12.0     CONCLUSION

12.1            While the Cyberport can continue to be constructed using concrete delivered by barges or by land to the site from an off-site concrete batching plant, there are obviously overall environmental benefits of setting up an on-site concrete batching plant. The approved EIA report has assessed the potential impact without this proposed plant. However, it has been shown above that with appropriate mitigation measures, adverse impacts due to the additional plant are unlikely to occur.

In addition, as the concrete batching plant is constructed on top of a concrete slab, land contamination will not be expected during decommissioning. Besides, during decommissioning of the proposed concrete batching plant, the noise and air quality impacts will be much lower than those in the construction and operation phases.

Air Quality Impacts

In terms of the air quality impacts, it is anticipated the dust impacts arising from the construction phase of the plant is insignificant, given the short construction period of the plant (< 120 days).

 

The net dust impact during the operation of the plant are well below the EIAO-TM Criterion for 1-hour TSP and Air Quality Objective (AQO) respectively with the built-in dust suppression measures for the batching plant. However, additional dust suppression measures such as speed control of dump trucks and increased watering of the site and haul roads will be required to meet the criteria arising from the cumulative effects of then plant with the concurrent construction works at the site.

Noise Impacts

In terms of noise impact, the construction of the concrete batching plant is considered to produce short-term and minor impact.

 

The operational noise impact from the plant is also minor. However, the concurrent construction activities and the batching plant could have some cumulative noise impacts at certain noise sensitive receivers, including domestic premises and educational institutions, and would exceed the respective construction noise limits. Mitigation measures are required to comply with the noise criteria at the nearby domestic premises, as well as the schools.

Waste Impacts

Construction of the batching plant will result in the generation of very limited quantities of wastes and materials and these are unlikely to be a cause for concern.

 

A concrete recycling machine will be installed on-site to recycle concrete waste in order to reduce material consumption and waste generation.  Concrete waste material will be broken down into slurry water and aggregates.  Sludge will be generated during the recycling process and will require off-site disposal. 

 

Limited amounts of chemical wastes, such as fuel and lubrication oils, will be generated from the operation of the plant. These will be stored and disposed in accordance with the chemical waste regulations. As such, no adverse environmental impacts are expected.

Water Quality Impacts

Limited surface run-off with grouting, cement materials and lubrication oils, etc, from the site during construction of the plant may affect the coastal water off the site. Good site management practices and the implementation of a construction site drainage system that includes sediment removal facilities will be required to meet the water quality objectives.

 

Temporary sanitary facilities such as portable chemical toilets will be required to treat the domestic sewage from the workforce.  No water quality impact is anticipated.

All water used within the concrete batching plant will be collected, stored and recycled to reduce resource consumption. This includes water used in the concrete batching process, truck cleaning, yard cleaning and spraying.  As no wastewater will be discharged outside the boundary of the plant, there will not be any potential water quality impacts associated with the operation of the facility. 

Visual Impacts

The proposed plant will be partially screened by an existing earth mound. As the main building works progress, high-rise buildings will be erected on the site to further reduce the view of the plant from the sensitive receivers at Baguio Villa and the visual impact of the concrete batching plant will be much reduced. Therefore, the visual impact of the concrete batching plant on the sensitive receivers can be considered as minor.

Environmental Monitoring and Audit (EM&A)

An Environmental Monitoring and Audit (EM&A) Manual has been prepared to provide the necessary mechanism to ensure the compliance with all environmental regulations currently in force in the HKSAR. This includes a real-time monitoring network to provide 24-hr noise and TSP data for subsequent posting to the web for public viewing.