9.
LANDSCAPE AND VISUAL IMPACT ASSESSMENT
9.1
A Landscape and Visual Impact
Assessment (LVIA) of the Castle Peak Road proposed upgrading works (hereafter
referred to as the Project), located between Siu Lam and Ka Loon Tsuen was
conducted by Design Research Unit HK Ltd. between June 2000 and July 2001. This
section summarises the assessment findings.
9.2
The objectives of the LVIA are to:
·
assess the potential landscape and
visual impacts associated with the construction and operation of the upgrading
works;
·
recommend mitigation measures for
incorporation into the design to minimise potential impacts and to meet the
Hong Kong Government's environmental planning intentions and the Hong Kong
Planning Standards and Guidelines (HKPSG);
·
evaluate residual landscape and visual
impacts assuming landscape mitigation measures are incorporated into the
Project;
·
identify key urban and landscape
planning issues which should be examined in further detail during detailed
design.
9.3
The LVIA methodology is in accordance
with the Project Brief and Annex 18 of Technical Memorandum on Environmental
Impact Assessment Process (hereafter referred to as “TM”) entitled “Guidelines
for Landscape and Visual Impact Assessment”.
The main stages of the LVIA are follows:
·
baseline study of landscape and visual
resources;
·
review of planning and development
control framework;
·
landscape impact assessment during
construction and operation;
·
visual impact assessment during
construction and operation;
·
recommendations for landscape
mitigation design measures.
·
assessment of residual impact and
conclusion on the acceptability of the Project.
9.4
The baseline study identified and
examined the existing landscape and visual resources within the study area,
particularly between the Siu Lam Interchange and Ka Loon Tsuen.
9.5
Landscape resources considered
included topography, woodland types, other vegetation, built forms, settlement
patterns, land use, scenic spots and details of local streetscapes. Reference
is made to the EIA Final Assessment Report, (Southern Section) for Route 10 –
North Lantau to Yuen Long Highway, Investigation and Preliminary Design
Assignment, for which a large section between Siu Lam and Tai Lam Chung is
complementary. The baseline study describes the landscape resources by
identifying broadly homogenous landscape units of a similar character. The landscape character was rated low,
moderate or high depending not only on the quality of elements present but also
to its sensitivity to change and its importance at a local, district, regional
or international level.
9.6
Visual resources considered were
typical viewpoints, location and direction of views towards the project. A viewshed (refer to Figure 9.3) was
established which approximately defined the extent of visual influence of the
project and, therefore, of the potential visual impacts. Definition of the
extent of the viewshed was based on desktop study and site investigation. Sensitive visual receivers who would be
present at typical viewpoints and likely to be affected by the Project were
identified within the viewshed. Sensitive visual receivers (SVRs) are
individuals or groups of who are sensitive to changes in the visual
environment. The Environmental
Guidelines for Planning in Hong Kong defines sensitive users as “land uses
which, by virtue of the nature of the activities thereon….are susceptible to
the influence of residual or physical changes generated by polluting uses”.
9.7
The next stage was a review of the
planning and development control framework.
This information was mapped and analysed to provide an insight to the
future outlook of the area affected and the way the Project would fit into its
wider context. This information
reviewed included:
·
land with landscape related zoning on
the Outline Zoning Plan (OZP);
·
landscape planning and visual
guidelines already established in other planning documents including the EIA
for Route 10 Southern Section.
9.8
The following stage was to assess
impacts on the landscape and visual resources during construction and
operation. The impact assessments allow predictions to be made about the likely
levels and significance of landscape and visual impacts.
9.9
The
assessment of landscape impacts will result from:
·
Identification of the sources of
impact and their magnitude that would be generated during construction and
operation of the project;
·
Identification of the principal
landscape impacts primarily in consideration of the degree of change to the
baseline conditions. The impacts are considered systematically in terms of
landscape elements, the project and its context.
9.10
The overall landscape impact is a
product of the following:
·
The landscape character and its
quality;
·
The sensitivity of the landscape in
accommodating change;
·
Source, nature and magnitude of impacts;
·
The degree of change caused by the
impacts to the existing landscape;
·
Significance of the change in
consideration of the local and regional areas and other developments;
·
Cumulative effects with other
proposals;
·
Identification of vegetation of significant
value which should be conserved.
9.11
The sensitivity / quality of the
landscape will be assessed as follows:
·
High: e.g. important components or
landscape of particularly distinctive character susceptible to small changes;
·
Moderate: e.g. a landscape of
moderately valued characteristics reasonably tolerant to change;
·
Low: e.g. a relatively unimportant
landscape which is able to accommodate extensive change.
9.12
The magnitude of change in the
landscape is as follows:
·
High – notable change in the landscape
characteristics over an extensive area ranging to very intensive change over a
more limited area;
·
Moderate – moderate changes to a local
area;
·
Low – virtually imperceptible changes
in any components.
9.13
The system for the assessment of
landscape impact is summarised in Tables 9.1 and 9.2. The significance threshold of landscape impact is derived from
the combined analysis of the magnitude of change and the landscape’s quality
and sensitivity to change. The matrix
in Table 9.1 indicates how the significance threshold of landscape impact is
derived. Table 9.2 explains the terms
used to in Table 9.1.
