1.                  BACKGROUND

 

1.1.           To cope with the anticipated increase in traffic, various sections of Castle Peak Road have been widened over the last few years.  Improvement to Castle Peak Road from Siu Lam to So Kwun Tan commenced in February 1997 and was completed in November 2000 while improvement to Castle Peak Road from Area 2 of Tsuen Wan to Ka Loon Tsuen is scheduled to commence in August 2001 and finish in June 2005.  When these proposals are completed, the whole section of Castle Peak Road between Tsuen Wan West and Hong Kong Gold Coast in Tuen Mun will be of dual 2-lane standard with the exception of the section between Ka Loon Tsuen and Siu Lam.

 

1.2.           An assessment has been carried out showing that by 2006 the capacity of a single two-lane Castle Peak Road between Ka Loon Tsuen and Siu Lam would be inadequate to cope with the increasing traffic flows.

 

1.3.           In view of the above, it was recommended that the section between Ka Loon Tsuen and Siu Lam should be widened to a dual-2 lane standard in order to provide a continuous level of service from So Kwun Tan to Tsuen Wan.  The Highways Department carried out a Preliminary Project Feasibility Study (PPFS), which was completed in March 1998.  A Preliminary Environmental Review (PER) was also carried out in conjunction with the PPFS to identify the potential environmental concerns arising from the implementation of the project.  The results of the PER indicated that during the construction and operation stages, air quality, noise, water quality, ecology, landscape and visual impacts were expected.

 

1.4.            In October 1999, Maunsell Consultants Asia Limited (MCAL) was commissioned by the Highways Department as lead consultant to undertake an engineering feasibility study and preliminary design for this project. Further studies including Traffic Impact Assessment Study, Environmental Impact Assessment (EIA) Study, Marine Impact Assessment Study and Drainage Impact Assessment Study were also carried out. Maunsell Environmental Management Consultants Limited (MEMCL) is responsible for the EIA study.

 

1.5.            Under Section C.2(ix), Schedule 2, Part 1 of the Environmental Impact Assessment Ordinance (Cap.499), the project is a designated project and therefore will require an environmental permit.

 

1.6.            The purpose of this EIA study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed project and related activities taking place concurrently.  This will provide information for public consultation and provide a basis for project assessment by the Environmental Protection Department (EPD) and relevant authorities.