(i) The
instrument should be a portable and weatherproof dissolved oxygen (DO)
measuring instrument complete with cable and sensor, and use a DC power
source. The equipment should be capable
of measuring:
·
a DO level in the range of 0
‑ 20 mg L-1 and 0 ‑ 200% saturation; and
·
a temperature of 0 ‑
45 degree Celsius.
(ii) It should have a membrane
electrode with automatic temperature compensation complete with a cable.
(iii) Should salinity compensation
not be built-in to the DO equipment, in-situ
salinity should be measured to calibrate the DO equipment prior to each DO
measurement.
Table 4.1 Analytical
Methods to be applied to Marine Water Quality Samples
Determinant |
Standard Method |
Detection Limit |
Suspended
solids (mg L-1) |
APHA
2540 D |
0.1
mg L-1 |
Copper
(Cu) (mg L-1) |
APHA
3120 B |
0.003
mg L-1 |
Zinc
(Zn) (mg L-1) |
APHA
3120 B |
0.005
mg L-1 |
Arsenic
(As) (mg L-1) |
APHA
3120 B |
0.003
mg L-1 |
Mercury
(Hg) (mg L-1) |
APHA
3112 B |
0.0002
mg L-1 |
Total
Inorganic Nitrogen (mg L-1) |
APHA
4500-Norg or equivalent methods subject to approval of EPD |
0.1
mg L-1 |
Nitrite
(mg L-1) |
APHA
4500-NO2- B |
0.1
mg L-1 |
Ammonia
Nitrogen (mg L-1) |
APHA
4500-NH3 B and C |
0.1
mg L-1 |
Sulphide
(mg L-1) |
APHA
4500-S2- D |
0.1
mg L-1 |
Colour
(Hazen unit) |
APHA
2120 C |
10
Hazen unit |
Threshold
Odour Number |
APHA
2150 B |
5
odour unit |
Synthetic
Detergent |
APHA
5540 C and D |
1 mg L-1 |
(i) Close to the sensitive receivers
(that is, the seawater intakes of the operating saltwater pumping stations)
which are directly or likely to be affected;
(ii) For monitoring locations in the
vicinity of the sensitive receivers, care should be taken to cause minimal
disturbance during monitoring. Other
monitoring locations (M1 to M5) are chosen to cover the mixing zone of
pollutants generated when marine works are undertaken; and
(iii) Two control stations that shall be
at locations representative of the project site in its undisturbed condition. Control stations should be located, as far as
is practicable, both upstream and downstream of the works area.
Table 4.2 Proposed Marine Water Quality
Monitoring Stations
Station |
Easting |
Northing |
Remark |
CR1
(Prince’s Building Group intakes) |
834701.6 |
816397.8 |
- |
CR2 (HSBC & Hotel Furama intakes) |
835046.7 |
816086.7 |
- |
CR3
(Queensway Government Offices) |
835190.5 |
816050.8 |
- |
R1
(Intakes for Telecom House / |
835659.2 |
815865.5 |
Impact monitoring
should be ended after decommission of the intakes |
R2
(Intake for HKCEC Phase I) |
835836.3 |
815906.9 |
Impact monitoring
should be ended after decommission of the intake |
R3
(Intakes for Great Eagle Centre / |
835940.6 |
815889.3 |
Impact monitoring
should be ended after decommission of the intakes |
R4
(Intakes for HKCEC Extension and reprovisioned intakes) |
835857.4 |
816219.4 |
- |
R5
(Water Supplies Department Wan Chai salt water intake) |
836231.8 |
815922.2 |
Impact monitoring
should be ended after decommission of the intake |
R6
(Intake for Sun Hung Kai Centre) |
836269.9 |
815932.3 |
Impact monitoring
should be ended after decommission of the intake |
R7
(Intakes for Excelsior Hotel and World Trade Centre) |
837014.1 |
815993.5 |
Impact monitoring
should be ended after decommission of the intakes |
R8
(Intake for |