Magnitude
of Change
|
Table
9.1 Assessment of Landscape Impact
|
High
|
Moderate Impact
|
Moderate / Significant
Impact
|
Significant Impact
|
Moderate
|
Slight / Moderate Impact
|
Moderate Impact
|
Moderate / Significant
Impact
|
Low
|
Slight Impact
|
Slight / Moderate Impact
|
Moderate Impact
|
|
Low
|
Moderate
|
High
|
Sensitivity / Quality
|
Table 9.2
Adverse / Beneficial Impacts of Landscape Impact
|
Significant:
|
Moderate:
|
Slight:
|
adverse
/ beneficial impact where the proposal would cause significant degradation or
improvement in existing landscape quality.
|
adverse
/ beneficial impact where the proposal would cause noticeable degradation or
improvement in existing landscape quality
|
adverse / beneficial
impact where the proposal would cause a barely conspicuous degradation or
improve in existing landscape quality.
|
9.14
This analysis of the significance
threshold of landscape impact will apply in the majority of situations, however
in certain cases a deviation may occur e.g. the impact may be so major that a
significant impact may occur to a low quality element.
9.15
The assessment of potential visual impacts will result from:
·
Identification of the sources of
visual impact and their magnitude that would be generated during construction
and operation of the scheme;
·
Identification of the principal visual
impacts primarily in consideration of the degree of change to the baseline
condition.
9.16
The significance threshold of visual
impact will result from the following:
·
the context and proximity of the SVRs’
location to the project;
·
other views available from the SVRs’
location;
·
the number of people normally present
at a SVR location;
·
the sensitivity of the SVRs (for
example, resident, working, studying, etc);
·
the frequency and length of the view
of the proposed scheme from the SVRs’ location;
·
the quality and sensitivity of the
existing view from the SVRs’ location and its ability to absorb change;
·
the magnitude of change brought about
by the project in relation to the overall view from the location of each SVR.
9.17
The magnitude of change to views from
SVRs is classified as follows:
·
High: e.g. the majority of viewers
affected and/or major changes to the view;
·
Moderate: e.g. many viewers affected
and/or moderate change in view;
·
Low: e.g. very few viewers affected
and/or minor change in view.
9.18
The significance threshold of visual
impact is rated in a similar fashion to the landscape impact and is illustrated
in Tables 9.3 and 9.4 below.
Magnitude of Change
|
Table 9.3 Assessment of Visual Impact
|
High
|
Moderate Impact
|
Moderate / Significant Impact
|
Significant Impact
|
Moderate
|
Slight / Moderate Impact
|
Moderate Impact
|
Moderate / Significant
Impact
|
Low
|
Slight Impact
|
Slight / Moderate Impact
|
Moderate Impact
|
|
Low
|
Moderate
|
High
|
Sensitivity / Quality
|
Table 9.4
Adverse/Beneficial Impacts of Visual Impact
|
Significant:
|
Moderate:
|
Slight:
|
adverse/beneficial
impact where the proposal would cause significant degradation or improvement
in existing landscape quality.
|
adverse/beneficial
impact where the proposal would cause noticeable degradation or improvement
in existing landscape quality
|
adverse/beneficial
impact where the proposal would cause a barely conspicuous degradation or
improve in existing landscape quality.
|
9.19
The next stage of the study following
impact assessment is to recommend
mitigation measures. The
identification of the landscape and visual impacts will highlight those sources
of conflict requiring design solutions or modifications to reduce impacts, and
if possible absorb the development and associated activities into the
surrounding landscape. These mitigation efforts should consider factors
including :-
·
Woodland, tree and shrub planting to
new or disturbed slopes, amenity strips, highway reservations and adjacent to
any proposed structures;
·
Contouring of new slopes to blend with
existing topography in a natural manner;
·
Earth mounding and screening;
·
Highlighting unacceptable impacts and
considering alternative proposals;
·
Hard landscape elements;
·
Significant landscape elements.
9.20
The above will result in the
formulation of landscape mitigation proposals which will as far as possible
help to alleviate the previously identified landscape and visual impacts.
9.21
The final stage of the LVIA study is
to assess the significance of the
residual impacts of the study assuming landscape mitigation measures are
incorporated into the design. The
landscape and visual impacts were then classified into five levels of
significance based on criteria in Annex 10 of the TM, as summarised below:
·
The impacts are is beneficial
if the project will complement the landscape and visual character of its setting, will follow the
relevant planning objectives and will improve the overall quality and visual quality of
the study area;
·
The impacts are is acceptable if the assessment
indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the project, or no
interference with key views;
·
The impacts are
acceptable if potential adverse effects are eliminated, reduced or offset to a
large extent by design mitigation measures;
·
The impact is acceptable with mitigation
measures if there will be some adverse effects, but these
can be eliminated, reduced or offset to a large extent by specific measures;
·
The impacts are is unacceptable if there
are excessive the adverse effects which cannot be
practically mitigated are considered too excessive and are unable to
mitigate practically.;
·
The impact is undetermined if significant
adverse effects are likely, but the extent to which they may occur or may be
mitigated cannot be determined from the study. Further detailed study will be
required for the specific effects in question.
Project Description
9.22
The boundary for the assessment of
landscape impacts was defined in the study brief as 500 m either side and along
the full length of the proposed new road alignment (see Figure 9.1A). The
existing Castle Peak Road through Tai Lam Chung, although in the project area,
is not intended to have improvement works in this area. The boundary for assessment of visual
impacts was defined by site inspection and is shown as a viewshed boundary on
Figure 9.3.
9.23
The proposed elements of the Project
is described in detail in earlier sections of the EIA (Sections 2.1-2.2). There are a number of proposed elements
which are particularly relevant to the LVIA as they will affect landscape and
visual resources (refer to Figures 9.1A and 9.1B):
·
The new viaduct at the mouth of the
Tai Lam Chung Nullah
·
Modifications to the junction at Siu
Lam Interchange to incorporate a new roundabout and ramps.
