Table 3.1 Proposed Construction Noise Monitoring Stations
NSR. |
Location |
NMC1 |
CSD Married Staff Quarters |
NMC2 |
Seamen’s Training Centre |
NMC3 |
Customs & Excise Training School |
a)
At locations close to the
major site activities which are likely to have noise impacts;
b)
Close to the most affected existing
noise sensitive receivers; and
c)
For monitoring locations
located in the vicinity of the sensitive receivers, care should be taken to
cause minimal disturbance to the occupants during monitoring.
a)
One set of measurements
between 0700-1900 hours on normal weekdays;
b)
One set of measurements
between 1900-2300 hours;
c)
One set of measurements between
2300-0700 hours of next day; and
d)
One set of measurements
between 0700-1900 hours on holidays, (or Sunday).
Table 3.2 Action/Limit
Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700-1900 hours on normal
weekdays |
When one documented complaint is
received |
75* dB(A) |
0700-2300 hours on holidays; and
1900-2300 hours on all other days |
60/65/70** dB(A) |
|
2300-0700 hours of next day |
45/50/55** dB(A) |
* reduce
to 70 dB(A) for schools and 65 dB(A) during school examination periods
** to
be selected based on Area Sensitivity Rating
Note : If works are to be carried out during restricted hours, the
conditions stipulated in the construction noise permit issued by the Noise
Control Authority have to be followed.
Table 3.3 Event/Action Plan for Construction Noise
EVENT |
ACTION |
||||
ET |
IC(E) |
ER |
CONTRACTOR |
||
ACTION
LEVEL |
|
|
|
||
|
1.
Notify IC(E) and Contractor; 2.
Carry out investigation 3.
Report the results of investigation to the I(E) and
Contractor; 4.
Discuss with the Contractor and formulate remedial
measures; and 5.
Increase monitoring frequency to check mitigation
effectiveness |
1. Review
the analysed results submitted by the ET 2. Review
the proposed remedial measures by the Contractor and advise the ER
accordingly 3. Supervise
the implementation of remedial measures |
1.
Confirm receipt of notification of failure in writing; 2. Notify
Contractor; 3.
Require Contractor to propose remedial measures for the
analysed noise problems; and 4. Ensure
remedial measures are properly implemented |
1. Submit
noise mitigation proposals to IC(E). 2. Implement
noise mitigation proposals. |
|
LIMIT LEVEL |
|
|
|
|
|
|
1.
Noise IE(E), ER, EPD and Contractor; 2.
identify source; 3.
Repeat measurement to confirm findings; 4.
increase monitoring frequency; 5.
carry out analysis of Contractor’s working procedures to
determine possible mitigation to be implemented; 6.
Inform IC(E)< ER and EPD the causes & actions
taken for the exceedances; 7.
Assess effectiveness of Contractor’s remedial actions and
keep IC(E)< EPD and ER informed of the results; and 8.
If exceedance stops, cease additional monitoring |
1. Discuss
amongst ER, ET and Contractor on the potential remedial actions. 2. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the E accordingly; and 3. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. Require
Contractor to propose remedial measures for the analysed noise problem; 4. Ensure
remedial measures are properly implemented; and 5. If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance is abated. |
1. Take
immediate action to avoid further exceedance 2.
Submit proposals for remedial actions to IC(E) within 3
working days of notification; 3. Implement
the agreed proposals; 4. Resubmit
proposals if problem still not under control; and 5. Stop
the relevant portion of works as determined by the ER until the exceedances
is abated. |
|
·
Viaduct from Tai Lam Kok to
Siu Lam : Piling, pile cap construction, bridge piers & abutment
construction, casting of bridge beams and lifting of bridge beams.
·
Siu Lam Interchange :
relocation of CLP power sub-station, bored pile wall construction, road
embankment, realignment of access road, roundabout modification, road pavement,
utilities, footpath and road furniture.
·
Road reconstruction from Tai
Lam Kok to Siu Lam: road construction (excavation of existing pavement, road
pavement, footpath and road furniture), utilities, fill slopes recompaction,
cut slopes stabilization (soil nailing to cut slopes).
·
Reclamation at Tai Lam Kok:
dredging and sand filling.
