Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Regular watering of all haul roads with
complete coverage once every 2 hours in normal conditions and hourly in dry /
windy conditions |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Speed control for all on-site vehicle
movement to 10km/h |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Watering of the whole area
with complete coverage twice daily |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Water spray installed on
barge for wetting the sand and aggregates. Conveyor
barge used for unloading aggregate. Fully
enclosed conveyor used to unload the material to the aggregate receiving
hopper. Aggregate receiving hopper
installed with 3 sides and water spray. The wetted sand and
aggregates are loaded into the tipper truck in enclosed loadout section. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The
storage yards are installed with 3 sides enclosure and roof, curtain at
entrance. Water
spray is installed in storage yard for wetting the sand and aggregates. Aggregate Storage Bins and
Aggregate Overhead Storage Bins are fully enclosed. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The
tipper trucks with wetted sand and aggregates are covered with plastic
canvas. The aggregate materials are
unloaded into storage yards which has 3 sides enclosure and roof, curtain at
entrance and water spray. The
sand and aggregates are wetted before transferring to aggregate receiving
hopper Aggregate receiving hopper
installed with 3 sides and roof and water spray. The
sand and aggregates are transferred by fully enclosed conveyors Aggregate
conveyor and Transfer Points are fully enclosed. The sand and aggregates are
unloaded into fully enclosed overhead storage bins. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The sand and aggregates are
transferred and weighed within an enclosed structure. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
All
cementitious materials are transferred within a fully enclosed piping system. The
cement blower of barge is enclosed. The
cement tanker and silos are fully enclosed systems. Dust-laden air is filtered
through bag filter and vented to the dust collectors. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
The
silos are fully enclosed Dust-laden
air is filtered through bag filter and vented to the dust collectors. The
level alarms are installed for all silos to prevent overfilling. Cement Tanker will transfer
the materials within an enclosure. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
The
weigh hopper is fully enclosed. Dust-laden
air from the cementitious weigh hoppers is filtered through bag filter and
vented to the dust collector. Cementitious transfer using fully enclosed
pipes and screw conveyors. |
Throughout the operation of
the concrete batching plant |
Plant Operator |
Ö |
|
Ö |
|
The
mixer is fully enclosed. Dust-laden
air in the mixer is filtered though bag filter and vented to the dust
collector. Mixer driven by electric motor. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
All
mixing & loading conduct in fully enclosed area. Truck loaded with concrete
in “Wet” form. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Well
maintained trucks. Clean
trucks regularly. Trucks comply with HKSAR
regulations. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Floor
to be concrete paved. Pavement to be kept moist
with water. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Perform
regular maintenance works for plant equipment. Maintain all environmental
control facilities in operating condition. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Remark: The Implementation Schedule as presented in EIA Report and EM&A
Manual on “Infrastructural Works for the Proposed Development at Telegraph Bay”
is still applicable to this Project.
Appendix C2 Implementation Schedule of
Mitigation Measures for Noise Control
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Use of quiet type equipment
including generator, excavator, mobile crane, truck and vibrator poker |
Throughout the construction
of the concrete batching plant |
Contractor |
|
Ö |
|
|
Fully enclose the conveyor
to unload the material to the aggregrate receiving hopper |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Fully enclose the concrete
mixer |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Mixer driven by electric
motor |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Conduct all mixing and
loading in fully enclosed area |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Well maintain all concrete
trucks |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
Perform regular maintenance
works for plant equipment |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
|
|
Ö |
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Remark: The
Implementation Schedule as presented in EIA Report and EM&A Manual on
“Infrastructural Works for the Proposed Development at Telegraph Bay” is still
applicable to this Project.
