12.              IMPLEMENTATION SCHEDULE OF RECOMMENDED MITIGATION MEASURES

 

Table 12.1 Implementation Schedule for Dust Control

 

EIA Ref  #

EM&A Log Ref

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant Legislation and Guidelines

Des

C

O

Dec

S.3.53 - 3.56

S.2.32 –2.33

·       Twice daily watering of the construction site where construction activities are conducted

·         Implementation of the Air Pollution Control (Construction Dust) Regulation and Good Site Practices

Work site / During the construction period

Contractor

 

ü

 

 

TM on EIA Process, APCO, Air Pollution Control (Construction Dust) Regulation

 

 

Table 12.2 Implementation Schedule for Noise Control

 

EIA Ref  #

EM&A Log Ref

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant Legislation and Guidelines

Des

C

O

Dec

S4.41-4.43

S.3.19

Use of quiet equipment

Work site/During construction period

Contractor

 

ü

 

 

EIAO-TM, NCO

S.4.44

S3.20

Use of movable noise barrier for the following construction activities:

·         construction of viaduct from Tai Lam Kok to Siu Lam including piling, pile cap, bridge piers and abutment, casting of bridge beams and lifting of bridge beams

·         construction works at Siu Lam Interchange including relocation of CLP power sub-station, bored pile wall construction, road embankment, realignment of access road, roundabout modification, road pavement, utilities, footpath and road furniture

 

Work sites of the viaduct from Tai Lam Kok to Siu Lam and Siu Lam Interchange /During construction period

Contractor

 

ü

 

 

 

S.4.46

S.3.21

Restriction on the usage of operating PME for the following construction activities during the examination period of the schools:

 

·         Road reconstruction from Tai Lam Kok to Siu Lam: road construction (excavation of existing pavement, road pavement, footpath and road furniture), utilities, fill slopes recompaction, cut slopes stabilization (soil nailing to cut slopes).

·         Reclamation at Tai Lam Kok: dredging and sand filling.

 

Work sites of the road reconstruction  from Tai Lam Kok to Siu Lam and reclamation at Tai Lam Kok/During construction period (examination period of the schools)

Contractor

 

ü

 

 

 

S.4.48

S.3.22

Rescheduling of the following concurrent construction activities so as to avoid simultaneous operating during the examination period of the schools:

 

Seamen’s Training Centre

 

·         Piling works for viaduct from Tai Lam Kok to Siu Lam and dredging works at Tai Lam Kok

·         Piling works for viaduct from Tai Lam Kok to Siu Lam and seawall construction at Tai Lam Kok

·         Pile cap, bridge pier & abutment and filling works at Tai Lam Kok

·         Fill slope recompaction and soil nailing to cut slopes (cut slopes stabilization) for road reconstruction from Tai Lam Kok to Siu Lam

 

Customs & Excise Training School

 

·         Fill slopes recompaction and soil nailing to cut slopes (cut slopes stabilization) along the existing Castle Peak Road from Tai Lam Kok to Siu Lam

 

Work sites of the road reconstruction  from Tai Lam Kok to Siu Lam and viaduct construction from Tai Lam Kok to Siu Lam/During construction period (examination period of the schools)

Contractor

 

ü

 

 

 

S4.40

S. 3.23

Good Site Practices

 

·         Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.

·         Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction program.

·         Mobile plant, if any, should be sited as far away from NSRs as possible.

·         Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum.

