Central Reclamation, Phase III

Studies, Site Investigation, Design and Construction

 

 

Environmental Monitoring and Audit Manual

(July 2001)

 


1.           Introduction

1.1.        Purpose of the Manual

1.2.        Requirement for EM&A Programme

1.3.        Project Description

1.4.        EIA Requirements

1.5.        Project Organisation

1.6.        Construction Works and Programme

1.7.        Construction Sequence – Issues and Constraints

1.8.        Proposed Construction Sequence

1.9.        Construction Programme

2.           AIR QUALITY

2.1.        Air Quality Parameters

2.2.        Total Suspended Particulates

2.3.        Monitoring Equipment

2.4.        Laboratory Measurement/ Analysis

2.5.        Monitoring Locations

2.6.        Baseline Monitoring

2.7.        Impact Monitoring

2.8.        Event and Action Plan for Air Quality

2.9.        Dust Mitigation Measures

3.           Noise

3.1.        Noise Parameters

3.2.        Monitoring Equipment

3.3.        Monitoring Locations

3.4.        Baseline Monitoring

3.5.        Impact Monitoring

3.6.        Event and Action Plan for Noise

3.7.        Noise Mitigation Measures

4.           MARINE Water Quality

4.1.        Marine Water Quality Parameters

4.2.        Monitoring Equipment

4.3.        Location of the monitoring sites

4.4.        Laboratory Measurement / Analysis

4.5.        Monitoring Locations

4.6.        Baseline Monitoring

4.7.        Impact Monitoring

4.8.        Event and Action Plan for Water Quality

4.9.        Water Quality Mitigation Measures

5.           Waste Management

5.1.        Waste Management

6.           Landscape and Visual

6.1.        Mitigation

6.2.        Monitoring and Audit Requirements

7.           Site Environmental Audit

7.1.        Site Surveillance

7.2.        Environmental Compliance

7.3.        Choice of Construction Method

7.4.        Environmental Complaints

8.           REPORTING

8.1.        General

8.2.        Baseline Monitoring Report

8.3.        Monthly EM&A Reports

8.4.        Quarterly EM&A Summary Reports

8.5.        Final EM&A Summary Report

8.6.        Data Keeping

8.7.        Interim Notifications of Environmental Quality Limit Exceedances

9.           Schedule of Mitigation from the EIA

 


TABLES

Table 1.1  : Summary of Construction Tasks and Stages for CRIII

Table 1.2  :  Summary of Construction Programme

Table 2.1  :  Construction Phase Air Sensitive Receivers

Table 2.2 :  Action and Limit Levels for Air Quality

Table 2.3  :  Event/Action Plan for Air Quality

Table 3.1  :  Action and Limit Levels for Construction Noise

Table 3.2  :  Event/Action Plan for Construction Noise

Table 4.1  : Proposed Water Quality Monitoring Stations

Table 4.2  :  Action and Limit Levels for Water Quality

Table 4.3  :  Event and Action Plan for Water Quality

Table 7.1 : Procedures in the Event of a Complaint

Table 8.1  : Sample Template for Interim Notifications of Environmental Quality Limits Exceedances

Table 9.1 :  Schedule of Impacts and Mitigation Measures

 

 

Figures

Figure 1.1            Study Area and Proposed Layout

Figure 1.2            Project Organisation

Figure 2.1            Data Sheet for TSP Monitoring

Figure 2.2            Air / Noise Sensitive Receivers

Figure 3.1            Noise Monitoring Field record Sheet

Figure 4.1            Water Quality Monitoring Data Record Sheet

Figure 4.2            Locations of Water Monitoring Stations

 

 

 


AL

Action/limit

APCO

Air Pollution control Ordinance

AQO

Air Quality Objective

CRIII

Central Reclamation Phase III Minimum Option

CNP

Construction Noise Permit

EIA

Environmental Impact Assessment

EIAO

Environmental Impact Assessment Ordinance

EM & A

Environmental Monitoring and Audit

EPD

Environmental Protection Department

ER

Engineer’s Representative

ET

Environmental Monitoring Team

ETL

Environmental Monitoring Team Leader

IC(E)

Independent Checker (Environment)

HKPSG

Hong Kong Planning Standards and Guidelines

HVS

High Volume Sampler

HyD

Highways Department

NCO

Noise Control Ordinance

NSR

Noise Sensitive Receiver

SR

Sensitive Receiver

TM

Technical Memorandum

TSP

Total Suspended Particulates

USAEPA

United States of America Environmental Protection Agency

WDO

Waste Disposal Ordinance

WPCO

Water Pollution Control Ordinance

 

 

 


1.           Introduction

1.1.        Purpose of the Manual

1.1.1.     The purpose of this Environmental Monitoring & Audit (EM&A) Manual is to guide the EM&A programme prepared for the Central Reclamation Phase III (CRIII), Minimum Option to ensure compliance with the Environmental Impact Assessment (EIA) Report. This is subject to approval of the EIA Report under the statutory procedures of the EIAO and supporting Technical Memorandum. The EIA recommends procedures to:

·           ensure that any environmental impacts resulting from the construction of CRIII are kept to within acceptable levels;

·           check that mitigation measures have been applied and are effective, and that the appropriate corrective actions are undertaken, if and when required; and

·           provide a means of checking compliance with environmental objectives, recording anomalies and documenting corrective action.

1.1.2.     This Manual contains the following:

·           information on the CRIII project, the project organisation and construction programme;

·           general EM&A principles and the EM&A team organisation;

·           monitoring parameters, schedules, Action/Limit Levels and action plans;

·           complaints procedures; and

·           reporting procedures.

1.1.3.     The EM&A Manual has taken on a dual function since the introduction of the EIAO. These roles are:

·           to provide a contract document between a Client and a contractor defining the monitoring requirements and other duties in a form that is consistent with accepted contract practice.

·           To provide additional controls that are implemented through the provisions of the Environmental Permit that are applicable to the project, but for which the responsibility does not rest with the Contractor.

1.1.4.     As a general note, the Independent Checker (Environment) [IC(E)] may be part of the Engineer's Team, or may be totally independent, employed under a separate contract by the project proponent. In the latter case, this Manual makes reference to items requiring agreement between the Contractor (or his monitoring team), the Engineer's Representative, relevant Government Departments and the IC(E). Attention is drawn to the possibility of requiring agreement from a third party outside the contract if the IC(E) is employed independently (refer also to paragraphs 1.5.9 and 1.5.10).

1.1.5.     To simplify the contractual arrangements, it is proposed that all communication with the IC(E) will be through the ER. Therefore, no reference is made in this Manual for agreement to be reached with the IC(E) as the Contractor will not be required to contact the IC(E) directly.

1.2.        Requirement for EM&A Programme

1.2.1.     The criteria for the requirement for undertaking EM&A are provided by EPD, these are summarised as follows:

(a)            to protect sensitive receivers from environmental impacts if mitigation is not implemented;

(b)           to protect the ecosystem;

(c)            to monitor activities in areas of high conservation value;

(d)           to monitor the effectiveness of mitigation measures which involves a long period to establish;

(e)            to monitor am unproven technology;

(f)             to validate the hypothesis in analysis and design;

(g)            to audit the changing project scheduling; and

(h)           others.

1.2.2.     Criteria a) is met as there are sensitive receivers which may be impacted by construction activities. Without mitigation for water quality, dust and noise during the construction phase, activities could cause nuisance and hence would be prejudicial to the health or well being of people, and detrimental to the marine environment. Also as there are potential water quality impacts, this further justifies the requirements for monitoring and audit. The other criteria are not relevant to this project. On this basis of Criteria a), an EM&A programme is required.

1.3.        Project Description

Background

1.3.1.     The proposed CRIII is located to the north-east of the main Central area in Hong Kong, on the coast of Victoria Harbour between Central and Admiralty. The site lies between Central Reclamation, Phase I and western Wan Chai. Following the rejection of ‘Full Reclamation’ proposals of over 30 hectares in size, a ‘Minimum Option’ has been proposed for CRIII in order to minimise the extent of reclamation but at the same time provide sufficient land to meet essential transport infrastructure requirements. This ‘Minimum Option’ will consist of 18 hectares of reclaimed land and will provide land for the redevelopment of several Government related facilities, existing facilities within the study area, construction of a section of the Central – Wanchai Bypass (CWB) in tunnel, the Hong Kong Station Extended Overrun Tunnel and North Island Link Protection Works (entrusted to this project), and a landscaped promenade.  In order to facilitate the construction of the CRIII works the existing Government Heliport at Tamar is to be relocated to Wan Chai PCWA: the Wan Chai PCWA is to be relocted to Chai Wan Basin.  In addition, the CRIII project will also involve the demolition of the existing Star Ferry and Queen’s Piers as well as the provision of necessary infrastructure such as new roads, piers, electricity sub-stations, drainage culverts, sewerage, and seawater cooling systems.

1.3.2.     The reclamation will take place over a period of approximately 55 months and will be phased to ensure the continuation of drainage and seawater cooling systems. A ‘fully dredged’ construction system is to be employed that will involve the removal and disposal of up to 580,000 m3 of dredged material.  It is estimated that 375,000 m3 of the material will be contaminated.

Sensitive Receivers

1.3.3.     The site is in a predominantly commercial business area in Hong Kong and, consequently there are no residential sensitive receivers that may be affected by the construction of CRIII. Commercial, Government and Institutional buildings and hotels around the site are all centrally ventilated and air-conditioned. They are, therefore, not classified as noise sensitive receivers (NSRs) under the HKPSG or the EIATM. At the Hong Kong Academy of Performing Arts (HKAPA), there is an outside auditorium area. This area is rarely used for performing arts events but is considered in the EIA Report as a potential NSR. A number of air sensitive receivers have been identified in the study area, these being the air intakes for the buildings around the project site. Water quality sensitive receivers have been identified as the seawater cooling system intakes in the direct vicinity of CRIII, as well as other seawater intakes located around Victoria Harbour. No ecological sensitive receivers have been identified in the EIA report.

1.3.4.     The project site and surrounding area are shown in Figure 1.1.

1.4.        EIA Requirements

1.4.1.     The EIA Report recommends a range of mitigation measures to control the project’s potential environmental impacts with regard to marine water quality, dust, construction waste, ecological and noise impacts. The schedule of mitigation measures as given in the EIA Report is repeated in Section 9 of this Manual.

1.5.        Project Organisation

1.5.1.     There is the possibility that multiple contractors may be employed at the work site.  The preferred approach, therefore, is for an Independent Monitoring Team to be employed directly by the project proponent to maintain impartiality. However, this is not commonly adopted. It is normal practice to require a contractor to undertake his own monitoring which should be audited and checked by the Engineer and an Independent Checker (Environment) [IC(E)].  The project organisation is illustrated in Figure 1.2.

1.5.2.     Environmental Monitoring Team Leader (ET Leader): This person should be professionally qualified with suitable experience in environmental management and planning. As a general recommendation, 7 years experience is desirable, although if the proposed ET Leader has less, agreement should be sought from the ER. Extensive knowledge of the study area is required. The ET Leader should have work experience in Hong Kong managing and providing specialist advice on environmental monitoring of infrastructure projects.

1.5.3.     Site Inspection Team Leader: Requires experience working on environmental projects in Hong Kong. Extensive experience in dealing with contractors directly is required.

1.5.4.     Noise/Air Specialist: Requires experience in the air and noise pollution field. Particularly skilled in the use of computer models, database design and management of monitoring programmes.

1.5.5.     Consultant: Experience as an environmental consultant with a broad range of expertise both in the technical and managerial aspects of environmental assessment. Proficient in: water quality sampling, analysis and assessment; air and noise monitoring, modelling and analysis; ecology; landscape and visual impact; site assessment; and scoping exercises to identify key environmental issues.

1.5.6.     Assistant Consultant: Experience in conducting on-site monitoring, data-gathering and subsequent computer-modelling data analyses.

1.5.7.     The duties to be undertaken by the Environmental Monitoring Team (ET) comprise the following:

·           sampling, analysis and statistical evaluation of monitoring parameters with reference to the EIA Study recommendations and requirements.

·           environmental site surveillance;

·           audit of compliance with environmental protection and pollution prevention and control regulations;

·           monitor the implementation of the environmental mitigation;

·           monitor compliance with the environmental protection clauses/specifications in the Contract;

·           review construction programme and comment as necessary;

·           review construction methodology and comment as necessary;

·           complaint investigation , evaluation and identification of corrective measures;

·           liaison with IC(E) on environmental performance matters and timely submission of relevant EM&A deliverables to IC(E) for approval; and

·           advise the Contractor on environmental improvement awareness and enhancement matters etc in site; and

·           timely submission of the EM&A report to the Project Proponent and the Director of Environmental Protection.

1.5.8.     Appropriate resources shall be allocated by the ET to fulfil their duties specified in this manual.

1.5.9.     The Independent Checker (Environment) [IC(E)] shall advise the Engineer's Representative on environmental issues related to the project.  The role of the Checker shall be independent from the management of construction works; but, the Checker shall be empowered to audit the environmental performance of construction.  The Checker shall have project management experience in addition to the requirements of the ET Leader stated in paragraph 1.5.7.  The appointment of the Checker is subject to the approval of the Engineer's Representative.

