4.1
This section
evaluates the likely air quality impacts associated with the
construction/operation of the proposed concrete batching plant and the
concurrent construction works at Telegraph Bay. The key issues will be dust
impacts arising from the works and the plant.
4.2
The criteria and
guideline for air quality assessment are laid out in Annex 4 and Annex 12 of
the Technical Memorandum on Environmental
Impact Assessment Process (EIA-TM), respectively.
4.3
The Air Pollution
Control Ordinance (APCO) provides the statutory authority for controlling air
pollutants from a variety of sources.
The ordinance encompasses a number of Air Quality Objectives (AQOs)
which stipulate maximum concentrations for a range of pollutants, of which
Total Suspended Particulates (TSP) are relevant to this study. The relevant AQOs are listed in Table 4.1.
Table 4.1 Hong Kong Air
Quality Objectives
Parameter |
Maximum Average
Concentration1, µg/m3 |
||
1-Hour2 |
24-Hour3 |
Annual4 |
|
TSP |
--- |
260 |
80 |
1. Measured at 298 K and 101.325 kPa.
2 Not to be
exceeded more than three times per year.
3 Not to be
exceeded more than once per year.
4. Arithmetic
means.
4.4
In addition to the
AQOs, a non-statutory 1-hour average criterion for Total Suspended Particulates
(TSP) of 500 mg/m3 (at 298 K and 101.325 kPA) is adopted for
assessing construction dust impacts (as specified in the EIA-TM).
4.5
Telegraph Bay is located
on the western side of Hong Kong Island and is to be developed with residential
towers and G/IC facilities which are compatible with existing developments in
the area.
4.6
Telegraph Bay
occupies a reclaimed bay with high landscape quality comprising wooded valleys
slopes, streams and armoured sea frontage. The site consists of two areas. The
larger northern section (proposals for 3 housing sites and 1 G/IC sit) is
located at the foot of the western slopes of Hong Kong Island, on the reclaimed
site of Telegraph Bay. The southern section ( 1 housing site) occupies the
prominent spur of headland between Waterfall Bay and Telegraph Bay.
4.7
Nearby sensitive
receivers for air quality in the vicinity of the Study Area are identified. The
selected sensitive receivers are made with reference to the approved EIA Report
. Description of the sensitive receivers is provided in Table 4.2. Figure 4.1
shows the location of the selected sensitive receiver for the air quality
assessment.
Table 4.2 Locations of the
Air Sensitive Receivers
ASR |
SR No. |
Description |
Land Use1 |
App. distance
between the plant and the ASRs (m) |
1 |
SR1 |
Stanley Ho Sports Centre |
Rec |
1033 |
2 |
SR2 |
Tam Villa |
R |
890 |
3 |
SR3 |
HKU Staff Quarters |
R |
771 |
4 |
SR4 |
42 Sasson Road |
R |
619 |
5 |
SR5 |
45 Sasson Road |
R |
530 |
6 |
SR6 |
47 Sasson Road |
R |
530 |
7 |
SR7 |
50 Sasson Road |
R |
518 |
8 |
SR8 |
60 Sasson Road |
R |
458 |
9 |
SR9 |
Magnolia Villas |
R |
577 |
10 |
SR10 |
Point Breeze |
R |
518 |
11 |
SR11 |
Carriana Sasson |
R |
601 |
12 |
SR12 |
Stone Manor |
R |
676 |
13 |
SR13 |
Provident Villas |
R |
768 |
14 |
SR14 |
HKU Medical Faculty |
S |
878 |
15 |
SR18 |
Ebenezer Home for the Blind |
S |
845 |
16 |
SR19 |
16-18, Baguio Villas |
R |
310 |
17 |
SR21 |
Pok Fu Lam Training Centre |
S |
571 |
18 |
SR22 |
Pok Fu Lam Garden |
R |
658 |
19 |
SR23 |
Wah Fu Estate |
R |
780 |
20 |
SR24 |
Lui Ming Choi Secondary School |
S |
726 |
21 |
SR25 |
Precious Blood Primary School |
S |
798 |
22 |
SR26 |
Tsui Ching Tong School for the Handicap |
S |
810 |
23 |
SR27 |
Kong Sin Wan Tsuen |
R |
589 |
24 |
SR40 |
Pui Ying Secondary School |
S |
774 |
1. Residential uses (R); School (S);
Recreational uses (Rec)
4.8
The potential for
the dispersion of air pollution is very much dependent on local factors such as
wind speed, wind direction, and atmospheric stability.
