4.                  NOISE

 

Introduction

 

4.1              This section presents an assessment of potential noise impacts arising from the proposed project during construction and operation phase and recommends appropriate mitigation measures, where necessary. 

 

Environmental Legislation, Standards and Guidelines

 

4.2              The Noise Control Ordinance (NCO) and Environmental Impact Assessment Ordinance (EIAO) provide the statutory framework for noise control.  Assessment procedures and standards are set out in five Technical Memoranda (TMs) listed below:

 

·        TM on Environmental Impact Assessment Process (EIAO-TM);

·        TM on Noise from Construction Work other than Percussive Piling (GW-TM);

·        TM on Noise from Percussive Piling (PP-TM);

·        TM on Noise from Construction Work in Designated Areas (DA-TM); 

·        TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM).

 

4.3              Noise impacts will be assessed in accordance with the criteria and methodology given in the Technical Memoranda (TM) made under the Noise Control Ordinance (NCO) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

 

Construction Noise

 

4.4              Daytime construction noise, i.e. 0700 – 1900 on weekdays, is under the control of EIAO-TM.  According to Table 1B of Annex 5 stipulated in the EIAO-TM: Criteria for Evaluating Noise Impact, the noise limit is Leq(30 min) 75 dB(A) for domestic premises and Leq(30 min) 70 dB(A) for schools during normal hours(65 dB(A) during examination) and all other where unaided voice communication is required.  Construction activities other than percussive piling using powered mechanical equipment (PME) undertaken at other times (i.e. restricted hours) are under the control of the NCO.

 

4.5              Between 1900 and 0700 hours and whole day on Sundays and public holidays, activities involving the use of PME for the purpose of carrying out construction work are prohibited unless a construction noise permit (CNP) has been obtained.  A CNP may be granted provided that the Acceptable Noise Level (ANL) for the Noise Sensitive Receivers (NSRs) can be complied with the requirements in the GW-TM. ANLs are assigned depending upon the Area Sensitivity Rating (ASR). The corresponding basic noise levels (BNLs) for evening and night time periods, are given in Table 4.1.

 


Table 4.1    Construction Noise Criteria for Activity other than Percussive Piling

 

Time Period

Basic Noise Level (BNLs)

 

ASR A

ASR B

ASR C

Evening (1900 to 2300 hours) 1

60

65

70

Night (2300 to 0700 hours)

45

50

55

Notes: 1 includes Sundays and Public Holidays during daytime and evening

 

4.6              The Study Area is generally rural in nature with low-density population is directly affected by traffic noise from Tuen Mun Road.  Therefore the existing noise sensitive receivers in the Study Area have been assumed to be ‘ASR B’.  According to Table 4.1, the construction noise criteria for the sensitive receivers would be 65dB(A) in the evening and 50dB(A) at night.  The NCO would decide the ASR at the time of assessment of such an application based on the contemporary situations/conditions.  It should be noted that the situations/conditions around the site may change from time to time.  The ASR assumed in this EIA report is for indicative assessment only. 

 

4.7              In addition to the general controls on the use of PME during the restricted hours, the Noise Control Authority has implemented a more stringent scheme via DA-TM.  Under the DA-TM, the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW) within a designated area during restricted hours requires a valid CNP.  The study area of this project is within the designated area, therefore, the operation of SPME including hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker will be controlled.  The PCWs to be controlled are :

 

·        Erecting or dismantling of formwork or scaffolding

·        Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material

·        Hammering

 

4.8              In general, the CNP would not be granted for the carrying out of PCW within a designated area during the restricted hours.  The CNP would be granted for the use of SPME during the restricted hours within a designated area when the Corrected Noise Level (CNL) for all the SPME proposed to be used are 15 dB(A) lower than the ANL stipulated in the GW-TM.

 

Percussive Piling

 

4.9              Percussive piling works, if necessary, are required to apply for construction noise permit. PP-TM sets out the requirements for working and determination of the permitted hours of operations.  ANLs for percussive piling for different type of NSRs are shown in Table 4.2.

 


Table 4.2    Acceptable Noise Levels for Percussive Piling

 

NSR Window Type or Means of Ventilation

ANL, dB(A)

(i) NSR (or part of NSR) with no windows or other opening

100

(ii) NSR with central air conditioning system

90

(iii) NSR with windows or other openings but without central air conditioning system

85

Note: 10dB(A) shall be subtracted from the ANLs shown above for NSRs which are hospitals, medical clinics, educational institutes, courts of law or other NSRs which are considered to be particularly noise sensitive by the Authority.

 

4.10          With effect from 1 October 1999, the use of diesel, pneumatic and/or steam hammers is prohibited in Hong Kong.  The permitted hours of operation for carrying out the percussive piling work not involving the use of diesel, pneumatic and steam hammers are listed in Table 4.3.

 

Table 4.3    Permitted Hours of Operation for Percussive Piling

 

Amount by which Corrected Noise Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL

Permitted hours of operation on any day not being a general holiday

10 dB(A) < CNL-ANL

0800 to 0900 AND 1230 to 1330 AND 1700 to 1800

0 dB(A) < CNL-ANL £ 10 dB(A)

0800 to 0930 AND 1200 to 1400 AND 1630 to 1800

CNL- ANL £ 0 dB(A)

0700 to 1900

 

Operational Noise

 

4.11          Annex 5 of EIAO-TM : Criteria for Evaluating Noise Impact defines the criteria L10(1hour) for road traffic noise at various NSRs:

 

·        70 dB(A) at the facades of dwellings, hotels, offices;

·        65 dB(A) at the facades of schools, places of workshop, courts of law; and

·        55 dB(A) at the facades of hospital.