837195.3 |
816144.3 |
Impact monitoring
should be ended after decommission of the intake |
R9
(Water Supplies Department Quarry Bay salt water intake) |
839692.5 |
817045.6 |
- |
R10
(Water Supplies Department Sai Wan Ho salt water intake) |
841057.9 |
816476.2 |
- |
R11
(Water Supplies Department Central Water Front salt water intake) |
833887.6 |
816534.0 |
- |
R12
(Water Supplies Department Sheung Wan Water Front salt water intake) |
833397.4 |
816754.1 |
- |
R13
(Water Supplies Department Kennedy Town salt water intake) |
830731.9 |
815996.5 |
- |
P1
(Reprovisioned intake of Sun Hung Kai Centre and temporary reprovisioned Water
Supplies Department Wan Chai salt water intake) |
836283.2 |
816060.6 |
Impact monitoring
should be commenced after commission of the intakes |
P2
(Reprovisioned intakes of Windsor House, Excelsior Hotel and World Trade
Centre) |
837283.9 |
816255.4 |
Impact monitoring
should be commenced after commission of the intakes |
M1 |
834101.8 |
817150.7 |
- |
M2 |
835597.2 |
816631.1 |
- |
M3 |
836551.1 |
816754.4 |
- |
M4 |
837484.1 |
817240.7 |
- |
M5 |
838893.1 |
817770.3 |
- |
C1 |
829916.3 |
817796.5 |
Impact monitoring
should be undertaken only at mid-ebb tide |
C2 |
843611.3 |
815723.9 |
Impact monitoring
should be undertaken only at mid-flood tide |
Table 4.3 Summary of
Baseline Monitoring Programme for Marine Water Quality
Parameter |
Stations |
Frequency |
Duration |
DO, temperature, turbidity,
pH, salinity, SS |
All |
Three days per week |
Four weeks |
Copper,
zinc, arsenic, mercury, TIN |
C1, C2, M1, M2, M3, M4 and
M5 |
Three days per week |
Four weeks |
Sulphide,
nitrite, ammonia nitrogen |
CR1, CR2, CR3, R1, R2, R3,
R4, R5, R6, R7, R8, R9, R10, R11, R12, R13, P1 and P2 |
Three days per week |
Four weeks |
Colour,
threshold odour number, synthetic detergent |
R5, R9, R10, R11, R12, R13
and P1 |
Three days per week |
Four weeks |
Table 4.4 Summary of Impact
Monitoring Programme for Marine Water Quality
Parameter |
Stations |
Frequency |
Duration |
DO, temperature, pH,
salinity and SS |
C1, C2, M1, M2, M3, M4, M5,
CR1, CR2, CR3, R4, R9, R10, R11, R12 and R13 |
Three days per week |
Entire duration of marine
works |
|
R1, R2, R3, R5, R6, R7 and R8 |
Three days per week |
From the commencement of marine
works until decommission of sea water intakes |
|
P1 and P2 |
Three days per week |
From the commission of
reprovisioned sea water intakes until the completion of marine works |
Turbidity |
C1, C2, M1, M2, M3, M4 and
M5 |
Three days per week |
Entire duration of marine
works |
|
R1, R2, R3, R5, R6, R7 and
R8 |
Three days per week |
From the commencement of
marine works until decommission of sea water intakes |
|
CR1, CR2, CR3, R4, R9, R10,
R11, R12 and R13 |
Three days per week (once
per day at R4 when dredging is undertaken in the vicinity of R4) |
Entire duration of marine
works |
|
P1 and P2 |
Three days per week (once
per day at P1 and / or P2 when dredging is undertaken in the vicinity of P1
and / or P2) |
From the commission of
reprovisioned sea water intakes until the completion of marine works |
Copper, zinc, arsenic, mercury and TIN |
C1, C2, M1, M2, M3, M4 and
M5 |
Three days per week |
Entire duration of dredging works |
Sulphide, nitrite, ammonia nitrogen |
CR1, CR2, CR3, R4, R9, R10,
R11, R12 and R13 |