4.9
Site specific
meteorological data for the Telegraph Bay Area are limited. The study has therefore
reviewed the nearest Hong Kong Observatory meteorological station data to gain
an overall appreciation of likely meteorological conditions that would prevail
at the study area.
4.10
The fugitive
emissions will be determined by local prevailing meteorological conditions. An
understanding of prevailing wind speed and direction at the study area will
help to determine potential air quality concerns.
4.11
Hong Kong’s
climate is dominated by two monsoons:
§
The warm rain
bearing south easterly summer monsoon; and
§
The cool dry
north-easterly winter monsoon
4.12
The frequency of
stable atmospheric conditions over Hong Kong is about 10-20% whilst unstable
conditions occur about 30-40% of the time.
4.13
The proposed
development site at Telegraph Bay lies between the HK Observatory
meteorological sites at Green Island and Wong Chuk Hang.
Concurrent
Construction Activities
4.14
Dust impact will
arise from the following concurrent construction activities:
Advance Works for
Telegraph Bay Development, including earthworks and surcharging on the
reclamation area;
Main Construction Works for Telegraph Bay Development, including
access roadworks, civil works and superstructure construction; and
Construction and operation of the
Concrete Batching Plant.
4.15
During the
construction phase, dust generating construction activities include vehicle
movements, site clearance, drilling, ground excavation and material handling.
Wheel wash units will be provided at the entrances and exits of the worksite
and, with the proper use of these facilities, there will be minimal dust
nuisance outside the worksite. However, fugitive dust will arise from the
vehicle movements within the worksite.
4.16
The main dust
impacts will arise from truck movements along the unpaved haul roads. Secondary
impacts will arise through the stockpiling and removal of spoil during the
advance works and main construction works period. The amounts of material
expected to be handled during the period December 2000 to December 2001 are
summarized in Table 4.3
Table 4.3 Spoil Handling During Construction Phases
Construction Activities |
Spoil Quantity (m3) |
Estimated Number of Dump Trucks on Haul road |
Advance Works Disposal* |
330,000 |
83 veh/hr |
Main Construction Works** Road D1 Road D2 Southern Access Road Northern Access Road |
22,280 8,700 124,165 9,900 |
20 veh/hr |
Concrete batching Plant |
|
185 trips/day |
* As the import
from the sand fill and public has been performed before December 2000, the
handling due to the import is not taken into account.
** Since the
concrete batching plant is situated on the proposed Route 7, the construction
of Route 7 will not take place during the operation of the concrete batching
plant.
Construction of Batching Plant
4.17
Major construction
works are formation of foundation, erection of carbon steel supports, metal
works including welding and assembly of fabricated metal sheets. Since the
excavation material is small (~1200m3), the amounts of dust that
will be generated from such works are relatively minor compared with other
concurrent construction works at the Telegraph Bay Reclamation. However, during construction, the
requirements of the Air Pollution Control (Construction Dust) Regulation in
dust control will be strictly followed.
Operation of the Batching Plant
4.18
During the operation
of the proposed batching plant, dust emission sources can be identified in the
plant. They involve:
Emissions from the dust collectors;
Emissions for unloading of materials to receiving hopper;
Emissions from aggregate stockpile; and
Emissions from paved access road.
