessment of environmental impacts from waste generation from the construction and operation of proposed LRT works is based on three factors:
a) The type and nature of waste generated;
b) The amounts and rates of principal waste types generated; and
c) The proposed reuse, recycling, storage, collection, transport and disposal method, and the impacts of these methods.
Construction activities will result in the generation of a variety of wastes that can be divided into distinct categories based on their constituents, as follows:
a) Site clearance waste;
b) Excess excavated material;
c) General construction waste;
d) Demolition waste;
e) Chemical waste; and
f) General refuse.
Site clearance waste is generated from site preparation work, and generally consists of a mixture of wood, metal and general refuse from the temporary structures. Excess excavated material is defined as inert material removed from the ground and sub-surface which will not be reused on site.
General construction waste comprises unwanted materials generated during the construction works, including rejected structures and materials, materials which have been over ordered or are surplus to requirements, and materials which have been used and discarded.
Demolition waste may be generated through the demolition of roads and permanent buildings prior to construction. Materials with high scrap value, such as metals, are normally recycled. The remaining materials should be separated into inert and non-inert material for disposal at public dump landfill.
Chemical waste likely to be generated from the construction works will, for the most part, arise from the maintenance of equipment, scrap batteries or spent acid/alkali, used engine oils and hydraulic fluids, chemicals/oil based emulsions, spent mineral oils and cleaning fluids, and spent solvents.
General refuse includes any waste that does not fit into any of the categories previously described.
During the operation phase of LRT, waste arisings will typically consists of the following:
a) General refuse;
b) Industrial waste; and
c) Chemical waste.
The amount of waste arising from these sources will depend on the staffing and customer levels and facilities available at the LRT stops and the nature of the maintenance activities.
General refuse will arise from the public and staff. As no commercial activity is allowed within the LRT stops, only miscellaneous waste produced during daily activities is expected.
Industrial waste will arise from the maintenance activities. The materials may include scrap materials from rail and carriage maintenance, cleaning materials and discarded electronic equipment.
Chemical waste will also arise from maintenance activities. This includes paints, lubricants and solvents etc.
The re-use, recycling, storage, collection, transport, and disposal methods for various wastes during the construction and operational stages, and the environmental implications will be proposed and discussed in Section 9.4.
The grade separations are located in Tuen Mun urban areas. Both the temporary and permanent structures will be located close to the existing at grade track. Site clearance will be limited to the removal of several planters. The alignment area in the Reserve Zone has been reserved since the early development stage of Tin Shui Wai. Therefore, no major site clearance works is required and no significant site clearance waste is anticipated.
The grade separations in Tuen Mun will be supported on the viaduct. The alignment of the new Reserve Zone Extension will be constructed at grade, with the ballast track (except the viaduct across Junction C). Extensive excavation works are not anticipated. The estimated quantity of excavated material is given in Section 9.3.2.1.2. Section 9.3.2.1.2 also highlight the potential to transport the excavated to other construction site for re-use.
General construction waste will be generated from the construction of the viaduct in Pui To Road and LT1, and tracks and passenger stops, and will consist of wood waste from formwork and falsework, material and equipment wrappings, and surplus or rejected construction material. The estimated quantity of general construction waste is given in Section 9.3.2.1.3. The measures to be taken during construction stage to reduce generation of construction waste and for the disposal of waste are given in Section 9.4.1.4.
No significant demolition works will be required for the proposed new extension and grade separations.
Substances likely to be generated by construction of the extension will, for the most part, arise from the maintenance of equipment. These include, but need not be limited to the following:
a)
Scrap batteries or spent acid/alkali from their maintenance;
b)
Used engine oils, hydraulic fluids and waste fuel;
c)
Spent mineral oils and cleaning fluids from mechanical machinery; and
d)
Spent solvent/solutions, some of which may be halogenated, from
equipment cleaning activities.
Chemical waste
may pose serious environmental, health and safety hazards if it is not properly
managed. These hazards include:
a)
Toxic effects to workers;
b)
Advance effects on water quality from spills;
c)
Fire hazards; and
d) Disruption of sewage treatment works if the chemical waste enters the sewerage system.
General refuse will be generated from the site offices. The storage of general refuse will have the potential to give rise to adverse environmental impacts. These include odour if waste is not collected frequently, windblown litter, water quality impacts if waste enters water bodies, and visual impacts. The site may also attract pests and vermin if the waste storage area is not well maintained and cleaned regularly. In addition, disposal of wastes at sites other than approved waste transfer or disposal facilities, can also lead to similar adverse impacts at those sites.
General refuse will arise mainly within the
LRT stops from the public. General waste produced during daily activities will
be the main refuse source. Similarly to the construction phase, the storage of
general refuse has the potential to give rise to adverse environmental impacts
if the waste is not collected frequently.
Industrial waste will be generated from maintenance activities of the grade separations, railway and LRT stops. The materials may include scrap materials from rail and carriage maintenance, used fluorescent tubes, cleaning materials and discarded electronic equipment.
Chemical waste will be generated from
maintenance activities of the grade separations, railway and LRT stops. The
waste may include lubricants, paints, acids/alkalis, coolants and solvents. Similarly
to the construction phase, these chemical wastes may cause significant
environmental, health and safety impacts if they are not
managed properly.
The grade separations will be built at the existing rail alignment areas. The proposed extension has been reserved since the early development stage of Tin Shui Wai. There will be minor site clearance works required. It is anticipated that the environmental impacts due to the storage, handling, transport and disposal of site clearance waste will be minimal.
Tunnelling works are not required for this grade separations and extension project.
Excavated material will be expected from the removal of the top layer soil for the construction of the ballast track bed of Phase 4. Excavation will also be carried out for construction of piles and pile cap foundations. The approximate length of ballast track for Reserved Extension is 2.5 km. The average width of the ballast track is 9.5 m and an average depth of 0.5 m of top layer soil will be excavated. Relatively insignificant quantities in the range of a few hundred cubic metres of excavated material will be generated by the grade separation. Therefore, the total quantity of excavated material is estimated to be in the range of 12,000 m3 to 12,500 m3.
According to the WR EIA Report, the construction of the Western Section (Tuen Mun and Yuen Long areas) will generate about 543,000 m3 (37,000 m3 of rock and 506,000 m3 of soil) of excavated material and will require 1.55 million m3 of structural and embankment fill. Therefore, fill material needs to be imported to the site. It is suggested that, if practicable, the excavated material from LRT Alterations project could be transported to the sites of the Western Section of WR as filling material. If any excavated material is unsuitable as fill, it should comply with the public dumping license requirements, and could therefore be accepted at public filling areas.
It is anticipated that approximately 1500 m3 of excavated material will be on-site used. The rest quantity of approximately 11000 m3 of excavated material will be transported to the sites of the Western Section of WR or, where unavoidable, disposed at public filling area. Therefore it is not anticipated to have a significant impact on the demand for public filling capacity. The disposal of inert excavated material at public filling areas or land formation sites will not have any long-term environmental impacts.
The storage, handling, transport and disposal of general construction wastes have the potential to create visual, water, dust and associated traffic impacts. A total of about 1,600m2 Gross Floor Area (GFA) will be constructed for the terminus and stops. Based on a waste generation rate of 0.1 m3/m2 of GFA to be constructed, approximately 160m3 of general construction waste will be generated from the construction of LRT stops. The construction waste generated from the construction of grade separations in Tuen Mun is difficult to assess at this stage. However, owing to their relatively small scale, the quantity of construction waste generated will be minimal.
General construction waste should be removed from the site as soon as practicable in order to avoid adverse environmental impacts arisen from on-site storage of the material.
The quantity of the demolition waste will be insignificant, as there are no major demolition works required for this new proposed extension project.
It is difficult to quantify the amount of chemical waste that will arise from the construction activities as it will be highly dependent on the Contractor’s on-site maintenance activities and the number of plants and vehicles used. However, it is believed that the quantity of chemical waste, such as lubricating oils and solvents, produced from plant maintenance will be relatively small. These chemical wastes should be readily accepted by the Chemical Waste Treatment Center (CWTC) at Tsing Yi.
The storage, handling, transport and disposal of chemical waste should be undertaken in strict accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Provided that this is complied, and chemical wastes are disposed of at a licensed facility, the environmental impact due to handling and disposal of chemical waste will be minimal.
In accordance with the information provided by KCRC, the construction sites for the Grade Separations in Tuen Mun and Reserve Zone Extension in Yuen Long will employ about 260 and 156 workers respectively. Estimation of waste generated from the number of workers indicates that the amount of general refuse produced will be approximately 160 kg and 96 kg per day respectively. The environmental impacts caused by storage, handling, transport and disposal of general refuse could be minimised by the adoption of appropriate mitigation measures recommended in the next section.
The daily activities in LRT stops will be the main source of general refuse during the operation stage. Two garbage bins (about 0.035m3) will be provided for each LRT stop platform and there are 16 passenger stops platforms in Tin Shui Wai Reserve Zone Extension.
It is assumed that the licensed contractor would collect the refuse up to 2 times per day, therefore, the maximum daily quantity of general refuse is estimated as about 2.24 m3. Any potential impacts could be minimised by the adoption of appropriate mitigation measures recommended in the next section.
The quantity of industrial waste to be produced during the operational phase is difficult to determine at this stage. However, it is likely to be relatively small. It is not expected that storage, handling, transport and disposal of industrial waste will cause any significant environmental impact if the scrap materials are collected regularly. Other general industrial waste such as plastic, cloth and paper can be collected together with the general refuse and disposed of at licensed waste transfer or disposal facilities.
The quantity of chemical waste to be produced during the operational phase is difficult to determine at this stage, but it is likely to be relatively small. Chemical waste should be stored, handled, transported and disposed of in accordance with the Chemical Waste Regulations and Code of Practice on Packaging, Labelling and Storage of Chemical Wastes. They should be collected and transported to the CWTC or other licensed facility by a registered waste collector. No unacceptable impacts associated with the management of chemical waste during the operational phase are anticipated if appropriate handling, storage and disposal procedures are followed.
This section sets out the storage, transportation and disposal measures which are recommended to avoid or minimise potential adverse impacts associated with waste arising from the construction and operation of the proposed LRT works. For the construction phase, the Contractor should incorporate these recommendations into a comprehensive on-site waste management plan. For the operational phase, it is recommended that KCRC should incorporate the recommendations into the current waste management plan of the operation of LRT.
The waste management options can be categorised in terms of preference from an environmental viewpoint. The options considered to be more preferable have the least impacts and are more sustainable in a long term context. The hierarchy is as follow:
a) Avoidance and minimisation (not generating waste through changing or improving practices and design);
b) Reuse of materials, thus avoiding disposal;
c) Recovery and recycling, thus avoiding disposal; and
d) Treatment and disposal, according to relevant regulations, guidelines and good practice.
The Contractor should consult the Waste Disposal Authority on the final disposal of waste.
The hierarchy should be used to evaluate waste management options, thus allowing maximum waste reduction and often reducing costs. Reduction measures should be introduced at the design and construction stages, wherever possible, by careful purchasing control, reuse of formwork and good site management. By reducing or eliminating over-ordering of construction materials, waste is avoided and costs are reduced both in terms of purchasing and in disposing of wastes.
Permitted waste collectors should be used to collect and transport wastes to the appropriate disposal points. The following measures to minimise adverse impacts should be instigated:
a) Handle and store wastes in a manner which ensures that they are held securely without loss or leakage, thereby minimising the potential for pollution;
b) Use authorised or licensed waste collectors to collect the specific category of waste;
c) Remove wastes in a timely manner;
d) Maintain and clean waste storage areas regularly;
e) Minimise windblown litter and dust during transportation by either covering trucks or transporting wastes in an enclosed container;
f) Obtain the necessary waste disposal permits from the appropriate authorities, if required, in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap 354) and the Land (Miscellaneous Provisions) Ordinance (Cap 28);
g) Dispose of waste at licensed sites;
h) Develop procedures such as a ticketing system to facilities, tracking of loads, particularly for chemical waste, and to ensure that illegal disposal of waste does not occur; and
i) Maintain records of the quantities of wastes generated, recycled and disposed.
The quantity of surplus excavated material to be generated from construction of the proposed LRT works is expected to be small. However, in order to minimise the quantity of surplus excavated material to be delivered to public filling areas, the priority for off-site disposal of surplus excavated material should be considered as follows:
a) Transport to the Western Section of WR for reuse, if practicable;
b) Transport to other land formation sites in the Tuen Mun and Yuen Long areas for reuse;
c) Transport to public filling areas.
The Contractor should liaise with other Contractors who will require fill material during that period. This will minimise the quantity of inert excavated material to be delivered to public filling areas.
In order to minimise waste arisings and keep environmental impacts within acceptable levels, the mitigation measures described below should be adopted.
