1.
Introduction
1.1
Background
1.1.1
MTR Corporation Limited (MTRCL) proposes
to modify the existing MTRC Tsim Sha Tsui (TST) Station in the form of a
southward extension, and provision of an associated pedestrian subway along
Nathan Road.
1.1.2
The need to modify the existing MTRC
TST Station was identified as a result of the planned construction of the new
KCRC East Tsim Sha Tsui (ETS) Station and associated pedestrian subways. The subway system is intended to facilitate
interchange between the MTRC TST Station and KCRC ETS Station. A pedestrian subway will be constructed under
Mody Road to connect ETS Station to TST Station. The implementation of this “Mody Road Link” will displace a
significant area of the existing TST station currently occupied by plant rooms
and Back of House accommodation. The extra passenger flows in TST resulting
from the interchange will also result in increased demand on public area and
space for larger plant rooms and station accommodation.
1.1.3
The southern extension was identified
to be the best solution for accommodating the displaced plant rooms and Back of
House accommodation. It was identified
through a passenger forecast study and station planning study that the
provision of a direct pedestrian link from the TST southern extension to the
planned KCRC pedestrian subway at Middle Road would give improved passenger
flows between the two stations.
1.1.4
CH2M HILL (China) Limited has been
commissioned by MTRCL to carry out an Environmental Impact Assessment (EIA) for
the proposed modifications to MTR TST Station.
The EIA Team is independent from MTRCL’s Engineering Design Consultants,
with MTRCL’s Environmental Manager providing the necessary interface between
them to ensure that appropriate designs and construction method taking into
full account the potential environmental impact and sufficient mitigation
measures are properly identified for inclusion into the construction
documentation.
1.2
EIA Requirement
1.2.1
In accordance with A.2 under Part I,
Schedule 2 of the EIA Ordinance, the construction of a railway and its associated
stations is classified as a designated project. However, the proposed project is regarded as modification works
and does not fall within such category (i.e. exempted project). Instead, the
proposed modification works at TST Station was identified as “material change”
to the exempted project under Section 9(4) of the EIA Ordinance (EIAO).
1.2.2
“Material Change” is defined as a
physical addition or alteration to a designated project, which results in an
adverse environmental impact as defined in the technical memorandum (EIAO-TM)
under the EIAO. As a general rule,
changes under the following circumstances are regarded as material changes to a
designated project as stated in the EIAO-TM:
i)
a
change to physical alignment, layout or design of the project causing an
environmental impact likely to affect existing or planned community,
ecologically important areas or sites of cultural heritage;
ii)
a
physical change resulting in an increase in the extent of reclamation or
dredging affecting water flow or quality likely to affect ecologically
important areas, or disrupting sites of cultural heritage;
iii)
an
increase in pollution emissions or discharges or waste generation likely to
violate guidelines or criteria in the technical memorandum without mitigation
measures in place;
iv)
an
increase in throughput or scale of the project leading to physical additions or
alterations that are likely to violate the guidelines or criteria in this
technical memorandum without mitigation measures in place; or
v)
a
change resulting in physical works that are likely to affect a rare, endangered
or protected species, or an important ecological habitat, or a site of cultural
heritage.
1.2.3
MTRCL submitted a Project Profile to
Director of Environmental Protection (DEP) on 13 November 2000 to apply for an
EIA Study Brief for the carrying of an EIA study for the proposed
modification. DEP issued a Study Brief
(No. ESB-063/2000) after public inspection of the Project Profile. This EIA Report was prepared in accordance
with detailed requirements as stated in the EIA Study Brief. An Environmental
Permit for the construction and operation of the project will only be issued
after the approval of the EIA report by DEP.
The EIA Study Brief is presented in Appendix I.
1.2.4
Potential construction phase impact
arising from dust and noise emission and construction waste management was
identified to be key environmental issues under the EIA Study Brief. The extent of the impact, though transient,
has been identified through the EIA study and sufficient environmental
mitigation measures identified to alleviate the impact to acceptable levels.
1.2.5
Figure 1-1 shows the location of the
project and the boundary of the study area for construction dust and noise
impact assessment.
1.3
Objectives of the EIA Study
1.3.1
As stated in Clause 1.4 of the EIA
Study Brief, this EIA aims to provide information on the nature and extent of
environmental impacts arising from the construction of the MTRC TST Station
Southern Extension and related activities that take place concurrently. This
EIA report will exemplify such information and will contribute to decision by
the Director of Environmental Protection on:
i)
the
overall acceptability of any adverse environmental consequences that are likely
to arise as a result of the Project;
ii)
the
conditions and requirements for the detailed design, and the construction of
the Project to mitigate against adverse environmental consequences wherever
practicable; and
iii)
the
acceptability of residual impacts after the implementation of the proposed
mitigation measures.
1.3.2
Clause 2.1 of the EIA Study Brief sets
out the specific objectives of the EIA Study.
These include:
i)
to
describe the Project and associated works together with the requirements for
carrying out the Project;
ii)
to
identify and describe elements of community and environment likely to be
affected by the Project and/or likely to cause adverse impacts to the Project,
including natural and man-made environment;
iii)
to
identify and quantify emission sources and determine the significance of
impacts on sensitive receivers and potential affected uses;
iv)
to
propose the provision of mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction of the Project;
v)
to identify,
predict and evaluate the residual environmental impacts (i.e. after practicable
mitigation) and the cumulative effects expected to arise during the
construction phase of the Project in relation to the sensitive receivers and
potential affected uses;
vi)
to
identify, assess and specify methods, measures and standards, to be included in
the Project which are necessary to mitigate these environmental impacts and
reducing them to acceptable levels;
vii)
to
investigate the extent of the secondary environmental impacts that may arise
from the proposed mitigation measures and to identify constraints associated
with the mitigation measures recommended in the EIA study, as well as the
provision of any necessary modification; and
viii)
to
design and specify environmental monitoring and audit requirements to ensure
the effective implementation of the recommended environmental protection and
pollution control measures.
1.4
Use of Relevant Studies
1.4.1
The following previously approved EIA
studies have been reviewed and made reference to in the EIA study:
i)
Environmental
Impact Assessment, East Rail Extension – Hung Hom to Tsim Sha Tsui,
Kowloon-Canton Railway Corporation (Feb., 2000) (EIAO Register No.
AEIAR-033/2000) (referred to as ETS-EIA Report in later sections of this
report); and
ii)
Environmental
Impact Assessment for Salisbury Road Underpass and Associated Road Improvement
Works including Middle Road Circulation System (Apr., 1999) (EIAO Register No.:
AEIAR-013/1999) (referred to as Salisbury Underpass EIA in later sections of
this report)
1.5
Structure of the EIA Report
1.5.1
The structure of this EIA Report is as
follows:
Section 1 : Introduction;
Section 2 : Project Description;
Section 3 : Construction Noise Impact Assessment;
Section 4 : Construction Dust Impact Assessment;
Section 5 : Waste Management;
Section 6 : Other Environmental Factors;
Section 7 : Summary of Environmental Outcomes;
Section 8 : Overall Conclusion.
1.5.2
Figures are presented at the end of
each section.
2.
Project Description
2.1
Identification of Project Need
2.1.1
KCRC has planned to build an extension
of East Rail from the existing Hung Hom Station to a new terminal at East Tsim
Sha Tsui. The new East Tsim Sha Tsui
(ETS) Station is located below the Middle Road Children’s Playground. Associated with the station construction
works is the plan to build a pedestrian subway from ETS via Blenheim Avenue and
Mody Road to MTRC TST Station (refer hereafter as the “Mody Road Link”). Figure 2-1 shows the subway arrangement plan
of KCRC “Mody Road Link” as presented in the ETS-EIA Report.
2.1.2
Implementation of the Mody Road Link
will require the relocation of the existing plant rooms and station
accommodation located underneath the Nathan Road – Mody Road junction. Figure 2-2 highlights the possible extent of
the affected existing facilities at MTRC TST Station.
2.1.3
Increased pedestrian flows as a result
of the proposed interchange will also result in increased demand on public area
within the station for passenger circulation, and additional space for station
accommodation and larger plant rooms to cater for increased demand for
electricity and other utilities.
2.1.4
The effect on passenger flows
associated with the implementation of the KCRC ETS Station including the Mody
Road Link was studied in details by MTRCL’s Traffic Consultant in a pedestrian
forecast study. It was identified that
due to the physical constraints associated with Mody Road subway width which is
limited to 4.5m only, even if the Mody Road subway is controlled for one-way
flows from ETS to TST only in the A.M. peak, under the worst-case situation, in
the order of 10,000 persons per hour passengers who want to interchange between
the two stations in the A.M. peak will be forced to find a route at street
level. The most likely route is predicted
to be along Nathan Road between the existing MTR Entrance E and the future KCRC
Middle Road Entrance. The need and
long-term benefits of providing a subway under Nathan Road (hereafter referred
to as the “Nathan Road Link”) to link the existing MTRC TST Station concourse
with the KCR Middle Road Link was identified.
2.1.5
In the absence of the project (i.e.
the do-nothing scenario), there will be no room to cater for the relocated
plant rooms and station accommodation.
Moreover, interchange between the KCRC ETS Station and MTRC TST Station
will rely on Mody Road Link only, which is predicted to be insufficient to
cater for peak passenger flows. As a
result, passengers would be forced to find a route at street level, which is
environmentally unfavourable. Furthermore, it is not certain that the KCRC ETS Station could be
operated safely without the completion of this interchange.
2.2
Alternative Design Options
Consideration
Key Objectives
2.2.1
As described above, the two prime
objectives to be achieved in the planning of the TST Station Modifications
include:
i)
To
provide a direct pedestrian subway link between the TST station and ETS
Station;
ii)
To
accommodate the plant rooms and back-of-house accommodation displaced by the
Mody Road Link.
2.2.2
While there may be different
alternative options for accommodating the displaced plant rooms and
back-of-house accommodation, the selection on the preferred alignment of the
concourse extension shall take into account the resultant effect on the length
and alignment of the associated pedestrian subway for linking the TST Station
and ETS Station. The key objective is
to minimise the walking distance as far as practicable. Obviously, if the
alignment of the pedestrian subway is not attractive to the passengers, the
purpose of building it will be defeated.
