AL
|
Action/limit
|
APCO
|
Air Pollution
control Ordinance
|
AQO
|
Air Quality
Objective
|
CRIII
|
Central
Reclamation Phase III Minimum Option
|
CNP
|
Construction
Noise Permit
|
EIA
|
Environmental
Impact Assessment
|
EIAO
|
Environmental
Impact Assessment Ordinance
|
EM & A
|
Environmental
Monitoring and Audit
|
EPD
|
Environmental
Protection Department
|
ER
|
Engineer’s
Representative
|
ET
|
Environmental
Monitoring Team
|
ETL
|
Environmental
Monitoring Team Leader
|
IC(E)
|
Independent
Checker (Environment)
|
HKPSG
|
Hong Kong
Planning Standards and Guidelines
|
HVS
|
High Volume
Sampler
|
HyD
|
Highways
Department
|
NCO
|
Noise Control
Ordinance
|
NSR
|
Noise Sensitive
Receiver
|
SR
|
Sensitive
Receiver
|
TM
|
Technical
Memorandum
|
TSP
|
Total Suspended
Particulates
|
USAEPA
|
United States
of America Environmental Protection Agency
|
WDO
|
Waste Disposal
Ordinance
|
WPCO
|
Water Pollution
Control Ordinance
|
1. Introduction
1.1. Purpose of the Manual
1.1.1. The purpose of this
Environmental Monitoring & Audit (EM&A) Manual is to guide the EM&A
programme prepared for the Central Reclamation Phase III (CRIII), Minimum
Option to ensure compliance with the Environmental Impact Assessment (EIA)
Report. This is subject to approval of the EIA Report under the statutory
procedures of the EIAO and supporting Technical Memorandum. The EIA recommends
procedures to:
·
ensure that any environmental impacts
resulting from the construction of CRIII are kept to within acceptable levels;
·
check that mitigation measures have
been applied and are effective, and that the appropriate corrective actions are
undertaken, if and when required; and
·
provide a means of checking compliance
with environmental objectives, recording anomalies and documenting corrective
action.
1.1.2. This Manual contains the
following:
·
information on the CRIII project, the
project organisation and construction programme;
·
general EM&A principles and the
EM&A team organisation;
·
monitoring parameters, schedules,
Action/Limit Levels and action plans;
·
complaints procedures; and
·
reporting procedures.
1.1.3. The EM&A Manual has
taken on a dual function since the introduction of the EIAO. These roles are:
·
to provide a contract document between
a Client and a contractor defining the monitoring requirements and other duties
in a form that is consistent with accepted contract practice.
·
To provide additional controls that
are implemented through the provisions of the Environmental Permit that are
applicable to the project, but for which the responsibility does not rest with
the Contractor.
1.1.4. As a general note, the
Independent Checker (Environment) [IC(E)] may be part of the Engineer's Team,
or may be totally independent, employed under a separate contract by the
project proponent. In the latter case, this Manual makes reference to items
requiring agreement between the Contractor (or his monitoring team), the
Engineer's Representative, relevant Government Departments and the IC(E).
Attention is drawn to the possibility of requiring agreement from a third party
outside the contract if the IC(E) is employed independently (refer also to
paragraphs 1.5.9 and 1.5.10).
1.1.5. To simplify the
contractual arrangements, it is proposed that all communication with the IC(E)
will be through the ER. Therefore, no reference is made in this Manual for
agreement to be reached with the IC(E) as the Contractor will not be required
to contact the IC(E) directly.
1.2. Requirement for EM&A Programme
1.2.1. The criteria for the
requirement for undertaking EM&A are provided by EPD, these are summarised
as follows:
(a)
to protect sensitive receivers from
environmental impacts if mitigation is not implemented;
(b)
to protect the ecosystem;
(c)
to monitor activities in areas of high
conservation value;
(d)
to monitor the effectiveness of
mitigation measures which involves a long period to establish;
(e)
to monitor am unproven technology;
(f)
to validate the hypothesis in analysis
and design;
(g)
to audit the changing project
scheduling; and
(h)
others.
1.2.2. Criteria a) is met as
there are sensitive receivers which may be impacted by construction activities.
Without mitigation for water quality, dust and noise during the construction
phase, activities could cause nuisance and hence would be prejudicial to the
health or well being of people, and detrimental to the marine environment. Also
as there are potential water quality impacts, this further justifies the
requirements for monitoring and audit. The other criteria are not relevant to
this project. On this basis of Criteria a), an EM&A programme is required.
1.3. Project Description
Background
1.3.1. The proposed CRIII is
located to the north-east of the main Central area in Hong Kong, on the coast
of Victoria Harbour between Central and Admiralty. The site lies between
Central Reclamation, Phase I and western Wan Chai. Following the rejection of
‘Full Reclamation’ proposals of over 30 hectares in size, a ‘Minimum Option’
has been proposed for CRIII in order to minimise the extent of reclamation but
at the same time provide sufficient land to meet essential transport infrastructure requirements. This ‘Minimum Option’
will consist of 18 hectares of reclaimed land and will provide land for the
redevelopment of several Government related facilities, existing facilities
within the study area, construction of a section of the Central – Wanchai
Bypass (CWB) in tunnel, the Hong Kong Station Extended Overrun Tunnel and North
Island Link Protection Works (entrusted to this project), and a landscaped
promenade. In order to facilitate the
construction of the CRIII works the existing Government Heliport at Tamar is to
be relocated to Wan Chai PCWA: the Wan Chai PCWA is to be relocted to Chai Wan
Basin. In addition, the CRIII project
will also involve the demolition of the existing Star Ferry and Queen’s Piers
as well as the provision of necessary infrastructure such as new roads, piers,
electricity sub-stations, drainage culverts, sewerage, and seawater cooling
systems.
1.3.2. The reclamation will take
place over a period of approximately 55 months and will be phased to ensure the
continuation of drainage and seawater cooling systems. A ‘fully dredged’
construction system is to be employed that will involve the removal and
disposal of up to 580,000 m3 of dredged material. It is estimated that 375,000 m3
of the material will be contaminated.
Sensitive Receivers
1.3.3. The site is in a
predominantly commercial business area in Hong Kong and, consequently there are
no residential sensitive receivers that may be affected by the construction of
CRIII. Commercial, Government and Institutional buildings and hotels around the
site are all centrally ventilated and air-conditioned. They are, therefore, not
classified as noise sensitive receivers (NSRs) under the HKPSG or the EIATM. At
the Hong Kong Academy of Performing Arts (HKAPA), there is an outside
auditorium area. This area is rarely used for performing arts events but is
considered in the EIA Report as a potential NSR. A number of air sensitive
receivers have been identified in the study area, these being the air intakes
for the buildings around the project site. Water quality sensitive receivers
have been identified as the seawater cooling system intakes in the direct
vicinity of CRIII, as well as other seawater intakes located around Victoria
Harbour. No ecological sensitive receivers have been identified in the EIA
report.
1.3.4. The project site and
surrounding area are shown in Figure 1.1.
1.4. EIA Requirements
1.4.1. The EIA Report recommends
a range of mitigation measures to control the project’s potential environmental
impacts with regard to marine water quality, dust, construction waste,
ecological and noise impacts. The schedule of mitigation measures as given in
the EIA Report is repeated in Section 9 of this Manual.
1.5. Project Organisation
1.5.1. There is the possibility
that multiple contractors may be employed at the work site. The preferred approach, therefore, is for an
Independent Monitoring Team to be employed directly by the project proponent to
maintain impartiality. However, this is not commonly adopted. It is normal
practice to require a contractor to undertake his own monitoring which should
be audited and checked by the Engineer and an Independent Checker (Environment)
[IC(E)]. The project organisation is
illustrated in Figure 1.2.
1.5.2. Environmental Monitoring Team Leader (ET Leader): This person
should be professionally qualified with suitable experience in environmental
management and planning. As a general recommendation, 7 years experience is
desirable, although if the proposed ET Leader has less, agreement should be
sought from the ER. Extensive knowledge of the study area is required. The ET
Leader should have work experience in Hong Kong managing and providing
specialist advice on environmental monitoring of infrastructure projects.
1.5.3. Site Inspection Team Leader: Requires experience working on
environmental projects in Hong Kong. Extensive experience in dealing with
contractors directly is required.
1.5.4. Noise/Air Specialist: Requires experience in the air and noise
pollution field. Particularly skilled in the use of computer models, database
design and management of monitoring programmes.
1.5.5. Consultant: Experience as an environmental consultant with a broad
range of expertise both in the technical and managerial aspects of
environmental assessment. Proficient in: water quality sampling, analysis and
assessment; air and noise monitoring, modelling and analysis; ecology;
landscape and visual impact; site assessment; and scoping exercises to identify
key environmental issues.
1.5.6. Assistant Consultant: Experience in conducting on-site monitoring,
data-gathering and subsequent computer-modelling data analyses.
1.5.7. The duties to be
undertaken by the Environmental
Monitoring Team (ET) comprise the following:
·
sampling, analysis and statistical
evaluation of monitoring parameters with reference to the EIA Study
recommendations and requirements.
·
environmental
site surveillance;
·
audit of compliance with environmental
protection and pollution prevention and control regulations;
·
monitor the implementation of the
environmental mitigation;
·
monitor compliance with the
environmental protection clauses/specifications in the Contract;
·
review construction programme and
comment as necessary;
·
review construction methodology and
comment as necessary;
·
complaint investigation , evaluation
and identification of corrective measures;
·
liaison with IC(E) on environmental
performance matters and timely submission of relevant EM&A deliverables to
IC(E) for approval; and
·
advise the Contractor on environmental
improvement awareness and enhancement matters etc in site; and
·
timely submission of the EM&A
report to the Project Proponent and the Director of Environmental Protection.
1.5.8. Appropriate resources
shall be allocated by the ET to fulfil their duties specified in this manual.
1.5.9. The Independent Checker
(Environment) [IC(E)] shall advise the Engineer's Representative on
environmental issues related to the project.
The role of the Checker shall be independent from the management of
construction works; but, the Checker shall be empowered to audit the
environmental performance of construction.
The Checker shall have project management experience in addition to the
requirements of the ET Leader stated in paragraph 1.5.7. The appointment of the Checker is subject to
the approval of the Engineer's Representative.
1.5.10. The main duty of the IC(E)
is to carry out environmental audit of the construction project; this shall
include, inter alia, the followings :
a)
Review and audit all aspects of the
EM&A programme;
b)
Validate and confirm the accuracy of
monitoring results, monitoring equipment, monitoring locations, monitoring
procedures and locations of sensitive receivers;
c)
Carry out random sample check and
audit on monitoring data and sampling procedures, etc;
d)
Conduct random site inspection;
e)
Audit the EIA recommendations and
requirements against the status of implementation of environmental protection
measures on site;
f)
Review the effectiveness of
environmental mitigation measures and project environmental performance;
g)
On a needs basis, audit the
Contractor's construction methodology and agree the least impact alternative in
consultation with the ET Leader and the Contractor;
h)
Check complaint cases and the
effectiveness of corrective measures;
i)
Review EM&A report submitted by
the ET Leader; and
j)
Feedback audit results to ET by
signing off relevant EM&A documents.
1.6. Construction Works and Programme
1.6.1. The details of the
construction works are described in the following sections
1.6.2. This programme is for
information for the ET Leader to get an initial idea of the sequencing of the
works. It may be refined and amended by the contractor(s). The ET Leader shall
make reference to the actual works progress and programme during the
construction stage to schedule the EM&A works. The project proponent should
instruct the contractor(s) to provide the relevant programme information to the
ET Leader for formulating the EM&A schedule.
1.7. Construction Sequence – Issues and
Constraints
1.7.1. The construction of the
reclamation for Central Reclamation Phase III is constrained by a number of
factors largely associated with maintaining existing facilities and operations
prior the completion of associated reprovisioned facilities. Critical issues and constraints which affect
the reclamation sequence are :
·
Private vessel and ferry operations
from the existing Queen’s Pier, “Star” Ferry Piers and Tsim Sha Tsui East
temporary ferry pontoon must be maintained until completion and opening of the
reprovisioned ferry pier (Ferry Pier 8), public landing steps and refurbishment
of the existing Ferry Pier 7 is completed.
In addition to maintaining safe marine access during this period,
adequate land access will have to be maintained for pedestrians, public
transport and private vehicles. During
earlier studies, it was established that the existing public landing steps to
the immediate north of the PLA Headquarters at Tamar would need to be closed
prior to commencing the CRIII construction works. Marine Department have confirmed that these arrangements would
still apply to the Minimum Option works with the exception that the westernmost
set of landing steps within the existing seawall could be retained until the
reprovisioned public landing steps are completed and opened for use.
·
The flows from stormwater drainage
culverts F, J and K must be maintained at all times throughout the project
works. Temporary diversions can be
utilised subject to satisfying the DSD that the flow capacity of the temporary
diversions will not cause any increased risk of upstream flooding in the
existing hinterland areas.
·
The operations of the existing cooling
water facilities located along the Central waterfront affected by the works
must be maintained until completion, commissioning and opening of the
reprovisioned facilities. This
requirement involves maintaining intake and outfall flows, maintaining water
quality at the intake to acceptable levels and maintaining adequate maintenance
access to the cooling water facilities.
·
The provision of sufficient land at as
early a time as possible to permit construction of the following key
infrastructure works :
-
The Central - Wanchai Bypass Tunnel;
and
-
The Hong Kong Station Extended Overrun
Tunnel.
·
The existing Government Heliport
located to the north of Lung Wui Road is planned to be reprovisioned to the Wan
Chai PCWA as soon as possible after the start of the CRIII works (further
relocation of this facility is planned as part of the WDII project to enable
WDII project works to be completed). To
facilitate the relocation of the Heliport to this site, the Wan Chai PCWA will
firstly need to be relocated to Chai Wan Basin.
1.8. Proposed Construction Sequence
1.8.1. Taking account of the
issues and constraints as outlined in Section 1.7, a proposed construction
sequence has been developed and is detailed in Table 1.1 below. The sequence is
broadly similar to that proposed for the CRIII-FR, but adapted to take account
of the reduction in reclamation area immediately to the north of the previous
CRIII-FR area.
