5.0       Noise Impact

Introduction

5.1               During the construction and operation of the proposed on-site concrete batching plant, other construction works such as road works (construction of Northern Access Road, Southern Access Road, D1 and D2 roads) and main construction works will be carried out concurrently.  Noise arising from these construction and operation activities are likely to create noise impacts on the surrounding NSRs. The extent of the impacts affecting the identified NSRs will vary from phase to phase depending upon the types of powered mechanical equipment (PME) used and locations of works to be carried out.

5.2               This section presents an assessment for the possible cumulative noise impacts arising from the road works, main construction work, together with the construction/operation of the proposed concrete batching plant at Telegraph Bay between December 2000 and December 2001.

Government Legislation and Standards

5.3               The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) provides guidance on construction noise levels at the openable windows of various types of noise sensitive buildings. The recommended noise standards are presented in Table 5.1.

Table 5.1         EIAO-TM Daytime Construction Noise Guidelines (Leq, 30min dB(A))

Land Use

Noise Standards dB(A)

Domestic Premises

75

Educational Institutions (normal periods)

70

Educational Institutions (during examination periods)

65

5.4               The target construction noise impact upon school adopted in this assessment is 65 dB(A). However, it is recongized that this target is only applicable during examinations periods, and EIAO-TM provides guidance on construction noise levels at the openable windows of various types of noise sensitive buildings.

5.5               The Noise Control Ordinance (NCO) provides statutory controls on general construction works during the restricted hours (i.e. 1900 to 0700 hours Monday to Saturday and at any time on Sundays and public holidays). The use of powered mechanical equipment (PME) for the carrying out of construction works during the restricted hours would require a Construction Noise Permit (CNP).  Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a CNP will be issued for the project construction.  The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the NCO.  The Noise Control Authority (NCA)will take into account of contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.  Nothing in this EIA Report shall bind the NCA in making his decision.  If a CNP is to be issued, the NCA shall included in it any condition he thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

Assessment Methodology

5.6               Noise predictions were undertaken for the Cyberport Development and its Associated Engineering Infrastructure works in accordance with the methodology outlined in the GW-TM. Additional information was obtained from “A Practical Guide to the Reduction of Noise from Construction Works’, EPD 1989 and British Standard 5228 Part 1: 1997, ‘Noise Control on Construction and Open Sites’.

5.7               A positive correction of 3 dB(A) was made to the calculated result to allow for façade effect. Also, the distance between the batching plant and noise sensitive receivers (NSRs) would be determined [D].  For distance attenuation equals to or below 300m, reference to Table 5 of the GW-TM has been made.  For distance attenuation above 300m, it has been estimated using the following formula:

Distance Attenuation in dB(A) = 20 log D +8 [where D is the distance in metre]

5.8               The distance attenuation calculated from the above formula would be subtracted from the total sound power level to give the Predicted Noise Level (PNL) at the existing NSR.

5.9               This assessment presents only the impacts during normal daytime hours (07:00 – 19:00) excluding Sundays and Public Holidays work. The relevant noise criteria as stipulated in the EIAO-TM are 75 dB(A) for residential dwellings, and 70dB(A) for education institutions during normal periods and 65dB(A) during examination periods.

5.10            The construction and operation of the concrete batching plant, and the construction of the road works and main works for cyberport will be carried out concurrently and therefore assessment for the possible cumulative noise impacts from these activities are required.  Since the assessment of the Northern Access Road and other main works are performed by two separate consultants. For the purpose of the cumulative assessment, the noise impacts arising from the construction of Northern Access Road and other main works have been made reference to the following two documents:

·         R1: Main Work for Cyber Port Development Environmental Permit Variation Application – Construction Noise Impact Assessment (February 2000); and

 

·         R2: Northern Access Road for Cyberport Development Environmental Permit Application – Supplementary Environmental Assessment Report (July 2000);

5.11            The mitigated noise levels at the existing NSRs during the construction of both Northern Access Road and other roads have been calculated in the above documents.  The highest mitigated noise level at each of the NSR as given in Appendix 5.1 has been used for the cumulative noise predictions.  


Identification of Sensitive Receivers

5.12            Twenty-two representative NSRs similar to those identified in the two documents have been selected for the cumulative noise assessment and are listed in Table 5.2. 

Table 5.2         Proposed Noise Sensitive Receivers (NSRs) during Construction of Telegraph Bay Development

 

NSR No.