2.2.3
The consideration of alternative
alignment design options and selection of the preferred design – an
approximately 80m southern concourse extension and an associated 30m long
Nathan Road subway link have been arrived at taking into full account the above
two objectives.
Pedestrian Subway Link Design
2.2.4
In identifying the preferred alignment
of the pedestrian subway, the design objective is to provide the most
convenient routing for the predicted passenger movements.
2.2.5
From the passenger forecast study, the
proposed “Nathan Road Link” was also identified to be the most direct and
convenient alignment of the subway to serve the public especially during the
A.M. peak as an alternative route to the Mody Road Link. It was predicted to be
especially attractive to the passengers using the front half of KCR trains.
2.2.6
By referring to Figure 2-1, the
proposed Nathan Road Link can be viewed as one that would complete a critical
“missing” length of the subway network between the TST station and ETS station
in future, which will function to:
§
Enhance
and enlarge the walking catchment areas of both stations and provide more
flexible route choice between the stations and the surrounding areas;
§
Provide
direct and convenient interchange routes between the various parts of the two
stations; and
§
Improve
accessibility generally, by enhancing the convenience, capacity and environment
of pedestrian facilities in the Tsim Sha Tsui area;
§
Minimise
the time and opportunities of passengers being in direct exposure to vehicular
emissions when walking along Nathan Road at street level
2.2.7
The proposed underground pedestrian
subway along Nathan Road extending to Middle Road is identified to be the most
direct connection to the Middle Road Link, especially when its design is
considered in association with the proposed southern concourse extension. Provision of an approximately 80m long TST
Station southward extension as currently planned will reduce the length of the
pedestrian subway along Nathan Road to about 30m only.
2.2.8
No other routing has been identified
that could provide a similar direct connection as the proposed Nathan Road Link
to facilitate passenger interchange between the TST station and new ETS
Station. The Nathan Road Link is identified to be the preferred alignment from
the pedestrian forecast study. A sketch
showing a subway link from TST Station to KCR Middle Road Link via Peking Road,
Hankow Road (Peking Road Link) is presented in Appendix II to illustrate the
not preferred indirect link. The total
length of the subway is about 165m.
Provision of such subway would result in a long walking distance. The result is that this may not be the
mostly used route by the passengers as a more direct route is present above
ground.
Concourse Extension Design
2.2.9
Consideration on possible options on
the design of the concourse extension shall take into account its relationship
with the design of the pedestrian subway planned between MTR and KCR. The key would be to provide an integrated
design that can achieve the two main objectives. The possible options are also
constrained by the existing location of the station and the nearby
buildings.
2.2.10
In associated with the consideration
of providing the Peking Road Link discussed above, the option of re-providing
the station accommodation and plant rooms under Peking Road was reviewed and
confirmed not be a preferred option after taking into consideration various
factors. The key is that this option
will not have the benefits provided by the southern extension of significantly
reducing the length of the planned pedestrian subway:
·
The long narrow strip area allowed for the construction
of the station extensions will result in an inefficient design, where additional
area of substantial extent will be displaced as corridor beside the areas used
to accommodate the required plant rooms and station accommodation
·
The underground subway structure will need to be
extended to the west of nearly 150m from the existing station box assuming that
one level of the concourse extension is to be built. It is considered that the long narrow layout is far from a
satisfactory design from a station functioning and a safety point of view.
·
This option is also not preferred from an environmental
viewpoint due to the need to build an additional vent shaft at Peking Road, the
long length of the construction work areas on a narrow road with residential
developments located on both sides and extra amount of construction and
demolition material generated.
·
There will also be technical difficulties associated
with severe headroom restrictions at the interface with the existing TST
station (at Entrance E) and the relative inefficiency of running long lengths
of cable and duct.
2.2.11
Similarly, reprovisioning of the plant
rooms and station facilities under Haiphong Road, Humphrey Avenue or Carnavon
Road, etc. or developing a northern extension cannot produce an integrated
design to facilitate the development of a short, direct and effective subway link
to facilitate passenger interchanges between the TST Station and ETS
Station. Besides, a number of capacity
enhancement measures have already been proposed for the TST station which
concentrate on the northern end of the station. These capacity enhancement works and station improvement works,
which have already been planned under the title of TST Essential Works, are
anticipated to include the provision of a new escalator and lift from platform
to concourse, new escalators between concourse and street level, a new Station
Control Room and related back of house facilities, new kiosks and new ceilings
at concourse and platform levels.
2.2.12
The alternative options for the
concourse extension are therefore not preferred when compared with the
integrated Southern Extension and Nathan Road subway link option in terms of
achieving the two prime objectives stated above.
Development of the selected Integrated Design
Option –Southern Concourse Extension and associated Nathan Road Link
2.2.13
Provision of a single floor southern
concourse extension and an associated Nathan Road Link directly connected with
the KCRC Middle Road Link was identified to be the preferred design/ alignment
option.
2.2.14
The basis for selecting the Southern
Extension and the environmental factors considered are summarised below:
§
the
extension of the station to the south will shorten the length of the direct
Nathan Road Link identified to be required in connection with the KCRC Middle
Road Link i.e. minimise walking distance between the two stations, minimize
extent of construction work area and limit the work area to the section of
Nathan Road that are mostly surrounded by hotels provided with central air
conditioning systems and do not rely on openable windows for ventilation;
§
the
option does not require construction of any additional vent shaft i.e. avoiding
the generation of additional noise impact on the nearby noise sensitive
receivers;
§
the
new plant rooms can be located conveniently relative to the existing plant
rooms i.e. minimize the impact on the passengers using the TST station during
the construction phase
2.2.15
Preliminary options on the design of
the Southern Extension and associated Nathan Road Link were developed by the
Engineering Design Consultants and discussed with the Government since August
2000. The preliminary design was
further developed into the “Preferred Option” following the basis design to
take into account the various site constraints. Detailed design of the Southern Concourse Extension and Nathan
Road Link is currently being considered by the Engineering Design Team in
parallel with the EIA study. Figure 2-3
presents the preferred option. Figure
2-4 and 2-5 illustrate the relationship of the Southern Concourse Extension and
Subway to the existing bored Tsuen Wan Line tunnels, respectively. Sufficient clearance has been incorporated
into the engineering design.
2.3
Evaluation on Alternative Construction Methods
2.3.1
Construction of this extension is
expected to be difficult, given the obvious need to minimise any effects on the
traffic, existing bored Tsuen Wan Line tunnels and the nearby building
structures. Bored tunnelling and
cut-and-cover method are the available techniques to select from.
2.3.2
Use of bored tunnelling, if
practicable, has the environmental benefit of avoiding the associated airborne
noise and dust impact on the nearby sensitive receivers when compared with the
cut-and-cover option. However, this
construction technique is not identified to be a technically feasible option
when a number of key site-specific engineering factors are taken into
account. The key engineering
constraints which led to the conclusion that application of bored tunnelling in
this project is not technically feasible are as follows:
§
The
use of bored tunnelling techniques normally requires a two-diameter cover to
achieve arching effect for safe bored tunnelling operations. The vertical limits on the alignment of the
extension is predetermined by the level of the existing TST station and limited
by the presence of the existing tunnels below as illustrated in Figure 2-4 and
Figure 2-5. The width of the extension
dose not suit bored tunnelling as there is insufficient cover to generate an
arching effect;
§
The
existing Tsuen Wan Line tunnel was constructed back in 1976 to 1980. The tunnel lining was formed partly of
bolted SGI segments and partly of precast concrete segment excavated in CDG and
back grouted. The tunnel linings are
able to accommodate only limited movements and distortions. It would be difficult to control and ensure
that the ground and tunnel movements can be kept within acceptable limits if
bored tunnelling technique is used;
§
Site
investigation data from previous studies revealed the general ground conditions
at the concourse extension. The general
stratigraphy involves fill, marine sand, alluvium, CDG down to some 12m below
ground as expected for areas near the seawall.
Bored tunnelling technique normally requires a continuous ground
condition for an infinite distance. The
vary stratigraphy would create difficulty in bored tunnelling design
2.3.3
The use of cut-and-cover method,
however, is not constrained by the above key engineering factors and other site
factors, given its simplistic nature which can accommodate the geotechnical
requirements and clearance requirements (from the existing tunnels and nearby
building foundation).
2.3.4
Besides, the potential dis-benefits
associated with the use of cut-and-cover technique in terms of dust and
airborne noise emission can be mitigated through undertaking the bulk excavation
activities under a road deck, phasing and sequence of construction activities
associated with the site clearance and temporary deck construction, as well as
implementation of sufficient dust and noise mitigation measures during the
execution of the construction activities.
2.4
Proposed Construction Programme and Sequence
2.4.1
The preliminary construction programme
and sequence has been considered with target to minimise the impact from the
construction works on the environment and traffic as a high project objective.
2.4.2
A preliminary construction programme
is presented in Figure 2-6. Site
clearance is assumed to commence in early 2002 for completion in 2004. This programme anticipated that the
temporary decking would be constructed in 15 stages for the completion of the
full road deck in early 2003. Nathan
Road will be reinstated to its original condition near mid 2004 after
excavation works and the construction of the extended station box.
2.4.3
It is expected that the construction
works will commence with removal of the existing median strip. The existing concrete road pavement will be
demolished in stages on a lane-by-lane basis such that impact on the traffic
movement can be minimised. Locations of
the existing utilities lying under Nathan Road have been taken account of as
far as practicable in the design of the preferred layout plan. The objectives are to maximise the
opportunities for the existing utilities to be hung above the underground
excavation area, if possible, instead of having to be diverted such that the
construction period and the associated environmental impact on the nearby
sensitive receivers can be minimised.
It is expected that the area requiring significant utility diversion
will be the footpath on the east side of Nathan Road.
2.4.4
Temporary piles will be installed at
required locations in stages across the full width and length of Nathan Road
within the project site area to support the temporary road deck and for control
of settlements during excavation.
Sufficient dust and noise mitigation measures will be implemented
through the construction period to control the potential environmental impact
to acceptable levels, including the provision of noise barriers and machinery
enclosures as detailed in Section 3.