Table 1.1 : Summary of Construction Tasks and Stages for
CRIII
Stage
|
Construction Period
|
Site Area
|
Main Construction Elements
|
1
|
End Aug 2002 to End March 2003
|
Initial Reclamation Area West
|
-
Dredging
-
Seawall Construction
-
Sand Filling
-
Civil Works for Cooling Water
Pumping Stations
-
Piling for Ferry Pier 8
|
|
|
Hinterland Areas
|
-
Public Transport Facilities Behind
Piers 4 - 6
-
Piling for EOT Vent Building
|
2
|
Start April 2003 to End Nov 2003
|
Initial Reclamation Area West
|
-
Sand Filling and Vibrocompaction
-
Civil Works for Cooling Water
Pumping Stations
-
Superstructure for Ferry Pier 8
-
Piling for Public Landing Steps
(Stage 1)
-
Superstructure for Public Landing
Steps (Stage 1)
|
|
|
Initial Reclamation Area East
|
-
Dredging
-
Temporary Diversion of Culvert J
|
|
|
Hinterland Areas
|
-
Public Transport Facilities Behind
Piers 6 - 7
-
Sheet Piling for EOT Vent Building
-
Superstructure for EOT Vent Building
-
NIL Protection Works, Stages 1&
2
|
3
|
Start Dec 2003 to End July 2004
|
Initial Reclamation Area West
|
-
Pipework for Cooling Water Pumping Stations
-
E&M and Finishing Works for Cooling Water Pumping
Stations
-
Substations for Cooling Water Systems
|
|
|
Initial Reclamation Area East
|
-
Seawall Construction
-
Sand Filling and Vibrocompaction
-
Civil Works for Cooling Water Pumping Stations
-
Pipework for Cooling Water Pumping Stations
-
Substations for Cooling Water Systems
-
E&M and Finishing Works for Cooling Water Pumping
Stations
-
Culvert J Construction
-
Central-Wan Chai Bypass Construction
-
NIL Protection Works, Stage 3
|
|
|
Hinterland Areas
|
-
EOT Vent Building Completion
-
NIL Protection Works, Stages 1 &
2
-
Drainage Improvement Works at
Connaught Place
|
4
|
August 2004
|
Initial Reclamation Area East
|
-
Central-Wan Chai Bypass Construction
|
|
|
Final Reclamation Area West
|
-
Demolition of Piers
|
|
|
Hinterland Areas
|
-
Piling for EOT Vent Shafts
-
Drainage Improvement Works at
Connaught Place
|
5
|
Start Sept 2004 to End April 2005
|
Initial Reclamation Area East
|
-
Central-Wan Chai Bypass Construction
|
|
|
Final Reclamation Area West
|
-
Dredging
-
Seawall Construction
-
Sand Filling
-
Surplus Soft Filling
-
Vibrocompaction
-
Temporary Diversion of Culvert F
-
Civil Works for Cooling Water Pumping Stations
-
Sheet Piling for EOT
|
|
|
Final Reclamation Area East
|
-
Dredging
-
Seawall Construction
|
|
|
Hinterland Areas
|
-
EOT Vent Shaft Construction
-
Drainage Improvement Works at Connaught Place
|
6
|
Start May 2005 to End Dec 2005
|
Final Reclamation Area West
|
-
Surplus Soft Filling and Vibrocompaction
-
Temporary Diversion of Culvert F
-
Foundations for Culvert F
-
Central Wan-Chai Bypass Construction
-
Sheet Piling for EOT
-
EOT Tunnel Construction
-
Piling and Superstructure for Public Landing Steps (Stage
2)
-
PLA Berth Construction
|
|
|
Final Reclamation Area East
|
-
Sand Filling and Vibrocompaction
-
Civil Works for Cooling Water Pumping Stations
-
Culvert K Construction
-
NIL Protection Works, Stage 4
-
Central-Wan Chai Bypass Construction
-
Road P2 Underpass
|
7
|
Start Jan 2006 to End Oct 2006
|
Final Reclamation Area West
|
-
Culvert F Construction
-
Central-Wan Chai Bypass Construction
-
EOT Tunnel Construction
-
Foundations to Man Yiu Street Footbridge
|
|
|
Final Reclamation Area East
|
-
Central-Wan Chai Bypass Construction
-
Road P2 Underpass
|
|
|
All Areas
|
-
Drainage & Utility Works
-
At Grade Roads & Landscaping (Except Roads D5, D6
& P1)
|
8
|
Start Nov 2006 to End Mar 2007
|
Final Reclamation Area West
|
-
Man Yiu Street Footbridge Construction
-
Drainage & Utilities to Roads D5, D6 & P1
-
PTI Construction
-
At Grade Roads & Landscaping to Roads D5, D6
& P1
|
1.9. Construction Programme
A construction programme for Central Reclamation Phase III
works has been prepared based upon the construction sequence detailed in Table
1.1. The construction programme is
presented in a summary form for the EIA in Table
1.2.
Table 1.2 : Summary of Construction Programme
Activity
|
Year 1
|
Year 2
|
Year 3
|
Year 4
|
Year 5
|
Year 6
|
Stage 1
(Aug 2002 –
Mar 2003)
|
|
|
|
|
|
|
Stage 2 (Apr 2003 –
Nov 2003)
|
|
|
|
|
|
|
Stage 3 (Dec 2003 – July 2004)
|
|
|
|
|
|
|
Stage 4 (Aug 2004 )
|
|
|
|
|
|
|
Stage 5 (Sept 2004 –
Apr 2005)
|
|
|
|
|
|
|
Stage 6 (May 2005 –
Dec 2005)
|
|
|
|
|
|
|
Stage 7 (Jan 2006 –
Oct 2006)
|
|
|
|
|
|
|
Stage 8 (Nov 2006 –
Mar 2007)
|
|
|
|
|
|
|
Note : The dates provided in the above table are
based upon a construction start date of August 2002 and may be subject to
change.
2. AIR QUALITY
2.1. Air Quality Parameters
2.1.1. The major air quality
issue associated with CRIII is the potential for dust generation to cause
elevated Total Suspended Particulates (TSP) levels at nearby sensitive
receivers.
2.2. Total Suspended Particulates
2.2.1. Monitoring and audit of
the TSP levels shall be undertaken by the ET Leader to ensure that any
deteriorating air quality could be readily detected and timely action taken to
rectify the situation.
2.2.2. 1-hour and 24-hour TSP
levels shall be measured to indicate the impacts of construction dust on air
quality. The TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix
B. Upon approval by the ER, 1-hour TSP
levels can be measured by direct reading methods which are capable of producing
comparable results as that by the high volume sampling method, to indicate
short event impacts.
2.2.3. All relevant data
including temperature, pressure, weather conditions, elapsed-time meter reading
for the start and stop of the sampler, identification and weight of the filter
paper, and any other local atmospheric factors affecting or affected by site
conditions etc. shall be recorded down in detail. A sample data sheet is shown in Figure 2.1.
2.3. Monitoring Equipment
2.3.1. High volume samplers (HVS)
to be used for carrying out the 1-hour and 24-hour TSP monitoring shall comply
with the following specifications:
·
0.6-1.7 m3/min (20-60 SCFM)
adjustable flow range;
·
equipped with a timing/control device
with +/- 5 minutes accuracy for 24 hours operation;
·
installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
·
capable of providing a minimum exposed
area of 406 cm2 (63 in2);
·
flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
·
equipped with a shelter to protect the
filter and sampler;
·
incorporated with an electronic mass
flow rate controller or other equivalent devices;
·
equipped with a flow recorder for
continuous monitoring;
·
provided with a peaked roof inlet;
·
incorporated with a manometer;
·
able to hold and seal the filter paper
to the sampler housing at horizontal position;
·
easy to change the filter; and
·
capable of operating continuously for
24-hour period.
2.3.2. The ET Leader is
responsible for provision of the monitoring equipment. He shall ensure that sufficient number of
HVSs with an appropriate calibration kit are available for carrying out the
baseline monitoring, regular impact monitoring and ad hoc monitoring. The HVSs shall be equipped with an
electronic mass flow controller and be calibrated against a traceable standard
at regular intervals. All the
equipment, calibration kit, filter papers, etc. shall be clearly labelled.
2.3.3. Initial cabibration of
dust monitoring equipment shall be conducted upon installation and thereafter
at bi-monthly intervals. The transfer
standard shall be traceable to the internationally recognised primary standard
and be calibrated annually. The
calibration data shall be properly documented for future reference by the
concerned parties such as the IC(E).
All the data shall be converted into standard temperature and pressure
condition.
2.3.4. The flow-rate of the
sampler before and after the sampling exercise with the filter in position
shall be verified to be constant and be recorded down in the data sheet in
Figure 2.1.
2.3.5. If the ET Leader proposes
to use a direct reading dust meter to measure 1-hr TSP levels, he shall submit
sufficient information to the IC(E) to prove that the instrument is capable of
achieving a comparable result as that of the HVS and may be used for the 1-hr
sampling. The instrument shall also be
calibrated regularly, and the 1-hr sampling shall be determined periodically by
HVS to check the validity and accuracy of the results measured by direct
reading method.
2.3.6. Wind data monitoring
equipment shall also be provided and set up at conspicuous locations for
logging wind speed and wind direction near to the dust monitoring locations.
The equipment installation location shall be proposed by the ET Leader and
agreed with the ER in consultation with the IC(E). For installation and
operation of wind data monitoring equipment, the following points shall be
observed:
·
the wind sensors should be installed
on masts at an elevated level 10m above ground so that they are clear of
obstructions or turbulence caused by the buildings;
·
the wind data should be captured by a
data logger. The data recorded in the
data logger shall be downloaded periodically for analysis at least once a
month;
·
the wind data monitoring equipment
shall be re-calibrated at least once every six months; and
·
wind direction should be divided into
16 sectors of 22.5 degrees each.
2.3.7. In exceptional situations,
the ET Leader may propose alternative methods to obtain representative wind
data upon approval from the ER and agreement from the IC(E).
2.3.8. The ET shall provide
sufficient equipment to ensure that the monitoring commences on schedule and is
not interrupted as a result equipment failure, damage, loss or routine
maintenance.
2.4. Laboratory Measurement/ Analysis
2.4.1. A clean laboratory with
constant temperature and humidity control, and equipped with necessary
measuring and conditioning instruments, to handle the dust samples collected,
shall be available for sample analysis, and equipment calibration and
maintenance. The laboratory shall be
HOKLAS accredited or other internationally accredited laboratory.
2.4.2. If a site laboratory is
set up or a non-HOKLAS accredited laboratory is hired for carrying out the
laboratory analysis, the laboratory equipment shall be approved by the ER in
consultation with the IC(E). Measurement
performed by the laboratory shall be demonstrated to the satisfaction of the ER
and the IC(E). IC(E) shall conduct
regular audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results. The ET
Leader shall provide the ER with one copy of the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.
2.4.3. Filter paper of size
8”x10” shall be labelled before sampling. It shall be a clean filter paper with
no folds or pin holes, and shall be conditioned in a humidity controlled
chamber for over 24-hour and be pre-weighed before use for the sampling.
2.4.4. After sampling, the filter
paper loaded with dust shall be kept in a clean and tightly sealed plastic bag.
The filter paper is then returned to the laboratory for reconditioning in the
humidity controlled chamber followed by accurate weighing by an electronic
balance with a readout down to 0.1 mg.
The balance shall be regularly calibrated against a traceable standard.
2.4.5. All the collected samples
shall be kept in a good condition for 6 months before disposal.
2.5. Monitoring Locations
2.5.1. Monitoring shall be
conducted at two representative air sensitive receivers (ASRs). These ASRs shall
be the closest to the project site and equipment shall be located as close to
the potentially worst affected ASRs as is practical, although there may be
practical constraints such as lack of access, power or refusal for permission
to locate equipment.
2.5.2. ASRs are listed in Table
2.1 and their locations are shown in Figure 2.2. The ASR reference numbers presented are consistent with those
used for the WDII and CWB EIA Studies.
Table 2.1 :
Construction Phase Air Sensitive Receivers
ASR
|
Description
|
ASR
|
Description
|
A6
|
Crocodile Building
|
A20
|
Central Barracks
|
A7
|
Hang Seng Bank Headquarters
|
A21
|
Central Barracks
|
A8
|
Exchange Square III
|
A22
|
Far East Financial Centre
|
A9
|
Exchange Square I & II
|
A23
|
Admiralty Centre
|
A10
|
Exchange Square I & II
|
A24
|
Harcourt Garden
|
A11
|
Garden House
|
A25
|
Police Headquarters
|
A12
|
Jardine House
|
A26
|
HK Academy for Performing Arts
|
A13
|
Statue Square
|
A27
|
Arts Centre
|
A14
|
Hong Kong Club Building
|
A28
|
Citic Tower
|
A15
|
City Hall
|
A29
|
Servicemen's Guides Association
|
A16
|
City Hall
|
A30
|
HK Academy for Performing Arts
|
A17
|
Furama Hotel
|
A31
|
Shui On Centre
|
A18
|
Hutchison House
|
A33
|
Pedestrian Plaza
|
A19
|
Bank of America Tower
|
A34
|
HKCEC Extension
|
2.5.3. The status and locations
of dust sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall
propose updated monitoring locations and seek approval from the ER and
agreement from the IC(E).
2.5.4. When alternative
monitoring locations are proposed, the following criteria, as far as practicable,
shall be followed :
·
At the site boundary or such locations
close to the major dust emission source;
·
Close to the sensitive receptors; and
·
Take into account the prevailing
meteorological conditions.
2.5.5. The ET Leader shall agree
with the ER in consultation with the IC(E) the position of the HVS for
installation of the monitoring equipment.
When positioning the samplers, the following points shall be noted :
·
a horizontal platform with appropriate
support to secure the samplers against gusty wind should be provided;
·
no two samplers should be placed less
than 2 metre apart;
·
the distance between the sampler and
an obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
·
a minimum of 2 metres of separation
from walls, parapets and penthouses is required for rooftop samplers;
·
a minimum of 2 metre separation from
any supporting structure, measured horizontally is required;
·
no furnace or incinerator flue is
nearby;
·
airflow around the sampler is
unrestricted;
·
the sampler is more than 20 metres
from the dripline;
·
any wire fence and gate, to protect
the sampler, shall not cause any obstruction during monitoring;
·
permission must be obtained to set up
the samplers and to obtain access to the monitoring stations; and
·
a secured supply of electricity is
needed to operate the samplers.