1.5.10.   The main duty of the IC(E) is to carry out environmental audit of the construction project; this shall include, inter alia, the followings :

a)         Review and audit all aspects of the EM&A programme;

b)        Validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;

c)         Carry out random sample check and audit on monitoring data and sampling procedures, etc;

d)        Conduct random site inspection;

e)         Audit the EIA recommendations and requirements against the status of implementation of environmental protection measures on site;

f)          Review the effectiveness of environmental mitigation measures and project environmental performance;

g)         On a needs basis, audit the Contractor's construction methodology and agree the least impact alternative in consultation with the ET Leader and the Contractor;

h)        Check complaint cases and the effectiveness of corrective measures;

i)          Review EM&A report submitted by the ET Leader; and

j)          Feedback audit results to ET by signing off relevant EM&A documents.

1.6.        Construction Works and Programme

1.6.1.     The details of the construction works are described in the following sections

1.6.2.     This programme is for information for the ET Leader to get an initial idea of the sequencing of the works. It may be refined and amended by the contractor(s). The ET Leader shall make reference to the actual works progress and programme during the construction stage to schedule the EM&A works. The project proponent should instruct the contractor(s) to provide the relevant programme information to the ET Leader for formulating the EM&A schedule.

1.7.        Construction Sequence – Issues and Constraints

1.7.1.     The construction of the reclamation for Central Reclamation Phase III is constrained by a number of factors largely associated with maintaining existing facilities and operations prior the completion of associated reprovisioned facilities.  Critical issues and constraints which affect the reclamation sequence are :

·           Private vessel and ferry operations from the existing Queen’s Pier, “Star” Ferry Piers and Tsim Sha Tsui East temporary ferry pontoon must be maintained until completion and opening of the reprovisioned ferry pier (Ferry Pier 8), public landing steps and refurbishment of the existing Ferry Pier 7 is completed.  In addition to maintaining safe marine access during this period, adequate land access will have to be maintained for pedestrians, public transport and private vehicles.  During earlier studies, it was established that the existing public landing steps to the immediate north of the PLA Headquarters at Tamar would need to be closed prior to commencing the CRIII construction works.  Marine Department have confirmed that these arrangements would still apply to the Minimum Option works with the exception that the westernmost set of landing steps within the existing seawall could be retained until the reprovisioned public landing steps are completed and opened for use.

·           The flows from stormwater drainage culverts F, J and K must be maintained at all times throughout the project works.  Temporary diversions can be utilised subject to satisfying the DSD that the flow capacity of the temporary diversions will not cause any increased risk of upstream flooding in the existing hinterland areas.

·           The operations of the existing cooling water facilities located along the Central waterfront affected by the works must be maintained until completion, commissioning and opening of the reprovisioned facilities.  This requirement involves maintaining intake and outfall flows, maintaining water quality at the intake to acceptable levels and maintaining adequate maintenance access to the cooling water facilities.

·           The provision of sufficient land at as early a time as possible to permit construction of the following key infrastructure works :

-           The Central - Wanchai Bypass Tunnel; and

-           The Hong Kong Station Extended Overrun Tunnel.

·           The existing Government Heliport located to the north of Lung Wui Road is planned to be reprovisioned to the Wan Chai PCWA as soon as possible after the start of the CRIII works (further relocation of this facility is planned as part of the WDII project to enable WDII project works to be completed).  To facilitate the relocation of the Heliport to this site, the Wan Chai PCWA will firstly need to be relocated to Chai Wan Basin.

1.8.        Proposed Construction Sequence

1.8.1.     Taking account of the issues and constraints as outlined in Section 1.7, a proposed construction sequence has been developed and is detailed in Table 1.1 below. The sequence is broadly similar to that proposed for the CRIII-FR, but adapted to take account of the reduction in reclamation area immediately to the north of the previous CRIII-FR area.

Table 1.1  : Summary of Construction Tasks and Stages for CRIII

Stage

Construction Period

Site Area

Main Construction Elements

1

End Aug 2002 to End March 2003

Initial Reclamation Area West

-         Dredging

-         Seawall Construction

-         Sand Filling

-         Civil Works for Cooling Water Pumping Stations

-         Piling for Ferry Pier 8

 

 

Hinterland Areas

-         Public Transport Facilities Behind Piers 4 - 6

-         Piling for EOT Vent Building

2

Start April 2003 to End Nov 2003

Initial Reclamation Area West

-         Sand Filling and Vibrocompaction

-         Civil Works for Cooling Water Pumping Stations

-         Superstructure for Ferry Pier 8

-         Piling for Public Landing Steps (Stage 1)

-         Superstructure for Public Landing Steps (Stage 1)

 

 

Initial Reclamation Area East

-         Dredging

-         Temporary Diversion of Culvert J

 

 

Hinterland Areas

-         Public Transport Facilities Behind Piers 6 - 7

-         Sheet Piling for EOT Vent Building

-         Superstructure for EOT Vent Building

-         NIL Protection Works, Stages 1& 2

3

Start Dec 2003 to End July 2004

Initial Reclamation Area West

-         Pipework for Cooling Water Pumping Stations

-         E&M and Finishing Works for Cooling Water Pumping Stations

-         Substations for Cooling Water Systems

 

 

Initial Reclamation Area East

-         Seawall Construction

-         Sand Filling and Vibrocompaction

-         Civil Works for Cooling Water Pumping Stations

-         Pipework for Cooling Water Pumping Stations

-         Substations for Cooling Water Systems

-         E&M and Finishing Works for Cooling Water Pumping Stations

-         Culvert J Construction

-         Central-Wan Chai Bypass Construction

-         NIL Protection Works, Stage 3

 

 

Hinterland Areas

-         EOT Vent Building Completion

-         NIL Protection Works, Stages 1 & 2

-         Drainage Improvement Works at Connaught Place

4

August 2004

Initial Reclamation Area East

-         Central-Wan Chai Bypass Construction

 

 

Final Reclamation Area West

-         Demolition of Piers

 

 

Hinterland Areas

-         Piling for EOT Vent Shafts

-         Drainage Improvement Works at Connaught Place

5

Start Sept 2004 to End April 2005

Initial Reclamation Area East

-         Central-Wan Chai Bypass Construction

 

 

Final Reclamation Area West

-         Dredging

-         Seawall Construction

-         Sand Filling

-         Surplus Soft Filling

-         Vibrocompaction

-         Temporary Diversion of Culvert F

-         Civil Works for Cooling Water Pumping Stations

-         Sheet Piling for EOT

 

 

Final Reclamation Area East

-         Dredging

-         Seawall Construction

 

 

Hinterland Areas

-         EOT Vent Shaft Construction

-         Drainage Improvement Works at Connaught Place

6

Start May 2005 to End Dec 2005

Final Reclamation Area West

-         Surplus Soft Filling and Vibrocompaction

-         Temporary Diversion of Culvert F

-         Foundations for Culvert F

-         Central Wan-Chai Bypass Construction

-         Sheet Piling for EOT

-         EOT Tunnel Construction

-         Piling and Superstructure for Public Landing Steps (Stage 2)

-         PLA Berth Construction

 

 

Final Reclamation Area East

-         Sand Filling and Vibrocompaction

-         Civil Works for Cooling Water Pumping Stations

-         Culvert K Construction

-         NIL Protection Works, Stage 4

-         Central-Wan Chai Bypass Construction

-         Road P2 Underpass

 

7

Start Jan 2006 to End Oct 2006

Final Reclamation Area West

-         Culvert F Construction

-         Central-Wan Chai Bypass Construction

-         EOT Tunnel Construction

-         Foundations to Man Yiu Street Footbridge

 

 

Final Reclamation Area East

-         Central-Wan Chai Bypass Construction

-         Road P2 Underpass

 

 

All Areas

-         Drainage & Utility Works

-         At Grade Roads & Landscaping (Except Roads D5, D6 & P1)

8

Start Nov 2006 to End Mar 2007

Final Reclamation Area West

-         Man Yiu Street Footbridge Construction

-         Drainage & Utilities to Roads D5, D6 & P1

-         PTI Construction

-         At Grade Roads & Landscaping to Roads D5, D6 & P1

 

1.9.        Construction Programme

A construction programme for Central Reclamation Phase III works has been prepared based upon the construction sequence detailed in Table 1.1.  The construction programme is presented in a summary form for the EIA in Table 1.2.

 

 

 

 

 

 

 

Table 1.2  :  Summary of Construction Programme

Activity

Year 1

Year 2

Year 3

Year 4

Year 5

Year 6

Stage 1 (Aug  2002 –
Mar 2003)

 

 

 

 

 

 

Stage 2 (Apr 2003 –
Nov 2003)

 

 

 

 

 

 

Stage 3 (Dec 2003 – July 2004)

 

 

 

 

 

 

Stage 4 (Aug 2004 )

 

 

 

 

 

 

Stage 5 (Sept 2004 –
Apr 2005)

 

 

 

 

 

 

Stage 6 (May 2005 –
Dec 2005)

 

 

 

 

 

 

Stage 7 (Jan 2006 –
Oct 2006)

 

 

 

 

 

 

Stage 8 (Nov 2006 –
Mar 2007)

 

 

 

 

 

 

Note :   The dates provided in the above table are based upon a construction start date of August 2002 and may be subject to change.

 

 


2.           AIR QUALITY

2.1.        Air Quality Parameters

2.1.1.     The major air quality issue associated with CRIII is the potential for dust generation to cause elevated Total Suspended Particulates (TSP) levels at nearby sensitive receivers.

2.2.        Total Suspended Particulates

2.2.1.     Monitoring and audit of the TSP levels shall be undertaken by the ET Leader to ensure that any deteriorating air quality could be readily detected and timely action taken to rectify the situation.

2.2.2.     1-hour and 24-hour TSP levels shall be measured to indicate the impacts of construction dust on air quality.  The TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.  Upon approval by the ER, 1-hour TSP levels can be measured by direct reading methods which are capable of producing comparable results as that by the high volume sampling method, to indicate short event impacts.

2.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions etc. shall be recorded down in detail.  A sample data sheet is shown in Figure 2.1.

2.3.        Monitoring Equipment

2.3.1.     High volume samplers (HVS) to be used for carrying out the 1-hour and 24-hour TSP monitoring shall comply with the following specifications:

·           0.6-1.7 m3/min (20-60 SCFM) adjustable flow range;

·           equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;

·           installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·           capable of providing a minimum exposed area of 406 cm2 (63 in2);

·           flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·           equipped with a shelter to protect the filter and sampler;

·           incorporated with an electronic mass flow rate controller or other equivalent devices;

·           equipped with a flow recorder for continuous monitoring;

·           provided with a peaked roof inlet;

·           incorporated with a manometer;

·           able to hold and seal the filter paper to the sampler housing at horizontal position;

·           easy to change the filter; and

·           capable of operating continuously for 24-hour period.

2.3.2.     The ET Leader is responsible for provision of the monitoring equipment.  He shall ensure that sufficient number of HVSs with an appropriate calibration kit are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring.  The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals.  All the equipment, calibration kit, filter papers, etc. shall be clearly labelled.

2.3.3.     Initial cabibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals.  The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually.  The calibration data shall be properly documented for future reference by the concerned parties such as the IC(E).  All the data shall be converted into standard temperature and pressure condition.

2.3.4.     The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded down in the data sheet in Figure 2.1.

2.3.5.     If the ET Leader proposes to use a direct reading dust meter to measure 1-hr TSP levels, he shall submit sufficient information to the IC(E) to prove that the instrument is capable of achieving a comparable result as that of the HVS and may be used for the 1-hr sampling.  The instrument shall also be calibrated regularly, and the 1-hr sampling shall be determined periodically by HVS to check the validity and accuracy of the results measured by direct reading method.

2.3.6.     Wind data monitoring equipment shall also be provided and set up at conspicuous locations for logging wind speed and wind direction near to the dust monitoring locations. The equipment installation location shall be proposed by the ET Leader and agreed with the ER in consultation with the IC(E). For installation and operation of wind data monitoring equipment, the following points shall be observed:

·           the wind sensors should be installed on masts at an elevated level 10m above ground so that they are clear of obstructions or turbulence caused by the buildings;

·           the wind data should be captured by a data logger.  The data recorded in the data logger shall be downloaded periodically for analysis at least once a month;

·           the wind data monitoring equipment shall be re-calibrated at least once every six months; and

·           wind direction should be divided into 16 sectors of 22.5 degrees each.

2.3.7.     In exceptional situations, the ET Leader may propose alternative methods to obtain representative wind data upon approval from the ER and agreement from the IC(E).

2.3.8.     The ET shall provide sufficient equipment to ensure that the monitoring commences on schedule and is not interrupted as a result equipment failure, damage, loss or routine maintenance.

2.4.        Laboratory Measurement/ Analysis

2.4.1.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments, to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance.  The laboratory shall be HOKLAS accredited or other internationally accredited laboratory.