 

4.12          If any facades of existing NSRs are still exposed to predicted noise levels exceeding the relevant noise criteria after the implementation of all direct mitigation measures, provision of indirect technical remedies (ITR) in the form of acoustic insulation and air conditioning should be considered under the EIAO-TM and the ExCo directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the Use of New Roads”.  The eligibility for indirect technical remedies will be tested against the following three criteria:

 

·        the predicted overall noise level from the new road, together with other traffic noise in the vicinity must be above 70 dB(A) for residential dwellings, 65 dB(A) for educational institutions and 55dB(A) for hospitals.

 

·        The predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level.

 

·        The contribution to the increase in the predicted overall noise level from the new road must be at least 1.0 dB(A).

 

4.13          According of the Study Brief, a ‘new’ road is defined when road section undergoes major modification which will directly result in 25% increase in lanes or substantial changes in alignment or characters (e.g. change to a high speed road) of existing road.  As a result, Siu Lam Interchange and the section of Castle Peak Road (CPR) from Ka Loon Tsuen to Siu Lam Interchange were defined as ‘new’ roads.  Other roads such as Tuen Mun Road, Route 10 NLYLH’s Siu Lam Link Roads (SLLR) and other existing local roads were defined as ‘existing’ roads.  Appendix 4.1 illustrates the extent of the defined new roads and existing roads.

 

Description of the Environment

 

4.14          The proposed CPR starts from Ka Loon Tsuen to the Siu Lam Interchange.  In general, the site is rural with low-density population.  A Vocational Training Council Seamen’s Training Centre, a correctional training school and some scattered village houses are situated at Tai Lam Kok.  A hospital, a psychiatric centre and the Correctional Services Department Staff Quarters are located at Siu Lam. The existing noise environment is dominated by road traffic noise along the existing Castle Peak Road and Tuen Mun Road.   The prevailing traffic noise levels at the existing noise sensitive receivers (NSRs) are in the range of 61 to 81 dB(A) (Appendix 4.2).  With the proposed CPR, the noise levels at the existing NSRs would likely be higher, if unmitigated. 

 

Noise Sensitive Receivers

 

4.15          The Study Area is generally rural in nature and comprises mainly scattered village houses, low-rise residential buildings, hospital and educational institutions located mainly at Tai Lam Kok and Siu Lam.

 

4.16          According to the So Kwun Wat OZP (No. S/TM-SKW/4), a comprehensive development area (CDA) is zoned at Tai Lam Chung (area between Wu Uk and Wong Uk).  In order to assess the traffic noise impact associated with the operation of the proposed CPR, an assessment point has assigned for the CDA.

 

4.17          In accordance with the Study Brief, a number of representative NSRs within the Study Area have been identified for the construction and traffic noise impact assessments as listed in Table 4.4 and Table 4.5.  Locations of the representative NSRs are illustrated in Figures 4.1 and 4.2.

 

Table 4.4 Summary of Representative Noise Sensitive Receivers for Construction Noise Impact Assessment

 

NSR

Location

Use

Ground elevation (mPD)

N2A

Siu Lam Hospital Library

Library

60

N2F

Siu Lam Hospital

Hospital

78

N3H

Correctional Services Department Married Staff Quarter

Residential

34.8

N4H

Correctional Services Department Married Staff Quarter

Residential

27

N1B

Siu Lam Psychiatric Centre

Hospital

45.2

NSC1

Customs & Excise Training School

Educational Institution

3.7

VH1

Village house at Wu Uk Tsuen

 

Residential

3

VTC1

Seamen’s Training Centre

Educational Institution

5

VTC3

Seamen’s Training Centre

Educational Institution

5

KLT

Ka Loon Tsuen

Residential

18

AP1

Correctional Services Department Staff Quarter

Residential

22

 

 

 

Table 4.5 Summary of Representative Noise Sensitive Receivers for Traffic Noise Impact Assessment

 

NSR

Location

Use

Ground elevation (mPD)

Assessment Floors

N2A

Siu Lam Hospital

 

Library

60

G/F

N2F

Siu Lam Hospital

 

Hospital

78

G/F, 1/F, 2/F

N3H

Correctional Services Department Married Staff Quarters

Residential

34.8

G/F, 2/F, 4/F

N4H

Correctional Services Department Married Staff Quarters

Residential

27

1/F, 2/F, 4/F

N1B

Siu Lam Psychiatric Centre

 

Hospital

45.2

1/F, 3/F, 4/F

NSC1

Customs and Excise Training School

Educational Institution

3.7

1/F, 3/F, 6/F

VH1

Village house at Wu Uk Tsuen

Residential

3

1/F, 3/F

VTC1

Seamen’s Training Centre

Educational Institution

5

G/F, 1/F, 2/F

VTC2

Seamen’s Training Centre

Educational Institution

5

G/F, 1/F, 2/F

VTC3

Seamen’s Training Centre

Educational Institution

5

G/F, 1/F, 2/F

KLT

Village house at Ka Loon Tsuen

Residential

18

1/F, 3/F

PC1

Poseidon Coast

Residential

10

1/F, 14/F, 27/F

AP1

Correctional Services Department Staff Quarter

Residential

22

G/F, 1/F, 2/F

CDA

Comprehensive Development Area at Tai Lam Chung

Residential

7.7

G/F, 20/F, 40/F

 

Assessment Methodology

 

Construction Phase

 

4.18          In accordance with the EIAO, the methodology outlined in the GW-TM is used for the assessment of construction noise (excluding percussive piling).  Sound Power Levels (SWLs) of the equipment will be taken from Table 3 of the GW-TM.  Where no sound power level (SWL) was given in the GW-TM, reference was made to BS 5228:Part 1:1997 Noise Control on Construction and Open Sites and previous similar studies or from measurements taken at other sites in Hong Kong.  Groups of powered mechanical equipment (PME) have been assigned for various construction activities of the CPR improvement works.  Details of the PME and the total SWLs for various construction activities are provided in Appendices 4.3a and 4.3b.