2.6. Baseline Monitoring
Total Suspended
Particulates
2.6.1. The ET Leader shall carry
out baseline monitoring at all of the designated monitoring locations for at
least 14 consecutive days prior to the commissioning of the construction works
to obtain daily 24-hr TSP samples. 1-hr
sampling shall also be done at least 3 times per day while the highest dust
impact is expected. Before commencing
the baseline monitoring, the ET Leader shall inform the IC(E) of the baseline
monitoring programme such that the IC(E) can conduct on-site audit to ensure
accuracy of the baseline monitoring results.
2.6.2. During the baseline
monitoring, there shall not be any construction or dust generation activities
in the vicinity of the monitoring stations.
2.6.3. In case the baseline
monitoring cannot be carried out at the designated monitoring locations during
the baseline monitoring period, the ET Leader shall carry out the monitoring at
alternative locations which can effectively represent the baseline conditions
at the impact monitoring locations. The
alternative baseline monitoring locations shall be approved by the ER and
agreed with the IC(E).
2.6.4. In the exceptional case,
when insufficient baseline monitoring data or questionable results are
obtained, the ET Leader shall liaise with the IC(E) and EPD to agree on an
appropriate set of data to be used as a baseline reference and submit to the ER
for approval.
2.6.5. Ambient conditions may
vary seasonally and shall be reviewed at three monthly intervals. If the ET Leader considers that the ambient
conditions have been changed and a repeat of the baseline monitoring is
required to be carried out for obtaining the updated baseline levels, the
monitoring shall be at times when the Contractor's activities are not
generating dust, at least in the proximity of the monitoring stations. Should change in ambient conditions be
determined, the baseline levels and, in turn, the air quality criteria, shall
be revised. The revised baseline levels
and air quality criteria shall be agreed with the IC(E) and EPD.
2.7. Impact Monitoring
Total Suspended
Particulates
2.7.1. The ET Leader shall carry
out impact monitoring during the course of the works. For regular impact monitoring, the sampling frequency of at least
once in every six-days, shall be strictly observed at all the monitoring
stations for 24-hr TSP monitoring. For
1-hr TSP monitoring, the sampling frequency of at least three times in every
six-days shall be undertaken when the highest dust impact occurs. Before commencing the impact monitoring, the
ET Leader shall inform the IC(E) of the impact monitoring programme such that the
IC(E) can conduct on-site audit to ensure accuracy of the impact monitoring
results.
2.7.2. The specific time to start
and stop the 24-hr TSP monitoring shall be clearly defined for each location
and be strictly followed by the field operator.
2.7.3. In case of non-compliance
with the air quality criteria, more frequent monitoring exercise, as specified
in the Action Plan in Section 2.8, shall be conducted within 24 hours after the
result is obtained. This additional
monitoring shall be continued until the excessive dust emission or the
deterioration in air quality is rectified.
2.8. Event and Action Plan for Air Quality
2.8.1. The baseline monitoring
results form the basis for determining the air quality criteria for the impact
monitoring. The ET Leader shall compare the impact monitoring results with air
quality criteria set up for 24-hour TSP and 1-hour TSP. Table 2.2 shows the air
quality criteria, namely Action and Limit levels, to be used. Should
non-compliance of the air quality criteria occur, actions in accordance with
the Action Plan in Table 2.3 shall be carried out .
Table 2.2 : Action and Limit Levels for Air Quality
Parameters
|
Action
|
Limit
|
24 Hour TSP
Level in mg/m3
|
For baseline level £200 mg/m3 Action level =
(Baseline level *1.3 + Limit level)/2;
For baseline level >200 mg/m3 Action level = Limit level
|
260
|
1 Hour TSP
Level in mg/m3
|
For baseline level £ 384 mg/m3, Action level =
(Baseline level *1.3 + Limit level)/2
For baseline level >384 mg/m3, a Action level = Limit level
|
500
|
Table
2.3 :
Event/Action Plan for Air Quality
Event
|
Action
|
ET Leader
|
IC(E)
|
ER
|
Contractor
|
Action Level
|
1. Exceedance for one sample
|
1.
Identify
source
2.
Inform
IC(E) and ER
3.
Repeat
measurement to confirm finding
4.
Increase
monitoring frequency to daily
|
1.
Check
monitoring data submitted by ET
2.
Check
Contractor's working method
|
1. Notify Contractor
|
1.
Rectify
any unacceptable practice
2.
Amend
working methods if appropriate
|
2. Exceedance
for two or more consecutive samples
|
1.
Identify
source
2.
Inform
IC(E) and ER
3.
Repeat
measurements to confirm findings
4.
Increase
monitoring frequency to daily
5.
Discuss
with IC(E) and Contractor on remedial actions required
6.
If
exceedance continues, arrange meeting with IC(E) and ER
7.
If
exceedance stops, cease additional monitoring
|
1.
Checking
monitoring data submitted by ET
2.
Check
Contractor's working method
3.
Discuss
with ET and Contractor on possible remedial measures
4.
Advise
the ER on the effectiveness of the proposed remedial measures
5.
Supervise
the implementation of remedial measures
|
1.
Confirm
receipt of notification of failure in writing
2.
Notify
Contractor
3.
Ensure
remedial measures properly implemented
|
1.
Submit
proposals for remedial actions to IC(E) within 3 working days of notification
2.
Implement
the agreed proposals
3.
Amend
proposal if appropriate
|
Limit Level
|
1. Exceedance for one sample
|
1.
Identify
source
2.
Inform
ER and EPD
3.
Repeat
measurement to confirm finding
4.
Increase
monitoring frequency to daily
5.
Assess
effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER
informed of the results.
|
1.
Check
monitoring data submitted by ET
2.
Check
Contractor's working method
3.
Discuss
with ET and Contractor on possible remedial measures
4.
Advise
the ER on the effectiveness of the proposed remedial measures
5.
Supervise
the implementation of remedial measures
|
1.
Confirm
receipt of notification of failure in writing
2.
Notify
Contractor
3.
Ensure
remedial measures properly implemented
|
1.
Take
immediate action to avoid further exceedance
2.
Submit
proposals for remedial actions to IC(E) within 3 working days of notification
3.
Implement
the agreed proposals
4.
Amend
proposal if appropriate
|
2. Exceedance
for two or more consecutive samples
|
1.
Notify
IC(E), ER, Contractor and EPD
2.
Identify
source
3.
Repeat
measurements to confirm findings
4.
Increase
monitoring frequency to daily
5.
Carry
out analysis of Contractor's working procedures to determine possible
mitigation to be implemented
6.
Arrange
meeting with IC(E) and ER to discuss the remedial actions to be taken
7.
Assess
effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER
informed of the results
8.
If
exceedance stops, cease additional monitoring
|
1.
Discuss
amongst ER, ET, and Contractor on the potential remedial actions
2.
Review
Contractor's remedial actions whenever necessary to assure their effectiveness
and advise the ER accordingly
3.
Supervise
the implementation of remedial
measures
|
1.
Confirm
receipt of notification of failure in writing
2.
Notify
Contractor
3.
In
consultation with the IC(E), agree with the Contractor on the remedial
measures to be implemented
4.
Ensure
remedial measures properly implemented
5.
If
exceedance continues , consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated
|
1.
Take
immediate action to avoid further exceedance
2.
Submit
proposals for remedial actions to IC(E) within 3 working days of notification
3.
Implement
the agreed proposals
4.
Resubmit
proposals if problem still not under control
5.
Stop
the relevant portion of works as determined by the ER until the exceedance is
abated.
|
2.9. Dust Mitigation Measures
2.9.1. The EIA report has
discussed the appropriate dust control and mitigation measures. The Contractor
shall implement dust suppression measures as identified in the Schedule given
in Section 9 of this EM&A Manual.
2.9.2. If the measures listed in
Section 9 of this EM&A Manual are not sufficient to restore the air quality
to acceptable levels upon the advice of ET Leader, the Contractor shall liaise
with the ET Leader on some other mitigation measures, propose to the ER for
approval, and implement the mitigation measures.
3. Noise
3.1. Noise Parameters
3.1.1. The construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 min) shall be used as the monitoring parameter
for the time period between 0700-1900 hours on normal weekdays. For all other
time periods, Leq (5 min) shall be employed for comparison with the NCO
criteria.
3.1.2. As supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference. A sample data record sheet is shown in
Figure 3.1 for reference.
3.2. Monitoring Equipment
3.2.1. As referred to in the
Technical Memorandum (TM) issued under the Noise Control Ordinance (NCO), sound
level meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0dB.
3.2.2. Noise measurements should
not be made in accordance with standard acoustical principles and practices in
relation to weather conditions.
3.2.3. The ET Leader is
responsible for the availability of monitoring equipment. He shall ensure that sufficient noise
measuring equipment and associated instrumentation are available for carrying
out the baseline monitoring, regular impact monitoring and ad hoc
monitoring. All the equipment and
associated instrumentation shall be clearly labelled.
3.3. Monitoring Locations
3.3.1. The only potential noise
sensitive receiver (NSR) is the HKAPA outdoor arena, as discussed in Section
1.3. However, this is rarely used
during the day, so it is suggested that monitoring is carried out at the
Central Barracks. The proposed location
(labelled A20) is shown in Figure 2.2.
No schools exist within the project area.
3.3.2. The status and locations
of noise sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall
propose updated monitoring locations and seek approval from the ER and
agreement from the IC(E) and EPD of the proposal.
3.3.3. When alternative
monitoring locations are proposed, the monitoring locations shall be chosen
based on the following criteria :
·
at locations close to the major site
activities which are likely to have noise impacts;
·
close to the noise sensitive receivers
(for the purposes of this section, any domestic premises, hotel, hostel,
temporary housing accommodation, hospital, medical clinic, educational
institution, place of public worship, library, court of law, performing art
centre shall be considered as a noise sensitive receiver); and
·
for monitoring locations located in
the vicinity of the sensitive receivers, care shall be taken to cause minimal
disturbance to the occupants during monitoring.
3.3.4. The monitoring station
shall normally be at a point 1m from the exterior of the sensitive receivers
building façade and be at a position 1.2m above the ground. If there is problem
with access to the normal monitoring position, an alternative position may be
chosen, and a correction to the measurements shall be made. For reference, a
correction of +3dB(A) shall be made to the free field measurements. The ET
Leader shall agree with the IC(E) on the monitoring position and the
corrections adopted. Once the positions
for the monitoring stations are chosen, the baseline monitoring and the impact
monitoring shall be carried out at the same positions.
3.4. Baseline Monitoring
3.4.1. The ETL shall carry out
baseline noise monitoring prior to the commencement of the construction works.
The baseline monitoring shall comprise one Leq (30 minutes)
measurement per day (07:00 to 19:00 hours) at the monitoring location for a
period of 14 days. In addition, 3 measurements for Leq (5 minutes)
between the hours of 19:00 – 23:00 shall be undertaken per day at the same
location. Total numbers of samples required will be: 14 Leq (30 minutes)
measurements and 42 Leq (5 minutes) measurements. Before commencing
the baseline monitoring, the ET Leader shall inform the IC(E) of the baseline
monitoring programme such that the IC(E) can conduct on-site audit to ensure
accuracy of the baseline monitoring results.
3.4.2. There shall not be any
noise impacts from construction activities in the vicinity of the stations
during the baseline monitoring.
3.4.3. In exceptional cases, when
insufficient baseline monitoring data or questionable results are obtained, the
ET Leader shall liaise with the IC(E) and EPD to agree on an appropriate set of
data to be used as a baseline reference and submit to the ER for approval.
3.5. Impact Monitoring
3.5.1. Noise monitoring shall be
carried out at the Central Barracks on a per week basis when noise generating
activities are underway:
·
one Leq (30 minutes)
measurement between 0700-1900 hours on normal weekdays;
3.5.2. It is not considered
necessary to conduct noise monitoring during the nightime. General Construction work carried out during
restricted hours is controlled by the CNP system under the NCO.
3.5.3. In case of non-compliance
with the construction noise criteria, more frequent monitoring, as specified in
the Action Plan in Section 3.6 shall be carried out. This additional monitoring
shall be continued until the recorded noise levels are rectified or proved to
be irrelevant to the construction activities.
3.6. Event and Action Plan for Noise
3.6.1. The Action and Limit
levels for construction noise are defined in Table 3.1. Should non-compliance
of the criteria occur, action in accordance with the Action Plan in Table 3.2
shall be carried out.
Table 3.1 :
Action and Limit Levels for Construction Noise
Time Period
|
Action
|
Limit
|
0700-1900 hrs
on normal weekdays
|
When
one documented complaint is received
|
75*
dB(A)
|
* reduce to 70 dB(A) for schools and 65
dB(A) during school examination periods.
Table 3.2 :
Event/Action Plan for Construction Noise
Event
|
Action
|
ET Leader
|
IC(E)
|
ER
|
Contractor
|
Action Level
|
1.
Notify IC(E) and Contractor
2.
Carry out investigation
3.
Report the results of investigation to the IC(E) and Contractor
4.
Discuss with the Contractor and formulate remedial measures
5.
Increase monitoring frequency to check mitigation effectiveness
|
1.
Review the analysed results submitted by the ET
2.
Review the proposed remedial measures by the Contractor and advise the
ER accordingly
3.
Supervise the implementation of remedial measures
|
1.
Confirm receipt of notification of failure in writing
2.
Notify Contractor
3.
Require Contractor to propose remedial measures for the analysed
noise problem
4.
Ensure remedial measures are properly implemented
|
1.
Submit noise mitigation proposals to IC(E)
2.
Implement noise mitigation proposals
|
Limit Level
|
1.
Notify IC(E), ER, EPD and Contractor
2.
Identify source
3.
Repeat measurement to confirm findings
4.
Increase monitoring frequency
5.
Carry out analysis of Contractor's working procedures to determine
possible mitigation to be implemented
6.
Inform IC(E), ER and EPD the causes & actions taken for the
exceedances
7.