·
The new seawall and reclamation
extending from Tai Lam Kok to Ka Loon Tsuen
·
Slope treatment to the existing
embankments and hillside separating Castle Peak Road and Tuen Mun Road
9.24
The design of the engineering elements
has been presented to the Advisory Committee on Bridges and Associated
Structures (ACABAS) and the comments received will be incorporated into the
design planning. During detailed design, ACABAS shall be consulted on the more
detailed aspects of the appearance of structures, particularly material
finishes and colour schemes.
Baseline Study of Landscape and Visual Resources
9.25
The study area was categorised into
distinct and separate landscape character areas (LCAs). Within each character
area the baseline information is homogenous with regard to local topography,
natural coastline, woodland extent and type, other vegetation, terrain,
habitation and settlement patterns, streetscapes, water availability, cultural
styles and land use. SVRs within each LCA were also identified. The areas are described in the following
paragraphs (refer to Figures 9.2A, 9.2B, and 9.2C and Tables 9.5 and 9.6).
Ma Wan Coast (LCA1)
9.26
A narrow stretch of coastal land, sea
and tidal flats segregated from surrounding natural landscape areas by both
Castle Peak Road and Tuen Mun Road comprising approximately 2.0 hectares of low habitat quality
backshore vegetation (see Section 7 for detailed information). The area
is extremely exposed to winds and salt spray and covers the rock, sands and
shingle found between the low and high tide lines. Occasional strand line
planting can be found within sheltered pockets. Backshore vegetation is made up
of common Hong Kong coastal species, dominated by Clerodendrum inerme and Vitex
rotundifolia and including Atalantia buxifolia, Canavalia maritima and Hibiscus
tiliaceus.
9.27
The sensitivity/quality of this LCA is
considered to be high, as it is particularly distinctive coastal landscape
susceptible to relatively small changes.
9.28
A single SVR location was identified
within the visual catchment between Tai Lam Kok and Ka Loon Tsuen (refer to
Figure 9.3):
·
Ma Wan boat traffic (SVR1);
Transport corridor (LCA2)
9.29
The Tuen Mun and Castle Peak Roads are
distinct man made environments, with artificial slopes and 0.5ha of amenity
planting. The ecosystems are poorly developed. Roadside tree planting has been
thorough at the Siu Lam interchange, but consists almost exclusively of
plantation species of Acacia confusa, Casuarina spp. and Eucalyptus spp.
Roadside tree planting along Castle Peak Road is extensive and acts to restrict
views beyond the roadside. Planting does include some fine examples of Albizia
lebbeck which has also become the most successful colonising tree in the area.
Typical roadside planting has been made immediately next to Tuen Mun Road on
the reclamation area across the Tai Lam Chung Channel which includes
predominantly Acacia confusa and Macaranga tanarius.
9.30
The sensitivity/quality of this LCA is
considered to be low.
9.31
A single SVR location has been
identified within the visual catchment between Siu Lam and Ka Loon Tsuen within
the transport corridor (refer to Figure 9.3):
·
Tuen Mun Road and Interchange traffic
(SVR2)
Siu Lam Ridge (LCA3)
9.32
A ridge separates Siu Lam Valley from
the neighbouring Tai Lam Chung. Parts
of the lower slopes have been developed and Tuen Mun Road has been carved
through a pass at the Siu Lam Interchange. The areas surrounding both sides of
Tuen Mun Road are littered with government and institutional buildings,
resulting in some limited degradation of the surrounding green belt
environment.
9.33
The sensitivity/quality of this LCA is
considered to be medium, as it is a landscape which has retained some natural
value on the upper ridge slopes despite peripheral modification and the
presence of buildings.
9.34
A number of SVR locations were
identified within the visual catchment between Siu Lam and Tai Lam Chung (refer
to Figure 9.3):
·
Siu Lam Hospital (SVR3);
·
Siu Lam Psychiatric Centre (SVR4);
·
Siu Lam Police Quarters (SVR5).
·
Poseidon Coast Residential Development
(SVR6)
Tai Lam Chung Valley (LCA4)
9.35
The modern village of Tai Lam Chung
Tsuen is oriented to the south-west, towards the sea. A temple is present in
the village. The watercourse running through the base of the valley serves as
an outflow for the Tai Lam Chung Reservoir at the valley head. In general the
LCA has the following characteristics:
·
The valley landscape is heavily
disturbed by development, roads and structures;
·
Interspersed amongst the development
are fragments of heavily vegetated woodland trees ranging between 6 – 12 metres
in height, which the ecological assessment has described as a typical young
secondary woodland common in Hong Kong. The tree species include many common
Hong Kong woodland species (see Appendix 7.2);
·
Shrubland was found in the northern
parts of the valley and comprising similar species to the woodland, but only
1.5 to 3 metres in height.
·
Tree planting is typically at roadside
with individual stands of some stature
9.36
The open nature of the valley floor is
lost at ground level due to a variety of elements such as trees, buildings and
structures. The outflow of the Tai Lam Chung reservoir has been canalised
causing loss of existing or potential habitats and generating poor visual
attributes. Roadside tree planting has helped to significantly improve the
outlook and structure of the landscape setting.
9.37
The sensitivity/quality of this LCA is
considered to be medium, owing to the presence of urban development within a
partially vegetated setting.
9.38
Two SVR locations were identified
within the visual catchment of Tai Lam Chung (refer to Figure 9.3):
·
Seaman’s Training Centre (SVR7);
·
Future residential buildings at Tai
Lam Chung Comprehensive Development Area (CDA) (SVR8).