·         Plant known to emit noise  strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

·         Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

 

Work site / During construction period

Contractor

 

ü

 

 

 

S4.60

S.3.36

A cantilevered barriers (5.5m high vertical barrier with a 5m cantilever at 45 degrees to the horizontal) of around 25m located behind the footpath of Castle Peak Road

Behind the footpath of Castle Peak Road near the Roundabout at Siu Lam/During operation period

HyD

ü

ü

ü

 

EIAO-TM

 

 

A cantilevered barriers (5.5m high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of around 15m located at northbound carriageway of the slip road to the Siu Lam Interchange;

Northbound carriageway of the slip road to the Siu Lam Interchange /During operation period

 

 

 

 

 

 

 

 

A full enclosure of around 76 m at the slip road to the Siu Lam Interchange (CH102-CH178);

Slip road to the Siu Lam Interchange (CH102-CH178) /During operation period

 

 

 

 

 

 

 

 

A full enclosure of around 175 m at the Castle Peak Road viaduct (CH175-CH350)

Castle Peak Road viaduct  (CH175-CH350) /During operation period

 

 

 

 

 

 

 

 

A cantilevered barriers (5.5m high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of around 604m located at eastbound carriageway of the Castle Peak Road viaduct (CH350 – CH954)

Eastbound carriageway of the Castle Peak Road viaduct (CH350 – CH954) /During operation period

 

 

 

 

 

 

# All recommendations and requirements resulted during the course of EIA/EA Process, including ACE and/or accepted public comment to the proposed project.

* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning


Table 12.3 Implementation Schedule for Water Quality Control

 

EIA Ref #

EM&A Log Ref

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant Legislation and Guidelines

Des

C

O

Dec

S5.54

S.4.36

Dredging

 

·         Dredging should be undertaken using closed grab dredgers with a maximum total production rate of 3,000 m3 day-1;

·         Deployment of silt curtain around the immediate dredging area while dredging works are in progress;

·         Filling should commence only after the completion of seawall construction and should be undertaken behind the seawalls;

·         Mechanical grabs should be designed and maintained to avoid spillage and seal tightly while being lifted; 

·         All vessels should be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash;

·         All hopper barges and dredgers should be fitted with tight fitting seals to their bottom openings to prevent leakage of material;

·         Construction activities should not cause foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site or dumping grounds; and

·         Loading of barges and hoppers should be controlled to prevent splashing of dredged material into the surrounding water.  Barges or hoppers should not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation.

 

Work site / During the construction period

Contractor

 

ü

 

 

WBTC No. 3/2000

S5.55 – 5.56

S.4.37-4.38

Construction Site Runoff  and Drainage

 

·         Before commencing any site formation work, all sewer and drainage connections shall be sealed to prevent debris, soil, sand etc. from entering public sewers/drains.

·         Provision of perimeter channels to intercept storm-runoff from outside the site.  These shall be constructed in advance of site formation works and earthworks.

·         Temporary ditches such as channels, earth bunds or sand bag barriers shall be included to facilitate runoff discharge into the stormwater drain, via a sand/silt basin/trap.

·         Works programmes shall be designed to minimise works areas at any one time, thus minimising exposed soil areas and reducing the potential for increased siltation and runoff.

·         Sand/silt removal facilities such as sand traps, silt traps and sediment basins shall be provided to remove the sand/silt particles from run-off.  These facilities shall be properly and regularly cleaned and maintained. These facilities shall be carefully planned to ensure that they would be installed at appropriate locations to capture all surface water generated on site.

·         Careful programming of the works to minimise excavation works during the rainy season.

·         Temporary access roads shall be protected by crushed gravel and exposed slope surfaces shall be protected when rainstorms are likely.

·         Open stockpiles of construction materials on-site shall be covered with tarpaulin or similar fabric during rainstorms to prevent erosion.

 

Work site / During the construction period

Contractor

 

ü

 

 

ProPECC

PN 1/94

S5.57

S.4.39

General Construction Activities

 

·         Debris and rubbish generated on-site should be collected, handled and disposed of properly to avoid entering the nearby coastal waters and stormwater drains.

·         All fuel tanks and store areas shall be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity.

·         Open drainage channels and culverts near the works areas should be covered to block the entrance of large debris and refuse

 

Work site / During the construction period

Contractor

 

ü

 

 

ProPECC

PN 1/94

S5.58

S.4.40

Sewage Effluent

 

Portable toilets shall be provided by the Contractors, where necessary, to handle sewage from the workforce.