Assess effectiveness of Contractor's remedial actions and keep (C(E),
EPD and ER informed of the results
8.
If exceedance stops, cease additional monitoring
|
1.
Discuss amongst ER, ET, and Contractor on the potential remedial
actions
2.
Review Contractor's remedial actions whenever necessary to assure
their effectiveness and advise the ER accordingly
3.
Supervise the implementation of remedial measures
|
1.
Confirm receipt of notification of failure in writing
2.
Notify Contractor
3.
Require Contractor to propose remedial measures for the analysed
noise problem
4.
Ensure remedial measures are properly implemented
5.
If exceedance continues, consider what portion of the work is
responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated
|
1.
Take immediate action to avoid further exceedance
2.
Submit proposals for remedial actions to IC(E) within 3 working days
of notification
3.
Implement the agreed proposals
4.
Resubmit proposals if problem still not under control
5.
Stop the relevant portion of works as determined by the ER until the
exceedance is abated
|
3.7. Noise Mitigation Measures
3.7.1. The Contractor shall
implement mitigation measures in accordance with the EIA Schedule in Section 9
of this EM&A Manual.
3.7.2. If the mitigation measures
listed in Section 9 of this EM&A Manual are not sufficient to restore the
construction noise quality to acceptable levels upon the advice of ET Leader,
the Contractor shall liaise with the ET Leader on some other mitigation
measures, propose them to the ER for approval, and carry out the mitigation
measures.
4. MARINE Water Quality
4.1. Marine Water Quality Parameters
4.1.1. Monitoring of turbidity in
NTU, dissolved oxygen (DO) in mg/l and suspended solids (SS) in mg/l, shall be
carried out by the ET to ensure that any deteriorating water quality is readily
detected and timely action can be taken to rectify the situation. The former
two parameters are measured in-situ while the latter one is determined in the
laboratory.
4.1.2. In association with the
water quality parameters, other relevant data shall also be measured, such as
monitoring location/position, time, water depth, water temperature, salinity,
DO saturation, pH value, weather conditions, sea conditions, tidal stage, any
special phenomena and work underway at the construction site and any other
relevant information.
4.1.3. A sample monitoring record
sheet is shown in Figure 4.1 for reference.
4.2. Monitoring Equipment
4.2.1. All monitoring equipment
shall be provided by the ET and approved by the ER.
Dissolved oxygen and
temperature measuring equipment
4.2.2. The instrument shall be a
portable, weatherproof dissolved oxygen measuring instrument complete with
cable, sensor, comprehensive operation manuals, and use a DC power source. It
should be capable of measuring:
·
a dissolved oxygen level in the range
of 0‑20 mg/l and 0‑200% saturation; and
·
a temperature of 0‑45° C.
4.2.3. It shall have a membrane
electrode with automatic temperature compensation complete with a cable.
Sufficient stocks of spare electrodes and cables shall be available for
replacement where necessary (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A
submersible stirrer with reel and cable or an approved similar instrument).
4.2.4. Should salinity
compensation not be built-in in the DO equipment, in-situ salinity shall be
measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement
Instrument
4.2.5. The instrument shall be a
portable, weatherproof turbidity-measuring instrument complete with comprehensive
operation manual. The equipment shall use a DC power source. It shall have a
photoelectric sensor capable of measuring turbidity between 0‑1000 NTU
and be complete with a cable (e.g. Hach model 2100P or an approved similar
instrument).
Suspended Solids
4.2.6. A water sampler comprises
a transparent PVC cylinder, with a capacity of not less than 2 litres and can
be effectively sealed with latex cups at both ends. The sampler shall also have a positive latching system to keep it
open and prevent premature closure until released by a messenger when the
sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an
approved similar instrument).
4.2.7. Water samples for
suspended solids measurement should be collected in high density polythene
bottles, packed in ice (cooled to 4°C without being frozen), and delivered to the
laboratory as soon as possible after collection.
Water Depth Detector
4.2.8. A portable,
battery-operated echo sounder should be used for the determination of water
depth at each designated monitoring station. This unit can either be handheld
or affixed to the bottom of the work boat, if the same vessel is to be used
throughout the monitoring programme.
Salinity
4.2.9. A portable salinometer
capable of measuring salinity in the range of 0-40ppt shall be provided for
measuring salinity of the water at each monitoring location.
4.3. Location of the monitoring sites
4.3.1. A hand-held or boat-fixed
type digital Global Positioning System (GPS) with way point bearing indication
or other equivalent instrument of similar accuracy shall be provided and used
during monitoring to ensure the monitoring vessel is at the correct location
before taking measurements.
4.3.2. All in-situ monitoring
instrument shall be checked, calibrated and certified by a laboratory
accredited under HOKLAS or any other international accreditation scheme before
use, and subsequently re-calibrated at 3 monthly intervals throughout all
stages of the water quality monitoring.
Responses of sensors and electrodes shall be checked with certified
standard solutions before each use. Wet
bulb calibration for a DO meter shall be carried out before measurement at each
monitoring location.
4.3.3. For the on site
calibration of field equipment, the BS 127:1993, "Guide to Field and
on-site test methods for the analysis of waters" shall be observed.
4.3.4. Sufficient stocks of spare
parts shall be maintained for replacements when necessary. Backup monitoring equipment shall also be
made available so that monitoring can proceed uninterrupted even when some
equipment is under maintenance, calibration, etc.
4.4. Laboratory Measurement / Analysis
4.4.1. Analysis of suspended
solids shall be carried out in a HOKLAS or other internationally accredited
laboratory. Water samples of about 1,000 ml shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The
detection limit shall be 1 mgL-1 or better. The SS determination work shall start within
24 hours after collection of the water samples. The SS determination shall
follow APHA 17ed 2540D or equivalent methods subject to approval of DEP.
4.4.2. If a site laboratory is
set up or a non-HOKLAS and non-international accredited laboratory is hired for
carrying out the laboratory analysis, the laboratory equipment, analytical
procedures, and quality control shall be approved by the DEP. All the analyses
shall be witnessed by the ER. The ET Leader shall provide the ER with one copy
of the relevant chapters of the "Standard Methods for the Examination of
Water and Wastewater" updated edition and any other relevant document for
his reference.
4.4.3. For the testing methods of
other parameters as recommended by the EIA or required by DEP, detailed testing
methods, pre-treatment procedures, instrument use, Quality Assurance/Quality
Control (QA/QC) details (such as blank, spike recovery, number of duplicate
samples per batch, etc.), detection limits and accuracy shall be submitted to
DEP for approval prior to the commencement of monitoring programme. The QA/QC shall be in accordance with the
requirement of HOKLAS or international accredited scheme. The QA/QC results shall be reported. EPD may also request the laboratory to carry
out analysis of known standards provided by EPD for quality assurance. Additional duplicate samples may be required
by EPD for inter laboratory calibration.
Remaining samples after anaysis shall be kept by the laboratory for 3
months in case repeat analysis is required.
If in-house or non-standard methods are proposed, details of the method
verification may also be required to be submitted to DEP. In any circumstance, the sample testing
shall have comprehensive quality assurance and quality control programme. The laboratory shall be prepared to
demonstrate the programmes to DEP or his representatives when requested.
4.5. Monitoring Locations
4.5.1. The marine water quality
monitoring stations during the construction works are shown in Figure 4.2. These stations are chosen based on the
following criteria :
i.
Close to the sensitive receivers (that
is, the seawater intakes of the operating saltwater pumping stations) which are
directly or likely to be affected.
These intakes will be relocated as the reclamation proceeds. Water Quality monitoring at the
re-provisioned intakes will continue at these re-provisioned intakes after the
re-provisioned pumping stations have been commissioned and are operational. For
monitoring locations located in the vicinity of the sensitive receivers, care
should be taken to cause minimal disturbance during monitoring;
ii.
At the boundary of the mixing zones so
as to verify predictive assessment results; and
iii.
Two control stations that shall be at
locations representative of the project site in its undisturbed condition. Control stations should be located, as far
as is practicable, both upstream and downstream of the works area.
The co-ordinates of the proposed initial
monitoring stations are listed in Table 4.1.
As shown in Figure 4.2, the proposed locations for the sensitive
receiver monitoring stations represent the sensitive receivers that are
predicted to be affected during the initial construction. Sensitive receivers at the boundary of the
mixing zone have not been indicated as they will depend upon the Contractor's
work sequencing and will need to be determined immediately prior to commencing
reclamation works. It should also be noted that the control stations shown in
Figure 4.2 are indicative and subject to further review before construction
phase. During this review, the location
of the impact stations for the boundary of the mixing zones shall also be
re-visited. Revisions to station
locations shall be submitted to EPD for approval four weeks before commencement
of baseline monitoring.
Table 4.1 : Proposed Water Quality Monitoring Stations
Station Ref.
|
E
|
N
|
1. Princess Building
Group / Mandarin Hotel
|
834,514.5
|
816,093.0
|
2. HSBC Headquarters
Building Intakes
|
834,644.0
|
816,026.5
|
3. Murray Road Carpark
Group / Central Government Offices Group / Furama Hotel Intakes
|
834,780.5
|
815,987.5
|
4. Central Barracks
Intake
|
835,002.0
|
815,985.5
|
5. Queensway Government
Offices Group / Pacific Place Intakes
|
835,409.0
|
815,839.0
|
6. MTRC South Intakes
|
835,597.5
|
815.857.0
|
7. Control Station 1
|
829,349.0
|
818,629.0
|
8. Control Station 2
|
844,170.0
|
814,880.0
|
Control stations are necessary to compare
the water quality from potentially impacted sites with the ambient water
quality. Control stations shall be
located within the same body of water as the impact monitoring stations but
should be outside the area of influence of the works and, as far as
practicable, not affected by any other works.
Measurements shall be taken at 3 water depths, namely, 1 m below water
surface, mid-depth and 1 m above seabed, except where the water depth is less
than 6m, the mid-depth station may be omitted.
At monitoring stations coincident with seawater intakes, the SS and
turbitity measurements should make reference to the vertical levels of the
individual intake pipes. Should the
water depth be less than 3m, only the mid-depth station will be monitored. The ET Leader shall seek approval from the
IC(E) and DEP on all monitoring station locations. The status and locations of water quality sensitive receivers may
change after issuing this manual. If
such cases exist, the ET Leader shall propose updated monitoring locations and
seek approval from the IC(E) and DEP.
4.5.2. When alternative
monitoring locations are proposed, they should be chosen based on the following
criteria:
·
at locations close to and preferably
at the boundary of the mixing zone of the major site activities as indicated in
the EIA Final Report, which are likely to have water quality impacts;
·
close to the sensitive receptors which
are directly or likely to be affected;
·
for monitoring locations located in
the vicinity of the sensitive receptors, care should be taken to cause minimal
disturbance during monitoring; and
·
at two or more control stations which
shall be at locations representative of the project site in its undisturbed
condition. Control stations should be located, as far as is practicable, both
upstream and downstream of the works area.
4.6. Baseline Monitoring
4.6.1. Baseline conditions for
water quality shall be established and agreed with the DEP prior to the
commencement of works. The purposes of the baseline monitoring are to establish
ambient conditions prior to the commencement of the works and to demonstrate
the suitability of the proposed impact, control and reference monitoring
stations. The baseline conditions shall normally be established by measuring
the water quality parameters specified in Section 4.1. The measurements shall
be taken at all designated monitoring stations including control stations, 3
days per week, at mid-flood and mid-ebb tides, for four weeks prior to the
commencement of marine works.
4.6.2. There shall not be any
marine construction activities in the vicinity of the stations during the
baseline monitoring.
4.6.3. In the exceptional cases
when insufficient baseline monitoring data or questionable results are
obtained, the ET Leader shall seek approval from the IC(E) and DEP on an
appropriate set of data to be used as baseline reference.
4.6.4. Baseline monitoring schedule
shall be faxed to EPD two weeks prior to commencement of baseline
monitoring. The interval between 2 sets
of monitoring shall be less than 36 hours.
4.6.5. Replicate in-situ
measurements and sample collected from each independent sampling event are
required for all parameters to ensure a robust statistically interpretable
database.
4.7. Impact Monitoring
4.7.1. During the course of the
marine works, monitoring shall be undertaken three days per week, at mid-flood
and mid-ebb tides, with sampling/measurement at the designated monitoring
stations. The interval between two sets
of monitoring shall not be less than 36 hours except where there are
exceedances of Action and/or Limit levels, in which case the monitoring
frequency will be increased.
4.7.2. Upon completion of all
marine activities, a post project monitoring exercise on water quality shall be
carried out for four weeks in the same manner as the impact monitoring.
4.7.3. Proposed water quality
monitoring schedule shall be faxed to EPD two weeks before the first day of the
monitoring month. EPD shall also be
notified immediately for any changes in schedule by fax.
4.7.4. Replicate in-situ measurements and sample collected from each
independent sampling event are required for all parameters to ensure a robust
statistically interpretable database.
4.8. Event and Action Plan for Water Quality
4.8.1. The water quality
criteria, namely Action and Limit levels are based on the results of baseline
monitoring and WQO of the relevant Water Control Zone and are shown in Table
4.2. Should the monitoring results of the water quality parameters at any
designated monitoring station indicate that the water quality criteria are
exceeded, the actions in accordance with the Action Plan in Table 4.3 shall be
carried out. Water Supplies Department
have requested that they should be informed in case the Action and Limit Levels
at their seawater intake points have been exceeded.
Table 4.2 :
Action and Limit Levels for Water Quality
Parameters
|
Action
|
Limit
|
DO in mg/l
(Surface, Middle & Bottom)
|
Surface & Middle
1%-ile of baseline data for surface
and middle layer; or
Midway between 5%-ile of baseline
data and limit level
Bottom
1%-ile of baseline data for bottom
layer; or
Midway between 5%-ile of baseline data and limit level
|
Surface & Middle
4 mg/l except 5 mg/l for FCZ
or
1%-ile of baseline data for surface
and middle layer
Bottom
2 mg/l
or
1%-ile of baseline data for bottom
layer
|
SS in mg/l
(depth-averaged)
|
95%-ile of baseline data or 120% of
upstream control station's SS at the same tide of the same day
|
99%-ile of baseline, 130% of
upstream control station's SS at the same tide of the same day and specific
sensitive receiver water quality requirements (e.g. required suspended solids
level for concerned sea water intakes)
|
Turbidity (Tby) in NTU
(depth-averaged)
|
95%-ile of baseline data or 120% of
upstream control station's Tby at the same tide of the same day
|
99%-ile of baseline or 130% of
upstream control station's Tby at the same tide of the same day
|
Notes: - For DO, non-compliance
of the water quality limits occurs when monitoring result is lower than the
limits.