Description

 

Land Use*

 

No. of Storeys

SR2

Tam Villa

R

22

SR3

HKU Staff Quarters

R

12

SR4-8

42,45,47,50 & 60 Sasson Road

R

3

SR9

Magnolia Villas

R

3

SR10

Point Breeze

R

3

SR11

Carriana Sasson

R

3

SR12

Stone Manor

R

3

SR13

Provident Villas

R

3

SR19

16-18 Baguio Villas

R

10

SR19 a, b

45-48 Baguio Villas

R

29

SR21

Pok Fu Lam Training Centre

S

7

SR22

Pok Fu Lam Garden

R

28

SR23

Wah Fu Estate

R

21

SR24

Lui Ming Choi Secondary School

S

7

SR25

Precious Blood Primary School

S

5

SR26

Tsui Ching Tong School For the Handicap

S

6

SR27

Kong Sin Wan Tsuen

R

2-3

SR40

Pui Ying Secondary School

S

7

* Residential Uses – R, School Uses - S

 

 

Noise Impact Assessment

 

        Potential Construction Noise Impacts

5.13            The construction and operation of the proposed concrete batching plant is scheduled to be carried out from December 2000 to December 2001, including three phases as shown in the following table.

12/2000

01/2001 – 03/2001

04/2001 – 12/2001

Phase 1

Phase 2

Phase 3

Construction of Stage 1 batching plant

Construction of Stage 2 batching plant and operation of Stage 1 batching plant

Operation of Stage 2 batching plant

 

5.14            A list of powered mechanical equipment (PME) items to be used during the construction and operation of the concrete batching plant, as well as the associated sound power levels (SWLs) are given in the Appendix 5.2.  As the conveyor belt will be fully enclosed on all four sides and therefore its contribution to the total sound power level of the concrete batching plant is excluded. 

5.15            The unmitigated noise levels for the construction and operation of the concrete batching plant in the three phases at the representative NSRs have been predicted and are presented in Table 5.3. The notional noise source due to the construction of the concrete batching plant and the location of the concrete batching plant are approximately the same. Therefore, same distances are assumed in the assessment of the construction and operation phases noise impact.

Table 5.3         Predicted Noise level due to the operation and construction of Concrete Batching Plant only (Unmitigated)

 

NSR No.

Approximately Distance to the notional Noise Source of the concrete batching plant(m)

Predicted Noise Level, dB(A)

EIAO-TM Noise Criteria, dB(A)

Phase 1

Phase 2

Phase 3

SR2

930

60

61

59

75

SR3

813

61

62

60

75

SR4

663

62

64

62

75

SR5

585

64

65

63

75

SR6

565

64

66

63

75

SR7

562

64

66

63

75

SR8

500

65

67

64

75

SR9

613

63

65

62

75

SR10

570

64

66

63

75

SR11

650

63

64

62

75

SR12

763

61

63

61

75

SR13

813

61

62

60

75

SR19

325

69

70

68

75

SR19 a

380

67

69

67

75

SR19 b

398

67

69

66

75

SR21*

600

63

65

63

70 (65)

SR22

695

62

64

61

75

SR23

825

61

62

60

75

SR24*

763

61

63

61

70 (65)

SR25*

850

60

62

60

70 (65)

SR26*

863

60

62

59

70 (65)

SR27

633

63

65

62

75

SR40*

830

60

62

60

70 (65)

Note: *   denotes education institution

Sound Pressure Level inside ( ) indicates the noise limit for education institutions during the examination period.

5.16            As indicated in Table 5.3, the noise levels at the NSRs are predicted to be in the range of 59-70dB(A).  The predicted noise levels at all the residential and educational NSRs would be below the noise criterion of 75dB(A) for residential dwellings and 70dB(A) for schools during normal periods and 65dB(A) during examination periods.

5.17            In order to assess the possible cumulative effect of the noise from the construction of Northern Access Road and other roads, and the construction/operation of the concrete batching plant, the cumulative noise levels at the representative NSRs have been calculated and are presented in Table 5.4.  The cumulative noise levels at the NSRs are predicted to vary between 59 and 76dB(A).  The result indicates that though the cumulative noise levels at all the educational NSRs would comply with the noise criterion of 70dB(A), the cumulative noise levels at some of schools still exceed the noise criterion of 65 dB(A) during examination. On the other hand, due to the cumulative effect, the noise levels at a residential NSR (SR19) are predicted to exceed 75dB(A) criterion by 1dB(A) during the duration between January and March of 2001.  Hence, appropriate mitigation measures for the construction and operation of batching plant are required to alleviate the noise impacts.  The appropriate mitigation measures are recommended in the following sections.