Careful design, planning and good site management can minimise over-ordering and waste materials such as concrete, mortars and cement grouts. The design of formwork should maximise the use of standard wooden panels so that high reuse levels can be achieved. Alternatives such as steel formwork or plastic fencing should be considered to increase the potential for reuse.
The Contractor should recycle as much as possible of the construction waste on-site. Proper segregation of wastes on site will increase the feasibility of recycling certain components of the waste stream by recycling Contractors. Concrete and masonry can be used as general fill and steel reinforcement bars can be used by scrap steel mills. Different areas should be designated for such segregation and storage wherever site conditions permit.
On-site sorting and segregation facility of all type of wastes is considered as one of the best practice in waste management and hence, should be implemented in all projects generating construction waste. The sorted public fill and construction & demolition (C&D) waste should be disposed of at the designated public filling areas and landfills, respectively.
The handling and disposal of bentonite slurries should be undertaken in accordance with ProPECC PN 1/94 [18] .
For these processes which generate chemical waste, it may be possible to find alternatives which generate reduced quantities or even no chemical waste, or less hazardous chemical waste.
Chemical waste that is produced, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, should be handled in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes as follows:
Containers used for the storage of chemical wastes should:
a) Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;
b) Have a capacity of less than 450 liters unless the specification has been approved by the EPD; and
c) Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the regulation.
The storage area for chemical wastes should:
a) Be clearly labelled and used solely for the storage of chemical waste;
b) Be enclosed on at least 3 sides;
c) Have an impermeable floor and bunding of sufficient capacity to accommodate 110% of the volume of the largest container or 20 % of the total volume of waste stored in that area, whichever is the greatest;
d) Have adequate ventilation;
e) Be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and
f) Be arranged so that incompatible materials are adequately separated.
Disposal of chemical waste should:
a) Be via a licensed waste collector; and
b) Be transported to a licensed facility to receive chemical waste, such as the Chemical Waste Treatment Centre which also offers a chemical waste collection service and can supply the necessary storage containers; or
c) Be to a reuser of the waste, under approval from the EPD.
The Centre for Environmental Technology operates a Waste Exchange Scheme, which can assist in finding receivers or buyers for the chemical wastes.
General refuse generated on-site should be stored in enclosed bins or compaction units separate from construction and chemical wastes. A reputable waste collector should be employed by the Contractor to remove general refuse from the site, separately from construction and chemical waste, on a daily or every second day basis to minimise odour, pest and litter impacts. The burning of refuse on construction sites should be prohibited.
Office wastes can be reduced through recycling of paper if volume is large enough to warrant collection. Participation in a local collection scheme should be considered if one is available.
Training should be provided to workers about the concepts of site cleanliness and appropriate waste management procedure, including reduction, reuse and recycling of wastes.
General refuse will be mainly generated from the daily activities of LRT stops. The management of LRT stops should be included in the current LR waste management plan. As mentioned in the current LR Waste Management Plan, at least 2 general garbage bins should be provided for each passenger stop, and the refuse to be collected by licensed Contractor twice per day. The small quantity of industrial waste generated can be collected together with general refuse.
Chemical waste is produced, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, and should be handled and disposed of in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Waste. For mitigation measures, the guidelines covered under the construction phase mitigation of chemical wastes should be referred.
The potential impacts of waste arising from the construction and operational stages of the proposed LRT works have been assessed as minor and insignificant.
Key issues found during the assessment include the requirement for effective waste management plan (during both the construction and operational phases), effective management of chemical/industrial and other potentially hazardous wastes, and the storage preference for reuse of clean surplus material. Waste management methods and practices and other mitigation measures have been recommended to ensure that potential impacts are avoided or controlled to acceptable levels.
The Antiquities and Monuments Ordinance[11] , provides powers for the designation of Antiquities and Monuments Sites or Declared Monuments in Hong Kong. The Ordinance provides statutory protection against the threat of development for gazetted monuments, historic buildings and archaeological sites which have been recommended by the Antiquities Advisory Board (AAB) and approved by the Chief Executive.
Deemed Monuments have been identified by AMO and agreement reached with the owners of the Monument to provide for specific measures to ensure preservation. Deemed Monuments have the potential to be upgraded to statutory Declared Monuments.
The AMO has also assigned gradings to buildings of historic interest ranging from the most valued buildings at Grade 1 down to Grade 3. This classification is for AMO internal reference and has no statutory protection power.
Although there are no statutory provisions for the protection of Sites of Historical Interest, Deemed Monuments and Graded Buildings in Hong Kong, the Government has administrative procedures which state that consideration must be given to protect listed and locally designated historic buildings and sites of cultural interest.
Section 11 (and its relevant sub-section) of the Antiquities and Monuments Ordinance requires any person who discovers an antiquity or supposed antiquity to report the discovery to the Antiquities Authority. However, procedures and mechanisms are required early in the project planning to ensure the preservation or formal notification of previously unknown archaeological resources that may be revealed or discovered during project assessment or construction.
The available technical information given in Section 4 has been reviewed with respect to the archaeological and cultural and heritage aspects.
The Archaeological Action Plan for WR has concluded that the viaduct sections from Yuen Long to Tuen Mun predominantly cross areas of low-lying land which is considered to have low archaeological potential. The Action Plan further recommends that the Contractor, when conducting the archaeological evaluation during construction phase, should adopt a 5% sampling strategy for the support columns of the viaduct. The selected column footings should be pre-excavated prior to the onset of construction activities, in order to retrieve sufficient information to assess the impact of the railway.
The Action Plan also recommends that, if pre-excavation of selected columns is not possible, the mitigation strategy should be the posting of an archaeological watching brief, although the “watch and stop” may have implications on the construction programme of the columns. The watching brief may need to be extended to cover a larger sample if positive results are gained.
The latest list for declared and deemed monuments maintained by AMO has been reviewed (Appendix 13). For the proposed LRT works in Tin Shui Wai Reserve Zone and the grade separation works in Lam Tei and Pui To Road, there are neither declared nor deemed monuments within 100m of the site boundary. It is noted that the West Rail EIA report has not indicated any declared and deemed monuments in Lam Tei and Tuen Mun areas.
AMO’s records for locations of archaeological sites were also inspected. It is noted that the nearest archaeological site identified by AMO is located near Lam Tei Village across Tuen Mun Road, and is more than 200m from the proposed LT1 grade separation work. There will not be any interface between the LT1 grade separation work and the archaeological site.
A liaison meeting was held with AMO to discuss the findings of the desktop research. The meeting concluded that a field evaluation is required for the area near the grade separation work in LT1 to confirm whether there are pre-1945 buildings or structures.
Further to the meeting with AMO, a field evaluation was carried out for the area near the grade separation work in LT1. It was noticed that all the buildings in Ng Lau Road were low-rise village houses and minor workshops. Photographs taken during the field evaluation are presented in Appendix 14. None of the buildings were pre-1945, and are well beyond the project boundary. Their architectural and historical values are relatively low, and would not be adversely affected by the proposed LRT works.
Tin Shui Wai Reserve Zone is located north of the Kingswood Villas in Tin Shui Wai Development Zone. All the proposed LRT work in Tin Shui Wai Reserve Zone will be at-grade and on ballast. According to the “Final Assessment Report, Tin Shui Wai Development Engineering Investigation for Development of Areas 3, 30 & 31 of the Development Zone and the Reserve Zone EIA”, the original fishing ponds in Tin Shui Wai Reserve Zone were filled to a minimum formation level of +5.5 mPD. The archaeological potential and value within the proposed LRT alignment are therefore considered insignificant.
After reviewing the records maintained by AMO, there are no buildings or structures of known historical interest and no identified archaeological sites that are likely to be directly impacted by the proposed LRT work in Tin Shui Wai Reserve Zone.
The grade separation work of Junction LT1 is located along Tsing Lun Road, about 350m north of the West Rail Tuen Mun North Station. The permanent grade separation work would elevate the existing track for a length of approximately 300m. Construction of concrete columns would be required for this grade separation work. The future alignment will be within the existing LRT reserve area and directly above the existing alignment. The future West Rail viaduct is aligned next to the east of the future LRT alignment. Given the close proximity between the West Rail and the proposed LRT alignments, the cultural and heritage assessment for West Rail is considered applicable to the proposed LRT works in LT1.
According to the West Rail Final Assessment Report, there are no buildings or structures of known historical interest, or identified archaeological sites that will be directly impacted by the West Rail alignment along Tsing Lung Road.
As discussed in Section 6.3, a field evaluation was conducted to identify any pre-1945 buildings or structures in the vicinity of LT1. Results indicate that there were no pre-1945 buildings or structures, and all the existing buildings were well beyond the project boundary. The construction and operation of the proposed grade separation work would therefore not have adverse cultural and heritage impacts.
Grade separation of Junctions J6, Mj7 and Mj8 are located on Pui To Road and south of West Rail Tuen Mun Centre Station.
Similar to the grade separation works in LT1, the future alignment would be directly above the existing alignment and within the existing LRT reserve area. Construction of columns would be required for the viaduct. The neighbouring areas for the 3 junctions are also within the urban area in central Tuen Mun and the industrial area located to the east of the nullah. However, a Grade III historic building named Sin Hing Tung is located at about 100m southeast of the site boundary of Junction J6. Tuen Mun Town Plaza, consisting of a podium with a highrise residential block located between Sin Hing Tung and Junction J6, has provided a substantial screening effect for the main building in Sin Hing Tung.. The large trees surrounding Sin Hing Tung also assist to isolate this historic building from the proposed grade separation at Junction J6. The proposed LRT work therefore would not have significant disturbance to the building during both operational and construction stages.
The West Rail EIA has also concluded that there are no historic buildings or structures that will be adversely affected. The construction and operation of the proposed grade separation work would therefore not have adverse cultural and heritage impacts.
The assessment has concluded that the construction and operation of the proposed LRT works would not have adverse impacts on archaeological, cultural and heritage aspects. However, it is still considered necessary for the Contractor to implement the following recommendations (similar to those for West Rail viaduct sections) during the construction phases of the viaduct structures:
a) The Contractor, when conducting the archaeological evaluation during construction phase, should adopt a minimum 5% sampling strategy for the support columns of the viaduct. The selected column footings should be pre-excavated prior to the onset of construction activities in order to retrieve sufficient information to assess the impact of the railway.
b) If pre-excavation of selected columns is not possible, the mitigation strategy should be the posting of an archaeological watching brief, although the “watch and stop” may have implications on the construction programme of the columns. The watching brief may need to be extended to cover a larger sample if positive results are gained.
c) The archaeological evaluation and watching brief must be conducted by a qualified archaeologist, who should be licensed by the Antiquities Authority before the evaluation or watching brief takes place. This licensing procedure is a statutory requirement stated in section 12 and 13 in the Antiquities and Monuments Ordinance (Cap. 53).
d) The contractor should inform AMO the time schedule of the archaeological evaluation or watching brief and notify AMO two weeks prior to the commencement of the evaluation or watching brief so as to allow AMO to arrange the on-site monitoring.
A cultural and heritage assessment has been conducted for the proposed LRT works. Relevant studies conducted for West Rail have been reviewed. The records maintained by AMO on the list of declared and deemed monuments, and location of sites of archaeological interest have also been reviewed. A field evaluation has also been conducted to verify the findings from the desktop research.
Results indicate that the operation and construction of the proposed LRT would not have adverse impacts on the cultural and heritage aspects. However, it is still recommended that the Contractor shall implement some recommendations during the construction of the columns for viaduct structures.
The landscape and visual impact assessments have been carried out in accordance with the guidelines contained in Annexes 10 and 18 of the TM-EIA.
The assessment of the potential impacts of the proposed works on the existing landscape has comprised two distinct sections as follows:
· Baseline survey, and;
· Potential landscape impacts assessment.
A baseline survey of the existing landscape character and quality has been undertaken from a combination of site inspections and desktop surveys. The landscape elements considered include;
· Local topography
· Woodland and other vegetation types
· Built form, land use and patterns of settlement
· Scenic spots
· Details of local materials, architectural styles and streetscapes
· Prominent watercourses
· Cultural and religious identity
The baseline survey will form the basis of the landscape context by describing broadly homogenous units of similar character (Landscape Character Units). The landscape character is rated into low, medium or high depending not only upon the quality of the landscape elements present but also according to their sensitivity to change and local or regional importance.
The assessment of the potential landscape impacts of the proposed development will result from:
· Identification of the sources and magnitude of impacts that would be generated during construction and operation.
· Identification of the principal landscape impacts, primarily in consideration of the degree of change to the baseline conditions.
The overall landscape impact is a product of the following factors:
· The landscape character and its sensitivity / quality;
· Source and nature of potential impacts;
· The magnitude of change caused by each of the impacts to the existing landscape;
· Tolerance of the landscape to absorb the change;
· Significance of this change in consideration of the local and regional areas and other developments;
· Cumulative effects on the landscape of this and neighbouring proposals; and,
· Identification of plant species of significant value which should be conserved.