- For SS and Tby, non-compliance of the water
quality limits occurs when monitoring result is higher than the limits.
- All the figures given in the table are used
for reference only and the EPD may amend the figures whenever it is considered
necessary.
Table 4.3 :
Event and Action Plan for Water Quality
Event
|
ET Leader
|
IC(E)
|
ER
|
Contractor
|
Action level being exceeded by one sampling day
|
1. Repeat
in-situ measurement to confirm findings;
2. Identify
source(s) of impacts;
3. Inform IC(E)
and Contractor;
4. Check
monitoring data, all plant, equipment and Contractor's working methods;
5. Discuss
mitigation measures with IC(E) and Contractor;
6. Repeat
measurement on next day of exceedance.
|
1.
Discuss with ET and Contractor on the mitigation measures;
2.
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly;
3.
Assess the effectiveness of the implemented mitigation measures.
|
1. Discuss with IC(E) on
the proposed mitigation measures;
2. Make agreement on the
mitigation measures to be implemented.
|
1. Inform the ER and confirm notification of
the non-compliance in writing;
2. Rectify unacceptable practice;
3.Check all
plant and equipment;
4. Consider
changes of working methods;
5. Discuss with
ET and IC(E) and propose mitigation measures to IC(E) and ER;
6. Implement the
agreed mitigation measures.
|
Action level being exceeded by more than one consecutive sampling day
|
1. Repeat
in-situ measurement to confirm findings;
2. Identify
source(s) of impact;
3. Inform IC(E)
and Contractor;
4. Check
monitoring data, all plant, equipment and contractor's working methods;
5. Discuss
mitigation measures with IC(E) and Contractor;
6. Ensure
mitigation measures are implemented;
7. Prepare to
increase the monitoring frequency to daily;
8. Repeat
measurement on next day of exceedance.
|
1.
Discuss with ET and Contractor on the mitigation measures;
2.
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly;
3.
Assess the effectiveness of the implemented mitigation measures.
|
1. Discuss with
IC(E) on the proposed mitigation measures;
2. Make
agreement on the mitigation measures to be implemented;
3. Assess the
effectiveness of the implemented mitigation measures.
|
1. Inform the
Engineer and confirm notification of the non-compliance in writing;
2. Rectify
unacceptable practice;
3. Check all plant and equipment;
4. Consider changes of working methods;
5. Discuss with the ET and IC(E) and propose
mitigation measures to IC(E) and ER within 3 working days;
6. Implement the agreed mitigation measures.
|
Limit level being exceeded by one sampling day
|
1. Repeat
in-situ measurement to confirm findings;
2. Identify
source(s) of impact;
3. Inform IC(E)
Contractor and EPD;
4. Check
monitoring data, all plant, equipment and Contractor's working methods
5. Discuss
mitigation measures with IC(E), ER and Contractor
6. Ensure
mitigation measures are implemented
7. Increase the
monitoring frequency to daily until no exceedance of Limit Level.
|
1.
Discuss with ET and Contractor on the mitigation measures;
2.
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly;
3.
Assess the effectiveness of the implemented mitigation measures.
|
1. Discuss with IC(E), ET
and Contractor on the proposed mitigation measures;
2. Request Contractor to
critically review the working methods;
3. Make agreement on the
mitigation measures to be implemented;
4. Assess the effectiveness
of the implemented mitigation measures.
|
1.Inform the
Engineer and confirm notification of the non-compliance in writing;
2. Rectify
unacceptable practice;
3. Check all
plant and equipment;
4. Consider
changes of working methods
5. Discuss with
ET and IC(E) and propose mitigation measures to IC(E) and ER within 3 working
days;
6. Implement the
agreed mitigation measures.
|
Limit level being exceeded by more than one consecutive sampling day
|
1. Repeat
in-situ measurement to confirm findings;
2. Identify
source(s) of impact
3. Inform IC(E),
Contractor and EPD;
4. Check
monitoring data, all plant, equipment and Contractor's working methods
5. Discuss
mitigation measures with IC(E), ER and Contractor;
6. Ensure
mitigation measures are implemented;
7. Increase the
monitoring frequency to daily until no exceedance of Limit level for two
consecutive days.
|
1.
Discuss with ET and Contractor on the mitigation measures;
2.
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly;
3.
Assess the effectiveness of the implemented mitigation measures.
|
1. Discuss with IC(E), ET
and Contractor on the proposed mitigation measures;
2. Request Contractor to
critically review the working methods;
3. Make agreement on the
mitigation measures to be implemented;
4. Assess the effectiveness
of the implemented mitigation measures;
5. Consider and instruct,
if necessary, the Contractor to slow down or to stop all or part of the
marine work until no exceedance of Limit Level.
|
1. Inform the ER
and confirm notification of the non-compliance in writing;
2. Rectify
unacceptable practice;
3. Check all
plant and equipment;
4. Consider
changes of working methods;
5. Discuss with
ET, IC(E) and ER and propose mitigation measures to IC(E) and ER within 3
working days;
6. Implement the
agreed mitigation measures;
7. As directed
by the Engineer, slow down or stop all or part of the marine work or
construction activities.
|
4.9. Water Quality Mitigation Measures
4.9.1. The EIA report has
recommended water quality control and mitigation measures. The contractor shall
be responsible for the design and implementation of these measures. The
proposed measures are given in Section 9 of this EM&A Manual.
4.9.2. If the measures listed in
Section 9 are not sufficient to restore the water quality to an acceptable
levels upon the advice of the ET Leader, the Contractor shall liaise with the
ET Leader on some other mitigation measures, propose to IC(E) and ER for
approval, and carry out the mitigation measures.
5. Waste Management
5.1. Waste Management
5.1.1. The contractor shall
be responsible for waste control within
the construction site, removal of the waste material produced from the site and
implementation of any mitigation measures to minimise waste or redress problems
arising from the waste from the site. The waste material may include any tunnel
spoil, sewage, waste water or effluent containing sand, cement, silt or any
other suspended or dissolved material which may flow from the site onto any adjoining land, storm sewer, sanitary
sewer, or any waste matter or refuse to be deposited anywhere within the site
or onto any adjoining land.
5.1.2. The implementation
schedule of the recommended mitigation measures for waste management is
presented in Section 9 of this EM&A Manual and the provisions therein
should be properly enforced.
5.1.3. When handling the waste material,
the following measures shall be undertaken:
·
the strategy for management and
disposal of all wastes arising from execution of individual projects shall be
based on the principle of segregation and re-use on site followed by disposal
to reclamation, public fill or land fill as appropriate;
·
it is not anticipated that bulk
excavations will be carried out in the underlying mud and any limited
quantities of mud which may arise will be disposed of at marine disposal ground
in accordance with WBTC 3/2000;
·
where surplus excavated material is to
be exported from the tunnel excavations to public fill, this should be carried
out by marine transfer if at all possible. It is recommended that a barge
loading point be provided to facilitate transfer of suitable material to public
fill which are accessible by barge and which can be equipped with off loading
facilities. Public filling areas will be designated by the Public Filling
Sub-committee of the Fill Management Committee;
·
disposal of other construction wastes
arising as a result of construction of structures and buildings is governed by
the EPD policy on disposal for construction waste. The principles established
maximise re-use of materials on site and segregation of wastes to ensure that
the minimum quantities are disposed of to landfill and that the maximum is
directed for disposal off-site to reclamation by public filling. All
construction waste should therefore be sorted on site into inert and non-inert
materials;
·
non-inert materials including wood and
other materials including glass, plastics, and metals should be disposed of a
landfill. Other inert materials including, sand, and rubble, are to be
separated from non-inert and disposed of as public fill;
·
site fencing, scaffolding and timber
for the building work should be reused where possible. Those materials that
cannot be re-used should be disposed of at landfill; and
·
paint residues, lubricants and other
oily wastes are classified as chemical waste under the Waste Disposal (Chemical
Waste) (General) Regulations and special controls are imposed to regulate
storage, labelling transport and disposal at the Chemical Waste Treatment
Facility. Construction sites must register individual as chemical waste
producers to comply with regulations.
5.1.4. The contractor shall pay
attention to the Waste Disposal Ordinance, the Dumping at Sea Ordinance, the
Public Health and Municipal Services Ordinance and the Water Pollution Control
Ordinance, and carry out the appropriate waste management work. The relevant
licences/permits, such as the effluent discharge license, the chemical waste
producer registration, etc. shall be obtained. The contractor shall refer
to relevant booklets issued by EPD when
applying for licenses/permits.
5.1.5. During the site inspections
and the document review procedures, the ETL shall pay special attention to the
issues relating to waste management, and check whether the contractor has
followed the relevant contract specifications and the procedures specified
under the laws of Hong Kong.
6. Landscape and Visual
6.1. Mitigation
6.1.1. Mitigation requirements as
identified in the EIA are provided in Section 9 of this EM&A Manual. These requirements were derived as a result
of a Landscape and Visual Impact Assessment undertaken - details of this
assessment are provided in Chapter 14 of the EIA Report.
6.2. Monitoring and Audit Requirements
6.2.1. Monitoring and audit of
the design of landscaping works for the CRIII project will be undertaken
through the implementation of quality assurance procedures within the
designer's organisation. Independent
checking and verification of designs to ensure that mitigation measures are
incorporated into the design will be ensured through the submission of design
proposals to relevant Government Departments.
6.2.2. Monitoring of landscaping
works to be undertaken as part of the CRIII project will to a large extent be
conducted through site inspections to ensure that works are implemented in accordance
with specifications. In addition, it is normal for the landscape contractor to
provide on site maintenance for 12 months following completion of works.
6.2.3. During the monitoring and
audit of noise, dust and runoff, visual inspection with regard to condition of
landscaping works, tree protection and preservation measures and implementation
of temporary landscape treatments should be made. The findings of these inspections shall be reported in the monthly
audit reports.
7. Site
Environmental Audit
7.1. Site
Surveillance
7.1.1. Site Surveillance provides
a direct means to assess and ensure that the project's environmental protection
and pollution control measures are in compliance with the contract
specifications. Site surveillance shall be undertaken regularly and routinely
by the Environmental Monitoring Team to inspect the construction activities in
order to ensure that appropriate environmental protection and pollution control
mitigation measures are implemented in accordance with the EIA recommendations.
With well defined pollution control and impact mitigation specifications and an
established, efficient and remedial action reporting system, the site
inspection is an effective tool to ensure acceptable environmental performance
on the construction site.
7.1.2. The ET Leader is
responsible for formulation of the environmental site inspection, deficiency
and remedial action reporting system, and for carrying out the site inspection
works. He shall in consultation with the IC(E) prepare a procedure for the site
inspection, deficiency and remedial action reporting requirements; and submit
to the Contractor for agreement and to the ER for approval, within 21 days of
commencement of the construction contract.
7.1.3. Regular site inspections
shall be carried out at least once per week for all works areas. The
inspections shall cover the environmental situation, pollution control and
mitigation measures within the site; they shall also review the environmental
situation outside the site area which is likely to be affected, directly or
indirectly, by the site activities. The ET Leader shall make reference to the
following information in conducting the inspections:
·
the EIA Report recommendations and
requirements on environmental protection and pollution control mitigation
measures;
·
works progress, programmes,
site/aerial photos and site plans;
·
individual construction works
methodology proposals (which shall include proposals on associated pollution
control measures);
·
the contract specifications for
environmental protection and pollution prevention control;
·
the relevant environmental protection
and pollution control laws, Pro PECC Notes; and
·
previous site inspection results.
7.1.4. The Contractor shall
update the ET Leader with all relevant information of the construction contract
for him to carry out the site inspections. The inspection report results and
its recommendations for any necessary improvements in the project's environmental
performance shall be submitted, in a site inspection performa, to the IC(E) and
the Contractor within 24 hours, for reference and the taking of immediate
remedial action. The Contractor shall
follow the procedures and time-frame as stipulated in the environmental site
inspection, deficiency and remedial action reporting system (formulated by the
ET Leader) to report on any remedial measures subsequent to the site
inspections.
7.1.5.Ad hoc site inspections shall also be
carried out by the ET and / or IC(E) if major unacceptable or unforeseen
environmental problems are identified. Inspections may also be required
subsequent to receipt of an environmental complaint, or as part of the
investigation work, as specified in the Action Plan for environmental
monitoring and audit.
7.2. Environmental Compliance
7.2.1. There are contractual
environmental protection and pollution control requirements as well as
environmental protection and pollution prevention and control laws in Hong Kong
with which the construction activities shall comply.
7.2.2. The ET Leader shall also
review the progress and programme of the works to check that relevant
environmental laws have not been violated, and that any foreseeable potential
for violating the laws can be prevented.
7.2.3. The Contractor shall
regularly copy relevant documents to the ET Leader so that the checking of the
project's environmental performance can be carried out effectively. The
documents to be submitted by the Contractor shall include at least the updated
Work Progress Reports, the Works Programme, application for any necessary
licenses/permits under the environmental protection laws, and all the valid
licenses/permits received to date. The site diary shall also be available for
the ET Leader's inspection upon his request.
7.2.4. After reviewing the
document, the ET Leader shall advise the ER and the Contractor of any
non-compliance with the project contractual and legislative requirements on
environmental protection and pollution control. The Contractor shall take follow-up and appropriate remedial
actions. If the ET Leader’s review concludes that the current status on
license/permit applications and any planned environmental protection and
pollution control works may not cope with the works programme or potential
violation of environmental protection and pollution control requirements may
arise, he shall advise the Contractor and the ER accordingly. The review shall be copied to the IC(E) for
follow-up action.
7.2.5. Upon receipt of the
advice, the Contractor shall undertake immediate action to remedy the
situation. The ER shall follow up to
ensure that appropriate action has been taken by the Contractor in order that
the project's environmental protection and pollution control requirements are
fulfilled.