Dispersion
Modelling
4.19
Dispersion
modelling has been undertaken using USEPA approved Fugitive Dust Model (FDM) to
assess potential dust impacts arising from construction activities and fugitive
dust sources. Surface roughness was taken to be 0.6 metre in the FDM model to
represent the terrain in the vicinity of the study area.
4.20
For the purpose of
this assessment, it is considered that dust emissions from vehicles moving on
unpaved road surfaces would constitute the major dust source for most of the
construction sites. There is no site-specific information relating to particle
size distribution, and as a result, assumptions were made using the unpaved
road emission equation from AP-42 (5th Edition) to provide input for the FDM
modelling. Particle size distribution was estimated based on the most
appropriate particle size multipliers.
For the modelling exercise 9 particle size classes were used in the FDM
model. Their averaged diameters are 0-1
µm, 1-2 µm, 2-2.5 µm, 2.5-3 µm, 3-4 µm, 4-5 µm, 5-6 µm, 6-10 µm and 10-30 µm.
The percentage in each class was estimated to be 4%, 7%, 4%, 3%, 7%, 5%, 4%,
17% and 49% respectively.
Meteorological
Conditions
4.21
According to the
Guideline on Choice of Models and Model Parameters, the worst case
meteorological data was used for the FDM modelling:
Mixing height : 500m
Stability Class : D
Wind Direction : worst-case wind angle
Surface Roughness : 0.6 m
Height of Emissions : Ground Level
Wind
speed at 1, 2 and 4m/s was tested and the worst case is selected.
Background
Pollutant Concentrations
4.22
Background
pollutant concentrations have been derived from the baseline monitoring result
performed in December 1999 in Cyberport. Therefore, the baseline 1-hour TSP and
24-hour TSP are 265 mg/m3 and 59 mg/m3 respectively.
4.23
In the absence of
in-situ monitoring data, the annual average TSP concentration has been used as
the background concentration for the impact assessment.
Emission Factors
4.24
The particulate
emission rates are estimated using the Compilation of Air Pollutant Emission
Factors (AP-42), USEPA, 5th edition, 1995. The emission factors used
in the modelling are tabulated in Table 4.4.
Table 4.4 Emission Factors of Dust Generating Activities
Activities |
Emission Factor |
Truck movements unpaved roads |
Appendix 4.1 |
Handling of spoil (loading/unloading) |
Appendix 4.1 |
Wind erosion |
Appendix 4.1 |
Emissions for unloading of materials to receiving hopper |
AP 42 Section 11.19.2, Table11.19.2-1 |
Emissions from aggregate stockpile |
AP 42 Section 13.2.4 |
Paved roads |
AP 42 Section 13.2.1 |
4.25
During the
construction of the Concrete Batching Plant, the requirement of the Air
Pollution Control (Construction Dust) will be followed. As the construction
period of the plant is short (< 120days) and the amount of excavated
material is small (~1200m3), the impact due to the construction
phase of the concrete batching plant is smaller than that during the operation
stage. Therefore, the operation phase of the concrete batching plant is
presented in this report.
4.26
In the schematic
process, there will be totally eleven emission points. Detail calculations of
the source strengths of the identified emission points in plant are given in
Appendix 4.2.
4.27
The concrete
recycling machine is used to recycle wet concrete waste, which will not
generate dust problem.
4.28
Mitigation
measures which have been assumed in the concrete batching plant assessment are
summarized in Table 4.5.