The sensitivity / quality of the landscape will be assessed as follows:
· High: e.g. important components or landscape of particularly distinctive character susceptible to relatively small changes;
· Medium: e.g. a landscape or moderately valued characteristics reasonably tolerant to change; and
· Low: e.g. a relatively unimportant landscape able to absorb significant change.
The magnitude of the change in the landscape is classified as follows:
· High: Notable change in the landscape characteristics over an extensive area ranging to very intensive change over a more limited area;
· Medium: Moderate changes in a localised area; and
· Low: Virtually imperceptible change in any components of the landscape.
The degree of impact is considered as follows:
· Significant: adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape quality;
· Moderate: adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality;
· Slight: adverse / beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in the existing landscape quality;
· Negligible: no discernible change in the existing landscape quality.
The analysis of the degree of impact is based on the following matrix:
|
Sensitivity /
Quality |
|||
Magnitude of Change |
|
Low |
Medium |
High |
Low |
Slight Impact |
Slight/Moderate Impact |
Moderate Impact |
|
Medium |
Slight/Moderate Impact |
Moderate Impact |
Moderate/ Significant Impact |
|
High |
Moderate Impact |
Moderate/ Significant Impact |
Significant Impact |
Similar to the landscape impact assessment, the assessment of the potential visual impacts of the proposed works has two distinct stages as follows:
· Baseline survey; and,
· Visual impact assessment.
The baseline survey of views towards the proposed development is carried out by identifying:
· The visual envelope within which the proposed development may be contained either wholly or partially within views, including indirect effects such as temporary contractor's works areas.
· The visually sensitive receivers (VSRs) within the visual envelope whose views will be affected by the scheme. The sensitivity of each VSR group is also influenced by the distance and direction of view to the proposed development. The potential receivers are divided into three groups;
(a) Views from residences. This group is the most sensitive due to the high potential intrusion on the visual amenity and quality of life;
(b) Views from workplaces. This group including e.g. schools, institutions and factories are less sensitive than (a) since visual amenity is less important within the work environment, and;
(c) Views from public areas not included in (a) or (b). This group includes, e.g., public parks, footpaths, roads etc. Sensitivity of this group is relatively low and will depend on the transitory nature of the receiver with views being typically glimpsed rather than sustained for long periods.
The baseline survey will describe and record by photograph typical views from within each of the visual envelopes to form the basis of the visual character and quality of the sites. Both present and future VSRs are considered.
The sensitivity of each receiver group and quality of views is based on the following:
· High: e.g. residential properties;
· Medium: e.g. recreational facilities or partially screened views; and,
· Low: e.g. workplaces, schools etc.
The assessment of potential visual impacts will result from;
· Identification of the sources of visual impacts and their magnitude that would be generated during construction and operation.
· Identification of the principal visual impacts with particular consideration given to the degree of change to the baseline conditions.
The impact assessment will compare the typical existing views identified in the baseline survey of the key receiver groups and the potential views after the sewerage works are complete. The visual impact will result from consideration of the following:
· Character of existing view;
· Quality of existing view;
· Context, location and distance of the VSR;
· Visual receiver group sensitivity;
· Number of viewers at VSR group;
· Degree of change to existing views; and,
· Other views available to visual receiver group and cumulative effects on views of this and other neighbouring developments.
The magnitude of change to the views is classified as follows:
· High: e.g. the majority of viewers affected / major changes in view;
· Medium: e.g. many viewers affected / moderate change in view; and,
· Low: e.g. few viewers affected / minor change in view.
The degree of visual impact is rated in a similar fashion to the landscape impact described in Section 11.2, i.e. significant, moderate, slight and negligible. The impacts may be beneficial or adverse. The analysis of the degree of visual impact, i.e. the correlation between magnitude of change and sensitivity/quality is also based on the matrix illustrated in Section 11.2.
The identification of the landscape and visual impacts will highlight those sources of conflict requiring design solutions or modifications to reduce the impacts and, if possible, blend the development with the surrounding landscape. The proposed landscape mitigation measures are described and illustrated by means of site plans and simple photomontage and will take into account factors including;
· Screen planting
· Rerouting of temporary works away from woodland or areas with mature vegetation of important landscape and visual amenity;
· Views with no mitigation, with mitigation at completion and 10 years after operation.
Residual impacts are those impacts remaining after the proposed mitigation measures have been implemented. This is often 10 to 15 years after operation commences when the planting mitigation measures are deemed to have reached a level of maturity which allows them to perform their original design objectives.
The level of impact is derived from the magnitude of change which the proposals will cause to the view or landscape character which would have existed during this period if the proposed scheme had not been constructed and its ability to tolerate change, i.e. its quality and sensitivity taking into account the beneficial effects of the proposed mitigation. The degree of impact is derived from the matrix shown in Section 11.2.
The degree of impact is defined as follows:
Beneficial |
Acceptable |
Acceptable with mitigation measures |
Unacceptable |
Undetermined |
The project will complement the
landscape and visual character of
its setting, will follow the relevant planning objectives and will
improve overall landscape and visual quality |
There will be no significant effects on
the landscape, no significant visual effects caused by the appearance of the
project or no interference with key views |
There are some adverse effects, but
these can be eliminated, reduced or offset to a large extent by specific
measures |
The adverse effects are considered too
excessive and would not be reduced to an acceptable level by mitigation |
Significant adverse effects are likely
but the extent to which they may occur or may be mitigated cannot be
determined from the study.
Further detailed study will be required for the specific effects in
question. |
The proposed LRT works will be located within the designated and constructed LRT reserves as indicated on the Tin Shui Wai OZP and in accordance with the previous Engineering Investigation Report [31] for the Tin Shui Wai Area. In Tin Shui Wai, the LRT works will be part of the phased development and extension of the existing system within the New Town and will not impose constraints on existing or planned development. In Tuen Mun the proposed works comprise viaduct construction within the horizontal alignment of existing tracks and will not comprise constraint on existing or planned development.
Figures 11.1 and 11.2 indicate the key landscape character units (LCUs) within 500m of the proposed LRT works and the visual envelope / key sensitive receivers respectively (Figure 11.3). The majority of the Tin Shui Wai Reserve Zone (LCU 1) is dominated by ongoing, large scale construction work comprising mainly site formation, drainage and road infrastructure projects. To the north and west of the Reserve Zone is the nullah (LCU 5). Beyond the nullah is the greenbelt at the interface with surrounding village areas, farmland and fishponds now mainly abandoned or used for storage (LCU 6). To the south of Tin Wah Road, the landscape and visual character can be divided into three distinct types, namely; LCU 2 comprising a number of high-rise residential estates and associated commercial facilities and schools, LCU 3 dominated by the existing LRT and bus termini and LCU 4 consisting of Tin Shui Wai Park – a green ‘oasis’ in the heart of the New Town.
The roadside landscape is in varied stages of completion throughout the study area. Reserves for planting are provided on the major roads between carriageways, footpaths, cyclepaths and LRT tracks. In some areas the planting, mainly common amenity and ornamental tree and shrub species, has been completed and is generally well maintained providing an attractive screen to road and rail traffic and shade to pedestrians and cyclists.
The land use mix proposed for the Reserve Zone on the Tin Shui Wai OZP is similar to that in LCU 2. Although the majority of the northern portion of the study area is presently a featureless construction site, it will in time generally resemble the built form and landscape character of the completed portion to the south.
The proposed LRT extension comprises a loop extending from the junction of Tin Shiu Road and Tin Wing Road northwards into the Reserve Zone and returning to the existing terminus at Tin Yan Road. The LRT extension will be routed on designated reserves within the planned road corridors and its construction will not affect any vegetation. If the amenity planting in the reserves alongside the proposed LRT extension are of similar quantity and quality as the existing sections in Tin Shui Wai then the LRT at-grade should blend satisfactorily into the roadside landscape. The screening effect of the planting will improve over time as the plants mature.
The relative visual impacts of the proposed LRT extension can be estimated by considering typical views from low and high levels in adjacent areas of similar design. As is typical in areas of similar development density the visual envelope is narrow, contained by the wall effect of blocks in adjacent high rise estates. The main visually sensitive receive groups are residents overlooking the LRT and pedestrians, cyclists and road users who are in closest proximity to the tracks and LRT vehicles as they pass by, particularly at junctions and crossings. The impacts are reduced for residents in high rise blocks who typically see the LRT tracks and vehicles from a much greater distance often as a ‘bird’s eye view’. The views from different estates vary from block to block although the overall vistas are very similar. From elevated positions the LRT tracks generally blend well with the streetscape when seen in the context of broad and busy roads.
During
Detailed The
Detailed Design Cosultant should submit a Landscape Master Plan Design Stage: for
approval before the LRT construction commences.
During construction : The majority of the works will be carried out within the designated LRT reserve and can be generally screened from view by site hoarding during the construction period. The hoarding will both screen the works and protect adjacent planter and footpaths and damage. Although no topsoil has been observed within the existing and proposed LRT reserves, if any topsoil is encountered during construction it shall be carefully stockpiled and provision made for its reuse in suitable planting areas.
During operation: Adopt a similar design for planting reserves flanking the LRT extension to those already in place to provide continuity of landscape character and effective screening for pedestrians, cyclists and road users. This includes use of raised planters and planting of trees and shrubs suited to roadside conditions, eg trees with compact crown to avoid snagging LRT vehicles and overhead power cables.
The landscape and visual mitigation measures are illustrated in Figures 11.4 to 11.8.
Figure 11.9 and 11.10 indicate the key landscape character units (LCUs) within 500m of the proposed LRT works and the visual envelope / key sensitive respectively. The study area is dominated by the numerous elevated structures of the Lam Tei Interchange (LCU 1) and considerable background noise generated by traffic on Tuen Mun Road and Castle Teak Road. Crossing the site from east to west is a 400kV power line with visually intrusive pylon positions near roadside footpaths. To the north and west of the interchange are the villages of To Yuen Wai, Tuen Mun San Tsuen, San Hing Tsuen and Tsz Tin Tsuen (LCU 2). The villages comprise a mix of old and new housing in generally low-lying topography interspersed with remnants of woodland, roadside amenity planting and copses of fruit trees planted by villagers. The original farmland is now mainly abandoned or used for open storage and workshops.
New high-rise housing development currently under construction in LCU 3 to the north of Lingnan College cerates a wedge separating the low-lying landscape of the village areas to the north from the small wooded knoll and Ching Leung Nunnery complex in LCU 4. The knoll and mature vegetation cover have been retained relatively intact with surrounding low-level areas cleared for storage and future development. LCU 4 is bounded to the west by Tuen Mun Road and Tuen Mun River Channel (LCU 5) the latter including promenade footpaths with ornamental planting. Further to the west on the other side of the LRT track is Siu Hong Court (LCU 6), a high-rise development overlooking the road, railway and river channel.
The proposed LRT works comprise elevating the existing track on to a viaduct to cross Tsing Lun Road. As the horizontal alignment is similar the viaduct itself will not impact on existing vegetation or require tree felling. Instead, the main concern is the need for careful routing of temporary track diversions required during construction to avoid tree felling to the perimeter of the ball courts north of Siu Hong Court. DSD is currently carrying out works in this area and have cleared a corridor parallel to the LRT (refer Figure 11.12). The drainage corridor would be utilised for the temporary track to avoid tree felling. The belt of trees between the drainage corridor and the future LRT viaduct would be retained and continue to provide a strategic screen for users of the ball courts.
The key sensitive receivers of visual impacts will be pedestrians and road users passing by or under the viaduct. Figure 11.11 shows the visual envelope for the proposed works. The viaduct structure will obscure some overhead views for those in close proximity. However, the LRT viaduct will not be viewed in isolation. The future West Rail viaduct is located immediately adjacent to the east with the elevated portions of the Lam Tei Interchange beyond. In addition, the proposed footbridge with staircase and ramp access over Tsing Lun Road abutting the LRT viaduct to the west will be more visually prominent. Accordingly, the relative impact of the LRT viaduct is expected to be reduced in the context of the existing and other proposed road and rail development.
Residents in Siu Hong Court will have a more distant and more vertical view of the viaduct and would not have existing views obscured. The majority of views from nearby villages are screened by existing roadside or village trees and the visual impacts are not anticipated to be significant. Residents in housing estates or village areas to the east of Lam Tei Interchange will have the road and West Rail viaducts in the foreground mainly screening the LRT viaduct behind.
During Detailed The
Detailed Design Cosultant should submit a Landscape Master Plan Design Stage: for
approval before the LRT construction commences.
Carefully detailing the use of forms, colour and finishes of external appearance of all above-ground structures should be carried out so that they are visually integrated into the surrounding landscape as much as practical.
During construction : Co-ordination with current works for utility routing would help retain the trackside tree screen north of Siu Hong Court. Site hoarding will also screen the works and protect adjacent planting from damage. Any topsoil encountered during construction shall be carefully stockpiled and provision made for its reuse in suitable planting areas.