Three days per week |
Entire duration of marine
works |
|
R1, R2, R3, R5, R6, R7 and
R8 |
Three days per week |
From the commencement of
marine works until decommission of sea water intakes |
|
P1 and P2 |
Three days per week |
From the commission of
reprovisioned sea water intakes until the completion of marine works |
Table
4.5 Summary of Post-Construction
Monitoring Programme for Marine Water Quality
Parameter |
Stations |
Frequency |
Duration |
DO, temperature, turbidity,
pH, salinity, SS |
C1, C2, M1, M2, M3, M4, M5,
CR1, CR2, CR3, R4, R9, R10, R11, R12, R13, P1 and P2 |
Three days per week |
Four weeks |
Copper, zinc, arsenic, mercury, TIN |
C1, C2, M1, M2, M3, M4 and
M5 |
Three days per week |
Four weeks |
Sulphide, nitrite, ammonia nitrogen |
CR1, CR2, CR3, R4, P1 and P2 |
Three days per week |
Four weeks |
Colour, threshold odour number, synthetic detergent |
R9, R10, R11, R12, R13 and
P1 |
Three days per week |
Four weeks |
Table 4.6 Action and Limit Levels for Marine
Water Quality
Parameters |
Action |
Limit |
DO in mg L-1 (Surface, Middle & Bottom) |
Surface and
Middle 1 percentile of
baseline data; or midway between 5 percentile of baseline data and limit
level Bottom 1 percentile of
baseline data or midway between 5 percentile of baseline data and limit level |
Surface and
Middle 4 mg L-1
Bottom 2 mg L-1
|
SS in mg L-1 (depth-averaged) at monitoring stations M1,
M2, M3, M4, M5 and control stations C1 and C2 |
95 percentile of
baseline data or 120% of upstream control station's SS at the same tide of
the same day |
99 percentile of
baseline or 130% of upstream control station's SS at the same tide of the
same day |
SS in mg L-1 (surface layer) at monitoring stations R5, R9,
R10, R11, R12, R13 and P1 close to WSD salt water intakes |
10 |
10 |
SS in mg L-1 (surface layer) at monitoring station R1 (or
R4 after reprovision) close to MTRC cooling water intake |
30 |
40 |
SS in mg L-1
(surface layer) at monitoring stations CR1, CR2, CR3, R2, R3, R4, R6, R7, R8
and P1 close to other cooling water intake |
- (7) |
- (7) |
Turbidity in NTU (depth-averaged) |
95
percentile of baseline data or 120% of upstream control station's Turbidity
at the same tide of the same day |
99
percentile of baseline or 130% of upstream control station's Turbidity at the
same tide of the same day |
TIN in mg L-1 (depth-averaged) |
95
percentile of baseline data or 0.4 mg L-1 |
99
percentile of baseline data or 0.4 mg L-1 |
Copper in mg L-1 (depth-averaged) |
5 |
5 |
Zinc in mg L-1 (depth-averaged) |
40 |
40 |
Arsenic in mg L-1 (depth-averaged) |
25 |
25 |
Mercury in mg L-1 (depth-averaged) |
0.3 |
0.3 |
Colour in Hazen unit
(surface layer) at monitoring stations R5, R9, R10, R11, R12, R13 and P1
close to WSD salt water intakes |
20 |
20 |
Threshold odour number in
odour unit (surface layer) at monitoring stations R5, R9, R10, R11, R12, R13 and
P1 close to WSD salt water intakes |
100 |
100 |
Synthetic detergent in mg L-1
(surface layer) at monitoring stations R5, R9, R10, R11, R12, R13 and P1
close to WSD salt water intakes |
5 |
5 |
Notes: 1. "depth-averaged"
is calculated by taking the arithmetic means of reading of all three depths.
2.
For DO, non-compliance of the water quality limits
occurs when monitoring result is lower than the limits.