The completed road deck will be flush with the existing road surface to
carry Nathan Road traffic while underground excavation works are carried
out.
2.4.5
Excavation will be carried out beneath
the deck proceeding layer by layer with regular monitoring of tunnel
integrity. Excavated materials will be
removed by gantry and hoist to trucks parked within the proposed noise
enclosure at the opening near the middle strip of Nathan Road (please refer to
Section 3 and Error! Reference source not found.). It is envisaged that the roof and base slabs
of the concourse extension would be constructed using a Bottom-up construction
method, involving the installation of pipe piles for supporting the road deck.
2.4.6
The bottom-up construction method is
evaluated at this planning stage to be more preferable than the top-up
approach. Pipe pile wall method adopted
in bottom-up construction can be installed with relatively compact machinery
which is more suitable for the project, given the narrow works area involved
and the headroom restrictions. The use
of smaller diameter, cased, and pre-drilled temporary works in pipe pile wall
method also help to avoid potential impact on the existing rail tunnel. Use of top-down construction could be
difficult given the extensive corestones and buried structure in the area. The working area for excavation would also
be confined one the roof slab is cast in top-down construction approach,
resulting in much longer period of confined working environment which is not preferable
from a safety point-of-view. Adopting
the top-down construction method, nevertheless, will involve similar
construction sequence with respect the site clearance and installation of the
temporary road deck with the potential dust and noise impact mitigated by
similar control techniques.
2.4.7
The temporary road deck will be
removed after the completion of the underground works and the road and
utilities reinstated using, again, a lane-by-lane approach in order again to
keep traffic movement on Nathan Road.
Sufficient noise mitigation measures will also be provided including use
of noise barriers and machinery enclosures.
2.4.8
Construction of the TST Station
southern extension is desired to commence in late 2001 – early 2002.
2.5
Major Elements of the Surrounding
Environment
2.5.1
Situated
in the vicinity of the work area are mostly hotels that are provided with
central air conditioning and do not rely on openable windows for
ventilation. These include, on the
western side, Peninsula Hotel, Kowloon Hotel and Hyatt Regency Hong Kong Hotel
and, on the eastern side, Sheraton Hotel, Imperial Hotel, and Holiday Inn
Hotel. Commercial buildings situated in
the vicinity of the work area include Prestige Tower, Alpha House and Oterprise
Square. Chung King Mansions situated to
the east of the work area is mostly occupied by commercial uses and hostels
equipped with window-type air conditioners.
At ground level, there are shops along both sides of Nathan Road. In the
following assessments, sensitive uses among these major elements have been
taken account of in the study.
2.5.2
Figure
2-7 presents an extract of the Tsim Sha Tsui Outline Zoning Plan (No. S/K1/12)
near the work area. All landuses in the
vicinity of the work area are zoned as “Commercial”.
3.
Construction Noise Impact Assessment
3.1
Introduction
3.1.1
In this chapter, noise impact as
generated during construction phase was evaluated. Relevant criteria for
construction noise impact assessment were made referenced to. Details of construction
activities and the possible noise impact arising from the use of Powered
Mechanical Equipment (PME) were evaluated. Representative noise sensitive
receivers (NSRs) were identified in the vicinity of the construction site. The
degree of noise impact was predicted based on consideration of basic acoustic
principles. Effective mitigation measures were recommended if necessary in
order to attenuate noise impact to acceptable levels. The study area covers an area within 300m from the construction worksite.
3.2
Assessment Methodology
3.2.1
The approach used in the assessment of
noise from construction works other than percussive piling is based on standard
acoustic principles, and the guidelines given in Para. 5.3 and 5.4 of Annex 13 of
the “Technical Memorandum on Environmental Impact Assessment Process” (TM).
3.2.2
Noise impact derived from the
construction activities has been predicted based on the following procedures:
(a)
Identify
from the preliminary construction programme presented in Figure 2-5 the key
construction phases involved that may generate a construction noise problem;
(b)
Identify
an inventory on type and quantity of Powered Mechanical Equipment (PME) that
would be required to achieve the works based on the time allowed under the programme;
(c)
Identify
from “Technical Memorandum on Noise From Construction Works other than
Percussive Piling” (TM1) the Sound Power Level (SWL) of each PME used in the
construction works;
(d)
Refer
to BS5228, “Noise and vibration control on construction and open sites – Part
1. Code of practice for basic information and procedures for noise and
vibration control” if the SWL of individual equipment cannot be found in TM1;
(e)
Select
representative NSRs in the vicinity of for the construction noise impact
assessment as Representative Assessment Point (RAP);
(f)
Identify
the notional source position for each RAP in accordance with the procedures as
described in TM1;
(g)
Calculate
the Predicted Noise Level (PNL) based on distance attenuation from notional
source positions to the representative RAPs;
(h)
With
consideration of the effect of facade reflection at the RAPs, predict the
Corrected Noise Level (CNL);
(i)
Based
on a comparison of the CNL with the noise assessment criteria, identify the
required noise mitigation measures and predict the mitigated noise levels.
3.3
Legislation and Assessment Criteria
3.3.1
Construction noise is controlled under
the Noise Control Ordinance (NCO)
which prohibits the use of powered mechanical equipment (PME) during the
restricted hours (7 p.m. to 7 a.m. on normal weekdays and any time on a public
holiday, including Sunday) without a valid Construction Noise Permit (CNP)
granted by the Authority. The criteria
and procedures for issuing such a permit are specified in TM1.
3.3.2
For construction works other than
percussive piling, although TM1 do not provide control over daytime
construction activities, noise assessment criteria are set out in Table 1B of
Annex 5 of the EIAO-TM. For hotels and
hostels which are the key NSRs in this study, the applicable noise assessment
criteria is Leq(30min.) 75dB(A) for construction works during the
non-restricted hours (i.e. 0700 to 1900 hours on any day not being a Sunday or
general holiday).
3.3.3
In the assessment, practicable direct
noise mitigation measures have been identified and recommended to achieve the
noise criteria as far as practicable.
Provision of indirect technical remedies in the form of noise insulation
and air conditioning was regarded as last resort solution only upon exhaust of
all practicable mitigation measures in the assessment.
3.4
Proposed Construction Sequence
3.4.1
The key construction activities are
expected to include the following and in the sequence as described. It can be noted that in order to minimise
the potential environmental (noise) and traffic impact, the construction work
area will be limited and with significant phasing and sequencing of
construction activities build into the programme.
Site Preparation:
·
Demolish
existing median strip;
·
Divert
and narrow existing footpath and one traffic lane on east side of Nathan Road;
·
Divert
utilities to create sufficient space for temporary wall installation;
Demolition of Road Pavement and
Temporary Road Decking
·
Demolish
existing concrete road pavement;
·
Install
temporary works (cofferdam, piling and road decking) for carrying out of
underground excavation activities subsequently;
·
Extend
traffic deck for a second lane;
·
Proceed
lane-by-lane across Nathan Road to divert utilities and construct concourse
extension walls and traffic deck;
·
Reinstate
Nathan Road traffic by the road deck and reserve sufficient area as
construction site and for the opening leading to the underground work area;
Underground Works
·
Construct
a noise enclosure to cover the opening planned near the middle strip of Nathan
Road;
·
Excavate
beneath the road deck and proceed layer by layer with regular monitoring of
tunnel integrity and potential deformations. Ground treatment and controlled
dewatering will proceed in parallel with excavation in order to balance loads
on existing MTR running tunnels.
Excavated material to be removed by gantry and hoist to trucks parked
within the noise enclosure;
·
Grouting
below excavation level to stabilize existing running tunnels if required;
·
Construct
roof and base slab of the concourse extension. Bottom up construction is
currently planned to be used;
Backfilling and Reinstatement
·
Remove
deck, backfill and reinstate utilities and road pavement using again a
lane-by-lane progressive approach.
Works within the Completed Structure
·
Breakthrough
existing station end wall;
·
E&M
fitout and relocation of plant;
·
Demolish
and make good existing areas in existing station;
·
Architectural
fitout to new station accommodation and existing areas of plantrooms.
3.5
Noise Sources
3.5.1
Based on the sequence on construction
activities involved as described above, the key construction activities and PME
anticipated to be involved were identified through liaison with the MTRCL’s
Engineering Design Consultant and are presented in Table 3‑1. The plant
inventory and utilisation rate adopted in the assessment are considered
practicable in achieving the preliminary construction programme taking into
account the phased lane-by-lane construction programme.
3.5.2
While it is expected that the future
appointed Contractor may propose a different PME inventory, the carrying out a
representative quantitative assessment at this planning stage will allow the
potential noise problem be realised and that practicable and sufficient noise mitigation
measures are derived and planned at an early stage. The Contractor will be required by MTRCL through specific
contract specification to provide and implement sufficient direct noise
mitigation measures based on the recommendation in this EIA to achieve
acceptable noise levels on the nearby NSRs.
Table 3‑1 Preliminary List on
Construction Activities and Equipment Inventory
Phase ID
|
Construction Activities
|
No. of Equipment
|
Percentage of Utilisation
|
Equipment
|
1
|
Site
establishment phase
|
4
|
80%
|
Concrete breakers
(20kg hammer)
|
|
|
2
|
100%
|
Compressors
|
|
|
1
|
10%
|
Lorry
|
|
|
1
|
50%
|
Mini excavator
|
|
|
|
|
|
2
|
Traffic deck piling
|
1
|
60%
|
500mm dia. piling
auger
|
|
|
1
|
100%
|
Compressors
|
|
|
2
|
100%
|
Water pumps
|
|
|
1
|
20%
|
Concrete lorry
|
|
|
|
|
|
3
|
Road demolition
|
2
|
80%
|
Concrete breakers
(20kg hammer)
|
|
|
1
|
50%
|
Mini excavator
|
|
|
1
|
20%
|
Lorry
|
|
|
1
|
100%
|
Compressor
|
|
|
|
|
|
4
|
Underground
excavation works
|
2
|
100%
|
Vent fans
|
|
|
1
|
100%
|
Compressors (1200
cfm)
|
|
|
1
|
100%
|
Water pump with
hydrocyclone
|
|
|
2
|
80%
|
Mini excavators
|
|
|
2
|
80%
|
Concrete breakers
|
|
|
1
|
50%
|
Gantry crane
|
|
|
|
|
|
5
|
Underground
concrete works
|
1
|
100%
|
Concrete pump
|
|
|
2
|
100%
|
Vent fans
|
|
|
2
|
100%
|
Vibrating pokers
|
3.6
Representative Assessment Points
3.6.1
Existing noise sensitive receivers
situated within the study area, which are noise sensitive uses that rely on
opened windows for ventilation, have been identified. Representative Assessment Points (RAPs) were selected and
presented in Table 3‑2 and Figure 3-1.