2.4.2.     If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the ER in consultation with the IC(E).  Measurement performed by the laboratory shall be demonstrated to the satisfaction of the ER and the IC(E).  IC(E) shall conduct regular audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.  The ET Leader shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.

2.4.3.     Filter paper of size 8”x10” shall be labelled before sampling. It shall be a clean filter paper with no folds or pin holes, and shall be conditioned in a humidity controlled chamber for over 24-hour and be pre-weighed before use for the sampling.

2.4.4.     After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper is then returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1 mg.  The balance shall be regularly calibrated against a traceable standard.

2.4.5.     All the collected samples shall be kept in a good condition for 6 months before disposal.

2.5.        Monitoring Locations

2.5.1.     Monitoring shall be conducted at two representative air sensitive receivers (ASRs). These ASRs shall be the closest to the project site and equipment shall be located as close to the potentially worst affected ASRs as is practical, although there may be practical constraints such as lack of access, power or refusal for permission to locate equipment.

2.5.2.     ASRs are listed in Table 2.1 and their locations are shown in Figure 2.2.  The ASR reference numbers presented are consistent with those used for the WDII and CWB EIA Studies.

Table 2.1  :  Construction Phase Air Sensitive Receivers

ASR

Description

ASR

Description

 

A6

Crocodile Building

A20

Central Barracks

A7

Hang Seng Bank Headquarters

A21

Central Barracks

A8

Exchange Square III

A22

Far East Financial Centre

A9

Exchange Square I & II

A23

Admiralty Centre

A10

Exchange Square I & II

A24

Harcourt Garden

A11

Garden House

A25

Police Headquarters

A12

Jardine House

A26

HK Academy for Performing Arts

A13

Statue Square

A27

Arts Centre

A14

Hong Kong Club Building

A28

Citic Tower

A15

City Hall

A29

Servicemen's Guides Association

A16

City Hall

A30

HK Academy for Performing Arts

A17

Furama Hotel

A31

Shui On Centre

A18

Hutchison House

A33

Pedestrian Plaza

A19

Bank of America Tower

A34

HKCEC Extension

 

2.5.3.     The status and locations of dust sensitive receivers may change after issuing this manual.  If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from the ER and agreement from the IC(E).

2.5.4.     When alternative monitoring locations are proposed, the following criteria, as far as practicable, shall be followed :

·           At the site boundary or such locations close to the major dust emission source;

·           Close to the sensitive receptors; and

·           Take into account the prevailing meteorological conditions.

2.5.5.     The ET Leader shall agree with the ER in consultation with the IC(E) the position of the HVS for installation of the monitoring equipment.  When positioning the samplers, the following points shall be noted :

·           a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;

·           no two samplers should be placed less than 2 metre apart;

·           the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;

·           a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;

·           a minimum of 2 metre separation from any supporting structure, measured horizontally is required;

·           no furnace or incinerator flue is nearby;

·           airflow around the sampler is unrestricted;

·           the sampler is more than 20 metres from the dripline;

·           any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;

·           permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and

·           a secured supply of electricity is needed to operate the samplers.

2.6.        Baseline Monitoring

Total Suspended Particulates

2.6.1.     The ET Leader shall carry out baseline monitoring at all of the designated monitoring locations for at least 14 consecutive days prior to the commissioning of the construction works to obtain daily 24-hr TSP samples.  1-hr sampling shall also be done at least 3 times per day while the highest dust impact is expected.  Before commencing the baseline monitoring, the ET Leader shall inform the IC(E) of the baseline monitoring programme such that the IC(E) can conduct on-site audit to ensure accuracy of the baseline monitoring results.

2.6.2.     During the baseline monitoring, there shall not be any construction or dust generation activities in the vicinity of the monitoring stations.

2.6.3.     In case the baseline monitoring cannot be carried out at the designated monitoring locations during the baseline monitoring period, the ET Leader shall carry out the monitoring at alternative locations which can effectively represent the baseline conditions at the impact monitoring locations.  The alternative baseline monitoring locations shall be approved by the ER and agreed with the IC(E).

2.6.4.     In the exceptional case, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with the IC(E) and EPD to agree on an appropriate set of data to be used as a baseline reference and submit to the ER for approval.

2.6.5.     Ambient conditions may vary seasonally and shall be reviewed at three monthly intervals.  If the ET Leader considers that the ambient conditions have been changed and a repeat of the baseline monitoring is required to be carried out for obtaining the updated baseline levels, the monitoring shall be at times when the Contractor's activities are not generating dust, at least in the proximity of the monitoring stations.  Should change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, shall be revised.  The revised baseline levels and air quality criteria shall be agreed with the IC(E) and EPD.

2.7.        Impact Monitoring

Total Suspended Particulates

2.7.1.     The ET Leader shall carry out impact monitoring during the course of the works.  For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hr TSP monitoring.  For 1-hr TSP monitoring, the sampling frequency of at least three times in every six-days shall be undertaken when the highest dust impact occurs.  Before commencing the impact monitoring, the ET Leader shall inform the IC(E) of the impact monitoring programme such that the IC(E) can conduct on-site audit to ensure accuracy of the impact monitoring results.

2.7.2.     The specific time to start and stop the 24-hr TSP monitoring shall be clearly defined for each location and be strictly followed by the field operator.

2.7.3.     In case of non-compliance with the air quality criteria, more frequent monitoring exercise, as specified in the Action Plan in Section 2.8, shall be conducted within 24 hours after the result is obtained.  This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified.

2.8.        Event and Action Plan for Air Quality

2.8.1.     The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring. The ET Leader shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP. Table 2.2 shows the air quality criteria, namely Action and Limit levels, to be used. Should non-compliance of the air quality criteria occur, actions in accordance with the Action Plan in Table 2.3 shall be carried out .

Table 2.2 :  Action and Limit Levels for Air Quality

Parameters

Action

Limit

24 Hour TSP

Level in mg/m3

For baseline level £200 mg/m3                    Action level = (Baseline level *1.3 + Limit level)/2;

For baseline level >200 mg/m3              Action level = Limit level

260

1 Hour TSP

Level in mg/m3

For baseline level £ 384 mg/m3,                  Action level = (Baseline level *1.3 + Limit level)/2

For baseline level >384 mg/m3, a          Action level = Limit level

500

 

 

 

 

 

 

 

 

 

 

 

 

 

Table 2.3  :  Event/Action Plan for Air Quality

Event

Action

ET Leader

IC(E)

ER

Contractor

Action Level

1.      Exceedance for one sample

1.         Identify source

2.         Inform IC(E) and ER

3.         Repeat measurement to confirm finding

4.         Increase monitoring frequency to daily

1.         Check monitoring data submitted by ET

2.         Check Contractor's working method

1.     Notify Contractor

1.         Rectify any unacceptable practice

2.         Amend working methods if appropriate

2.      Exceedance for two or more consecutive samples

1.         Identify source

2.         Inform IC(E) and ER

3.         Repeat measurements to confirm findings

4.         Increase monitoring frequency to daily

5.         Discuss with IC(E) and Contractor on remedial actions required

6.         If exceedance continues, arrange meeting with IC(E) and ER

7.         If exceedance stops, cease additional monitoring

1.         Checking monitoring data submitted by ET

2.         Check Contractor's working method

3.         Discuss with ET and Contractor on possible remedial measures

4.         Advise the ER on the effectiveness of the proposed remedial measures

5.         Supervise the implementation of remedial measures

1.         Confirm receipt of notification of failure in writing

2.         Notify Contractor

3.         Ensure remedial measures properly implemented

1.         Submit proposals for remedial actions to IC(E) within 3 working days of notification

2.         Implement the agreed proposals

3.         Amend proposal if appropriate

Limit Level

1.      Exceedance for one sample

1.         Identify source

2.         Inform ER and EPD

3.         Repeat measurement to confirm finding

4.         Increase monitoring frequency to daily

5.         Assess effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER informed of the results.

1.         Check monitoring data submitted by ET

2.         Check Contractor's working method

3.         Discuss with ET and Contractor on possible remedial measures

4.         Advise the ER on the effectiveness of the proposed remedial measures

5.         Supervise the implementation of remedial measures

1.         Confirm receipt of notification of failure in writing

2.         Notify Contractor

3.         Ensure remedial measures properly implemented

1.         Take immediate action to avoid further exceedance

2.         Submit proposals for remedial actions to IC(E) within 3 working days of notification

3.         Implement the agreed proposals

4.         Amend proposal if appropriate

 

2.      Exceedance for two or more consecutive samples

1.         Notify IC(E), ER, Contractor and EPD

2.         Identify source

3.         Repeat measurements to confirm findings

4.         Increase monitoring frequency to daily

5.         Carry out analysis of Contractor's working procedures to determine possible mitigation to be implemented

6.         Arrange meeting with IC(E) and ER to discuss the remedial actions to be taken

7.         Assess effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER informed of the results

8.         If exceedance stops, cease additional monitoring

1.         Discuss amongst ER, ET, and Contractor on the potential remedial actions

2.         Review Contractor's remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly

3.         Supervise the  implementation of remedial measures

1.         Confirm receipt of notification of failure in writing

2.         Notify Contractor

3.         In consultation with the IC(E), agree with the Contractor on the remedial measures to be implemented

4.         Ensure remedial measures properly implemented

5.         If exceedance continues , consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated

1.         Take immediate action to avoid further exceedance

2.         Submit proposals for remedial actions to IC(E) within 3 working days of notification

3.         Implement the agreed proposals

4.         Resubmit proposals if problem still not under control

5.         Stop the relevant portion of works as determined by the ER until the exceedance is abated.

 

 

2.9.        Dust Mitigation Measures

2.9.1.     The EIA report has discussed the appropriate dust control and mitigation measures. The Contractor shall implement dust suppression measures as identified in the Schedule given in Section 9 of this EM&A Manual.

2.9.2.     If the measures listed in Section 9 of this EM&A Manual are not sufficient to restore the air quality to acceptable levels upon the advice of ET Leader, the Contractor shall liaise with the ET Leader on some other mitigation measures, propose to the ER for approval, and implement the mitigation measures.

 

 


3.           Noise

3.1.        Noise Parameters

3.1.1.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 min) shall be used as the monitoring parameter for the time period between 0700-1900 hours on normal weekdays. For all other time periods, Leq (5 min) shall be employed for comparison with the NCO criteria.

3.1.2.     As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference. A sample data record sheet is shown in Figure 3.1 for reference.

3.2.        Monitoring Equipment

3.2.1.     As referred to in the Technical Memorandum (TM) issued under the Noise Control Ordinance (NCO), sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0dB.

3.2.2.     Noise measurements should not be made in accordance with standard acoustical principles and practices in relation to weather conditions.

3.2.3.     The ET Leader is responsible for the availability of monitoring equipment.  He shall ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring.  All the equipment and associated instrumentation shall be clearly labelled.

3.3.        Monitoring Locations

3.3.1.     The only potential noise sensitive receiver (NSR) is the HKAPA outdoor arena, as discussed in Section 1.3.  However, this is rarely used during the day, so it is suggested that monitoring is carried out at the Central Barracks.  The proposed location (labelled A20) is shown in Figure 2.2.  No schools exist within the project area.

3.3.2.     The status and locations of noise sensitive receivers may change after issuing this manual.  If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from the ER and agreement from the IC(E) and EPD of the proposal.

3.3.3.     When alternative monitoring locations are proposed, the monitoring locations shall be chosen based on the following criteria :

·           at locations close to the major site activities which are likely to have noise impacts;

·           close to the noise sensitive receivers (for the purposes of this section, any domestic premises, hotel, hostel, temporary housing accommodation, hospital, medical clinic, educational institution, place of public worship, library, court of law, performing art centre shall be considered as a noise sensitive receiver); and

·           for monitoring locations located in the vicinity of the sensitive receivers, care shall be taken to cause minimal disturbance to the occupants during monitoring.

3.3.4.     The monitoring station shall normally be at a point 1m from the exterior of the sensitive receivers building façade and be at a position 1.2m above the ground. If there is problem with access to the normal monitoring position, an alternative position may be chosen, and a correction to the measurements shall be made. For reference, a correction of +3dB(A) shall be made to the free field measurements. The ET Leader shall agree with the IC(E) on the monitoring position and the corrections adopted.  Once the positions for the monitoring stations are chosen, the baseline monitoring and the impact monitoring shall be carried out at the same positions.

3.4.        Baseline Monitoring

3.4.1.     The ETL shall carry out baseline noise monitoring prior to the commencement of the construction works. The baseline monitoring shall comprise one Leq (30 minutes) measurement per day (07:00 to 19:00 hours) at the monitoring location for a period of 14 days. In addition, 3 measurements for Leq (5 minutes) between the hours of 19:00 – 23:00 shall be undertaken per day at the same location. Total numbers of samples required will be: 14 Leq (30 minutes) measurements and 42 Leq (5 minutes) measurements. Before commencing the baseline monitoring, the ET Leader shall inform the IC(E) of the baseline monitoring programme such that the IC(E) can conduct on-site audit to ensure accuracy of the baseline monitoring results.