 

4.19          Noise impacts at the nearest sensitive facades of the residential buildings to the source positions will be assessed.  All PME items required for a particular construction activity are located at the notional or probable source position of the segment where such activity is performed.  A +3 dB(A) façade correction will be added to the predicted noise levels in order to account for the facade effect at each NSR.  A sample calculation for the construction assessment is provided in Appendix 4.4.

 

4.20          In accordance with the preliminary construction progamme (Appendix 2.19), the project will last from June 2003 to June 2007, which includes eight major tasks as listed below:

 

1.      Viaduct from Tai Lam Kok to Siu Lam.

2.      Reclamation at Tai Lam Kok.

3.      Road widening from Temporary Site Boundary to Tai Lam Kok.

4.      Road widening from Ka Loon Tsuen to Temporary Site Boundary.

5.      Siu Lam Interchange.

6.      Road reconstruction from Temporary Site Boundary to Tai Lam Kok.

7.      Road reconstruction from Ka Loon Tsuen to Temporary Site Boundary.

8.      Road reconstruction from Tai Lam Kok to Siu Lam.

 

4.21          As informed by HyD, Bridge No. 15 will not be reconstructed in this project and therefore construction noise impact assessment for that is not required.

 

4.22          Generally, the construction activities of the project will be carried out in non-restricted hours (0700-1900 hours) with the exception of dredging works which will be carried out on 24-hour day. For any construction works planned during the restricted hours, it will be the responsibility of the Contractor to ensure compliance with the NCO and the relevant TMs.  In such cases, the Contractor will be required to submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.  Therefore, the potential noise impacts of dredging works proposed within restricted hours are not formally assessed in this EIA.  In order to facilitate the efforts of the project proponent to avoid any potentially adverse noise impacts, an indicative assessment (Sections 4.69 – 4.73) is undertaken at representative NSRs. 

 

4.23          Based on the construction programme and the assigned PME groups, both the individual and cumulative construction noise levels from individual and all concurrent construction activities which are considered to be significant at the NSRs have been assessed.

 

Operational Phase

 

4.24          Traffic noise impact was predicted using the methodology provided in the UK Department of Transport Calculation of Road Traffic Noise (CRTN) 1988.  According to EIAO-TM, the road traffic noise should be predicted based on the maximum traffic forecast within 15 years upon the operation of the proposed roadwork. Year 2022 is considered to be the maximum traffic forecast and has been adopted for the assessment.  Transport Department has approved the adopted traffic figures.  Projected peak hourly traffic flow and vehicle composition for 2022 is presented in Appendix 2.21. 

 

4.25          Since the completion of Route 10 NLYLH’s SLLR would be deferred until after 2010, a traffic forecast has been conducted to verify whether the traffic volumes for the case of without Route 10 NLYLH’s SLLR in year 2011 on the proposed CPR would be higher than the projected figures for 2022.  The traffic forecast results indicate that the projected 2011 traffic flows on the proposed CPR would be lower than the projected 2022 figures.  Hence, the projected 2022 traffic flows would still be valid for the assessment.  Details of the traffic forecast are given in Appendix 4.8.

 

4.26          Where appropriate, the prevailing existing noise levels for the construction year (Year 2003) will also be predicted in order to determine whether or not NSRs exposed to residual traffic noise impacts will qualify the Noise Insulation Works under this project.

 

4.27          The operation speed for the proposed Castle Peak Road between Ka Loon Tsuen and Siu Lam is 70km/h, which is approved by Transport Department. The traffic speeds for Tuen Mun Road and the existing Castle Peak Road adopted in the model are 80km/h and 70km/h respectively. The operation speed for other existing slip roads and the proposed roundabouts were assumed to be 50km/h.

 

4.28          Low noise road surfacing is assumed to be a standard feature for Tuen Mun Road in the assessment.  In accordance with the EIA Final Assessment Report of the Route 10 NLYLH, it is assumed that the main alignment (excluding the main span of Tsing Lung Bridge and the toll plaza) and associated slip roads with speed limit higher than 50km/hr will be surfaced using low noise road surfacing.

 

4.29          The following noise mitigation measures (as shown in Figure 4.3) proposed in the approved EIA Final Report (Southern Section) of Route 10 have been included in the assessment.

 

·        A 400 m long, 5m tall absorptive vertical barrier on the eastern edge of southbound Route 10 NLYLH’s SLLR;

·        A 150 m long, 5m tall absorptive vertical barrier on the eastern edge of northbound Route 10 NLYLH’s SLLR;

·        A 230 m long, full enclosure for southbound Route 10 NLYLH’s SLLR;

·        A 370 m long , semi-enclosure on the eastern edge of Route 10 NLYLH’s SLLR;

·        A 360 m long, semi-enclosure on the eastern edge of northbound Route 10 NLYLH’s SLLR;

·        A 230 m long, full enclosure for northbound Route 10 NLYLH’s SLLR;

·        A 140 m long, 5m tall absorptive vertical barrier on western edge of northbound Route 10 NLYLH’s SLLR.

 

4.30          The alignment of the Route 10 NLYLH’s SLLR adopted in the assessment has made reference to the Drawings Nos. 524/BRG/509 to 511 as provided by HyD.  Based on the available information, no noise barriers on the section of Tuen Mun Road at Siu Lam are included in the assessment.

 

4.31          The road network, proposed building layout and all other features that could have noise screening or reflective effects, were taken into account in the road traffic noise model.  The roads were divided into segments.  A road layout defines the road width, road surface type and traffic mix, flow and road design speed.  The segmentation and calculation process were carried out using a model based on the CRTN, which is agreed by EPD. Noise levels were calculated at each receiver point at three different elevations (i.e. 1st floor, mid floor and top floor).  A sample calculation is provided in Appendix 4.5 for reference.

 

Identification of Impacts

 

Construction Phase

 

4.32          The major noisy construction tasks would be the construction of viaduct from Tai Lam Kok to Siu Lam and road reconstruction from Tai Lam Kok to Siu Lam. It is anticipated that Seamen’s Training Centre, Customs and Excise Training School, Correctional Services Department Married Staff Quarters and Siu Lam Psychiatric Centre may be affected by the construction noise arising from the project.

