2.0       DESCRIPTION OF THE PROJECT

Background

2.1               The approved EIA has assumed that ready-mixed concrete in concrete mixer trucks would be delivered by barges to Telegraph Bay for the construction of Cyberport. The delivery of concrete by sea or by road would cause environmental and traffic problems in the peak production period. The production of concrete at an off-site concrete batching plant would also create environmental problem for local sensitive receivers.  It proposes, as an alternative, that an on-site concrete batching plant be constructed to meet the concrete demand on site.

2.2               Estimated quarterly consumption of concrete quantity required for the current programme of construction at Cyberport is tabulated in Table 2.1.

Table 2.1         Estimated Quarterly Consumption of Concrete Quantity

Quarter

Quantity1, m3

Average Truck Load per Day2

2Q2000

11,000

29

3Q2000

24,630

64

4Q2000

39,850

104

1Q2001

54,460

141

2Q2001

54,460

141

3Q2001

71,360

185

4Q2001

58,970

151

1Q2002

48,285

125

2Q2002

48,285

125

3Q2002

44,420

115

4Q2002

44,420

115

Quantity is estimated based on 25 production days per month.

Concrete capacity of each mixer truck is assumed to be 5 m3/Load.

 

 

Environmental and Programming Benefits

2.3               According to the concrete consumption in Table 2.1, it is estimated that more than 10 barges would be required for daily delivery of concrete mixer trucks after the fourth quarter in year 2000.  The maximum barge traffic would be 26 barges per day in the third quarter of 2001. It is anticipated this additional barge traffic may have implications on the busy marine traffic around the Hong Kong waters.

2.4               The short-term tenancy for the concrete batching plant operated by Ready Mixed Concrete (H.K.) Limited (RMC), the concrete provider of the site, at Aberdeen may be terminated very soon. The employment of other batching plant at Ap Lei Chau may also affect the marine traffic. It is very likely that the supply of concrete would rely on batching plant not in the practical vicinity of Telegraph Bay. This would definitely lengthen the travelling time for barges, with consequential problem on concrete quality.

2.5               The barge traffic would also create air quality, noise and water quality pollution along the marine route. Dark smoke from barges is both unsightly and air polluting and this has been a cause for complaint by residents at Baguio Villas. Barge horn noise would be unavoidable under misty weather and therefore can be another cause for complaint. In addition, minor quantities of wastewater may be discharged from these barges into the water, causing local water pollution.

2.6               The existing jetty vertical seawall is not designed for berthing of a large number of barges. However, construction of a new jetty would cause marine water quality impact and programming constraints on the construction works.

2.7               Other demerits include the delivery time of concrete by barges. It is very likely that because of busy marine traffic, concrete may not always be delivered to the site by barges earlier than, say, 6: 00 p.m., for the concrete to be placed before 7:00pm on each working day. Any delay in the delivery would require concreting to proceed into the restricted hours and therefore risk the violation of the Environmental Permit conditions.

2.8               On the other hand, land transportation of concrete would require a large number of trucks on road after the 4th quarter of 2000, which would, in turn, cause serious traffic problem for Victoria Road and generate air quality and noise impacts on the nearby sensitive receivers

2.9               An on-site concrete batching plant is therefore desirable from environmental and operational points of view. Table 2.2 summarizies the benefits between an on site concrete batching plant and the concrete delivery by barges.

Table 2.2         Comparison between on site concrete batching plant and concrete delivery by barges

 

Concrete Batching off-site

Concrete Batching Plant on Site

Barge Traffic

4 to 5 barges per day for Stage 1

Up to 26 barges per day for Stage 2

2- 3 barges per day for two days a week

Air Quality impact

High, due to the dust and exhaust emissions from the barges

Low, due to the low number of barges operating and the batching plant is totally enclosed

Noise Impact

Medium, but high during misty weather.

In case that land transportation is used, the delivery of concrete will increase the traffic noise impact on the nearby sensitive receivers.

Low, due to the low number of barges operating and the batching plant is totally enclosed.

Water Quality Impact

High risk of polluting the harbour due to barges

Low risk

Marine Traffic Impact

High

Low

Visual Impact

High, particularly when dark smokes are emitted from a large number of barges

Low, as the earth mound and future buildings will reduce the visual impact

Delivery Timing Control

Little control on the timing due to the busy marine traffic

Good control on concrete delivery

Potential for Mitigation

Mitigation measures are difficult to implement on barges.

Easy to implement. As the concrete batching plant is stationary, the mitigation measures (such as totally enclose the plant) can easily be applied.

 

2.10            It is clear from Table 2.2 that an on-site concrete batching plant has far better environmental benefits than an off-site concrete batching plant. In addition, the on-site concrete batching plant will only supply concrete for the day to day use at Cyberport only. No concrete will be delivered off site.

In addition, as the concrete batching plant is constructed on top of a concrete base slab which separates the plant from existing ground, it is anticipated that no land contamination will be resulted during decommissioning of concrete batching plant.

Location of the proposed Batching Plant

2.11            RMC has proposed to install a concrete batching plant with a maximum hourly production of 300 m3 concrete. Location of the proposed batching plant is shown in Figure 2.1.

2.12            The siting of the concrete batching plant has been carefully examined. The proposed location is considered the best in terms of environmental and visual impacts while maintaining the stability of the seawall. In addition, the proposed location is quite farher awaymost from Baguio Villa.  It is anticipated that the existing earth mound and the future commercial  buildings would screen the plant at this location from the sensitive receivers, and hence the potential visual impact can be much reduced. Further details are given in Chapter 8. For other locations further south along the seawall, the earth mound and the future commercial buildings can only screen a small portion of the proposed concrete batching plant, thisthe advantage of using earth mound and building advantages to reduce the visual impact may not be guaranteed.