Noise levels were predicted at the lowest, worst affected noise
sensitive floors at the selected RAPs for the unmitigated and mitigated
scenarios.
Table 3‑2 RAPs selected for the
Construction Noise Impact Assessment
RAP
|
Name of Building
|
Noise Sensitive Use
|
N1
|
Chungking
Mansions
|
Hostels
|
N2
|
Mirador Mansion
|
Residential
|
N3
|
Harilela
Mansion
|
Residential
|
N4
|
Wing Lok
House
|
Residential
|
N5
|
Mohan’s
Building
|
Residential
|
3.7
Assessment Results
3.7.1
Table
3‑3 presents the unmitigated noise levels predicted at
the RAPs for each of the 5 construction phases. Those predicted noise levels exceeding the noise criteria are
shown in bold. Worksheets showing the calculation are provided in Appendix II
for reference. The worksheets also
cover an assessment of potential noise impact from the road reinstatement at
the conclusion of the civil works.
3.7.2
Noise shielding effect due to the road
decking structure in construction group 4 – underground excavation works has
been accounted for. It was assumed that
once the traffic deck is built, noise associated with construction activities
carried out beneath the deck will be greatly attenuated. The road decking shall have a sufficient
thickness (at least 25mm) to be noise insulating and shall not be allowed to
have noise leaks such as any sizeable openings. The deck shall be able to achieve a transmission noise of at
least 15dB(A) for underground construction activities carried out under the
deck.
3.7.3
Results of the calculation revealed
that in the absence of additional mitigation, N1 and N2 situated in the
vicinity of the site would be affected by the construction noise impact under
the worst-case scenarios. Cumulative
noise impact as high as 85dB(A) could occur at the worst affected NSR N1.
3.7.4
It must be pointed out that the
assessment results only represent the worst-case scenarios when all equipment
involved in each construction phase are assumed to be in concurrent operation
within a 30 minute period. In reality,
this worst-case scenario is expected to be rare. Yet, results obtained have shown exceedance in the daytime noise
criteria under the worst-case scenario mainly at N1. Implementation of sufficient noise mitigation measures especially
when construction works are carried out near N1 is necessary to alleviate the
noise impact to acceptable levels.
Table 3‑3 Unmitigated Construction
Noise Levels predicted at the RAPs
|
Predicted Noise Levels in Different Phases, Leq(30min.)
dB(A)
|
NSR
|
Phase 1
|
Phase 2
|
Phase 3
|
Phase 4
|
Phase 5
|
N1
|
85
|
83
|
84
|
84
|
83
|
N2
|
74
|
73
|
73
|
73
|
72
|
N3
|
70
|
68
|
68
|
69
|
68
|
N4
|
73
|
71
|
71
|
72
|
71
|
N5
|
71
|
69
|
69
|
70
|
69
|
*Bold
and shaded cell denotes exceedance
3.8
Recommended Construction Noise
Mitigation Measures
3.8.1
In addition to phasing and sequencing
of construction activities for the site clearance and temporary road deck
construction, as well as keeping the PME to be used concurrently in each phase
to a minimum which have been seriously considered and built into the
construction programme, noise generation from the construction activities can
be further minimised, where necessary, by adopting a number of noise mitigation
measures as far as practicable, including:
à
Use of
quiet PME with lower Sound Power Level;
à
Erect
temporary noise barriers and machinery enclosure;
à
Provide
Noise Enclosure at the Traffic Deck Opening retained as entrance to the
underground work area and for exporting of excavated material;
à
Implement
good site practice and noise management;
3.8.2
A mitigation package has been
developed progressively from consideration of the noise reduction effect of
each of these mitigation measures.
Use of Silenced PME
3.8.3
Silenced types of equipment for use in
construction activities are available in Hong Kong. For each item of PME proposed for the construction works, the
corresponding SWL of quieter plant were identified from TM1 or BS5228 Part
I:1984 and are presented in Appendix II. Silencers are also recommended to be
used in fan ventilation system to attenuate noise generated during fan
operation to achieve a noise reduction of 15dB(A).
3.8.4
Table
3‑4 shows the mitigated noise levels when silenced PME
are in use at N1 where there is predicted noise exceedance under the
unmitigated scenario. The predicted
noise levels that still exceed the noise criteria are shown in bold for ease of
reference. Predicted noise levels at other NSRs (N2 to N5) are not shown as the
relevant assessment criteria are already met under the unmitigated scenario.
3.8.5
By adopting silenced type of PME, it
is identified that due to its close proximity to the worksite, N1 would
inevitably still be affected with the maximum noise level of 84dB(A) at the
worst affected floor, reaching a maximum noise level of 84dB(A) in Phase 1.
Table 3‑4 Construction Noise Levels Predicted at the
RAP N1 (with silenced PME & silencers)
|
Predicted Noise Levels in
Different Phases, Leq(30min.) dB(A)
|
NSR
|
Phase 1
|
Phase 2
|
Phase 3
|
Phase 4
|
Phase 5
|
N1
|
84
|
82
|
81
|
80
|
79
|
*Bold
and shaded cell denotes exceedance
Use of Temporary Noise Barriers & Machinery
Enclosures
3.8.6
The erection of noise barriers between
noise sources and NSRs represented by N1 will be effective in reducing the
noise impact. Temporary barriers of
sufficient height with skid footing and a cantilevered upper portion can be
erected within a short distance from stationary plants, and at practicable
distance from mobile plants operating over a small work area under a
well-defined route, to alleviate the potential construction noise impact.
3.8.7
The minimum effective height of the
noise barriers should be as such that no part of the noise sources associated
with the operation of the PME should be visible from the target NSRs to be
protected. The guidelines given in the Booklet entitled “A Practical Guide for the Reduction of Noise from Construction Works”
issued by EPD is recommended to be followed by the appointed contractor in the
design of the temporary acoustic barriers.
Barriers should have no openings or gaps, and preferably have a
superficial surface density of at least 10 kg/m2. The locations of the temporary noise
barriers shall be adjusted where and when necessary taking into consideration
the locations and type of PME involved and the NSRs intended to be protected.
3.8.8
Temporary noise barriers shall be
provided during the execution of construction phases 1 to 3 and during road
reinstatement to be carried out at the conclusion of the underground
works. To mitigate the noise impact
from the installation of piles in Phase 2, it is planned to erect a cantilever
noise barrier of sufficient height (approx. 7m subject to the exact height of
the auger). Such direct noise
mitigation measure has been successfully applied in previous MTRCL’s project - Contract 506B in Mei Foo during the
installation of pipe piles and were demonstrated by an Environmental Monitoring
and Audit programme to be effective in keeping the noise levels at the nearby
NSRs in the proximity to within Leq(30min.) 75dB(A). The barriers can be made movable to fit the
locations of the work areas. A
schematic sectional diagram for the barrier structure is provided in Error! Reference source not found.. In addition to temporary noise barriers,
certain types of PME such as compressors can be totally shielded by machine
enclosures provided with ventilation, giving a noise reduction of 10 dB(A) or more. It is expected that proper use of barriers
and machinery enclosures for PME can achieve a noise reduction of 10 dB(A) for
stationary sources and 5 dB(A) for mobile sources.
3.8.9
Table
3‑5 presents the further mitigated noise levels predicted
at N1 when temporary noise barriers of sufficient effective height and
machinery enclosures are used on-site.
3.8.10
Results of the calculation showed that
with the combined use of silenced PME, noise barriers and machinery enclosures,
construction noise levels at N1 can be mitigated to a maximum of 74dB(A) except
in Phase 4. where a maximum noise level of 80dB(A) is predicted. It is identified that the dominant noise
sources associated with the construction works in Phase 4 can be mitigated to
acceptable levels, as presented blow, when the opening retained for the road
deck is provided with acoustic enclosure.
Table 3‑5 Noise Levels predicted at
the RAP N1 (with Silenced PME + Temporary Noise Barriers + Machinery Enclosure)
|
Predicted Noise Levels in
Different Phases, Leq(30min.) dB(A)
|
NSR
|
Phase 1
|
Phase 2
|
Phase 3
|
Phase 4
|
Phase 5
|
N1
|
74
|
72
|
72
|
80
|
71
|
3.8.11
As shown in the calculations presented
in Appendix III, the use of silenced PME and provision of temporary noise
barriers and machinery enclosures during the road instatement will also control
the potential noise impact to acceptable levels.
Use of Noise Enclosure at the Traffic Deck
Opening
3.8.12
Due to the execution of underground
excavation works below the road deck, an opening will be retained at a fixed
location near the middle of Nathan Road for site access and exporting of
excavated material. The erection of a noise enclosure at the opening of the
traffic deck in Phase 4 will further reduce the noise impact from the relevant
PME. With the road deck and noise
enclosure, all noise generated from construction activities such as loading and
unloading of construction and demolition materials carried out will be
effectively shielded so that the noise impact on the nearby NSRs will be
further reduced to acceptable levels.
3.8.13
Table
3‑6 presents the further mitigated noise levels predicted
at N1 when noise enclosure is planned at the traffic deck opening is also
considered in the assessment. Worksheet showing the calculation at the RAPs is
provided in Appendix III for reference.
3.8.14
Results of the calculation presented
in Table 3-4 to Table 3-6 demonstrated that with the combined use of silenced
PME, noise barriers, machinery enclosures and deck opening noise enclosure,
residential noise impact at N1 can also be mitigated to acceptable levels as
other nearby NSRs.