 

4.33          As indicated in Table 2.1, the project ‘Castle Peak Road Improvement from Sham Tseng to Ka Loon Tsuen (Project 553TH)’ would likely be carried out concurrently with the proposed project.  However, all the identified representative NSRs are located at a distance of more than 300m from the site boundary of the Project 553TH with the exception of NSR KLT.  As illustrated on Figure 4.1, apart from the work site of Ka Loon Tuen to Temporary Site Boundary, all other work sites are located more than 300m from the NSR KLT.  In addition, the construction programme indicates that the section of proposed CPR from Ka Loon Tuen to Temporary Site Boundary will be constructed upon the completion of the Project 553TH.  Hence, cumulative construction noise impact from the Project 553TH is not anticipated.

 

4.34          As indicated in Section 2.67, it is anticipated that the construction of Route 10 NLYLH’s SLLR will not be undertaken concurrently with the project.  Hence no cumulative construction noise impact from the Route 10 Project is expected. 

 

Operational Impacts

 

4.35          This project is a road improvement work.  The proposed works are carried out along the coastal area from Ka Loon Tsuen to Siu Lam.  The widening section between Ka Loon Tsuen and Tai Lam Kok is not expected to adversely affect any residential or other kinds of development due to the topographical conditions.  On the other hand, the additional dual-two lanes from the section between Tai Lam Kok and Siu Lam Interchange would likely enhance the traffic noise impacts on the nearby NSRs such as Seamen’s Training Centre and Correctional Services Department Married Staff Quarters. Appropriate noise mitigation measures may be required to alleviate any traffic noise impact.

 

Prediction and Evaluation of Impacts

 

Construction Phase

 

4.36          As broadly illustrated in the construction programme (Appendix 2.19), various construction activities may be carried out concurrently during a particular period.  Cumulative noise impacts arising from different construction activities of the proposed project on the representative NSRs have been predicted and the results are presented in Appendix 4.6a.

 

4.37          As indicated in Appendix 4.6a, the cumulative noise levels at the representative NSRs are predicted to range from 45 dB(A) to 84 dB(A).  Apart from NSRs N4H, the cumulative noise levels at all NSRs are predicted to exceed the noise criteria of 75 dB(A) for residential uses and 70 dB(A) for schools during normal hour and the place where unaided voice communication is required.  Mitigation measures are therefore required to alleviate the construction noise impacts.

 

Operational Phase

 

4.38          Unmitigated traffic noise levels at the 14 representative NSRs have been predicted and the results are given in Appendix 4.7a.  Table 4.6 summarizes the potential traffic noise impacts associated with the project.

 

4.39          As indicated in Appendix 4.7a, the unmitigated road traffic noise levels at the representative NSRs are predicted to range from 62dB(A) to 82dB(A).  Apart from CDA and the lower floor of VH1 and PC1, the noise levels at all the NSRs would exceed the noise criteria of 70dB(A) for residential uses, 65dB(A) for educational institutions and 55dB(A) for hospitals.  A breakdown of the overall noise levels indicates that most of the exceedances are primarily attributable to existing roads.  With the exception of N2F, N3H, N4H, N1B, VTC2 and VTC3, the noise levels from new roads at all the NSRs would be below the noise criteria and contribute less than 1dB(A) to the overall noise levels.  In order to abate the traffic noise impact arising from the proposed CPR on the affected NSRs, noise mitigation measures are required.

 


Table 4.6    Potential Traffic Noise Impacts

 

NSR

Residential Premises/Schools

Exceedance of the Noise Criteria1, dB(A)

Estimated Number of dwellings /classrooms/noise sensitive elements

 

Exceed the  Noise Criteria

Exceed the  Noise Criteria with New Roads Contribution >1dB(A)

N2A

 Siu Lam Hospital (Library)

6

Whole block

0

N2F

Siu Lam Hospital

13 – 17

Southern block

Ground floor of Southern block

N3H & N4H

Correctional Services Department Married Staff Quarters

5 – 10

30

20

N1B

Siu lam Psychiatric Centre

17

Whole block

0

NSC1

Customs and Excise Training School

9

15*

0

VH1

Village house at Wu Uk Tsuen

1

5

0

VTC1, VTC2 & VTC3

Seamen’s Training Centre

14 – 17

10*

0

KLT

Village House at Ka Loon Tsuen

2

5

0

PC1

Poseidon Coast

6

120

0

AP1

Correctional Services Department Staff Quarter

12

10

0

CDA

Comprehensive Development Areas at Tai Lam Chung

0

0

0

Total (exclude the hospitals)

170/25*

20

Note:

1               70dB(A) for residential dwellings, 55dB(A) for hospitals and 65dB(A) for schools

*              denotes classroom

 

Mitigation of Adverse Environmental Impacts

 

Construction Phase

 

Good Site Practice

 

4.40          Although the noise mitigation effects are not easily quantifiable and the benefits are specific to the site and operating conditions, good site practices are easy to implement and do not impact upon the works schedule.  The following site practices should be followed during each phase of construction:

 

·        Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.

 

·        Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction program.

 

·        Mobile plant, if any, should be sited as far away from NSRs as possible.

 

·        Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum.

 

·        Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

 

·        Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

 

Adoption of Quieter Plant

 

4.41          In order to reduce the excessive noise impacts at the affected NSRs, quieter plants are recommended.  The type of quiet PMEs adopted in this assessment is not a must that the Contractors have to use specific items of plant for the construction operations.  The Contractors are allowed to use other type of quiet PMEs, which have the same total SWL, to meet their need.