7.3. Choice of Construction Method
7.3.1. At times during the
construction phase the Contractor may submit method statements for various
aspects of construction (other than those construction methods that the EIA
study has not imposed conditions; for construction methods that have been
assessed in the EIA study the Contractor is bound to follow the requirements
and recommendations in the EIA study).
Contractor's options for alternative construction methods may introduce
adverse environmental impacts into the project. It is the responsibility of the Environmental Monitoring Team
Leader and the Environmental Monitoring Team, in accordance with established
standards, guidelines and EIA study recommendation to review and determine the
adequacy of the environmental protection and pollution control measures in the
Contractor's proposal in order to ensure no unacceptable impacts would
result. To achieve this end, the
Environmental Monitoring Team Leader shall provide a completed copy of a
Proactive Environmental Protection Proforma to the IC(E) for approval. The IC(E) shall audit the review of the
construction method and endorse the proposal on the basis of no adverse
environmental impacts as per all Environmental Permit Conditions, EIA Study
recommendations and reports, ACE conditions and any endorsed public comments
related to the project and/or any established standards or guidelines.
7.4. Environmental
Complaints
7.4.1. Complaints shall be
referred to the ET Leader for carrying out complaint investigation procedures.
The ET Leader shall undertake the following procedures upon receipt of any
complaints:
·
log complaint and date of receipt onto
the complaint database and inform the IC(E) immediately;
·
investigate the complaint to determine
its validity, and to assess whether the source of the problem is due to project
works;
·
if a complaint is valid and due to
project works, identify mitigation measures in consultation with the IC(E);
·
if mitigation measures are required,
advise the Contractor accordingly;
·
review the Contractor’s implementation
of the identified and required mitigation measures, and the current situation;
·
if the complaint is transferred from
EPD, submit interim report to EPD on status of the complaint investigation and
follow-up action within the time frame assigned by EPD;
·
undertake additional monitoring and
audit to verify the compliant if necessary, and ensure that any valid reason
for complaint does not recur through proposed amendments to work methods,
procedures, machines and/or equipment, etc;
·
report the investigation results and
the subsequent actions to the complainant (if the source of complaint is
identified through EPD, the results should be reported within the time frame
assigned by EPD); and
·
log a record of the complaint,
investigation, the subsequent actions and the results in the monthly EM&A
reports.
7.4.2. During the complaint
investigation work, the Contractor and ER shall co-operate with the ET Leader
in providing all the necessary information and assistance for completion of the
investigation. If mitigation measures (in consultation with the IC(E)) are
required following the investigation, the Contractor shall promptly carry out
the measures. The ER shall ensure that
the measures have been carried out by the Contractor. The complaints handling procedure is shown in Table 7.1.
Table 7.1 :
Procedures in the Event of a Complaint
Step
|
Action
|
Responsible Party
|
ET
|
ER
|
Contractor
|
IC(E)
|
1.
|
The party who receives the complaint
shall notify other parties on the same day :
·
ET notifies ER and the Contractor;
or
·
The Contractor notifies ET and ER;
or
·
ER notifies ET and the Contractor
|
Ö
|
Ö
|
Ö
|
|
|
2.
|
Check workers and sub-contractor's
working methods and remind them of their contractual obligations.
|
|
|
Ö
|
|
|
3.
|
If complaint is related to noise,
dust or water quality, ER may instruct ET to increase monitoring frequency
and to verify the validity of the complaint.
ET notifies ER and the Contractor of the monitoring results.
|
Ö
|
Ö
|
|
|
|
4.
|
Discuss with the Contractor about the
complaint and remedial measures within one day when feasible.
|
Ö
|
Ö
|
|
|
|
5.
|
Implement remedial measures on the same
day if feasible.
|
|
|
Ö
|
|
|
6.
|
If complaint is related to noise, dust or
water quality, ER may instruct ET to increase monitoring frequency to assess
the efficacy of the remedial actions.
Notify the Contractor of the monitoring results.
|
Ö
|
Ö
|
|
|
|
7.
|
May increase site audit frequency to
assess efficacy of remedial measures.
Inform the Contractor of the effect of the remedial measures.
|
|
|
|
Ö
|
|
8.
|
Party who received the complaint shall
inform the complainant of the actions taken.
|
Ö
|
Ö
|
Ö
|
|
|
|
|
|
|
|
|
|
|
|
8. REPORTING
8.1. General
8.1.1. The following reporting
requirements are based upon a paper documented approach. However, the same
information can be provided in an electronic medium upon agreeing the format
with the ER and EPD. All the monitoring
data (baseline and impact) shall also be submitted in diskettes in an agreed
format.
8.2. Baseline
Monitoring Report
8.2.1. The ET Leader shall
prepare and submit a Baseline Environmental Monitoring Report within 10 working
days of completion of the baseline monitoring. Copies of the Baseline
Environmental Monitoring Report shall be submitted to each of the four parties:
the Contractor, the IC(E), the ER, and the EPD. The ET Leader shall liaise with
the relevant parties on the exact number of copies required. The form and content of the report, and the
representation of baseline monitoring data shall be in a format to the
satisfaction of EPD and include, but not be limited to the following :
·
up to half a page executive summary;
·
brief project background information;
·
drawings showing locations of the
baseline monitoring stations;
·
an updated construction programme with
milestones of environmental protection / mitigation activities annotated;
·
monitoring results (in both hard and
diskette copies) together with the following information:
-
monitoring methodology;
-
name of laboratory used type of
equipment used and calibration details;
-
parameters monitored;
-
monitoring locations (and depth);
-
monitoring date, time, frequency and
duration; and
-
QA/QC results and detection limits.
·
details on influencing factors,
including:
-
major activities, if any, being
carried out on the site during the period;
-
weather conditions during the period;
and
-
other factors which might affect the
results.
·
determination of the Action and Limit
Levels (AL Levels) for each monitoring parameter and statistical analysis of
the baseline data. The analysis shall
conclude if there is any significant difference between control and impact
stations for the parameters monitored;
·
revisions for inclusion in the
EM&A Manual; and
·
comments and conclusions.
8.3. Monthly
EM&A Reports
8.3.1. The ETL shall undertake
all reporting during the course of the construction works which shall be
reviewed by the IC(E) to determine that the reporting has been carried out in
accordance with the requirements of the Manual.
8.3.2. The results and findings
of all EM&A work required in the Manual shall be recorded in the monthly
EM&A Reports prepared by the ET Leader. The EM&A Report shall be
endorsed by the IC(E) and submitted within 10 working days of the end of each
reporting month, with the first report due in the month after construction
commences. A maximum of 4 copies of each monthly EM&A Report shall be
submitted to each of the four parties: the Contractor, the IC(E), the ER, and
the EPD. Before submission of the first EM&A Report, the ET Leader shall
liaise with the parties on the exact number of copies and format of the monthly
reports in both hard copy and electronic medium requirement. The ET Leader shall review the number and
location of monitoring stations and parameters to monitor every 6 months or on
an as needed basis in order to cater for the changes in the surrounding
environment and nature of works in progress.
First
Monthly EM&A Report
8.3.3. The first monthly EM&A
report shall include at least, but not be limited to, the following :
·
Executive Summary (1 - 2 pages) :
-
Breaches of AL levels;
-
Complaint Log;
-
Notifications of any summons and
successful prosecutions;
-
Reporting Changes;
-
Future key issues.
·
Basic Project Information :
-
Project organisation including key
personnel contact names and telephone numbers;
-
Construction Programme with fine
tuning of construction activities showing the inter-relationship with
environmental protection/mitigation measures for the month;
-
Management structure; and
-
Works undertaken during the month.
·
Environmental Status :
-
Works undertaken during the month with
illustrations (such as location of works, daily dredging/filling rates,
percentage fines in the fill material used); and
-
Drawing showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations.
·
Summary of EM&A requirements :
-
All monitoring parameters;
-
Environmental quality performance
limits (Action and Limit levels);
-
Event-Action Plans;
-
Environmental mitigation measures, as
recommended in the project EIA study final report;
-
Environmental requirements in contract
documents;
·
Implementation Status :
Advice on the implementation status of
environmental protection and pollution control/mitigation measures including
measures for ecological and landscape and visual impacts, as recommended in the
project EIA study report, summarised in the updated implementation schedule;
·
Monitoring Results :
To provide monitoring results (in both
hard and diskette copies) together with the following information:
-
Monitoring methodology;
-
Name of laboratory and types of equipment used and
calibration details;
-
Parameters monitored;
-
Monitoring locations (and depth);
-
Monitoring date, time, frequency, and duration;
-
Weather conditions during the period;
-
Graphical plots of the monitored parameters in the
month annotated against;
i.
The major activities being carried out on site during
the period;
ii.
Weather conditions that may affect the result; and
iii.
Any other factors which might affect the monitoring
results.
-
Any other factors which might affect the monitoring
results; and
-
QA/QC results and detection limits.
·
Report on Non-compliance, Complaints, Notifications
of Summons and Successful Prosecutions
-
Record of all noncompliance (exceedances) of the
environmental quality performance limits (Action and Limit levels);
-
Record of all complaints received (written or verbal)
for each media, including locations and nature of complaints investigation,
liaison and consultation undertaken, actions and follow-up procedures taken,
results and summary;
-
Record of all notifications of summons and successful
prosecutions for breaches of the current environmental protection/pollution
control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
-
Review of the reasons for and the implications of
non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
-
Description of the actions taken in the event of
noncompliance and deficiency reporting and any follow-up procedures related to
earlier noncompliance.
·
Others
-
An account of the future key issues as reviewed from
the works programme and work method statements;
-
Advice on the solid and liquid waste management
status; and
-
Submission of implementation status proforma,
proactive environmental protection proforma, regulatory compliance proforma,
site inspection proforma, data recovery schedule and complaint log summarizing
the EM&A of the period.
Subsequent Monthly EM&A Report
8.3.4. The subsequent monthly
EM&A reports shall include the following :
·
Executive Summary (1-2 pages)
-
Breaches of AL levels ;
-
Notification of any summons and
successful prosecutions;
-
Complaint Log;
-
Reporting Changes; and
-
Future key issues.
·
Environmental Status
-
Construction Programme with fine
tuning of construction activities showing the inter-relationship with
environmental protection/mitigation measures for the month;
-
Works undertaken during the month with
illustrations including key personnel contact names and telephone numbers; and
-
Drawing showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations.
·
Implementation Status
Advice on the implementation status of environmental
protection and pollution control/mitigation measures including measures for
ecological and visual impacts, as recommended in the project EIA study report,
summarised in the updated implementation schedule.
·
Monitoring Results
To provide monitoring results (in both
hard and diskette copies) together with the following information :
-
Monitoring methodology;
-
Name of laboratory and types of
equipment used and calibration details;
-
Parameters monitored;
-
Monitoring locations (and depth);
-
Monitoring date, time, frequency, and
duration;
-
Weather conditions during the period;
-
Graphical plots of the monitored
parameters in the month annotated against :
i.
The major activities being carried out on site during the period;
ii. Weather conditions that may affect the results; and
iii. Any other factors which might affect the monitoring results.
-
Any other factors which might affect
the monitoring results; and
-
QA/QC results and detection limits.
·
Report on Non-compliance, Complaints,
Notifications of Summons and Successful Prosecutions
-
Record of all noncompliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels);
-
Record of all complaints received
(written or verbal) for each media, including locations and nature of
complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
-
Record of all notifications of summons
and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, including locations and nature of
the breaches, investigation, follow-up actions taken, results and summary;
-
Review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
-
A description of the actions taken in
the event of noncompliance and deficiency reporting and any follow-up
procedures related to earlier noncompliance;
·
Appendix
-
AL levels;
-
Graphical plots of trends of monitored
parameters at key stations over the past four reporting periods for
representative monitoring stations annotated against the following :
i.
Major activities being carried out
site during the period;
ii.
Weather conditions during the period; and
iii. Any other factors which might affect the monitoring results.
-
Monitoring schedule for the present
and next reporting period;
-
Cumulative statistics on complaints,
notifications of summons and successful prosecutions; and
-
Outstanding issues and deficiencies.
8.4. Quarterly
EM&A Summary Reports
8.4.1. The Quarterly EM&A
Summary Report which should generally be around 5 pages (including about 3 of
text and tables and 2 of figures) should contain at least the following
information. Apart from these, the
first quarterly summary report should also confirm that the monitoring work is
proving effective and that it is generating data with the necessary statistical
power to categorically identify or confirm the absence of impact attributable
to the works :
·
Up to half a page executive summary;
·
Basic project information including a
synopsis of the project organisation, programme, contacts of key management,
and a synopsis of work undertaken during the quarter;
·
A brief summary of EM&A
requirements including:
-
Monitoring parameters;
-
Environmental quality performance
limits (Action and Limit levels); and
-
Environmental mitigation measures, as
recommended in the project EIA study final reports.
·
Advice on the implementation status of
environmental protection and pollution control/mitigation measures, as
recommended in the project EIA study report, summarised in the updated
implementation schedule;
·
Drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations;
·
Graphical plots of the trends of
monitored parameter over the past 4 months (the last month of the previous
quarter and the present quarter) for representative monitoring stations
annotated against;
-
The major activities being carried out
on site during the period;
-
Weather conditions during the period;
and
-
Any other factors which might affect
the monitoring results.
·
Advice on the solid and liquid waste
management status;
·
A summary of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels);
·
A brief review of the reasons for and
the implications of non-compliance including review of pollution sources and
working procedures;
·
A quarterly assessment of construction
impacts on suspended solids at the project site, including, but not limited to,
a comparison of the difference between the quarterly means and 1.3 times of the
ambient mean, which is defined as 30% increase of the baseline data or EPD
data, of the related parameters by using appropriate statistical procedures. Suggestion of appropriate mitigation
measures if the quarterly assessment analytical results demonstrate that the
quarterly mean is significantly higher than the 1.3 on water quality times of
the ambient mean (p < 0.05);
·
A summary description of the actions
taken in the event of non-compliance and any follow-up procedures related to
earlier non-compliance;
·
A summary record of all complaints
received (written or verbal) for each media, liaison and consultation
undertaken, actions and follow-up procedures taken;
·
A summary record of notifications of
summons and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, locations and nature of the
breaches, investigation, follow-up actions taken and results;
·
Comments (e.g. effectiveness and
efficiency of the mitigation measures), recommendations (e.g. any improvement
in the EM&A programme) and conclusions for the quarter; and
·
Proponent’s contacts and any hotline
telephone number for the public to make enquiries.