Table 3‑6 Noise Levels predicted at
the RAP N1 (with Silenced PME + Temporary Noise Barriers + Machinery Enclosure
+ Noise Enclosure at Traffic Deck Opening)
|
Predicted Noise Levels in
Different Phases, Leq(30min.) dB(A)
|
NSR
|
Phase 1
|
Phase 2
|
Phase 3
|
Phase 4
|
Phase 5
|
N1
|
74
|
72
|
72
|
74
|
71
|
3.8.15
Use of the proposed noise barriers and
noise enclosure, as other construction site equipment and structures onsite,
should take into account the following standard requirements of Fire Services
Departments:
i)
A
minimum of 4.5m wide thoroughfare with not less than 4.5 headroom to be
maintained at all times for the free passage of fire appliances;
ii)
Normal
operation of nearby street fire hydrants shall not be impeded in that a minimum
all round clearance of 1.5m shall be maintained at each hydrant outlet and its
controlling ground valve;
iii)
Such
enclosure shall not cause obstruction to the movement of the aerial ladder
during rescue operation at adjacent buildings;
iv)
A
minimum width of 6.5m for the carriageways shall be provided at all times in
front of the major facades of the buildings along Nathan Road in order to
maintain adequate area and space for fire fighting and rescue operation; and
v)
The
total length of the construction area for a noise barrier or enclosure shall be
limited to not more than 20m, taking into account the plan that the noise
barrier and noise enclosure will not co-exist in the construction works.
3.8.16
The above requirements have been
evaluated with the Project Engineering Design Team. It is considered that these
requirements, which are common for construction activities of similar nature
with the erection of site structures and use of equipment in the territory, can
be satisfied without affecting the feasibility to erect the proposed noise
barriers and noise enclosure.
3.8.17
The detailed design of the noise
barriers and noise enclosure shall take into account the above FSD requirements
and other safety issues, while observing the required acoustic effectiveness of
the barriers/ enclosure to achieve the acceptable levels at the nearby
NSRs. To illustrate the importance of
appropriate barrier design and erection by the Contractor, a sensitivity test
based on assuming a noise reduction of 5dB(A) only for both stationary sources
and mobile sources when a vertical noise barrier of insufficient height is in
use is conducted and the findings are presented in a spreadsheet also given in
Appendix III for future reference.
3.8.18
Other practicable noise mitigation
measures in form of good site practices and noise management are also
recommended below to achieve the acceptable noise levels at the nearby NSRs.
Good Site Practices and Noise Management
3.8.19
Based on the findings of the assessment
presented above, it is demonstrated that the potential noise impact arising
from the construction of the Southern Concourse Extension together with the
pedestrian subway can be alleviated to acceptable levels when the noise
mitigation measures recommended above are in place. To be prudent in the construction noise management, the following
additional noise management measures and good site practices are recommended
for implementation:
à the Contractor shall comply with and
observe the Noise Control Ordinance (NCO) and its current subsidiary
regulations;
à before the commencement of any work,
the Contractor shall submit to the Engineer for approval the method of working,
equipment and sound-reducing measures intended to be used at the site;
à only well-maintained plants should
be operated on-site;
à plants should be serviced regularly
during the construction programme;
à machines that may be in intermittent
use should be shut down or throttled down to a minimum between work periods;
à silencer and mufflers on construction
equipment should be utilised and should be properly maintained during the
construction programme;
à noisy activities can be scheduled to
minimise exposure of nearby NSRs to high levels of construction noise. For example, noisy activities can be scheduled
for midday or at times coinciding with periods of high background noise (such
as during peak traffic hours);
à noisy equipment such as emergency
generators shall always be sited as far away as possible from noise sensitive
receivers;
à mobile plants should be sited as far
away from NSRs as possible; and
à material stockpiles and other
structures should be effectively utilised as noise barrier, where practicable.
3.9
Potential Cumulative Noise Impact
3.9.1
With reference to the approved EIA
report carried out for KCRC East Rail Extension – Hung Hom to Tsim Sha Tsui
(ETS-EIA), consideration has been given to evaluation of potential cumulative
construction noise impact. The NSRs
that could be subject to cumulative noise impact from construction activities
at separate worksites of two projects - “East Rail Extension Hung Hom to Tsim
Sha Tsui” and “Salisbury Road Underpass and Associated Road Improvement Works
including Middle Road Circulation System” were identified from the ETS-EIA
Report to include the representative assessment points N10 ETS-EIA
(Mirador Mansion) and N4 ETS-EIA (Far East Mansion) (Table 5.1 and
Figure 5-1 in ETS-EIA refers).
3.9.2
KCRC has advised that a firm programme
for construction activities at the western end of Mody Road for the Mody Road
Link is currently not available. In the
absence of such information, the worst-case scenario has been assessed in the
analysis of the possible cumulative noise impact on N1 (Chungking Mansions) and
N2 (Mirador Mansion) which are the NSRs located closest to the KCRC Mody Road
worksite and Middle Road worksite studied in the assessment. Since the noise level at N1 has not been
predicted in the ETS-EIA report, the maximum noise level of 79dB(A) predicted
at N4ETS-EIA Far East Mansion in ETS-EIA (Table 5.5b in ETS-EIA for
Far East Mansion), which will also be affected by the Middle Road Link
construction, has been made reference to and corrected for distance to predict
the corresponding noise level at N1.
3.9.3
Table
3‑7 below presents the assessment on potential cumulative
noise impact associated with the event of concurrent construction activities
associated with the TST Station modifications and KCRC Mody Road Link and
Middle Road Link construction. In
reality, it expected that the concurrent operation representing the worst-case
situation would be a rare event.
Table 3‑7 Evaluation of Potential Cumulative Noise Impact
NSR
|
Worst-case mitigated noise levels,
Leq(30min.) dB(A)
|
|
MTRC TST Station Modifications
|
KCRC East Rail Extension
|
Concurrent construction activities
|
N1
|
74 (Table 3-6 refers)(i)
|
61(iii)
|
74
|
N2
|
74 (Table 3-3 refers)(ii)
|
84
|
84(iv)
|
(i) Mitigated noise levels;
(ii) Worst-case unmitigated noise level;
(iii) Calculated noise level at N1 based on the
maximum noise level of 79dB(A) predicted at Far East Mansion (Table 5.5b in ETS-EIA for Far East
Mansion refers);
(iv) Indirect technical remedies in the form of
upgraded glazing and air-conditioners will be provided at Mirador Mansion at
Mody Road in accordance with the permit condition issued for East Rail
Extension – Hung Hom and Tsim Sha Tsui
3.9.4
The assessment results indicated that
due to the significant distance separation of N1 from Middle Road, the
potential cumulative construction noise impact is not a concern. On the other hand, the noise level predicted
at N2 due to the TST Station modifications is at least 10dB(A) below the noise
impact generated from the Mody Road Link constrution works. Therefore, the noise generated from the TST
Station modifications will not give any noticeable contribution to the overall
noise impact at N2 when the Mody Road Link construction works are taking place. Besides, with reference to the ETS-EIA
Report and the environmental permit issued for the KCRC Hung Hum to Tsim Sha
Tsui Extension, indirect technical remedies in the form of upgraded glazing and
air-conditioners will be provided for the protection of Mirador Mansion at Mody
Road.
3.10
Operational Phase Impact
3.10.1
The proposed TST Station southern
extension and pedestrian subway will operate underground. Provision of
additional vent shaft was not identified to be required. Operation of the project is not expected to
give rise to any unacceptable noise impact during the operational phase.
EM&A Requirements
3.10.2
In order to protect the nearby NSRs
from unacceptable construction noise impact, the implementation of the
recommended construction noise mitigation measures should be checked through by
a regular construction noise monitoring and audit programme. Details on the noise monitoring
requirements, methodology and action plans are described in the EM&A Manual
issued as a stand-alone document.
3.10.3
Since implementation of sufficient
direct noise mitigation measures will reduce the potential noise impact to
acceptable level, the carrying out of weekly monitoring of noise levels with
increase in monitoring frequency triggered by the action/ limit level is
considered sufficient to check the adequacy of direct noise mitigation measures
in place from time to time.
3.11
Conclusion
3.11.1
The potential impact of construction
noise has been conservatively predicted with assumptions of a typical construction
schedule and combinations of different powered mechanical equipment likely to
be in use. Whilst the contractor may
prefer to use different types and numbers of plant, the above assessment will
give information on the individual and combined SWLs of the PME that could be
used given the locations of the nearby existing NSRs such that the overall
noise levels at the NSRs will be within the daytime construction noise limits.
3.11.2
The assessment has predicted that the
unmitigated noise impact at the nearest NSRs could reach a maximum noise level
up to Leq(30min.) 85dB(A).
Sufficient practicable direct mitigation measures have been recommended,
in addition to the measures- including the phasing and sequencing of
construction activities and minimise the number of PME working together in each
phase- which have been built into the construction work method. These additional noise control measures
include the use of silenced PME, temporary noise barriers, machinery enclosure,
noise enclosure for the road deck opening, and good site practice as well as
noise management.
3.11.3
Quantitative assessments indicated
that the combined use of the recommended noise mitigation measures can
alleviate the construction noise impacts at all potentially affected NSRs to
levels satisfying the noise assessment criteria for daytime construction
activities.
3.11.4
Potential cumulative noise impact
arising from possible concurrent activities for the TST Station modifications
and the East Rail Extension – Hung Hom to Tsim Sha Tsui (Mody Road Link and
Middle Road Link) has been assessed.
The noise assessment results revealed that potential cumulative noise
impact is not a concern.
3.11.5
Construction activities during the
restricted hours are under statutory control and would require a valid
construction noise permit issued by the Authority before construction works, if
needed, can take place within the restricted hours.
3.11.6
The contractor shall be, from time to
time, aware of the noise impact on the surrounding NSRs through active liaison
with the Environmental Team who shall undertake regular noise monitoring weekly
during the whole course of the project when civil works are carried out so that
adjustments could be made in modifying or increasing the level of direct noise
mitigation measures. The proposed
mitigation measures will have an effect to mitigate any unacceptable noise
impact once these measures are properly provided and maintained. These
monitoring requirements shall be triggered by an Event Contingency Plan (ECP)
as part of the EM&A which should be incorporated into the works contract so
as to make it enforceable.