 

4.42          The silenced PMEs adopted in the assessment were taken from the BS5228: Part 1:1997, which are known to be in Hong Kong (Appendix 4.3c).  It should be noted that the silenced PME can be found in Hong Kong.  However, the EPD, when processing a CNP application, will apply the SWL of a particular plant specified in the GW-TM unless the noise emission of a particular piece of equipment can be validated by a certificate or demonstration.  With the implementation of the silenced PMEs, the noise levels at the representative NSRs have been predicted and are given in Appendix 4.6b.

 

4.43          With the use of the quiet PMEs, a noise reduction of 2-8 dB(A) could be achieved, depending on the type of construction activities.  The results show that cumulative construction noise levels arising from various construction activities of the project at all the NSRs would comply with the EIAO-TM noise criteria, except NSRs VTC1, VTC3, NSC1, and N3H.  Therefore, further noise mitigation measures are required for these NSRs.

 

Adoption of Quiet PMEs and Movable Noise Barriers

 

4.44          With the use of quiet PMEs, exceedances of the EIAO-TM noise criteria are still predicted at the representative NSRs VTC1, VTC3, NSC1, and N3H.  Therefore movable noise barriers are recommended in order to screen the noise from a particular plant.  It is anticipated that a movable noise barrier with a skid footing and a cantilevered upper portion located close to the noise generating part of the PME such that the line of sight could be blocked by the barriers when viewed from NSRs, can produce at least 10 dB(A) screening for stationary plant and large plant such as vibratory poker, compactor and air compressor and 5 dB(A) for mobile plant including mobile crane, excavator, concrete pump truck, winch and roller.   The use of this measure has only been applied to the following construction activities:

 

·        Viaduct from Tai Lam Kok to Siu Lam : Piling, pile cap construction, bridge piers & abutment construction, casting of bridge beams and lifting of bridge beams

 

·        Siu Lam Interchange : relocation of CLP power sub-station, bored pile wall construction, road embankment, realignment of access road, roundabout modification, road pavement, utilities, footpath and road furniture

 

4.45          With the adoption of the quiet PMEs and movable noise barriers, a noise reduction of 1-4dB(A) would be achieved (Appendix 4.3d).  The result (Appendix 4.6c) shows that all the NSRs would comply with the noise criteria of 75dB(A) for residential uses and 70dB(A) for schools during normal school hours.  However, the use of the recommended direct mitigation measures is still insufficient to reduce the construction noise levels at the educational NSRs VTC1, VTC3 and NSC1 to below the noise criterion for schools during examination period.  Noise exceedances of the noise criterion for schools during examination period by 1 to 4dB(A) are still predicted at NSRs VTC3 (August 2003 - April 2004, June - August 2004, November 2004, September 2005 and January 2006– February 2007), VTC1 (August 2003 - April 2004 and November 2004) and NSC1 (April-December 2006 and February 2007).

 

4.46          In order to reduce the potential noise impacts on the schools during examination, further mitigation measures including restriction on the usage of operating PME and re-scheduling the construction activities are proposed.  Restriction on PME usage has been tested by limiting the number of plant used for the construction activities which may generate excessive noise levels to the educational NSRs.  The following construction activities have been chosen to reduce the number of plant in operation:

 

·        Road reconstruction from Tai Lam Kok to Siu Lam: road construction (excavation of existing pavement, road pavement, footpath and road furniture), utilities, fill slopes recompaction, cut slopes stabilization (soil nailing to cut slopes).

 

·        Reclamation at Tai Lam Kok: dredging and sand filling.

 

4.47          With the adoption of the quiet PMEs, movable barriers and restriction on the usage of operating PME (Appendix 4.3e), only around 1-2dB(A) exceedances of the noise criterion for schools during examination are predicted at the educational NSRs and the duration of the exceedances could be shortened (Appendix 4.6d).  The exceedances at VTC3 would last from August 2003 to April 2004, July to December 2006 and February 2007, at VTC1 from August 2003 to April 2004, and at NSC1 from July-September 2006.  Based on the construction programme, the noise exceedances are mainly due to the cumulative effect of some noisy construction activities in the vicinity of the NSRs.  Table 4.7 presents the duration of the exceedances and the major concurrent construction activities which lead to the exceedances.

 


Table 4.7 Duration of Exceedance of Noise Criterion for School during Examination Period

 

NSRs

Major Concurrent Construction Activities Lead to the Exceedance of Noise Criterion for Schools during Examination Period.

Duration of Exceedance of Noise Criterion for Schools during Examination Period.

VTC1

Piling works for viaduct from Tai Lam Kok to Siu Lam and dredging works at Tai Lam Kok

 

Piling works for viaduct from Tai Lam Kok to Siu Lam and seawall construction at Tai Lam Kok

 

Pile cap, bridge pier & abutment and filling works at Tai Lam Kok

 

August and September 2003

 

 

October 2003-February 2004

 

 

 

March-April 2004

VTC3

Piling works for viaduct from Tai Lam Kok to Siu Lam and dredging works at Tai Lam Kok

 

Piling works for viaduct from Tai Lam Kok to Siu Lam and seawall construction at Tai Lam Kok

 

Pile cap, bridge pier & abutment and filling works at Tai Lam Kok

 

 

Fill slope recompaction and soil nailing to cut slopes (cut slopes stabilization) for road reconstruction from Tai Lam Kok to Siu Lam

 

August and September 2003

 

 

October 2003-February 2004

 

 

 

March-April 2004

 

 

 

July -December 2006 and February 2007

NSC1

Fill slopes recompaction and soil nailing to cut slopes (cut slopes stabilization) along the existing Castle Peak Road from Tai Lam Kok to Siu Lam

 

July-September 2006

 

4.48          Rescheduling of the concurrent construction activities as shown in the above table to avoid simultaneous operating during the examination period is required so as to reduce the potential noise impact to comply with the noise criterion of 65dB(A). 