 

Work site / During the construction period

Contractor

 

ü

 

 

ProPECC

PN 1/94

S5.59

S4.41

Operation Phase

 

·         The road drainage should be directed through silt traps in the gully inlets to remove silt and grit before entering the public storm water drainage system; and

·         The silt traps should be regularly cleaned and maintained in good working condition.

 

Road drainage system / During operational period

Project Proponent

ü

 

ü

 

ProPECC PN 5/93

# All recommendations and requirements resulted during the course of EIA/EA Process, including ACE and/or accepted public comment to the proposed project.

* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning

 

Table 12.4 Implementation Schedule for Waste Management

 

EIA Ref #

EM&A Ref #

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant

Legislation

and Guidelines

Des

C

O

Dec

S.6.35–S.6.37

S5.3 - S5.5

Marine Sediments

 

·         In accordance with the WBTC No. 3/2000, the seriously contaminated material must be dredged and transported with great care.  Mitigation measures, including the use of closed-grab dredgers, shall be incorporated.

·         The dredged contaminated sediment must be effectively isolated from the environment upon final disposal and shall be disposed of at the East Sha Chau Contaminated Mud Pits.

 

During transportation and disposal of the dredged marine sediments, the following measures shall be taken to minimise potential impacts on water quality:

 

·         Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material.  Excess material shall be cleaned from the decks and exposed fittings of barges and hopper dredgers before the vessel is moved.

·         Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation.  Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by the Director of Environmental Protection.

Work site / During the construction period

Contractor

 

ü

 

 

WBTC No. 3/2000

S.6.38

S 5.6

Good Site Practices and Waste Reduction Measures

 

·         Use waste haulier authorized or licensed to collect specific category of waste;

·          Obtain the necessary waste disposal permits from the appropriate authorities, if they are required, in accordance with the Waste Disposal Ordinance (Cap 354, Waste Disposal (Chemical Waste) (General) Regulation (Cap 354), the Land (Miscellaneous Provision) Ordinance (Cap 28);

·         nomination of an approved personnel, such as a site manager, to be responsible for good site practice, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site;

·         training of site personnel in proper waste management and chemical handling procedures;

·         provision of sufficient waste disposal points and regular collection for disposal;

·         appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

·         separation of chemical wastes for special handling and appropriate treatment at the CWTF;

·         regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors;

·         a recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites);

·         In order to monitor the disposal of C&D and solid wastes at public filling facilities and landfills, and control fly-tipping, a trip-ticket system should be included as one of the contractual requirements and implemented by the Environmental Team.  One may make reference to WBTC No. 5/99 for details; and

·         A Waste Management Plan (WMP) should be prepared and this WMP should be submitted to the Engineer for approval.  One may make reference to WBTC No. 29/2000 for details.

 

Work site / During the construction period

Contractor

 

ü

 

 

Waste Disposal Ordinance (Cap.54)

S6.39

S5.7

Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

 

·         segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

·         to encourage collection of aluminium cans by individual collectors, separate labelled bins shall be provided to segregate this waste from other general refuse generated by the work force;

·         any unused chemicals or those with remaining functional capacity shall be recycled;

·         use of reusable non-timber formwork to reduce the amount of C&D material;

·          

·         prior to disposal of C&D waste, it is recommended that wood, steel and other metals shall be separated for re-use and / or recycling to minimise the quantity of waste to be disposed of to landfill;

·         proper storage and site practices to minimise the potential for damage or contamination of construction materials; and

·         plan and stock construction materials carefully to minimize amount of waste generated and avoid unnecessary generation of waste.

 

Work site / During planning and design stage, and construction stage

Contractor

ü

ü

 

 

WBTC No. 4/98, 5/98

S 6.41 - S.6.43

S.5.9 – 5.11

Construction and Demolition (C&D) Waste

 

·         Careful design, planning and good site management can minimize over-ordering and generation of waste materials such as concrete, mortar and cement grouts.  The design of formwork should maximize the use of standard wooden panels so that high reuse levels can be achieved.  Alternatives such as steel formwork or plastic facing should be considered to increase the potential for reuse.