3.11.7
Implementation of the construction
noise mitigation measures, procedures and protocols as recommended shall be
ensured through incorporation into the works contract to ensure their enforceability. The carrying out of weekly monitoring of the
noise levels, with increase in monitoring frequency triggered by the action/
limit level, is considered sufficient to check the implementation and adequacy
of direct noise mitigation measures in place from time to time.
4.
Construction Dust Impact Assessment
4.1
Introduction
4.1.1
This section presents an air quality
impact assessment for the construction of the Project. The key air quality issues of interest will
be fugitive dust emissions during the construction phase.
4.1.2
The criteria and guidelines as laid
down in Annexes 4 and 12 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO TM) have been
followed in the assessment. The study area for the air quality assessment
covers an area within 500m from the construction worksite.
4.2
Legislation and Guidelines
4.2.1
The principal legislation regulating
air quality in Hong Kong is the Air
Pollution Control Ordinance (APCO) (Cap. 311). Air Quality Objectives (AQOs) are set for the whole Territory,
which specify the statutory concentration limits for various criteria
pollutants and the maximum numbers of times allowed to exceed over a specified
period of time. The AQOs for Total
Suspended Particulates (TSP) are summarised in Table 4‑1.
Table 4‑1 Hong Kong Air Quality
Objectives
Pollutant
|
Pollutants Concentration (mg/m3)
|
|
Averaging
Time
|
|
1
hour (i)
|
8
hours (ii)
|
24
hours (ii)
|
1
year (iii)
|
TSP
|
N.A.
|
N.A.
|
260
|
80
|
(i) Not to be exceeded more than 3 times per year;
(ii) Not to be exceeded more than once per year;
(iii) Arithmetic means;
N.B. Concentrations measured at 298 K and 101.325 kPa (one atmospheric pressure).
4.2.2
On the other hand, Annex 4 Clause
1.1(b) in EIAO TM requires consideration of the hourly TSP limit of 500mg/m3 as assessment criteria in construction dust impact
assessment. Table 4‑2 summarises the dust assessment criteria used in the
study.
Table 4‑2 Air Quality Criteria
Adopted in this Assessment
|
Average Concentration (mg/m3)
|
Air Pollutant
|
1-hour
|
24-hour
|
TSP
|
500
|
260
|
4.2.3
The Air Pollution Control (Construction Dust) Regulation came into
effect since 16 June 1997. Contractors and site agents are required to inform
EPD and adopt the required dust control measures to cut down dust emissions to
an acceptable level while carrying out construction works.
4.3
Ambient Air Quality
4.3.1
It is considered not necessary to
carry out on-site ambient air quality monitoring for the purpose of the air
quality impact assessment because short-term monitoring is not able to give
representative background air pollutant levels. Rather, the background air pollutant levels can be assumed to be
in line with the available data obtained at EPD’s Air Quality Monitoring
Station in Central/Western. Table 4‑3 summarises the annual average concentrations of TSP
monitored at EPD’s Station in years 1997 to 1999.
Table 4‑3 Annual Average
Concentrations of TSP measured at EPD’s Air Quality Monitoring Station in
Central/Western from 1997 to 1999
Air Pollutant
|
Concentration (mg/m3)
|
|
1997
|
1998
|
1999
|
Average
|
TSP
|
84
|
77
|
81
|
81
|
4.3.2
For purpose of the air quality impact assessment,
the average value of the air pollutant concentrations obtained from 1997 to
1999 has been adopted i.e. 81 mg/m3
for TSP.
4.4
Assessment Approach
4.4.1
The primary source of potential air
quality impact is expected to be attributable to fugitive dust emissions
generated from excavation activities and material handling before the
construction of the road deck and noise enclosure. Significant impact from emissions of the other criteria
pollutants such as nitrogen oxides (NOx), sulphur dioxide (SO2),
and carbon monoxide (CO) is not anticipated, as emission of these pollutants in
large quantity from on-site machinery is considered unlikely.
4.4.2
Dust levels at representative
assessment points situated nearest to the site have been predicted
quantitatively using a Gaussian dispersion model - “Fugitive Dust Emission”
(FDM). Potential cumulative dust impact due to possible concurrent construction
activities at nearby worksites including construction works for the Mody Road
Link and Middle Road Link has also been assessed, taking into account the
background dust levels in the study area to simulate the worst-case scenario.
4.4.3
In order to maintain traffic flows on
Nathan Road and to minimise the environmental impact associated with the
construction works, construction activities for site clearance and the road
deck construction will be carried out on a lane-by-lane basis. Once the road deck is completed, all bulk
excavation works will be effectively enclosed underground. The opening retained for site access and
exporting of excavated material will also be provided with a noise
enclosure. It is expected that based on
the proposed construction phasing and sequencing, only limited dust emission
will be generated and will arise from excavation activities associated with the
initial site clearance for the
subsequent temporary road deck construction.
4.4.4
Dust emissions associated with
material handling and excavation during the site clearance phase representing
the worst-case situation has been modelled quantitatively using the “Fugitive
Dust Model” (FDM). The unmitigated dust emission rates (Table 4‑4) have been referenced to the EIA carried out for the
Hung Hom to Tsim Sha Tsui East Rail Extension. Given the progressive nature of
the construction works, the dust emission sources have been assumed to be
located at different work positions in turn within the project site
boundary. Separate air quality models
were then developed and the worst-case maximum TSP levels for each assessment
points based on the models were determined and reported. A table and a figure showing the dust
emission source locations (W1 to W26) are presented in Appendix IV. Dust particle size distribution adopted is
presented in Table
4‑5.
Table 4‑4 Unmitigated TSP Emission
Factors for Site Activities
Activities
|
Emission Factors (g/m2/s)
|
Material Handling
|
1.96 x 10-7
|
Excavation
|
1.89 x 10-7
|
Table 4‑5 Dust Particulate Size
Distribution
Dust Size (mm)
|
Fraction
|
10
|
0.2
|
30
|
0.8
|
4.5
Air Sensitive Receivers
4.5.1
To capture the worst-case situations, representative
air sensitive receivers located in close proximity to the worksite at different
directions were selected. Figure 4-1
shows the locations of the selected representative Air Sensitive Receivers
(ASRs). These representative ASRs are described in Table 4‑6. Given their
closest position, it is expected that should the dust impact on these worst
affected representative ASRs be identified to be within acceptable levels, dust
impact on other ASRs located at further distance away from the project site
will also be within acceptable levels.
Particulate levels were predicted at the representative ASRs at 5.6mPD
(i.e. 1.5m above ground level).
Table 4‑6 Representative ASRs for the Dust Emission Impact Assessment
ASR
|
Type of ASRs
|
Description
|
Horizontal Distance from Worksite Boundary (m)
|
A1
|
Residential + Shop
|
Mirador Mansion
|
41.8
|
A2
|
Hotel + Shop
|
Holiday Inn Hotel
|
0.7
|
A3
|
Hostel + Shop
|
Chungking Mansion
|
0.6
|
A4
|
Hostel + Shop
|
Chungking Mansion
|
0.4
|
A5
|
Hostel + Shop
|
Chungking Mansion
|
0.5
|
A6
|
Hotel + Shop
|
Imperial Hotel
|
0.6
|
A7
|
Shop
|
Oterprise Square
|
8.5
|
A8
|
Hotel + Shop
|
Kowloon Hotel
|
9.4
|
A9
|
Shop
|
Prestige Tower
|
10.3
|
A10
|
Office + Shop
|
Alpha House
|
6.1
|
A11
|
Office + Shop
|
Alpha House
|
6.0
|
A12
|
Hotel + Shop
|
Hyatt Regency Hotel
|
19.4
|
A13
|
Hotel + Shop
|
Hyatt Regency Hotel
|
8.6
|
A14
|
Hotel + Shop
|
Hyatt Regency Hotel
|
10.2
|
4.6
Modelling Methodology
4.6.1
Construction dust impact arising from
site formation works on the nearby existing ASRs has been predicted using the
air quality model “Fugitive Dust Model”
(FDM). The model was particularly developed
to model fugitive dust emissions and is well accepted by HKEPD and USEPA for
this purpose. The model was developed
based on the widely used Gaussian plume formulae for estimation of pollutant
concentrations but has been adapted to incorporate a gradient-transfer
deposition algorithm which accounts for the settling out of dust particles, and
to include the wind dependent factor on dust emission rates. The model is designed to predict fugitive
dust dispersion from point, line and area sources.
4.6.2
The following meteorological data of
the year 1998 relevant to the study have been obtained from Hong Kong
Observatory and used in the modelling study of the dust emission impact
assessment:
à
Hourly
wind direction and speed, air temperature together with atmospheric Pasquill
stability class at the Hong Kong Observatory Headquarters in Tsim Sha Tsui;
à
Daily
morning and maximum mixing heights based on the radiosonde ascent at King’s
Park; and
à
Hourly
total sky cover, cloud amount and cloud based height of the 1st - 4th
layers observed at the Hong Kong Observatory Headquarters in Tsim Sha Tsui.
4.6.3
The worst-case situations were assumed
in the air quality model. Given the
stringent noise limits that need to be satisfied for construction works within
the restricted hours, it has been assumed in the dust model that the working
hours for construction activities will be restricted to 0700 to 1900 hours
only. Maximum 1-hour average and 24-hour average TSP concentrations were
predicted at the representative ASRs and compared with the 1-hour and daily TSP
limits of 500mg/m3 and 260mg/m3, respectively after summation with a background TSP
level of 81mg/m3.
4.7
Modelling Results
4.7.1
The predicted highest 1-hour and daily
average TSP concentrations at the representative ASRs at the modelled heights
are shown in Table 4‑7. Appendix III
presents a typical FDM data and result file for reference. The modelling results showed that the
unmitigated cumulative dust levels under the worst-case situations including
all dust sources plus the background dust level will be within the relevant
assessment criteria presented in Table
4‑2.