The Contractor should implement tree and shrub planting within the railway reserve to soften the visual impact of the viaduct, and make use of climbing plants to soften the appearance of viaduct column.
During operation: The design of the viaduct should be coordinated with the West Rail proposals to avoid visual clutter of different structures. In particular, the parapet detailing and column shape should be complementary. Wherever possible, the spacing of columns for the LRT and West Rail viaducts should be aligned to minimise obstruction of views under the viaducts for pedestrians and road users.
The landscape and visual mitigation measures are illustrate in Figures 11.13 & 11.14
The portion of LRT track at grade replaced by the viaduct should be removed and the area designated for amenity planting in raised planters where headroom permits. Such planting will help improve the roadside amenity for pedestrians and road users and help screen the low quality views below the viaduct to the road interchange.
Figures 11.15, 11.16 & 11.17 indicate the key landscape character units (LCUs) within 500m of the proposed LRT works and the visual envelope / key sensitive receivers respectively. The landscape character of the study area comprises a broad mix of land uses and range of good to poor quality environments. LCU 1 (Tai Hang Garden), LCU 2 (Tuen Mun San Hui) and LCU 3 (Shan King Estate) to the north and west are typical self-contained high rise residential developments with commercial facilities and schools. LCU 1 and 3 are separated by the extensive and generally unattractive industrial area (LCU 4) to the west of the river. On the opposite bank the older Housing Authority residential area of San Fat Estate (LCU 5) is proposed to be redeveloped as part of the West Rail Tuen Mun Centre Station.
LCUs 6 & 7 on the urban fringe contain mainly village settlements with some low-rise school or institute developments. There are extensive areas of attractive natural woodland behind the villages with mature copses and amenity planting extending downhill as far as Tsing Wun Road and Castle Peak Road. By far the most attractive area within Tuen Mun is the Town Park (LCU 8) which is bounded by river and promenade (LCU 11) to the west and the town centre commercial and town hall complexes (LCU 9) to the east. To the south of the park are two of the older Housing Authority developments Yau Oi Estate and On Ting Estate (LCU 10).
The proposed LRT works comprise elevating the existing track on to a viaduct to cross Pui To Road. As the horizontal alignment is similar the viaduct is not expected to have a significant impact on existing vegetation or require tree felling. One exception of major concern is in the vicinity of the town park where the column footings for the viaduct encroach on the park boundary. The earth mounding and dense tree belt along the northern and eastern boundaries of the park have been designed as a strategic buffer from the road and rail traffic. Loss of any portion of this tree belt would be an unacceptable landscape and visual impact and seriously detract from the amenity of the park. Although initial design of the viaduct indicates the footings should be clear of the trees at the bottom of the boundary of the boundary slope detailed study of the precise location of footings and works areas will be required for discussion with Regional Services Department.
The temporary track diversions at Pui To stop and Kin On stop utilise existing roads and footpaths and are not anticipated to have significant landscape or visual impacts once the project is completed and the disturbed areas reinstated. The temporary diversion south of Ho Tin stop may affect a strip of amenity shrub planting and will require detailed route selection to utilise footpaths areas as far as possible. If the planter is disturbed, there would be no permanent landscape or visual impacts once reinstated upon completion.
In addition to track diversions three footbridges will be demolished / redesigned to accommodate the elevated portion of the LRT. The first footbridge affected, between the town park and the town centre, will stop east of the viaduct and provide access via stops to street level and connect unobtrusively to the park by a new footpath under the viaduct. The second footbridge which links the town park and promenade to the San Fat stop and San Fat Estate will be truncated to the north of the viaduct and be incorporated into the new station building. The third footbridge is located along the west bank of the river and is not intended to be reprovisioned. No significant landscape or visual impacts are anticipated as a result of the footbridge works.
The major visual impacts will be caused by introducing the viaduct over existing heavily trafficked road junctions where large numbers of pedestrians and road users will pass alongside or under the elevated structures. When the viaduct is seen against other higher structures such as the new Tuen Mun Centre Station or factory buildings west of the river the relative impact is less. However, when viewed at street level against the backdrop of the town park or in isolation crossing Tuen Mun Heung Sze Wui Road the viaduct will be more intrusive and will obstruct overhead views. Views from within the town park are well screened by a continuous belt of mature trees around the perimeter adjacent to the proposed viaduct. It should be reiterated that any alignment or temporary diversion during construction that affects the tree screenbelt in the town park should be avoided. The other low-level views of the viaduct are from the river promenade. Figure 11.18 indicates the visual envelope in the absence of the proposed Tuen Mun Centre Station with long uninterrupted views of the viaduct as it crosses the river from as far north as the footbridge at Ho Tin stop and as far south as Yau Oi Estate. After construction of the Tuen Mun Centre Station the river portion of the viaduct will be incorporated into the station building and will not be visible.
The visual envelope for high level sensitive receivers is relatively contained by the high-rise developments bordering the river channel and road corridors, i.e. San Fat Estate, Tuen Mun Town Plaza and the factories to the west of the river. One exception is residents on upper floors of Yau Oi Estate who will view the viaduct and the proposed Tuen Mun Centre Station complex over the town park. However, this view is relatively distant (approximately 500m) and is not anticipated to be significant. The visual impacts from the factories parallel to the river and along Pui To Road are not considered to be high as workers’ attention is not normally focused on outside views. Residents in upper floors of tower blocks close to the LRT alignment have a nearly vertical view of the viaduct and the elevation of the track is therefore less evident. The viaduct does not obstruct views and is seen in the context of the road network resulting in relatively low visual impacts.
During Detailed The
Detailed Design Cosultant should submit a Landscape Master Plan Design Stage: for
approval before the LRT construction commences.
Carefully detailing the use of forms, colour and finishes of external appearance of all above-ground structures should be carried out so that they are visually integrated into the surrounding landscape as much as practical.
During Construction: It will not be possible to totally screen the proposed works for the viaducts. Hoarding will help screen the ground level work site and protect adjacent planting or footpaths from damage. Any topsoil encountered during construction shall be carefully stockpiled and provision made for its reuse in suitable planting areas.
The Contractor should implement tree and shrub planting within the railway reserve to soften the visual impact of the viaduct, and make use of climbing plants to soften the appearance of viaduct column.
During Operation: Similar to the construction phase, the viaducts cannot be totally screened by landscape mitigation measures. However, once the viaduct is complete the areas below will be returned to Government and it is proposed that, wherever feasible, the opportunity is taken to enhance the roadside amenity by reinstatement using raised planters and ornamental planting. Use of shade tolerant palm and shrub species and trees with compact crowns, wherever headroom and light levels below the viaduct permit, is recommended to have the maximum effect (Figures 11.19 to 11.23).
The portion of track between the two footbridges to be demolished connecting to the town park offers a good opportunity to provide an amenity area with ornamental planting, seating and footpath connection at grade below the viaduct. The current design of the viaduct is pairs of steel portals with cladding supporting the overhead deck. By suspending an arched decorative steel or aluminum frame between the columns an otherwise plan, impersonal structure can become a more attractive colonnade providing shade to pedestrians. Although the viaduct design is still under investigation it is recommended that the overall structure be as light in form as possible and have a rounded and tapered profile rater than an angular box-like form. The decorative arch panels described above would be consistent with this design objective.
The proposed landscape and visual impact mitigation measures are off-site, ie, the screen planting will be located in existing amenity planters or planters currently under construction, provided by Government, as part of the road / LRT infrastructure in Tin Shui Wai. In the Tuen Mun area the proposed planting would be located below the viaduct structures where feasible. Funding and implementation of the planters will be by Territory Development Department with Highways Department and Regional Services Department responsible for management and maintenance of hard landscape (raised planter walls) and soft landscape works respectively (Appendix 15). TDD have confirmed that the landscape hardworks and softworks will be completed under ongoing TDD construction contracts before the LRT commence operation. Areas below proposed viaducts in Tuen Mun are still subject to detailed design and on-going policy discussion regarding end usage.
Landscape Character Unit
(LCU) |
Description |
Quality/ Sensitivity |
Magnitude of Change |
Impact |
Degree of impact without mitigation |
|
|
|
|
|
|
During
Construction |
During
Operation |
Tin Shui Wai Reserve Zone |
||||||
LCU 1 |
Majority of LCU
1 is currently a vast construction site. Upon completion this area will be predominantly high-rise
residential estates bordering both sides of road and rail corridors similar
to southern portion of Tin Shui Wai |
Low |
Low |
Route of
proposed LRT located within designated roadside reserves with no loss of
vegetation. |
Slight adverse |
Slight adverse |
LCU 2 |
Generally
completed belt of high-rise residential estates with associated, schools, commercial
centre, amenity planting and road / LRT infrastructure. |
Low |
Low |
Route of
proposed LRT located within designated roadside reserves with no vegetation
loss. |
Slight adverse |
Slight adverse |
LCU 3 |
Landscape
dominated by extensive at-grade LRT and bus termini. |
Low |
Low |
Route of
proposed LRT located within designated roadside reserves with no vegetation
loss. |
Slight adverse |
Slight adverse |
LCU 4 |
Tin Shui Wai
District Park comprising comprehensively landscaped recreational facilities
providing green ‘oasis’ in the center of the New Town. |
Medium |
Nil |
Route of
proposed LRT extension does not encroach on this LCU. |
Nil |
Nil |
LCU 5 |
Nullah
comprising engineered embankments and amenity tree planting |
Low |
Nil |
Route of
proposed LRT extension does not encroach on this LCU. |
Nil |
Nil |
LCU 6 |
Urban fringe
area comprising former farmland / fishponds new mainly abandoned or used for
storage |
Low |
Nil |
Route of
proposed LRT extension does not encroach on this LCU. |
Nil |
Nil |
Grade Separation at Tsing Lun Road |
||||||
LCU 1 |
Lam Tei Highway
interchange dominated by numerous elevated road structures and at-grade
sliproads. Predominately grass
covered embankments with small groups of amenity tree planting. |
Low |
Low |
Existing LRT
will be elevated at the junction of Tsing Lun Road following existing
horizontal alignment. No loss of
vegetation anticipated. |
Slight adverse |
Slight adverse |
LCU 2 |
Extensive
village areas bisected by road and rail corridors. Mix of old and new housing in generally low-lying
topography. Remnants of woodland, roadside amenity planting and copses of
fruit trees throughout. Original
farmland mainly abandoned or used for open storage or workshops. |
Low |
Low |
Exiting LRT will
be elevated at the junction of Tsing Lun Road following existing horizontal
alignment. No loss of vegetation. |
Slight adverse |
Slight adverse |
LCU 3 |
Extensive
redevelopment area. High-rise
housing under construction |
Low |
Nil |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
Grade Separation at Tsing Lun Road |
||||||
LCU 4 |
Nunnery complex
and wooded knoll isolated within highway infrastructure |
Medium |
Nil |
LRT works do not
encroach on this LCU |
Nil |
Nil |
LCU 5 |
Tuen Mun River
Channel comprising engineered embankments and landscaped footpath / cyclepath
promenade parallel to existing LRT |
Medium |
Nil |
LRT works do not
encroach on this LCU |
Nil |
Nil |
LCU 6 |
Siu Hong Court
high-rise residential development.
The recreational area contains a dense tree belt bordering the LRT
route. |
Medium |
Low Medium |
The existing LRT
will be elevated at the junction of Tsing Lun Road following existing
horizontal alignment. No loss of
vegetation. Temporary track
alignment during construction will encroach on ball court. Use of previously cleared route by
DSD will avoid trees. |
Slight adverse Moderate adverse |
Slight adverse |
Grade Separation at Pui To Road |
||||||
LCU 1 |
Tai Hang Garden.
Self contained high-rise residential estate with commercial centre and
landscaped open space. |
Medium |
Nil |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
LCU 2 |
Tuen Mun San
Hui. Self-contained high-rise
residential estate with commercial centre and landscaped open space. |
Medium |
Nil |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
LCU 3 |
Shan King
Estate. Self-contained high-rise
residential estate with commercial centre and landscaped open space. |
Medium |
Nil |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
LCU 4 |
Industrial area
comprising extensive area of generally unattractive factory / warehouse buildings of poor landscape
character, dominated by goods vehicle traffic and existing LRT |
Low |
Low |
Part of the
existing LRT within the industrial area will be elevated following the
existing horizontal alignment.
No loss of vegetation. |
Slight adverse |
Slight adverse |
LCU 5 |
San Fat
Estate. Older generation Housing
Authority Estate planned for redevelopment for proposed West Rail
station development. |
Low |
Low |
Proposed
elevated portion of LRT, parallel to southern perimeter, will not result in
loss of vegetation. |
Slight adverse |
Slight adverse |
LCU 6 |
Urban fringe
comprising mainly village settlements, pockets of woodland and low-rise
school or institute developments. |
Medium |
Nil |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
LCU 7 |
Urban fringe
comprising mainly village settlements, pockets of woodland and low-rise
school or institute developments. |
Medium |
Nil |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
LCU 8 |
Town Park
comprising generously landscaped recreational facilities as a green ‘oasis’
in the centre of the New Town. |
Medium |
Medium |
Route of LRT
grade separation to follow existing horizontal alignment around north and
north-east park boundary.