9.39
The village areas of Tai Lam Chung
itself and surrounding hamlet and building, including Wu Uk Tsuen, clusters
were not designated as an SVR since the low-lying character of the valley
precludes distant views to the Project owing to intermediate topography,
development and vegetation. Similarly the nearby Customs and Excise Training
School is hidden behind existing trees on Castle Peak Road. However future CDA
residential buildings between the nullah and Tai Lam Ridge will have sweeping
views over the valley and out to sea in the distance and this area is therefore
classified as an SVR.
Tai Lam Ridge (LCA5)
9.40
This ridge forms a high backdrop
behind Tai Lam Valley and Tuen Mun Road, reaching over 170 metres at the local
crest. The ridge is undeveloped and footpaths connecting with the adjacent Tai
Lam Country Park are popular with local hikers. The sides of the ridge are
steep and vegetated primarily by rough grass and scrub and unlike many of the
hills in the area have not been eroded. The convex nature of the landform,
coupled with the vegetation cover preclude views of the roads below and these
only become visible for occasional distant views across the valley.
9.41
Three herb layer species of
conservation interest were identified in the ecological survey within the grass
/ shrubland of the steep slopes of the south facing hillside. They were
Alloteropsis semialatus and Thysanotus chinensis, which are both rare and
Platycodon grandiflorus, which is protected in Hong Kong.
9.42
The sensitivity/quality of this LCA is
considered to be high, as it is particularly distinctive and visually exposed
undisturbed natural coastal landscape susceptible to relatively small changes.
9.43
A single SVRs was identified within
the visual catchment of Tai Lam Ridge (refer to Figure 9.3):
·
Ridge Footpaths (SVR9).
9.44
Tables 9.5 and 9.6 summarise the
findings of the baseline studies. Table
9.6 indicates the type and distance of the viewer groups likely to be found at
each SVR.
9.45
Viewer groups at three SVR locations
(SVRs 1,2 and 9) are transitory and would not be present in the study area
permanently. Therefore they would have a lower sensitivity to change or visual
intrusion. when considered with other factors as described in 9.16.
9.46
Viewer groups at five SVR locations
are present for long periods (SVR 3, 4, 5, 6 7 and 8) and would be 150 to 500
metres away from the project. They are considered to have a higher sensitivity
to change or visual intrusion when considered with other factors as described
in 9.16.
|
LCA number
|
Name
|
Sensitivity to Change
|
LCA1
|
Ma Wan Coast
|
High
|
LCA2
|
Transport Corridor
|
Low
|
LCA3
|
Siu Lam Ridge
|
Moderate
|
LCA4
|
Tai Lam Chung Valley
|
Moderate
|
LCA5
|
Tai Lam Ridge
|
High
|
Table 9.6 Summary of Sensitive Visual Receivers
|
Location
|
Type of viewer
|
|
Sensitivity to Change and Visual Intrusion
|
|
Ma Wan Boat Traffic
|
Local commuters,
international shipping, fishing boats and tourist vessels, transitory views.
|
Adjacent
|
Low
|
|
Tuen Mun Road
|
|
|
Moderate
|
|
Siu Lam Hospital
|
Resident staff
|
250m
|
Moderate
|
|
Siu Lam Psychiatric Centre
|
Resident staff
|
400m
|
Moderate
|
|
Siu Lam Police Quarters
|
|
|
High
|
|
Poseidon Coast residences
|
Residents (Upper Level)
|
150m
|
Moderate
|
|
Seaman’s Training Centre
|
Resident staff
|
200m
|
Moderate
|
|
Tai Lam Chung CDA
|
Future Residents
|
500m
|
Moderate
|
|
Ridge Footpaths
|
Hikers, transitory views.
|
Varies from
adjacent to 2km.
|
Low
|
|
9.47
The majority of the baseline landscape
and visual resources within the study area are considered to be of local
importance for the following reasons:
·
Whilst the presence of roads,
settlements and other built forms have had a low level of immediate disruption
in a localised sense, when considered in the greater context their cumulative
effect has been a significant erosion and fragmentation of the previously
strong landscape character generated by the backdrop of the ridges of Siu Lam
and Tai Lam. Whilst the landscape resources in the study area are individually unspectacular
they are locally important owing to their cumulative effect.
·
The strong transportation links of
Tuen Mun Road and Castle Peak Road have served to compartmentalise the
landscape character and resources and have severed the natural relationship
between the Siu Lam / Tai Lam ridges and the Tai Lam Country Park with coastal
landscape. While the small part of
study area covered by Tai Lam Country Park could be considered to be of
regional importance.
·
Given the size of the study area the
SVRs are few in number compared to the other denser-populated parts of Hong
Kong such as nearby Tuen Mun.
Outline Zoning Plan
9.48
The starting point for the review of
the planning and development control framework is the Outline Zoning Plan for
So Kwan Wat (S/TM-SKM/5). This plan
forms the statutory basis for the control of the use of land, and gives insight
into the future pattern of development. In summary, the land use zones relevant
to the LVIA are as follows (refer to Figure 9.4):
·
The slopes north of Tuen Mun Road
zoned as green belt
·
The area of CDA in Tai Lam Chung
Village
·
The area zoned G/IC at the outflow of
the Tai Lam Chung Nullah which includes the Seaman’s Training Centre, Customs
and Excise Training School and Highways Department Maintenance Depot
·
The coastal hill area west of Siu Lam
Interchange zoned as G/IC
·
The coastal area below Castle Peak
Road zoned as G/IC
·
The areas accommodating the new
viaduct across the Tai Lam Chung Nullah which is outwith the boundary of the
OZP, lying within coastal waters.
·
The interchange at Siu Lam Ridge lying
within blocks of G/IC
9.49
The study found there to be no
conflict between the proposed development and the Outline Zoning Plan for So
Kwan Wat (S/TM-SKM/5).