3.
For turbidity, SS, TIN, Cu, Zn, As and Hg,
non-compliance of the water quality limits occurs when monitoring result is
higher than the limits. The SS limit
levels correspond to the WSD and MTRC water quality target levels, while the limit
levels of Cu, Zn, As and Hg correspond to the UK water quality standards.
4.
All the figures given in the table are used for
reference only and the EPD may amend the figures whenever it is considered as
necessary.
5.
No action and limit levels are set for sulphide,
nitrite and ammonia nitrogen as they are not generated from the marine works. Sulphide discharged from the outfalls is
monitored as it is a corrosive substance that may damage the facilities of the
pumping stations. Nitrite and ammonia
are monitored as they may accumulate within embayed waters with storm water outfalls
nearby.
6.
The action and limit levels of colour, threshold odour
unit and synthetic detergent correspond to the WSD water quality target levels.
7.
To be determined after consultation or agreed with EPD
prior to the commencement of the impact monitoring programme.
Table 4.7 Event
and Action Plan for Marine Water Quality
Event |
ET
Leader |
IC(E) |
ER |
Contractor |
Action level being exceeded by one sampling
day |
Repeat in
situ measurement on next day of exceedance to confirm findings; Identify source(s) of impact; Inform IC(E), contractor and ER; Check monitoring data, all plant, equipment
and Contractor's working methods. If exceedance occurs at WSD salt water intake
or cooling water intake, inform WSD and the owner of cooling water intake,
respectively. |
Check monitoring data submitted by ET and
Contractor’s working methods. |
Confirm receipt of notification of
non-compliance in writing; Notify Contractor. |
Inform the ER and confirm notification of the
non-compliance in writing; Rectify unacceptable practice; Amend working methods if appropriate. |
Action level being exceeded by two or
more consecutive sampling days |
Repeat measurement on next day of exceedance
to confirm findings; Identify source(s) of impact; Inform IC(E), contractor, ER and EPD; Check monitoring data, all plant, equipment
and Contractor's working methods; Discuss
mitigation measures with IC(E), ER and Contractor; Ensure mitigation measures are implemented; Increase the monitoring frequency to daily
until no exceedance of Action level; If exceedance occurs at WSD salt water intake
or the cooling water intake, inform WSD or the owner of the cooling water
intake, respectively. |
Check monitoring data submitted by ET and
Contractor’s working method; Discuss with ET and Contractor on possible
remedial actions; Review the proposed mitigation measures
submitted by Contractor and advise the ER accordingly; Supervise the implementation of mitigation
measures. |
Discuss with IC(E) on the proposed mitigation
measures; Ensure mitigation measures are properly
implemented; Assess the effectiveness of the implemented
mitigation measures. |
Inform the Engineer and confirm notification
of the non-compliance in writing; Rectify unacceptable practice; Check all plant and equipment and consider
changes of working methods; Submit proposal of additional mitigation
measures to ER within 3 working days of notification and discuss with ET, IC(E)
and ER; Implement the agreed mitigation measures. |
Limit level being exceeded by one sampling
day |
Repeat measurement on next day of exceedance
to confirm findings; Identify source(s) of impact; Inform IC(E), contractor, ER and EPD; Check monitoring data, all plant, equipment
and Contractor's working methods; Discuss mitigation measures with IC(E), ER
and Contractor; If exceedance occurs at WSD salt water intake
or the cooling water intake, inform WSD or the owner of the cooling water
intake, respectively. |
Check monitoring data submitted by ET and
Contractor’s working method; Discuss with ET and Contractor on possible
remedial actions; Review the proposed mitigation measures
submitted by Contractor and advise the ER accordingly. |
Confirm receipt of notification of failure in