Potential encroachment of column foundations into town park and
disturbance of grass and shrub planting during construction |
Moderate adverse |
Moderate adverse |
LCU 9 |
Town centre
commercial and town hall complex comprising mainly podium level open space
and landscaped garden. |
Low |
Low |
LRT works do not
encroach on this LCU. |
Nil |
Nil |
LCU 10 |
Older Housing
Authority estates of Yau Oi Estate and On Tong |
Low |
Nil |
Route of
proposed LRT grade separation does not encroach on this LCU. |
Nil |
Nil |
LCU 11 |
Tuen Mun River
Channel comprising engineered embankments and landscaped promenades |
Medium |
Medium |
Route of LRT
grade separation to follow horizontal alignment at river crossing, mainly
contained within structure of West Rail Tuen Mun Central Station building. |
Moderate adverse |
Moderate adverse |
Table 11.1: Summary of Landscape Analysis and Impact Assessment
Key Visually Sensitive
Receivers |
Typical Viewpoint |
Quality/ Sensitivity |
Magnitude of Change |
Impact |
Degree of impact without mitigation |
|
|
During construction |
During operation |
||||
Tin
Shui Wai Reserve Zone |
||||||
Residential
(High
Level) ·
Tin
Shui Estate ·
TSYTL
No 3 ·
TSYTL
No.5 ·
Future
residents in Areas 30, 31, 101, 102, 103, 105, 106, 108B, 110, 111, 112 &
115 |
Typical
views from upper floors of the housing estates noted, bordering the proposed
LRT route, are generally similar. That is, views are relatively short being
contained by adjacent high-rise estates on both sides of LRT/road corridors
resulting in narrow visual envelope. |
High |
Low |
LRT
will be located within designated at grade reserves, under construction, and
will not obstruct views of high level VSRs. |
Moderate adverse |
Moderate adverse |
Residential
(Low
Level) Above
residential areas and villages |
Typical
views from lower floor of the housing estates noted, bordering the proposed LRT
route, are generally similar. That is, dominated by road infrastructure and
adjacent high-rise buildings. |
High |
Low |
LRT
will be located within designated at grade reserves, under construction, and will
not obstruct views, particularly when seen in context of adjacent road
infrastructure. |
Moderate adverse |
Moderate adverse |
Pedestrians,
cyclists and road users |
Views
will be generally short being contained by adjacent high-rise buildings and
roadside amenity planting similar to southern portion of Tin Shui Wai. |
Low |
Medium |
LRT
will be located within designated at-grade reserves under construction.
Visual intrusion by passing LRT vehicles reduced as LRT seen in context of
road infrastructure. |
Slight / Moderate adverse |
Slight / Moderate adverse |
Open
area (Area 107) |
Low-rise
views will be generally contained by perimeter structure planting with high-rise
buildings as surrounding backdrop. |
Medium |
Low |
LRT
will be located within designated at-grade reserves under construction.
Visual intrusion by passing LRT vehicles beyond open space entrance as LRT
seen in context of road infrastructure. |
Slight/ moderate
adverse |
Slight/
moderate adverse |
Grade
Separation at Tsing Lun Road |
||||||
Residential (High
level) ·
Sui
Hong Court ·
Botania
Villa ·
Future
high-rise estate in Area 22 ·
Mui
Fat Buddhist Monastery |
Long
distance views of residential areas noted across valley to distant hill
ranges. Medium to short distance
views dominated by road interchange |
High |
Low |
LRT
works will comprise elevating existing track on to viaduct. Siu Hong Court residents would see
LRT viaduct from above and on end.
Relatively low impact overall when seen in context of road viaducts
and proposed West Rail viaduct.
More distant views from Area 22, Bontania Villa and Mui Fat Buddhist
Monastery have Lam Tei Interchange and West Rail viaduct in foreground
generally concealing LRT viaduct beyond. |
Moderate
adverse |
Moderate
adverse |
Resident (Low
level) |
Some
long distance views across valley to distant hill ranges with some obstruction
by Lam Tei Interchange, particularly medium to short distance views. |
High |
Low |
LRT
viaduct closer to low level viewer in Siu Hong Court although impact reduced
by on-end view and context of highway infrastructure. Low level views of LRT viaduct from
Area 22, Bontania Villa and Mui Fat Buddhist Monastery screened by road
interchange. |
Moderate
adverse |
Moderate
adverse |
Pedestrians,
cyclists and road users |
Medium
to long distance views typically screened by proximity to roadside trees in
low-lying topography and dominated by LRT, road structures and high voltage
pylons. |
Low |
Low |
Cumulative
effect of road, West Rail and LRT viaducts will further obstruct views from
west. LRT viaduct generally
screened behind interchange when viewed from street level east of Lam Tei
Interchange. |
Slight
adverse |
Slight
adverse |
Pui
To Road Grade Separation |
||||||
Residentail
(High
Level) ·
San
Fat Estate ·
Tuen
Mun Town Plaza ·
Yau
Oi Estate ·
On
Ting Estate |
Majority
of medium length views towards attractive town park and open vistas along
river channel. Longer views from
housing estates over unattractive industrial area, across valley to Castle
Peak. |
High |
Low |
High
level viewpoints close to the LRT alignment not obstructed and viaduct less
noticeable when seen from above against adjacent road network. VSRs in more distant locations in Yau
Oi and On Ting Estates see more of the viaduct elevation in the more exposed
river channel portion. However,
distance diminishes the overall impact and future West Rail Tuen Mun Centre
Station will be more dominant. |
Moderate
adverse |
Moderate
adverse |
Industrial area |
Views
within industrial area typically short, unattractive and contained by
proximity of adjacent buildings.
Building design not intended for workers external views. |
Low |
Low |
Focus
of workforce in industrial area, including police station and bus depot is
generally not on external features.
LRT viaduct follows existing horizontal track alignment and is not
expected to significantly alter overall quality of views within industrial area. |
Slight adverse |
Slight adverse |
Residential
(low
level) |
Majority
of views dominated by town park and river channel vistas. Longer views generally contained by
surrounding high-rise estates |
High |
Low |
LRT
viaduct more prominent to low-level residential units, particularly in San
Fat Estate and Tuen Mun Town Plaza. Context of road infrastructure in
foreground reduces overall impact. |
Moderate adverse |
Moderate adverse |
Town Park |
Long
distance views from within town park to hills beyond and up and down river
from promenade |
Medium |
Low |
Views
to LRT from park mainly screened by boundary tree belt. |
Slight / moderate adverse |
Slight / moderate adverse |
Pedestrian
cyclists and road users |
Short
views by roadside dominated by traffic and road structures |
Low |
High |
LRT
viaduct will be most visually prominent when seen from street level partially
obstructing views towards the park and along the river. General familiarity with existing LRT
viaducts and use of existing horizontal alignment will help reduce overall
impact. |
Moderate adverse |
Moderate adverse |
Table 11.2: Analysis of Visually Sensitive Receivers and Impact Assessment
Landscape Character Unit (LCU) |
Sources of Impact |
Magnitude of change |
Landscape
Quality / Sensitivity |
Mitigation
Measures |
Residual
Impact after implementation of mitigation measures |
||
|
|
Construction |
Operation |
|
|
Construction |
Operation |
Tin Shui Wai Reserve Zone |
|||||||
LCU 1 |
No loss of
vegetation LRT to occupy
planned reserves under construction |
Low |
Low |
Low |
Planting to planters under construction adjacent to
LRT reserve |
Slight adverse |
Slight adverse |
LCU 2 |
No loss of
vegetation LRT to occupy
planned reserves under construction |
Low |
Low |
Low |
Planting to planters constructed adjacent to LRT
reserve. |
Slight adverse |
Slight adverse |
LCU 3 |
No loss of
vegetation LRT to occupy
planned reserves under construction |
Low |
Low |
Low |
Planting to planters constructed adjacent to LRT
reserve |
Slight adverse |
Slight adverse |
LCU 4 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
LCU 5 |
No encroachment /
loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
LCU 6 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
Grade Separation at Tsing Lun Road |
|||||||
LCU 1 |
Viaduct over
existing track – no vegetation loss |
Low |
Low |
Low |
N/A |
Slight adverse |
Slight adverse |
LCU 2 |
Viaduct over
existing track – no vegetation loss |
Low |
Low |
Low |
N/A |
Slight adverse |
Slight adverse |
LCU 3 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
LCU 4 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 5 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 6 |
Viaduct over
existing track – no vegetation loss Temporary track
diversion encroaches on ball court |
Medium |
Low |
Medium |
Careful route selection for temporary diversion to
use existing cleared land and avoid exsting trees. Full reinstatement upon completion. Designate area below viaduct for
amenity planting. |
Moderate adverse |
Moderate adverse |
Pui To Road Grade Separation |
|||||||
LCU 1 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 2 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 3 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 4 |
Viaduct over
existing track – no vegetation loss |
Low |
Low |
Low |
Designate area below viaduct for amenity planting |
Slight adverse |
Slight adverse |
LCU 5 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
LCU 6 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
LCU 7 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Low |
N/A |
Nil |
Nil |
LCU 8 |
Potential
encroachment of viaduct column footings into Town Park with disturbance to
grass / shrub planting during construction |
Medium |
Medium |
Medium |
Careful selection of column foundation locations to avoid
felling park trees and reinstate disturbed areas upon completion. Designate area below viaduct for
amenity planting / footpath |
Moderate adverse |
Moderate adverse |
LCU 9 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 10 |
No encroachment
/ loss of vegetation |
Nil |
Nil |
Medium |
N/A |
Nil |
Nil |
LCU 11 |
Viaduct over
existing track – no vegetation loss.
Alignment contained partly within future West Rail TM Central Station. |
Medium |
Medium |
Medium |
Designate area below viaduct for amenity planting /
footpath |
Moderate adverse |
Moderate adverse |
Table 11.3 Summary of Mitigation Measures and Residual Landscape Impacts
Visually Sensitive Receivers |
Sources of Impact |
Magnitude of change |
Visual Quality/ Sensitivity |
Mitigation Measures |
Residual impact after implementation of mitigation
measures |
||
|
|
Construction |
Operation |
|
|
Construction |
Operation |
Tin Shui Wai
Reserve Zone |
|||||||
Residents of Tin
Shui Estate TSYTL 3 TSYTL 5 Future housing
in Areas 30, 31, 101, 102, 103, 105, 106, 108B, 110, 111, 112 & 115 (High level) |
LRT will occupy
designated reserves generally blending with road infrastructure |
Low |
Low |
High |
Screening
planting to planters constructed adjacent to LRT |
Moderate adverse |
Moderate adverse |
Residents (Low level) |
LRT closer to
viewer but will occupy designated reserves and generally blend with road
infrastructure |
Low |
Low |
High |
Screening
planting to planters constructed adjacent to LRT |
Moderate adverse |
Moderate adverse |
Pedestrians
cyclists and road users |
Intrusion from
passing LRT vehicles at grade reduced by background context of road traffic |
Medium |
Medium |
Low |
Screening
planting to planters constructed adjacent to LRT |
Slight / moderate adverse |
Slight / moderate adverse |
Open space (Area 107) |
Minor intrusion
by passing LRT vehicles reduced by background context of road traffic |
Low |
Low |
Medium |
Screening
planting to planters constructed adjacent to LRT |
Slight / moderate adverse |
Slight / moderate adverse |
Grade separation of Tsing Lun Road |
|||||||
Residents of Siu
Hong Court Botania Villa Future housing in Area 22 Mui Fat Buddist Monastery (High Level) |
Viaduct located
over existing tracks. Impact
reduced when seen from above and in context of adjacent elevated road
interchange and future parallel West Rial viaduct. |
Low |
Low |
High |
Sensitive
structural deisgn to complement adjacent viaducts. |
Moderate adverse |
Moderate adverse |
(Low level) |
Although the LRT
viaduct is closer to viewer, the road interchange viaduct will dominate
views. |
Low |
Low |
High |
Sensitive
structural design to complement adjacent viaducts. |
Moderate adverse |
Moderate adverse |
Pedestrian, cyclists
and road users |
LRT visduct
generally screened when viewed from east of the Lam Tei Interchange. Viewed from west, impact reduced by
context / backdrop of road and future West Rail viaducts. |
Low |
Low |
Low |
Sensitive
structural design to complement adjacent viaducts including coordination of
column alignments to increase visual permeability below structures. |
Slight adverse |
Alight adverse |
Pui To Road Grade Separation |
|||||||
Residents of San
Fat Estate Tuen Mun Town Plaza, Yau Oi Estate (High Level) |
Viaduct located
over existing tracks. Impact
reduced when seen from above and in context of road infrastructure. |
Low |
Low |
High |
Sensitive
structural design to present simple uncluttered outline to viaduct. |
Moderate adverse |
Moderate adverse |
(Low Level) |
Although the LRT
viaduct is closer to viewer, the impact is reduced by the dominant scale of the
dominant scale of the adjacent road infrastructure. |
Low |
Low |
High |
Sensitive
structural design to present simple uncluttered outline to viaduct. Designated area below viaduct for
amenity planting. |
Moderate adverse |
Moderate adverse |
Industrial Area |
Viaduct located
over existing tracks. Impact
reduced due to context of road / industrial infrastructure. |
Low |
Low |
Low |
Sensitive
structural design to present simple uncluttered outline to viaduct. Designated area below viaduct for
amenity planting. |
Slight adverse |
Slight adverse |
Town Park |
Views to LRT
viaduct generally screened by boundary tree belt |
Low |
Low |
Medium |
Retain
existing tree belt to park boundary |
Slight / moderate adverse |
Slight / moderate adverse |
Pedestrians,
cyclists and road users |
LRT viaduct will
be most prominent from street level partially obstructing views towards the
town park and along the river |
High |
High |
Low |
Sensitive
structural design to present simple uncluttered outline to viaduct. Designated area below viaduct for
amenity planting. |
Moderate adverse |
Moderate adverse |
Table
11.4 Summary
of Mitigation Measures and Residual Visual Impacts
Tin Shui Wai Reserve Zone
Due to the LRT being entirely located in designated reserves there is no loss of vegetation neither during construction nor operation.