EIA Route 10 – Southern Section
9.50
The next document reviewed was the
Environmental Impact Assessment for Route 10 (Southern Section). The linking of
the existing Tuen Mun Road to the proposed Route 10 Highway is intended to be
made via link roads which cross the Tai Lam Chung Nullah on either side of Tuen
Mun Road, starting from Brothers Point and forming viaducts over the
interchange at Siu Lam. The impact of these link roads is likely to be very
high and will have distinct implications for the impacts of the new Castle Peak
Road viaduct (Figure 9.1B).
9.51
The EIA identifies the impacts caused
to much of the area contained within this study and can be summarised as
followed :-
9.52
Route 10 link road viaducts will
result in significant adverse visual impacts on the following viewer groups:
·
Ma Wan Boat Traffic
·
Tai Lam Chung Residents
·
Siu Lam Residents
·
Ridge Trail walkers
9.53
The Route 10 link road viaducts will
cross the Tai Lam Chung Nullah well above the level of the existing Tuen Mun
Road and will be seen from most of the valley area in Tai Lam Chung, Siu Lam
and surrounding ridges.
9.54
A series of barriers and enclosures
are recommended for the Route 10 link road viaducts. The requirement for noise
barriers along substantial sections of the viaducts is potentially an added source
of visual impact by increasing the depth of the road profile.
Summary of planning and development control framework
9.55
The review of the planning and
development control framework indicated that the presence of the Project would
not weaken the planning intentions of the surrounding landscape zonings in the
study area.
Ma Wan Coast (LCA1)
9.56
There are a number of sections of
roadside planting next to Castle Peak Road and naturalised coastal margin flora
that will be severely impacted by the reclamation works and road construction.
The resulting total is a loss of 16 individual tree stands in various tree
pockets measuring 0.1ha in area between Ka Loon Tsuen and Brothers Point (refer
to Figure 9.5), and 2.0ha of coastal and backshore vegetation although these
are not considered highly developed ecosystems. The majority of developed trees
surveyed were medium to poor form and are not considered worthy of
transplantation.
9.57
The landscape resource is considered
to be of a high sensitivity as it is particularly distinctive coastal landscape
susceptible to relatively small changes. As the magnitude of change is also
going to be high the landscape impact to LCA1 will be significant and adverse.
Ma Wan Boat Traffic (SVR1)
9.58
The new high level viaducts and
seawall will contrast conspicuously with the existing surrounding physical form
characterised by the backdrop of naturally vegetated hillside (see Figure
9.6A). Visual impacts will be long term since visual mitigation of the viaducts
is not possible and will be exacerbated by the addition of noise mitigation
barriers, especially when considered cumulatively with the intended
construction of the Route 10 link roads.
9.59
The magnitude of change of view for
receivers is going to be high. This is set against a low sensitivity and will
result in a moderate adverse visual impact during
construction and operation.
Transport corridor (LCA2)
9.60
Revision of the existing road junction
at Siu Lam to a roundabout form, allowing the new viaducts to return to grade,
requires the construction of a large abutment wall and viaduct construction
through the existing plantation of trees at the centre of the junction, along
with some slope cutting work at the periphery of the road. An approximate 0.4
ha loss of existing amenity planting will result (see Figure 9.5 for location
of planting affected).
9.61
The roadside environment will undergo
the addition of new and enhanced engineering features including high mast
lighting, noise barriers, fast access ramps and roadside barriers. The
character of Castle Peak Road is likely to change significantly being a wider
and faster transport corridor receiving a much higher degree of traffic (see
Figures 9.6B and C). However there is opportunity to enhance a low value
landscape resource into something of far more benefit. Roadside planting and
amenity areas will create new habitats and improved pedestrian environments can
be created with access to the waterside which is not currently possible.
9.62
The landscape resource is considered
to be low in sensitivity to change. As the magnitude of change will be high the
landscape impact to LCA2 will be moderate
and adverse during construction
and operation.
Tuen Mun Road and Interchange traffic (SVR2)
9.63
Visual impacts to the existing
transport corridor on Tuen Mun Road will be very noticeable as the new road
alignment runs parallel and adjacent (see Figures 9.6B and C). The open views
out to sea currently enjoyed by road users will be obscured during construction
phase and further affected in the longer term, with the new viaduct sailing
overhead, columns interrupting views and deck casting shade. This will be
exacerbated on the sections where noise barriers are in place.
9.64
The magnitude of change of view for
receivers is going to be high. The sensitivity of the viewer groups is medium
owing to their large number but transitory nature. A moderate / significant adverse visual impact is predicted
during construction and operation.
Siu Lam Ridge (LCA3)
9.65
The proposed works impinge little on
the existing landscape character area and should provide slight adverse impacts during construction and operation.
Siu Lam Hospital (SVR3) / Siu Lam Psychiatric Centre
(SVR4)
9.66
The main views out to the sea will be
affected by the viaduct construction and noise mitigation measures. The noise
mitigation measures on the viaducts will create far more visual intrusion than
would otherwise be expected and will form the main visual impact. In addition, night time glare from lighting
can be expected.
9.67
The magnitude of change of view for
viewer groups at these SVRs is moderate. This is set against a moderate
sensitivity to change resulting in an moderate
visual impact during construction and operation.
Police Quarters (SVR5)
9.68
The project at Siu Lam interchange
will be in proximity to viewer groups at this SVR leading to a high magnitude
of change in this view (see Figure 9.6D). This is predominantly caused by the
noise mitigation measures proposed in front of the facility which will create
far more impact than would otherwise be expected. In addition, night time glare
from lighting can be expected. The more
distant view out across the bay to the Tai Lam Ridge to the south-east will be
compromised in the long term with the new viaducts running across the line of
the hills at eye level and their visual depth significantly increased by noise
mitigation measures. The effects of this will be seriously compounded by the
Route 10 Link Roads.