 

Operational Phase

 

4.49          In order to reduce the traffic noise impacts on the affected NSRs, a mitigation package (Mitigation 1) has been developed and evaluated for effectiveness.  The recommended noise mitigation measures are described below: 

 

·        A 5 m high vertical barrier of about 430 m located at westbound carriageway of the Castle Peak Road viaduct (CH 170 – CH 600);

·        A 3.5m high vertical barrier of about 92 m located at northbound carriageway of the slip road to the Siu Lam Interchange;

·        A cantilevered barrier (5.5m high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of around 25m located behind the footpath of Castle Peak Road; and

·        A cantilevered barriers (5.5m high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) located of around 795m at eastbound carriageway of the Castle Peak Road viaduct (CH186 – CH978)

 

4.50          Locations of the above recommended noise barriers are shown in Figure 4.3

 

4.51          With the adoption of the recommended mitigation measures, the noise levels at the representative NSRs have been predicted and are presented in Appendix 4.7a.  Mitigated traffic noise levels at the NSRs are in the range of 62 to 82 dB(A).  The results show that the noise levels from new roads at N1B, N4H, VTC2 and VTC3 could be reduced to be within the noise criteria and contribute less than 1dB(A) to the overall noise levels.  While the new road noise levels at N2F and N3H would still exceed the noise criteria of 55dB(A) for hospitals and 70dB(A) for residential by 1-3dB(A).  Hence, further mitigation measures are considered in order to reduce the new road noise levels at these NSRs to meet the noise criteria.

 

4.52          According to the Noise Insulation Works for Improvement to Castle Peak Road from Siu Lam to So Kwun Tan, noise insulation works (NIW) have been installed for all the affected units of the CSD Married Staff Quarters (H3H and H4H) in the form of air conditioning and acoustic insulation.  Nevertheless, direct mitigation measures on roads would also be considered in this study.

 

Further Mitigation Measures

 

4.53          With the adoption of the recommended mitigation measures (mitigation 1), the new road noise levels at N3H and N2F would still exceed the noise criteria.  In view of the modeling result, it is shown that the new road noise exceedances at N2F and N3H are mainly attributable to traffic noise from the proposed Siu Lam Interchange.  In order to reduce the new road noise levels at these NSRs, a range of noise mitigation measures such as more extensive noise barriers/enclosures, low noise road surfacing and realignment of the roundabout at Siu Lam have been considered. 

 

Realignment of Roundabout

 

4.54          It is considered that relocation of the roundabout at Siu Lam Interchange further away from N3H is not feasible due to the following constraints in sitting the proposed roundabout:

 

·        Interface with PWP item no. 6541 TH (Section 2.32);

·        Castle Peak Road flyover over Tuen Mun Road (Section 2.33);

·        Access road leading to CSD staff quarters (Section 2.34);

·        CLP power sub-station (Section 2.35); and

·        CSD septic tank (Section 2.36).

 

4.55          The one selected which is a compromised layout taking into account of the aforementioned constraints, which were approved by HyD, TD and CSD.

 

4.56          Alternative layout of the roundabout (Option 1B) as described in Section 2.51 is also considered because this layout would allow room for erecting noise barrier at the western periphery of the roundabout to screen out traffic noise from the roundabout.  The similar set of noise mitigation measures recommended in Mitigation 1 has been tested for this alternative layout.  Owing to the absence of the CSD access road exit at the roundabout, a cantilevered barrier is allowed to be erected at the western periphery of the roundabout (Figure 4.4).  The result (Appendix 4.7b) indicates that the new noise levels at N3H and N2F would still exceed the noise criteria by 1-2dB(A) and 1-3 dB(A), respectively.  Considering that there would be safety concern at the junction where the access road join the slip road to Tuen Mun Road, the alternative layout is not considered.

 

Low Noise Road Surfacing

 

4.57          A Guidance Notes on Noise Reducing Road Surfacing (2nd Draft) have been developed by a Steering Group chaired by the Deputy Director of HyD and comprised representatives from Research and Development Division of HyD, PELB, TB and EPD.  According to the Guidance Notes, noise reducing road surface should be applied for low speed roads (<50km/hr) subject to the following conditions:

 

·        Not on inclined roads;

·        No sharp bend in road geometry

·        Average annual daily traffic not exceeding 18,500 in traffic volume and percentage of commercial vehicles not exceeding 35%; and

·        Not on roads where a minimum crossfall of 2.5% cannot be practically achieved to drain water to roadside gullies effectively.

 

4.58          In addition, as low noise road surfacing has high air void content and is susceptible to damage when subjected to acceleration, braking and turning movements (when approaching or leaving roundabouts) particularly on inclined local roads.

 

4.59          For the proposed CPR, the traffic speed at the roundabout and the slip road would be 50kph, which is classified as low speed roads.  Since the slip road is inclined at more than 1% and the roundabout will have sharp bend in road geometry, low noise road surfacing (LNRS) is not appropriate to be applied for the roundabout and the slip road as well as the section of CPR approaching the roundabout.  Hence, LNRS is not considered for the roundabout and the slip road at the Siu Lam Interchange.

 

More Extensive Noise Barriers/Enclosures

 

4.60          A more extensive noise mitigation package (Mitigation 2) has been developed so as to abate the traffic noise impact on the CSD Married Staff Quarters and Siu Lam Hospital.  The mitigation measures are recommended as follows:

 

·        A cantilevered barriers (5.5m high vertical barrier with a 5m cantilever at 45 degrees to the horizontal) of around 25m located behind the footpath of Castle Peak Road;

·        A cantilevered barriers (5.5m high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of around 15m located at northbound carriageway of the slip road to the Siu Lam Interchange;

·        A full enclosure of around 76 m at the slip road to the Siu Lam Interchange (CH102-CH178);

·        A full enclosure of around 175 m at the Castle Peak Road viaduct (CH175-CH350);

·        A cantilevered barriers (5.5m high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of around 604m located at eastbound carriageway of the Castle Peak Road viaduct (CH350 – CH954);

 

4.61          Locations of the above recommended noise barriers are shown in Figure 4.5.

 

4.62          With the adoption of the Mitigation 2, mitigated traffic noise levels at the NSRs have been predicted and are given in Appendix 4.7a.  The mitigated noise levels at the NSRs are predicted to range from 62 to 82 dB(A).  The result shows that the adoption of the proposed mitigation measures could reduce the new road noise levels at all NSRs to be within the EIAO-TM noise criteria of 55dB(A) for hospitals, 65dB(A) for schools and 70dB(A) for residential.  In addition, the mitigated new road levels would contribute less than 1dB(A) to the overall noise levels.  Although the overall noise levels at all NSRs would still exceed the EIAO-TM noise criteria, the exceedances are mainly attributable to the existing roads.  Any further mitigation applied to the new road would not be effective to protect the NSRs to be within the criteria.  Hence, no further mitigation measures are considered.