3.4.2.     There shall not be any noise impacts from construction activities in the vicinity of the stations during the baseline monitoring.

3.4.3.     In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with the IC(E) and EPD to agree on an appropriate set of data to be used as a baseline reference and submit to the ER for approval.

3.5.        Impact Monitoring

3.5.1.     Noise monitoring shall be carried out at the Central Barracks on a per week basis when noise generating activities are underway:

·           one Leq (30 minutes) measurement between 0700-1900 hours on normal weekdays;

3.5.2.     It is not considered necessary to conduct noise monitoring during the nightime.  General Construction work carried out during restricted hours is controlled by the CNP system under the NCO.

3.5.3.     In case of non-compliance with the construction noise criteria, more frequent monitoring, as specified in the Action Plan in Section 3.6 shall be carried out. This additional monitoring shall be continued until the recorded noise levels are rectified or proved to be irrelevant to the construction activities.

3.6.        Event and Action Plan for Noise

3.6.1.     The Action and Limit levels for construction noise are defined in Table 3.1. Should non-compliance of the criteria occur, action in accordance with the Action Plan in Table 3.2 shall be carried out.

Table 3.1  :  Action and Limit Levels for Construction Noise

Time Period

Action

Limit

0700-1900 hrs on normal weekdays

When one documented complaint is received

75* dB(A)

*        reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods.

Table 3.2  :  Event/Action Plan for Construction Noise

Event

Action

ET Leader

IC(E)

ER

Contractor

Action Level

1.         Notify IC(E) and Contractor

2.         Carry out investigation

3.         Report the results of investigation to the IC(E) and Contractor

4.         Discuss with the Contractor and formulate remedial measures

5.         Increase monitoring frequency to check mitigation effectiveness

1.         Review the analysed results submitted by the ET

2.         Review the proposed remedial measures by the Contractor and advise the ER accordingly

3.         Supervise the implementation of remedial measures

1.         Confirm receipt of notification of failure in writing

2.         Notify Contractor

3.         Require Contractor to propose remedial measures for the analysed noise problem

4.         Ensure remedial measures are properly implemented

1.         Submit noise mitigation proposals to IC(E)

2.         Implement noise mitigation proposals

Limit Level

1.         Notify IC(E), ER, EPD and Contractor

2.         Identify source

3.         Repeat measurement to confirm findings

4.         Increase monitoring frequency

5.         Carry out analysis of Contractor's working procedures to determine possible mitigation to be implemented

6.         Inform IC(E), ER and EPD the causes & actions taken for the exceedances

7.         Assess effectiveness of Contractor's remedial actions and keep (C(E), EPD and ER informed of the results

8.         If exceedance stops, cease additional monitoring

1.         Discuss amongst ER, ET, and Contractor on the potential remedial actions

2.         Review Contractor's remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly

3.         Supervise the implementation of remedial measures

1.         Confirm receipt of notification of failure in writing

2.         Notify Contractor

3.         Require Contractor to propose remedial measures for the analysed noise problem

4.         Ensure remedial measures are properly implemented

5.         If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated

1.         Take immediate action to avoid further exceedance

2.         Submit proposals for remedial actions to IC(E) within 3 working days of notification

3.         Implement the agreed proposals

4.         Resubmit proposals if problem still not under control

5.         Stop the relevant portion of works as determined by the ER until the exceedance is abated

 

3.7.        Noise Mitigation Measures

3.7.1.     The Contractor shall implement mitigation measures in accordance with the EIA Schedule in Section 9 of this EM&A Manual.

3.7.2.     If the mitigation measures listed in Section 9 of this EM&A Manual are not sufficient to restore the construction noise quality to acceptable levels upon the advice of ET Leader, the Contractor shall liaise with the ET Leader on some other mitigation measures, propose them to the ER for approval, and carry out the mitigation measures.

 


4.           MARINE Water Quality

4.1.        Marine Water Quality Parameters

4.1.1.     Monitoring of turbidity in NTU, dissolved oxygen (DO) in mg/l and suspended solids (SS) in mg/l, shall be carried out by the ET to ensure that any deteriorating water quality is readily detected and timely action can be taken to rectify the situation. The former two parameters are measured in-situ while the latter one is determined in the laboratory.

4.1.2.     In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, water depth, water temperature, salinity, DO saturation, pH value, weather conditions, sea conditions, tidal stage, any special phenomena and work underway at the construction site and any other relevant information.

4.1.3.     A sample monitoring record sheet is shown in Figure 4.1 for reference.

4.2.        Monitoring Equipment

4.2.1.     All monitoring equipment shall be provided by the ET and approved by the ER.

Dissolved oxygen and temperature measuring equipment

4.2.2.     The instrument shall be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

·           a dissolved oxygen level in the range of 0‑20 mg/l and 0‑200% saturation; and

·           a temperature of 0‑45° C.

4.2.3.     It shall have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables shall be available for replacement where necessary (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.2.4.     Should salinity compensation not be built-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

4.2.5.     The instrument shall be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment shall use a DC power source. It shall have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Suspended Solids

4.2.6.     A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres and can be effectively sealed with latex cups at both ends.  The sampler shall also have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

4.2.7.     Water samples for suspended solids measurement should be collected in high density polythene bottles, packed in ice (cooled to 4°C without being frozen), and delivered to the laboratory as soon as possible after collection.

Water Depth Detector

4.2.8.     A portable, battery-operated echo sounder should be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

Salinity

4.2.9.     A portable salinometer capable of measuring salinity in the range of 0-40ppt shall be provided for measuring salinity of the water at each monitoring location.

4.3.        Location of the monitoring sites

4.3.1.     A hand-held or boat-fixed type digital Global Positioning System (GPS) with way point bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

4.3.2.     All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring.  Responses of sensors and electrodes shall be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

4.3.3.     For the on site calibration of field equipment, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" shall be observed.

4.3.4.     Sufficient stocks of spare parts shall be maintained for replacements when necessary.  Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.4.        Laboratory Measurement / Analysis

4.4.1.     Analysis of suspended solids shall be carried out in a HOKLAS or other internationally accredited laboratory. Water samples of about 1,000 ml shall be collected at the monitoring stations for carrying out the laboratory SS determination. The detection limit shall be 1 mgL-1 or better.  The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 17ed 2540D or equivalent methods subject to approval of DEP.

4.4.2.     If a site laboratory is set up or a non-HOKLAS and non-international accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment, analytical procedures, and quality control shall be approved by the DEP. All the analyses shall be witnessed by the ER. The ET Leader shall provide the ER with one copy of the relevant chapters of the "Standard Methods for the Examination of Water and Wastewater" updated edition and any other relevant document for his reference.

4.4.3.     For the testing methods of other parameters as recommended by the EIA or required by DEP, detailed testing methods, pre-treatment procedures, instrument use, Quality Assurance/Quality Control (QA/QC) details (such as blank, spike recovery, number of duplicate samples per batch, etc.), detection limits and accuracy shall be submitted to DEP for approval prior to the commencement of monitoring programme.  The QA/QC shall be in accordance with the requirement of HOKLAS or international accredited scheme.  The QA/QC results shall be reported.  EPD may also request the laboratory to carry out analysis of known standards provided by EPD for quality assurance.  Additional duplicate samples may be required by EPD for inter laboratory calibration.  Remaining samples after anaysis shall be kept by the laboratory for 3 months in case repeat analysis is required.  If in-house or non-standard methods are proposed, details of the method verification may also be required to be submitted to DEP.  In any circumstance, the sample testing shall have comprehensive quality assurance and quality control programme.  The laboratory shall be prepared to demonstrate the programmes to DEP or his representatives when requested.

4.5.        Monitoring Locations

4.5.1.     The marine water quality monitoring stations during the construction works are shown in Figure 4.2.  These stations are chosen based on the following criteria :

i.               Close to the sensitive receivers (that is, the seawater intakes of the operating saltwater pumping stations) which are directly or likely to be affected.  These intakes will be relocated as the reclamation proceeds.  Water Quality monitoring at the re-provisioned intakes will continue at these re-provisioned intakes after the re-provisioned pumping stations have been commissioned and are operational. For monitoring locations located in the vicinity of the sensitive receivers, care should be taken to cause minimal disturbance during monitoring;

ii.             At the boundary of the mixing zones so as to verify predictive assessment results; and

iii.           Two control stations that shall be at locations representative of the project site in its undisturbed condition.  Control stations should be located, as far as is practicable, both upstream and downstream of the works area.

The co-ordinates of the proposed initial monitoring stations are listed in Table 4.1.  As shown in Figure 4.2, the proposed locations for the sensitive receiver monitoring stations represent the sensitive receivers that are predicted to be affected during the initial construction.  Sensitive receivers at the boundary of the mixing zone have not been indicated as they will depend upon the Contractor's work sequencing and will need to be determined immediately prior to commencing reclamation works. It should also be noted that the control stations shown in Figure 4.2 are indicative and subject to further review before construction phase.  During this review, the location of the impact stations for the boundary of the mixing zones shall also be re-visited.  Revisions to station locations shall be submitted to EPD for approval four weeks before commencement of baseline monitoring.

Table 4.1  : Proposed Water Quality Monitoring Stations

Station Ref.

E

N

1.      Princess Building Group / Mandarin Hotel

834,514.5

816,093.0

2.      HSBC Headquarters Building Intakes

834,644.0

816,026.5

3.      Murray Road Carpark Group / Central Government Offices Group / Furama Hotel Intakes

834,780.5

815,987.5

4.      Central Barracks Intake

835,002.0

815,985.5

5.      Queensway Government Offices Group / Pacific Place Intakes

835,409.0

815,839.0

6.      MTRC South Intakes

835,597.5

815.857.0

7.      Control Station 1

829,349.0

818,629.0

8.      Control Station 2

844,170.0

814,880.0

Control stations are necessary to compare the water quality from potentially impacted sites with the ambient water quality.  Control stations shall be located within the same body of water as the impact monitoring stations but should be outside the area of influence of the works and, as far as practicable, not affected by any other works.  Measurements shall be taken at 3 water depths, namely, 1 m below water surface, mid-depth and 1 m above seabed, except where the water depth is less than 6m, the mid-depth station may be omitted.  At monitoring stations coincident with seawater intakes, the SS and turbitity measurements should make reference to the vertical levels of the individual intake pipes.  Should the water depth be less than 3m, only the mid-depth station will be monitored.  The ET Leader shall seek approval from the IC(E) and DEP on all monitoring station locations.  The status and locations of water quality sensitive receivers may change after issuing this manual.  If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from the IC(E) and DEP.

4.5.2.     When alternative monitoring locations are proposed, they should be chosen based on the following criteria:

·           at locations close to and preferably at the boundary of the mixing zone of the major site activities as indicated in the EIA Final Report, which are likely to have water quality impacts;

·           close to the sensitive receptors which are directly or likely to be affected;

·           for monitoring locations located in the vicinity of the sensitive receptors, care should be taken to cause minimal disturbance during monitoring; and

·           at two or more control stations which shall be at locations representative of the project site in its undisturbed condition. Control stations should be located, as far as is practicable, both upstream and downstream of the works area.

4.6.        Baseline Monitoring

4.6.1.     Baseline conditions for water quality shall be established and agreed with the DEP prior to the commencement of works. The purposes of the baseline monitoring are to establish ambient conditions prior to the commencement of the works and to demonstrate the suitability of the proposed impact, control and reference monitoring stations. The baseline conditions shall normally be established by measuring the water quality parameters specified in Section 4.1. The measurements shall be taken at all designated monitoring stations including control stations, 3 days per week, at mid-flood and mid-ebb tides, for four weeks prior to the commencement of marine works.

4.6.2.     There shall not be any marine construction activities in the vicinity of the stations during the baseline monitoring.

4.6.3.     In the exceptional cases when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall seek approval from the IC(E) and DEP on an appropriate set of data to be used as baseline reference.

4.6.4.     Baseline monitoring schedule shall be faxed to EPD two weeks prior to commencement of baseline monitoring.  The interval between 2 sets of monitoring shall be less than 36 hours.

4.6.5.     Replicate in-situ measurements and sample collected from each independent sampling event are required for all parameters to ensure a robust statistically interpretable database.

4.7.        Impact Monitoring

4.7.1.     During the course of the marine works, monitoring shall be undertaken three days per week, at mid-flood and mid-ebb tides, with sampling/measurement at the designated monitoring stations.  The interval between two sets of monitoring shall not be less than 36 hours except where there are exceedances of Action and/or Limit levels, in which case the monitoring frequency will be increased.

4.7.2.     Upon completion of all marine activities, a post project monitoring exercise on water quality shall be carried out for four weeks in the same manner as the impact monitoring.

4.7.3.     Proposed water quality monitoring schedule shall be faxed to EPD two weeks before the first day of the monitoring month.  EPD shall also be notified immediately for any changes in schedule by fax.

4.7.4.     Replicate in-situ measurements and sample collected from each independent sampling event are required for all parameters to ensure a robust statistically interpretable database.