Appendix C3 Implementation Schedule of
Mitigation Measures for Water Pollution Control
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Works should be programmed
to avoid the rainy season whenever possible to minimise storm runoff. If work
during rainy season cannot be avoided, precautions should be taken to prevent
soil erosion. |
Throughout the construction
of concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Channel or earth bunds
should be constructed to direct the runoff to sand/silt removal facilities. |
Throughout the construction
of concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Perimeter channels should
be constructed to stop the storm runoff from washing across the site |
Throughout the construction
of concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Sand/silt removal
facilities should be checked and cleaned regularly to ensure these facilities
are working in good condition. |
Throughout the construction
of concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Exposed soil surface should
be paved to reduce the potential soil erosion. |
Throughout the construction
of concrete batching plant |
Plant
Operator |
|
Ö |
|
|
Stockpiles of construction
materials on site should be covered with tarpaulins or similar fabric to
prevent surface erosion. Minimisation of stockpiling in the wet season will
reduce the chance of silt laden surface runoff from entering the ocean |
Throughout the construction
of concrete batching plant |
Plant
Operator |
|
Ö |
|
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Remark: The
Implementation Schedule as presented in EIA Report and EM&A Manual on
“Infrastructural Works for the Proposed Development at Telegraph Bay” is still
applicable to this Project.
Appendix C4 Implementation Schedule of
Mitigation Measures for Waste Management
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Install a concrete
recycling machine to reduce material consumption and waste generation. |
Throughout the operation of
concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
Maintenance of records of
quantities of wastes generated, recycled and disposed, including disposal
location |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Where practicable,
different types of wastes should be segregated, stockpiled and stored in
different containers or skips to enhance reuse or recycling of materials and
their proper disposal |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Good site management,
planning and design considerations to reduce over-ordering and waste
generation |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Educate workers on the
concepts of site cleanliness and appropriate waste management procedures |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Minimise land-take by
reducing the size of the stockpiles and associated working areas |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Provide fencing to separate
sensitive habits and landscape areas to prevent accidental stockpiling in
these areas |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Designate appropriate
haulage routes |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Keep material covered in
heavy rainfall |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Keep movement of stockpiled
material to a minimum |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Optimise reuse of suitable
material on site to reduce the volume of materials to be disposed to public
filling areas |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Use appropriate dust
suppression by use of appropriate bunding, interceptors and direction of
run-off into settlement ponds |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
For wastes with <20% of
non-inert materials, should be segregated and disposed of to public filling
area |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Waste collection by an
approved licensed waste collectors |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
All necessary waste
disposal permits should be obtained |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Store appropriately and
isolate from current working areas |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Secure storage area should be
set up for chemical waste storage (refer to ‘Practice on the Package,
Labelling and Storage of Chemical Wastes’) |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Remark: The
Implementation Schedule as presented in EIA Report and EM&A Manual on
“Infrastructural Works for the Proposed Development at Telegraph Bay” is still
applicable to this Project.
Appendix C4 (Cont’d)
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Erect appropriate fence and
signs beside the chemical waste storage area |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Minimise waste production
and careful handling of waste fuel and oil
residues |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Supply spill absorbent
material and emulsifiers on is in case of spillages |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Store wastes remote from
sensitive receivers |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Wastes should be stored in
black refuse bags prior to collection and disposal |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Frequent collection of
general refuse |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Regular maintenance and
cleaning of the waste storage areas |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
Sewage generated on the
site should be controlled through the use of chemical toilets or sewage
holding tanks. Either would require regular cleaning with the resulting
sewage disposed of appropriately |
Throughout the construction
and operation of concrete batching
plant |
Plant
Operator |
|
Ö |
Ö |
|
Storage of a material in
suitable containers |
Throughout the construction
and operation of concrete batching plant |
Plant
Operator |
|
Ö |
Ö |
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Remark: The
Implementation Schedule as presented in EIA Report and EM&A Manual on
“Infrastructural Works for the Proposed Development at Telegraph Bay” is still
applicable to this Project.
Appendix C5 Implementation Schedule of
Mitigation Measures for Visual Impacts
Environmental
Protection Measures |
Timing |
Implementation
Agent |
Implementation
Stages * |
|||
|
|
|
Des |
C |
O |
Dec |
Concrete batching plant shall be painted in
a suitable colour to increase the visual compatibility. |
Throughout the operation of
the concrete batching plant |
Plant
Operator |
Ö |
|
Ö |
|
* Des = design, C = construction, O = operation, Dec = decommissioning
Remark: The
Implementation Schedule as presented in EIA Report and EM&A Manual on
“Infrastructural Works for the Proposed Development at Telegraph Bay” is still
applicable to this Project.