 

Evaluation of Residual Environmental Impacts

 

Construction Phase

 

4.63          With the implementation of all appropriate and practical mitigation measures, the cumulative construction noise levels at all the residential NSRs would comply with the EIAO-TM noise criteria of 75dB(A) and hence no residual impact on the residential NSRs is anticipated. 

 

4.64          For the educational NSRs (VTC1, VTC2 and NSC1), the use of the recommended direct mitigation measures would protect them against noise exceedance of the noise criterion for schools during normal hours.  However, it is still insufficient to protect the educational NSRs against noise exceedances of the criterion for school during examination period.  In order to reduce the potential noise impacts on the schools, restriction on the usage of operating PME and re-scheduling of construction activities to avoid concurrently operating are required during the examination period.

 

4.65          A summary of the maximum cumulative construction noise levels from various construction activities of the project at the representative NSRs is shown in Table 4.8.

 


Table 4.8 Summary of Maximum Cumulative Construction Noise Levels at the Representative NSRs

 

NSR

Description

Criteria

dB(A)

Maximum Predicted Construction Noise Levels dB(A)

Unmitigated

Quiet Plant

Quiet Plant + Movable noise barrier

Quiet Plant + Movable Noise Barrier + Restriction on Usage of Operating PME

KLT

Ka Loon Tsuen

75

77

71

--

--

VTC3a

Seamen’s Training Centre

70 (65)

78b

72 b

70 b

67 b

VTC1a

Seamen’s Training Centre

70 (65)

75b

70 b

69 b

67 b

VH1

Village house at Wu Uk Tsuen

75

79

73

--

--

NSC1a

Customs and Excise Training School

70 (65)

77b

70 b

69 b

66 b

N1B

Siu Lam Psychiatric Centre

70

78

72

70

--

N2A

Siu Lam Hospital (Library)

70

76

70

--

--

N2F

Siu Lam Hospital

70

79

73

70

--

AP1

Correctional Services Department Staff Quarter

75

79

73

--

--

N3H

Correctional Services Department Married Staff Quarters

75

84

78

75

--

N4H

Correctional Services Department Married Staff Quarters

75

72

--

--

--

Note:   a     Denotes school

b         indicate an exceedance of the EIAO-TM noise criteria of 65dB(A) for schools during examination period

Bold figures indicate an exceedance of the EIAO-TM noise criteria of 75 dB(A) for Residential uses and 70dB(A) for schools during normal school hours

 

 

Operational Phase

 

4.66          Two packages of direct mitigation measures (Mitigation 1 and Mitigation 2) has been developed and evaluated.  The result verified that Mitigation 2 is preferable as the recommended mitigation measures could abate the new road noise levels at all the NSRs to comply with the EIAO-TM noise criteria and the mitigated new road noise levels would contribute less than 1dB(A) to the overall noise levels.  The effectiveness of the noise mitigation measures recommended in Package 2, in terms of number of NSRs which will either be protected or benefited (by at least 1dB(A)), is summarised in Table 4.9.

 


Table 4.9    Effectiveness of Recommended Mitigation Measures

 

NSR

Description

Estimated Number of Residential Dwellings/Classrooms

Exceed the Noise Criteria1

Exceed the Noise Criteria with New Roads Contribution >1dB(A)

Protected within Criteria1

Benefited (by ³ 1dB(A)

N2A

 Siu Lam Hospital (Library)

Whole block

0

0

0

N2F

Siu Lam Hospital

Southern block

0

0

0

N3H & N4H

Correctional Services Department Married Staff Quarters

30

0

2

30

N1B

Siu lam Psychiatric Centre

Whole blocks

0

0

0

NSC1

Customs and Excise Training School

15*

0

0

0

VH1

Village house at Wu Uk Tsuen

5

0

0

0

VTC1, VTC2 & VTC3

Seamen’s Training Centre

10*

0

0

0

KLT

Village House at Ka Loon Tsuen

5

0

0

0

PC1

Poseidon Coast

120

0

0

0

AP1

Correctional Services Department Staff Quarter

10

0

0

0

CDA

Comprehensive Development Area at Tai Lam Chung

 

0

0

0

0

 

Total

170/25*

0

2

30

Note:

1               70dB(A) for residential dwellings and 65dB(A) for schools

*              denotes classroom

 

4.67          As shown in the above table, the use of the mitigation measures could protect about 2 residential dwellings against noise criteria exceedances and about 30 residential dwellings could be benefited by more than 1dB(A) noise reduction.  No NSR exceeds the noise criteria with new roads contribution greater than 1dB(A).  This indicates that the exceedances are mainly attributable to the existing roads.  Any further mitigation applied to the new road would not be effective to protect the NSRs to be within the criteria.

 

4.68          The residual impacts have been assessed against the noise insulation criteria (Section 4.12), and the result is summarized in Appendix 4.7c.  The results show that all the residential dwellings, educational institutions and hospitals would not meet the criteria and therefore ITR in the form of window insulation and air conditioning would not be required. 