4.8.        Event and Action Plan for Water Quality

4.8.1.     The water quality criteria, namely Action and Limit levels are based on the results of baseline monitoring and WQO of the relevant Water Control Zone and are shown in Table 4.2. Should the monitoring results of the water quality parameters at any designated monitoring station indicate that the water quality criteria are exceeded, the actions in accordance with the Action Plan in Table 4.3 shall be carried out.  Water Supplies Department have requested that they should be informed in case the Action and Limit Levels at their seawater intake points have been exceeded.

Table 4.2  :  Action and Limit Levels for Water Quality

Parameters

Action

Limit

DO in mg/l

(Surface, Middle & Bottom)

Surface & Middle

1%-ile of baseline data for surface and middle layer; or

Midway between 5%-ile of baseline data and limit level

Bottom

1%-ile of baseline data for bottom layer; or
Midway between 5%-ile of baseline data and limit level

Surface & Middle

4 mg/l except 5 mg/l for FCZ

or

1%-ile of baseline data for surface and middle layer

Bottom

2 mg/l

or

1%-ile of baseline data for bottom layer

SS in mg/l

(depth-averaged)

95%-ile of baseline data or 120% of upstream control station's SS at the same tide of the same day

99%-ile of baseline, 130% of upstream control station's SS at the same tide of the same day and specific sensitive receiver water quality requirements (e.g. required suspended solids level for concerned sea water intakes)

Turbidity (Tby) in NTU

(depth-averaged)

95%-ile of baseline data or 120% of upstream control station's Tby at the same tide of the same day

99%-ile of baseline or 130% of upstream control station's Tby at the same tide of the same day

Notes:   -     For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

             -     For SS and Tby, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

             -     All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered necessary.

 

 

 

 

 

 

 

 

 

 

 

Table 4.3  :  Event and Action Plan for Water Quality

Event

ET Leader

IC(E)

ER

Contractor

Action level being exceeded by one sampling day

1. Repeat in-situ measurement to confirm findings;

2. Identify source(s) of impacts;

3. Inform IC(E) and Contractor;

4. Check monitoring data, all plant, equipment and Contractor's working methods;

5. Discuss mitigation measures with IC(E) and Contractor;

6. Repeat measurement on next day of exceedance.

1.         Discuss with ET and Contractor on the mitigation measures;

2.         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.         Assess the effectiveness of the implemented mitigation measures.

1. Discuss with IC(E) on the proposed mitigation measures;

2. Make agreement on the mitigation measures to be implemented.

 

1.   Inform the ER and confirm notification of the non-compliance in writing;

2.   Rectify unacceptable practice;

3.Check all plant and equipment;

4. Consider changes of working methods;

5. Discuss with ET and IC(E) and propose mitigation measures to IC(E) and ER;

6. Implement the agreed mitigation measures.

Action level being exceeded by more than one consecutive sampling day

1. Repeat in-situ measurement to confirm findings;

2. Identify source(s) of impact;

3. Inform IC(E) and Contractor;

4. Check monitoring data, all plant, equipment and contractor's working methods;

5. Discuss mitigation measures with IC(E) and Contractor;

6. Ensure mitigation measures are implemented;

7. Prepare to increase the monitoring frequency to daily;

8. Repeat measurement on next day of exceedance.

1.         Discuss with ET and Contractor on the mitigation measures;

2.         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.         Assess the effectiveness of the implemented mitigation measures.

1. Discuss with IC(E) on the proposed mitigation measures;

2. Make agreement on the mitigation measures to be implemented;

3. Assess the effectiveness of the implemented mitigation measures.

1. Inform the Engineer and confirm notification of the non-compliance in writing;

2. Rectify unacceptable practice;

3.   Check all plant and equipment;

4.   Consider changes of working methods;

5.   Discuss with the ET and IC(E) and propose mitigation measures to IC(E) and ER within 3 working days;

6.   Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day

1. Repeat in-situ measurement to confirm findings;

2. Identify source(s) of impact;

3. Inform IC(E) Contractor and EPD;

4. Check monitoring data, all plant, equipment and Contractor's working methods

5. Discuss mitigation measures with IC(E), ER and Contractor

6. Ensure mitigation measures are implemented

7. Increase the monitoring frequency to daily until no exceedance of Limit Level.

1.         Discuss with ET and Contractor on the mitigation measures;

2.         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.         Assess the effectiveness of the implemented mitigation measures.

1. Discuss with IC(E), ET and Contractor on the proposed mitigation measures;

2. Request Contractor to critically review the working methods;

3. Make agreement on the mitigation measures to be implemented;

4. Assess the effectiveness of the implemented mitigation measures.

1.Inform the Engineer and confirm notification of the non-compliance in writing;

2. Rectify unacceptable practice;

3. Check all plant and equipment;

4. Consider changes of working methods

5. Discuss with ET and IC(E) and propose mitigation measures to IC(E) and ER within 3 working days;

6. Implement the agreed mitigation measures.

 

Limit level being exceeded by more than one consecutive sampling day

1. Repeat in-situ measurement to confirm findings;

2. Identify source(s) of impact

3. Inform IC(E), Contractor and EPD;

4. Check monitoring data, all plant, equipment and Contractor's working methods

5. Discuss mitigation measures with IC(E), ER and Contractor;

6. Ensure mitigation measures are implemented;

7. Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days.

1.         Discuss with ET and Contractor on the mitigation measures;

2.         Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.         Assess the effectiveness of the implemented mitigation measures.

1. Discuss with IC(E), ET and Contractor on the proposed mitigation measures;

2. Request Contractor to critically review the working methods;

3. Make agreement on the mitigation measures to be implemented;

4. Assess the effectiveness of the implemented mitigation measures;

5. Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the marine work until no exceedance of Limit Level.

1. Inform the ER and confirm notification of the non-compliance in writing;

2. Rectify unacceptable practice;

3. Check all plant and equipment;

4. Consider changes of working methods;

5. Discuss with ET, IC(E) and ER and propose mitigation measures to IC(E) and ER within 3 working days;

6. Implement the agreed mitigation measures;

7. As directed by the Engineer, slow down or stop all or part of the marine work or construction activities.

 

4.9.        Water Quality Mitigation Measures

4.9.1.     The EIA report has recommended water quality control and mitigation measures. The contractor shall be responsible for the design and implementation of these measures. The proposed measures are given in Section 9 of this EM&A Manual.

4.9.2.     If the measures listed in Section 9 are not sufficient to restore the water quality to an acceptable levels upon the advice of the ET Leader, the Contractor shall liaise with the ET Leader on some other mitigation measures, propose to IC(E) and ER for approval, and carry out the mitigation measures.

 


5.           Waste Management

5.1.        Waste Management

5.1.1.     The contractor shall be  responsible for waste control within the construction site, removal of the waste material produced from the site and implementation of any mitigation measures to minimise waste or redress problems arising from the waste from the site. The waste material may include any tunnel spoil, sewage, waste water or effluent containing sand, cement, silt or any other suspended or dissolved material which may  flow from the site onto any adjoining land, storm sewer, sanitary sewer, or any waste matter or refuse to be deposited anywhere within the site or onto any adjoining land.

5.1.2.     The implementation schedule of the recommended mitigation measures for waste management is presented in Section 9 of this EM&A Manual and the provisions therein should be properly enforced.

5.1.3.     When handling the waste material, the following measures shall be undertaken:

·           the strategy for management and disposal of all wastes arising from execution of individual projects shall be based on the principle of segregation and re-use on site followed by disposal to reclamation, public fill or land fill as appropriate;

·           it is not anticipated that bulk excavations will be carried out in the underlying mud and any limited quantities of mud which may arise will be disposed of at marine disposal ground in accordance with WBTC 3/2000;

·           where surplus excavated material is to be exported from the tunnel excavations to public fill, this should be carried out by marine transfer if at all possible. It is recommended that a barge loading point be provided to facilitate transfer of suitable material to public fill which are accessible by barge and which can be equipped with off loading facilities. Public filling areas will be designated by the Public Filling Sub-committee of the Fill Management Committee;

·           disposal of other construction wastes arising as a result of construction of structures and buildings is governed by the EPD policy on disposal for construction waste. The principles established maximise re-use of materials on site and segregation of wastes to ensure that the minimum quantities are disposed of to landfill and that the maximum is directed for disposal off-site to reclamation by public filling. All construction waste should therefore be sorted on site into inert and non-inert materials;

·           non-inert materials including wood and other materials including glass, plastics, and metals should be disposed of a landfill. Other inert materials including, sand, and rubble, are to be separated from non-inert and disposed of as public fill;

·           site fencing, scaffolding and timber for the building work should be reused where possible. Those materials that cannot be re-used should be disposed of at landfill; and

·           paint residues, lubricants and other oily wastes are classified as chemical waste under the Waste Disposal (Chemical Waste) (General) Regulations and special controls are imposed to regulate storage, labelling transport and disposal at the Chemical Waste Treatment Facility. Construction sites must register individual as chemical waste producers to comply with regulations.

5.1.4.     The contractor shall pay attention to the Waste Disposal Ordinance, the Dumping at Sea Ordinance, the Public Health and Municipal Services Ordinance and the Water Pollution Control Ordinance, and carry out the appropriate waste management work. The relevant licences/permits, such as the effluent discharge license, the chemical waste producer registration, etc. shall be obtained. The contractor shall refer to  relevant booklets issued by EPD when applying for licenses/permits.

5.1.5.     During the site inspections and the document review procedures, the ETL shall pay special attention to the issues relating to waste management, and check whether the contractor has followed the relevant contract specifications and the procedures specified under the laws of Hong Kong.

 

 


6.           Landscape and Visual

6.1.        Mitigation

6.1.1.     Mitigation requirements as identified in the EIA are provided in Section 9 of this EM&A Manual.  These requirements were derived as a result of a Landscape and Visual Impact Assessment undertaken - details of this assessment are provided in Chapter 14 of the EIA Report.

6.2.        Monitoring and Audit Requirements

6.2.1.     Monitoring and audit of the design of landscaping works for the CRIII project will be undertaken through the implementation of quality assurance procedures within the designer's organisation.  Independent checking and verification of designs to ensure that mitigation measures are incorporated into the design will be ensured through the submission of design proposals to relevant Government Departments.

6.2.2.     Monitoring of landscaping works to be undertaken as part of the CRIII project will to a large extent be conducted through site inspections to ensure that works are implemented in accordance with specifications. In addition, it is normal for the landscape contractor to provide on site maintenance for 12 months following completion of works.

6.2.3.     During the monitoring and audit of noise, dust and runoff, visual inspection with regard to condition of landscaping works, tree protection and preservation measures and implementation of temporary landscape treatments should be made.  The findings of these inspections shall be reported in the monthly audit reports.

 


7.           Site Environmental Audit

7.1.        Site Surveillance

7.1.1.     Site Surveillance provides a direct means to assess and ensure that the project's environmental protection and pollution control measures are in compliance with the contract specifications. Site surveillance shall be undertaken regularly and routinely by the Environmental Monitoring Team to inspect the construction activities in order to ensure that appropriate environmental protection and pollution control mitigation measures are implemented in accordance with the EIA recommendations. With well defined pollution control and impact mitigation specifications and an established, efficient and remedial action reporting system, the site inspection is an effective tool to ensure acceptable environmental performance on the construction site.

7.1.2.     The ET Leader is responsible for formulation of the environmental site inspection, deficiency and remedial action reporting system, and for carrying out the site inspection works. He shall in consultation with the IC(E) prepare a procedure for the site inspection, deficiency and remedial action reporting requirements; and submit to the Contractor for agreement and to the ER for approval, within 21 days of commencement of the construction contract.

7.1.3.     Regular site inspections shall be carried out at least once per week for all works areas. The inspections shall cover the environmental situation, pollution control and mitigation measures within the site; they shall also review the environmental situation outside the site area which is likely to be affected, directly or indirectly, by the site activities. The ET Leader shall make reference to the following information in conducting the inspections:

·           the EIA Report recommendations and requirements on environmental protection and pollution control mitigation measures;

·           works progress, programmes, site/aerial photos and site plans;

·           individual construction works methodology proposals (which shall include proposals on associated pollution control measures);

·           the contract specifications for environmental protection and pollution prevention control;

·           the relevant environmental protection and pollution control laws, Pro PECC Notes; and

·           previous site inspection results.

7.1.4.     The Contractor shall update the ET Leader with all relevant information of the construction contract for him to carry out the site inspections. The inspection report results and its recommendations for any necessary improvements in the project's environmental performance shall be submitted, in a site inspection performa, to the IC(E) and the Contractor within 24 hours, for reference and the taking of immediate remedial  action. The Contractor shall follow the procedures and time-frame as stipulated in the environmental site inspection, deficiency and remedial action reporting system (formulated by the ET Leader) to report on any remedial measures subsequent to the site inspections.

7.1.5.Ad hoc site inspections shall also be carried out by the ET and / or IC(E) if major unacceptable or unforeseen environmental problems are identified. Inspections may also be required subsequent to receipt of an environmental complaint, or as part of the investigation work, as specified in the Action Plan for environmental monitoring and audit.