Seamen’s Training Centre
·
Piling works for viaduct from
Tai Lam Kok to Siu Lam and dredging works at Tai Lam Kok
·
Piling works for viaduct from
Tai Lam Kok to Siu Lam and seawall construction at Tai Lam Kok
·
Pile cap, bridge pier &
abutment and filling works at Tai Lam Kok
·
Fill slope recompaction and
soil nailing to cut slopes (cut slopes stabilization) for road reconstruction
from Tai Lam Kok to Siu Lam
·
Fill slopes recompaction and
soil nailing to cut slopes (cut slopes stabilization) along the existing Castle
Peak Road from Tai Lam Kok to Siu Lam
·
Only well-maintained plant
should be operated on-site and plant should be serviced regularly during the
construction program.
·
Silencers or mufflers on construction
equipment should be utilised and should be properly maintained during the
construction program.
·
Mobile plant, if any, should
be sited as far away from NSRs as possible.
·
Machines and plant (such as
trucks) that may be in intermittent use should be shut down between work
periods or should be throttled down to a minimum.
·
Plant known to emit noise
strongly in one direction should, wherever possible, be orientated so that the
noise is directed away from the nearby NSRs.
·
Material stockpiles and other
structures should be effectively utilised, wherever practicable, in screening
noise from on-site construction activities.
·
They should be at NSRs in the
vicinity of recommended direct technical remedies; preferably, there should be on
representative monitoring locations near each type of noise screening element
(i.e. vertical barrier, cantilever barrier and enclosure);
·
One high floor and one medium
floor monitoring points should be chosen at each location as far as possible;
and
·
Selected monitoring locations
should enable monitoring to be done twice within one year after implementation
of the mitigation measures during operation.
Table 3.4 Proposed
Operation Noise Monitoring Stations
NSR |
Location |
NMO1 |
Block H of Correctional Services Department Married Staff
Quarters |
NMO2 |
Siu Lam Hospital |
NMO3 |
Seamen’s Training Centre |
NMO4 |
Block J of Correctional Services Department Married Staff
Quarters |
·
alternative location shall be
similarly exposed to potential noise impacts;
·
it shall be close to the
noise sensitive receivers; and
·
shall be located so as to
cause minimal disturbance to the occupants.
·
The operational noise
monitoring shall be carried out at a distance of 1 m from the openable window
and 1.2 m above the floor level of the noise sensitive receivers identified in
Table 3.2. The ET Leader shall agree
with the IC(E) on any necessary corrections adopted.
·
one set of measurements at
the morning traffic peak hour on normal weekdays (exact timing to be confirmed
with Transport Department and agreed with EPD);
·
one set of measurements at
the evening traffic peak hour on normal weekdays (exact timing to be confirmed
with Transport Department and agreed with EPD);
·
a concurrent census of
traffic flow and percentage heavy vehicle shall be conducted for the road and
the existing road network in the vicinity of each measuring point;
·
average vehicle speed
estimated; and
·
the two sets of monitoring
data should be obtained within the first year of operation.
Table 3.5 Action Levels for Operational Noise
Sensitive Receiver |
Action Level |
Village Houses/other
residential development |
L10 equal
to or higher than 70 dB(A) |
Schools/educational
establishments |
L10 equal
to or higher than 65 dB(A) |
Table 3.6 Event/Action Plan for Operational Noise
EVENT |
ACTION |
|
Monitoring Contractor |
Highways Department |
|
·
Notify Highways Departments. Provide
details of traffic flow and other monitoring condition to EPD. Notify Highways Department. Provide details of traffic flow and other
monitoring condition to EPD |
·
Liaise with EPD to investigate noise mitigation proposals. ·
Implement noise mitigation proposals if required implement noise
mitigation proposals if required. |
·
A cantilevered barriers (5.5m
high vertical barrier with a 5m cantilever at 45 degrees to the horizontal) of
around 25m located behind the footpath of Castle Peak Road;
·
A cantilevered barriers (5.5m
high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of
around 15m located at northbound carriageway of the slip road to the Siu Lam
Interchange;
·
A full enclosure of around 76
m at the slip road to the Siu Lam Interchange (CH102-CH178);
·
A full enclosure of around
175 m at the Castle Peak Road viaduct (CH175-CH350);
·
A cantilevered barriers (5.5m
high vertical barrier with a 3m cantilever at 45 degrees to the horizontal) of
around 604m located at eastbound carriageway of the Castle Peak Road viaduct
(CH350 – CH954);