9.69
The magnitude of change of view for
viewer groups at this SVR is high. This is set against a high sensitivity to
change resulting in a significant adverse visual impact during
construction and operation.
Poseidon Coast (SVR6)
9.70
South and West facing upper floors of
the residential units look out to sea to the south. The foreground of this open view will be dominated by the
construction of new viaducts and noise barriers at Siu Lam interchange and also
in the middle and distance across Tai Lam Channel (see Figure 9.6E). This will be exacerbated by the future Route
10 link roads. Night time glare from lighting from both roads can be
expected.
9.71
The magnitude of change of view for
viewer groups at this SVR is moderate. This is set against a moderate
sensitivity to change resulting in a moderate
adverse visual impact during construction
and operation.
Tai Lam Chung Valley (LCA4)
9.72
The proposed works impinge little on
the existing landscape character area and should provide slight adverse impacts during construction and operation.
Seaman’s Training Centre (SVR7);
9.73
The viewer groups will experience a
high magnitude of change owing to dominance of the Project in the foreground.
This is set against a moderate sensitivity to change resulting in a moderate / significant adverse
visual impact during construction and operation.
Tai Lam Chung CDA (SVR8);
9.74
The village of Tai Lam Chung itself
was not designated as a SVR since the low-lying character of the valley
precludes distant views due to development and vegetation. However the CDA
between the nullah and Tai Lam Ridge is zoned to accept residential tower
development and will have sweeping views over the valley and out to sea in the
distance. It is likely that the
magnitude of change will be influenced by the timing of the CDA development and
the project. If the project is
constructed first, the new road will already be an established feature in the
landscape therefore there would be no change to views from the CDA
development. However, adopting a worse
case scenario, if the CDA development is constructed first then the magnitude
of change would be moderate as the distance between the SVR location and the
project is 500m but directly obscures the views to sea. Other possible
developments which have not received planning permission have not been
considered.
9.75
The worst case scenario magnitude of
change of view for receivers is going to be moderate. With a moderate
sensitivity to change a moderate adverse visual impact will result during
construction and operation.
Customs and Excise Training School
9.76
The Customs and Excise Training School
is hidden behind the existing trees on Castle Peak Road and is not a visual
receiver. A low level of visual impact from the Route 10 Viaducts may be felt
in the higher storeys of this development but it is not expected to be affected
by the proposed Castle Peak Road viaducts.
Tai Lam Ridge (LCA5)
9.77
The proposed works impinge little on
the existing landscape character area and should provide slight adverse impacts during construction and operation.
Ridge footpaths (SVR9)
9.78
Much of the foreground along Brothers
Point is generally out of view due to the convex landform and steep drop in
level to the road. However, users of the recreational walking routes atop Tai
Lam Ridge will have a moderate degree of change upon distant and middle ground
views caused by the construction of viaducts of Castle Peak Road and subsequent
higher Route 10 Viaducts to Siu Lam and the north-west. These viaducts run in
front of the nullah and a visually open foreshore making the high viaducts
conspicuous. However, the residual
impact of Castle Peak Road will become less significant when viewed with the
visual impact of the Route 10 viaducts.
9.79
The magnitude of change of view for
receivers is going to be moderate. This is set against a low sensitivity to
change and will result in a slight/moderate adverse visual impact during
construction and operation.
Recommended Landscape Mitigation Measures
9.80
The assessment predicts a number of
significant landscape and visual impacts, which are summarised in Tables 9.7
and 9.9. In order to mitigate these impacts,
a number of on-site landscape mitigation measures are recommended for
incorporation into the Project, subject to further studies during detailed
design. The aim of the mitigation
measures is twofold :
·
to alleviate those landscape and
visual impacts that are unavoidable through the engineering design;
·
to enhance the existing landscape and
visual context of the surrounding areas.
9.81
The mitigation measures are summarised
in the following paragraphs in addition to the likely funding, implementation,
management and maintenance agencies and will be in accordance with Appendix A
to Works Branch Circular No 18/94, Management And Maintenance Of Both Natural
Vegetation And Landscape Works. No
off-site mitigation measures have been proposed.
9.82
Landscape
mitigation measure 1 (LMM1) – Construction programming and management. The construction
programme for the Project should be reduced to the shortest possible period,
particularly in those locations where severe or high landscape and visual
impacts are expected, e.g., coastal area and viaducts. Additionally, the periphery of the works
areas at street level should be managed so that they do not appear cluttered,
untidy and unattractive and inconvenient to pedestrians. For example, all hoarding should be
colourfully designed with interesting motifs demonstrating the work of Highways
Department. Hoarding with bland colours
should be avoided.
Funding:
Highways Department (HyD);
Implementation, management and maintenance:
Contractor.
9.83
Landscape
mitigation measure 2 (LMM2) - Advanced planting and erosion control works. Where possible,
the stockpiling of topsoil, new planting and erosion control works should be
carried out as early as possible in the construction period instead of at the
end (refer to Figures 9.8A to E for proposed locations where this LMM is
recommended). This will assist in
maximising the time for carrying out new planting, resulting in a higher
success rate for the establishment of new screen trees. Excavated topsoil will be stockpiled for
re-use, on site if possible, in mounds of height no greater than 1.5 metres in
height and for no longer than 12 months to prevent the build up of anaerobic
conditions. These areas can be
temporarily hydroseeded to minimise erosion and improve the visual appearance.