7.2.        Environmental Compliance

7.2.1.     There are contractual environmental protection and pollution control requirements as well as environmental protection and pollution prevention and control laws in Hong Kong with which the construction activities shall comply.

7.2.2.     The ET Leader shall also review the progress and programme of the works to check that relevant environmental laws have not been violated, and that any foreseeable potential for violating the laws can be prevented.

7.2.3.     The Contractor shall regularly copy relevant documents to the ET Leader so that the checking of the project's environmental performance can be carried out effectively. The documents to be submitted by the Contractor shall include at least the updated Work Progress Reports, the Works Programme, application for any necessary licenses/permits under the environmental protection laws, and all the valid licenses/permits received to date. The site diary shall also be available for the ET Leader's inspection upon his request.

7.2.4.     After reviewing the document, the ET Leader shall advise the ER and the Contractor of any non-compliance with the project contractual and legislative requirements on environmental protection and pollution control.  The Contractor shall take follow-up and appropriate remedial actions. If the ET Leader’s review concludes that the current status on license/permit applications and any planned environmental protection and pollution control works may not cope with the works programme or potential violation of environmental protection and pollution control requirements may arise, he shall advise the Contractor and the ER accordingly.  The review shall be copied to the IC(E) for follow-up action.

7.2.5.     Upon receipt of the advice, the Contractor shall undertake immediate action to remedy the situation.  The ER shall follow up to ensure that appropriate action has been taken by the Contractor in order that the project's environmental protection and pollution control requirements are fulfilled.

7.3.        Choice of Construction Method

7.3.1.     At times during the construction phase the Contractor may submit method statements for various aspects of construction (other than those construction methods that the EIA study has not imposed conditions; for construction methods that have been assessed in the EIA study the Contractor is bound to follow the requirements and recommendations in the EIA study).  Contractor's options for alternative construction methods may introduce adverse environmental impacts into the project.  It is the responsibility of the Environmental Monitoring Team Leader and the Environmental Monitoring Team, in accordance with established standards, guidelines and EIA study recommendation to review and determine the adequacy of the environmental protection and pollution control measures in the Contractor's proposal in order to ensure no unacceptable impacts would result.  To achieve this end, the Environmental Monitoring Team Leader shall provide a completed copy of a Proactive Environmental Protection Proforma to the IC(E) for approval.  The IC(E) shall audit the review of the construction method and endorse the proposal on the basis of no adverse environmental impacts as per all Environmental Permit Conditions, EIA Study recommendations and reports, ACE conditions and any endorsed public comments related to the project and/or any established standards or guidelines.

7.4.        Environmental Complaints

7.4.1.     Complaints shall be referred to the ET Leader for carrying out complaint investigation procedures. The ET Leader shall undertake the following procedures upon receipt of any complaints:

·           log complaint and date of receipt onto the complaint database and inform the IC(E) immediately;

·           investigate the complaint to determine its validity, and to assess whether the source of the problem is due to project works;

·           if a complaint is valid and due to project works, identify mitigation measures in consultation with the IC(E);

·           if mitigation measures are required, advise the Contractor accordingly;

·           review the Contractor’s implementation of the identified and required mitigation measures, and the current situation;

·           if the complaint is transferred from EPD, submit interim report to EPD on status of the complaint investigation and follow-up action within the time frame assigned by EPD;

·           undertake additional monitoring and audit to verify the compliant if necessary, and ensure that any valid reason for complaint does not recur through proposed amendments to work methods, procedures, machines and/or equipment, etc;

·           report the investigation results and the subsequent actions to the complainant (if the source of complaint is identified through EPD, the results should be reported within the time frame assigned by EPD); and

·           log a record of the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.

7.4.2.     During the complaint investigation work, the Contractor and ER shall co-operate with the ET Leader in providing all the necessary information and assistance for completion of the investigation. If mitigation measures (in consultation with the IC(E)) are required following the investigation, the Contractor shall promptly carry out the measures.  The ER shall ensure that the measures have been carried out by the Contractor.  The complaints handling procedure is shown in Table 7.1.

Table 7.1 : Procedures in the Event of a Complaint

Step

Action

Responsible Party

ET

ER

Contractor

IC(E)

1.

The party who receives the complaint shall notify other parties on the same day :

·         ET notifies ER and the Contractor; or

·         The Contractor notifies ET and ER; or

·         ER notifies ET and the Contractor

Ö

Ö

Ö

 

 

2.

Check workers and sub-contractor's working methods and remind them of their contractual obligations.

 

 

Ö

 

 

3.

If complaint is related to noise, dust or water quality, ER may instruct ET to increase monitoring frequency and to verify the validity of the complaint.  ET notifies ER and the Contractor of the monitoring results.

Ö

Ö

 

 

 

4.

Discuss with the Contractor about the complaint and remedial measures within one day when feasible.

Ö

Ö

 

 

 

5.

Implement remedial measures on the same day if feasible.

 

 

Ö

 

 

6.

If complaint is related to noise, dust or water quality, ER may instruct ET to increase monitoring frequency to assess the efficacy of the remedial actions.  Notify the Contractor of the monitoring results.

Ö

Ö

 

 

 

7.

May increase site audit frequency to assess efficacy of remedial measures.  Inform the Contractor of the effect of the remedial measures.

 

 

 

Ö

 

8.

Party who received the complaint shall inform the complainant of the actions taken.

Ö

Ö

Ö

 

 

 

 


8.           REPORTING

8.1.        General

8.1.1.     The following reporting requirements are based upon a paper documented approach. However, the same information can be provided in an electronic medium upon agreeing the format with the ER and EPD.  All the monitoring data (baseline and impact) shall also be submitted in diskettes in an agreed format.

8.2.        Baseline Monitoring Report

8.2.1.     The ET Leader shall prepare and submit a Baseline Environmental Monitoring Report within 10 working days of completion of the baseline monitoring. Copies of the Baseline Environmental Monitoring Report shall be submitted to each of the four parties: the Contractor, the IC(E), the ER, and the EPD. The ET Leader shall liaise with the relevant parties on the exact number of copies required.  The form and content of the report, and the representation of baseline monitoring data shall be in a format to the satisfaction of EPD and include, but not be limited to the following :

·           up to half a page executive summary;

·           brief project background information;

·           drawings showing locations of the baseline monitoring stations;

·           an updated construction programme with milestones of environmental protection / mitigation activities annotated;

·           monitoring results (in both hard and diskette copies) together with the following information:

-           monitoring methodology;

-           name of laboratory used type of equipment used and calibration details;

-           parameters monitored;

-           monitoring locations (and depth);

-           monitoring date, time, frequency and duration; and

-           QA/QC results and detection limits.

·           details on influencing factors, including:

-           major activities, if any, being carried out on the site during the period;

-           weather conditions during the period; and

-           other factors which might affect the results.

·           determination of the Action and Limit Levels (AL Levels) for each monitoring parameter and statistical analysis of the baseline data.  The analysis shall conclude if there is any significant difference between control and impact stations for the parameters monitored;

·           revisions for inclusion in the EM&A Manual; and

·           comments and conclusions.

8.3.        Monthly EM&A Reports

8.3.1.     The ETL shall undertake all reporting during the course of the construction works which shall be reviewed by the IC(E) to determine that the reporting has been carried out in accordance with the requirements of the Manual.

8.3.2.     The results and findings of all EM&A work required in the Manual shall be recorded in the monthly EM&A Reports prepared by the ET Leader. The EM&A Report shall be endorsed by the IC(E) and submitted within 10 working days of the end of each reporting month, with the first report due in the month after construction commences. A maximum of 4 copies of each monthly EM&A Report shall be submitted to each of the four parties: the Contractor, the IC(E), the ER, and the EPD. Before submission of the first EM&A Report, the ET Leader shall liaise with the parties on the exact number of copies and format of the monthly reports in both hard copy and electronic medium requirement.  The ET Leader shall review the number and location of monitoring stations and parameters to monitor every 6 months or on an as needed basis in order to cater for the changes in the surrounding environment and nature of works in progress.

First Monthly EM&A Report

8.3.3.     The first monthly EM&A report shall include at least, but not be limited to, the following :

·           Executive Summary (1 - 2 pages) :

-           Breaches of AL levels;

-           Complaint Log;

-           Notifications of any summons and successful prosecutions;

-           Reporting Changes;

-           Future key issues.

·           Basic Project Information :

-           Project organisation including key personnel contact names and telephone numbers;

-           Construction Programme with fine tuning of construction activities showing the inter-relationship with environmental protection/mitigation measures for the month;

-           Management structure; and

-           Works undertaken during the month.

 

 

·           Environmental Status :

-           Works undertaken during the month with illustrations (such as location of works, daily dredging/filling rates, percentage fines in the fill material used); and

-           Drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.

·           Summary of EM&A requirements :

-           All monitoring parameters;

-           Environmental quality performance limits (Action and Limit levels);

-           Event-Action Plans;

-           Environmental mitigation measures, as recommended in the project EIA study final report;

-           Environmental requirements in contract documents;

·           Implementation Status :

Advice on the implementation status of environmental protection and pollution control/mitigation measures including measures for ecological and landscape and visual impacts, as recommended in the project EIA study report, summarised in the updated implementation schedule;

·           Monitoring Results :

To provide monitoring results (in both hard and diskette copies) together with the following information:

-           Monitoring methodology;

-           Name of laboratory and types of equipment used and calibration details;

-           Parameters monitored;

-           Monitoring locations (and depth);

-           Monitoring date, time, frequency, and duration;

-           Weather conditions during the period;

-           Graphical plots of the monitored parameters in the month annotated against;

i.      The major activities being carried out on site during the period;

ii.    Weather conditions that may affect the result; and

iii.  Any other factors which might affect the monitoring results.

-           Any other factors which might affect the monitoring results; and

-           QA/QC results and detection limits.

·           Report on Non-compliance, Complaints, Notifications of Summons and Successful Prosecutions

-           Record of all noncompliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

-           Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

-           Record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

-           Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and

-           Description of the actions taken in the event of noncompliance and deficiency reporting and any follow-up procedures related to earlier noncompliance.

·           Others

-           An account of the future key issues as reviewed from the works programme and work method statements;

-           Advice on the solid and liquid waste management status; and

-           Submission of implementation status proforma, proactive environmental protection proforma, regulatory compliance proforma, site inspection proforma, data recovery schedule and complaint log summarizing the EM&A of the period.

Subsequent Monthly EM&A Report

8.3.4.     The subsequent monthly EM&A reports shall include the following :

·           Executive Summary (1-2 pages)

-           Breaches of AL levels ;

-           Notification of any summons and successful prosecutions;

-           Complaint Log;

-           Reporting Changes; and

-           Future key issues.

·           Environmental Status

-           Construction Programme with fine tuning of construction activities showing the inter-relationship with environmental protection/mitigation measures for the month;

-           Works undertaken during the month with illustrations including key personnel contact names and telephone numbers; and

-           Drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.

·           Implementation Status

Advice on the implementation status of environmental protection and pollution control/mitigation measures including measures for ecological and visual impacts, as recommended in the project EIA study report, summarised in the updated implementation schedule.

·           Monitoring Results

To provide monitoring results (in both hard and diskette copies) together with the following information :

-           Monitoring methodology;

-           Name of laboratory and types of equipment used and calibration details;

-           Parameters monitored;

-           Monitoring locations (and depth);

-           Monitoring date, time, frequency, and duration;

-           Weather conditions during the period;

-           Graphical plots of the monitored parameters in the month annotated against :

i.      The major activities being carried out on site during the period;

ii.    Weather conditions that may affect the results; and

iii.  Any other factors which might affect the monitoring results.

-           Any other factors which might affect the monitoring results; and

-           QA/QC results and detection limits.

·           Report on Non-compliance, Complaints, Notifications of Summons and Successful Prosecutions

-           Record of all noncompliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

-           Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

-           Record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

-           Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and

-           A description of the actions taken in the event of noncompliance and deficiency reporting and any follow-up procedures related to earlier noncompliance;

·           Appendix

-           AL levels;

-           Graphical plots of trends of monitored parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following :

i.      Major activities being carried out site during the period;

ii.    Weather conditions during the period; and

iii.  Any other factors which might affect the monitoring results.

-           Monitoring schedule for the present and next reporting period;

-           Cumulative statistics on complaints, notifications of summons and successful prosecutions; and

-           Outstanding issues and deficiencies.

8.4.        Quarterly EM&A Summary Reports

8.4.1.     The Quarterly EM&A Summary Report which should generally be around 5 pages (including about 3 of text and tables and 2 of figures) should contain at least the following information.  Apart from these, the first quarterly summary report should also confirm that the monitoring work is proving effective and that it is generating data with the necessary statistical power to categorically identify or confirm the absence of impact attributable to the works :

·           Up to half a page executive summary;

·           Basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the quarter;

·           A brief summary of EM&A requirements including:

-           Monitoring parameters;

-           Environmental quality performance limits (Action and Limit levels); and

-           Environmental mitigation measures, as recommended in the project EIA study final reports.

