Appendix F1 Impact Prediction Review of Construction Dust at the Air Quality Monitoring Station
Table 1 Hourly & 24-Hour
Average TSP concentration at Discrete ASRs without mitigation at 1.5m height
during operational phase of batching plant and other concurrent construction
activities of Cyberport Development (mg/m3)
(Unmitigated)
ASR ID |
Air Monitoring Station ID |
TSP Concentrations (mg/m3) +
Background |
|||
1 - hour |
24 – hour |
||||
1.5 m |
10 m |
1.5 m |
10 m |
||
19 40 |
A1 A2 |
1400 1070 |
1270 1064 |
627 461 |
561 458 |
Table 2 Hourly & 24-Hour Average TSP
concentration at Discrete ASRs without mitigation at 1.5m height during
operational phase of batching plant and other concurrent construction
activities of Cyberport Development (mg/m3) (mg/m3) (Mitigated)
ASR ID |
Air Monitoring Station ID |
TSP Concentrations (mg/m3) +
Background |
|||
1 - hour |
24 – hour |
||||
1.5 m |
10 m |
1.5 m |
10 m |
||
19 40 |
A1 A2 |
362 307 |
358 307 |
108 80 |
106 80 |
Note :
1.
Bold
figures indicate exceedance of the 1-hr TSP criterion 500 mg/m3&
the 24-hr TSP criterion 260 mg/m3.
2.
Background
concentration : 265 mg/m3.for 1-hour TSP
& 59 mg/m3
for 24-hourTSP
The impact prediction review checklist is used to check the extent of discrepancy between the actual and the predicted impact at the designated monitoring stations. ET should estimate the efficiency of proposed mitigation and plan it carefully for the ongoing construction activities.
Appendix F2 Impact Prediction Review of Construction Noise at the Noise Monitoring Station
Table 1 Predicted Cumulative Construction Noise Levels at the Noise Monitoring Stations (Unmitigated)
NSR ID |
Noise Monitoring Station
ID |
Leq (30min)
dB(A) |
||||||||||||
Scenario |
||||||||||||||
Dec00 |
Jan01 |
Feb01 |
Mar01 |
Apr01 |
May 01 |
Jun01 |
Jul 01 |
Aug01 |
Sep01 |
Oct01 |
Nov01 |
Dec01 |
||
8 |
N1 |
72 |
74 |
74 |
74 |
74 |
74 |
74 |
75 |
72 |
71 |
71 |
66 |
70 |
27 |
N2 |
64 |
66 |
66 |
66 |
64 |
64 |
64 |
64 |
63 |
63 |
63 |
63 |
63 |
19 |
N3 |
75 |
76 |
76 |
76 |
75 |
75 |
75 |
75 |
74 |
74 |
74 |
74 |
74 |
40 |
N4 |
64 |
64 |
64 |
64 |
63 |
63 |
62 |
62 |
61 |
61 |
61 |
61 |
61 |
Table 2 Predicted Cumulative Construction Noise Levels at the Noise Monitoring Stations (Mitigated)
NSR ID |
Noise Monitoring Station
ID |
Leq (30min)
dB(A) |
||||||||||||
Scenario |
||||||||||||||
Dec00 |
Jan01 |
Feb01 |
Mar01 |
Apr01 |
May 01 |
Jun01 |
Jul 01 |
Aug01 |
Sep01 |
Oct01 |
Nov01 |
Dec01 |
||
8 |
N1 |
72 |
73 |
73 |
74 |
74 |
74 |
74 |
74 |
71 |
71 |
71 |
65 |
69 |
27 |
N2 |
60 |
62 |
62 |
62 |
62 |
62 |
62 |
62 |
61 |
61 |
61 |
61 |
61 |
19 |
N3 |
74 |
75 |
75 |
75 |
75 |
75 |
75 |
75 |
73 |
73 |
73 |
73 |
73 |
40 |
N4 |
62 |
62 |
62 |
62 |
62 |
62 |
60 |
60 |
60 |
60 |
60 |
60 |
60 |
Note :
1.
Bold figures indicate an
exccedance of the acceptable noise limits – Residential 75 dB(A), Schools 70
dB(A) (for normal school hours)
The impact prediction review checklist is used to check the extent of discrepancy between the actual and the predicted impact at the designated monitoring stations. ET should estimate the efficiency of proposed mitigation and plan it carefully for the ongoing construction activities.