Tsing Lun Road Grade Separation
Disturbance to ball court during construction. Detailed tree survey and route selection required to avoid tree belt for temporary track diversion.
Pui To Road Grade Separation
Detailed tree survey and route selection required to avoid tree belt in Town Park and promenade planters for temporary track diversion.
The three packages of LRT alterations that have been assessed in the EIA present different site specific landscape and visual impacts. The Tin Shui Wai Extension has the advantage of making use of planned reserves to be constructed in parallel with the road infrastructure. The appearance of the extension will be similar to those portions of track already in use throughout Tin Shui Wai. At Tsing Lun Road and Pui To Road in Tuen Mun the existing track has to remain in operation during construction and this has required identification of temporary diversions and alternative viaduct designs which are still under investigation. Landscape and visual impact mitigation measures have been proposed which are intended to integrate the new development into the streetscape and coordinate with other related developments. It is considered that these mitigation measures as well as the general public familiarity with the LRT in Tin Shui Wai and Tuen Mun should ensure that the landscape and visual impacts will be generally acceptable.
.
Environmental Monitoring and Auditing (EM&A) is an important aspect in EIA studies. It specifies the time frame and responsibilities for the implementation of the environmental mitigation measures identified in the EIA process. Requirements on the monitoring (including baseline and impact monitoring) will be given.
The EM&A system to be adopted should be systematic, efficient and with clear line of authority. A common approach to EM&A is for the EIA consultant to devise an EM&A manual for the concerned project, based on the latest information available during the EIA stage. The manual should specify the following:
· Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET) with respect to the environmental monitoring and audit (EM&A) requirements during construction;
· Information on project organisation and programming of construction activities for the project;
· Requirements with respect to the construction schedule and the necessary environmental monitoring and audit programme to track the varying environmental impact;
· Full details of the methodologies to be adopted, including all field, laboratory and analytical procedures, and details on quality assurance;
· Definition of Action and Limit levels;
· Establishment of event and action plans;
· Requirements of reviewing pollution sources and working procedures required in the event of non-compliance of the environmental criteria and complaints;
· Requirements for review of EIA predictions, implementation of mitigation measures, and the effectiveness of the environmental protect and pollution control measures adopted;
· Requirements of presentation of environmental monitoring and audit data and appropriate reporting procedures.
An EM&A Manual for this EIA study has been prepared based on the latest available information and EPD’s generic EM&A manual. An Implementation Schedule is also included in the EM&A Manual.
The Contractor shall be requested to review the mitigation measures and Implementation Schedule with respect to the design developments during the Detailed Design Stage and their construction methodology. In case where the Contractor needs to update the mitigation measures and the Implementation Schedule, a updated EM&A shall be submitted to the Environmental Manager for approval. The Contractor shall seek EPD’s prior approval on these amendments before construction commences.
An Implementation Schedule has been prepared to summarise all the required mitigation measures that need to be implemented during the design, construction and operation of the proposed LRT Works (see EM&A Manual and Section 15). The implementation responsibilities are also identified.
For the effective implementation of the mitigation measures, monitoring and remedial requirements presented in the EIA, EM&A and Implementation Schedule (IS), a systematic Environmental Management Plans (EMP) shall be set up by the Contractor. KCRC will audit against the EMP and advise the necessary remedial actions required. These remedial actions shall be enforced by the Engineer through contractual means.
The EMP will require the Contractor (together with it’s sub-contractors) to define in details how to implement the recommended mitigation measures in order to achieve the environmental performance defined in the Hong Kong Environmental Legislation and the EIA documentation.
In the first instance, each Tenderer shall prepare a skeletal EMP for submission as part of the tendering process; the skeletal EMP will demonstrate the determination and commitment of the organisation and indicate how the environmental requirements laid out in the available EIA documentation will be met. It is a clear indication to all Tenderers of the Corporation’s commitment to the minimisation and management of environmental impacts. Upon Contract Award, the successful Tenderer shall be required to submit a draft EMP for the approval of the Engineer and a final version prior to the commencement of the works.
Under the EMP, the Contractor is recommended to define the significant environmental aspects for each construction activities, identify the legal requirements need to comply with, setup an objective and target in order to achieve the requirements. The environmental management programme shall be formulated. The structure and responsibilities of each operation team leaders shall be identified. Appropriate training shall be provided to both management and working levels in order to meet the specified performance. Channels of communication, document control, operational control and emergency procedure shall be listed out in details in the EMP. The checking and corrective action procedures, together with the Contractor’s management review procedure shall be elaborated. This requirement shall be put down as the tender requirement.
The environmental performance review programme comprises the regular assessment of the effectiveness of the EMPs. Specifically it shall ensure that the environmental aspects are correctly identified, site practices and procedures are being followed, reliable internal audit work are in placed, and environmental standards are maintained.
The criteria against which the reviews will be conducted shall be derived from:
· The approaches, procedures and commitments given by the Contractor in the EMP;
· The clauses contained within the Contractual Documentation; and
· Those parts of the Contractor’s Method Statements which relate to the minimisation of environmental impacts
The review of on-site environmental performance shall be undertaken by KCRC through a systemic checklist and audit trail once the project commences. Objective evidence shall be inspected in the following areas:
· The identification and evaluation of significant environmental aspects;
· The consequent objectives and targets;
· The performance monitoring, measuring, reporting and review against the objective and targets;
· The effectiveness of the environmental management activities;
· The speed and effectiveness of response to complaints; and
· The way to handle frequent non-compliance.
An EIA study has been completed for the proposed LRT works in Tin Shui Wai Phase 4 area, according to the requirements given in the EIA study brief and the TM-EIA. The environmental aspects that have been thoroughly studied include:
· Air quality;
· Operational noise;
· Construction noise;
· Water quality;
· Waste management;
· Cultural heritage;
· Landscape and visual impacts; and
· Environmental monitoring and auditing
Environmental assessments have been conducted based on the latest information available during study period. Assessment methodologies are consistent with the methodologies adopted in other similar EIA studies. Results indicate that the proposed LRT would not impose adverse impacts on the neighbouring environmental sensitive receivers provided appropriate mitigation measures are implemented.
A brief summary of the mitigation measures is given below for easy reference. The Implementation Schedule in the EM&A manual provides more detailed information on when these measures are required and the corresponding responsibility for implementation.
Aspect |
Key Mitigation Measures (see
Sections 5 to 12, & EM&A Manual for details) |
Air quality |
· The Contractor to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation during the construction stage |
Operational noise |
During the operational stage, · The railway operator should ensure that the worst-case noise level of 65 dB(A) Lmax at 25m from straight and well maintained ballast track is always achieved. During the design stage, the Detailed Design Consultant should · Ensure that the structure re-radiated noise from viaduct structure is at least 10dB(A) below the noise criteria of 65dB(A) Lmax at 25m, at 50kph. · Ensure a maximum noise level of 66dB(A) at 2m from transformer bays in rectifier stations. · Orientate the open side of transformer bays in rectifier station to face away from the nearest NSRs, and preferably facing onto a main road, if practicable. · Conduct a review on ventilation systems in the rectifier stations to determine the need for any noise attenuation (eg silencers, acoustic louvres etc). |
Construction noise |
The Contractor should adopt the following · Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme; · Machines and plant (such as trucks, cranes) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum; · Plant known to emit noise strongly in one direction, where possible, be orientated so that the noise is directed away from nearby NSRs; · Silencers or mufflers on construction equipment should be properly fitted and maintained during the construction works; · Mobile plant should be sited as far away from NSRs as possible and practicable; and · Material stockpiles, mobile container site office and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities. · Scheduling of construction activities outside school examination periods; · Use of quiet equipment and working methods; · Use of purpose-built temporary noise screens; · Delocalisation of plant items; and · Sequential operation of plant items. |
Water quality |
During construction stage, the Contractor should · Use sediment / silt traps · Provide adequate maintenance of drainage systems to prevent flooding and overflowing · Provide portable chemical toilets and sewage holding tanks and employ a licenced Contractor for waste disposal. During the design stage, the Detailed Design Consultant should · Provide a surface water drainage system to collect track runoff (with oil / grit interceptors / chambers or sub-soil drainage system, where necessary. During the operational stage, the railway operator should · Clean and maintain the oil / grit interceptors / chambers regularly. |
Waste management |
During the construction stage, the Contractor should · Adopt good site management practices to minimise the production of waste During the operational stage, the railway operator should · Employ a licenced waste collectors for refuse |
Cultural heritage |
During the construction stage, the Contractor should · Conduct a 5% sampling strategy (for archaeological evaluation) for the support columns of the viaduct · Adopt a archaeological watching brief, if necessary |
Landscape and visual impacts |
· The Detailed Design Consultant should adopt a similar design for planting reserves flanking the LRT extension for those already in place to provide continuity of landscape character and effective screening for pedestrains, cyclists and road users. · The Detailed Design Consultant should submit a Landscape Master Plan for approval. · Carefully detailing the use of forms, colour and finishes of external appearance of all above-ground structures should be carried out so that they are visually integrated into the surrounding landscape as much as practical. · The Contractor should implement tree and shrub planting within the railway reserve to soften the visual impact of the viaduct, and make use of climbing plants to soften the appearance of viaduct column. · The Contractor should provide hoarding to all works area boundary to protect adjacent operation. · Territory Development Department should implement planting to planter reserves alongside LRT alignment and maintained by Highway Department (planter walls) and Regional Services Department (softworks). Programme is subject to TDD detailed schedule of works. |
EM&A |
· The Contractor and the Detailed Design Consultant should implement the mitigation measures as specified in the EM&A manual and the Implementation Schedule. |
According to the OZP S/TSW/3, there would be about 129,000 population in Tin Shui Wai reserve zone. Starting from the existing LRT junction at Tin Wing Road and Tin Shui Road, the proposed LRT work in the Reserve Zone pass along various future development lots and joins the junction between Tin Wing Road and Tin Shing Road. The proposed LRT route is developed along a gyratory system that runs around the area to provide efficient services to the surrounding developments. Along the alignment, there are mainly residential building and school developments in the Reserve Zone. The key environmental issues that have been identified in this study are operational noise, construction noise, landscaping and visual impacts. The assessment works carried out in this study has concluded that the environmental impacts can be controlled to within the statutory standards, with the implementation of the appropriate mitigation measures.
Construction noise mitigation measures are recommended in this report for implementation by the contractors. The residential blocks and schools would be exposed to cumulative construction noise impacts (including the impacts from West Rail) that are within the statutory noise limits. Operational noise is controlled through a rigorous specification of the rolling stock and a pragmatic preventive maintenance schedule. The electric train operation of the LRT system means that the local environment will have less air pollution impacts, as compared to a road network. There is a net environmental benefit to the whole 129,000 population in the reserve zone.
The key
landscape and visual elements of the proposed works, which contribute to the
overall environmental outcome are the continuity of design and character of the
existing LRT system. Extension of
the tracks in Tin Shui Wai Reserve Zone will be in planned and landscaped
reserves comprising raised planters with ornamental tree and shrub
planting. These reserves are
consistent in design to those of adjoining areas and have the dual purpose of
screening views of both LRT and road traffic as well as providing shade and
colour to adjacent footpaths and cyclepaths. Within Tuen Mun, the proposed viaduct works are contained
within the existing rail corridor avoiding loss of amenity planting, footpaths
or other public facilities. The
viaduct design will be consistent with that of existing viaducts elsewhere
throughout the Tuen Mun, Tin Shui Wai and Yuen Long. Wherever possible, the space remaining under the viaducts
will be provided with amenity planting representing a net gain in planting
compared with the existing at grade tracks.