Table 5.4         Cumulative Construction Noise Levels (Unmitigated)

NSR

Dec-00

Jan-01

Feb-01

Mar-01

Apr-01

May-01

Jun-01

Jul-01

Aug-01

Sep-01

Oct-01

Nov-01

Dec-01

SR2

65

63

63

62

61

65

61

59

61

61

61

61

61

SR3

75

74

74

75

72

74

75

68

75

75

74

73

73

SR4

74

73

74

69

72

74

69

66

69

69

69

72

72

SR5

66

68

68

68

66

66

66

66

65

65

65

65

65

SR6

64

66

67

66

66

66

66

66

66

66

66

63

63

SR7

69

71

72

72

72

72

72

72

70

70

70

65

67

SR8

72

74

74

74

74

74

74

75

72

71

71

66

70

SR9

75

75

75

74

74

75

73

70

72

72

72

75

75

SR10

69

71

70

71

70

70

69

69

66

65

66

65

67

SR11

65

66

66

66

65

65

65

65

64

64

64

64

64

SR12

64

65

65

65

64

64

64

64

63

63

63

63

63

SR13

63

64

64

64

63

63

63

63

62

62

62

62

62

SR19

75

76

76

76

75

75

75

75

74

74

74

74

74

SR19A

74

75

75

75

74

74

74

74

73

73

73

73

73

SR19B

74

75

75

75

74

74

74

74

73

73

73

73

73

SR21*

66

67

67

67

66

66

66

66

65

65

65

65

65

SR22

66

67

67

67

65

65

65

65

64

64

64

64

64

SR23

66

66

66

66

65

65

62

62

62

62

62

62

62

SR24*

67

66

66

66

65

65

64

64

64

64

64

64

64

SR25*

62

63

63

63

61

61

63

63

63

63

63

63

63

SR26*

64

64

64

64

63

63

62

62

62

62

62

62

62

SR27

64

66

66

66

64

64

64

64

63

63

63

63

63

SR40*

64

64

64

64

63

63

62

62

61

61

61

61

61

Noted: *  denotes educated institutes

Bold means exceedance of the EIAO-TM criteria (75 dB(A) for residential dwellings, 70dB(A) for education institutions during normal periods and 65dB(A) for education institutions during examination period)

 

            Mitigation Measures

5.18            In order to alleviate the noise impacts from the construction and operation of the concrete batching plant, appropriate and practicable mitigation measures have been recommended and are presented in the following sections.

Selecting Quiet Plant and Working Methods

5.19            The most effective way to mitigate noise impact is to reduce noise at source. This involves using quieter equipment plants. With reference to the two documents (R1 and R2), GW-TM and the BS5228: Part 1: 1997 “Noise Control on Construction and open Sites”, some quieter equipment has been selected, including generator, excavator, mobile crane, truck and vibration poker.

5.20            In addition to the above recommended mitigation measures, percentage ‘on-time’ of each PME (the time when the PME is in operation within a 30 minutes time slot) has been taken into account to give a more realistic calculation. 

5.21            With the adoption of the recommended mitigation measures and the percentages ‘on –time, the total SWLs for the construction and operation activities of the batching plant are presented in Appendix 5.3.  The mitigated noise levels for the Concrete Batching Plant and the cumulative noise levels at the representative NSRs have been calculated and are given in Table 5.5 and 5.6, respectively. 

5.22            As indicated in Table 5.6, with the implementation of the recommended mitigation measures, the cumulative construction noise levels at almost all the NSRs (except 24) could be mitigated to be within the EIAO-TM criteria of 75dB(A) for residential dwellings, and 70dB(A) for education institutions during normal periods and 65dB(A) for examination.  Therefore, no further mitigation measures are required.

5.23            However, it is noted that 1dB(A) exceedances of the 65dB(A) (noise criterion for schools during examination periods) at SR24 (Lui Ming Choi Secondary School) are predicted in December 2000.  On checking with the examination schedule in Lui Ming Choi Secondary School, there is no examination in December. Therefore, the cumulative predicted noise level at SR24 still complies with the 70dB(A) for education institutions during normal periods.