Table 4.5 Mitigation Measures incorported on the Proposed Concrete
Batching Plant
Item/ Process |
Description |
Mitigation
Measures |
Unloading of Sand And Aggregates |
a. Unloading of Sand and Aggregates from Barge to aggregate
Receiving Hopper at Seafront |
·
Water
spray installed on barge for wetting the sand and aggregates1 ·
Conveyor
barge designed for unloading aggregate3 ·
Fully
enclosed conveyor used to unload the material to the aggregate receiving
hopper1 ·
Aggregate
receiving hopper installed with 3 sides and water spray1 |
b. Unloading of wetted Sand and Aggregates from Aggregate
Receiving Hopper to Tipper truck |
·
The wetted
sand and aggregates are loaded into the tipper truck in enclosed loadout
section1 |
|
Storage of Sand and Aggregates |
Storage of Sand and Aggregates in Ground Storage Yards and
Aggregate Storage Bins. Storage of Sand and Aggregates in Fully Enclosed Aggregate
Overhead Storage Bins |
·
The
storage yards are installed with 3 sides enclosure and roof, curtain at
entrance1 ·
Water
spray is installed in storage yard for wetting the sand and aggregates1 ·
Aggregate
Storage Bins and Aggregate Overhead Storage Bins are fully enclosed1 |
Transfer of Sand And Aggregates |
a. Transfer of sand and Aggregates from Loadout Section to
Storage Yards by tipper truck |
·
The tipper
trucks with wetted sand and aggregates are covered with plastic canvas2 ·
The
aggregate materials are unloaded into storage yards, which have 3 sides and
roof enclosed and curtain at entrance and water spray1 |
b. Transfer of Sand and Aggregates from Storage Yards to
Aggregate Receiving Hoppers by loader |
·
The sand
and aggregates are wetted before transferring to aggregate receiving hopper1 ·
Aggregate
receiving hopper installed with 3 sides and roof and water spray1 |
|
c. Transfer of Sand and Aggregates from Seafront Aggregate
Receiving Hopper to Aggregate Storage Bins OR from Ground Aggregate Receiving
Hopper or from Aggregate Storage Bins to Overhead Aggregates Storage Bins |
·
The sand
and aggregates are transferred by fully enclosed conveyors1 ·
Aggregate
conveyor and Transfer Points are fully enclosed1 ·
The sand
and aggregates are unloaded into fully enclosed overhead storage bins1 |
|
Batching of Sand And Aggregates |
a. Weighing and Batching of Sand and Aggregate by Aggregate
Weigh Hopper |
·
The sand
and aggregates are transferred and weighed within an enclosed structure1 |
Unloading of Cementitious Material |
a. Transfer of Cementitous Material from Cement Barge to Cement
Tankers or directly to Plant Silos |
·
All
cementitious materials are transferred within a fully enclosed piping system1,2 ·
The cement
blower of barge is enclosed1,2 ·
The cement
tanker and silos are fully enclosed systems1,2 ·
Dust-laden
air is filtered through bag filter and vented to the dust collectors1,2 |
Transferring of Cementitious Material |
a. Transferring of Cementitious Material from cement tanker to
Silos |
·
The silos
are fully enclosed1,2 ·
Dust-laden
air is filtered through bag filter and vented tot he dust collectors1,2 ·
The level
alarms are installed for all silos to prevent overfilling1,2 ·
Cement
Tanker will transfer the materials within an enclosure1,2 |
Batching of Cementitious Material |
a. Weighing and batching of Cementitious Material by Cement
Weigh Hoppers |
·
The weigh
hopper is fully enclosed1,2 ·
Dust-laden
air from the cementitious weigh hoppers is filtered through bag filter and
vented to the dust collector1,2 ·
Cementitious
transfer using fully enclosed pipes and screw conveyors1,2 |
Mixing of Sand, Aggregates and Cementitious Material |
a. Mixing of Batched Sand, Aggregates and Cementitious Material
in the Concrete Mixer |
·
The mixer
is fully enclosed1,2 ·
Dust-laden
air in the mixer is filtered though bag filter and vented to the dust
collector1,2 |
Truck Loading |
a. Loading of mixed concrete into the trucks |
·
All mixing
& loading conduct in fully enclosed area1 ·
Truck
loaded with concrete in “Wet” form1,2 |
Plant Yard |
a. The Concrete Batching Plant Area |
·
Floor to
be concrete paved1,2 ·
Pavement
to be kept moist with water1,2 |
Concrete trucks |
a. Concrete Delivery Mixer Trucks within Cyber Port Site |
·
Well
maintained trucks3 ·
Clean
trucks regularly1 ·
Trucks
comply with APCO regulations2 |
Plant Equipment |
a. Facilities and equipment operates within the batching plant
for handling materials and producing concrete |
·
Perform
regular maintenance works for plant equipment1,3 ·
Maintain
all environmental control facilities in operating condition3 |
4.29
Sample of computer
output is shown in Appendix 4.3.