8.4.2. Each quarterly EM&A
Report shall be prepared by the ET Leader and endorsed by the IC(E). It shall be submitted within 10 working days
of the end of each reporting quarter. A
maximum of 4 copies of each quarterly EM&A Report shall be submitted to
each of the four parties: the Contractor, the IC(E), the ER, and the EPD.
Before submission of the first quarterly EM&A Report, the ET Leader shall
liaise with the parties on the exact number of copies and format of the
quarterly reports in both hard copy and electronic medium requirement.
8.5. Final EM&A Summary Report
8.5.1. The termination of
EM&A programme shall be determined on the following basis :
·
Completion of construction activities
and insignificant environmental impacts fo the remaining outstanding
construction works;
·
Trends anslysis to demonstrate the
narrow down of monitoring exceedances due to construction activities and the
return of ambient environmental conditions in comparison with baseline data;
and
·
No environmental complaint and prosecution
involved.
8.5.2. The proposed termination
may be required to be consulted with related local community such as District
Council and the proposal should be endorsed by the IC(E), ER and the project
proponent prior to final approval from the Director of Environmental
Protection.
8.5.3. The Final EM&A Report
shall be prepared by the ET Leader and endorsed by the IC(E). It shall be submitted within 10 working days
of the end of the termination of the EM&A programme. A maximum of 4 copies of the Final EM&A
Report shall be submitted to each of the four parties: the Contractor, the
IC(E), the ER, and the EPD. Before submission of the Final EM&A Report, the ET Leader shall liaise
with the parties on the exact number of copies and format of the report in both
hard copy and electronic medium requirement.
8.5.4. The final EM&A summary
report shall include, inter alia, the following :
·
An executive summary;
·
Basic project information including a
synopsis of the project organisation, programme, contacts of key management,
and a synopsis of work undertaken during the entire construction period;
·
A brief summary of EM&A
requirements including :
-
Monitoring parameters;
-
Environmental quality performance
limits (Action and Limit levels); and
-
Environmental mitigation measures, as
recommended in the project EIA study final report;
·
Advice on the implementation status of
environmental protection and pollution control/mitigation measures, as
recommended in the project EIA study report, summarised in the updated
implementation status proformas;
·
Drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations;
·
Graphical plots of the trends of
monitored parameters over the construction period for representative monitoring
stations annotated against;
-
The major activities being carried out
on site during the period;
-
Weather conditions during the period;
-
Any other factors which might affect
the monitoring results; and
-
The return of ambient environmental
conditions in comparison with baseline data;
·
Compare and contrast the EM&A data
with the EIA predictions and annotate with explanation for any discrepancies;
·
Provide clear-cut decisions on the
environmental acceptability of the project with reference to the specific
impact hypothesis;
·
Advice on the solid and liquid waste
management status;
·
A summary of noncompliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels);
·
A brief review of the reasons for, and
the implications of, non-compliance including review of pollution sources and
working procedures;
·
A summary description of the actions
taken in the event of non-compliance and any follow-up procedures related to
earlier non-compliance;
·
A summary record of all complaints
received (written or verbal) for each media, liaison and consultation
undertaken, actions and follow-up procedures taken;
·
Review the monitoring methodology
adopted and with the benefit of hindsight, comment on its effectiveness
(including cost effectiveness);
·
A summary record of notifications of
summons and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, location and nature of the breaches,
investigation, follow-up actions taken and results;
·
Review the practicality and
effectiveness of the EIA process and EM&A programme (e.g. effectiveness and
efficiency of the mitigation measures), recommend any improvement in the
EM&A programme; and
·
A conclusion to state the return of
ambient and/or the predicted scenario as per EIA findings.
8.6. Data
Keeping
8.6.1. All documentation is
required to be filed in a traceable and systematic manner. Site documents, such as, monitoring field
records, laboratory analysis records, meeting minutes, correspondences etc.,
shall be cross-referenced by the ET Leader and be ready for inspection upon
request. All Construction Phase
EM&A results and findings shall be documented in the Construction Phase
EM&A reports prepared by the ET and endorsed by IC(E) prior to
dissemination to the Contractor, ER and the Director of Environmental
Protection.
8.6.2. All documentation to the
Director of Environmental Protection shall be in paper form and/or electronic
form (in the format in agreement with the Director) upon request. Prior to submission, the water quality data
software format shall be agreed with EPD.
All documents and data shall be kept for at least one year after the
completion of the construction contract.
All submissions (reports, data, and correspondences etc.) to the
Director of Environmental Protection shall be liable to use freely for the
purposes of communicating environmental data and the owner of information shall
claim no copyright. Any request to
treat all or part of submission in confidence will be respected, but if no such
request is made it will be assumed that the submission is not intended to be
confidential.
8.7. Interim
Notifications of Environmental Quality Limit Exceedances
8.7.1. With reference to Event/Action
Plans in Tables 2.3, 3.2 and 4.3, when the environmental quality limits are
exceeded, the ET Leader shall immediately notify the ER and relevant Government
Departments, as appropriate. The notification shall be followed up with advice
to EPD on the results of the investigation, proposed action and success of the
action taken, with any necessary follow-up proposals. A sample template for the
interim notifications is shown in Table 8.1.
Table 8.1 : Sample Template for Interim Notifications
of Environmental Quality Limits Exceedances
Project
|
|
Date
|
|
Time
|
|
Monitoring Location
|
|
Parameter
|
|
Action & Limit Levels
|
|
Measured Level
|
|
Possible reason for Action or Limit Level
Non-compliance
|
|
Actions taken / to be taken
|
|
Remarks
|
|
|
|
|
|
Location
Plan
|
Prepared by :
|
|
|
|
|
Designation :
|
|
|
|
|
Signature :
|
|
|
|
|
Date :
|
|
|
|
|
9. Schedule of Mitigation from the EIA
Table 9.1 : Schedule of Impacts and Mitigation Measures
No.
|
Activity
|
Mitigation/EIA Recommendations
|
Responsibility for Implementation
|
Location
Duration completion
of measures
|
Implementation Stage
C : Construction
D : Design
|
Permit Conditions apply to
|
Relevant Guidelines Legislation
|
1
|
Operational Traffic Noise*
|
The openings of ventilation buildings or ventilation shafts should be
placed carefully and ideally should be such that they are not facing directly
onto any NSR.
|
Various
|
Area Wide, Proposals at
design stage for Implementation during construction
|
D/C
|
N/A
|
--
|
2
|
Operational Air Quality
|
Air intakes for commercial/G/IC buildings should be placed such that
they are at locations where contours indicate AQOs are met.
|
ArchSD/Private sector +
|
CRIII
During development of sites
Completion of CRIII
|
Development of CRIII
|
Carry forward to design
stage
|
6
|
3
|
Operational Water Quality
|
Provision of grit traps for surface drainage
|
TDD’s Contractor
|
New roads and paved areas
During construction
End of construction
|
C
|
P, R, A, C
|
7
|
4
|
Operational
Landscape and Visual
|
Operational stage landscape and visual mitigation measures should
include +
|
|
|
|
|
|
|
|
·
Implementation of the Waterfront Promenade, Statue Square Corridor,
Historic Corridor, Civic Corridor, Arts and Entertainment Corridor,
Streetscape Network, Landscape Decks, and Supplementary Landscape Spaces;
|
Various
|
Area wide, proposals at
design stage for implementation during construction
|
D/C
|
P
|
--
|
|
|
·
provision of a legible, integrated pedestrian circulation system
linking major activity nodes, reinforcing links with adjoining areas, and
providing an international quality hard and soft landscape treatment;
|
|
|
|
|
|
|
|
·
provision of a grade separated pedestrian system to minimise
vehicular/ pedestrian conflict;
|
|
|
|
|
|
|
|
·
provision of an integrated network of local and regional open spaces
for passive and active recreation;
|
|
|
|
|
|
|
|
·
preservation of selected architectural features;
|
|
|
|
|
|
|
|
·
preservation insitu of existing significant vegetation, principally
the two Banyan Trees flanking the Tamar Site;
|
|
|
|
|
|
|
|
·
new roads to incorporate suitable streetscape amenity and landscape
planting to minimise visual and environmental impacts;
|
|
|
|
|
|
|
|
·
existing roads upgraded to ‘marry’ with the proposed landscape
framework;
·
Hydroseeding of reclamation if there is no immediate use of the site,
periphery of the reclamation;
·
Designated service corridors beneath footpaths to prevent potential
impacts upon vegetation during services maintenance;
|
|
|
|
|
|
|
|
·
Sensitively designed colour themes to footpath paving areas; and
·
Sensitively designed seawall to enhance the recreational value of the
future promenade can be included.
|
Various
|
Area wide, proposals at
design stage for implementation during construction
|
D/C
|
P
|
--
|
5
|
Construction Noise Control Requirements
|
Use
of the following quiet mechanical equipment for construction
works :
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P, R, A, C
|
-
|
|
|
·
air compressor;
|
|
|
|
|
|
|
·
paver;
|
|
|
|
|
|
|
|
·
hand held breaker;
|
|
|
|
|
|
|
|
·
breaker, excavator mounted;
|
|
|
|
|
|
|
|
·
bulldozer;
|
|
|
|
|
|
|
|
·
concrete lorry mixer;
|
|
|
|
|
|
|
|
·
concrete pump;
|
|
|
|
|
|
|
|
·
crane;
|
|
|
|
|
|
|
|
·
dump truck;
|
|
|
|
|
|
|
|
·
excavator/ loader;
|
|
|
|
|
|
|
|
·
grader;
|
|
|
|
|
|
|
|
·
lorry ;
|
|
|
|
|
|
|
|
·
poker;
|
|
|
|
|
|
|
|
·
road roller;
|
|
|
|
|
|
|
|
·
vibratory roller;
|
|
|
|
|
|
|
|
Use
of noise barriers (in the form if purpose built site hoarding of 3 - 5 m
height and surface density of at least 7 kgm2 with cranked top)
for the following works:
·
Hong Kong Station Extended Overrun Tunnels to north of Central
Barracks.
·
North Island Line Protection Works to north of Central Barracks;
·
Road/Drainage Works to north of Central Barracks;
·
Culvert F Piling Works to north of City Hall.
|
TDD’s Contractor
|
Work Sites as stated
Start of activity stated
End of activity stated
|
C
|
P, A
|
|
|
|
·
Only well-maintained plant should be operated on-site and plant
should be serviced regularly during the construction programme.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
4
|
|
|
·
Silencers or mufflers on construction equipment shoud be utilised and
should be properly maintained during the construction programme.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
4
|
|
|
·
Mobile plant, if any, should be sited as far away from noise
sensitive facilities as possible.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
4
|
|
|
·
Machines and plant (such as trucks) that may be in intermittent use
should be shut down between works periods or should be throttled down to a
minimum.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
4
|
|
|
·
Plant known to emit noise strongly in one direction should, wherever
possible, be orientated so that the noise is directed away from nearby noise
sensitive facilities.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
4
|
|
|
·
Material stockpiles and other structures should be effectively
utilised, wherever practicable, in screening noise from on-site construction
activites.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
4
|
6
|
Construction
Air Quality Control Requirements
|
·
Strictly limit truck speed on site to below 10 km per hour and water
spraying to keep the haul roads in wet condition.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6,7
|
|
|
·
Twice daily watering of the site with active operations when the
weather and the work site are dry.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6,7
|
|
|
·
Watering during excavation and material handling.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6,7
|
|
|
·
Provision of vehicle wheel and body washing facilities at the exit points
of the site, combined with cleaning of public roads where necessary.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6,7
|
|
|
·
Tarpaulin covering of all dusty vehicle loads transported to, from
and between site locations.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6,7
|
|
|
·
Covers for dusty stockpiles
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6
|
|
|
·
All plant shall be maintained ot prevent any undue air emmissions
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
6
|
7
|
Construction Water Quality Control Requirements
|
Specific
Meaures Associated with Dredging Works
|
|
|
|
|
|
|
·
the use of closed clamshell (water-tight) grab dredgers to remove
seriously contaminated material such that the amount of SS and other
pollutants released from the marine mud and pore water can be minimised;
|
TDD’s Contractor
|
Whole reclamation area
During reclamation works
End of reclamation works
|
C
|
R
|
7
|
|
|
·
the prohibition of stockpiling of any moderately or seriously
contaminated marine sediment, and careful control of stockpiling of any
uncontaminated sediment to prevent runoff, resuspension and odour nuisances;
and
|
|
|
|
|
|
|
·
the control of dredging and bulk reclamation filling rates within
acceptable limits. Based upon the
construction sequence developed for this study the maximum dredging and
filling rates adopted for Final Reclamation Area East were :
Maximum Dredging
Rate : 184 m2/hour
Maximum Daily
Filling Rate : 17,727 m3/day
(for bulk
reclamation filling)
Maximum dredging and filling rates for other
reclamation sites should take account of information contained in Table 10.14
of the EIA Report and envisaged construction sequence.
|
|
|
|
|
|
|
|
·
no dredging should take place under very bad weather conditions.
|
|
|
|
|
|
|
|
·
silt curtain around dredging sites to be provided as necessary.