·           Advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation schedule;                                  

·           Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

·           Graphical plots of the trends of monitored parameter over the past 4 months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against;

-           The major activities being carried out on site during the period;

-           Weather conditions during the period; and

-           Any other factors which might affect the monitoring results.

·           Advice on the solid and liquid waste management status;

·           A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels);

·           A brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;

·           A quarterly assessment of construction impacts on suspended solids at the project site, including, but not limited to, a comparison of the difference between the quarterly means and 1.3 times of the ambient mean, which is defined as 30% increase of the baseline data or EPD data, of the related parameters by using appropriate statistical procedures.  Suggestion of appropriate mitigation measures if the quarterly assessment analytical results demonstrate that the quarterly mean is significantly higher than the 1.3 on water quality times of the ambient mean (p < 0.05);

·           A summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;

·           A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

·           A summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, locations and nature of the breaches, investigation, follow-up actions taken and results;

·           Comments (e.g. effectiveness and efficiency of the mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions for the quarter; and

·           Proponent’s contacts and any hotline telephone number for the public to make enquiries.

8.4.2.     Each quarterly EM&A Report shall be prepared by the ET Leader and endorsed by the IC(E).  It shall be submitted within 10 working days of the end of each reporting quarter.  A maximum of 4 copies of each quarterly EM&A Report shall be submitted to each of the four parties: the Contractor, the IC(E), the ER, and the EPD. Before submission of the first quarterly EM&A Report, the ET Leader shall liaise with the parties on the exact number of copies and format of the quarterly reports in both hard copy and electronic medium requirement.

8.5.        Final EM&A Summary Report

8.5.1.     The termination of EM&A programme shall be determined on the following basis :

·           Completion of construction activities and insignificant environmental impacts fo the remaining outstanding construction works;

·           Trends anslysis to demonstrate the narrow down of monitoring exceedances due to construction activities and the return of ambient environmental conditions in comparison with baseline data; and

·           No environmental complaint and prosecution involved.

8.5.2.     The proposed termination may be required to be consulted with related local community such as District Council and the proposal should be endorsed by the IC(E), ER and the project proponent prior to final approval from the Director of Environmental Protection.

8.5.3.     The Final EM&A Report shall be prepared by the ET Leader and endorsed by the IC(E).  It shall be submitted within 10 working days of the end of the termination of the EM&A programme.  A maximum of 4 copies of the Final EM&A Report shall be submitted to each of the four parties: the Contractor, the IC(E), the ER, and the EPD. Before submission of the Final  EM&A Report, the ET Leader shall liaise with the parties on the exact number of copies and format of the report in both hard copy and electronic medium requirement.

8.5.4.     The final EM&A summary report shall include, inter alia, the following :

·           An executive summary;

·           Basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the entire construction period;

·           A brief summary of EM&A requirements including :

-           Monitoring parameters;

-           Environmental quality performance limits (Action and Limit levels); and

-           Environmental mitigation measures, as recommended in the project EIA study final report;

·           Advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation status proformas;

·           Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

·           Graphical plots of the trends of monitored parameters over the construction period for representative monitoring stations annotated against;

-           The major activities being carried out on site during the period;

-           Weather conditions during the period;

-           Any other factors which might affect the monitoring results; and

-           The return of ambient environmental conditions in comparison with baseline data;

·           Compare and contrast the EM&A data with the EIA predictions and annotate with explanation for any discrepancies;

·           Provide clear-cut decisions on the environmental acceptability of the project with reference to the specific impact hypothesis;

·           Advice on the solid and liquid waste management status;

·           A summary of noncompliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

·           A brief review of the reasons for, and the implications of, non-compliance including review of pollution sources and working procedures;

·           A summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;

·           A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

·           Review the monitoring methodology adopted and with the benefit of hindsight, comment on its effectiveness (including cost effectiveness);

·           A summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, location and nature of the breaches, investigation, follow-up actions taken and results;

·           Review the practicality and effectiveness of the EIA process and EM&A programme (e.g. effectiveness and efficiency of the mitigation measures), recommend any improvement in the EM&A programme; and

·           A conclusion to state the return of ambient and/or the predicted scenario as per EIA findings.

8.6.        Data Keeping

8.6.1.     All documentation is required to be filed in a traceable and systematic manner.  Site documents, such as, monitoring field records, laboratory analysis records, meeting minutes, correspondences etc., shall be cross-referenced by the ET Leader and be ready for inspection upon request.  All Construction Phase EM&A results and findings shall be documented in the Construction Phase EM&A reports prepared by the ET and endorsed by IC(E) prior to dissemination to the Contractor, ER and the Director of Environmental Protection. 

8.6.2.     All documentation to the Director of Environmental Protection shall be in paper form and/or electronic form (in the format in agreement with the Director) upon request.  Prior to submission, the water quality data software format shall be agreed with EPD.  All documents and data shall be kept for at least one year after the completion of the construction contract.  All submissions (reports, data, and correspondences etc.) to the Director of Environmental Protection shall be liable to use freely for the purposes of communicating environmental data and the owner of information shall claim no copyright.  Any request to treat all or part of submission in confidence will be respected, but if no such request is made it will be assumed that the submission is not intended to be confidential.

8.7.        Interim Notifications of Environmental Quality Limit Exceedances

8.7.1.     With reference to Event/Action Plans in Tables 2.3, 3.2 and 4.3, when the environmental quality limits are exceeded, the ET Leader shall immediately notify the ER and relevant Government Departments, as appropriate. The notification shall be followed up with advice to EPD on the results of the investigation, proposed action and success of the action taken, with any necessary follow-up proposals. A sample template for the interim notifications is shown in Table 8.1.

Table 8.1  : Sample Template for Interim Notifications of Environmental Quality Limits Exceedances

Project

 

Date

 

Time

 

Monitoring Location

 

Parameter

 

Action & Limit Levels

 

Measured Level

 

Possible reason for Action or Limit Level Non-compliance

 

Actions taken / to be taken

 

Remarks

 

 

 

 

 

 

 

Location Plan

 

Prepared by :

 

 

 

 

 

Designation :

 

 

 

 

 

Signature :

 

 

 

 

 

Date :

 

 

 

 

 


9.           Schedule of Mitigation from the EIA

Table 9.1 :  Schedule of Impacts and Mitigation Measures

No.

Activity

Mitigation/EIA Recommendations

Responsibility for Implementation

Location
Duration completion
of measures

Implementation Stage
C : Construction
D : Design

Permit Conditions apply to

Relevant Guidelines Legislation

1

Operational Traffic Noise*

The openings of ventilation buildings or ventilation shafts should be placed carefully and ideally should be such that they are not facing directly onto any NSR.

Various

Area Wide, Proposals at design stage for Implementation during construction

D/C

N/A

--

2

Operational Air Quality

Air intakes for commercial/G/IC buildings should be placed such that they are at locations where contours indicate AQOs are met.

ArchSD/Private sector +

CRIII

During development of sites

Completion of CRIII

Development of CRIII

Carry forward to design stage

6

3

Operational Water Quality

Provision of grit traps for surface drainage

 

TDD’s Contractor

New roads and paved areas

During construction

End of construction

C

P, R, A, C

7

4

Operational Landscape and Visual

Operational stage landscape and visual mitigation measures should include +

 

 

 

 

 

 

 

·          Implementation of the Waterfront Promenade, Statue Square Corridor, Historic Corridor, Civic Corridor, Arts and Entertainment Corridor, Streetscape Network, Landscape Decks, and Supplementary Landscape Spaces;

Various

Area wide, proposals at design stage for implementation during construction

D/C

P

--

 

 

·          provision of a legible, integrated pedestrian circulation system linking major activity nodes, reinforcing links with adjoining areas, and providing an international quality hard and soft landscape treatment;

 

 

 

 

 

 

 

·          provision of a grade separated pedestrian system to minimise vehicular/ pedestrian conflict;

 

 

 

 

 

 

 

·          provision of an integrated network of local and regional open spaces for passive and active recreation;

 

 

 

 

 

 

 

·          preservation of selected architectural features;

 

 

 

 

 

 

 

·          preservation insitu of existing significant vegetation, principally the two Banyan Trees flanking the Tamar Site;

 

 

 

 

 

 

 

·          new roads to incorporate suitable streetscape amenity and landscape planting to minimise visual and environmental impacts;

 

 

 

 

 

 

 

·          existing roads upgraded to ‘marry’ with the proposed landscape framework;

·          Hydroseeding of reclamation if there is no immediate use of the site, periphery of the reclamation;

·          Designated service corridors beneath footpaths to prevent potential impacts upon vegetation during services maintenance;

 

 

 

 

 

 

 

·          Sensitively designed colour themes to footpath paving areas; and

·          Sensitively designed seawall to enhance the recreational value of the future promenade can be included.

Various

Area wide, proposals at design stage for implementation during construction

D/C

P

--

5

Construction Noise Control Requirements

Use of the following quiet mechanical equipment for construction
works :

TDD’s Contractor

Works Area

During construction

End of construction

C

P, R, A, C

-

 

 

·          air compressor;

 

 

 

 

 

 

·          paver;

 

 

 

 

 

 

 

·          hand held breaker;

 

 

 

 

 

 

 

·          breaker, excavator mounted;

 

 

 

 

 

 

 

·          bulldozer;

 

 

 

 

 

 

 

·          concrete lorry mixer;

 

 

 

 

 

 

 

·          concrete pump;

 

 

 

 

 

 

 

·          crane;

 

 

 

 

 

 

 

·          dump truck;

 

 

 

 

 

 

 

·          excavator/ loader;

 

 

 

 

 

 

 

·          grader;

 

 

 

 

 

 

 

·          lorry ;

 

 

 

 

 

 

 

·          poker;

 

 

 

 

 

 

 

·          road roller;

 

 

 

 

 

 

 

·          vibratory roller;

 

 

 

 

 

 

 

Use of noise barriers (in the form if purpose built site hoarding of 3 - 5 m height and surface density of at least 7 kgm2 with cranked top) for the following works:

·          Hong Kong Station Extended Overrun Tunnels to north of Central Barracks.

·          North Island Line Protection Works to north of Central Barracks;

·          Road/Drainage Works to north of Central Barracks;

·          Culvert F Piling Works to north of City Hall.

TDD’s Contractor

Work Sites as stated
Start of activity stated
End of activity stated

C

P, A

 

 

 

·          Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

4

 

 

·          Silencers or mufflers on construction equipment shoud be utilised and should be properly maintained during the construction programme.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

4

 

 

·          Mobile plant, if any, should be sited as far away from noise sensitive facilities as possible.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

4

 

 

·          Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

4

 

 

·          Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from nearby noise sensitive  facilities.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

4

 

 

·          Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activites.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

4

6

Construction Air Quality Control Requirements

·          Strictly limit truck speed on site to below 10 km per hour and water spraying to keep the haul roads in wet condition.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6,7

 

 

·          Twice daily watering of the site with active operations when the weather and the work site are dry.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6,7

 

 

·          Watering during excavation and material handling.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6,7

 

 

·          Provision of vehicle wheel and body washing facilities at the exit points of the site, combined with cleaning of public roads where necessary.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6,7

 

 

·          Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6,7

 

 

·          Covers for dusty stockpiles

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6

 

 

·          All plant shall be maintained ot prevent any undue air emmissions

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

6

7

Construction  Water Quality Control Requirements

Specific Meaures Associated with Dredging Works

 

 

 

 

 

 

·          the use of closed clamshell (water-tight) grab dredgers to remove seriously contaminated material such that the amount of SS and other pollutants released from the marine mud and pore water can be minimised;

TDD’s Contractor

Whole reclamation area

During reclamation works

End of reclamation works

C

R

7

 

 

·          the prohibition of stockpiling of any moderately or seriously contaminated marine sediment, and careful control of stockpiling of any uncontaminated sediment to prevent runoff, resuspension and odour nuisances; and

 

 

 

 

 

 

·          the control of dredging and bulk reclamation filling rates within acceptable limits.  Based upon the construction sequence developed for this study the maximum dredging and filling rates adopted for Final Reclamation Area East were :

             Maximum Dredging Rate : 184 m2/hour

             Maximum Daily Filling Rate : 17,727 m3/day

             (for bulk reclamation filling)

Maximum dredging and filling rates for other reclamation sites should take account of information contained in Table 10.14 of the EIA Report and envisaged construction sequence.

 

 

 

 

 

 

 

·          no dredging should take place under very bad weather conditions.

 

 

 

 

 

 

 

·          silt curtain around dredging sites to be provided as necessary.