4.30
Results in Tables
4.6 and 4.7 demonstrate that the TSP concentrations arising from the batching
plant at the representative ASRs are well below the AQOs. Therefore, there is
no air quality impact arising from the plant on the nearby ASRs.
Table 4.6 Predicted TSP Concentration Levels at Representative Air
Sensitive Receivers without mitigation at 1.5m height
|
|
TSP Concentration (mgm-3) |
|||||||
|
|
Concrete1 |
Others2 |
Background |
Overall |
||||
|
|
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
1 |
SR1 |
8 |
4 |
432 |
216 |
265 |
59 |
705 |
279 |
2 |
SR2 |
11 |
5 |
550 |
275 |
265 |
59 |
826 |
339 |
3 |
SR3 |
13 |
7 |
685 |
342 |
265 |
59 |
963 |
408 |
4 |
SR4 |
19 |
9 |
957 |
479 |
265 |
59 |
1241 |
547 |
5 |
SR5 |
24 |
12 |
1108 |
554 |
265 |
59 |
1397 |
625 |
6 |
SR6 |
24 |
12 |
1162 |
581 |
265 |
59 |
1451 |
652 |
7 |
SR7 |
26 |
13 |
1296 |
648 |
265 |
59 |
1587 |
720 |
8 |
SR8 |
30 |
15 |
1453 |
726 |
265 |
59 |
1748 |
800 |
9 |
SR9 |
22 |
11 |
1091 |
545 |
265 |
59 |
1378 |
615 |
10 |
SR10 |
26 |
13 |
1341 |
670 |
265 |
59 |
1632 |
742 |
11 |
SR11 |
20 |
10 |
961 |
481 |
265 |
59 |
1246 |
550 |
12 |
SR12 |
16 |
8 |
772 |
386 |
265 |
59 |
1053 |
453 |
13 |
SR13 |
13 |
7 |
671 |
336 |
265 |
59 |
949 |
402 |
14 |
SR14 |
11 |
5 |
540 |
270 |
265 |
59 |
816 |
334 |
15 |
SR18 |
11 |
6 |
476 |
238 |
265 |
59 |
752 |
303 |
16 |
SR19 |
57 |
29 |
1078 |
539 |
265 |
59 |
1400 |
627 |
17 |
SR21 |
23 |
12 |
543 |
271 |
265 |
59 |
831 |
342 |
18 |
SR22 |
18 |
9 |
529 |
265 |
265 |
59 |
812 |
333 |
19 |
SR23 |
13 |
7 |
739 |
369 |
265 |
59 |
1017 |
435 |
20 |
SR24 |
15 |
8 |
1010 |
505 |
265 |
59 |
1290 |
572 |
21 |
SR25 |
13 |
7 |
788 |
394 |
265 |
59 |
1066 |
460 |
22 |
SR26 |
13 |
6 |
763 |
382 |
265 |
59 |
1041 |
447 |
23 |
SR27 |
20 |
10 |
1011 |
505 |
265 |
59 |
1296 |
574 |
24 |
SR40 |
14 |
7 |
791 |
395 |
265 |
59 |
1070 |
461 |
1Concrete batching plant, with dust
suppression measures
2Concurrent construction works at
the site
Bolded figure indicate the exceedance of
the 1-hr or 24-hr TSP criteria
Table 4.7 Predicted TSP Concentration Levels at Representative Air
Sensitive Receivers without mitigation at 10m height
|
|
TSP Concentration (mgm-3) |
|||||||
|
|
Concrete1 |
Others2 |
Back- |
Overall |
||||
|
|
1-hr |
24-hr |
1-hr |
24-hr |
ground |
1-hr |
24-hr |
|
1 |
SR1 |
9 |
4 |
446 |
