Introduction
9.1 In order to reduce the potential impact
due to the construction and operation of the concrete batching plant, the
following tables summarize the implementation schedules in during the design,
construction, operation and decommissioning of the concrete batching plant.
Implementation Schedule of
Mitigation Measures for Air Quality Control on the Concrete Batching Plant
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Water spray installed on barge
for wetting the sand and aggregates1. Conveyor barge used for unloading aggregate3. Fully enclosed conveyor used to unload the material to the
aggregate-receiving hopper1. Aggregate receiving hopper
installed with 3 sides and water spray1. The wetted sand and aggregates
are loaded into the tipper truck in enclosed loadout section1. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The storage yards are installed with 3 sides enclosure and roof,
curtain at entrance1. Water spray is installed in storage yard for wetting the sand
and aggregates1. Aggregate Storage Bins and
Aggregate Overhead Storage Bins are fully enclosed1. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The tipper trucks with wetted sand and aggregates are covered
with plastic canvas2. The aggregate materials are
unloaded into storage yards which has 3 sides enclosure and roof, curtain at
entrance and water spray1. The sand and aggregates are wetted before transferring to
aggregate receiving hopper1. Aggregate receiving hopper
installed with 3 sides and roof and water spray1. The sand and aggregates are transferred by fully enclosed
conveyors1. Aggregate conveyor and Transfer Points are fully enclosed1. The sand and aggregates are
unloaded into fully enclosed overhead storage bins1. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The sand and aggregates are
transferred and weighed within an enclosed structure1. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
All cementitious materials are transferred within a fully
enclosed piping system1,2. The cement blower of barge is enclosed1,2. The cement tanker and silos are fully enclosed systems1,2. Dust-laden air is filtered
through bag filter and vented to the dust collectors1,2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The silos are fully enclosed1,2. Dust-laden air is filtered through bag filter and vented to the
dust collectors1,2. The level alarms are installed for all silos to prevent
overfilling1,2. Cement Tanker will transfer the
materials within an enclosure1,2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
The weigh hopper is fully enclosed1,2. Dust-laden air from the cementitious weigh hoppers is filtered
through bag filter and vented to the dust collector1,2. Cementitious transfer using
fully enclosed pipes and screw conveyors1,2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The mixer is fully enclosed1. Dust-laden air in the mixer is
filtered though bag filter and vented to the dust collector1,2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
All mixing & loading conduct in fully enclosed area1,2. Truck loaded with concrete in
“Wet” form1,2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Well maintained trucks3. Clean trucks regularly1. Trucks comply with HKSAR
regulations2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Floor to be concrete paved1,2. Pavement to be kept moist with
water1,2. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Perform regular maintenance works for plant equipment1,3. Maintain all environmental
control facilities in operating condition3. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Implementation Schedule of Mitigation Measures for Air
Quality Control on the Concurrent Works at Telegraph Bay which was already in
place
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Regular watering of all haul
roads with complete coverage once every 2 hours in normal conditions and
hourly in dry / windy conditions |
Cyberport Construction |
Contractors |
|
Ö |
|
|
Speed control for all on-site
vehicle movement to 10km/h |
Cyberport Construction |
Contractors |
|
Ö |
|
|
Watering of the whole area with
complete coverage twice daily |
Cyberport Construction |
Contractors |
|
Ö |
|
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Implementation
Schedule of Mitigation Measures for Noise Control
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Use of quieter
equipment |
During the construction of the
Concrete batching Plant |
Contractors |
|
Ö |
|
|
Fully enclose the conveyor to
unload the material to the aggregrate receiving hopper |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Fully enclose the concrete mixer |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Mixer driven by electric motor |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Conduct all mixing and loading
in fully enclosed area |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Well maintain all concrete
trucks |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Perform regular maintenance
works for plant equipment |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
|
|
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Implementation Schedule of Mitigation
Measures for Water Pollution Control
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Works should be programmed to
avoid the rainy season whenever possible to minimise storm runoff. If work
during rainy season cannot be avoided, precautions should be taken to prevent
soil erosion. |
Throughout the construction of
concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Channel or earth bunds should be
constructed to direct the runoff to sand/silt removal facilities. |
Throughout the construction of
concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Perimeter channels should be
constructed to stop the storm runoff from washing across the site |
Throughout the construction of
concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Sand/silt removal facilities
should be checked and cleaned regularly to ensure these facilities are
working in good condition. |
Throughout the construction of
concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Exposed soil surface should be
paved to reduce the potential soil erosion. |
Throughout the construction of
concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Stockpiles of construction
materials on site should be covered with tarpaulins or similar fabric to prevent
surface erosion. Minimisation of stockpiling in the wet season will reduce
the chance of silt laden surface runoff from entering the ocean |
Throughout the construction of
concrete batching plant |
Plant
Operator |
|
Ö |
|
|
All washing water will be
collected, stored and recycled. No water will be discharged outside the plant
boundary |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Implementation Schedule of Mitigation
Measures for Waste Management
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Install a concrete recycling
machine to reduce material consumption and waste generation. |
Throughout the operation of
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Maintenance of records of
quantities of wastes generated, recycled and disposed, including disposal
location |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Where practicable, different
types of wastes should be segregated, stockpiled and stored in different
containers or skips to enhance reuse or recycling of materials and their
proper disposal |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Good site management, planning
and design considerations to reduce over-ordering and waste generation |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Educate workers on the concepts
of site cleanliness and appropriate waste management procedures |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Minimise land-take by reducing
the size of the stockpiles and associated working areas |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Provide fencing to separate
sensitive habits and landscape areas to prevent accidental stockpiling in
these areas |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Designate appropriate haulage
routes |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Keep material covered in heavy
rainfall |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Keep movement of stockpiled
material to a minimum |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Optimise reuse of suitable
material on site to reduce the volume of materials to be disposed to public
filling areas |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Use appropriate dust suppression
by use of appropriate bunding, interceptors and direction of run-off into
settlement ponds |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
For wastes with <20% of
non-inert materials, should be segregated and disposed of to public filling
area |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Waste collection by an approved
licensed waste collectors |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
All necessary waste disposal
permits should be obtained |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Store appropriately and isolate
from current working areas |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Secure storage area should be
set up for chemical waste storage (refer to ‘Practice on the Package,
Labelling and Storage of Chemical Wastes’) |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Implementation Schedule of Mitigation
Measures for Waste Management
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Erect appropriate fence and
signs beside the chemical waste storage area |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Minimise waste production and
careful handling of waste fuel and oil
residues |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Supply spill absorbent material
and emulsifiers in case of spillages |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Store wastes remote from
sensitive receivers |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Wastes should be stored in black
refuse bags prior to collection and disposal |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Frequent collection of general
refuse |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Regular maintenance and cleaning
of the waste storage areas |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Sewage generated on the site
should be controlled through the use of chemical toilets or sewage holding
tanks. Either would require regular cleaning with the resulting sewage
disposed of appropriately |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Storage of a material in
suitable containers |
Throughout the construction and
operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning
Implementation Schedule of Mitigation
Measures for Visual Impacts
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
The external façade and
reflective surface of the concrete batching plant shall be painted to dull
green to reduce reflection and increase the visual compatibility. |
Throughout the operation of the
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
* Des
= design, C = construction, O = operation, Dec = decommissioning