 

Construction Activities during Restricted Hours

 

4.69          As mentioned in Section 4.22, the dredging works will be carried out during the restricted hours (1900-2300 and 2300-0700) and therefore will be under the control of the GW-TM.  An indicative assessment has been undertaken to investigate the potential noise impact arising from the dredging works which are expected to be performed in restricted hours in accordance with the criteria and methodology stated in the GW-TM.  As discussed in Section 4.6, the construction noise criteria of 65dB(A) in the evening and 50dB(A) at night are adopted in this assessment.

 

4.70          Apart from KLT and VH1, all the NSRs are located at a distance of more than 500m from the dredging area.  Hence, only KLT and VH1 were selected for this indicative assessment.  The PMEs and the total SWL for dredging works are provided in Appendix 4.3b.  The construction noise levels at these two NSRs during the restricted hours have been predicted and the results are presented in Table 4.10.

 

Table 4.10 Construction Noise Levels at Representative NSRs During Restricted Hours (Unmitigated)

 

NSR

Predicted Noise Level, dB(A)

KLT

58

VH1*

51

Note: *          assumed 10dB(A) reduction due to topographical screening

 

4.71          As indicated in Table 4.10, the noise levels at both NSRs are predicted to comply with the noise criterion of 65dB(A) in the evening, whereas exceed the nighttime noise criterion of 50dB(A).  In order to reduce the noise impact arising from the dredging activities during nighttime, it is recommended to reduce the number of barges from four to two and grab dredgers from two to one during the dredging activities at night (2300-0700) (Appendix 4.3e).   Table 4.11 shows the predicted noise levels at the NSRs with the implementation of restriction on the usage of operating PME.

 

Table 4.11 Construction Noise Levels at Representative NSRs During Restricted Hours (Mitigated)

 

NSR

Predicted Noise Level, dB(A)

KLT

55

VH1*

48

Note: *          assumed 10dB(A) reduction due to topographical screening

 

4.72          As indicated in Table 4.11, the mitigated noise level at VH1 is predicted to comply with the nighttime noise criterion of 50dB(A), whereas the mitigated noise level at KLT is still predicted to exceed the nighttime noise criterion by 5dB(A).  Hence, it is recommended that the dredging works is required to avoid undertaking at night along the coastal area between Ka Loon Tsuen and Tai Lam Kok.  According to the preliminary construction programme, there will be a total of around 104 days allowable for the dredging works from Ka Loon Tsuen to Tai Lam Kok.  If nighttime dredging (2300-0700) is prohibited, the daily dredging rate will be reduced from 3000 m3 per day (assumed 24 hours) to 2000 m3 per day.  It is estimated that the volume of material to be dredged from Ka Loon Tsuen to Tai Lam Kok is 196,245 m3.  With the daily dredging rate of 2000 m3 per day, the time required for the dredging works from Ka Loon Tsuen to Tai Lam Kok will be around 98 days which is less than the allowed period of 104 days.  Hence, it is considered feasible to avoid dredging works undertaking at night along the coastal area between Ka Loon Tsuen and Tai Lam Kok based on the preliminary construction programme.

 

4.73          It should be noted that the result of the construction noise impact assessment for restricted hours is for indicative purpose only.  The Noise Control Authority will process any CNP application, based on the NCO and the relevant TMs in addition to considering the contemporary situations/conditions.

 

Environmental Monitoring and Audit

 

Construction Phase

 

4.74          An Environmental Monitoring and Audit (EM&A) programme is recommended to be established according to the predicted occurrence of noisy activities.  All the recommended mitigation measures should be incorporated into the EM&A programme for implementation during construction.  Details of programme are provided in a stand-alone EM&A Manual.

 

Operational Phase

 

4.75          It is recommended that traffic noise monitoring is carried out at representative NSRs within one year of the road opening.  The recommended mitigation measures, monitoring procedures and locations are presented in the EM&A Manual.

 

Conclusion

 

Construction Phase

 

4.76          Noise arising from the construction activities of the project would have potential impact on the noise sensitive receivers (NSRs) located in the vicinity of the work sites.  Unmitigated cumulative construction noise levels at the representative NSRs have been predicted, which are in the range of 45 dB(A) to 84 dB(A).  The results indicate that the cumulative noise levels at most of the NSRs would exceed the EIAO-TM noise criteria.

 

4.77          Sufficient noise control measures would be required to mitigate the noise levels to the EIAO-TM noise criteria.  Mitigation measures recommended include good site practices, the use of quiet plant, movable noise barriers and restriction on the usage of operating plant. 

 

4.78          With the adoption of the recommended control measures, all the residential NSRs could be protected against the construction noise impact.  For the educational NSRs (VTC1, VTC3 and NSC1), the use of the recommended direct mitigation measures would protect them from exceedance of the noise criterion for schools during normal hours, whereas it is still insufficient to protect them from exceedance of the noise criterion for school during examination period.  In order to reduce the potential noise impacts on the schools, restriction on the usage of operating PME and re-scheduling of construction activities to avoid concurrently operating are required during the examination period.

 

Operational Phase

 

4.79          Potential road traffic noise impact associated with the project has been assessed for the maximum traffic flows in 2022.  The modeling results indicate that about 170 residential dwellings and 25 classrooms are likely to experience noise levels exceeding the EIAO-TM traffic noise criteria, if unmitigated.  Hence direct mitigation measures would be required.

·         

4.80          With the implementation of the recommended direct mitigation measures, the mitigated noise levels from new roads at all NSRs are predicted to be below 70dB(A) and the new roads contribution would be less than 1dB(A) to the overall noise levels.  It is estimated that about 30 residential dwellings could be benefited by more than 1dB(A).

 

4.81          The residual impacts have been assessed against the noise insulation criteria.  The results show that all residential dwellings, schools and hospitals would not meet the noise insulation criteria as described in Section 4.12, and therefore, indirect technical remedies in the form of window insulation and air conditioning would not be required.