223 |
265 |
59 |
720 |
286 |
2 |
SR2 |
11 |
5 |
560 |
280 |
265 |
59 |
836 |
344 |
3 |
SR3 |
13 |
7 |
689 |
344 |
265 |
59 |
967 |
410 |
4 |
SR4 |
19 |
9 |
936 |
468 |
265 |
59 |
1220 |
536 |
5 |
SR5 |
24 |
12 |
1051 |
526 |
265 |
59 |
1340 |
597 |
6 |
SR6 |
24 |
12 |
1103 |
552 |
265 |
59 |
1392 |
623 |
7 |
SR7 |
25 |
13 |
1217 |
609 |
265 |
59 |
1507 |
681 |
8 |
SR8 |
29 |
15 |
1323 |
662 |
265 |
59 |
1617 |
736 |
9 |
SR9 |
21 |
11 |
1053 |
526 |
265 |
59 |
1339 |
596 |
10 |
SR10 |
25 |
13 |
1260 |
630 |
265 |
59 |
1550 |
702 |
11 |
SR11 |
20 |
10 |
933 |
467 |
265 |
59 |
1218 |
536 |
12 |
SR12 |
16 |
8 |
764 |
382 |
265 |
59 |
1045 |
449 |
13 |
SR13 |
13 |
7 |
672 |
336 |
265 |
59 |
950 |
402 |
14 |
SR14 |
11 |
5 |
549 |
274 |
265 |
59 |
825 |
338 |
15 |
SR18 |
11 |
6 |
479 |
240 |
265 |
59 |
755 |
305 |
16 |
SR19 |
53 |
26 |
952 |
476 |
265 |
59 |
1270 |
561 |
17 |
SR21 |
23 |
12 |
521 |
260 |
265 |
59 |
809 |
331 |
18 |
SR22 |
18 |
9 |
523 |
262 |
265 |
59 |
806 |
330 |
19 |
SR23 |
14 |
7 |
735 |
368 |
265 |
59 |
1014 |
434 |
20 |
SR24 |
15 |
8 |
896 |
448 |
265 |
59 |
1176 |
515 |
21 |
SR25 |
13 |
7 |
765 |
383 |
265 |
59 |
1043 |
449 |
22 |
SR26 |
13 |
6 |
734 |
367 |
265 |
59 |
1012 |
432 |
23 |
SR27 |
20 |
10 |
948 |
474 |
265 |
59 |
1233 |
543 |
24 |
SR40 |
14 |
7 |
785 |
392 |
265 |
59 |
1064 |
458 |
1Concrete batching plant, with dust
suppression measures
2Concurrent construction works
at the site
Bolded figure indicate the exceedance of
the 1-hr or 24-hr TSP criteria
4.31
Contours of the
cumulative 1-hour and 24-hour average TSP concentrations at the levels of 1.5m
and 10m above ground are presented in Figures 4.2 and 4.3, showing exceedance
of the TSP criteria at sensitive receiver locations.
4.32
As shown in Tables
4.6 and 4.7, the cumulative TSP concentrations are expected to exceed the TSP criteria at all Air sensitive
Receivers. In order to comply with the
TSP criteria, the following mitigation measures are proposedhave incorporated for the
concurrent construction works at Telegraph Bay:
Twice daily watering (with complete coverage) of the whole
area. Through the implementation of
this mitigation measure, dust emissions from materials handling can be reduced
by 50%, according to AP-42.
Speed control of dump truck in site area can reduce dust
generation by 50%, according to AP-42.