4.7.2
Error! Reference source not found.
shows the contours of predicted 1-hour average TSP concentration at 5.6mPD
(1.5m above ground) with background TSP concentration included. The modelling
results revealed that the construction activities will unlikely generate any
unacceptable air quality impact on the nearby ASRs.
Table 4‑7 TSP Levels predicted at the representative ASRs
|
Predicted TSP Concentration (mg/m3)
|
ASR
|
1-Hour Results (at various heights, mPD)
|
24-Hour Results (at various heights, mPD)
|
|
5.6
|
10.6
|
15.6
|
20.6
|
5.6
|
10.6
|
15.6
|
20.6
|
A1
|
82
|
81
|
81
|
81
|
81
|
81
|
81
|
81
|
A2
|
109
|
81
|
81
|
81
|
88
|
81
|
81
|
81
|
A3
|
95
|
81
|
81
|
81
|
86
|
81
|
81
|
81
|
A4
|
115
|
81
|
81
|
81
|
87
|
81
|
81
|
81
|
A5
|
95
|
81
|
81
|
81
|
85
|
81
|
81
|
81
|
A6
|
91
|
81
|
81
|
81
|
85
|
81
|
81
|
81
|
A7
|
84
|
81
|
81
|
81
|
82
|
81
|
81
|
81
|
A8
|
86
|
81
|
81
|
81
|
83
|
81
|
81
|
81
|
A9
|
85
|
81
|
81
|
81
|
83
|
81
|
81
|
81
|
A10
|
87
|
81
|
81
|
81
|
84
|
81
|
81
|
81
|
A11
|
89
|
81
|
81
|
81
|
85
|
81
|
81
|
81
|
A12
|
83
|
81
|
81
|
81
|
82
|
81
|
81
|
81
|
A13
|
86
|
81
|
81
|
81
|
83
|
81
|
81
|
81
|
A14
|
84
|
81
|
81
|
81
|
82
|
81
|
81
|
81
|
N.B. : A background TSP level of 81 mg/m3 has been included in the results.
4.8
Required Dust Control/ Mitigation Measures
4.8.1
The modelling results confirm that the
project will unlikely generate a significant construction dust impact. Dust control measures stipulated in the Air Pollution Control (Construction Dust)
Regulation should be incorporated into the Contract Specifications and be
implemented to control dust generation to acceptable levels. A number of practicable dust mitigation
measures are summarised below:
(i)
dusty
vehicle loads transported to and from the work location should be covered by
tarpaulin sheets and should not be overloaded;
(ii)
dusty
material should be sprayed with water immediately prior to any loading,
unloading or transfer operation to minimise dust emission;
(iii)
routing
of vehicles and positioning of dust generating construction plant at maximum
possible separation distances from ASRs;
(iv)
watering
of all dust emission sources when necessary;
(v)
side
enclosure and covering, by impervious sheeting where practicable, of any
aggregate or other dusty material storage piles, placing of stockpiles in an
area sheltered on the top and the three sides, and/or sprayed with water or a
dust suppression chemical so as to maintain the entire surface wet.
(vi)
drop
height of excavated materials should be controlled to a minimum to limit
fugitive dust generation from unloading as far as practicable;
(vii)
demolished
items shall be covered by impervious sheeting or placed in area sheltered on
the top and the three sides within a day of demolition.
(viii)
instigation
of a programme to monitor the construction process in order to enforce controls
and modify methods of work if dusty conditions arise.
4.9
Potential Cumulative Dust Impact
4.9.1
KCRC has advised that a detailed
construction programme showing the timing of construction activities at
different site locations is currently not available. To simulate the worst case scenario in the air quality study,
possible cumulative impacts arising from concurrent construction works for the
KCRC East Rail Extension, as well as the Salisbury Road Underpass and
Associated Road Improvement Works in the study area have been assessed.
4.9.2
The cumulative TSP concentrations
presented in the ETS-EIA, as reported, represents the cumulative effect
resulting from concurrent construction activities for KCRC East Rail Extension
as well as Sailisbury Road underpass and Associated Road Improvement Works.
4.9.3
Given that the exact dust levels at
the various assessment points selected in the study due to construction
activities associated with the KCRC East Rail Extension and Salisbury Road
Underpass and Associated Road Improvement Works are not available, the findings
on worst-case maximum 1-hour and 24-hour average TSP levels predicted at a
number of worst-affected ASRs have been made referenced to for the purpose of
the evaluation. These ASRs include
Titus Square, Kowloon Hotel, Mirador Mansion and Holiday Inn Hotel (A22, A24,
A37 and A38 as shown in Table 6.1, ETS-EIA).
A simple summation of the predicted TSP concentrations represents a
conservative approach in the prediction.
Table 4‑8 Predicted Maximum Ground
Level 1-Hour & 24-Hour TSP Concentration (Cumulative)
|
Predicted 1-Hour and 24-Hour TSP Concentration (mg/m3)
|
|
|
MTRC TST Station Southern Concourse Extension
(excluding background concentration)
|
Salisbury Road Underpass and Haul Roads
(excluding background concentration)
|
East Rail Extension
(excluding background concentration)
|
Cumulative Impact*
(including background concentration)
|
ASR reference in
ETS-EIA#
|
ASR
|
1-Hour Average
|
24-Hour Average
|
1-Hour Average
|
24-Hour Average
|
1-Hour Average
|
24-Hour Average
|
1-Hour Average
|
24-Hour Average
|
|
A1
|
1
|
0
|
30
|
5
|
4
|
2
|
116
|
88
|
A37
|
A2
|
28
|
7
|
30
|
6
|
4
|
2
|
143
|
96
|
A38
|
A3
|
14
|
5
|
30
|
6
|
4
|
2
|
129
|
94
|
A38
|
A4
|
34
|
6
|
30
|
6
|
4
|
2
|
149
|
95
|
A38
|
A5
|
14
|
4
|
30
|
6
|
4
|
2
|
129
|
93
|
A38
|
A6
|
10
|
4
|
62
|
7
|
142
|
71
|
295
|
163
|
A22
|
A7
|
3
|
1
|
62
|
7
|
142
|
71
|
288
|
160
|
A22
|
A8
|
5
|
2
|
43
|
4
|
186
|
93
|
315
|
180
|
A24
|
A9
|
4
|
2
|
43
|
4
|
186
|
93
|
314
|
180
|
A24
|
A10
|
6
|
3
|
43
|
4
|
186
|
93
|
316
|
181
|
A24
|
A11
|
8
|
4
|
43
|
4
|
186
|
93
|
318
|
182
|
A24
|
A12
|
2
|
1
|
43
|
4
|
186
|
93
|
312
|
179
|
A24
|
A13
|
5
|
2
|
43
|
4
|
186
|
93
|
315
|
180
|
A24
|
A14
|
3
|
1
|
43
|
4
|
186
|
93
|
313
|
179
|
A24
|
*A background TSP level of 81 mg/m3 has
been included in the cumulative results.
# Worst-case 1-hour and 24-hour average TSP levels at
the assessment points A1 through A14 were assumed based on the predicted dust
levels predicted at the relevant ASRs considered in the ETS-EIA. These ASRs
include A22-Titus Square; A24-Kowloon Hotel; A37-Mirador Mansion; A38-Holiday
Inn.
4.9.4
The modelling results presented in Table 4‑8 above demonstrated that potential cumulative dust
impact on the nearby ASRs should not be a concern, especially when each of the
individual construction site are required to implement sufficient dust control
measures in accordance with the requirements under the Air Pollution Control
(Construction Dust) Regulation.
4.10
Operational Phase Impact
4.10.1
The proposed southern concourse
extension and pedestrian subway design will operate underground. No additional
vent shaft was identified to be required. It is not expected that operation of
the project will result in any air quality impact on the surroundings during
operational phase.
4.11
Environmental Monitoring and Audit Requirements
4.11.1
It is recommended that an
Environmental Monitoring and Audit (EM&A) Programme be implemented during the
construction phase of the development to check the implementation of the
recommended dust mitigation measures. This will enable the contractor to
identify the potential dust emission problem, and react immediately when the
dust criteria are approached by increasing the level of dust mitigation
measures. Details of the recommended
EM&A are presented in the EM&A Manual.
4.12
Conclusion
4.12.1
Fugitive dust emission due to
construction activities associated with the proposed TST Station concourse
extension and Nathan Road subway link has been assessed. Potential cumulative dust impact due to
concurrent construction activities for other projects in the vicinity have also
been assessed.
4.12.2
The assessment results demonstrated
that implementation of the project will unlikely pose any unacceptable air
quality impact on the nearby sensitive receivers. Taking into account the background TSP level and dust emission
generated from other nearby construction sites under the worst-case situation
when there are concurrent construction activities, the predicted dust levels at
the ASRs are satisfying the relevant Air Quality Objectives.
4.12.3
Implementation of sufficient
mitigation measures in accordance with the requirements under the Air Pollution Control (Construction Dust)
Regulation will ensure that, as predicted, the dust impact at the ASRs be
alleviated to acceptable levels. An
EM&A programme is recommended to be in place during the construction phase
of the project to check for the implementation and adequacy of dust mitigation
measures to protect the nearby Air Sensitive Receivers (ASRs).
5.
wASTE mANAGEMENT
5.1
Introduction
5.1.1
This section identifies the types of
waste likely to be generated during the construction of the Project, and assesses
the waste management implications in accordance with the criteria and
guidelines given in Annex 7 and Annex 15 of the EIAO TM. Clause 3.5.4 of the EIA Study Brief sets out
the scope and requirements of the assessment.
5.1.2
It is recognised that the quantity of
waste associated with the construction works is relatively small and will
mainly involve excavated material. Besides, given the progressive nature of the
construction works, the quantity of excavated material generated daily would be
limited. Nevertheless, given that density of the built-up area surrounding the
project site, proper waste management is considered necessary to avoid
generation of any significant environmental impact associated with the
handling, collection and disposal of construction waste. Environmental
mitigation measures required to mitigate these environmental impacts were
identified and recommended.
5.1.3
Waste management during the
operational phase would be similar to the existing operation in TST Station and
other MTR Stations and is not expected to be key issue in the EIA study.