Other techniques of stockpiling of topsoil in a manner that would avoid washing
into the drainage scheme should be examined comprehensively.
Funding: HyD;
Implementation:
Contractor
Management and
maintenance during construction: Contractor;
Management
during operation in accordance with Appendix A to WBTC 18/94.
9.84
Landscape
mitigation measure 3 (LMM3) – Maximisation of
amenity planting in road corridor (refer to Figures 9.8A to E for proposed
locations where this LMM is recommended).
Opportunities to incorporate significant amenity areas along the
alignment should be maximised to provide visual relief in an otherwise
congested traffic environment. The requirements of pedestrians are to be
considered uppermost here as footpaths running adjacent to the Tuen Mun and
Castle Peak Roads are in an unpleasant, windswept environment subject to the
pollution of heavy passing traffic. Efforts to remove the footpath from the
immediate road edge are to be incorporated whenever possible.
Funding: HyD;
Implementation:
Contractor
Management and
maintenance during construction: Contractor;
Management
during operation in accordance with Appendix A to WBTC 18/94.
9.85
Landscape
mitigation measure 4 (LMM4) –Design, materials and finishes of engineering
structures. The quality of the design of all engineering structures, which will
include viaducts, portals, parapets, piers, slip roads, noise barriers, noise
enclosures and drainage systems are an important consideration and will need to
be approved by ACABAS during detailed design (refer to Figures 9.8A to E for
proposed locations where this LMM is recommended). They should be designed in accordance with HyD’s guidelines, but
equally attention should be given to design modern and attractive structures.
Correctional Services Department should be consulted about the design of an
architectural screen adjacent to its low rise staff quarters. The design of the
overall noise barrier structure should be elegant, and integrate together all
the component parts eg supporting members, panels etc. The height of any
members supporting the transparent view panels should be as low as possible,
with spacing of these members as wide as practical. Horizontal edges should be
kept to a minimum number and be as thin and slim as possible. Additionally the
colour and surface treatment of all noise barrier materials should be as
visually recessive as possible.
Funding: HyD;
Implementation:
Contractor
Management and
maintenance during construction: Contractor;
Management
during operation in accordance with Appendix A to WBTC 18/94.
9.86
Landscape
mitigation measure 5 (LMM5) – Maximisation of Woodland Planting on Disturbed land (refer to
Figures 9.8A to E for proposed locations where this LMM is recommended). All land disturbed by construction should be
restored to an equivalent standard or higher.
Compensatory planting should be adopted for all felled trees. All felled mature trees which are considered
to be high in environmental amenity, should be compensated by a similar size
specimen. Where slopes or ground
conditions prevent the planting of mature trees, other locations as close as
possible to the location of the felled tree within the works area should be
used. Existing woodland cleared by
construction activity will also be replaced at a ratio of at least twenty trees
planted for every tree felled. All
planting on slopes should be in accordance with Works Branch Technical Circular
25/93.
Funding: HyD;
Implementation: Contractor
Management and maintenance during
construction: Contractor;
Management during operation in accordance
with Appendix A to WBTC 18/94.
9.87
Landscape
mitigation measure 6 (LMM6) – Urban area under-viaduct hard and soft landscape
works. Where
viaducts result in sterilised space under viaducts, extensive hard and soft
landscape works should be provided to enhance and restore the function of the
land, including creepers and climbers on retaining walls and supporting columns
(refer to Figures 9.8A to E for proposed locations where this LMM is
recommended).
Funding: HyD;
Implementation:
Contractor
Management and
maintenance during construction and operation in accordance with Appendix A to
WBTC18/94.
9.88
A detailed landscape design will be
prepared and issued to all management and maintenance agencies, particularly
LCSD, for approval prior to implementation (refer to Figures 9.8A to E for
proposed locations where the detailed landscape design is recommended). In particular, the following design
parameters should be observed:
·
Proper and adequate automatic
irrigation systems with lockable water points are required at planting
locations which are difficult to access or are considered feature planting
areas.
·
Adequate, safe and convenient access
and drop off points/ lay-bys to soft landscaping areas for maintenance vehicles
should be provided.
·
Planter beds should be of good
drainage with minimum soil depth of 1,200 mm for trees and 600 mm for shrubs,
etc.
·
Planter beds are preferably placed
under direct sunlight. Sufficient
illumination for plant growth should also be provided.
·
The minimum headroom for planting
areas under flyovers is 2,000 mm unless such areas are less than 2,000 mm in
width and situated adjacent to access paths.
·
Planter beds should preferably be in
continuous form with an internal width of at least 1,000 mm.
·
Planter beds within central dividers
or elevated roads’ decks should have a minimum internal width of 1,000 mm.
Ma Wan Coast (LCA1)
(No Landscape
Mitigation Measures)
9.89
Approximately 2.0ha of backshore
vegetation will be lost within LCA1 replaced by the new reclamation and road
corridor. The opportunities for
effective mitigation measures to reduce the residual landscape impact have not
been included. The design of the reclamation structures do not allow for
significant or varied planting outwith the seawall and it is not feasible to
provide suitable potential habitats within the rock armour. Residual impacts
remain significant adverse.
Ma Wan Boat Traffic (SVR1)
LMM 1, 2, 3, 4,
5, and 6
9.90
Visual impacts will be long term since
effective mitigation of the viaducts to reduce visibility is not possible and
the visual impact is exacerbated by the addition of noise mitigation barriers
resulting in significant and adverse residual landscape impacts (see Figure
9.6A). While a number of mitigation measures have been proposed for the
appearance of the viaducts and seawalls, the opportunities for substantial
reduction of visual impact are otherwise extremely limited. The integration of the seawall visually in
plan or elevation and the strong engineering form has no variation in height
nor does it respond to the natural coastline and mountain forms around it owing
to design restrictions. The linear roadside planting will be extremely limited
in its ability to reduce any visual impacts in the long term. There is no
ability for coastal margin species to invade and mitigate the seawall
construction. It has been concluded that the residual visual impact will remain
moderate adverse.