Table 5.5         Predicted Noise level due to the operation and construction of Concrete Batching Plant only (Mitigated)

 

NSR

Dec-00

Jan-01

Feb-01

Mar-01

Apr-01

May-01

Jun-01

Jul-01

Aug-01

Sep-01

Oct-01

Nov-01

Dec-01

SR2

52

57

57

57

56

56

56

56

56

56

56

56

56

SR3

53

58

58

58

58

58

58

58

58

58

58

58

58

SR4

55

60

60

60

59

59

59

59

59

59

59

59

59

SR5

56

61

61

61

60

60

60

60

60

60

60

60

60

SR6

56

61

61

61

61

61

61

61

61

61

61

61

61

SR7

57

61

61

61

61

61

61

61

61

61

61

61

61

SR8

58

62

62

62

62

62

62

62

62

62

62

62

62

SR9

56

61

61

61

60

60

60

60

60

60

60

60

60

SR10

56

61

61

61

61

61

61

61

61

61

61

61

61

SR11

55

60

60

60

60

60

60

60

60

60

60

60

60

SR12

54

59

59

59

58

58

58

58

58

58

58

58

58

SR13

53

58

58

58

58

58

58

58

58

58

58

58

58

SR19

61

66

66

66

66

66

66

66

66

66

66

66

66

SR19A

60

65

65

65

64

64

64

64

64

64

64

64

64

SR19B

60

64

64

64

64

64

64

64

64

64

64

64

64

SR21*

56

61

61

61

60

60

60

60

60

60

60

60

60

SR22

55

60

60

60

59

59

59

59

59

59

59

59

59

SR23

53

58

58

58

57

57

57

57

57

57

57

57

57

SR24*

54

59

59

59

58

58

58

58

58

58

58

58

58

SR25*

53

58

58

58

57

57

57

57

57

57

57

57

57

SR26*

53

58

58

58

57

57

57

57

57

57

57

57

57

SR27

55

60

60

60

60

60

60

60

60

60

60

60

60

SR40*

53

58

58

58

57

57

57

57

57

57

57

57

57

Noted: *  denotes educated institutes

 

Table 5.6         Cumulative Noise Levels (Mitigated)

NSR

Dec-00

Jan-01

Feb-01

Mar-01

Apr-01

May-01

Jun-01

Jul-01

Aug-01

Sep-01

Oct-01

Nov-01

Dec-01

SR2

64

61

60

59

60

64

59

56

60

60

60

60

60

SR3

74

74

73

75

72

74

75

67

75

75

74

73

73

SR4

73

72

73

68

72

74

68

65

68

68

68

72

72

SR5

64

65

65

65

65

65

65

65

64

64

64

64

64

SR6

57

61

65

62

65

65

65

65

65

65

65

61

61

SR7

68

70

71

71

72

72

72

72

70

70

70

63

66

SR8

72

73

73

74

74

74

74

74

71

71

71

65

69

SR9

74

74

75

74

74

75

72

70

72

72

72

75

73

SR10

67

70

69

70

70

70

69

69

64

63

64

63

66

SR11

62

64

64

64

64

64

64

64

62

62

62

62

62

SR12

61

63

63

63

63

63

63

63

61

61

61

61

61

SR13

60

62

62

62

62

62

62

62

61

61

61

61

61

SR19

74

75

75

75

75

75

75

75

73

73

73

73

73

SR19A

73

74

74

74

74

74

74

74

73

73

72

73

73

SR19B

73

74

74

74

74

74

74

74

73

73

73

73

73

SR21*

64

65

65

65

65

65

65

65

64

64

64

64

64

SR22

64

65

65

65

65

65

64

64

63

63

63

63

63

SR23

65

65

65

65

65

65

61

61

61

61

61

61

61

SR24*

66

65

65

65

65

65

63

63

63

63

63

63

63

SR25*

59

60

60

60

59

59

62

62

62

62

62

62

62

SR26*

63

62

62

62

62

62

61

61

61

61

61

61

61

SR27

60

62

62

62

62

62

62

62

61

61

61

61

61

SR40*

62

62

62

62

62

62

60

60

60

60

60

60

60

Noted: *  denotes educated institutes

 

Monitoring Audit

5.24            The Independent Environmental Consultant should conduct regular monitoring and audit during the construction works.

Conclusions

5.25            The construction of Roads and other Main works, and the construction /operation of the concrete batching plant will be carried out concurrently.  An assessment for cumulative construction noise impacts arising from these activities has been conducted.  The assessment result shows that the cumulative noise levels at some NSRs (SR19, 21 and 24) would likely exceed the EIAO-TM noise criteria without mitigation measures for the construction/operation of the concrete batching plant. 

5.26            In order to alleviate the cumulative noise impacts, appropriate mitigation measures including the use of quiet equipment in both construction and operation stages of the concrete batching plant. With the adoption of the recommended mitigation measures, the predicted noise levels at all the representative NSRs would comply with the EIAO-TM criteria for residential dwellings and for schools during normal and examination periods.