A watering program of once every 2 hours in normal weather
conditions, and hourly in dry/windy condition on all haul roads can reduce dust
emission by 97%, according to the Scheme 1 of the EIA report for the
Infrastructural Works for the Proposed Development at Telegraph Bay.
4.33
The mitigated
cumulative 1-hour and 24-hour average TSP concentrations are shown in Tables
4.8 and 4.9. The contours of the TSP concentration are shown in Figures 4.4 and
4.5.
Table 4.8 Predicted TSP Concentration Levels at Representsative Air
Sensitive Receivers with mitigation at 1.5m height
|
|
TSP Concentration (mgm-3) |
|||||||
|
|
Concrete1 |
Others2 |
Background |
Overall |
||||
|
|
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
1 |
SR1 |
8 |
4 |
16 |
8 |
265 |
59 |
289 |
71 |
2 |
SR2 |
11 |
5 |
20 |
10 |
265 |
59 |
296 |
74 |
3 |
SR3 |
13 |
7 |
25 |
12 |
265 |
59 |
303 |
78 |
4 |
SR4 |
19 |
9 |
34 |
17 |
265 |
59 |
318 |
85 |
5 |
SR5 |
24 |
12 |
41 |
21 |
265 |
59 |
330 |
92 |
6 |
SR6 |
24 |
12 |
42 |
21 |
265 |
59 |
331 |
92 |
7 |
SR7 |
26 |
13 |
45 |
23 |
265 |
59 |
336 |
95 |
8 |
SR8 |
30 |
15 |
51 |
25 |
265 |
59 |
346 |
99 |
9 |
SR9 |
22 |
11 |
39 |
19 |
265 |
59 |
326 |
89 |
10 |
SR10 |
26 |
13 |
47 |
24 |
265 |
59 |
338 |
96 |
11 |
SR11 |
20 |
10 |
35 |
18 |
265 |
59 |
320 |
87 |
12 |
SR12 |
16 |
8 |
28 |
14 |
265 |
59 |
309 |
81 |
13 |
SR13 |
13 |
7 |
24 |
12 |
265 |
59 |
302 |
78 |
14 |
SR14 |
11 |
5 |
20 |
10 |
265 |
59 |
296 |
74 |
15 |
SR18 |
11 |
6 |
18 |
9 |
265 |
59 |
294 |
74 |
16 |
SR19 |
57 |
29 |
40 |
20 |
265 |
59 |
362 |
108 |
17 |
SR21 |
23 |
12 |
20 |
10 |
265 |
59 |
308 |
81 |
18 |
SR22 |
18 |
9 |
20 |
10 |
265 |
59 |
303 |
78 |
19 |
SR23 |
13 |
7 |
26 |
13 |
265 |
59 |
304 |
79 |
20 |
SR24 |
15 |
8 |
37 |
18 |
265 |
59 |
317 |
85 |
21 |
SR25 |
13 |
7 |
29 |
14 |
265 |
59 |
307 |
80 |
22 |
SR26 |
13 |
6 |
28 |
14 |
265 |
59 |
306 |
79 |
23 |
SR27 |
20 |
10 |
38 |
19 |
265 |
59 |
323 |
88 |
24 |
SR40 |
14 |
7 |
28 |
14 |
265 |
59 |
307 |
80 |
1Concrete batching plant, with dust
suppression measures
2Concurrent construction works at
the site, with dust suppression measures
Table 4.9 Predicted TSP Concentration Levels at the Selected Air
Sensitive Receivers with mitigation at 10m height
|
|
TSP Concentration (mgm-3) |
||||||||
|
|
Concrete1 |
Others2 |
Background |
Overall |
|||||
|
|
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
1-hr |
24-hr |
|
1 |
SR1 |
8 |
4 |
16 |
8 |
265 |
59 |
289 |
71 |
|
2 |
SR2 |
11 |
5 |
20 |
10 |
265 |
59 |
296 |
74 |
|
3 |
SR3 |
13 |
7 |
25 |
12 |
265 |
59 |
303 |
78 |
|
4 |
SR4 |
19 |
9 |
34 |
17 |
265 |
59 |
318 |
85 |
|
5 |
SR5 |
24 |
12 |
39 |
20 |
265 |
59 |
328 |
91 |
|
6 |
SR6 |
24 |
12 |
40 |