2.13            Furthermore, the proposed location of the concrete batching plant to the nearest sensitive receiver is about 280m away, which comply with the Hong Kong Planning and Standard Guideline (HKPSG).

2.14            In addition, the proposed plant is very close to the vertical seawalljetty. If alternative locations are selected, longer converyance system and more traffic will be required to transfer the cement and aggregates from the vertical seawall to the concrete batching plant. These may introduce additional and unnecessary noise and dust nuisance to local sensitive receivers.

Description of the Proposed Batching Plant

2.15            The actual operation of the plant will be subject to the issuance date of the Environmental Permit and the S.P. License. The concrete batching plant would operate until November 2001 when the land lease for the plant expires; thereafter the need for such a concrete batching plant will be re-visited.

2.16            As the operation of a concrete batching plant with a total silo capacity exceeding 50 tonnes is a specified process (S.P.) under the Air Pollution Control Ordinance (APCO), application for a S.P. license is required in order to conduct the works. As it takes time for the authority to issue a S.P. license, the intention is to divide the works into two stages for the operation of the concrete batching plant. A mobile batching plant of a total cement silo capacity of 45 tonnes would be employed for temporary production in Stage 1 while a complete batching plant of a total capacity of 800 tonnes would be operated in Stage 2 (Fig.2.2).

2.17            For the Stage 1 plant, a mobile batching plant Mob 60 with a total silo capacity of 45 tonnes – one 30 tonnes and one 15 tonnes, would be employed. The mixer capacity is 1.25 m3/batch. The dimension of Stage 1 plant is 23m x 20m x15m. Cement and aggregates are delivered to the site by barges. Fig.2.3 shows the schematic diagram for stage 1. Predetermined mixing ratios of cement and aggregates are set to produce different grades of concrete for application. Appropriate amount of water is also injected to form the mix.

2.18            Cement is pumped from the barge to a cement tanker. The cement tanker transfers the cement to the fully enclosed cement silos. Cement is stored in the silos and properly weighed for mixing. Dust collectors would be installed at the cement silos and the concrete mixer. Totally three dust collectors would be employed.

2.19            Aggregates would be transferred from a barge to a tripper truck through the sea front receiving hopper. In order to reduce dust emission, water will be sprayed on the barge (Fig.2.4). The tripper truck then transports the aggregates to the aggregate storage yard (Fig.2.5). A wheel loader would transfer the aggregates to an aggregate-receiving hopper (Fig.2.6). Finally, the aggregates are conveyed to a fully enclosed aggregate storage bin with a total capacity of 30 tonnes by a belt conveyor. Aggregates are stored in the overhead storage bins and ready for mixing in the mixer

2.20            For the Stage 2 plant, a fixed batching plant with a total cement silo capacity of 800 tonnes – two 200 tonnes and four 100 tonnes, would be employed (Fig.2.7). The mobile batching plant Mob 60 would be used as a standby and will not be operated concurrently with the Stage 2 plant. The total dimensions of the Stage 2 and Stage 1 plants is 95m x 45m x 24m. The Stage 2 plant is composed of two identical mixers. Both will be operated at batch mode and the capacity is 3.5 m3/batch each. Cement and aggregates are also delivered to the site by barges. Similar operations to the Stage 1 are involved.

2.21            In Stage 2, cement is directly pumped from the barge to the cement silos. The schematic diagram is shown in Fig. 2.8. There are totally six cement silos – two are 200 tonnes and four are 100 tonnes. The two 200 tonnes silos are interconnected while the other four silos are also connected. Two dust collectors would serve each group of silos and one dust collector would serve the two mixers. Therefore, totally five dust collectors would be employed in the Stage 2 plant.

2.22            The operating hours will be 0700 to 1900 hours on a normal working day. There will be no operation on Sundays and Public Holidays.

2.23            Aggregates would be transferred from a barge to the sea front receiving hopper. Afterwards, the aggregates would be transported to a group of five 200 tonnes aggregate storage bins by enclosed belt conveyors (Fig.2.9). Moreover, each mixer is equipped with an overhead storage bin composing of four compartments (Fig. 2.10). Each compartment can hold 40 tonnes of aggregates.

2.24            Three sets of generators would be used in the plant - two sets for the batching plant and the other for maintenance workshop.

2.25            A concrete recycling machine of capacity 20m3/hr will be installed on-site to recycle concrete waste (Fig.2.11). In the worst case situation, the recycled concrete will not exceed 5m3/day.

2.26            Before decommissioning of the proposed concrete batching plant, remained materials shall be removed from the facilities before decommissioning of concrete batching plant. The storage, handling and disposal of unused materials, chemical waste, construction waste, general refuse shall be conducted with current waste management practices. In addition, during decommissioning, the noise and air quality impacts will be much lower than those in the operation and construction phases. 

 

Construction Program

2.27            Table 2.3 shows the schedules of the concrete batching plant

Table 2.3         Schedules of Concrete Batching Plant

Description

Period

Time

Construction of Stage 1

~ 1 month

Dec 2001

Operation of Stage 1 and Construction of Stage 2

~ 3 month

March 2001

Operation of Stage 2

~3 month after and onwards

April 2001

 

2.28            The construction works during the commencement of Concrete Production and the completion of Concrete Production (i.e. Dec, 2000 to Dec, 2001) will comprise the following works:

           Main Construction Works for the Telegraph Bay Development

           Construction and operation of the Concrete Batching Plant

2.29            The main construction work includes construction of the Cyberport Phase C1, C2, C3 and R1, sewage treatment plant, Southern Access Road, Northern Access Road, Road D1, D2 and L1.

2.30            The working Programmes for various works are shown in Fig.2.12 and Fig.2.13.