·         The contractor should use as much of the C&D material as possible on-site.  Proper segregation of waste types on site will increase the feasibility of certain components of the waste stream by recycling contractors. 

·         Inert C&D material (public fill) are directed to reclamation areas, where they have the added benefit of offsetting the need for removal of materials from borrow areas for reclamation purposes, or to an approved public filling area (PFA). 

 

Work site / During the construction period

Contractor

 

ü

 

 

 

S6.44 –S.4.48

S.5.12-5.17

Chemical Wastes

 

After use, chemical wastes should be handled according to the Code of Practice on the Packaging, Labeling and Storage of Chemical Wastes.  Spent chemicals should be stored and collected by an approved operator for disposal at the Chemical Waste Treatment Facility or other licensed facility in accordance with the Chemical Waste (General) Regulation.

·         Containers used for the storage of chemical waste should:

·         Be suitable for the substance they are holding, resistant to corrosion, maintained in good condition, and securely closed;

·         Have a capacity of less than 450 litres unless the specifications have been approved by the EPD; and

·         Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.

 

The storage area for chemical waste should:

·         Be clearly labeled and used solely for the storage of chemical waste;

·         Be enclosed on at least 3 sides;

·         Have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;

·         Have adequate ventilation;

·         Be covered to prevent rainfall entering (water collected within the bund must be tested and disposal as chemical waste if necessary); and

·         Be arranged so that incompatible materials are adequately separated.

 

Disposal of chemical waste should:

·         Be via a licensed waste collector.

·         Be a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which offers a chemical waste collection service and can supply the necessary storage containers; or be a reuser of the waste, under approval from the EPD.

·         Be a reuser of the waste, under approval from the EPD

Work site / During the construction period

Contractor

 

ü

 

 

Waste Disposal (Chemical Waste)

(General) Regulation,

Code of Practice on the

Packaging, Labelling and

Storage of Chemical Wastes

S.6.49 – S.6.50

S.5.18 – 5.19

General Refuse

 

·         General refuse should be stored in enclosed bins or compaction units separate from C&D and chemical wastes.  A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D and chemical wastes, on a daily or every second day basis to minimize odour, pest and litter impacts. 

·         Office waste can be reduced through recycling of paper if volumes are large enough to warrant collection.  Participation in a local collection scheme should be considered if one is available.

Work site / During the construction period

Contractor

 

ü

 

 

PHMSO & Air Pollution

control (Open Burning) Regulation

# All recommendations and requirements resulted during the course of EIA/EA Process, including ACE and / or accepted public comment to the proposed project.

* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning

 

 


Table 12.5 Implementation Schedule for Ecology

 

EIA Ref #

EM&A Ref #

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant

Legislation

and Guidelines

Des

C

O

Dec

S.7.57

S.6.4

On-site planting should be provided if there are loss of vegetation due to construction activities.

Work site / during construction period

Contractor

 

ü

 

 

 

S.7.58 – 7.61

S.6.5 –S.6.8

Erect fences where practical along the boundary of construction sites.

 

Check the work site boundaries regularly.

 

Prohibit and prevent open fires within the site boundary and provide temporary fire fighting equipment.

 

Work Site / during construction period

Contractors

 

ü

 

 

 

S.7.59

S.6.6

Reinstate temporary work sites / disturbed areas to its original condition immediately after completion of the construction.

 

Work Site / during construction period

Contractor

 

ü

 

 

 

# All recommendations and requirements resulted during the course of EIA/EA Process, including ACE and/or accepted public comment to the proposed project.

* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning

 

 


Table 12.6 Implementation Schedule for Landscape and Visual Impact

 

EIA Ref #

EM&A Log Ref

Environmental Protection Measures / Mitigation Measures

Location / Timing

Implementation Agent

Implementation Stages*

Relevant Legislation and Guidelines

Des

C

O

Dec

S.9.64

S.7.6-7.8

Construction programming and management. (LMM1)

 

 

 

 

 

 

 

 

 

The construction programme for the Project should be reduced to the shortest possible period, particularly in those locations where severe or high landscape and visual impacts are expected

Work site / During the construction period

 

Contractor

ü

ü

 

 

 

 

 

Keeping the periphery of the works areas at street level clean and tidy and attractive and convenient for pedestrians.

Work site / During the construction period

 

Contractor

 

 

ü

 

 

 

 

 

Use of colourful hoarding with interesting motifs

 

Work site / During the construction period

 

Contractor

ü

ü

 

 

 

S.9.83

S.7.9-7.11

Advanced planting and erosion control works. (LMM2)

 

 

 

 

 

 

 

 

 

Advance planting of trees and landscape areas

Work site / During the construction period

 

Contractor

 

ü

 

 

 

 

 

Temporary hydroseeding of stockpiled topsoil to minimise erosion and improve the visual appearance.

Work site / During the construction period

 

Contractor

 

ü

 

 

 

 

 

Maintenance and Management of planting during operation

Work site / During the operation period

 

 

LCSD

 

 

ü

 

WBTC 18/94

LU/GN001

S.9.84

S.7.12-7.14

Maximisation of amenity planting in road corridor (LMM3)

 

 

 

 

 

 

 

 

 

 

Opportunities to incorporate significant amenity areas along the alignment should be maximised to provide visual relief in an otherwise congested traffic environment. Efforts to remove the footpath from the immediate road edge are to be incorporated whenever possible.

 

 

Work site / During Detailed Design

Design

HyD

ü

 

 

 

 

 

 

 

 

Substantial planting of amenity areas

Work site / During the construction period

 

 

Contractor

 

ü

 

 

 

 

 

 

Maintenance of planting during operation

Work site / During the operation period

 

LCSD

 

 

ü

 

WBTC 18/94

LU/GN001

S.9.85

7.15-7.17

Design, materials and finishes of engineering structures (LMM4).

 

 

 

 

 

 

 

 

 

The quality of the design of all engineering structures, which will include viaducts, parapets, piers, slip roads, noise barriers, noise enclosures and drainage systems. Attention should be given to design modern and attractive structures.

 

Detailed Design

Design Consultants

ü

 

 

 

ACABAS

Submission HyD Standards

 

 

 

High quality finishes to structural elements

 

Work site / During the construction period

 

Contractor

 

ü

 

 

 

 

 

Maintenance and management during operation

Work site / During the operation period

 

 

HyD STR

 

 

 

ü

 

 

S.9.86

S.7.18-7.19

Maximisation of woodland planting on disturbed land. (LMM5)

 

 

 

 

 

 

 

 

 

 

Compensatory planting.

 

 

Work site / During the construction period

Contractor

 

ü

 

 

WBTC 25/93.

 

 

Maintenance and Management of planting during operation

Work site / During the operation period

 

LCSD

 

 

ü

 

WBTC 18/94

LU/GN/001

 

S.9.87

S.7.20-7.21

Urban area under-viaduct hard and soft landscape works. (LMM6)

 

 

 

 

 

 

 

 

 

 

Where viaducts result in sterilised space under viaducts, extensive hard and soft landscape works should be provided to enhance and restore the function of the land, including creepers and climbers on retaining walls and supporting columns.

Work site / During the construction period

Contractor

 

ü

 

 

 

 

 

Maintenance and management of during operation

Work site / During the operation period

 

LCSD / ArchSD / HyD

 

 

ü

 

WBTC 18/94

LU/GN001

# All recommendations and requirements resulted during the course of EIA/EA Process, including ACE and/or accepted public comment to the proposed project.

* Des - Design, C - Construction, O – Operation, and Dec – Decommissioning

Based on Appendix A to WBTC 18/94