Transport corridor (LCA2)
LMM 1, 2, 3, 4
and 5
9.91
Extensive planting of the roadside and
creation of amenity areas will create an immediate landscape environment. This
will mature in time to provide robust links to the surrounding woodland
environment and provide significantly increased amenity value and landscape
resource. For this reason, the remedial
landscape impact is considered to become slightly beneficial over time as the
planting matures and establishes (see Figure 9.6B).
Tuen Mun Road and Interchange traffic (SVR2)
LMM 1, 2, 3, 4 and 5
9.92
The compensatory planting on the
reclamation for Castle Peak Road between Ka Loon Tsuen and Brothers Point will
create an immediate landscape environment.
The planting will mature of time to provide significantly increased visual
amenity along this section of the road corridor. The viaduct section will
however continue to give long term significant adverse visual impact. Careful
design of the engineering elements and in particular with the extensive noise
mitigation measures may help to reduce the immediate visual impact at Day1 from
moderate / significant adverse to moderate adverse whilst the planting
mitigation may reduce this further to moderate
/ slight adverse by Year 10. (see Figure 9.6B).
Siu Lam Ridge (LCA3)
(No Landscape Mitigation Measures)
9.93
The proposed works do not impinge on
the landscape character area.
Siu Lam Hospital (SVR3) / Siu Lam Psychiatric Centre
(SVR4)
LMM 1, 2, 3 and
4
9.94
The main views out to the sea will be
affected by the viaduct construction and noise mitigation measures. The noise
mitigation measures on the viaducts will create far more visual intrusion than
would otherwise be expected and will form the main visual impact. While a
number of recommendations have been made regarding the design of these
structures resulting in a limited reduction in visual impact, the opportunities
for more substantive reduction is otherwise extremely limited. Therefore the residual visual impacts will
reduce only slightly from moderate
adverse to moderate / slight adverse
at these locations.
Police Quarters
(SVR5)
LMM 1, 3, 4 and
5
9.95
The project at Siu Lam interchange
will be in proximity to this SVR leading to significant adverse visual impact
on viewer groups. This is predominantly
caused by the noise mitigation measures proposed in front of the facility. While
a number of recommendations have been made regarding the design of these
structures resulting in a limited reduction in visual impact, the opportunities
for more substantive reduction is otherwise extremely limited. Therefore the residual visual impacts will
reduce only slightly from significant
adverse to moderate / significant
adverse at this location.
Poseidon Coast
(SVR6)
LMM 1, 3, 4 and
5
9.96
The views from this SVR will become
obscured with the construction of new viaducts and noise barriers in the
foreground at Siu Lam interchange and also in the middle and distance across
Tai Lam Chung Channel. The proposed Route 10 viaducts will exacerbate this
visual impact. While a number of
recommendations have been made regarding the design of these structures
resulting in a limited reduction in visual impact, the opportunities for more
substantive reduction is otherwise extremely limited. Therefore the residual visual impacts will reduce only slightly
from moderate adverse to slight/moderate adverse at this location.
Tai Lam Chung Valley (LCA4)
(No Landscape
Mitigation Measures)
9.97
The proposed works impinge little on
the existing landscape character area and should provide negligible adverse or beneficial impacts.
Seaman’s Training Centre (SVR7);
LMM 1 and 4
9.98
The project will be in immediate
proximity to this SVR with the viaduct construction over the Tai Lam nullah.
While a number of recommendations have been made regarding the design of these
structures resulting in a limited reduction in visual impact, the opportunities
for more substantive reduction is otherwise extremely limited. Therefore the residual visual impacts will
reduce only slightly from moderate/significant
adverse to moderate adverse
during operation at this location.
Tai Lam Chung CDA (SVR8);
LMM 4
9.99
Owing to the distance from this SVR to
the Project, the effects of the recommendations regarding the design of these
structures will be limited. Therefore
the residual visual impacts will remain slight/moderate adverse at this
location during operation.
Customs and Excise Training School
9.100
The Customs and Excise Training School
is hidden behind the existing trees on Castle Peak Road and is not a visual
receiver. A low level of visual impact from the Route 10 Viaducts may be felt
in the higher storeys of this development but it is not expected to be affected
by the proposed Castle Peak Road viaducts.
Tai Lam Ridge (LCA5)
(No Landscape
Mitigation Measures)
9.101
The proposed works impinge little on
the existing landscape character area and should provide no adverse or beneficial impacts during operation.
Ridge footpaths (SVR9)
LMM 1, 2, 4 and 5
9.102
Owing to the distance from this SVR to
the Project, the effects of the recommendations regarding the design of these
structures will be limited. As the compensatory planting works of LMM 5 come
into effect a further reduction of residual impacts should take place resulting
in a Year 10 slight adverse residual
impact.
9.103
Tables 9.10, 9.11 and 9.12 on the
following pages summarise the predicted residual landscape and visual impacts
assuming the landscape mitigation measures are incorporated into the Project.
9.104
The tables indicate that in general
the proposed landscape mitigation measures would reduce the levels of landscape
and visual impacts to some extent.
However, there
is a net gain
of 0.13ha of trees and shrubs. The
proposed mitigation measures to reduce landscape impacts will be increasingly
effective at Year 10 of operation onwards.