A list of the key environmental mitigation measures for various aspects are summaried in Section 13.
The Implementation Schedule for the mitigation measures during both operational and construction phases of the project is attached for reference.
Implementation Schedule of
Recommended Mitigation Measures (Reserve Zone & Grade Separations) |
|
||||
Parameters |
Mitigation Measures/ Preventive Actions |
Responsibility |
Implementation Stage* |
||
Design |
Const |
Oper |
|||
Air Quality |
1) The contractor is obliged to
follow the procedures and requirements given in the Air Pollution Control
(Construction Dust) Regulation |
Mitigation measures shall be
generally applied by Contractor at all work sites |
|
ü |
|
(A) Construction Dust
Impact |
- Use of regular
watering to reduce dust from exposed site surfaces and unpaved roads, at
least twice daily with complete coverage |
throughout the construction phase |
|
|
|
|
- Use of frequent
watering for particular dusty construction areas close to the site boundary
and sensitive receivers |
|
|
|
|
|
- Side enclosure and
covering of any aggregate or dusty material storage piles |
|
|
|
|
|
- Open stockpiles
should be avoided or covered |
|
|
|
|
|
- Provision of
temporary or movable barriers between the site and sensitive receivers |
|
|
|
|
|
- Use of tarpaulin to
cover all dusty material on the transport vehicle |
|
|
|
|
|
- Use of vehicle wheel and
body washing facilities at all exit locations |
|
|
|
|
|
- Use of wind shield or
extractor at the loading and unloading areas |
|
|
|
|
|
- Speed control of max
15kph at unpaved road section |
|
|
|
|
|
- Position of all plant
at the maximum separation distance from receiver if possible |
|
|
|
|
|
2) Detailed Design Consultant
(DDC) to incorporate the controlled measures into the Particular
Specification (PS) for the civil work.
The PS should also draw the contractor’s attention to the relevant
latest Practice Notes issued by EPD |
To be incorporated in the PS by
the Detailed Design Consultant |
ü |
|
|
Water Quality |
1) Follow the site practices
outlined in ProPECC PN 1/94 as far as practicable in order to minimise
surface runoff and the chance of erosion, and to reduce any suspended solids
prior to discharge |
Mitigation measures shall be
generally applied by Contractor at all work sites throughout the construction
phase |
|
ü |
|
(A) Construction Phase
- water |
2) All fuel/oil tanks and chemical
storage tanks/areas should be provided with locks and be sited on sealed
areas, within bunds of a capacity equal to 110% of the storage capacity of
the largest tank, to prevent spilled fuel oils from reaching the receiving
water bodies |
|
|
|
|
|
3) Adequate maintenance of
drainage systems to prevent flooding and overflowing |
|
|
|
|
|
4) Wheel washing facilities should
be implemented and regularly cleaned and maintained |
|
|
|
|
|
5) Oil interceptors should be
provided in the drainage system downstream of any oil/fuel pollution sources.
The oil interceptors should be emptied and cleaned regularly to prevent the release
of oils and grease into the storm water drainage system after accidental
spillage |
|
|
|
|
|
6) Use of sediment/silt traps |
|
|
|
|
|
7) All temporary and permanent
drainage pipes and culverts provided to facilitate runoff should be
adequately designed for the controlled release of storm flows. All these measures should be
regularly inspected and maintained in good order |
|
|
|
|
|
8) Portable chemical toilets and sewage
holding tanks are recommended to handle the construction sewage generated by
workers from both the construction areas and dispersed along the alignment. A
licensed contractor should provide appropriate and adequate portable toilets
and is responsible for appropriate disposal and maintenance |
|
|
|
|
(A) Construction Phase
- water |
9) Detailed Design Consultant
(DDC) to incorporate the controlled measures into the Particular
Specification (PS) for the civil work.
The PS should also draw the contractor’s attention to the relevant
latest Practice Notes issued by EPD |
To be incorporated in the PS by
the Detailed Design Consultant |
ü |
|
|
(B) Operational Phase -
water |
1) Detailed Design Consultant (DDC)
to provide detailed design of the oil interceptors/sub-soil drainage system,
and to incorporate the controlled measures into the Particular Specification
(PS). The PS should also draw
the contractor’s attention to the relevant latest TM and Practice Notes
issued by EPD |
DDC to provide detailed design and
to incorporate the specifications in the PS |
ü |
|
|
|
2) The sewage discharge from the
toilets in the terminus shall be designed to discharge to the nearby public
sewers. |
|
|
|
|
|
3) Provide a surface water
drainage system in order to collect the track runoff. Where oil and
lubricating fluids could be spilt, the track drainage channels discharge
should pass through oil/grit interceptors/chambers, or a sub-soil drainage
system to remove oil, grease and sediment before being pumped to the public
stormwater drainage system |
Mitigation measures shall be
provided by LRT for all the LRT extension works |
|
|
ü |
|
4) Silt traps and oil interceptors
should be cleaned and maintained regularly. The efficiency and performance of
these facilities are highly dependent on regular cleaning and maintenance |
|
|
|
|
|
5) Oily contents of the oil
interceptors should be transferred to an appropriate disposal facility, or to
be collected for reuse, if possible |
|
|
|
|
Noise Impact |
1) use of good site practices to
limit noise emissions by considering the following: |
Noise mitigation measures shall be |
|
|
|
|
- Selection of quiet plants
which complied with the BS 5228 Part 1 or TM Standards |
generally applied by Contractor at
all |
|
|
|
(A) Construction Noise
- General |
- Use of 3.5m high
hoarding along the site boundary, and permanent or movable noise barrier to screen
noise at ground level zone. For
high-rise Noise Sensitive Receivers, cantilevered top cover should be
considered. The surface density of these barriers and hoarding need to be not
less than 7kg/m2. |
work sites throughout the
construction phase |
|
ü |
|
|
- Delocalization of
equipment and/or local reduction of number of plant items |
|
|
|
|
|
- Limiting the
operating time of construction equipment on site and use of smaller equipment
|
|
|
|
|
|
- scheduling of construction
works outside school examination periods in critical areas. If feasible, try
to avoid cumulative and concurrent noisy activities within the Phase 4 and
Reserve Zone. |
|
|
|
|
|
- Well-maintained plant
should be operated on-site and plant should be serviced regularly during the
construction programme |
|
|
|
|
|
- Machines and plant
(such as trucks, cranes) that may be in intermittent use should be shut down
between work periods or should be throttled down to a minimum |
|
|
|
|
|
- Plant known to emit
noise strongly in one direction, where possible, be orientated so that the
noise is directed away from nearby NSRs |
|
|
|
|
|
- Silencers or mufflers
on construction equipment should be properly fitted and maintained during the
construction works |
|
|
|
|
|
- Mobile plant should
be sited as far away from NSRs as possible and practicable |
|
|
|
|
(A) Construction Noise
- General |
- Material stockpiles,
mobile container site office and other structures should be effectively
utilised, where practicable, to screen noise from on-site construction
activities |
Mitigation measures shall be
generally applied by Contractor at all work sites throughout the construction
phase |
|
ü |
|
|
1) Pui To Road |
|
|
|
|
(B) Construction Noise
- Specific |
- Adoption of quiet plant, noise
barrier, equipment delocalisation, reducing the plant items and limiting the operation
time of construction equipment should be applied to sections close to Tuen
Mun Town Plaza |
Mitigation measures to be reviewed
and implemented by Contractor carrying on |
|
ü |
|
|
- Adoption of quiet plant, noise barrier
and equipment delocalisation should be applied to critical areas closed to
Top Court, Man Shing Building, Kam Wah Garden, Sun Court and San Fat Estate |
works for sections closed to these
receivers |
|
|
|
|
2) LT1 Junction |
Mitigation measures to be reviewed
and |
|
ü |
|
|
- Adoption of quiet plant, noise barrier and equipment
delocalization should be applied to critical areas closed to low-rise
residential houses at Ng Lau Road |
implemented by Contractor carrying
on works for sections closed to these receivers |
|
|
|
|
3) TSW Reserve Zone |
|
|
|
|
|
- Adoption of quiet plant, noise
barrier, equipment delocalisation and limiting the operation time of construction
equipment should be applied to sections close to Area 110 Phase 2 |
Mitigation measures to be reviewed
and implemented by Contractor carrying on works for sections closed to these
receivers |
|
ü |
|
|
- Adoption of quiet plant and noise
barrier should be applied to sections close to Area 105 Phase 1, Area 30
Block 4, Area 110 Phase 2 |
|
|
|
|
|
- Adoption of quiet plant, noise
barrier and equipment delocalisation should be applied to sections close to
Area 31 Phases 1 & 2 Primary Schools, Area 102 Phase 1 Block 4, Area 102
Phase 5 Block 17, and Area 30 Phase 1 |
|
|
|
|
|
4) Further review of the
construction method should be carried out by contractor. Considerations
should be focussed on: |
Mitigation measures to be reviewed
and implemented by Contractor carrying on |
|
ü |
|
|
- The availability of
detailed plans or work areas and locations of plant (as opposed to gazetted work
boundaries) will enable the Contractor to reduce the amount of uncertainty in
the distance corrections applied to source noise levels used in this
assessment. |
works for sections closed to these
receivers |
|
|
|
|
- The layout of worksites
should be critically reviewed and judiciously planned in order to make best
use of existing features which may be able to provide screening of NSRs from
plant noise eg site offices, site containers, etc. |
|
|
|
|
|
- To determine specific
SWL measurement of typical plant proposed to be used, particularly those
activities that have been identified to be noisy or cause exceedances above
daytime noise criteria. These
'actual' levels may then be able to be used in place of the values in the TM-CW. |
|
|
|
|
(B) Construction Noise
- Specific |
- Use of smaller PME
with lower SWL, e.g. smaller excavator, lorry to replace dump truck, where
practicable. |
Mitigation measures to be reviewed
and implemented by Contractor carrying on |
|
ü |
|
|
-
Practicality/cost-effectiveness of portable, full noise barriers for sections
of works identified in this report. |
works for sections closed to these
receivers |
|
|
|
|
- Sequential operation
of a limited number of plant items in every 30-minute interval. For example, only excavator and
vibratory roller are used in every 30-minute interval while only grader and
dump truck are used in the next consecutive 30-minute period, where
practicable; and |
|
|
|
|
|
- Use of limiting the
operational period of other PME, where appropriate and practicable, as a last
resort in order to meet the noise criteria. As an example, if PME could be operated for only 10
minutes out of any 30 minute period, a reduction of 5dB(A) could be achieved |
|
|
|
|
(C) Operational Noise |
1) KCRC operator to ensure that
the 65 dB(A) Lmax at 25m from straight and well maintained ballast track is
always achieved. |
KCRC LRT operation section to
review and implement the EMS system |
|
|
ü |
|
2) The Detailed Design Consultant
should ensure that the structure re-radiated noise from viaduct structure is
at least 10dB(A) below the noise criteria of 65 dB(A) Lmax at 25m, at 50kph. |
|
|
|
|
|
3) The Detailed Design Consultant
should ensure that the noise level at 2m from the transformer bays in the
rectifier would be less than 66dB(A). |
DDC to review the design and
incorporate the mitigation measures where feasibile |
|
|
|
|
4) The Detailed Design Consultant
should orientate the open side of transformer bays in rectifier station to face
away from the nearest NSRs, and preferably facing onto a main road, if
practicable. |
ü |
|
|
|
|
5) The Detailed Design Consultant
should conduct a detailed review on ventilation systems in the rectifier
stations to determine the need for any noise attenuation (eg silencers,
acoustic louvres etc). |
|
|
|
|
Waste Management |
1) The following waste management
hierarchy should be considered in general: |
To be reviewed and applied by
Contractor and LRT operators whenever practicable |
|
ü |
ü |
(A) General - waste |
- Avoidance and
minimisation (not generating waste through changing or improving practices
and design); |
|
|
|
|
|
- Reuse of materials,
thus avoiding disposal (generally with only limited reprocessing); |
|
|
|
|
|
- Recovery and
recycling, thus avoiding disposal (although reprocessing may be required);
and |
|
|
|
|
|
- Treatment and
disposal, according to relevant regulations, guidelines and good practice. |
|
|
|
|
|
1) Storage, Collection and Transportation |
|
|
|
|
(B) Construction Phase
- waste |
- Handle and store
wastes in a manner which ensures that they are held securely without loss or
leakage, thereby minimising the potential for pollution; |
To be reviewed and applied by
Contractor whenever practicable |
|
ü |
|
(B) Construction Phase
- waste |
- Use waste collectors
authorised or licensed to collect the specific category of waste; |
To be reviewed and applied by Contractor