20 |
265 |
59 |
329 |
91 |
|
7 |
SR7 |
26 |
13 |
43 |
21 |
265 |
59 |
334 |
93 |
|
8 |
SR8 |
30 |
15 |
46 |
23 |
265 |
59 |
341 |
97 |
|
9 |
SR9 |
22 |
11 |
37 |
19 |
265 |
59 |
324 |
89 |
|
10 |
SR10 |
26 |
13 |
44 |
22 |
265 |
59 |
335 |
94 |
|
11 |
SR11 |
20 |
10 |
34 |
17 |
265 |
59 |
319 |
86 |
|
12 |
SR12 |
16 |
8 |
28 |
14 |
265 |
59 |
309 |
81 |
|
13 |
SR13 |
13 |
7 |
24 |
12 |
265 |
59 |
302 |
78 |
|
14 |
SR14 |
11 |
5 |
20 |
10 |
265 |
59 |
296 |
74 |
|
15 |
SR18 |
11 |
6 |
18 |
9 |
265 |
59 |
294 |
74 |
|
16 |
SR19 |
57 |
29 |
36 |
18 |
265 |
59 |
358 |
106 |
|
17 |
SR21 |
23 |
12 |
19 |
10 |
265 |
59 |
307 |
81 |
|
18 |
SR22 |
18 |
9 |
19 |
10 |
265 |
59 |
302 |
78 |
|
19 |
SR23 |
13 |
7 |
26 |
13 |
265 |
59 |
304 |
79 |
|
20 |
SR24 |
15 |
8 |
32 |
16 |
265 |
59 |
312 |
83 |
|
21 |
SR25 |
13 |
7 |
28 |
14 |
265 |
59 |
306 |
80 |
|
22 |
SR26 |
13 |
6 |
27 |
13 |
265 |
59 |
305 |
78 |
|
23 |
SR27 |
20 |
10 |
35 |
18 |
265 |
59 |
320 |
87 |
|
24 |
SR40 |
14 |
7 |
28 |
14 |
265 |
59 |
307 |
80 |
|
1Concrete batching plant, with dust
suppression measures
2Concurrent construction works at
the site, with dust suppression measures
4.34
From the results,
it was noted that with the implementation of the dust suppression measures on
the concurrent construction works at Telegraph Bay, no adverse cumulative dust
impact is expected at all ASRs.
4.35
The construction
works of the concrete batching plant are much smaller than the concurrent
construction works of the Telegraph Bay Reclamation. Therefore, the dust impact
during construction phase of the concrete batching plant is insignificant.
However, during the construction of concrete batching plant, the Air Pollution
Control (Construction Dust) Regulation would be strictly followed.
4.36
During operation
phase, the concrete batching plant should strictly follow the requirements stipulated
in the Best Practicable Means Requirement for Cement Works (Concrete Batching
Plant) and the Air Pollution Control (Construction Dust) for dust control.
Besides, the following practices will also be incorporated:
·
Dust collectors
will be sized to exceed the requirement of the Specified Processes Regulation.
·
For Stage 1, the
cement tankers will be working inside enclosure with cladding to reduce air quality impactnoise.
·
For stage 2,
cement will be transferred directly from barges to the plant. There is no need
for cement tankers for intermediate transfer.
4.37
With the
implementation of the mitigation measures at the concrete batching plant and
the concurrent construction site at the Telegraph Bay, the predicted cumulative
1-hour and 24 hour TSP concentration are expected to comply with the Air
Quality Objectives.