writing; Discuss with IC(E), ET and Contractor on the
proposed mitigation measures; Request Contractor to review the working
methods. |
Inform the ER and confirm notification of the
non-compliance in writing; Rectify unacceptable practice; Check all plant and equipment and consider
changes of working methods; Submit proposal of mitigation measures to ER
within 3 working days of notification and discuss with ET, IC(E) and ER. |
Limit level being exceeded by two or more
consecutive sampling days |
Repeat
measurement on next day of exceedance to confirm findings; Identify
source(s) of impact; Inform IC(E),
contractor, ER and EPD; Check monitoring
data, all plant, equipment and Contractor's working methods; Discuss
mitigation measures with IC(E), ER and
Contractor; Ensure mitigation
measures are implemented; Increase the monitoring frequency to daily until no
exceedance of Limit level for two consecutive days; If exceedance
occurs at WSD salt water intake or the cooling water intake, inform WSD or
the owner of the cooling water intake, respectively. |
Check monitoring
data submitted by ET and Contractor’s working method; Discuss with ET
and Contractor on possible remedial actions; Review the
Contractor’s mitigation measures whenever necessary to assure their
effectiveness and advise the ER accordingly; Supervise the
implementation of mitigation measures. |
Discuss with IC(E), ET and Contractor on the proposed mitigation
measures; Request
Contractor to critically review the working methods; Make agreement on
the mitigation measures to be implemented; Ensure mitigation
measures are properly implemented; Consider and
instruct, if necessary, the Contractor to slow down or to stop all or part of
the construction activities until no exceedance of Limit level. |
Take immediate
action to avoid further exceedance; Submit proposal
of mitigation measures to ER within 3 working days of notification and
discuss with ET, IC(E) and ER; Implement the
agreed mitigation measures; Resubmit
proposals of mitigation measures if problem still not under control; As directed by
the Engineer, to slow down or to stop all or part of the construction
activities until no exceedance of Limit level. |
Construction Phase
Construction
Design
·
a number of small and confined areas of land
formation are planned;
·
containment of fill within each of these areas by
seawalls is proposed, with the seawall constructed first (to above high water
mark) and filling being carried out behind the completed seawalls. Any gaps that may need to be provided for
marine access will be shielded by silt curtains to control sediment plume
dispersion away from the site. Filling
should be carried out behind the silt curtain; and
·
a partially dredged reclamation that is dictated
by the minimum extent of dredging required for foundations of seawalls, roads
and drainage culverts is proposed.
(i)
deployment of silt curtains around the closed grab
dredgers to contain SS within the construction site during dredging and seawall
trench sand filling;
(ii)
deployment of silt screens at the cooling water intakes
and WSD salt water intakes to further minimise the intake of SS within the sea
water.
Table 4.8 Maximum
Dredging and Filling Rates of WDII -
Scenario 2A
Activity |
Maximum
Production Rate (m3
per week) |
Dredging |
|
Causeway Bay Shoreline
Zone |
31,500 |
Wan Chai Shoreline Zone |
31,500 |
Cross Harbour Water
Mains |
14,000 |
Wan Chai East Submarine
Sewage Pipeline |
7,000 |
Seawall Trench Sand Filling |
|
Causeway Bay Shoreline
Zone |
13,125 |
Wan Chai Shoreline Zone |
26,250 |
Table 4.9 Application of Silt Curtains and Silt
Screens under Scenario 2A
Mitigation Measures
|
Location of Applications
|
Silt Curtains |
·
Construction
sites where dredging and seawall trench sand filling are undertaken,
including CBR1, WCR1, WCR3E, Wan Chai PCWA, Breakwater of Kellett Island
Marina and FRAE of CRIII.
|
Silt Screens |
·
WSD salt water
intakes at Wan Chai, Central Water Front, Sheung Wan, Quarry Bay, Sai Wan Ho
and Siu Sai Wan.