whenever practicable |
|
ü |
|
|
- Remove wastes in a
timely manner; |
|
|
|
|
|
- Maintain and clean
waste storage areas regularly; |
|
|
|
|
|
- Minimise windblown litter
and dust during transportation by either covering trucks or transporting
wastes in an enclosed container; |
|
|
|
|
|
- Obtain the necessary
waste disposal permits from the appropriate authorities, if they are required,
in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 354) and the Land (Miscellaneous
Provisions) Ordinance (Cap 28); |
|
|
|
|
|
- Dispose of waste at
licensed sites; |
|
|
|
|
|
- Develop procedures
such as a ticketing system to facilities, tracking of loads, particularly for
chemical waste, and to ensure that illegal disposal of waste does not occur;
and |
|
|
|
|
|
- Maintain records of
the quantities of wastes generated, recycled and disposed. |
|
|
|
|
|
2) Excavated Material |
|
|
|
|
|
- Transport to the
Western Section of WR for reuse, if practicable; |
|
|
|
|
|
- Transport to other
land formation sites in the Tuen Mun and Yuen Long areas for reuse; |
|
|
|
|
|
- Transport to public
filling areas. |
|
|
|
|
|
3) Construction and Demolition
Material |
|
|
|
|
|
- Careful design,
planning and good site management can minimise over-ordering and waste
materials such as concrete, mortars and cement grouts. The design of formwork
should maximise the use of standard wooden panels so that high reuse levels
can be achieved. Alternatives such as steel formwork or plastic fencing
should be considered to increase the potential for reuse. |
|
|
|
|
|
- The contractor should
recycle as much as possible of the construction waste on-site. Proper
segregation of wastes on site will increase the feasibility of recycling
certain components of the waste stream by recycling contractors. Concrete and
masonry can be used as general fill and steel reinforcement bars can be used
by scrap steel mills. Different areas should be designated for such
segregation and storage wherever site conditions permit. |
|
|
|
|
|
- On-site sorting and
segregation facility of all type of wastes is considered as one of the best practice
in waste management and hence, should be implemented in all projects
generating construction waste. The sorted public fill and construction &
demolition (C&D) waste should be disposed to public filling areas and
landfills, respectively. |
|
|
|
|
|
- The handling and
disposal of bentonite slurries should be undertaken in accordance with
ProPECC PN 1/94 . |
|
|
|
|
|
4) Chemical Waste |
|
|
|
|
(B) Construction Phase
- waste |
- Chemical waste that
is produced, as defined by Schedule 1 of the Waste Disposal (Chemical Waste)
(General) Regulation, should be handled in accordance with the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes. |
To be reviewed and applied by
Contractor whenever practicable |
|
ü |
|
|
- Containers used for
the storage of chemical wastes should be suitable for the substance they are
holding, resistant to corrosion, maintained in a good condition, and securely
closed; have a capacity of less than 450 liters unless the specification has
been approved by the EPD; and display a label in English and Chinese in
accordance with instructions prescribed in Schedule 2 of the regulation. |
|
|
|
|
|
- The storage area for
chemical wastes should be clearly labelled and used solely for the storage of
chemical waste; enclosed on at least 3 sides; have an impermeable floor and
bunding of sufficient capacity to accommodate 110% of the volume of the
largest container or 20 % of the total volume of waste stored in that area,
whichever is the greatest; have adequate ventilation; covered to prevent
rainfall entering; and arranged so that incompatible materials are adequately
separated. |
|
|
|
|
|
- Disposal of chemical
waste should be via a licensed waste collector; be to a facility licensed to
receive chemical waste, such as the Chemical Waste Treatment Centre which
also offers a chemical waste collection service and can supply the necessary
storage containers; or be to a reuser of the waste, under approval from the
EPD. |
|
|
|
|
|
5) General Refuse |
|
|
|
|
|
- Contractor to remove
general refuse from the site, separately from construction and chemical waste,
on a daily or every second day basis to minimise odour, pest and litter
impacts. |
|
|
|
|
|
- Office wastes can be
reduced through recycling of paper if volume is large enough to warrant collection.
Participation in a local collection scheme should be considered if one is
available. |
|
|
|
|
|
- Training should be
provided to workers about the concepts of site cleanliness and appropriate waste
managemnet procedure, including reduction, reuse and recycling of wastes. |
|
|
|
|
|
1) General Refuse and Industrial
Waste |
|
|
|
|
(C) Operational Phase -
waste |
- General refuse will
be mainly generated from the daily activities of LRT stops of the Phase 4
Extension. The LRT stops of the new extension should be included in the
current LRT Waste Management Plan.
As mentioned in the current LRT Waste Management Plan, at least 2
general garbage bins should be provided for each passenger stop, and the
refuse should be collected by licensed contractor twice per day. The small
quantity of industrial waste generated can be collected together with general
refuse. |
To be reviewed and applied by LRT
operation staff whenever practicable |
|
|
ü |
|
2) Chemical Waste |
|
|
|
|
(C) Operational Phase -
waste |
- Chemical waste is
produced, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General)
Regulation, and should be handled and disposed of in accordance with the Code
of Practice on the Packaging, Labelling and Storage of Chemical Waste. For
mitigation measures, the guidelines covered under the construction phase
mitigation of chemical wastes should be referred. |
To be reviewed and applied by LRT
operation staff whenever practicable |
|
|
ü |
Landscape
& Visual |
1) The Detailed Design Consultant (DDC) to carry out a Baseline
Detailed tree survey to establish a record of the locations of existing
mature trees. All trees to be retained, transplanted or felled shall be
identified on site and on survey plan. |
DDC to carried out at
commenencement of the detailed design Stage |
ü |
|
|
|
2) A Landscape Master Plan should
be formulated and submitted to Govt Department for approval |
Detailed Design Consultant to
prepare and implement the plan before construction work commence |
ü |
|
|
|
3) Carefully detailing the use of
forms, colour and finishes of external appearance of all above-ground
structures so that they are visually integrated into the surrounding
landscape as much as practical |
DDC to carry out during the detailed
design stage |
ü |
|
|
|
4) Implementation of tree and
shrub planting within the railway reserve to soften the visual impact of the
viaduct and make use of climbing plants to soften the appearance of viaduct
column. |
To be implemented by the
Contractor during the construction and operation stages |
|
ü |
ü |
|
5) The Contractor to carry out Tree Survey Audit and to ensure
all approved protection measures are in place prior to any excavation or site
formation works. Regular monthly
site inspections shall be made by the Supervising Officer. |
To conduct at the outset of the
construction contract |
|
ü |
|
|
6) The Contractor to make
conservation of topsoil. |
Throughout the construction phase |
|
ü |
|
|
7) Hoarding to works area boundary
to protect adjacent operation |
Generally applied by Contractor at
all work sites |
|
ü |
|
|
8) Planting to planter reserves
alongside LRT alignment |
To be implemented by Territory
Development Department (TDD) and maintained by Highway Department (planter
walls) and Regional Services Department (softworks). |
|
ü |
ü |
|
9) The Government Contractor shall
carry out the maintenance and establishment works to all planted areas for
the period specified in the Landscape contract (typically 12 months). Regular monthly site inspections shall
be made by the Supervising Officer. |
To conduct upon competion of the
construction contract |
|
|
ü |
Cultural Heritage |
1) The Contractor, when conducting
the archaeological evaluation during construction phase, should adopt a
minimum 5% sampling strategy for the support columns of the viaduct. The selected column footings should
be pre-excavated prior to the onset of construction activities in order to
retrieve sufficient information to assess the impact of the railway. |
Precautionary measures shall be
generally applied by Contractor at all work sites prior to and throughout the
construction phase |
|
ü |
|
|
2) If pre-excavation of selected columns
is not possible, the mitigation strategy should be the posting of an
archaeological watching brief, although the “watch and stop” may have
implications on the construction programme of the columns. The watching brief may need to be
extended to cover a larger sample if positive results are gained. |
Precautionary measures shall be
generally applied by Contractor at all work sites prior to and throughout the
construction phase |
|
ü |
|
Cultural Heritage -
Construction Phase |
3) The archaeological evaluation
and watching brief should be conducted by a qualified archaeologist, who
should be licensed by the Antiquities Authority before the evaluation or
watching brief takes place. This licensing procedure is a statutory
requirement stated in Sections 12 and 13 in the Antiquities and Monuments
Ordinance (Cap. 53). |
Precautionary measures shall be
generally applied by Contractor at all work sites prior to and throughout the
construction phase |
|
ü |
|
|
|
|
|
|
|
Note: |
|
|
|
|
|
* The recommended noise mitigation
measures are developed based on the conceptual layout plan and subject to
refinement in the detailed design stage. |
|
|
|||
Reassessment are necessary when
there are changes in design. |
|
|
|
|
|
Alternative measures which are
proven to have equivalent or higher performance are acceptable. The overall
compliance rate should be comparable to that of the conceptual layout. |
[1] EIA Study Brief No. ESB-017/1998
[2] Environmental Impact Assessment Ordinance
[3] Air Pollution Control Ordinance, (CAP. 311), June 1997
[4] Air Pollution Control (Construction Dust) Regulation, (CAP. 311R), June 1997
[5] Noise Control Ordinance, (CAP.400), June 1997
[6] Water Pollution Control Ordinance, (CAP. 358), June 1997
[7] Waste Disposal Ordinance, (CAP. 354), June 1997
[8] Waste Disposal (Chemical Waste) (General) Regulation, (CAP. 354C), June 1997
[9] Public Health and Municipal Service Ordinance – Public Cleansing and Prevention of Nuisance (Urban Council and Regional Council) By-Law, (CAP. 132), June 1997
[10] Dumping at Sea Ordinance, (CAP. 466), June 1997
[11] The Antiquites and Monuments Ordinance, (CAP. 53), June 1997
[12] The Land (Miscellaneous Provision) Ordinance, (CAP 28), June 1997
[13] Technical Memorandum on Environmental Impact Assessment Process, April 1998
[14] Technical Memorandum for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites, June 1997
[15] Technical Memorandum on Noise from Construction Work Other Than Percussive Piling, Sept 1996
[16] Technical Memorandum on Noise from Construction Work in Designated Areas, June 1996
[17] Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters, June 1991
[18] Practice Note for Professional Person, Construction Site Drainage, ProPECC, PN 1/94
[19] Hong Kong Planning Standards and Guidelines, 1998
[20] BS5228, Noise Control on Construction and Open Site, Part 1: 1997
[21] Final Assessment Report, West Kowloon to Tuen Mun Centre, Contract No TS-900 Environmental Impact Assessment Report, KCR, Feb 1999
[22] Agreement No CE 10/95, Tin Shui Wai Development, Engineering Investigations for Development of Areas 3, 30 & 31 of the Development Zone and the Reserve Zone, Final Investigation Report, Vol 1 – Main Text, Territory Development Department, Mar 1997
[23] Calculation of Rail Noise, Department of Transport, UK, 1995
[24] Transit Noise and Vibration Impact Assessment, 1995, US Department of Transportation
[25] Transportation Noise Reference Book, Paul Nelson, Butterworths
[26] Working Paper # 1, GSA-021, Waste Management, Ove Arup & Partners, August 1999
[27] Working Paper # 3, GSA-021, Construction Noise Assessment, Ove Arup & Partners, September 1999
[28] Working Paper # 4, GSA-021, Cultural Heritage, Ove Arup & Partners, August 1999
[29] Working Paper # 5, GSA-021, Water Quality Assessment, Ove Arup & Partners, August 1999
[30] Working Paper # 6, GSA-021, Operational Noise Assessment, Ove Arup & Partners, September, 1999
[31] TCRP Report 32, Wheel / Rail Noise Control Manual”, US Department of Transportation
APPENDIX 1 – Layout of Proposed LRT Works
APPENDIX 2 – Locations and Description of
Neighbouring NSRs
APPENDIX 3 – Building Plans for Tin Shui Wai
Reserve Zone (Provided by HKHA)
APPENDIX 4 – Predicted Train Frequency and
Speed (Provided by KCR)
APPENDIX 5 – Updated Noise Calculations from
West Rail (with 12-car trains)
APPENDIX 6 – Normal, Abnormal &
Emergency Operations for LRT
APPENDIX 7 – Predicted Cumulative Train
Noise Impacts
APPENDIX 8 – Not Used
APPENDIX 9 – Fixed Plant Noise Assessment
APPENDIX 10 – Separation Distance of NSRs to
Construction Sites
APPENDIX 11 – Construction Plant Inventory
and Construction Schedule
APPENDIX 12 – Sound Power Level of Quiet
Equipment
APPENDIX 13 – List of Declared and Deemed
Monuments
APPENDIX 14 – Photos Taken During Field
Evaluation
APPENDIX 15 – Letter from TDD