|
|
|
|
|
|
|
|
Specific
Measure for Marine Disposal of Dredged Materials and Maine Sand Filling Works
|
TDD’s Contractor
|
Whole reclamation area
During reclamation works
End of reclamation works
|
C
|
R
|
7
|
|
|
·
all vessels should be sized such that adequate clearance is
maintained between vessels and the sea bed at all states of the tide to
ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash;
|
|
|
|
|
|
|
·
all hopper barges and dredgers should be fitted with tight fitting
seals to their bottom openings to prevent leakage of material;
|
|
|
|
|
|
|
|
·
loading of hopper barges should be controlled to prevent splashing of
dredged or filling material to the surrounding water, and barges or hoppers
should not be filled to a level which will cause the overflow of materials or
polluted water during loading or transportation;
|
|
|
|
|
|
|
|
·
the works should cause no visible foam, oil, grease, scum, litter or
other objectionable matter to be present on the water within the site or
dumping grounds;
|
TDD’s Contractor
|
Whole reclamation area
During reclamation works
End of reclamation works
|
C
|
R
|
7
|
|
|
·
bulk filling should be carried out, where feasible, behind completed
seawall to above high water mark. In
general and where physically practical, filling should not be carried out
without the seawall having been substantially completed for a distance of
100m – 200m ahead of filling; and
|
|
|
|
|
|
|
|
·
fill materials should comply with technical specification
requirements and be taken from approved sources only. The maximum fines content of marine sand
should be limited to 5% as assumed in the water quality assessments.
|
|
|
|
|
|
|
|
·
transport of contaminated mud (or filling material) to the marine
disposal site (or works site) should, wherever possible, be by split barge of
not less than 750 m3 capacity, well maintained and capable of
rapid opening and discharge at the disposal site;
·
the dredged material should be disposed in the pit by bottom dumping,
at a location within the pit specified by the MFC;
·
discharge should be undertaken rapidly and the hoppers should then
immediately be closed. Material adhering to the sides of the hopper should
not be washed out of the hopper and the hopper should remain closed until the
barge next return to the disposal site;
·
the dumping vessel is not required to station but will be guided by
the site staff managing the disposal facility. The vessel crew should be familiar with such operational
procedures;
·
monitoring of the barge loading to ensure that loss of material does
not take place during transportation; and
|
|
|
|
|
|
|
|
·
Transport barges or vessels shall be equipped with automatic
self-monitoring devices.
|
|
|
|
|
|
|
|
Specific
Measures Associated with Dredging and Filling Works when CRIII Dredging and
Filling Works are being constructed concurrently with WDII Dredging and
Filling Works
|
|
|
|
|
|
|
|
·
deployment of silt curtains around the dredging and fill release
points to contain SS within the construction site during dredging and filling;
·
deployment of silt screens at the cooling water intakes and WSD salt
water intakes to further minimise the intake of SS within the sea water.
|
TDD’s Contractor
|
Reclamation Areas as appropriate
When CRIII and WDII - Dredging and Filling Works occur concurrently
End of Concurrent Works
|
C
|
R
|
-
|
|
|
Specific Measures Associated with Floating Debris
The result of the floating debris simulation has shown that the
intermediate layout of the proposed reclamation has potential to trap
floating rubbish. Monitoring and control of the construction activities
should be taken to prevent the release of construction waste and rubbish from
the construction site. Collection of floating debris should be carried out at
least once every day by the CRIII Contractor, and more frequently (two or
three times per day) at the water body south of the Initial Reclamation Area
West and near the cooling water intakes where large substances could block
the screens and filter pipes of the intakes and reduce their efficiency.
Debris should be collected and taken to landfill sites for disposal.
|
TDD’s Contractor
|
Whole reclamation area
During construction
At end of construction
|
C
|
R
|
-
|
|
|
Specific Measures for Dealing with Culvert L Outfall at Completion of
CRIII Eastern Seawall
|
|
|
|
|
|
|
|
As a mitigation measure, to avoid the accumulation of water borne
pollutants within a temporary embayment to the east of CRIII, an impermeable
barrier, suspended from a floating boom on the water surface and extending
down to the seabed, will be erected by the CRIII
Contractor on completion of the CRIII eastern seawall. The barrier will
channel the stormwater discharge flows from Culvert L to the outside of the
embayment. The CRIII Contractor will
maintain this barrier until the WDII Contractor takes possession of this
site, whereupon the WDII Contractor will takeover the maintenance of this
barrier until the reclamation works in this area are carried out and the new
Culvert L extension is constructed.
|
TDD's Consultant
|
Culvert L Outfall
During Construction
To handover to WDII Contractor
|
C
|
R
|
--
|
|
|
Construction
Run-off and Drainage
|
|
|
|
|
|
|
|
·
Control of Site
Surface Runoff:
- Surface run-off
from construction sites should be discharged into storm drains via adequately
designed sand/silt removal facilities such as sand traps, silt traps and
sediment basins. Channels or earth bunds or sand bag barriers should be
provided on site to properly direct stormwater to such silt removal
facilities. Perimeter channels at site boundaries should be provided where
necessary. Catchpits and perimeter channels should be constructed in advance
of site formation works and earthworks.
- Silt removal
facilities, channels and manholes should be maintained.
|
TDD’s Contractor
|
Works Area
During construction
End of construction
|
C
|
P,R,A,C
|
7
|
|
|
- Construction
works should be programmed to minimise soil excavation works in rainy seasons
(April to September). If excavation in soil cannot be avoided, temporarily
exposed slope surfaces should be covered and temporary access roads should be
protected by crushed stone or gravel, as excavation proceeds. Intercepting
channels should be provided.
- Earthworks
final surfaces should be well compacted and the subsequent permanent work or
surface protection should be carried out immediately after the final surfaces
are formed to prevent erosion caused by rainstorms. Appropriate drainage such
as intercepting channels should be provided where necessary.
- Measures
should be taken to minimise the ingress of rainwater into trenches. If
excavation of trenches in wet seasons is necessary, they should be dug and
backfilled in short sections. Rainwater pumped out from trenches or
foundation excavations should be discharged into storm drains via silt
removal facilities.
- Open
stockpiles of construction materials should be covered.
- Manholes
should be adequately covered and temporarily sealed.
|
|
|
|
|
|
|
|
·
Groundwater
- Groundwater pumped out of tunnels or
caverns should be discharged into storm drains after the removal of silt.
|
|
|
|
|
|
|
|
·
Boring and Drilling Water
- Water
used in ground boring and drilling for site investigation or rock/soil
anchoring should as far as practicable be recirculated after sedimentation.
Wastewater should be discharged into storm drains via silt removal
facilities.
|
TDD’s Contractor
|
Work Area
During construction
End of construction
|
C
|
P,R,A,C
|
7
|
|
|
·
Wastewater from Concrete Batching and Precast Concrete Casting
- Wastewater
generated from the washing down of mixer trucks and drum mixers and similar
equipment should wherever practicable be recycled. The discharge of
wastewater should be kept to a minimum.
- To
prevent pollution from wastewater overflow, the pump sump of any water
recycling system should be provided with an on-line standby pump of adequate
capacity and with automatic alternating devices.
- Under
normal circumstances, surplus wastewater may be discharged into foul sewers
after treatment in silt removal and pH adjustment facilities (to within the
pH range of 6 to 10). Disposal of wastewater into storm drains will require
more elaborate treatment. Surface run-off should be segregated from the
concrete mixing and casting yard area as much as possible, and diverted to
the stormwater drainage system. Surface run-off contaminated by materials in
a concrete mixing area or casting yard should be adequately treated before
disposal into stormwater drains.
|
|
|
|
|
|
|
|
·
Wheel Washing Water
- All
vehicles and plant should be cleaned before they leave the construction site.
A wheel washing bay should be provided at every site exit if practicable and
wash-water should have sand and silt settled out or removed before
discharging into storm drains. The section of construction road between the
wheel washing bay and the public road should be paved with backfall to reduce
vehicle tracking of soil and to prevent site run-off from entering public
road drains.
|
TDD’s Contractor
|
Work Area
During construction
End of construction
|
C
|
P,R,A,C
|
7
|
|
|
·
Bentonite Slurries
- Bentonite
slurries should be reconditioned and reused wherever practicable. If the disposal
of a certain residual quantity cannot be avoided, the used slurry may be
disposed of at the marine spoil site subject to obtaining a marine dumping
licence from EPD (on a case-by-case basis).
- If
the used bentonite slurry is intended to be disposed of through the public
drainage system, it should be treated to the respective effluent standards
applicable to foul sewers, storm drains or the receiving waters as set out in
the WPCO Technical Memorandum on Effluent Standards.
|
|
|
|
|
|
|
|
·
Wastewater from Building Construction
- Before commencing any demolition works,
all sewer and drainage connections should be sealed to prevent building
debris, soil, sand etc. from entering public sewers/drains.
- Wastewater generated from building
construction activities including concreting, plastering, internal
decoration, cleaning of works and similar activities should not be discharged
into the stormwater drainage system. If the wastewater is to be discharged
into foul sewers, it should undergo the removal of settleable solids in a
silt removal facility, and pH adjustment as necessary.
|
|
|
|
|
|
|
|
·
Licensing of Construction Site Discharges within Water Control Zones
- All discharges into any drainage or
sewerage systems, or inland or coastal waters, or into the ground (e.g. from
septic tanks) within a Water Control Zone are controlled under the Water
Pollution control Ordinance (WPCO), except the discharge of domestic sewage
into foul sewers or the discharge of unpolluted water into storm drains or
into the waters of Hong Kong. Construction site discharges are controlled
under the WPCO.
- Discharges controlled under the WPCO must
comply with the terms and conditions of a valid WPCO licence.
|
|
|
|
|
|
8.
|
Construction
Waste Control Requirements
|
Specific
Measures Associated with Marine sediments
|
|
|
|
|
|
|
|
In
accordance with the WBTC No. 3/2000, the seriously contaminated material must
be dredged and transported with great care.
Mitigation measures, includeding the use of close-grab dredgers, shall
be incorporated.
The
dredged contaminated sediment must be effectively isolated from the
environment upon final disposal and shall be disposed of at the East Sha Chau
Contaminated Mud Pits.
|
TDD's Contractor
|
Whole Reclamation Area
During Reclamation Works
End of Reclamation Work
|
C
|
R
|
7
|
|
|
Segregation
and Disposal of Wastes
|
|
|
|
|
|
|
|
·
inert demolition/construction waste material when deemed suitable for
reclamation or land formation should be re-used on-site;
·
non-inert demolition / construction waste material should be disposed
of at landfills;
·
chemical waste as defined by Schedule 1 of the Waste Disposal
(Chemical Waste) (General) Regulation, should be stored in accordance with
approved methods defined in the Regulation and Code of Practice and the
chemical waste disposed of at the Chemical Waste Treatment Facility located
at Tsing Yi or an approved recycler;
·
general refuse should be recycled where possible or disposed of at
public landfill.
|
TDD's Contractor
|
Works Areas
During Construction
End of Construction
|
C
|
P, R, A, C
|
1,8, 9
|
|
|
Storage, Collection and Transport of Waste
·
wastes should be handled and stored in a manner which ensures that
they are held securely without loss or leakage thereby minimising the
potential for pollution. Release of these potential pollutants into marine
waters during storage, handling or barge transportation should not be
permitted as introduction of polluted waters is likely to have detrimental
effects on water quality and water sensitive receivers;
·
only reputable waste hauliers authorised to collect the specific category
of waste concerned should be employed;
·
appropriate measures should be employed to minimise windblown litter
and dust during transportation by using enclosed bins, covering trucks or
transporting wastes in enclosed containers;
·
the necessary waste disposal permits and registrations should be
obtained from the appropriate authorities, if they are required, in
accordance with the Waste Disposal Ordinance (Cap 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap 354) and the Crown Land Ordinance;
·
collection of general refuse should be carried out frequently,
preferably daily;
·
waste should only be disposed of at licensed sites and the civil
engineering contractor should develop procedures to ensure that illegal
disposal of wastes does not occur;
·
waste storage areas should be well maintained and cleaned regularly;
·
records should be maintained of the quantities of wastes generated,
recycled and disposed, determined by weighing each load or other method; and
·
A “trip ticket” system should be implemented, if required by
Government.
|
TDD's Contractor
|
Works Areas
During Construction
End of Construction
|
C
|
P, R, A, C
|
1, 8, 9
|
9
|
Construction
Landscape and Visual Control Requirements
|
Construction
stage landscape and visual mitigation measures should include :
·
Minimising contractors accesses and working areas as far as possible;
·
Protection and retention of existing vegetation where possible in
accordance with the Hong Kong Government "A Guide to Tree Planting and
Maintenance in Urban Hong Kong, Section 5" Care of Trees on Development
Sites' and the Country Parks Ordinance
·
Transplanting of trees where appropriate;
·
Advance planting and visual screening;
·
Conservation of top soil;
·
Design of the temporary works areas so as to optimise eventual use as
promenade and public open space; and
·
Sensitively designed site hoarding.
|
TDD's design consultant
|
Area wide during design and contract preparation
|
D
|
P, R, A, C
|
11, 12, 13,14
|
10
|
Monitoring
and Audit
|
To
be carried out in accordance with the Schedule in the EM and A Manual
|
TDD*/Contractor/RSS
|
Works areas
During construction
End of construction and within one year of operational phase
|
C/O
|
P, R, A, C
|
1
|
|
|
|
TDD’s design consultant
|
Area wide during design and contract preparation
|
D
|
P, R, A, C
|
11,12,13,14
|
1. Environmental Impact Assessment
Ordinance Technical Memorandum (EIAO)
2. HKPSG
3. ExCo Criteria for ITR
4. Noise Control Ordinance
5. The ProPECC Note PN2/93 (Construction
Noise daytime limits)
6. Air Pollution Control Ordinance (APCO)
7.
Water Pollution Control Ordinance
(WPCO)(Cap. 358)
8. Waste Disposal Ordinance (Cap 354)
9. Waste Disposal (Chemical
Waste)(General) Regulation (Cap 354)
10. Land Ordinance (Cap 28)
11. WBTC 25/92 Allocation of Space for Urban
Trees
12. WBTC 25/93 Control of Visual Impact of Slopes
13. WBTC 18/94 Management and Maintenance of
both Natural Vegetation and Landscape Works
14. WBTC 24/94 and PELBTC 3/94 “Tree
Preservation”
15.
Antiquities and Monuments Ordinance (Cap 53)
P Primary and District Distributor Roads
R Reclamation
A North Island Line Protection Works
C Central and Wanchai Bypass
+ These items should be excluded from any Environmental
Permit conditions as these refer to future development of the area (which is
not designated under the EIAO), and are not related to reclamation and dredging
activities which are designated, and can hence be controlled through EP
conditions.
* Normally undertaken by a specialist
monitoring team employed directly by the proponent and audited by the
Environmental Works Checker.