 

 

 

 

 

 

 

Specific Measure for Marine Disposal of Dredged Materials and Maine Sand Filling Works

TDD’s Contractor

Whole reclamation area

During reclamation works

End of reclamation works

C

R

7

 

 

·          all vessels should be sized such that adequate clearance is maintained between vessels and the sea bed at all states of the tide to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash;

 

 

 

 

 

 

·          all hopper barges and dredgers should be fitted with tight fitting seals to their bottom openings to prevent leakage of material;

 

 

 

 

 

 

 

·          loading of hopper barges should be controlled to prevent splashing of dredged or filling material to the surrounding water, and barges or hoppers should not be filled to a level which will cause the overflow of materials or polluted water during loading or transportation;

 

 

 

 

 

 

 

·          the works should cause no visible foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site or dumping grounds;

TDD’s Contractor

Whole reclamation area

During reclamation works

End of reclamation works

C

R

7

 

 

·          bulk filling should be carried out, where feasible, behind completed seawall to above high water mark.  In general and where physically practical, filling should not be carried out without the seawall having been substantially completed for a distance of 100m – 200m ahead of filling; and

 

 

 

 

 

 

 

·          fill materials should comply with technical specification requirements and be taken from approved sources only.  The maximum fines content of marine sand should be limited to 5% as assumed in the water quality assessments.

 

 

 

 

 

 

 

·          transport of contaminated mud (or filling material) to the marine disposal site (or works site) should, wherever possible, be by split barge of not less than 750 m3 capacity, well maintained and capable of rapid opening and discharge at the disposal site;

·          the dredged material should be disposed in the pit by bottom dumping, at a location within the pit specified by the MFC;

·          discharge should be undertaken rapidly and the hoppers should then immediately be closed. Material adhering to the sides of the hopper should not be washed out of the hopper and the hopper should remain closed until the barge next return to the disposal site;

·          the dumping vessel is not required to station but will be guided by the site staff managing the disposal facility.  The vessel crew should be familiar with such operational procedures;

·          monitoring of the barge loading to ensure that loss of material does not take place during transportation; and

 

 

 

 

 

 

 

·          Transport barges or vessels shall be equipped with automatic self-monitoring devices.

 

 

 

 

 

 

 

Specific Measures Associated with Dredging and Filling Works when CRIII Dredging and Filling Works are being constructed concurrently with WDII Dredging and Filling Works

 

 

 

 

 

 

 

·          deployment of silt curtains around the dredging and fill release points to contain SS within the construction site during dredging and filling;

·          deployment of silt screens at the cooling water intakes and WSD salt water intakes to further minimise the intake of SS within the sea water.

TDD’s Contractor

Reclamation Areas as appropriate
When CRIII and WDII - Dredging and Filling Works occur concurrently
End of Concurrent Works

C

R

-

 

 

Specific Measures Associated with Floating Debris

The result of the floating debris simulation has shown that the intermediate layout of the proposed reclamation has potential to trap floating rubbish. Monitoring and control of the construction activities should be taken to prevent the release of construction waste and rubbish from the construction site. Collection of floating debris should be carried out at least once every day by the CRIII Contractor, and more frequently (two or three times per day) at the water body south of the Initial Reclamation Area West and near the cooling water intakes where large substances could block the screens and filter pipes of the intakes and reduce their efficiency. Debris should be collected and taken to landfill sites for disposal.

TDD’s Contractor

Whole reclamation area

During construction

At end of construction

C

R

-

 

 

Specific Measures for Dealing with Culvert L Outfall at Completion of CRIII Eastern Seawall

 

 

 

 

 

 

 

As a mitigation measure, to avoid the accumulation of water borne pollutants within a temporary embayment to the east of CRIII, an impermeable barrier, suspended from a floating boom on the water surface and extending down to the seabed, will be erected by the CRIII Contractor on completion of the CRIII eastern seawall. The barrier will channel the stormwater discharge flows from Culvert L to the outside of the embayment.  The CRIII Contractor will maintain this barrier until the WDII Contractor takes possession of this site, whereupon the WDII Contractor will takeover the maintenance of this barrier until the reclamation works in this area are carried out and the new Culvert L extension is constructed.

TDD's Consultant

Culvert L Outfall
During Construction
To handover to WDII Contractor

C

R

--

 

 

Construction Run-off and Drainage

 

 

 

 

 

 

 

·       Control of Site Surface Runoff:

-    Surface run-off from construction sites should be discharged into storm drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins. Channels or earth bunds or sand bag barriers should be provided on site to properly direct stormwater to such silt removal facilities. Perimeter channels at site boundaries should be provided where necessary. Catchpits and perimeter channels should be constructed in advance of site formation works and earthworks.

-    Silt removal facilities, channels and manholes should be maintained.

TDD’s Contractor

Works Area

During construction

End of construction

C

P,R,A,C

7

 

 

-    Construction works should be programmed to minimise soil excavation works in rainy seasons (April to September). If excavation in soil cannot be avoided, temporarily exposed slope surfaces should be covered and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds. Intercepting channels should be provided.

-    Earthworks final surfaces should be well compacted and the subsequent permanent work or surface protection should be carried out immediately after the final surfaces are formed to prevent erosion caused by rainstorms. Appropriate drainage such as intercepting channels should be provided where necessary.

-    Measures should be taken to minimise the ingress of rainwater into trenches. If excavation of trenches in wet seasons is necessary, they should be dug and backfilled in short sections. Rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities.

-    Open stockpiles of construction materials should be covered.

-    Manholes should be adequately covered and temporarily sealed.

 

 

 

 

 

 

 

·          Groundwater

-    Groundwater pumped out of tunnels or caverns should be discharged into storm drains after the removal of silt.

 

 

 

 

 

 

 

·          Boring and Drilling Water

-    Water used in ground boring and drilling for site investigation or rock/soil anchoring should as far as practicable be recirculated after sedimentation. Wastewater should be discharged into storm drains via silt removal facilities.

TDD’s Contractor

Work Area

During construction

End of construction

C

P,R,A,C

7

 

 

·          Wastewater from Concrete Batching and Precast Concrete Casting

-    Wastewater generated from the washing down of mixer trucks and drum mixers and similar equipment should wherever practicable be recycled. The discharge of wastewater should be kept to a minimum.

-    To prevent pollution from wastewater overflow, the pump sump of any water recycling system should be provided with an on-line standby pump of adequate capacity and with automatic alternating devices.

-    Under normal circumstances, surplus wastewater may be discharged into foul sewers after treatment in silt removal and pH adjustment facilities (to within the pH range of 6 to 10). Disposal of wastewater into storm drains will require more elaborate treatment. Surface run-off should be segregated from the concrete mixing and casting yard area as much as possible, and diverted to the stormwater drainage system. Surface run-off contaminated by materials in a concrete mixing area or casting yard should be adequately treated before disposal into stormwater drains.

 

 

 

 

 

 

 

·          Wheel Washing Water

-    All vehicles and plant should be cleaned before they leave the construction site. A wheel washing bay should be provided at every site exit if practicable and wash-water should have sand and silt settled out or removed before discharging into storm drains. The section of construction road between the wheel washing bay and the public road should be paved with backfall to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.

TDD’s Contractor

Work Area

During construction

End of construction

C

P,R,A,C

7

 

 

·          Bentonite Slurries

-    Bentonite slurries should be reconditioned and reused wherever practicable. If the disposal of a certain residual quantity cannot be avoided, the used slurry may be disposed of at the marine spoil site subject to obtaining a marine dumping licence from EPD (on a case-by-case basis).

-    If the used bentonite slurry is intended to be disposed of through the public drainage system, it should be treated to the respective effluent standards applicable to foul sewers, storm drains or the receiving waters as set out in the WPCO Technical Memorandum on Effluent Standards.

 

 

 

 

 

 

 

·          Wastewater from Building Construction

-    Before commencing any demolition works, all sewer and drainage connections should be sealed to prevent building debris, soil, sand etc. from entering public sewers/drains.

-    Wastewater generated from building construction activities including concreting, plastering, internal decoration, cleaning of works and similar activities should not be discharged into the stormwater drainage system. If the wastewater is to be discharged into foul sewers, it should undergo the removal of settleable solids in a silt removal facility, and pH adjustment as necessary.

 

 

 

 

 

 

 

·          Licensing of Construction Site Discharges within Water Control Zones

-    All discharges into any drainage or sewerage systems, or inland or coastal waters, or into the ground (e.g. from septic tanks) within a Water Control Zone are controlled under the Water Pollution control Ordinance (WPCO), except the discharge of domestic sewage into foul sewers or the discharge of unpolluted water into storm drains or into the waters of Hong Kong. Construction site discharges are controlled under the WPCO.

-    Discharges controlled under the WPCO must comply with the terms and conditions of a valid WPCO licence.

 

 

 

 

 

8.

Construction Waste Control Requirements

Specific Measures Associated with Marine sediments

 

 

 

 

 

 

 

In accordance with the WBTC No. 3/2000, the seriously contaminated material must be dredged and transported with great care.  Mitigation measures, includeding the use of close-grab dredgers, shall be incorporated.

The dredged contaminated sediment must be effectively isolated from the environment upon final disposal and shall be disposed of at the East Sha Chau Contaminated Mud Pits.

TDD's Contractor

Whole Reclamation Area
During Reclamation Works
End of Reclamation Work

C

R

7

 

 

Segregation and Disposal of Wastes

 

 

 

 

 

 

 

·          inert demolition/construction waste material when deemed suitable for reclamation or land formation should be re-used on-site;

·          non-inert demolition / construction waste material should be disposed of at landfills;

·          chemical waste as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, should be stored in accordance with approved methods defined in the Regulation and Code of Practice and the chemical waste disposed of at the Chemical Waste Treatment Facility located at Tsing Yi or an approved recycler;

·          general refuse should be recycled where possible or disposed of at public landfill.

TDD's Contractor

Works Areas
During Construction
End of Construction

C

P, R, A, C

1,8, 9

 

 

Storage, Collection and Transport of Waste

·          wastes should be handled and stored in a manner which ensures that they are held securely without loss or leakage thereby minimising the potential for pollution. Release of these potential pollutants into marine waters during storage, handling or barge transportation should not be permitted as introduction of polluted waters is likely to have detrimental effects on water quality and water sensitive receivers;

·          only reputable waste hauliers authorised to collect the specific category of waste concerned should be employed;

·          appropriate measures should be employed to minimise windblown litter and dust during transportation by using enclosed bins, covering trucks or transporting wastes in enclosed containers;

·          the necessary waste disposal permits and registrations should be obtained from the appropriate authorities, if they are required, in accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap 354) and the Crown Land Ordinance;

·          collection of general refuse should be carried out frequently, preferably daily;

·          waste should only be disposed of at licensed sites and the civil engineering contractor should develop procedures to ensure that illegal disposal of wastes does not occur;

·          waste storage areas should be well maintained and cleaned regularly;

·          records should be maintained of the quantities of wastes generated, recycled and disposed, determined by weighing each load or other method; and

·          A “trip ticket” system should be implemented, if required by Government.

TDD's Contractor

Works Areas
During Construction
End of Construction

C

P, R, A, C

1, 8, 9

9

Construction Landscape and Visual Control Requirements

Construction stage landscape and visual mitigation measures should include :

·          Minimising contractors accesses and working areas as far as possible;

·          Protection and retention of existing vegetation where possible in accordance with the Hong Kong Government "A Guide to Tree Planting and Maintenance in Urban Hong Kong, Section 5" Care of Trees on Development Sites' and the Country Parks Ordinance

·          Transplanting of trees where appropriate;

·          Advance planting and visual screening;

·          Conservation of top soil;

·          Design of the temporary works areas so as to optimise eventual use as promenade and public open space; and

·          Sensitively designed site hoarding.

TDD's design consultant

Area wide during design and contract preparation

D

P, R, A, C

11, 12, 13,14

10

Monitoring and Audit

To be carried out in accordance with the Schedule in the EM and A Manual

TDD*/Contractor/RSS

Works areas

During construction

End of construction and within one year of operational phase

C/O

P, R, A, C

1

 

 

 

TDD’s design consultant

Area wide during design and contract preparation

D

P, R, A, C

11,12,13,14

1.          Environmental Impact Assessment Ordinance Technical Memorandum (EIAO)

2.          HKPSG

3.          ExCo Criteria for ITR

4.          Noise Control Ordinance

5.          The ProPECC Note PN2/93 (Construction Noise daytime limits)

6.          Air Pollution Control Ordinance (APCO)

7.          Water Pollution Control Ordinance (WPCO)(Cap. 358)

8.          Waste Disposal Ordinance (Cap 354)

9.          Waste Disposal (Chemical Waste)(General) Regulation (Cap 354)

10.        Land Ordinance (Cap 28)

11.        WBTC 25/92 Allocation of Space for Urban Trees

12.        WBTC 25/93 Control of Visual Impact of Slopes

13.        WBTC 18/94 Management and Maintenance of both Natural Vegetation and Landscape Works

14.        WBTC 24/94 and PELBTC 3/94 “Tree Preservation”

15.             Antiquities and Monuments Ordinance (Cap 53)

P          Primary and District Distributor Roads

R          Reclamation

A          North Island Line Protection Works

C          Central and Wanchai Bypass

+           These items should be excluded from any Environmental Permit conditions as these refer to future development of the area (which is not designated under the EIAO), and are not related to reclamation and dredging activities which are designated, and can hence be controlled through EP conditions.

*           Normally undertaken by a specialist monitoring team employed directly by the proponent and audited by the Environmental Works Checker.