·
Cooling water
intakes for Windsor House, Excelsior Hotel and World Trade Centre, Sun Hung
Kai Centre, Great Eagle Centre / China Resources Building, Wan Chai Tower /
Revenue Tower / Immigration Tower, HKCEC Phase I, HKCEC Extension, Telecom
House / Hong Kong Academy for Performing Arts / Shun On Centre, MTRC South
Intake, Prince’s Building Group at CRIII, Queensway Government Offices at
CRIII, Admiralty Centre at CRIII, HSBC and Hotel Furama at CRIII.
|
(i)
seawall trench dredging at CBR2E and WCR2E, within 150
m radius from the adjacent operating seawater intakes on WCR1, shall not be
more than 1,500 m3 per day;
(ii)
dredging within CBR2E and WCR2E shall only be
undertaken behind the partially constructed seawall (above high water mark)
extended at least 150 m length from the adjacent reprovisioned intakes on the
newly completed seawall (thus, sediment within CBR2E and WCR2E will be
effectively contained and SS impact upon the adjacent intakes will be
minimised);
(iii)
any dredging in WCR3W and WCR2W, within 150 m radius
from the adjacent operating seawater intakes on WCR1, shall not be more than
1,500 m3 per day; any dredging in HKCEC2E, within 150 m radius from
the adjacent operating seawater intakes on the north side of HKCEC Extension,
shall not be more than 1,500 m3 per day;
(iv) deployment
of silt curtains around the grab dredgers to contain SS within the construction
site during dredging and seawall trench sand filling (this will reduce the
dispersion of SS by a factor of 4 or about 75%);
(v)
deployment of a silt screen at the WSD Wan Chai and
Quarry Bay salt water intakes to further minimise the intake of SS within the
sea water, as silt curtains recommended in item (iv) are considered not
sufficient.
Table 4.10 Maximum
Dredging and Filling Rates of WDII -
Scenario 2B
Activity |
Maximum
Production Rate (m3
per week) |
Dredging |
|
31,500 |
|
Wan Chai Reclamation
Zone (1) |
31,500 |
HKCEC Reclamation Zone (1) |
31,500 |
Seawall Trench Sand Filling |
|
Causeway Bay
Reclamation Zone |
13,125 |
Wan Chai Reclamation
Zone |
13,125 |
HKCEC Reclamation Zone |
13,125 |
Mitigation
Measures
|
Location of
Applications
|
Silt Curtains
|
·
Construction
sites where dredging and seawall trench sand filling are undertaken,
including CBR2E, CBR2W, WCR2E, WCR2W, WCR3W, HKCEC2E and HKCEC2W.
|
Silt Screens
|
·
Reprovisoned
WSD salt water intake at Wan Chai and WSD salt water intake at Quarry Bay.
·
Cooling water
intakes for Windsor House, Excelsior Hotel and World Trade Centre, Sun Hung
Kai Centre, Great Eagle Centre / China Resources Building, Wan Chai Tower /
Revenue Tower / Immigration Tower, HKCEC Phase I, HKCEC Extension, Telecom
House / Hong Kong Academy for Performing Arts / Shun On Centre, MTRC South
Intake, Prince’s Building Group at CRIII, Queensway Government Offices at
CRIII, Admiralty Centre at CRIII, HSBC and Hotel Furama at CRIII.
|
·
mechanical grabs, if used, should be designed and
maintained to avoid spillage and sealed tightly while being lifted. For dredging of any contaminated mud, closed
watertight grabs must be used;
·
all vessels should be sized so that adequate
clearance is maintained between vessels and the seabed in all tide conditions,
to ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash;
·
all hopper barges and dredgers should be fitted with
tight fitting seals to their bottom openings to prevent leakage of material;
·
construction activities should not cause foam, oil,
grease, scum, litter or other objectionable matter to be present on the water
within the site or dumping grounds;
·
loading of barges and hoppers should be controlled
to prevent splashing of dredged material into the surrounding water. Barges or hoppers should not be filled to a
level that will cause the overflow of materials or polluted water during
loading or transportation; and
·
before commencement of the reclamation works, the
holder of Environmental Permit has to submit plans showing the phased
construction of the reclamation, design and operation of the silt curtain.
Operational Phase