5.2
Legislation and Guidelines
5.2.1
The principle legislation governing
waste management in Hong Kong is the Waste
Disposal Ordinance (Cap. 354) (WDO), and its subsidiary regulations. The Ordinance, enacted in 1980, generally
encompasses all stages of waste management, from place of arising to final
disposal point of waste. The Waste Disposal (Chemical Waste) (General)
Regulation, enacted under the WDO in 1992, provides controls on all aspects
of chemical waste disposal, including storage, collection, transport, treatment
and final disposal.
5.2.2
In addition to the WDO and its
subsidiary regulation, the following legislation have some bearing on the
handling, treatment and disposal of wastes in Hong Kong, viz.,:
·
Dumping at Sea Ordinance (1995);
·
Crown Land Ordinance (Cap. 28);
·
Public Health and Municipal Services Ordinance
(Cap. 132) Public Cleansing and Prevention of Nuisances (Urban Council) and
(Regional Council) By-laws; and
·
Dangerous Goods Ordinance.
5.2.3
There are also various guidelines
which are relevant to waste management in Hong Kong. Technical Circulars issued
for Government projects are also stated below for reference:
·
Waste Disposal Plan for Hong Kong (December
1989), Planning, Environmental and Lands Branch Government Secretariat;
·
New Disposal Arrangements for Construction
Waste (1992), Environmental Protection Department & Civil Engineering
Department;
·
Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes (1992), Environmental Protection Department;
·
Works Branch Technical Circular No. 6/92, Fill
Management;
·
Works Branch Technical Circular 22/92, Hong
Kong Government;
·
Works Branch Technical Circular No. 2/93,
Public Dumps;
·
Work Branch Technical circular No. 16/93, Wet
Soil in Public Dumps;
·
Works Bureau Technical Circular No. 5/98, On
Site Sorting of Construction Waste on Demolition Sites;
·
Works Bureau Technical Circular No. 5/99,
Trip-ticket System for Disposal of Construction and Demolition Material;
·
Works Bureau Technical Circular No. 25/99,
Incorporation of Information on Construction and Demolition Material Management
in Public Works Subcommittee Papers;
·
Technical Circular No. 11/92 Classification of
Dredging Sediments for Marine Disposal, Environmental Protection Department;
5.3
Construction Waste
Management
General
5.3.1
The key construction activities are
stated below. The quantity of waste
generated from each construction stage is also evaluated:
·
Site
clearance - waste generation expected is minimal;
·
Road
and pavement demolishing and deck installation - the amount of works expected
is minimal;
·
Underground
excavation – quantity of excavated material is estimated to be in the order of
100m3 per day;
·
Concourse
extension and underground subway construction – quantity of waste is expected
to be minimal;
·
Reinstatement
of road and pavement – minimal waste generation is expected
5.3.2
The waste categories that would be
generated are identified to include the following:
·
Construction
and demolition material (C&D material) – will form the major portion of
waste generated and will involve mainly inert excavated material;
·
Chemical
waste – quantity is expected to be limited;
·
General
refuse - quantity is expected to be insignificant given the build-up nature of
the area surrounding the worksite.
5.3.3
The nature and quantity of each of
these waste types arising from the construction phase of the Project are
evaluated below. The potential
environmental impacts, which may arise from the handling, storage, transport
and disposal of each waste type, are then assessed. Prior to consideration of disposal options for each waste type,
opportunities for waste reduction, reuse, or recycling were identified.
Construction and Demolition (C&D) Material
5.3.4
The construction phase when the
highest quantity of excavated material would be generated will arise when
underground excavation works are carried out.
It is preliminary estimated that a total quantity in the order of 100m3
per day of excavated material would be generated, giving a total quantity in
the order of 12,000m3. The
excavated material is expected to be the only major source of C&D material,
which will be inert suitable for reuse in public filling areas or other
reclamation sites. The amount of
non-inert C&D waste will be insignificant and shall be disposed of at landfills
when encountered.
5.3.5
Based on the preliminary design of the
modification, an estimated total quantity of approximately 2,600m3
imported general fill is required for backfilling the top of the extended
station box and subway. The possibility
to retain some of the excavated material generated onsite for subsequent reuse
as backfill material after the completion of the station box and subway
construction was evaluated with the Project Engineers but not considered
practicable, considering the quality of the excavated material in meeting the
necessary engineering function. Given
the necessary lane-by lane-progressive approach to the construction activities
in order to maintain the traffic on Nathan Road, the work area available for
the construction works will be very limited.
Storage of excavated material onsite is not considered practicable as
the site is small and could become a source of nuisance to the public. Possible offsite reuse of the excavated
material at other MTRCL’s project sites will be subject to the meeting of the
necessary engineering requirements depending of the functions of the fill
material required and is a function of the actual relative timing of other
projects. The offsite reuse opportunities
can be reviewed during the detailed design stage and by the appointed
Contractor.
5.3.6
The excavated material generated daily
onsite during the excavation work period should be immediately delivered to a
truck parked within the noise enclosure and delivered to another MTRC project
site, a public filling area or other reclamation sites as appropriate. Assuming a 10 hours working day and a truck
capacity of 7.5m3, it can be calculated that the average number of
trucks involved is 1.3 per hour.
5.3.7
The excavated material is expected to
be inert waste and is not expected to give rise to any potential hazard during
the handling, collection and disposal.
5.3.8
Air and noise emissions would also be
limited as the activities will be carried out below the road deck and within
the noise enclosure. The excavation activities will be land based and are not
expected to generate any significant water quality impact.
Chemical Waste
5.3.9
As defined under the Waste Disposal (Chemical Waste) (General)
Regulation, chemical waste includes any substance being scrap material or unwanted
substances specified under Schedule 1 of the Regulation. The rate of chemical waste generation from
the construction work is anticipated to be limited but would arise from time to
time associated with the operation and maintenance of on-site equipment. These may include fuel, oil, lubricants,
cleaning fluids and other solvents.
Chemical generated from daily operation of the construction works shall
be recycled/ reused on-site as far as practicable before the disposal option
should be considered. If off-site
disposal of chemical waste is required, they should be collected and delivered
by licensed contractors to Tsing Yi Chemical Waste Treatment Facility and be
disposed of in strict accordance with the Waste
Disposal (Chemical Waste) (General) Regulation. Contractors shall register
with EPD as chemical waste producers when disposal of chemical waste is
anticipated to be required. Chemical
waste materials have to be stored within suitable containers so that leakage or
spillage is prevented during the handling, storage, and subsequent
transportation.
5.3.10
Provided that the handling, storage,
reuse and disposal of chemical wastes are in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation and the Code of Practice
on the Packaging, Labelling and Storage of Chemical Wastes, it will not
cause an unacceptable environmental impact and the issue is not discussed
further.
General Refuse
5.3.11
Throughout the construction phase, the
workforce on the construction site would generate a variety of general refuse
requiring disposal. It is expected that
these refuse will mainly consist on food wastes, aluminium cans, and waste
paper, etc. The above ground work area
is very limited so that only a few workers can work together. Activities such
as eating and smoking are expected to be prohibited and not preferred by the
workers below the road deck. Given the
limited work area, and the presence of existing general refuse disposal
facilities in the vicinity of the work area that can be made use of by the workers,
it is expected that the quantity of general refuse generated within the
construction work site requiring disposal would be very limited. Nevertheless, a reliable waste collector
shall be assigned by the Contractor to collect general refuse generated from
the construction site on a daily basis to minimise the potential odour, pest
and litter impacts.
Overall Waste Management
5.3.12
A Preliminary Waste Management Plan
(WMP) is presented in Appendix V. To
ensure the appropriate handing of the C&DM, the contractor will be required
to prepare a WMP for submission to EPD.
Apart from those conditions listed out in Appendix V, this WMP shall
also contain:
(i)
details
of the construction wastes such as location of the stockpile sites, breakdown
of different categories of waste, disposal routings and the timing for peak
disposal, etc; and
(ii)
a trip-ticket system, or equivalent, to monitor
waste disposal arising from the project.
5.3.13
The following additional control/
mitigation measures are recommended to be followed by the Contractor:
(i)
Storage
of different waste types - different types of waste should be segregated and
stored in different containers, skips or stockpiles to enhance reuse or
recycling of materials and their proper disposal. A temporary storage area equipped with required control measures
(e.g. dust) should be provided onsite or off-site for temporary storage of
chemical waste;
(ii)
Monitoring
waste disposal – the Contractor shall propose the means by which he will
monitor and record waste produced for agreement with MTRCL and on the advice of
EPD;
(iii)
Records
of Wastes - a recording system for the amount of wastes generated, recycled and
disposed (including the disposal sites) should be proposed;
(iv)
Training
- training should be provided by the Contractor to workers in respect of site
cleanliness and appropriate waste management procedure, including waste
reduction, reuse and recycling, and avoid contamination of reusable C&DM.
5.4
Construction Waste EM&A Requirements
5.4.1
In order to ensure that each
construction waste stream generated from the construction phase of the Project
are managed in accordance with the procedures recommended in this EIA, it is
recommended that regular auditing by an Environmental Team be carried out. The regular audit should look at all aspects
of waste management including waste generation, storage, recycling, reuse,
transport and disposal, though recognising that the waste generation from this
site is not significant.
5.5
Conclusion
5.5.1
The waste streams that would be
generated during the construction phase of the roadwork project were identified
and evaluated in terms of their quantity, type and nature. Opportunities for reduction in waste
generation through reuse or recycling are identified. The waste management implications and potential environmental
impacts associated with the handling, transport, and disposal of the identified
waste types are addressed. Mitigation
measures based on good practices have been recommended for each waste type to
address any potential environmental impacts.
5.5.2
A Waste Management Plan (WMP) is
defined and will be implemented by the appointed Contractor. In addition, an audit programme is
recommended to be in place during the construction phase to check that the
waste generated from the construction site are being managed in accordance with
the recommended procedures. Handling
and disposal of waste generated during construction is not expected to give
rise to any significant dust, noise or water quality impact.
5.5.3
Provided that the recommendations set
out in this section are implemented, no waste related regulatory non-compliance
and unacceptable environmental impacts is expected to arise from the handling,
storage, transport and disposal of wastes during the construction and operation
phases of the Project.